Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
© 2017 Electric Power Research Institute, Inc. All rights reserved.
Industry-NRC Materials Exchange MeetingRockville, MDMay 23, 2017
Joint EPRI MRP/PWR Owners Group Baffle-Former-Bolt Focus Group
Update
2© 2017 Electric Power Research Institute, Inc. All rights reserved.
Westinghouse Baffle-Former Assembly Details
Source: ML15331A179
Baffle
Baffle Plate Edge Bolt (Baffle-to-Baffle Bolts)
Baffle-Former Bolt (Long & Short)
Corner Edge Bracket Baffle to
Former Bolt
Core Barrel to Former Bolt
Core BarrelFormer
Core barrel, baffle and former plates– Type 304 austenitic stainless steel material
Baffle-Former Bolts (BFBs)– Attach the baffle plates to the former plates in
the reactor lower internals assembly– Type 347 or Type 316 cold worked austenitic
stainless steel material– Bolt head designs and shank lengths vary
from plant-to-plant, which can challenge the NDE technique
Source: ML15331A179
3© 2017 Electric Power Research Institute, Inc. All rights reserved.
Westinghouse Coolant Flow Configurations
Source: ML073190376
Large Differential Pressure (∆P) Across the Baffle Plate -> greater BFB bolt loads
May cause baffle jetting
Small Differential Pressure (∆P) across the baffle plate -> lower BFB bolt loads
Alleviates baffle jetting
*Figure shows modifications made for Upflow Conversion
4© 2017 Electric Power Research Institute, Inc. All rights reserved.
Operating Experience Overview
Note: UT deployed as it became available and qualified for the various sites
1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
DC Cook2 finds degraded bolts by visual inspection
First UT baffle-former bolts (BFB) inspections in French
PWR CP0 units and first cracks found
Indian Point 2, Salem 1,
DCCook2 find degraded bolts
(visual+UT)
Ginna performs first MRP-227
inspectionsFirst degraded baffle-former bolts
found in U.S.
WCAP-13266: BFB Program for the
Westinghouse Owners Group - Plant
Categorization
NRC Information Notice 98-11
on BFBs MRP publishes assessment of
French BFB OE (MRP-03)
NRC reviews & approves MRP-227
Westinghouse Technical Bulletin TB-12-5, related to the DC Cook OE
MRP publishes Reactor Internals
Inspection Guidelines (MRP-227)
Operating Experience
Guidance
NSAL-16-1AREVA CSB-16-02
Interim Guidance
Per MRP-227-A, BFB UT exam is performed for WEC plants initially at 25-35EFPY and repeated every 10-yearsNote: UT deployed as it becomes available and qualified for the various sites
5© 2017 Electric Power Research Institute, Inc. All rights reserved.
Joint Owners Baffle Bolt Program (15-22 EFPY) Sponsored Inspections of four plants (1998-2000)
– Ginna: 2-loop, Downflow, Type 347SS (total of 728 BFBs) 9% UT Indications (Of these, 14 were sent for metallurgical examination. Results showed no
indications of cracking, so this 9% likely contains a number of false calls) Partial replacement program (56)
– Point Beach Unit 2: 2-loop, Upflow (converted), Type 347SS (total of 728 BFBs) 8% UT Indications Partial replacement program (175)
– Farley Unit 1: 3-loop, Upflow (converted), Type 316SS (total of 1088 BFBs) No UT Indications Proactive replacement of minimum pattern (276)
– Farley Unit 2: 3-loop, Converted Upflow (downflow at time of inspection), Type 316SS (total of 1088 BFBs) No UT Indications Proactive replacement of minimum pattern (203)
Based on work at the time, inspection results and metallurgical exams of bolts removed during this program led to conclusion that BFB degradation was not a concern for the original plant operating period and that this could be addressed by an aging management program for license renewal (MRP-227-A).
6© 2017 Electric Power Research Institute, Inc. All rights reserved.
Westinghouse NSSS MRP-227-A BFB Inspections2010 through 2016 (excluding IP2, SAL1, DCCook2)
Ginna: 2-Loop, Downflow, 347SS – 2nd Inspection (2011)(partial inspection of 123
original bolts and 56 replacement bolts): one additional UT Indication (Partial Replacement of an additional 25 bolts)
Point Beach Unit 1: 2-Loop, Upflow(converted), 347SS – 1st Inspection (2013): No UT Indications
Point Beach Unit 2: 2-Loop, Upflow(converted), 347SS – 2nd Inspection (2014): 2% Additional UT
Indications Prairie Island 1: 2-Loop, Downflow, 347SS
– 1st Inspection (2014): 6% UT Indications Prairie Island 2: 2-Loop, Downflow, 347SS
– 1st Inspection (2013): 10% UT Indications
2-Loop plants currently have 2 to 10% UT indications
Surry Unit 1: 3-Loop, Downflow, 347SS– 1st Inspection (2010): <1% UT Indications
Surry Unit 2: 3-Loop, Downflow, 347SS– 1st Inspection (2011): <1% UT Indications
Robinson: 3-Loop, Downflow, 347SS– 1st Inspection (2013): <1% UT Indications
Turkey Point 3: 3-Loop,Downflow, 347SS– 1st Inspection (2015 - partial inspection of 305
bolts out of 1088): No UT Indications North Anna 1, 3-loop, Upflow (converted),
316SS– 1st Inspection (2016): <1% UT indications
3-Loop plants currently have <1% UT indications
7© 2017 Electric Power Research Institute, Inc. All rights reserved.
B&W NSSS and International Plant Results Crystal River Unit 3, Type 304SS (2005)
– No relevant UT indications - UT performed due to visual indication from baffle-to-baffle bolts (aka ‘WEC edge-bolts’)
Oconee Unit 1, Type 304SS (2012)– No relevant UT indications - Four BFBs uninspectable due
to large welds on locking bars
Oconee Unit 2, Type 304SS (2013)– No relevant UT indications - One BFB uninspectable due to
UT probe not seating properly
Oconee Unit 3, Type 304SS (2014)– One BFB identified with crack-like indications - One BFB
uninspectable due to UT probe not seating properly
ANO Unit 1, Type 304SS (2016)– No relevant UT indications
Doel 1: 2-Loop Downflow, Type 316SS– 1st Inspection: No relevant UT indications (1991)– 2nd Inspection (2005) and 3rd Inspection (2015): 2% UT
Indications (replaced 9 bolts in 2015) Doel 2: 2-Loop Downflow, Type 316SS
– 1st Inspection (2006) and 2nd Inspection (2015): <1% UT Indications (replaced 7 bolts in 2015)
Krsko: 2-Loop, Downflow (prior to inspection), Type 316SS– 1st Inspection: <1% UT Indications (2013)
Tihange 1: 3-Loop, Upflow (converted), Type 316SS– 960 of 1088 bolts inspected in each of the following inspections– 1st Inspection: 4% UT Indications (1995)– 2nd Inspection: 3% UT Indications (2002)– Most recent Inspection: No relevant UT Indications (5 bolts either
not inspectable or not interpretable) (2014) Ringhals 2: 2-Loop Upflow (converted), Type 316SS
– 1st, 2nd, 3rd exams: <1% UT Ind., (2000, 2008, 2015) Ringhals 3: 3-Loop Downflow, Type 316SS
– 1st and 2nd Inspections: <1% UT Indications/uninspectable (2000 and 2007)
– 3rd Inspection: <1% UT Indications/uninspectable (2016) Ringhals 4: 3-Loop Upflow with cooling holes, Type 316SS
– 1st inspection: <1% UT Ind. (2010, next exam in 2019)
8© 2017 Electric Power Research Institute, Inc. All rights reserved.
Observations from Broader OE Excluding the OE at DC Cook Unit 2, Indian Point Unit 2+3, and Salem Unit 1
(discussed later in the presentation), the following observations can be made based on inspection OE gathered to date from international and domestic plants:– Bolts with UT indications tend to be randomly distributed– Findings are consistent with expectations of IASCC failures and fluence effects near belt-line of
core– Quantity and distribution of bolts with indications are bounded by historical generic safety
assessment generated in mid-1990s (documented in PWROG report WCAP-15328) Future UT inspection findings may be driven by plant-specific parameters
9© 2017 Electric Power Research Institute, Inc. All rights reserved.
DC Cook Unit 2 (10/2010 / 22 EFPY) (4-Loop Downflow) Fuel failure in peripheral assembly from fretting wear at broken bolt head Bolt heads and lock bars found on lower core plate after fuel removal Visual inspections revealed 18 degraded bolts on wide baffle plate
– Additional bolts removed from plate with visual indications to define extent of localized degradation (approx. 40 bolts in single patch)
– Additional test bolts removed from symmetrical locations to evaluate potential for degradation on other plates (all of these test bolts were found to be intact)
No UT inspections performed in 2010 (at that time UT was not qualified or optimized for the Cook 2 bolt design) Degraded and test bolts replaced (total of 52 bolts and 2 empty holes)
– Performed testing on some removed bolts in hot cell in 2011Westinghouse issued Technical Bulletin TB-12-5, dated 3/7/2012
– Failures may have resulted from crack propagation due to combination of IASCC and fatigue
100% Visual VT-3 inspection conducted in 2012 with no indications
10© 2017 Electric Power Research Institute, Inc. All rights reserved.
Indian Point Unit 2 (3/2016 / 31 EFPY) (4-Loop Downflow) Degraded bolts/lock bars noted visually prior to planned MRP-227 100% UT exams Markings on periphery of neighboring fuel assembly identified (no fuel failure) Inspections identified 227 BFB with visual or UT indications (includes 14 uninspectable)
UT indications were clustered– Spanned various quadrants, mostly in upper region of core baffles– Multiple groups of 10+ adjacent failures / At least one cluster of 50+ adjacent failures
Observed failures exceed WCAP-17096-NP-A engineering acceptance criteria Site-specific response was needed
– Performed Acceptable Bolting Pattern Analysis (ABPA) and Replacement Bolting Pattern Analysis– Performed baffle-former bolt removal and replacement (278), including ‘anti-cluster’ bolts– Quarantined and shipped select bolts for testing in hot cell
11© 2017 Electric Power Research Institute, Inc. All rights reserved.
Salem Unit 1 (4/2016 / 28 EFPY) (4-Loop Downflow) Conducted visual exams every other refueling outage in response to DC Cook Unit 2 OE from
2010 and the resulting TB-12-5; MRP-227 UT exams were not originally planned until 2017 Degraded bolts/lock bars noted in visual exams followed by doing 100% UT exams Loose/protruding bolt heads resulted in fuel fretting and one fuel clad failure Inspections identified 182 BFB with visual degradation or UT indications (includes 18 uninspectable) UT indications were clustered
– More concentrated (than Indian Point 2) to a few adjacent octants– Multiple groups of 10+ adjacent failures / At least one cluster of 50+ adjacent failures
Observed failure pattern exceeds WCAP-17096-NP-A engineering acceptance criteria Site-specific response was needed
– Performed Acceptable Bolting Pattern Analysis (ABPA) and Replacement Bolting Pattern Analysis– Performed baffle-former bolt removal and replacement (189)– Quarantined and shipped select bolts for testing in hot cell
12© 2017 Electric Power Research Institute, Inc. All rights reserved.
DC Cook Unit 2 (11/2016 / 28 EFPY) (4-Loop Downflow) Two (2) on-line fuel leaks identified during the last fuel cycle associated with two (2) empty bolt-
holes from bolts that were not replaced in 2010 (suspected damaged by jetting thru vacant hole) Inspections identified 179 BFB with visual degradation or UT indications (includes 9 that were not
inspectable, and three (3) with visibly degraded lock-bar welds)– Includes six (6) replacement BFBs from 2010 event that exhibit UT indications (first-of-a-kind finding)
– Five (5) Baffle-Edge-Bolts on one seam appear visually failed (first-of-a-kind finding)
UT indications were clustered– Spanned various quadrants– Multiple groups of 10+ adjacent failures / At least one cluster of 50+ adjacent failures
Observed failure pattern exceeds WCAP-17096-NP-A engineering acceptance criteria Site-specific response was needed
– Performed Acceptable Bolting Pattern Analysis (ABPA) and Replacement Bolting Pattern Analysis– Performed baffle-former bolt removal and replacement (201)– Quarantined and shipped several bolts for testing in hot cell
13© 2017 Electric Power Research Institute, Inc. All rights reserved.
Indian Point Unit 3 (3/2017 / 28.6 EFPY) (4-Loop Downflow) Inspections identified 259 BFB with UT indications (includes 3 that were not inspectable)
– No visual evidence of missing or protruding BFB heads or lock-bars– No visual evidence of degradation of edge bolts
UT indications were clustered– Spanned various quadrants– Multiple groups of 10+ adjacent failures / At least one cluster of 30+ adjacent failures
Observed indication pattern exceeds WCAP-17096-NP-A engineering acceptance criteria Site-specific response was needed
– Performed Acceptable Bolting Pattern Analysis (ABPA) and Replacement Bolting Pattern Analysis– Performed baffle-former bolt removal and replacement (270)– Quarantined several bolts for potential future testing in hot cell if deemed necessary
14© 2017 Electric Power Research Institute, Inc. All rights reserved.
Salem Unit 2 (4/2017 / 25.4 EFPY) (4-Loop Downflow) Inspections identified 9 BFB with UT indications, all of the BFBs were UT inspectable
No evidence of clustered indications
Observed indication pattern meets existing WCAP-17096-NP-A engineering acceptance criteria
Site-specific response considered pro-active BFB replacements for additional margin– Performed Acceptable Bolting Pattern Analysis (ABPA) and Replacement Bolting Pattern Analysis– Performed baffle-former bolt removal and replacement (129 BFBs)
15© 2017 Electric Power Research Institute, Inc. All rights reserved.
Conclusions from Recent OE These five US plants share a common plant design configuration (4-loop
downflow), bolt design (int.hex+lock bar), and material (347SS) – Tier 1a Assessing impact of new findings from fall 2016 DC Cook 2 exams:
– Replacement 316 CW BFBs (6) from 2010 event with UT indications, were found broken upon removal
– Visually degraded edge bolts (5) on one panel, in the center of a large area/cluster of BFB failures (left in-place; two adjacent fuel assemblies were hardened with solid stainless pins)
Bolts with visual and/or UT indications tend to be ‘clustered’ together Distributions seem to indicate the presence of a mechanism causing adjacent
bolts to become more susceptible to failure (i.e., ‘unzippering’) The latest inspection results from Spring 2017 are still being evaluated
16© 2017 Electric Power Research Institute, Inc. All rights reserved.
NDE (UT and visual) exams are finding defective bolts
Bolt removal findings validate significant quantities of broken bolts and loose bolts (based on torque wrench)
BFB Exam/Removal Experiences from Recent Outages
17© 2017 Electric Power Research Institute, Inc. All rights reserved.
Industry BFB FG Immediate Actions Completed
Supported presentation to NSIAC on 5/23/2016– Westinghouse Technical Bulletin TB-12-5 remains validProvided Industry Alert Letter from the PMMP Chairman to PWR site
VPs on 6/1/2016 (MRP-2016-014)– NEI 03-08 Interim Guidance will require the 4-loop plants identified in the Westinghouse TB-
12-5 bulletin to perform UT inspections of all the BFBs or replace an acceptable pattern of bolts at their next outage.
– Consideration should also be given to proceeding with procurement of replacement bolts prior to issuance of interim guidance due to potentially long manufacturing lead times.
Westinghouse NSAL 16-1 issued 07/05/16 and revised 08/01/16AREVA Customer Service Bulletin issued 07/14/16 Industry technical exchange meeting with NRC staff 7/19/2016Supported ACRS metallurgy subcommittee meeting 11/16/2016
18© 2017 Electric Power Research Institute, Inc. All rights reserved.
Intermediate Term Industry BFB FG Actions Completed
Issued NEI 03-08 “Needed” Interim Guidance regarding BFB exams as identified in Westinghouse NSAL 16-1– Tier 1 plants provided interim guidance in MRP-2016-021, dated 7/25/2016 – Remaining plants provided interim guidance in MRP-2017-009, dated 3/15/2017– Industry team reviewed interim guidance with NRC in public meeting on 4/12/2017– Additional technical discussions with NRC staff are tentatively planned for summer 2017
Assessed 2017 and 2018 outage seasons for developing contingency plans for tooling and BFB material needs– Spring 2017: 3 UT inspections (Tier 1a plants) and 1 VT-3 inspection (Tier 1b plant)– Fall 2017: 2 planned UT inspections (Tier 1a plants), one which is a re-examination – CY2018: 5 planned UT inspections (1 Tier 1a plant, 2 Tier 1b plants and 2 Tier 2b plant)
Performing Hot Cell Post Irradiation Examinations of BFBs– Microscopic examinations and mechanical tests nearing completion
19© 2017 Electric Power Research Institute, Inc. All rights reserved.
Objectives of Hot Cell Testing
What is the material condition of the bolt?• Chemical composition• Radionuclide analysis
What was the condition of the bolt at the onset of failure?• Tensile testing of machined specimens• Whole bolt pull testing
Which mechanisms contributed to the failure of the bolts?• Optical and scanning electron
microscopy
What is the correlation between material condition and failure process?• Cross-sectional metallography
Metallurgical testing was conducted on bolts from Indian Point 2 and Salem 1 to answer the following questions:
20© 2017 Electric Power Research Institute, Inc. All rights reserved.
Summary of BFB Hot Cell Testing ResultsMechanical / Chemical Properties
Chemical compositions of the bolts are consistent with the CMTRs for the 347SS heats Measured values of dose (dpa) are
consistent with the calculated values and are in the range of 12 to 25 dpa(underside of the bolt heads) Yield stress, ultimate tensile stress,
and ductility for whole BFBs and also tensile specimens machined from bolts are consistent with MRP-211 data for irradiated Type 347 SS
Fractography Characteristics
Initiation is always by intergranular cracking - typical of IASCC Fracture surfaces can contain regions
of IG-SCC, TG-SCC, Fatigue, and Ductile Overload – Extent of IG cracking found to vary from 4% to
66%– Extent of cracking mechanisms varies bolt-to-bolt– No obvious correlation of extent of each cracking
mode with bolt location or expected dose. IASCC observed on anti-cluster bolts
that were removed and found to be in 2 pieces
21© 2017 Electric Power Research Institute, Inc. All rights reserved.
BFB Metallurgical Testing Findings - Examples Exams of 347SS BFB fracture surfaces have found IASCC and fatigue:
(bolt identified as rejectable by UT exam)
22© 2017 Electric Power Research Institute, Inc. All rights reserved.
BFB Metallurgical Testing Findings - Examples Exams of 347SS BFB fracture surfaces have found IASCC and fatigue:
(bolt identified as rejectable by UT exam)
23© 2017 Electric Power Research Institute, Inc. All rights reserved.
BFB Hot Cell Testing – Crack Initiation Type 347SS BFB fracture surface
following pull testing (red, intact bolt) IASCC region is ~10% sectional area
which is consistent with the as-found UT signal indications from multiple channels
24© 2017 Electric Power Research Institute, Inc. All rights reserved.
BFB Hot Cell Testing – Crack Propagation
IASCC• IASCC was seen on the
fracture surface of bolts that were removed in two pieces
• IASCC was also seen on the fracture surface of an IP “anti-cluster” green bolt
• In some cases, IASCC is only a few grains deep
Transgranular Cracking• TG and mixed-mode
cracking is apparent on many fracture surfaces
Fatigue• In some regions, fatigue
striations can be seen; although, the striations may be attributed to transgranular stress corrosion cracking
Ductile Overload• The fracture of the
remaining ligament shows retained ductility on most bolts consistent with tensile/pull test results
25© 2017 Electric Power Research Institute, Inc. All rights reserved.
BFB Hot Cell Testing – Cross-section Metallography
Flowlines found in head-to-shank radius, along with aligned precipitationNo other microstructural features identified that might potentially lead
to invalid UT results (e.g., large inclusion or precipitates)
26© 2017 Electric Power Research Institute, Inc. All rights reserved.
BFB Hot Cell Testing Summary
Hot cell results are consistent with prior findings from 1990s– Hot cell work has not identified a different crack initiation or crack
growth mechanism than predicted or previously seen– Defective or incorrect materials have not been observed for these
BFBs– Intact bolts with UT indications have maintained their load-carrying
capabilities– Metallography results have not identified significant microstructural
features that contributed to UT results
27© 2017 Electric Power Research Institute, Inc. All rights reserved.
Inspection Tasks - Steps to Address NDE QuestionsModeling of BFB UT Techniques during Summer 2017– Enhancements to UT techniques have been made to improve reliability– Currently investigating geometric effects and beam mode conversion at
head-to-shank radius of internal hex bolts– Considering investigating impacts of variations in UT probe contact
surfaces from plant-to-plant– Considering investigating possibility of UT beam redirection due to flow
lines in microstructureConsider enhancements to BFB UT exam protocol for 2018
– Revising procedure qualification to require 90% probability of detection (POD)
– Enhance UT inspection personnel qualification for detecting flaws of various sizes and orientations
28© 2017 Electric Power Research Institute, Inc. All rights reserved.
Industry Focus Group Assessment of NDE Technique
The internal-hex head geometries are known to be the most challenging to examine due to the presence of lock-bars and weldsUT methods were qualified and demonstrated to find a range
of cracks in qualification bolts under conditions simulating field exams– Uses underwater remote control delivery systems in irradiation field– Applicable to multiple head geometries but requires different probe
headsNDE experts are working to enhance UT methods
29© 2017 Electric Power Research Institute, Inc. All rights reserved.
Together…Shaping the Future of Electricity