Birmingham Public Schools 2015 Bond Program Monthly Construction Update July 2016 Brief Project Description On June 20, 2016 construction began at several buildings for the 2015 Bond Program. The scope of work includes new secured entries at Beverly, Bingham Farms, Greenfield, Harlan, Pembroke, Pierce, Quarton and Birmingham Covington. All existing unit ventilators are being replaced along with the existing temperature controls at Pierce. A few other projects at Pierce include updating the softball field and replacing the door system off Pierce Street. New lockers are being installed at Covington. Fuel pumps have been replaced at the Transportation building. The boilers and domestic water heaters are being replaced at Groves and the pool locker rooms have received new epoxy flooring. Lastly at Seaholm and Groves new scoreboards will be installed for the football and varsity baseball and softball fields, and the tennis courts are being repaved and resurfaced. Construction Schedule Update Inspections will be scheduled for the week of 8/29. Groves At the tennis courts, fencing is ongoing and expected to be complete on or before 8/10. Acrylic coating and striping is starting following the fencing and will take roughly oneweek weather depending. Tennis courts should be ready for use by 8/22 at the latest. Domestic hot water replacement is almost complete, hot water is scheduled to be back on by 8/8. Piping is ongoing for the boiler replacement. The epoxy floor in the locker rooms is completed, ready for punchlist. Pierce Unit Ventilators Temperature controls are approximately 70% complete. Unit ventilators and louvers are all on site. Piping unit ventilators began on Saturday 7/30 and the unit ventilator installation is on track to be completed by 8/12. Startup, Controls, testing and balancing of the unit ventilators will begin on 8/15. Counter tops in the classrooms will begin being installed following the completion of the unit ventilators the week of 8/15. Secured Entries Drywall finishing at all of the secured entries will be complete by 8/5. Painting is ongoing and is scheduled to be complete next week.

July Monthly Report Update 2 - Birmingham Schools€¦ · Door hardware and access control installation is approximately 80% complete. FRP ... T&M Ken (248) 529-2465 ... Axiom Perp

Embed Size (px)

Citation preview

  

 

Birmingham Public Schools 2015 Bond Program Monthly Construction Update 

July 2016  

Brief Project Description 

 On June 20, 2016 construction began at several buildings for the 2015 Bond Program.  The scope of work 

includes new secured entries at Beverly, Bingham Farms, Greenfield, Harlan, Pembroke, Pierce, Quarton 

and  Birmingham  Covington.    All  existing  unit  ventilators  are  being  replaced  along with  the  existing 

temperature controls at Pierce.   A  few other projects at Pierce  include updating  the softball  field and 

replacing the door system off Pierce Street.  New lockers are being installed at Covington.  Fuel pumps 

have been replaced at the Transportation building.   The boilers and domestic water heaters are being 

replaced at Groves and the pool locker rooms have received new epoxy flooring.  Lastly at Seaholm and 

Groves new scoreboards will be installed for the football and varsity baseball and softball fields, and the 

tennis courts are being repaved and resurfaced.  

 

Construction Schedule Update 

Inspections will be scheduled for the week of 8/29. 

Groves  

At the tennis courts, fencing is ongoing and expected to be complete on or before 8/10. 

Acrylic coating and striping is starting following the fencing and will take roughly one‐week 

weather depending.  

Tennis courts should be ready for use by 8/22 at the latest.  

Domestic hot water replacement is almost complete, hot water is scheduled to be back on by 

8/8. 

Piping is ongoing for the boiler replacement. 

The epoxy floor in the locker rooms is completed, ready for punchlist. 

 

Pierce Unit Ventilators 

Temperature controls are approximately 70% complete.  Unit ventilators and louvers are all on 

site. 

Piping unit ventilators began on Saturday 7/30 and the unit ventilator installation is on track to 

be completed by 8/12. 

Start‐up, Controls, testing and balancing of the unit ventilators will begin on 8/15. 

Counter tops in the classrooms will begin being installed following the completion of the unit 

ventilators the week of 8/15. 

 

Secured Entries 

Drywall finishing at all of the secured entries will be complete by 8/5.  

Painting is ongoing and is scheduled to be complete next week.   

  

 

Reworking ceiling grid/tile will begin this week.  

Aluminum framed entrances will be installed this week at Beverly and Pembroke.   

Hollow metal doors and frames have all been installed. 

Door hardware and access control installation is approximately 80% complete. 

FRP doors and frames for Covington, Quarton and Harlan will be delivered and installed the 

week of 8/8. 

FRP doors and frames for Greenfield and Pierce will be delivered and installed the week of 8/29. 

Existing casework has been installed.  Millwork should be installed week of 8/8 and casework 

will be delivered and installed week of 8/22. 

Owner installed floor covering can begin at all of the schools the week of 8/8. 

Miscellaneous Projects 

Transportation Fuel Pumps are completed, ready for punchlist scheduled on 8/3. 

Seaholm Tennis Courts are completed. Waiting on bangboards to be delivered in approximately 

2 weeks. 

Electrical boring for the football scoreboards started last week and is ongoing.  

Demo of the existing beams and scoreboards, and pouring concrete for new beams next week.  

Scoreboards are shipping 8/4 and the new beams will be delivered and installed the week of 

8/15.   

Locker installation at Covington is on track to be completed this week. 

Translucent panels in Bingham Farms Multipurpose room have been completed. 

 

Safety 

All contractors will go through Clark Construction Company’s site specific safety orientation 

before beginning work on site.  To date over 100 contractors have been through orientation. 

Hard hats, safety glasses and safety vests will be required 100% of the time on site.  

Clark’s BRAVO program (Being Resistant Against Violations Openly) is being utilized on this 

project.  This program is to ensure everyone has their eyes open to potential safety hazards and 

is looking out for one another. 

Clark has set this project up with a MIOSHA SET Alliance.  

There have been 5,280 trade hours worked to date with no safety incidents. 

 

Logs 

Attached is an updated potential change order log 

Attached is an updated material tracking log. 

Attached is a 3 week look ahead schedule. 

To date, there have been 9 bulletins issued by TMP. 

To date, 82 RFIs issued and 81 have been answered. 

To date, 142 submittals have been submitted and completed.  

 

    

     

PROGRESS PHOTOS 

 Transportation Building Fuel Pump 

 

 Seaholm Tennis Courts 

 

    

     

PROGRESS PHOTOS 

 Quarton Elementary Secured Entry 

 

 Pierce Elementary Relocated Murals 

 

    

     

PROGRESS PHOTOS 

 Bingham Farms Secured Entry 

 

 Harlan Elementary Secured Entry 

 

    

     

PROGRESS PHOTOS 

 Birmingham Covington Lockers 

 

 Pembroke Elementary Secured Entry 

Material Status ReportCCC Job No.: xxxx

Run Date: 7/29/2016

Project Name: Birmingham Public Schools

BP / Division Contractor Description LocationSubmittal Package

NumberSubmittal Status

Date Required On

Site

Confirmed Delivery

Beverly 081113 Reviewed/Approved 7/1/2016 6/27/2016

Bingham 081113 Reviewed/Approved 7/1/2016 6/27/2016

Covington 081113 Reviewed/Approved 7/1/2016 6/27/2016

Greenfield 081113 Reviewed/Approved 7/1/2016 6/27/2016

Harlan 081113 Reviewed/Approved 7/1/2016 6/27/2016

Pembroke 081113 Reviewed/Approved 7/1/2016 6/27/2016

Pierce 081113 Reviewed/Approved 7/1/2016 6/27/2016

Quarton 081113 Reviewed/Approved 7/1/2016 6/27/2016

Seaholm 081113 Reviewed/Approved 7/1/2016 6/27/2016

Beverly Reviewed/Approved 7/1/2016 8/22/2016

Bingham Reviewed/Approved 7/1/2016 8/22/2016

Covington Reviewed/Approved 7/1/2016 8/22/2016

Greenfield Reviewed/Approved 7/1/2016 8/22/2016

Harlan Reviewed/Approved 7/1/2016 8/22/2016

Pembroke Reviewed/Approved 7/1/2016 8/22/2016

Pierce Reviewed/Approved 7/1/2016 8/22/2016

Quarton Reviewed/Approved 7/1/2016 8/22/2016

Seaholm Reviewed/Approved 7/1/2016 8/22/2016

Wood Doors 081113 Reviewed/Approved 7/1/2016 7/5/2016

Beverly 087100 Reviewed/Approved 7/1/2016 On Site

Bingham 087101 Reviewed/Approved 7/1/2016 On Site

Covington 087102 Reviewed/Approved 7/1/2016 On Site

Greenfield 087103 Reviewed/Approved 7/1/2016 On Site

Harlan 087104 Reviewed/Approved 7/1/2016 On Site

Pembroke 087105 Reviewed/Approved 7/1/2016 On Site

Pierce 087106 Reviewed/Approved 7/1/2016 On Site

Quarton 087107 Reviewed/Approved 7/1/2016 On Site

Seaholm 087108 Reviewed/Approved 7/1/2016 On Site

Pierce 082250 Reviewed/Approved 7/1/2016 8/22/2016

Pembroke 082250 Reviewed/Approved 7/1/2016 8/22/2016

Quarton 082250 Reviewed/Approved 7/1/2016 8/22/2016

Greenfield 082250 Reviewed/Approved 7/1/2016 8/22/2016

Covington 082250 Reviewed/Approved 7/1/2016 8/22/2016

Harlan 082250 Reviewed/Approved 7/1/2016 8/22/2016

Beverly 082250 Reviewed/Approved 7/1/2016 8/22/2016

Pierce 087100 Reviewed/Approved 7/1/2016 On Site

Pembroke 087100 Reviewed/Approved 7/1/2016 On Site

Quarton 087100 Reviewed/Approved 7/1/2016 On Site

Bingham 087100 Reviewed/Approved 7/1/2016 On Site

Greenfield 087100 Reviewed/Approved 7/1/2016 On Site

Covington 087100 Reviewed/Approved 7/1/2016 On Site

Harlan 087100 Reviewed/Approved 7/1/2016 On Site

Beverly 087100 Reviewed/Approved 7/1/2016 On Site

Greenfield 082250 Reviewed/Approved 7/1/2016 6/29/2016

Covington 084413 Reviewed/Approved 7/1/2016 6/29/2016

Harlan 084414 Reviewed/Approved 7/1/2016 6/29/2016

Translucent panels Bingham 084523 Reviewed/Approved 7/1/2016 6/22/2016

Fire Rated Aluminum Doors Pierce 081116 Reviewed/Approved 7/1/2016 8/30/2016

Glass & Glazing All 088000 Reviewed/Approved 7/1/2016 8/4/2016

10

Steel Equipment Co.David (248) 334-1900cell: (248) 930-1800

[email protected]

Lockers Covington Reviewed/Approved 7/1/2016 6/22/2016

Unit Ventilators 238223 Reviewed/Approved 7/1/2016 7/14/2016

Louvers 238223 Reviewed/Approved 7/1/2016 7/8/2016

23BOscar Larson

Jeff (248) 620-0070 x [email protected]

Pumps Transporation Reviewed/Approved 7/1/2016 On Site

Scoreboards Groves 116843 Reviewed/Approved 7/1/2016 8/4/2016

Scoreboards Seaholm 116843 Reviewed/Approved 7/1/2016 8/4/2016

Access control and visitor notifiation system Beverly Revise & Resubmit 7/1/2016 7/10/2016

Access control and visitor notifiation system Bingham Revise & Resubmit 7/1/2016 7/10/2016

Access control and visitor notifiation system Greenfield Revise & Resubmit 7/1/2016 7/10/2016

Chainlink Fence - Vinyl Groves 323130 Reviewed/Approved On Site

Chainlink Fence - Vinyl Seaholm Reviewed/Approved On Site

Chainlink Fence - Galvanized Pierce 323102 Reviewed/Approved On Site

06AAxiom

Deib (248) [email protected]

Hollow metal

Casework

Hardware

FRP and AMP doors (aluminum)

Hardware08

Peterson GlassKevin (248) 541-6800

[email protected]

Curtain Wall

23Johnson and Wood

Jon Clark (810) [email protected]

26 OSC

Rick/Jayson (810) [email protected]

32T&M

Ken (248) 529-2465

409FR037 Version 1

Material Status ReportCCC Job No.: xxxx

Run Date: 7/29/2016

BP / Division Contractor Description LocationSubmittal Package

NumberSubmittal Status

Date Required On

Site

Confirmed Delivery

Water Heater Groves 223400 Reviewed/Approved On Site

Boilers Groves 235216 Reviewed/Approved On Site

Storage Tanks Groves 221223 Reviewed/Approved On Site

Industrial Process PipingBP4 - 02, 23, & 26

409FR037 Version 1

BirminghamSchools‐2700MeetingDate:

M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa

7/25/2016

THREE‐WEEKLOOKAHEAD ScheduledActivities

MeetingNo.4WORK ACTIVITES FORWEEK: 7/25/2016

BP School Contractor PlannedCommitments CommentsAxiom Modifylouveropenings(interior&exterior) x xJ&W Controlwiring x x x x x x x x x x x x x x x x x x x xJ&W InstallUnitVentilators x x x x x x x x x x x x x x x x x x x xT&M ReinstallfenceatSoftballField x x xAxiom TapeandFinishdrywall x x x x x xAxiom Fieldmeasurecountertops xAxiom Muralcolumms x xOSC InstallLightsinStairwell xAxiom AcousticalCeillingTileinStairwell x x x xAxiom Painting x xAxiom InstallHMdoorsandframes x

Axiom Fieldweldendofwindowlight xAxiom InstallHMdoorsandframes x xAxiom Sandbulkhead xAxiom Paint x xPeterson ReinstallAluminumframeanddoors x x x x xPeterson Measureglass x xOSC Completeaccesscontrols x xAxiom PrepA3doors x x

Axiom SetHMFrames(Grout&Anchor)2doors x xAxiom FinshDrywall x x xOSC Relocatelights,sensor,speaker x xAxiom Paint x xPeterson ResetAluminumframeanddoors x xAxiom Reinstallceilinggrid xOSC Completeaccesscontrols x xAxiom PrepA3doors x x

Axiom SetHMframesandmasonry x xAxiom PrepA3Doors xAxiom Metalstudsdrywall x xOSC Roughelectric x xAxiom Removeandreinstallboilerdoor x xAxiom DrywallFinish x x xAxiom Paintng x x xAxiom Reinstallceilinggrid xOSC Relocatelighting xOwner Carpet x xAxiom Setreceptiondesk x x xOSC Trimoutelectricalandlowvoltage x x

Axiom SetnewHMframe x xAxiom WeldFramePeterson AluminumEntryInstall x xAxiom PatchandrepairsoffitandPaint x x xAxiom Reworklay‐inceiling x xPeterson Measureglass x xAxiom PrepA3Doors x x x

Axiom DrywallFinish x x xAxiom Paint xPeterson InstallAluminumEntrance x xAxiom PerpA3Door x x x

Axiom DrywallTapeandFinish x x x xAxiom Paint x xSteelEq. NewLockerInstall x x x xAxiom Ceilingrework x xAxiom PrepA3Doors x x x

Axiom InstallHMdoorsandframes xAxiom Tape&FinishDrywall x x xAxiom PrepexistingdoorsforAccesscontro x xAxiom Paint xAxiom ReworkCeilingGrid x xAxiom ReinstallMillwork x x xOSC FinishElectric x

OscarLarson FinalDEQInspection xOscarLarson CreatePunchlist x x

T&M Fencing x x x x x x x x x x x x xT&M Colorcoatandmarkings&Netpostinstallation x x x x xT&M Restoration x x xT&M Punchlist

Seaholm T&M BangBoards x

IPP PipingDomesticHotWater x x x x x

IPP PipingBoilers x x x x x x x x x x

IPP PressureTest x

IPP Inspection x x x

8/2

WORKACTIVITESFORWEEK: 7/25/2016

7/25

7/26

7/27

7/28

7/29

7/30

7/31

8/1

8/3

8/4

8/5

8/6

8/7

8/8

8/9

8/10

8/11

8/12

8/13

Groves

4 Groves

1

Pierce

Pembroke

Beverly

Quarton

Harlan

Greenfield

Covington

BinghamFarms

Transportation

Potential Change Order

Summary Log

Birmingham Public Schools Clark Construction CompanyProject # 15-2700

31301 Evergreen, Beverly Hills Michigan 48025 Tel: Fax:

Budget Cost

Number Description PCCO No Approximate

(Anticipated)

Pending Approved Approximate

(Anticipated)

Pending Approved Contingency

Funds

001 Covington: Revise lockers to a knock down locker in lieu

of welded and 3 point latchign in lieu of single point.

Also add a 4" metal Z base. This was a voluntary

alterante at bid time.

2700 - 001 $0.00 $0.00 $0.00 $0.00 $0.00 -$22,400.00 $0.00

002 Operations - Credit to not replace the fuel island pump at

Operations.

2700 - 001 $0.00 $0.00 $0.00 $0.00 $0.00 -$42,080.00 $0.00

003 Seaholm and Groves - Remove cost to paint the pool

and gym locker rooms.

2700 - 001 $0.00 $0.00 $0.00 $0.00 $0.00 -$45,000.00 $0.00

004 All Secured Entries - Add alternate A3. 2700 - 001 $0.00 $0.00 $0.00 $0.00 $0.00 $49,131.00 $0.00

005 Bulletin #2 - Revise the secured entrance at Pembroke,

Beverly, Greenfield and Quarton due to comments from

Bureau of Fire Services. Also miscellaenous RFIs.

2700 - 002 $0.00 $0.00 $26,292.00 $0.00 $0.00 $26,292.00 -$26,292.00

006 Pierce - RFI 003 add light fixture in stairwell A218 where

the acoustical ceiling is being installed.

2700 - 002 $0.00 $0.00 $1,210.00 $0.00 $0.00 $1,210.00 -$1,210.00

007 Bulletin #4 - Remove cabinet unit heater at Pembroke

and add electrical at Sealhom and Groves.

2700 - 002 $0.00 $0.00 -$13,072.00 $0.00 $0.00 -$13,072.00 $13,072.00

008 Bulletin #3 - Casework revisions at Bingham Farms and

Quarton.

2700 - 002 $0.00 $0.00 $2,484.00 $0.00 $0.00 $2,484.00 -$2,484.00

009 Covington - Removal of concrete bases for lockers in

cubbies per ASI #1.

2700 - 002 $0.00 $0.00 $4,886.00 $0.00 $0.00 $4,886.00 -$4,886.00

010 Seaholm and Groves - Add the team name message

centers and electronic captions to the football

scoreboards

2700 - 002 $0.00 $0.00 $22,185.00 $0.00 $0.00 $22,185.00 -$22,185.00

011 Make Bid Pack #1 and #4 Budgets Whole 2700 - 003 $0.00 $0.00 $49,452.00 $0.00 $0.00 $0.00 -$49,452.00

012 Harlan - Relocate sprinkler head that is in conflict with

new curtain wall and modify existing bulkhead.

$5,100.00 $0.00 $0.00 $5,100.00 $0.00 $0.00 -$5,100.00

013 Covington - Relocate an existing pull station that is in

conflict with the new curtain wall per RFI 004.

2700 - 002 $0.00 $0.00 $865.00 $0.00 $0.00 $865.00 -$865.00

014 Covington & Quarton - Remove and salvage carpet tile

in the main office per RFI 004.

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 -$3,000.00

015 Bingham Farms - Furnish and install a lintel for new door

opening B111 per RFI 15, this was not shown to be

masonry.

2700 - 002 $0.00 $0.00 $383.00 $0.00 $0.00 $383.00 -$383.00

Prolog Converge Printed on: 8/2/2016 Prolog_Converge Page 1

Potential Change Order

Summary Log

Budget Cost

Number Description PCCO No Approximate

(Anticipated)

Pending Approved Approximate

(Anticipated)

Pending Approved Contingency

Funds

016 Quarton - furnish and install decorative caps for the

removed push bars per RFI 013.

017 Cost to re-certify the fire rated doors that need to be

modified per Alternate 3.

$0.00 $3,827.00 $0.00 $0.00 $3,827.00 $0.00 -$3,827.00

018 Bulletin #6 - Revise door hardware on fire rated doors at

Pierce.

2700 - 002 $0.00 $0.00 $3,277.00 $0.00 $0.00 $3,277.00 -$3,277.00

019 Groves - Glycol backcharge -$21,232.00 $0.00 $0.00 -$21,232.00 $0.00 $0.00 $21,232.00

020 Groves and Seaholm - Delete the protective nettings

from this summers work.

2700 - 002 $0.00 $0.00 -$65,200.00 $0.00 $0.00 -$65,200.00 $65,200.00

021 Groves - Add 3 - 8" valves to seperate chilled and

heating systems to drain glycol because existing valves

are not holding.

2700 - 002 $0.00 $0.00 $9,960.00 $0.00 $0.00 $9,960.00 -$9,960.00

022 Groves - Sawcut existing concrete where fencing posts

are embedded and extend asphalt per RFI 027.

2700 - 002 $0.00 $0.00 $2,500.00 $0.00 $0.00 $2,500.00 -$2,500.00

023 Demo Scoreboards and Foundations at Seaholm and

Groves

2700 - 002 $0.00 $0.00 $11,000.00 $0.00 $0.00 $11,000.00 -$11,000.00

024 Remove existing VCT where carpet is shown to be

installed at Bingham Farms, Harlan and Pierce.

025 Remove and replace toilets in the locker rooms at

Seaholm and Groves for the epoxy flooring.

$5,000.00 $0.00 $0.00 $5,000.00 $0.00 $0.00 -$5,000.00

026 Investigate domestic water piping at Pierce to see if it

needs to be replaced next summer.

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 -$5,000.00

027 Transportation - Patch asphalt where new conduits are

being installed.

$1,800.00 $0.00 $0.00 $1,800.00 $0.00 $0.00 -$1,800.00

028 Pierce - provide engineered stamped drawings for cold

formed metal framing for the louver openings per

Addendum #1.

2700 - 002 $0.00 $0.00 $863.00 $0.00 $0.00 $863.00 -$863.00

029 Seaholm - drill and epoxy dowels into the existing

foundations for the tennis court nets because there is not

enough room to get the full depth foundation with the

exisitng foundations there.

$1,500.00 $0.00 $0.00 $1,500.00 $0.00 $0.00 -$1,500.00

030 Transportation - Replace the concrete in the island

around the fuel pumps per request by Birmingham

Public Schools.

2700 - 002 $0.00 $0.00 $6,273.00 $0.00 $0.00 $6,273.00 -$6,273.00

031 Pierce - Remove receptacles being fed through univents

and refeed with the new univent.

$2,500.00 $0.00 $0.00 $2,500.00 $0.00 $0.00 -$2,500.00

032 Groves - Sawcut existing sidewalk and replace after the

edgedrain is installed per RFI 31.

2700 - 002 $0.00 $0.00 $1,922.00 $0.00 $0.00 $1,922.00 -$1,922.00

033 Transportation - Pump out water and put a test well in so

the tanks do not float.

$8,970.00 $0.00 $0.00 $8,970.00 $0.00 $0.00 $0.00

034 Transportation - Test the column supporting the canopy $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 -$923.00

Prolog Converge Printed on: 8/2/2016 Prolog_Converge Page 2

Potential Change Order

Summary Log

Budget Cost

Number Description PCCO No Approximate

(Anticipated)

Pending Approved Approximate

(Anticipated)

Pending Approved Contingency

Funds

over the fuel pumps to make sure it is structurally sound.

035 Groves - Bulletin #1 Bid Pack #4 - Furnish and Install a

SpiroTherm Air and Dirt Serperator in tbe boiler room.

2700 - 002 $0.00 $0.00 $0.00 $0.00 $0.00 $30,332.00 $0.00

036 Transportation - Remove the asphalt around the

concrete island and regrade so the concrete island will

drain properly and there will not be standing water by the

fuel pumps. Replace this perimieter with new concrete.

2700 - 002 $0.00 $0.00 $7,400.00 $0.00 $0.00 $7,400.00 -$7,400.00

037 Pembroke - Relocate electrical outlet found in display

case when demo'd. Conduit is in the floor so this can be

moved over to the adjacent wall.

$1,000.00 $0.00 $0.00 $1,000.00 $0.00 $0.00 -$1,000.00

038 Quarton - Relocate two 1" conduits found in demo'd wall

per RFI 51.

$1,000.00 $0.00 $0.00 $1,000.00 $0.00 $0.00 -$1,000.00

039 Covington - Build two metal stud and drywall walls to

accomodate U shape locker configuration per RFI #56.

$0.00 $1,859.00 $0.00 $0.00 $1,859.00 $0.00 -$1,859.00

040 Quarton - Build a chase wall for the fire alarm panel

location in the main office per RFI 29.

$717.00 $0.00 $0.00 $717.00 $0.00 $0.00 -$717.00

041 Transportation - RFI 64 - Furnish and install sump

sensors that are required by law and existing sensors

were damaged and not working.

$1,746.00 $0.00 $0.00 $1,746.00 $0.00 $0.00 -$1,746.00

042 Covington - There were 5 receptacles behind lockers

that needed to be removed per code in order to re-install

lockers.

$450.00 $0.00 $0.00 $450.00 $0.00 $0.00 -$450.00

043 Pierce - RFI 58 - Furnish and install isolation valves for

2nd floor gym finned tube radiation on both sides of the

control valve.

$439.00 $0.00 $0.00 $439.00 $0.00 $0.00 -$439.00

044 Pierce - RFI 60 - Furnish and install a metal pipe

enclosure at the art rooms to match the unit ventilators.

$5,000.00 $0.00 $0.00 $5,000.00 $0.00 $0.00 -$5,000.00

045 Pierce - glycol needed to bring system to 35% propylene

glycol per RFI 37.

$2,775.00 $0.00 $0.00 $2,775.00 $0.00 $0.00 -$2,775.00

046 Greenfield - furnish electric strikes per RFI 44. The

specified strike Von Duprin 6111 does not fit.

$1,086.00 $0.00 $0.00 $1,086.00 $0.00 $0.00 -$1,086.00

047 Covington - Paint all locker areas per RFI 65. $0.00 $9,000.00 $0.00 $0.00 $9,000.00 $0.00 -$9,000.00

048 Pierce - relocate receptacle found in door opening

A119C per RFI 41.

$300.00 $0.00 $0.00 $300.00 $0.00 $0.00 -$300.00

049 Pierce - Backcharge to Axiom to replace conduit that

was damaged by masons while modifying louver

openings.

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

050 Pierce - Furnish and install a 90 minute fire rated door,

frame and hardware for PIerce due to the late delivery of

the permenant door.

$0.00 $1,682.00 $0.00 $0.00 $1,682.00 $0.00 -$1,682.00

051 Bulletin No. 8 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Prolog Converge Printed on: 8/2/2016 Prolog_Converge Page 3

Potential Change Order

Summary Log

Budget Cost

Number Description PCCO No Approximate

(Anticipated)

Pending Approved Approximate

(Anticipated)

Pending Approved Contingency

Funds

052 Bulletin #6 - tie hardware into fire alarm panel. $0.00 $6,745.00 $0.00 $0.00 $6,745.00 $0.00 -$6,745.00

053 Covington - Furnish and install break metal or EIFS at

Covington to cover 2" gap between new door and head

per RFI 70.

$2,500.00 $0.00 $0.00 $2,500.00 $0.00 $0.00 -$2,500.00

054 Pierce - Furnish and install sheet metal below wall

sleeve where louver is over 4" off ground creating a gap

per RFI 75.

$2,500.00 $0.00 $0.00 $2,500.00 $0.00 $0.00 -$2,500.00

055 Pierce - Furnish and install a removable metal pipe

enclosure to conceal the exposed pipes per RFI 76.

$1,500.00 $0.00 $0.00 $1,500.00 $0.00 $0.00 -$1,500.00

056 Modify escutcheon plates to accomodate surface

mounted raceways.

057 Beverly - Add a removable mullion at the boiler room

door. The door and frame that was ordered does not fit

the existing opening per RFI 67.

$0.00 $863.00 $0.00 $0.00 $863.00 $0.00 -$863.00

058 Pierce - Funish and Install a new woord door at A123 per

RFI 79.

059 Bulletin 7 $0.00 $6,557.00 $0.00 $0.00 $6,557.00 $0.00 -$6,557.00

060 Bulletin 10

Project Totals: $24,651.00 $30,533.00 $72,680.00 $24,651.00 $30,533.00 -$6,789.00 -$127,817.00

Prolog Converge Printed on: 8/2/2016 Prolog_Converge Page 4