Upload
bayu-nurwinanto
View
215
Download
0
Embed Size (px)
Citation preview
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 1/57
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 2/57
Rehabilitation Coatings inIOCL
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 3/57
COATINGS USED IN WRPL
1. COAL TAR ENAMEL COATING (CTE)
2. COAL TAR BASED TAPE COATING (Hot tape)
Above two coatings stopped using for field
application due to environmental issues
3. FUSION BONDED EPOXY (FBE)
4. 3LAYER POLY-ETHYLENE COATING (3LPE)
Above coatings are suitable for plant coating only.
5. COLD TAPE COATING (Poly Ethylene)6. POLY URETHENE (PU)
Above coatings are presently being used for field
applications
7. LIQUID EPOXY COATING- Under trial run for bulk use
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 4/57
DESIRED PROPERTIES OF COATINGS
EASE OF APPLICATION
GOOD ADHESION TO PIPE GOOD IMPACT RESISTANCE
FLEXIBILITY
RESISTANCE TO SOIL STRESS
RESISTANCE TO FLOW (CREEP)
GOOD ELECTRICAL RESISTANCE
CHEMICAL STABILITY
RESISTANCE TO SOIL BACTERIA
RESISTANCE TO MARINE ORGANISMS
RESISTANCE TO CATHODIC DISBONDMENT
WATER PROOF
PERTOLEUM RESISTANCE
ECONOMICAL
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 5/57
Cold Tape Coating
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 6/57
Ultrasonic gauge
Surface Profile Gauge
SA 2 ½ films
Coat meter for measurement of primer thickness/Coating thickness
Holiday Detector
Adhesion Tester
Thermometer
Mirror
Instruments required at site
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 7/57
EXC V TION
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 8/57
Requirements of sand blasting
Inspect surface the pipe for pitting/ any defects
Check compressor, requirement – 7kg/sq.cm, 5.6 to 7
Cubic m/min, swing 15m
Abrasive size 1mm ( max), nozzle angle 30 deg.
Cleaning of pipe:
Inspect surface after blasting ( Ref SA 2 ½ visual
standard of SIS05 5900 “ Pictorial surface prep….Steel surface”.
surface profile:
50-75microns
Sand Blasting-cleaning of pipe
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 9/57
SA 2 ½ film-Before cleaning of pipe
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 10/57
SA 2 ½ film-After cleaning of pipe
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 11/57
Inner two layer+Outer
two layer
Outer-Inner
Pipe
Butyl rubber
Butyl rubber
PE
3ply/2ply Cold tape
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 12/57
COLD TAPE COATING APPLICATION
Primer:
Primer is a mix, of butyl rubber, syntheticcompound and solvent confirming to DIN-30672
Primer coat thickness shall be as per requirement.
(25 microns DFT) Before application of coating, primer shall be
touch dry on pipe.
Coating should be applied within the time
specified by the supplier after application of primer.
Excessive delay in application of tape willnecessitate application of fog coat of primer
before applying tape
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 13/57
Cold Tape – Application
Mastic putty.
Mastic putty is used to get the smooth surfaceat girth welds, sleeves and also at acceptable
defects. It is compatible for primer and tape for
getting bonding
3 ply / 2 ply PE tape.
1st layer ( 3 ply) consists of PE film sandwitched between butyl rubber films on bothside.
2nd layer (2 ply) or top ply PE film with butylrubber on the inner side
1st layer to be wrapped at a predefined tensionmachine with 50% overlap on primed surface.
2nd layer shall be over lap 50% on 1st inner tape
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 14/57
Cold tape pplication of Coating
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 15/57
Cold tape pplication of Coating
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 16/57
Cold tape pplication of Coating
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 17/57
Cold pplied Tape Peel testing
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 18/57
Cold pplied Tape Peel testing
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 19/57
( )
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 20/57
Polyurethane coating (PU)
Primer based/non-primer based PU100% Solids solvent free, two component,
High Build Polyurethane Coating.Blasting media: Copper slag, steel grit
Surface cleaning: Per SSPC SP-10 SA 2 ½
Surface Profile shall be 75-100 Microns
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 21/57
IMPORTANT PU SPECIFICATIONS
SL Properties Value required
1 Primer Shelf life 6 months minimum
2 Drying time at 25 Deg’ C Touch dry: 30 minutes
maximum.
3 Adhesion to steel (ASTM D 4541) >1500 PSI
4 Dry film thickness by one run 1250microns
5 Hard cure time 4 hours maximum
6 Tensile strength >12 N/sq.mm
7 Hardness shore D (ASTM D 2240) 65 shore D min
8 Impact resistance (ASTM G-14) More than 23 Nm
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 22/57
Blast cleaning pipe with copper slag
S f P fil M t ith P O Fil
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 23/57
Surface Profile Measurement with Press-O-Film
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 24/57
I t t ti f th fil ith S G
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 25/57
Interpretation of the film with Screw Gauge
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 26/57
Priming
Record Dew Point ,Substrate Temperature
Ensure the Substrate Temperature is at least 3
Deg C over the dew Point
Surface shall be free from loose dirt beforePriming
Mix Resin, Activator in 4.6:1 ratio by Volume
Wet Film Thickness 50 Microns
Theoretical Consumption 50 ml/ Sqr Mtr
Priming application
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 27/57
Priming application
P i li ti
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 28/57
Primer application
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 29/57
Primed Surface Curing till Touch Dry
Power Heating shall be done to Heat the Resin till 45
deg C
Ensure Substrate Temperature at least 3 deg Cabove Dew Point
Demarking on the Pipe for every Meter length
Tracking of the Volume of the Material Per Meter application shall be done by Numeric Counter on the
Coating Unit
Coating Application
PU i li i
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 30/57
PU coating application
Spraying with Tip Size 313
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 31/57
Spraying with Tip Size 313
PU C d
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 32/57
PU Coated pipe
Coating thickness measurement
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 33/57
Coating thickness measurement
Hardness Test
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 34/57
Hardness Test
Adhesion Test
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 35/57
Adhesion Test
Holiday Identification
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 36/57
Holiday Identification
Holiday Identification
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 37/57
Holiday Identification
General Defects in
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 38/57
General Defects in
Operating Pipelines
CORROSION DEFECTSInternal & External
MECHANICAL DEFECTSThird party
damage
Dents
Gouges
Cracks
Wrinkles/buckles
Arc burns
Mill anomalies
Laminations
Ovality
Blisters
Accepted pipeline repair methods
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 39/57
Accepted pipeline repair methods
Weld metal deposition- Not in regular practice in
IOCL Sleeves: for non leaking defects
Epoxy sleeve- no direct welding on pipe
Direct welding sleeve Composite sleeve- Non metallic compound
Mechanical clamps- for leaking defects
Pipe replacement Hot tapping- No pipe line shutdown
Open cut – Line shutdown required
Corrosion leak at Ch 3 3km ofVC
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 40/57
Corrosion leak at Ch 3.3km of VC
C k f ti i D t t 6 l k i SMPL d t
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 41/57
Crack formation in Dent at 6 o clock in SMPL due to
wooden skid at botom of pipe
Crack in pipeline due to Dent
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 42/57
Crack in pipeline due to Dent
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 43/57
PROCEDURE FOR LEAK
CLAMP INSTALLATION
Pipelines repair-By Leak clamp
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 44/57
Pipelines repair By Leak clamp
Basically accepted for all type of pipe repairs.
Recommended for repairing corrosion &
pilferage leaks, isolated pitting.
As a temporary repair in case of emergency
Design pressure of clamp should be more
than pipe being repaired
Not recommended where defects are
circumferentially oriented
Before installation of leak clamp neoprene
seal should be checked for its elasticity
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 45/57
DECIDING TYPE OF SLEEVE
Steps: Calculate ERFIf ERF =/> 0.95 or defect depth =/>80% wall thickness
prefer B type sleeve
1) If ERF < 0.95 or defect depth <80% wall thickness
analyze the defect through defect sentencing curves(defect length X axis & ratio of defect depth/WT on Yaxis
2) If the point falls in
Failure zone- B type sleeve
Repair zone-A type sleeve
Reassessment zone- A type sleeve/left with out repairas per site condition
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 46/57
History:SMPL pipe line is 28” Crude pipeline, constructed in 1978
Grade of pipe:API5LX52.
Defect & Observation:
Laminations- on one pipe only through out the
length and minor seepage of crude oil from laminations at
two/three locations observed during coatingrefurbishment. No further leakage of oil from pipe. No
cracks observed during inspection
Remedial action taken: Provided Continuous sleeve
Case Study of Pipe defect repair
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 47/57
Repair of pipeline defects-
By Hot Tapping Technique
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 48/57
Hot Tapping
Making a hole on pipeline for the purpose of jointing a section with an
operating pipe line at operating pressurewithout shut down of operating line.
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 49/57
Where Hot Tapping is required ?
1.Replacement of a section.
2.Rerouting of line3.Take off a new line from existing
line.
4.Hook up a line with another line
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 50/57
Advantages of Hot tapping
1. Avoid thruput loss.
2. Saving of money.
3. Avoid retrieval & transportation of bulk
quantity of product.
4. Safe operation, no spillage of product5. Environmental friendly.
6. Fast operation.
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 51/57
Hot tapping flash presentation link
Safety measures in Pipeline
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 52/57
Safety measures in Pipeline
maintenance Recommendations
◦ EIC / Site engineer to ensure trench is prepared as per tender specification and site requirement.
◦ Adherence to safety guidelines shall be certified by Site
Engineer / EIC and supervisor by generation of checklist
type format.◦ Display boards to be displayed showing trenching design
and danger of working in trench.
◦ PPEs to be worn by all the labours. This to be ensisted
by Site Engineer / EIC◦ Provision of shuttering for trench more than 2.0 m
◦ All works to start with TOOL BOX TALK
◦ Surprise checks to be carried out by Senior executives
Format for checks during trenching works
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 53/57
Format for checks during trenching worksS.No. Activity Status
01. Clearance given by EIC to start excavation at the site
02. Tool Box Talk given to all Contractor labour and supervisor
03. Lift tools to be used at site viz., crane, sling are tested and testing certificate(s)
checked and available at site
04. The Crane operator is holding valid driving licence and more than 21 years of age
(10.9.1.3 GCC)
06. Register of wage-cum-Muster Roll for the workmen opened at site
07. Proof regarding qualification of the supervisor checked.
08. Workmen’s Compensation Insurance
09. Safety helmet provided to all worker for safety of personnel working
10 First Aid Box with medicines placed at site
11. Drinking water available
12. Trench beyond 1.5 meter up to 3.0 meter (6.1.5 OISD-GDN-192)
Safe angle of repose 45 degree and 0.5 meter width and every 1.5 meter depth
Beyond 3.0 meter
Required shuttering and scaffolding provided
13. Barricade at 1 M height (with red and white band, self glowing caution board) for excavation beyond 1.5 meter (6.1.10 OISD-GDN-192)
14. Arrangement for entry into and exit from the trench.
15. Trench more than 4’ to have one ladder for more than 100’.
Ladder shall be extended from the bottom of the trench to at least3’3” above the
surface of the ground.( 10.5.2.0 GCC)
16 Excavation (10.5.2.0 GCC)
Excavated material shall not be placed within 5’ of the edge of the trench or half of the trench deep which ever is more
Mainline emergency Equipment
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 54/57
Mainline emergency Equipment
Equipment required for Mainline emergencies:
Generators, Compressors, Welding machine,
Dewatering pump, Pneumatic pump, Cold cutting
machine, Fire extinguishers etc are kept at
stations/ base stations.
These are mobilised to the repair site on
requirement basis during any emergency.
In case of non availability, the equipment are to
be taken on hire basis.
Maintenance of M/L equipment system
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 55/57
Maintenance of M/L equipment system
All the equipment should be run trouble free during
maintenance of any mainline work.
Trial run should be taken for all equipment for 15
minutes on monthly basis and monitor the condition of
each equipment and details should be noted.
Any defect noticed during trial run should be rectified
immediately with proper maintenance
The record of the trial run, defects observed and
maintenance carried out if any should be maintained as
per the format.
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 56/57
Discussion session
7/27/2019 Jpsinha II
http://slidepdf.com/reader/full/jpsinha-ii 57/57
Thank you