14
· .. ·...• > .··.

publications.iowa.govpublications.iowa.gov/16409/1/IADOT_hr215_Improv_Long_Jnts_Asp… · joint as presently described in the construction manual. Section 2A, stations 183+14 to 7+95

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: publications.iowa.govpublications.iowa.gov/16409/1/IADOT_hr215_Improv_Long_Jnts_Asp… · joint as presently described in the construction manual. Section 2A, stations 183+14 to 7+95

· .. ·...• > .· .··.

Page 2: publications.iowa.govpublications.iowa.gov/16409/1/IADOT_hr215_Improv_Long_Jnts_Asp… · joint as presently described in the construction manual. Section 2A, stations 183+14 to 7+95

Improvement of Longitudinal Joints in

Asphalt Pavement

Final Report

Iowa Highway Research Board Project HR-215

By

Richard D. Smith Research Technician Office of Materials

515-239-1392

January 1987

Disclaimer

The contents of this report reflect the views of the author and do not necessarily reflect the official views or policy of the Iowa Department 6f Transportation. This report does not constitute a standard, specification or regulation.

Page 3: publications.iowa.govpublications.iowa.gov/16409/1/IADOT_hr215_Improv_Long_Jnts_Asp… · joint as presently described in the construction manual. Section 2A, stations 183+14 to 7+95

Introduction.

Location .....

Construction.

Evaluation ..

Conclusions .•...

Acknowledgement.

Table of Contents

Page

1

1

1

4

7

9

Appendix A. . . . . . . . . . . . • . . . . . . • . . . . . . . . . . . . . . . . . . . . . . • • . . . • 10

Page 4: publications.iowa.govpublications.iowa.gov/16409/1/IADOT_hr215_Improv_Long_Jnts_Asp… · joint as presently described in the construction manual. Section 2A, stations 183+14 to 7+95

Introduction

PAGE l

Improvement of Longitudinal Joints

in Asphalt Pavement

One significant benefit of asphalt concrete pavement construction

is that it may be opened to traffic within one hour after being

placed. Therefore, road closure and detour are not normally neces­

sary, but only temporary lane closure and control of traffic.

This one lane construction, even though desirable in regard to

maintaining traffic flow, does pose an additional problem. The longi­

tudinal joint at centerline often becomes a maintenance problem.

The objective of this research project is to identify construction

procedures that will provide an improved centerline joint.

Location

The research was incorporated by extra work order into project

FR-44-4(26)--2G-39. This was a widening and asphaltic concrete resur­

facing project on Iowa 44 in Guthrie and Dallas Counties, Figure 1.

The resea.rch sections total approximately 8. 7 miles between stations

156+14 in Guthrie County and 451+00 in Dallas County.

Construction

The experimental sections were constructed between July 23 and Au­

gust 12, 1980.

The paver was a Blaw-Knox PF-500, the breakdown roller was a

Ray-Go Vibratory, the pneumatic tired roller was a Michigan

Page 5: publications.iowa.govpublications.iowa.gov/16409/1/IADOT_hr215_Improv_Long_Jnts_Asp… · joint as presently described in the construction manual. Section 2A, stations 183+14 to 7+95

PAGE 2

Model RW 181 with a tire pressure of 120 psi, and the finish roller

was a Huber Model T-1014H.

Th~re were eight construction procedures used with two sections (A

and B) for each procedure.

Section lA, stations 156+14 to 183+14 and section lB, stations

206+40 to 232+40 were placed with a one inch overlap at the centerline

joint as presently described in the construction manual.

Section 2A, stations 183+14 to 7+95 and section 2B, stations

232+40 to 258+40 required a double tack coat on the VE,rtical face of

the previously placed pass. The first shot of tack was at the end of

the day the first pass was placed and the second shot was the morning

that the joint was closed.

Section 3A, stations 7+95 to 32+95 and section 3B, stations 258+40

to 284+40 were placed without a horizontal offset between layers; the

centerline joint for the two layers being vertical.

Section 4A, stations 76+40 to 102+40 and section 4B, stations

317+00 to 344+00 were placed with the 1:1 edge slope shoe removed from

the paver. This was done only on the surface course.

Section SA, stations 102+40 to 128+40 and section SB, stations

344+00 to 372+00 were placed and compacted using a revised rolling

procedure. The revised procedure used on the second lane placed was

to roll within four inches of the longitudinal joint on the breakdown

pass and to overlap on the second pass rather than overlapping on the

first pass as is currently specified.

Section fiA, stations 128+40 to 154+40 and section 6B, stations

372+00 to 398+00 called for trimming 1 1/2 inches from the centerline

edge of the first lane placed just before the edge was tacked for the

Page 6: publications.iowa.govpublications.iowa.gov/16409/1/IADOT_hr215_Improv_Long_Jnts_Asp… · joint as presently described in the construction manual. Section 2A, stations 183+14 to 7+95

. 24·.o·· E3 Exisri"9 • 'lJ>riff ~ 12'-0" { 12'-0" Vari .. -+Exi<ting E~rth Sh~I- I ! 3·po·· -- .. sl~ •@ _,...... --·Slope©~ --- i Iii J'~O ... ' l Earth Shov!.ier

Granular Mate<ial . ! Gron.olor Moteriol I --- ----- --------- ~ au,h'.~.'"'"'~~uide~

: ORIGINAL . PAVEMENT 1 US/~' re.-7C.t:_,:::;.~~~f;

,•

DESIGN QUANTITIES

ITEM RATE

140 !1>1./<u. h. 140 Jtn./q1. ft.

!l"•t Stci1ion!

VOLUME

Swtlo(.e Cov••• 8.irui •• co ... no Tod• Coot 0 05 901./•4- ytl.

7; 11 To .. , 2..1.33 To"• 27.00 Gel.(!)

G'"""lor Motottcl ------f 1.00 To•• ~

© lsri•eted let 2 epplicotio..,s.

\%! (tf;•oled f.,. 1 st>o.,.lc:loo:

t I 4>!6:" "3~A.~.C _;}c':"-C . . I .~ CU;>:;~ I

LJI 19;"'TYPE-"B" ASPHALT CEMENT·c-6N-CRETE SURFACE couRSE i I - - . TYPE "8" ASPHALT CEMEN-T -1 lV2" ( Averoge Thickness} _CONCRETE .BINDER COURSE :

TYPICAL CROSS SECTION ASPHALT CEMENT CONCRETE RESURFACING

ROAD IDENT. STATION TO STATION

la. M :'.!• i'5. :>:) 5-R• %. IX! la. M 76+00.00 1;; .. 52_~5

Ii. U 11i; ... 12_ 1s 2:Q.o. 19. ))

ta. 44 •JQuation: Sta. 2CQ'tl9.CO-Sta. 0-Xl. J

tz. 41 o-oo. ro .&'>'.rll la. M" 5A+r:1 ron ~~22.Xl

Ii .. 44 >I0-~.00 6i3•.'.:f.:.O

@ F-.,.,.J>.,d •lop• 1hcJJ .. c;a~ ,.,.,, .... .,; ,_.,~,,. .. -••t•P' tftot tl•o "'0'-''"'" .. o'·~..,.;~:." ;P" ) 0 ... , Cftd .;.,, • ..,,.. o·'<>wO':>· .. < :>" ! .s~.

S•cloo,. •OV b.- "'od;;.,,g OU :' •fl<H

•,.ff,,.••~ 1iuou!itj, 0~•1n ol <!)•'·": >'>C.C .. q

t .. !~. lo IObvl<l~lfd !;S!'"il C' ·~--~

(<J<v•• ond Ston<'I -.,__ i!oocl i>!o1" 0QQ,11onol re<:,,;_..., • .,,1 .,.,.,,.g.., '"Olf•lfllf<tOle" ;.,, .. .,,

Figure 1: Project FR-44-4(26)--2G-39 Guthrie County "Cl

e; ,.,, w

Page 7: publications.iowa.govpublications.iowa.gov/16409/1/IADOT_hr215_Improv_Long_Jnts_Asp… · joint as presently described in the construction manual. Section 2A, stations 183+14 to 7+95

PAGE 4

second pass. The method of trimming was not specified but it was as­

sumed it would be by sawing or using a rolling Colter. Neither method

was used. An attempt was made to do the trimming with a motor patrol

blade but a straight edge could not be obtained. The edge of the

bucket on a skid-type loader was sharpened and used to trim the edge.

Immediately following the trimming, the mat was rolled to assure bond

with the underlying layer. The edge was tack coated the same day a.nd

again prior to closing the longitudinal joint.

Section 7A, stations 1S4+40 to 180+40 and section 7B, stations

398+00 to 424+00 again had the centerline edge trimmed as in sections

6A and 6B but with the revised rolling pattern used in sections SA and

SB, that is lapping over the longitudinal joint on the second roller

pass instead of the first.

Section 8A, stations 180+40 to 206+40 and 8B, stations 424+00 to

4.51+00 had the longitudinal joint sealed by the pneumatic tired roller

on the final pass.

The project was paved from east to west and the joint was normally

closed from the south side.

Evaluation

Cores were drilled from each section August lS, 1980, about three

inches left and right of the longitudinal joint and from the quarter­

point of each lane. The densities of each core and the average for

each location per longitudinal joint procedure are included in

Table 1.

Page 8: publications.iowa.govpublications.iowa.gov/16409/1/IADOT_hr215_Improv_Long_Jnts_Asp… · joint as presently described in the construction manual. Section 2A, stations 183+14 to 7+95

PAGE 5

TABLE I

HR-215

IMPROVEMENT OF LONGITUDINAL JOINTS IN ASPHALT PAVEMENT

Section Sta. Density S-15-SO Procedure No. .. pt. CL CL .. pt •

Rt. Rt. Lt. Lt.

lA 170 2.24 2.25 2.23 2.30 Present lB 220 2.35 2.24 2.35 2.35 construction 1 AV 2.30 2.25 2.29 2 .. 33 procedure - 1" overlap

2A 195 2. 29 2.24 2.12 2.2S Tack coat 2B 245 2.34 2.21 2.20 2.29 vertical face 2 AV 2.32 2.23 2.16 2.29 between passes

3A 20 2.30 2.14 2.21 2.31 Delete 3B 270 2.27 2.25 2.17 2.32 transverse 3 AV 2.29 2.20 2.19 2.32 offsets

4A 90 2.36 2.27 2.31 2.29 Delete 1:1 4B 330 2.33 2.33 2. 30 2.32 slope shoe 4 AV 2.35 2. 30 2.31 2.31 on edge

5A 115 2.34 2. 23 2.lS 2.37 Roll within 4" of CL SB 360 2.33 2.25 2. 19 2.31 on breakdown, overlap 5 AV 2.34 2.24 2.19 2.34 CL on 2nd pass

6A 140 2.36 2.26 2.27 2.33 Trim 1st pass ±_ll:i" 6B 3S5 2.32 2.24 2.26 2.33 before 2nd pass tack. 6 AV 2.34 2.25 2.27 2.33 Standard roll pattern.

Surface course only. 7A 165 2.3S 2.29 2.2s 2.31 7B 410 2.32 2.23 2.26 2.33 Same trim as 6, rolling 7 AV 2.35 2.26 2.27 2.32 procedure as 5.

SA 195 2.32 2.25 2.25 2.29 Use pneumatic roller SB 440 2.35 2.26 2. 29 2.35 on joint on final pass. s AV 2.34 2.26 2.27 2.32

Page 9: publications.iowa.govpublications.iowa.gov/16409/1/IADOT_hr215_Improv_Long_Jnts_Asp… · joint as presently described in the construction manual. Section 2A, stations 183+14 to 7+95

PAGE 6

The core densities show that densities at centerline are less than

those at the quarter points. This difference in density could be

eliminated by using a full width paver which would require closing the

road.

Visual inspections were made the first three years after con­

struction. At four, five, and six years, measurement of centerline

cracking was done with the roadmeter car using the distance counters.

One counter was used for cracked areas and the other counter for areas

not cracked. The total of the two counters was the denominator when

determining the percentage of centerline cracking for each section.

The totals for corresponding sections were added to determine percent­

ages for each procedure.

The only procedure to rank the same when comparing cracking and

density is No. 4 (delete the 1:1 slope shoe on the edge). This proce­

dure had the highest average density and also had the least cracking

through 1985. The other sections did not correlate well when compar­

ing density to cracking.

All but procedures 1, 2, and 3 had cracked 100% of their length by

November 1986, and they were cracked 96.1%,. 92.7%, and 92.5% respec­

tively. Each of those procedures had one section that was 100%

cracked. The percentage of cracking by section and year is listed in

Table II along with the densities near the centerline that were deter­

mined after construction in 1980. After 1984, all procedures exhib­

ited a very steep slope in the rate of cracking (Figure 2).

Page 10: publications.iowa.govpublications.iowa.gov/16409/1/IADOT_hr215_Improv_Long_Jnts_Asp… · joint as presently described in the construction manual. Section 2A, stations 183+14 to 7+95

PAGE 7

TABLE II TABULATION OF CRACKING AND CENTERLINE DENSITY

% Cracked CL Density Section 1984 1985 1986 Rt Lt

lA 56.9 87.1 92.0 2.25 2.23 B 3.0 24.7 100.0 2.24 2.35

A+B 27.3 55.5 96.1 2.25 2.29

2A 25.7 61. 8 85.8 2.24 2.12 B 24.0 48.l 100.0 2.21 2.20

A+B 24.9 55.2 92.7 2.23 2.16

3A 1 7. 1 35.5 84.4 2.14 2.21 B 13.5 68.6 100.0 2.25 2.17

A+B 15.2 52.8 92.5 2.20 2.19

4A 4 . 4 24.9 100.0 2.27 2.31 B 19.0 73.0 100.0 2.33 2.30

A+B 9.0 40.2 100.0 2.30 2.31

SA 7.6 58.7 100.0 2.23 2.18 B 58.3 89.7 100.0 2.25 2.19

A+B 33.8 74.7 100.0 2.24 2.19

6A 13.4 47.9 100.0 2.26 2.27 ~ " ~ nc c 'nn n " OA " oc D <:t .l. " I OJ.J ..LVV,. V .£. • .£. "t .:::. • .£. u

A+B 23.8 66.3 100.0 2.25 2.27

7A 1. 0 22.1 100.0 2.29 2.28 B 64.3 92.9 100.0 2.23 2.26

A+B 32.7 57.6 100.0 2.26 2.27

BA 18.5 68.0 100.0 2.25 2.25 B 12.4 52.2 100.0 2.26 2.29

A+B 15.4 59.9 100.0 2.26 2.27

Conclusions

None of the procedures used on this project succeeded in prevent-

ing a longitudinal crack along centerline.

The method providing the best performance for four years after

construction was removal of the 1:1 slope shoe from the paver when

placing the surface course. This method had 9.0% cracked after four

years and 100% cracked after six years of service.

Page 11: publications.iowa.govpublications.iowa.gov/16409/1/IADOT_hr215_Improv_Long_Jnts_Asp… · joint as presently described in the construction manual. Section 2A, stations 183+14 to 7+95

I

. I 1

I

PAGE 8

1 oo 1-" ·· :··1T:--i-:·:- , .. ,.-, l' ,., .. , , 11i 1 .... 1nr11.r-:-r·

--..,----:-

I :

z 0

~ " ' 0' CL I~

" ' 0' u; z ' w; 0 N f-w 0

" w

" < " I

" < I " u (.~ z

z" "w B"

'O Q)

-"' u

"' s.. u

t-o ~ ~ -Dx

o~

" 0 • M

d z

! l··

90

80

70

I I

! I I

, I . -:~~! . ! ..... 1 _1 __ ,_

Procedure

! i

' I

I

l Present construction proccdui:e - l" overl,1p

2 Tuck coat VerL:.ical fucc bct\.Jeen passes

3

4

5

6

De lr,~ te transverse:! offsets

Delete l: l slope shoe on edge

Roll within I\" of CL on breakdown, ovcr~ap CL on 2nd pass

Trim lst pass +1~·· before 2nd pasi tack. Standard roll pattern. Surface course only.

I' I I ' ' ! I I ' ! I I ,_;_,_ f 1 j·' I i i

~ ·1 i 111 i ·-

1

,-1

1

-! r n !-1 1.

, I ,. , I : ! II_ .··1 .. - ·_1 j 1· i : : I

' • • 1- • ' I ' '·i-l. ' ( .. 1 I ! I ·' ' ' I :··!·''["I' J,;,' ' I '

I (' ! I ' ' ~ '

... --1 +-1 : !

I! .. _,. l ' '

' I I I ' . I . i -!+ 1' : ! : : ~: ! : I I I '_ · ·

I i ' ' I ' : : ' ' ! i : : , !_ j ·: : I , , '< ' ' •• : l. . ,- ' ' ' ' l··

·-'-4--1-H·-.' I -t· I .' : ' ': ' ' I : I .. ' I,·· r-.... ~. ,, . 1·· 'I I • : I : ' ., .. , .. , .... +L, ;

·''"'t

L

.i -l" .

I

. : '. I I i : ·i : j ,1

: ! I ~~~-; ... ,- ! I I · i I ! ' I ··I 1 \ I I·!.' I

I : ·'!' t·!"' ·11. ' ' I ' ' ,1 ' .. ' •• ·I .. I ' ,, I I i ' ' i I

I ! . , I ··1- ~ ... .;.J~ .

i i I I '

r I J ·' 1 ) ! I . ' .

.. ,.,·"f rt:;·:~;-1,-1 , '·' , I

• I I I ' I I '+-·-·· ···i J,,j_·_j :

i· 1· .. ~--i·-·'.· ·l·-i .. l i i ! j'

7 Sarne trir;o us 6, :col. ling procedure as 5.

, 1 · ·. , . ! 1 ' • t .• !··· I r ' 1 :

' I ' : i F r-r r--f-1~-L-L ... .J .. I.

[I' 40 :-. ' 1--!

I ··' : I I I

8 use pneumatic roller on joint on final pass.

! ' .. ; ·t· -~ -·1 ; ::··!..~!- 1 . : : .:-·r:·-r .. :··-! I I 1 I , i I I ! ' ; i I i : : i

-I 11 i 1·1·1: I: 1., f-J+·1·1 ··· . 301-l-h-- ·;-,--·-t-··-,--i-c- ·t--~.,. ..

· !+jl 1· j· · · I 1 1 ,. r, · • ; ·1 1 ' .. +l··r ... I ' ' ' '·1 ' . I t ' ' I ' I ' • I ·:1:.l"·t.-t· .. :~:·· r-r r:. -~-1-~-1 .. :. ··!-·.: ··::.t·r.:r .,L,_, -I '-~IT··~- ·'- -i---1-r I

,J'' ij, i ! I I !Jr1 ll1j ' .. , ; ; !.·--1 .. : :.-.! ! T i .· r .. : . T~--i

' 'l..I I : ! I I : i ' ·.····' !·I _:._f_i ... .j.:._ t .,;-~-L·t· --··1~ t--J-...;_. -

' 1·· ii ! I : ! l ' 1· ! I i +-··• : ! j ·i ; 1··j I' t I I I I I 1 ... , ; !

. ; __ ,,; (. !-- ·•··t· l·-·i .j I

lo ll". I I --T7 T''. ·-, ' ·Q;D, , .. ' ' 1·' ! 1 ·1··l·1 l#I

'I'· 1.1?17\)

'80

I i ' 1 ·. :: ; I 1'· . I 1 ·i· i i ·: . J !-;--l--f)- '

·1 : ·! l : I: i I ! , I -:-!--:-- ·~""""t-~·-;·

Figure 2: Rate ...........

"" .. 1

"\ "1 I

I

··r-·;

fTTTI -

111 I i , I

I

.J.

-T;2'·-2

I"?.,--I

i I

i l ·:-+1

i I I I . i­i

I ! ! ! I • ' I

. · __ L~: .. h-r : .LI

i i

' I I

;·:J_, \ I·' j

: : I ;··· .:j.'.J . , I

I ... _)., .

l ' i ' i I I

I I

. ;_;J . . , I , : r ; I

·i_J~.: I I ) ' I .. , ' I : , I . ~ . ~ ' ! I I

.j .. ,_f - +1 ; ' I ,.j·

--~.-I i : -J

:··r ! !· ! I ·]·

' :.I : I ' i

I

T I

'86

!--i ~L '. .1 i t ! i , ' . I

1--}+"1

I •1' ' '

' ' ' .

: i I ... ,, ..... ,11..I ' I I i I i 1; :tJ ' I ' !'' I ; r·++.:....1

I : ·: .. r 1 1 ' ; , .. ,,.:_I

I I '. ! .l I I

I i :-:Ill, I ! ..

i ... i·-·-~·i.......!......'.-.j

I I ; L I . , ... I J .. _

:.) .. !.I I -1 I

.... i I '

: I ; ·l·1 1' ,,_.J_J__

Page 12: publications.iowa.govpublications.iowa.gov/16409/1/IADOT_hr215_Improv_Long_Jnts_Asp… · joint as presently described in the construction manual. Section 2A, stations 183+14 to 7+95

PAGE 9

The areas placed with a one inch overlap as presently described in

the construction manual had 27.3% of the joint cracked after four

years and 96.1% cracked after six years of service.

Between four and six years of service the rate of cracking for all

methods used on this project was about the same. Overall, there was

no one method that out performed the others in this project.

Acknowledgement

The cooperation of the contractor, Henningsen Construction Com­

pany, is appreciated, as is the help of personnel from the Creston

Construction Office, especially Larry Delaney, Project Supervisor for

his help in supplying construction information included in this re­

port.

Page 13: publications.iowa.govpublications.iowa.gov/16409/1/IADOT_hr215_Improv_Long_Jnts_Asp… · joint as presently described in the construction manual. Section 2A, stations 183+14 to 7+95

Appendix A Paae 10

IOWA OEPARTMEIH OF TRANSPORTATION HIGHWAY DIVISION

2/10/86 CONSTRUCTION MANUAL

8.43 GUIDELINE STRINGS AND EDGE ALIGNMENT

True edge alignment controls the correct lap at the longitudinal joint. If there is no lap, the joint will lack density and raveling 1·1ill occur. An excessive lap produces an objectionable wide scab of mixture on the surface next to the joint, that has to be removed with hand tools to obtain an acceptable appearance.

An intended lap of one inch-with a variance of one-half i.nch each way has been observed to produce correct longitudinal joint construction with minimum effort. If these close variances are to be maintained, the adjacent lane has to be constructed with true edge alignment. . . .

One Df the inspector's duties in obtaining true edge alignment is to make frequent measurements to insure that the guideline string has been correctly set and maintained. The nails used to secure the guideline string shall be at intervals close enough to eliminate chords on curves and other irregularities caused by wind, etc.

Guideline strings placed on all two-lane pavements except old concrete should be located by measuring from redhead nails which have been placed on the centerline by instrume~t parties. The spreading of the lower layer will cover the redheads. For succ"eeding layers, the guidei ine string should therefore be located by measuring from the exposed nails that were used to hold the string for the lower layers.

When resurfacing old concrete pavements that are only t.wo lanes in width, the contractors-have been permitted to locate the guideline strings on the shoulders along the outer edges. This is done by measuring out from one of the pavement edges at intervals of approximately 500 feet, then tightening the string and using intermediate nails to secure the string. To insure that parallel alignment is used for the adjacent lane, the guideline string for that lane shall be located by measuring across the pavement from the nails used to secure the first line. To prepare a smooth location on the shoulder for the guideline string, the specifications require that the grass shall be closely mowed for a width of approximately 18 inches.

On curves for all surfaces, a sufficient number of nails shall be used to permit the finishing machine to follow the line exactly without producing objectionable chords on the curved edge alignment.

The finishing machine operator shall follow the guiclel ine string exactly. If the machine (JOes off the line for any rt'i1Son, it c,hoJll lw ildj11stcd bad onto the line immediately. It is incorrect to smooth ouL the edge align111ent ily coming back onto the line gradually. This results in long stretches where incorrect lap at the longitudinal joint will occur. Also when batch trucks bump the finishing machines off the line on curves, the movement is usually down the slope of the curve. If the machine is brought back on the line gradually, an objectionable, long, straight chord will result in what is supposed to be the curved edge alignment.

8-25

Page 14: publications.iowa.govpublications.iowa.gov/16409/1/IADOT_hr215_Improv_Long_Jnts_Asp… · joint as presently described in the construction manual. Section 2A, stations 183+14 to 7+95

IOWA DEPARTMENT OF TRANSPORTATION HIGHWAY DIVISION

Paae 11

2/10/86 CONSTRUCTION t'ANUAL n. '14

.

When automatic screed controls are used, the short joint matching shoe shall not be permitted except when placing a single lift only, with a tl1ickness nf ll .inches or less, or for placement- in conjunction with heater scarification work: When the lower layers are constructed, the specified 30 foot ski device shall be used for joint matching on each layer.

The short joint matching shoes produce joints with smoother appearances than the 30 foot ski devices. Hewever, they do not contribute toward construction of a smoother riding surface. The 30 foot ski device does.

,_Smo,oth l ongi tu di na l joints are very important for surface l aye1's and the short joint matching shoes may be used when surface layers are spread.

Careful adherence to the inspection procedures described in Section 8.43 will insure true edge alignment which is essential for the correct construction of longitudinal joints .

8.45 PRIME AND TACK COATS USING EMULSIONS

P" , General lack coats using emulsions are required prior to October 1. Dilution of emulsion is required i( non-uniform tack applications are experienced. SS-1, SS-lH, CSS-1, and CSS-lH. grades are specified.

8. For Dilution Dilute at 1:1 ratio, i.e., 1 gallon emulsion to 1 gallon water.

C. Application Rate Double the usual specification rates of application normally used for RC-70 or MC-70. Ex., 0.03 to 0.05 Gal./S.Y. increased to 0.06 to 0.10 Gal./S.Y. dilute emulsion.

D. Sample for Com~liance Sample the emu sion at the spray bar of the distributor with the bar valve in a circulating position.

E. 0easurement for Pay 1'11e"net gallons of undiluted emulsion.

Note: Undiluted emulsion must contain a minimum of 57% asphalt residue. Diluted emulsion must therefore contain a minimum of 28.5% residue.

F Settlement of Diluted Emulsions ASs.urance sample reports received on a number of projects indicate tha-'t dilute emulsions are not meeting the minimum residue requirements. A review of this problem with producers in the state indicates that the dilution rate is being carefully controlled and that the residue of the original emulsion is higher than the minimum required.

8-27