21
REPUBLIC OF KENYA THE JUDICIARY JPIP FIRST QUARTER PROGRESS WORKSHOP REPORT, JUDICIARY TRAINING INSTITUTE NAIROBI, KENYA 26- 27 TH NOVEMBER 2013 Prepared by: Fredrick Ombwori, Joseph Osewe and Victor Lumumba

JPIP Report 5-12-13

Embed Size (px)

Citation preview

Page 1: JPIP Report 5-12-13

REPUBLIC OF KENYA

THE JUDICIARY

JPIP FIRST QUARTER PROGRESS WORKSHOP

REPORT, JUDICIARY TRAINING INSTITUTE

NAIROBI, KENYA

26- 27TH

NOVEMBER 2013

Prepared by: Fredrick Ombwori, Joseph Osewe and Victor Lumumba

Page 2: JPIP Report 5-12-13

2

TABLE OF CONTENTS

1.0 INTRODUCTION ............................................................................................................... 3

1.1 Goal and Objectives ...................................................................................................................... 4

2.0 OPENING REMARKS, Mr. Kakai kissinger, Ag CRJ ....................................................... 5

3.0 JPIP 1ST

QUARTER PROGRESS REPORT, Kennedy Mugonyi ...................................... 6

3.1 Procurement .................................................................................................................................. 6

3.2 Financial ........................................................................................................................................ 6

3.3 Implementation structures ............................................................................................................. 6

3.4 Project Management Unit ............................................................................................................. 6

3.5 Integrated fiduciary agent ............................................................................................................. 7

3.6 Challenges ..................................................................................................................................... 7

3.7 Suggestions ................................................................................................................................... 7

3.8 Plenary Discussion ........................................................................................................................ 7

4.0 PROCUREMENT, Michael Obuya ..................................................................................... 8

4.1 Procurement procedures for JPIP .................................................................................................. 8

4.2 Procurement for Training Workshops and Seminars .................................................................... 9

5.0 CIVIL WORKS, Arch John Okello ................................................................................... 10

5.1 Scope of Infrastructure works ..................................................................................................... 10

5.2 Works in progress ....................................................................................................................... 10

5.3 Rehabilitation projects initiated .................................................................................................. 11

6.0 COMMUNICATION, Nicholas Simani ............................................................................ 11

7.0 FINANCIAL MANAGEMENT AND STANDARDS, Jackson Karanja ......................... 12

7.1 Role of IFA ................................................................................................................................. 12

7.2 Processing of payments ............................................................................................................... 12

7.3 Staff payments ............................................................................................................................ 13

7.4 Imprest ........................................................................................................................................ 13

7.5 Proposals/requests ....................................................................................................................... 13

7.6 Ineligible expenses ...................................................................................................................... 13

8.0 ROLES AND RESPONSIBILITIES, Mbuba Mbungu ..................................................... 14

8.1 Specific roles and responsibilities ............................................................................................... 15

9. ROLE OF M&E IN JPIP, Kennedy Mugonyi ..................................................................... 16

10. ANNUAL WORK PLAN 2014/15, Mbuba Mbungu ........................................................ 17

10.1 Proposed time lines for 2014/15 JPIP Work plan preparation .................................................. 17

11. WAY FORWARD, Beatrice Kamau ................................................................................. 18

ANNEXES ............................................................................................................................... 19

Annex 1. Progress as at September 2013 .......................................................................................... 19

Annex 2: Planned Activities for Q2-Q4 That Commenced In Q1 .................................................... 20

Annex 3: List of Participants ............................................................................................................ 21

Page 3: JPIP Report 5-12-13

3

ABBREVIATIONS

Ag Acting

AO Accounting Officer

AWP Annual Work plan

CUC Court Users Committee

CRJ Chief Registrar of Judiciary

DF Directorate of Finance

DPAC Directorate of Public Administration and Communication

DSCM Directorate of Supply Chain Management

DCRJ Deputy Chief Registrar of Judiciary

HC High Court

IFMIS Integrated Financial Management System

IDA International Development Association

IU Implementing Units

IPMAS Integrated Performance Management Accountability system

ICT Information Communication Technology

IFA Integrated Fiduciary Agent

JPIP Judiciary Performance Improvement Project

JTF Judiciary Training institute

JSC Judiciary Service Commission

LPO Local Purchase Order

LSO Local service Order

M&E Monitoring and Evaluation

NCAJ National Commission of Administration of Justice

OCRJ Office of the Chief Registrar of Judiciary

PC Performance Contracting

PMU Project Management Unit

PM Performance management Directorate

PWC Price Water house coopers

Q1-4 Quarter one to four

TOR Terms of Reference

WB World Bank

Page 4: JPIP Report 5-12-13

4

1.0 INTRODUCTION

The Judicial Performance Improvement Project (JPIP) is financed through a credit from the

International Development Association (IDA). It is a six year project estimated to cost

US$120m. The objective of the project is to strengthen the capacity of the judiciary to deliver

justice expeditiously, effectively, transparently and in an accountable manner. The project

became effective on 30th

April, 2013 and officially launched on 30th

July, 2013.

The JPIP 1stquarter report workshop was held on 26-27

th November, 2013 at the Judiciary

Training Institute, Nairobi. It was organized and facilitated by the JPIP, Performance

Management Unit (PMU), Integrated Fiduciary Agent (IFA) and attended by JPIP

implementing units.

Mr. Mbuba Mbungu, Operations and Procurement Consultant welcomed participants to the

workshop and asked them to individually introduce themselves before inviting Ag Chief

Registrar of the Judiciary for his opening remarks.

1.1 Goal and Objectives

The workshop was organized to share a draft report on the status of implementation of JPIP

for the 1st quarter of 2012/2013 Financial Year, discuss operational issues and understand

roles of various implementing units. The specific objectives were as follows:-

Presenting first quarter M&E draft report to stakeholders for review and comments to

enable finalization of the report.

Identifying whether planned and implemented activities are producing the intended

results

Providing early warning of any potential problems/challenges encountered and

recommending mitigating measures

Discussing operational areas that are not very clear that for example lead to late

submission of requests from the implementing units

Capacity building for the implementing units on requisite project skills (procurement,

financial operations and Monitoring and Evaluation

The workshop demonstrated clear links and synergies between implementing units.

Page 5: JPIP Report 5-12-13

5

2.0 OPENING REMARKS, Mr. Kakai kissinger, Ag CRJ

Mr. K Kissinger, Ag Chief Registrar of the Judiciary, during his opening remarks expressed

gratitude to all the implementing units for their continued resilience in rolling out the planned

activities of JPIP. He underscored the importance of the review meeting of the project in

enabling the implementing units assess their performance and identify areas of improvement.

He noted with concern that the progress made in the first quarter of implementation of the

project is not impressive keeping in mind the annual targets. He asked the implementing units

to make concerted efforts to ensure timely requests for approval for purposes of proper and

speedy implementation of the project.

He implored participants to understand project objectives, components and activities and

relate them to Judicial Transformation Framework. He informed members that

implementation of the project as well as planning and budgeting will be coordinated by PMU

and will be supported by IFA. He asked the participants to support the units in providing

information and liaising with them in order to ensure smooth implementation of the project.

Communication which is vital in any program implementation needs to be enhanced and

sustained according to the Ag CRJ.

The progress report will be shared with the JSC and all implementing units who were

encouraged to give timely comments to enrich the process. He emphasized that the PMU is

the engine of the project and should always be consulted in the event of any constraints.

Additionally, he reminded the units that the program is supposed to run for six (6) years and

that one year has elapsed and the performance of the implementing units assessed and ranked

accordingly. Some of the worst performing units include Supply Chain Directorate, Office of

the Chief Justice, office of the Deputy Chief Justice, Office of the Chief Registrar of the

Judiciary (OCRJ), Judiciary Transformation Framework (JTF) secretariat and

Ombudspersons Office while some of the best performers include, Performance Management

Directorate, National Commission on Administrative Justice (NCAJ), and Office of the

Deputy Chief Registrars of the Judiciary (DCRJ’s).

According to the report of Ksh2.1 billion allocated for the first year, only Ksh63 million

representing 0.3 % has been spent hence the conclusion that overall implementation process

is not on track as intended.

The poor performance according to the Ag CRJ can be attributed to operational challenges

including the length of time taken by World Bank to give the No Objection, the lengthy

procurement process, operational issues and the lengthy time taken to access funds from

Treasury.

In conclusion he urged all the implementing units to continually engage and consult the PMU

and amongst themselves when faced with challenges.

Page 6: JPIP Report 5-12-13

6

He noted that some of challenges that have greatly impacted the implementation of JPIP

programs include the recruitment of the Project coordinator with continued objection from

the World Bank.

3.0 JPIP 1ST

QUARTER PROGRESS REPORT, Kennedy Mugonyi

According to the annual work plan the Judiciary committed to implement 154 activities in 9

key result areas and 13 indicators. The Court Administration component had 87 activities,

case management 6, Judiciary Training and Development 18, Court infrastructure 39 and

Project management 4.

Sixty eight (68) activities were scheduled to be implemented in the first quarter, of which 52

are under court admin & case management, 7 under judiciary training and development, 5

under court infrastructure; and 4 under project management. 9 activities (13%) were planned

to be completed in quarter 1 out of which 7 were completed. Activities started and scheduled

to complete in Q2, Q3 and Q4 are 19, 14 and 26 respectively.

Overall 48% of the work plan activities have commenced in which 44% are at less than 25%

implementation. Only 4% were achieved that is development of Court Users Committee

(CUC) policy and Guidelines, designing and implementing a training curriculum in change

management, streamlining of registry systems processes and structures of the High Court’s,

establishment of PMU and IFA, development of transformation magazine and one capacity

building for IUs.

3.1 Procurement

Seven (7) contracts were at bid preparation stage, 3 contracts were at bid evaluation stage and

1 contract for technical assistance to develop Integrated Performance Management and

Accountability System (IPMAS) and an Annual Staff PerformanceReview system was in the

short listing stage.

3.2 Financial

The total budget for 2013/14 is Kshs2,601,688,302 out of which 27% is allocated court

administration, 13% case management, 11% judiciary training and staff development, 44%

infrastructure and 5% Project Management. A total sum of US$ 619,339 of the project

financial advance has been spent since the project started. Consisting of US$ 484,349 used on

preparatory technical assistance, and US$ 134,990 used on training and development in the

design of the project. These funds had not been expended on goods.

3.3 Implementation structures

The Project Technical Committee has been set up and has been providing quality assurance

and overall technical guidance for the project. It approved the 2013/14 JPIP work plan and

budget and transmitted to the World Bank and is overseeing the implementation of the project

in line with the finance agreement.

3.4 Project Management Unit

It was established and coordinates day to day implementation of the project and provides

monitoring, evaluation, reporting, communication as well as technical guidance on civil

engineering and architectural matters relating to court construction.

Page 7: JPIP Report 5-12-13

7

3.5 Integrated fiduciary agent

It was established however, has been understaffed. Required to have 5 staff but only 2 are

currently in the project. The WB has cleared PWC’s request to substitute 3 IFA staff that

were not able to take up their positions in June 2013. The IFA staff are expected to report in

December, 2013

3.6 Challenges

Delays in approvals - It is noted that the project has initiated processing of major contracts

that are also subject to World Bank approval. Unfortunately, approvals and review takes time,

making it difficult for the Project to live up to the timelines on the Work plan and

Procurement Plan.

Internal constraints - On the other hand, internal constraints also cause delays; these include

late submission of specifications, TORs, and cost estimates by implementing units to supply

chain management, formation of various committees, completion of evaluations, and

approvals by Tender committee.

Financial Bottlenecks - Bottlenecks in disbursement and thereby accessing funds result into

delays in project implementation. It is therefore critical that any future deadlocks that could

delay disbursement and thereby utilization of funds be resolved quickly.

3.7 Suggestions

Timely Planning - Timely planning remains critical in improving implementation and

absorption rates. Therefore, there is need for project implementing units and agencies at all

times to undertake timely planning in order to ensure early commencement of activities.

Capacity building - Weaknesses in capacity particularly on requisite project skills can pose a

challenge on timely implementation of activities. Therefore there is need for capacity

building in critical project skill areas of planning, budgeting, implementation, reporting and

M &E.

Focus on judicial performance - Activities proposed for work plan should be well thought

out and prioritized based on how they contribute to the project objectives. Careful planning,

sequencing of activities is critical to ensure performance and improvement.

Increased dedication and commitment - Participatory approach in implementation and

cooperation among the implementing units is key in the success of the project. To promote

this, there is need for constant dialogue among the players in the project.

Communication and flow of information - To facilitate improved project implementation

and coordination, continuous communication and flow of information between implementing

units, PMU, IFA and the World Bank should be enhanced and speeded up.

3.8 Plenary Discussion

Inadequate communication on implementation of the project by various implementing units

especially supplies chain management, finance and accounts. It was resolved that finance

should generate a summary of utilization of funds and circulate to all units every month.

Page 8: JPIP Report 5-12-13

8

It was noted that the indicators in the annual work plan were not understood as well as were

not widely consulted. It was agreed to have a meeting on 24th

January 2014 to engage the

indicators.

On procurement participants agreed to initiate the process in time especially those with no

financial implication. in time so that they can utilize the funds

4.0 PROCUREMENT, Michael Obuya

Procurement forms a major part of JPIP and must carried with due care. Failure in this area

means failure of the whole project. It should be carried out with due attention to economy,

efficiency and transparency. To effectively conduct this process, we need to be committed,

motivated and knowledgeable. In JPIP context it involves procurement of goods, works and

services. Contract packages in the procurement plan are linked to units work plan.

Procurement is only done as per procurement plan except items for training and other

operations. A procurement contract is between the Judiciary and a supplier a contractor or a

consultant. It is done by competition, negotiation or direct purchase.

4.1 Procurement procedures for JPIP

World Bank procedures - Are used for all Goods contracts over US$ 500,000 (SH 42.50

Million], all works contracts over US$ 5.00 million (SH 425.00 Million], all Procurement of

Consultants.

National procurement procedures- Are used for all Goods contracts between US$ 80,000-

500,000 (SH 6.8-42.5 million], all works contracts between US$ 80,000- 500,000 (SH 6.80-

425.00 million], request for quotations to be used for all contracts below US$ 80,000 [SH

6.80 Million].The National procurement procedures are guided by the public procurement

and disposal act (2005), regulations (2006) and a general procurement manual. The

exceptions are provided in the PAD Page 51 &51 and Financing Agreement Page 13.

Information required for procurement

i. Schedule of requirements – goods, works, services

ii. Cost estimates - every contract package

iii. Specifications - Goods

iv. Drawings and Tender Documents- works

v. Terms of reference – consulting services

Procurement stages requiring attention i. Short-listing consultant firms

ii. Bid and proposal evaluation

iii. negotiations

iv. Contract supervision

v. Payments

vi. Disputes

Important Documents in procurement

i. Annual work plan and Procurement plan

ii. Internally generated project progress reports

iii. Latest project supervision mission reports, including aide memoirs

iv. Communications from project management

v. Newspaper and other JPIP-related reports

Page 9: JPIP Report 5-12-13

9

Because procurement process is so lengthy, there is need for Planning, by preparing annual

work plans and procurement plans. There is also need for budgetary adequacy and cash

releases, cooperation with others. The roles of Judiciary staff are to prepare procurement

plan, prepare and issue bidding documents, inviting bids/proposals, receiving and evaluating

bids/proposals, awarding contracts and supervising implementation of contracts.

The role of the World Bank in the process is to supervise the process by reviewing

procurement plan, advertisement notice, bidding documents [goods/works] and request for

proposals, bid and proposal evaluation reports – proposed contract awards, draft contracts,

contract amendments, performance on contracts and other procurement matters to ensure

compliance with credit agreement and ex-post procurement.

4.2 Procurement for Training Workshops and Seminars

Procurement is one of the most important processes that will ensure the JPIP is successful.

80% of the activities involve procurement which is governed by the procurement Act that

describes procurement cycle. This cycle includes Need Recognition; Referring to the Project

AWP/Procurement Plan; Funding Approval; Service Provider Selection; Procurement

Evaluation; Contract Award; Placement of a Purchase/Service Order; Contract Management;

and Record Maintenance.

According to the work plan each implementing unit has a number of trainings lined up to

conducted within the first year of implementation of JPIP as listed below; DPAC-

2;OCJ/ODCJ-2; OCRJ-2; ODCRJ-3; JSC-3; JTI-3; DF- 3; DSCM-2; CAO-2; HC-1; *PMD-

1; ICT- 1; RMC-4.Consequently all procurement requests should be done in conjunction with

JPIP procurement specialists.

Before any implementing unit makes any procurement request, the following needs to be

adhered to avoid any delays. First, the requisition must include the type of training, number

of participants, location (town), duration and facilitators’ names. This should be submitted in

two or three weeks for local and international training respectively to the project coordinator.

Secondly, the budget for the training should be broken down and comply with the JPIP

annual work plan.

The procurement rules that have been put in place allows only for the requisition of the

venue, transport, training material and facilitators/ consultants. The government owned

venues must be legally and financially autonomous, operating under commercial law, and

should not be dependent on the government.

After the conclusion of the training, for payment to the suppliers, the implementing unit in

conjunction with IFA and PMU must have the following Approved Requisition; Invoice;

Signed daily attendance list; Daily room list from hotel; Activity report; quotations and

comparison report and Signed minutes of the Tender Committee or Procurement Committee.

In addition to this , per diem will only be payable in events that are more than one day and

will be governed by the respective judiciary and government payment rates that are eligible

under the world bank guidelines. The anticipated reimbursable expenses should be included

in the budget or will not be reimbursed at all. For all these to be successful, the implementing

units need to make timely and planned requests that take into consideration their preferences

Page 10: JPIP Report 5-12-13

10

5.0 CIVIL WORKS, Arch John Okello

Civil works is covered under Judiciary Transformation Framework 2012-2016 Pillar 3, on

provision of adequate financial resources and physical infrastructure and Pillar 4, on

harnessing technology as an enabler for Justice since the Courts have to be fully equipped

with adequate ICT infrastructure. Court Infrastructure means buildings and permanent

installations necessary to modernize the Judiciary. This includes constructions of ten new

courts, rehabilitation of thirty courts, inclusion of ICT in sixty eight courts, and setting of a

building unit.

The main reasons why Courts are constructed are to better functional performance, enhance

security, comfort, health and access, improve efficacy and rationalization of space, greater

strategic, transparency and management capacity for capital investments. The infrastructure

work for the World Bank project covers the below mentioned areas

5.1 Scope of Infrastructure works

SNo. Scope Type of court Number Cost

1. Construction High Courts 8 US$

277.2m/Court Magistrate Courts 2

2. Rehabilitation Magistrate Courts 30 US$ 9m/Court

3.

Existing Courts for installing ICT and

Refurbishment of demountable

buildings

-

20 US$ 6m

4 Building services unit - - US$ 2m

5.2 Works in progress

Location Type of

court Contract sum

Start

date

Due end

date Remarks

Kangema Magistrate

Court Kshs17,093,631.00 8/07/2013 16/12/2013

45 % complete,

Additional Works to

accommodate fencing and

a new Administration

Block are to be tendered

separately

Kitui County

High Court Kshs57,581,327

Work done 0%,

Additional Works to

accommodate: Fencing

are to be tendered

separately

Projects to be constructed which have been initiated include Siaya, Kakamega, Olkalau, Nanyuki,

Nakuru, Kajiado, Mombasa, Wajir, Garissa High Courts, and Kabete, magistrate Court

Page 11: JPIP Report 5-12-13

11

5.3 Rehabilitation projects initiated

Cluster A

LOCATION COURTS CHAMBERS

Engineer 2 2

Kigumo 2 2

Chuka 4 4

Cluster B

LOCATION COURTS CHAMBERS

Molo 3 3

Nyando 3 3

Vihiga 4 4

Cluster C

LOCATION COURTS CHAMBERS

Oyugis 3 3

Muhoroni 2 2

Nyamira 4 4

Cluster D

LOCATION COURTS CHAMBERS

Makueni 4 4

Makindu 3 3

Mukurueini 3 3

Kibera 10 10

The following are the court facility problems identified in 2009

i. Lack of space for important court functions in many buildings

ii. Inadequate number of courtrooms and size

iii. Inadequate storage space for evidence and records

iv. Lack of space for libraries

v. Inadequate space for remanded defendants, including lack of separate facilities for females,

males, and juveniles

vi. Inadequate space for services such as help desks, court-annexed mediation, small claims

courts

vii. Inadequate building capacities for automated and sound recording equipment

viii. Inadequate security, including lack of separated internal building circulation for judges,

public, and defendants in remand

ix. Lack of public amenities, such as handicap accessibility and restrooms.

x. General building deterioration and structural problems affecting functionality, health, and

safety

xi. Long distances and travel times to available courts for many citizens

6.0 COMMUNICATION, Nicholas Simani

Communication is the life line of an organization and must at all times be credible. The cornerstone of

credibility is integrity and the foundation of integrity is constant and complete consistency of flow of

relevant communication and performance. The Judiciary must be an organization that is seen, heard

and felt as an institution that is geared at improving quality of service at all times.

Page 12: JPIP Report 5-12-13

12

Recent surveys indicate that 70% of Kenyans have confidence in the Chief Justice while 84% still

believe that the courts are dispensing justice with 77% preferring to use the courts to resolve their

disputes. This however is coupled with some dislikes including delay in handling cases, easily

corruptible staff and poor working environment. This therefore calls for a good communication

strategy that will help disseminate information about the progress of JPIP to both the internal and

external publics.

This can be done using media briefs to enhance relationships with the media houses, Infomercials,

documentaries, features, brochures, periodic e-magazines and calendars. Other activities that are being

undertaken to enhance communication include the revamping of the Judiciary Website to be all

inclusive and comprehensive, development of Judiciary Cooperate service charters from which all

other directorates can draw their respective from and the use of Mahakama football club in

communication and advocacy. All these are supposed to enhance corporate ownership, commitment,

trust, access to information, accountability, transparency and availability of feedback on the

implementation outcomes.

The scope of work of the communication consultant include; Identifying events on JPIP that require

packaging for dissemination to the media and to the public; Advice the Judiciary on the best media

practices which promote good Judiciary relations; Gather information on the project’s success story

and the themes that can be used in communication campaigns; Enhance Media

relations/briefings/press releases; and produce appropriate infomercials, documentaries, features

articles on Judiciary programmes and activities with the hope of improving the visibility of JPIP on

improving service delivery by the judiciary.

7.0 FINANCIAL MANAGEMENT AND STANDARDS, Jackson Karanja

7.1 Role of IFA

IFA is responsible for the procurement and financial management of the project, on behalf of

the Judiciary. It assists in capacity building, support and knowledge transfer to judiciary staff.

It also assists in preparing annual budgeting, based on the AWP, manage the project’s bank

account, preparing the annual financial statements, IFRs and IDA credit withdrawal

applications for submission by the Judiciary to World Bank through Finance. Processing

disbursements, expenditure control, reconciliation of project bank account, and overall

expenditure control systems for the project, preparing regular financial reports for auditing on

timely basis and prepare appropriate financial procedures.

7.2 Processing of payments

Implementing units will be required to raise requests or proposal to the Project Coordinator

for approval. Once approved will be submitted to IFA for onward submission to procurement

and Accountants for imprest processing. In case of goods and services procurement will

requests for bids or quotations. Procurement will oversee the bidding process and will notify

successful bidders. It will raise LPO/LSO for successful bidders for the Project Coordinator

and head of IFA approval. The successful bidders will raise invoices, which the IFA

accountant will validate and payment will follow the normal process of voucher preparation,

examination, vote book etc. Finally payment will be forwarded to G-Pay 1 and 2 for approval

and payment. Once payment is made IFA accountant informs suppliers, stamps the invoice

PAID and files the PVs. IFA accountant posts Payment Voucher to the cash book.

Page 13: JPIP Report 5-12-13

13

7.3 Staff payments

Staff submits claim/request to Project Coordinator approval. Once approved it is submitted to

IFA accountant. IFA accountant checks and sends it to the invoice. Payment goes through the

same stages listed above as for the suppliers.

Per diems - Per diems will be processed as imprests. Judiciary staff travelling outside Kenya

will be paid as per memo ref. JSC 1/2 of 23.12.2011 and within Kenya will be paid as per

letter ref. JSC 1/2 of 9.8.2011. Non judiciary staff will be paid as per the relevant GoK

circulars.

Workshop support and travel - Venue invoice, LPO/LSO, Signed daily attendance list,

daily room list from hotel and Activity report are required. On transport a work ticket for

local transport and boarding passes and copy of passport required showing exit and entry.

Trainings - The AWP must specify the type of training, Purpose, Personnel to be trained,

Institution or individual who will do the training, Location and duration and cost. Staff

trainings should follow the internal procedures and approvals

7.4 Imprest

Imprest is a cash advance or float authorized by the Accounting Officer (AO) to be issued to

officers whose payments cannot be conveniently be made through the cash office. Holder of

temporary (safari) imprest should account for it within 48 working hours after return to duty

station. Foreign travel should be supported by the boarding pass or passport copy and receipts

for ground transport. Local imprest (other than per diem) should be supported by receipts of

the actual costs and work tickets. Perdiem should be supported by the work tickets

Processing of imprest - User requests vide proposal/ budget. PC approves. IFA checks and

forward for processing. Imprest warrant filled and signed by holder, Warrant is signed by

Accounts section. Imprest invoiced in IFMIS. Imprest is validated and forwarded for payment

and Imprest paid via G-Pay.

7.5 Proposals/requests

Should be submitted to PC two weeks in advance. PC approves and forwards them to IFA.

Directorates should ensure that the activity is in the approved AWP & B. For workshop

venues, the facilities required should be stated. Venues, unless there is adequate justification,

should be at the JTI.

Contents of proposal - Should have an introduction, objective(s) of the activity, expected

outputs, budget. It should also indicate TORs for consultants/facilitators, proposed dates and

itinerary and travel dates. Component and Name of imprest holder should be provided.All

procurements should be ready two days before start of activity and Imprest should be ready

one day before start of activity.

7.6 Ineligible expenses

Salary top ups. Sitting allowances (for attending workshops, project steering committee

meeting, other committee meetings, etc). Honorarium (payments for services performed in

committees, meetings, workshops, etc) and Internal consulting of public and civil servants

currently on government payrolls.Sitting allowances, honorarium etc to consultants financed

under a project.

Page 14: JPIP Report 5-12-13

14

8.0 ROLES AND RESPONSIBILITIES, Mbuba Mbungu

The roles and responsibilities of implementing units was made by Mr. Mbuba Mbungu,

Operations and Procurement specialist, JPIP. He underscored the fact that procurement forms

the major part of JPIP in terms of financing and activities. In this regard, it must be done with

due diligence and in a transparence manner. This therefore calls for development of annual

procurement plan. Failure in procurement is actually failure in the whole Project.

Procurement must be negotiated and done competitively. However, we have instances where

it can be done through individual sourcing. World Bank rules will apply for All Goods

contracts over US$ 500,000 (SH 42.50 Million], All Works Contracts over US$ 5.00 million

(SH 425.00 Million]. National procedures will apply for Goods contracts between US$

80,000- 500,000(SH 6.8-42.5 million], all Works Contracts between US$ 80,000-500,000

(SH 6.80-425.00 million]. Request for quotations will be for contracts below US$ 80,000 (SH

6.80 Million).

Information required for procurement include schedule of requirements, cost estimates,

specifications, works and terms of reference. The Procurement processing stages requiring

attention are Short-listing consultant firms, Bid and proposal evaluation, negotiations,

Contract supervision, Payments and disputes.

The major challenge facing procurement is the long procedures. In order to address this there

is need to ensure timely planning, reduce internal bureaucracy, institutional rules and

procedures, arrangements, ensure budget adequacy and cash releases and ensure cooperation

with others.

Role of judiciary staff - solely responsible for procurement, prepares procurement plan,

prepares and issues bidding documents, invites bids/proposals, receives and evaluates

bids/proposals, awards contracts and supervises implementation of contracts.

On the other hand the role of world bank will include supervision of process, assists borrower

in preparation of projects, provide procurement training, review of procurement plan, bidding

documents, Bid and proposal evaluation reports, draft contracts, Contract amendments,

Performance on contracts and other procurement matters to ensure compliance with credit

agreement.

In addition it verifies withdrawal applications prior to disbursements, monitors procurement,

addresses complaints from firms on procurement matters and declares misprocurement.

Plenary

In order to fast truck procurement of goods and services participants proposed that the

tender committee of the Judiciary should meet more often than twice a month.

Participants suggested to having feedback on the status of procurement of their

requests monthly by PMU.

Page 15: JPIP Report 5-12-13

15

DAY TWO

Day two begun by having a recap of roles and responsibilities of implementing units on

procurement.The session was designed to allow participants time and opportunity to reflect

on the purpose or definition of their role, their role within the project team and interactions

with key stakeholders.

8.1 Specific roles and responsibilities

S/NO ACTIVITY RESPONSIBLE PARTY

START-UP OPERATIONS

1 Prepare Schedules of requirements and Budget IMPLEMENTING UNIT

2 Prepare General Procurement Notice if need be IFA

3 Preparation of the Procurement Plan IFA

4 Open and keep a procurement file for each contract IFA

PRECONTRACT OPERATIONS

5 Prepare specifications, TORs, cost estimate of the contract

package and send to Procurement

IMPLEMENTING UNIT

6 Prepare and have approved Bidding/Proposal

Documents

a)Goods IFA

b)Works contracts IFA/ PMU

c)Consulting Services IFA

7 Advertise for bids or Expression of Interest or

Prequalification

PIFA

8 Constitute Bid/Proposal Evaluation Committee IFA

IMPLEMENTING UNIT

9 Prepare a short-listing report for selection of consultants IFA

IMPLEMENTING UNIT

10 Prepare a shortlist of suppliers for an RFQ contract IFA

11 Prepare a shortlist of contractors for a small works contract PMU Engineer

12 Open bids/Proposals IFA

Evaluate Bids/Proposals IFA

IMPLEMENTING UNIT

13 SUBMIT APPROVAL REQUESTS TO:

a)HEAD OF IMPLEMENTING UNIT IFA

b)TENDER BOARD IFA

c)WORLD BANK PMU

14 Approve proposed contract award Tender Board.

Which one?

15 Prepare notification of proposed contract award IFA

16 Issue notification of proposed contract award Secretary to the tender

committee

17 Prepare contract documents IFA

18 Contract Negotiations IFA/ Tender Processing

Committee

19 Signing of Contracts Accounting Officer

CONTRACT MANAGEMENT

20 Mobilize Supplier, contractor, Consultant IFA

21 GOODS:

Place orders and supervise delivery

IFA

Receive goods and certify delivery Tender processing committee

Certify invoices/payments IMPLEMENTING UNIT/IFA

Deal with Disputes IFA

Page 16: JPIP Report 5-12-13

16

IMPLEMENTING UNIT

Certify Contract completion IMPLEMENTING UNIT/IFA

19 WORKS: Supervise works PMU ENGINEER

Approve valuations and Payment certificates PMU ENGINEER

Deal with Disputes IFA

PMU

IMPLEMENTING UNIT

Certify Contract completion PMU ENGINEER

IMPLEMENTING UNIT

20 CONSULTANT SERVICES: Supervise assignment IMPLEMENTING UNIT

Receive, evaluate and certify consultant’s deliverables IMPLEMENTING UNIT

Certify payments IMPLEMENTING UNIT

Deal with Disputes IMPLEMENTING UNIT

IFA

Certify Contract completion IMPLEMENTING UNIT

MAKE PAYMENTS

21 Receive and certify invoice IMPLEMENTING UNIT

22 Make Payments IFA/ ACCOUNTS

CONTROLLER

23 Prepare a performance evaluation Report IFA

IMPLEMENTING UNIT

9. ROLE OF M&E IN JPIP, Kennedy Mugonyi

The presentation covered what M&E is all about including definition of key terms. The M&E

approach for the project was presented. Results Based Monitoring and Evaluation will be

used to track implementation of the project. This is guided by the development of a results

chain. It was emphasized that focus will be on achievement of outcomes and results as

activities and outputs do not necessarily imply that the desired outcomes and results have

been realized. The process will include stakeholders in setting targets and indicators. The

stakeholder involvement will assist in gathering of information and increased understanding

of their roles and expectations.

The M&E report will assist in planning and clarifying the objectives of the project, drawing

lessons from activities implemented, providing early warning of any potential problems,

feedback on performance of project, establishing whether planned and implemented activities

are producing the intended results.

The following steps will be followed in undertaking M&E. Readiness assessment, agreeing

on the outcomes to monitor and evaluate, selection of key indicators to monitor outcomes,

establishing baseline data for the indicators identified, selecting results targets, monitoring

results, midterm evaluation, reporting findings, using findings and assistance on sustaining

M&E system within the Judiciary.

Six supplementary indicators outside the results framework were proposed that can measure

changes in accountability of judicial officers. They include case clearance, employee

engagement rate, reduction in time taken to retrieve/access a document in the project courts,

corruption eradication, rate of performance based on IPMAS and court productivity.

Page 17: JPIP Report 5-12-13

17

The implementing units will be required to identify required baselines where not available,

provide regular information on progress made, information on outputs and whether they

contribute towards achievement of outcomes and gathering information for M&E.

It was noted that an impact evaluation will be done on an identified project intervention. It

was stated that Impact evaluation is aimed at providing feedback to help improve the design

of programs and policies because it helps in attributing observable changes onto an

intervention.

10. ANNUAL WORK PLAN 2014/15, Mbuba Mbungu

A work plan is an outline of a set of goals and processes by which a team and/or person can

accomplish those goals, Offers a better understanding of the scope of the project. Work plans

help in organizing while working on projects. Through work plans, you break down a process

into small, achievable tasks and identify the things you want to accomplish.

Key steps for preparation of the work plan was also presented including determination of

goals and objectives, resources available, responsibility, anticipated risks and constraints etc.

In addition, highlights on financial agreement requirements for preparing the next JPIP work

plan were presented.

Format - The objective of having a detailed work plan structure is to have a traceable

pathway from inputs to activities and activities to outputs, and performance against

objectives, using indicators and available evidence. The following is the format of the annual

work plan.

ACTIVITY OBJECTIVES PERFROMANCE

INDICATOR

OUTPUTS INPUTS ESTIMATED

COST KSHS

10.1 Proposed time lines for 2014/15 JPIP Work plan preparation

ACTIVITY DATE RESPONSIBILITY

1. Guidelines issued for Annual Work

plan (AWP) preparation 15

th Dec 2013 PMU

2. Preparation of Draft WP by IUs 16

th/12/2013 –

4th/2/2014

IUs

3. Submission of draft WP by IUs 4th Feb 2014 IUs

4. Compilation of draft WP 4th -15

th Feb 2013 PMU

5. Workshop to discuss & prioritize

work plan activities 16

th Feb 2014 PMU

6. Incorporation of comments &

finalization of WP 16

th – 20

th Feb 2014 PMU

7. Endorsement of AWP and approval

by PTC 22

nd Feb 2014 IUs/PTC

8. Submission of AWP to WB 25th Feb 2014 PD

Page 18: JPIP Report 5-12-13

18

11. WAY FORWARD, Beatrice Kamau

a) Annual work plan is key tool for planning and implementation of project activities. Implementing

units are required to develop them as per the schedule and shall align them to the project

document as well as the Judiciary Transformation Framework.

b) Improve utilization of project funds by fast tracking implementation of activities and timely

request for approvals

c) During supplementary budget, to review project budget downwards by removing activities which

will not be completed or implemented within the remaining six months

d) To discuss with World Bank, key challenges hindering timely implementation of projects such as

delay in approval of requests and allowances.

e) In order to realize the objectives of the project and achieve the targets implementing units to

develop and submit proposal for approval in time. They will also use available guidelines on the

processing of proposal and requisition of funds to avoid delays and rejections.

f) Implementing Units to adherence to government financial rules and regulations in order to avoid

audit queries. Implementing units to use available guidelines in the processing of funds,

procurement among others.

g) Implementing units to support PMU and IFA in providing information and liaising with them in

developing work plans, budgets and making requests.

h) The M&E to circulate progress reports on status of implementation of the project more especially

activities as well as utilization of funds to all implementing units monthly.

i) Finally all implementing units to remain committed in implementing the project and support IFA

and PMU in order to get value of money from the project.

END

Page 19: JPIP Report 5-12-13

19

ANNEXES

Annex 1. Progress as at September 2013

COMPONENT

PLANNED

ACTIVITI

ES

TAR

Q1

ACHEV

Q1 REMARKS

COURT ADMIN

Technical

Assistance 4 3

Completed with funds from GIZ

TA to develop sensitization

materials on public complaints

procedures not done

T&SD 2 1

Development of transformation

magazine (mageuzi news)

achieved

Holding speaker forums for

Judges of the Supreme Court

and invite speakers to share

their experiences as well as

engage academia on several

issues not done

CASE

MANAGEMENT

Technical

Assistance None NA

Nothing planned to complete in

Q1

T&SD None NA Nothing planned to complete in

Q1

JUDICIARY

TRAINING AND

DEVELOPMENT

Technical

Assistance None NA

Nothing planned to complete in

Q1

T&SD None NA Nothing planned to complete in

Q1

COURT

INFRASTRUCTU

RE

Technical

Assistance None NA

Nothing planned to complete in

Q1

Training &

other

operational

None NA Nothing planned to complete in

Q1

PROJECT

MANAGEMENT

Technical

Assistance 2 2 PMU and IFA established

Training &

other

operational

1 1 1 Training for IUs conducted

Page 20: JPIP Report 5-12-13

20

Annex 2: Planned Activities for Q2-Q4 That Commenced In Q1

COMPONENT PLANNED ACTIVITIES TAR Q2 TAR Q3 TAR

Q4

COURT ADMIN

Technical Assistance 13 10 8

T&SD 2 3 7

CASE MANAGEMENT

Technical Assistance 1 1 1

T&SD 0 0 0

JUDICIARY TRAINING

AND DEVELOPMENT

Technical Assistance 2 0 3

T&SD 0 0 2

COURT INFRASTRUCTURE

Technical Assistance 1 0 4

Training & other operational 0 0 0

PROJECT MANAGEMENT

Technical Assistance 0 0 0

Training & other operational 1 1 1

TOTAL

19 14 26

Page 21: JPIP Report 5-12-13

21

Annex 3: List of Participants

1. CHRISTINE OGARI JTI

2. LUCY NJARAMBA SUPREME COURT

3. JUDY OMANGE HIGH COURT

4. CATHERINE MUGOYA JTI

5. ONESMUS NZOMO JTI

6. JULIE OSEKO JTI

7. JACKSON KARANJA IFA

8. JOHN OKELLO PMU

9. STEPHEN NJEHIA JPIP

10. MBUBA MBUNGU JPIP

11. HELLEN MUSYOKI SUPREME COURT

12. KAKAI KISSINGER SUPREME COURT

13. MARTIN OKWATTA SUPREME COURT

14. GRACE OTERA SUPREME COURT

15. MICHAEL OBUYA IFA

16. LILLY ODUNDO SUPREME COURT

17. ANDREW KIARIE SUPREME COURT

18. ANN ASUGAH SUPREME COURT

19. PETER MULWA SUPREME COURT

20. BETH GITAU PMU

21. ELSIE NJUGUNA NCAJ

22. NEWTON KIPLAGAT JPIP

23. NICHOLAS SIMANI PMU

24. CAROLYN MAKANA COURT OF APPEAL

25. JOSEPH OSEWE PERFOMANCE MANAGEMENT

26. FREDRICK OMBWORI PERFOMANCE MANAGEMENT

27. LUMUMBA VICTOR PERFOMANCE MANAGEMENT

28. KENNEDY MUGONYI PMU

29. EDWIN MURETI JSC

30. ANGELLA MANYALLA SUPREME COURT

31. BEATRICE KAMAU SUPREME COURT