Win As a Team Be Responsible Miners Strive For Continuous Improvement Deliver Results Mount Milligan 2017

June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

Embed Size (px)

Citation preview

Page 1: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

Win As a Team Be Responsible MinersStrive For Continuous Improvement Deliver Results

Mount Milligan 2017

Page 2: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

Mount Milligan Location

2

Page 3: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

Mount Milligan Location

3

Page 4: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

Mount Milligan Minesite

4

Page 5: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

Mt. Milligan Claim Status

5

Page 6: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

Regional Geologic Setting

6

Page 7: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

Deposit Geology

7

Page 8: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

Main Deposit Cross Section

8

Page 9: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

Resource Expansion Potential

9

Page 10: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

Mt. Milligan Exploration Targets

10

Page 11: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

Mount Milligan Site Overview

11

Open Pit

North Pond

East Pond

South Pond

Cleaner Cell

PAG Cell

South Embankment

SE Embankment

North Embankment

NE Embankment

East Embankment

Mill

Primary Crusher

South Seepage Collection Pond

North #2 Seepage Collection Pond

North #1 Seepage Collection Pond

WSBOpen Pit

North Pond

East Pond

South Pond

Cleaner Cell

PAG Cell

South Embankment

SE Embankment

North Embankment

NE Embankment

Mill

Primary Crusher

WSB

Alpine Lake

Secondary Crusher

TSF

Page 12: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

Mine Summary

12

• Environmental Assessment Certificate granted in 2009

• Construction began in 2010

• Commercial production, February 18, 2014

• 22 year projected mine life

• Gold (average grade 0.36) & Copper (average grade 0.19%)

• BC’s first major new metal mine in more than 15 years

• Second largest gold reserve in Canada

• Open-pit mine produces 120,000 TPD

• Nominal 62,500 TPD processing plant

Page 13: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

Current Pit – June 2017 (looking south)

13

Page 14: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

Mine Operations – Major Equipment

14

Major Mining Equipment:

• 2 Caterpillar 7495HR2 Electric Mining Shovels

• 2 Caterpillar 994F Wheel Loaders

• 2 Caterpillar Electric Drill MD6640

• 1 Caterpillar Diesel Drill MD6290

• 13 Caterpillar 793F Haul Trucks

• 2 Caterpillar 789C Haul Trucks

Page 15: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

Mine Operations – Mining Strategy

15

A 15 m bench height is usedfor mining both ore and waste. The overall mining sequence was developed through a series of mining pushbacks specific to the MBX, 66 and WBX subzones (collectively, the Main Zone), and SS phases. The approach was designed to:

• maintain higher grade mineralization in the MBX and 66 subzones;

• maintain a smooth waste/ore ratio with required TSF construction materials;

• develop an ore blending strategy while selectively mining from the Main Zone and SS pits to smooth delivery of copper and gold head grades to achieve the required concentrate grades;

• provide potential waste rock storage in the mined out sections of the Main Zone pit for waste generated from the WBX and SS mining phases

Page 16: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

Mine Operations – Waste Rock Strategy

16

• Mining and placement of overburden, non-acid generating (NAG) sulphide rock, weathered and oxide rock from the mine is integrated at the TSF with the construction of the south, southeast, northeast, and north embankments, Pipeline Corridor Causeway (PCC), Eskers Road and West Separator Berm (WSB).

• Delivery of potentially acid generating (PAG) rock for sub-aqueous storage at the TSF will be integrated in the cleaner/scavenger tailing Separator Dyke and bulk storage area within the TSF.

• Residual overburden will be stockpiled in the WSB laydown area and a temporary stockpile located west of the primary crusher (the South Stockpile).

• Overburden will be reclaimed from the South Stockpile during the later years of the mine life for shortfalls of TSF material requirements, and for the completion of the last four construction stages (Stages 18–21) of the TSF embankment.

Page 17: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

TSF Main Components

17

Open Pit

North Pond

East Pond

South Pond

Cleaner Cell

PAG Cell

South Embankment

SE Embankment

North Embankment

NE Embankment

East Embankment

Mill

Primary Crusher

South Seepage Collection Pond

North #2 Seepage Collection Pond

North #1 Seepage Collection Pond

WSBOpen Pit

North Pond

East Pond

South Pond

Cleaner Cell

PAG Cell

South Embankment

SE Embankment

North Embankment

NE Embankment

MillSouth Seepage Collection Pond

North #1 Seepage Collection Pond

WSB

Alpine Lake

Meadows Creek Pumping Stations

North #2 Seepage Collection Pond

Page 18: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

Tailings Storage Facility Design Concepts

• Mine waste to be confined behind a zoned water retaining earth-rockfilldam approximately 7,300 meters long averaging 55 to 70 meters high with a maximum height of 90 meters;

• Cleaner tailing will be stored within a separate cell within the larger scavenger tailing basin;

• High PAG, low PAG, Low NAG, oxide and weathered rock waste storage areas (located within TSF)

• Portion of low NAG, oxide and weathered materials used in construction of the upstream shell zones

• Tailing distribution system,Reclaim water system;

• PAG, low PAG and low NAG Waste Storage Area (located within TSF)

18

Page 19: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

TSF Design

19

Design follows a modified centerline construction

Page 20: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

TSF Till Core Construction

20

Glacial till material is mined directly from deposits overlying bedrock throughout the Mine

Till is placed in the Core zone and spread with tracked dozers

Page 21: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

21

Placed till is compacted to specified density

Downstream of till core has two filter zones (Filter (F) and Transition (T))

Page 22: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

TSF Waste Embankment Construction

22

Upstream and downstream embankments are constructed from run of mine rock

Rock is placed in 1-2 meter lifts

Page 23: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

TSF Construction

23

Till Core Downstream filter zones

Downstream Embankment

Upstream Embankment

TSF construction – typical completed lift

Page 24: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

Seepage Collection Ponds

24

Seepage collection ponds at toe of dam collect all drainage which is pumped back into the facility

Page 25: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

Milling

25

The Mount Milligan concentrator was originally designed to process ore at a nominal rate of 60,000 t/d, producing a marketable concentrate of copper, gold and silver. A secondary crushing circuit together with mill optimization projects will increase throughput to a nominal rate of 62,500 t/d.

Key process equipment consists of:

• primary crushing plant with a 1.525 m x 2.794 m gyratory crusher• secondary pre-crushing plant with two cone crushers, each powered by one 1,000 kW• motor prior to the grinding circuit• SAG/ball mill/crusher grinding circuit:

• one 12.20 m diameter x 6.71 m EGL SAG mill with one 23.5 megawatt (MW) gearless motor drive• two 7.32 m diameter x 12.50 m EGL ball mills each driven by two 6.5 MW variable speed

synchronous motors (26 MW total installed ball mill power)• two cone crushers, each powered by one 750 kW motor

Flotation circuits:• rougher flotation: two parallel trains of five 200 m3 tank cells• first cleaner flotation: seven 100 m3 tank cells• second and third cleaner flotation: six 30 m3 tank cells

Regrinding and gravity concentration circuits:• one 1,119 kW tower mill operated in closed circuit with six 380 mm cyclones• two 3,000 kW IsaMills operated in closed circuit with twenty-six 250 mm cyclones• one centrifugal gold concentrator

Page 26: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

Simplified Process Plant Flowsheet

26

Page 27: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

New Secondary Crusher Facility

27

Primary Crusher

Secondary Crusher

Coarse Ore Stockpile Mill

Page 28: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

Process Plant Improvement Opportunities

28

During 2016, the operation has spent approximately $51 M to increase tonnage beyond 60,000 t/d with the financial plan target being 62,500 tpd. However, data indicates that as throughput increases there will be a shift in the bottleneck from primary grinding downstream to two areas: the ball mills being able to achieve target grind and the flotation circuits to achieve recovery.

In order to further enhance the processing plant to achieve targeted throughput and recovery, a number of capital improvement initiatives have been identified.

Capital Projects Estimated Cost $ M

Additional Grinding Capacity $18.9Additional Cleaner Capacity $4.6Additional Rougher Capacity $9.1Water Quality Control Circuit $9.1Water Treatment Circuit $3SAG Discharge/Cyclone Feed Pump Box Modifications $1.5Total $46.2

All of these projects require test work, engineering and execution before a proper cost and benefit analysis can be performed. At this time the capital costs associated with the above improvements are scoping quality in nature with an accuracy of -30% to +50%.

Page 29: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

Reclaim Barge in South Pond

29

Page 30: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

2017 Technical Report Reserves

30

MINERAL RESERVE ESTIMATE EFFECTIVE DECEMBER 31, 2016

Mineral Reserve Category Tonnes (000)

Cu (%)

Au (g/t)

In-Situ Cu Mlb

In-Situ Au (000 oz)

Proven 256,847 0.187 0.424 1,058.6 3,503 Probable 239,362 0.188 0.293 990.9 2,257 Total Proven + Probable 496,210 0.187 0.361 2,049.5 5,760

Notes: (1) CIM definitions were followed for Mineral Reserves. (2) Mineral Reserves are estimated at a $6.25/t (C$8.12/t) cut-off value using metal prices of $2.95 per

pound copper and $1,200 per ounce gold, and a US$/C$ exchange rate of US$1.00/C$1.30. (3) Figures may not total exactly due to rounding.

Page 31: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

2017 Technical Report Reserves

31

Page 32: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

2017 Technical Report Resources

32

Page 33: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

2017 Technical Report Reserves (by Phase)

33

Page 34: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

LOM Phases Plan and Section

34

Page 35: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

LOM – Pit and TSF at End of 2016

35

Page 36: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

LOM – Pit and TSF at End of 2017

36

Page 37: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

LOM – Pit and TSF at End of 2018

37

Page 38: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

LOM – Pit and TSF at End of 2021

38

Page 39: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

LOM – Pit and TSF at End of 2025

39

Page 40: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

LOM – Pit and TSF at End of 2032

40

Page 41: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

LOM – Pit and TSF at End of 2038

41

Page 42: June 2017 Mt. Milligan Mine Site Tour 201… · mining sequence was developed through a series of mining ... CIM definitions were followed for Mineral ... should achieve about 60,000

Opportunities

42

Near-term

• Continue to optimize comminution circuit

• Mill throughput averaged 53,000 tpd for Q1, improving on monthly basis, should achieve about 60,000 tpd average for the year,

• Focus on optimizing mine and mill to increase gold and copper recoveries

Long-term

• Geometallurgical drill program to build geomet model (18 months)

• Expand throughput to 70,000 tpd

• Add gold cyanidation circuit