Upload
lekiet
View
220
Download
7
Embed Size (px)
Citation preview
John Hart Generating Station
Replacement Project
November 2016
Community Construction Update
Report #41
Prepared by: Stephen Watson, BC Hydro
(O) 250-755-4795 or (C) 250-616-9888
Twitter: @Puntledge Email: [email protected]
• Work is underway to remove some of the
rock beneath the dam to prepare for the
installation of the intake gates. Primary
concrete work for those gates is
complete;
• Excavation of the power tunnel has
officially passed the halfway point, with
over 820 metres of the 1,575 metre
tunnel complete;
• The permanent crane for the powerhouse
is being installed. This crane will replace
the two temporary cranes that have been
used in the powerhouse;
• Tailrace tunnel: Roughly 40-45% of the
tunnel is now complete; and
• Installation of gate guides at the tailrace
outlet is underway.
Project Status
• December: Permanent
powerhouse crane
commissioned and ready to
support installations;
• January: Installation of Intake
Maintenance Gates complete;
• February: Excavation under the
existing John Hart dam
complete;
• March: Construction of lower
elbow connecting power tunnel
shaft to the power tunnel begins;
and
• April: Completion of tailrace
tunnel.
Project Schedule
Record storms hit the Campbell River watershed with
high downstream flood risk management flows. See
slides 16 and 17.
Construction Pictures – John Hart Dam Area
4
Construction Pictures – John Hart Dam Area
5
Nov 23
Construction Pictures – Water Intake
Maintenance Gate Area
6
Upstream of John Hart dam.
The placement of concrete for the water intake
maintenance gates. The below picture provides a more
vertical view, with the bottom left picture showing the view
from the bottom looking up, and the top left picture shows
the top of the works.
Construction Pictures – Downstream Work
Area Below John Hart Dam Area
7
Excavation
of rock for
the water
release
works for
flows down
Elk Falls
Canyon.
Construction Pictures – Downstream Work
Area Below John Hart Dam Area
8
Nov 3
Construction Pictures – Power Tunnel
9
Ventilation piping is also shown.
Construction Pictures – Powerhouse Cavern
10
6,400 cubic metres of concrete, or enough to fill
about 2.5 Olympic-sized swimming pools, has been
placed in the powerhouse to date.
Construction Pictures – Powerhouse Cavern
11
Construction Pictures – Powerhouse Cavern
12
Construction Pictures – Powerhouse Cavern
13
Construction Pictures – Powerhouse Cavern
14
Shows some of the generator housings with Generator #3 in the distance beside
the east wall of the powerhouse cavern.
Construction Pictures – Gate Gallery and
Surge Chamber
15
Shows the work advancements in the
gate gallery (above) and in the surge
chamber (left).
Construction Pictures – Tailrace Outlet
16
Shows the concrete placements and the gate
guides (right) for the new gates to be installed.
With very high river levels, a short concrete wall
was constructed (shown below) to prevent any
flooding into the tailrace outlet area.
Record storms
In the first eight days of the November, the Upper Campbell River watershed received the normal
amount of rainfall usually experienced during the entire month of November (400mm). From a
water inflow perspective, in the six weeks since the start of October, Upper Campbell
Reservoir/Buttle Lake received the runoff volume that would normally occur between October to
mid-January. Over seven day and 14 day periods, we set volume records of water inflows coming
into the Campbell River system. Our records go back 53 years. The amount of water into the
reservoir over one seven day period exceeded a 1-in-100 year return period for storm inflows.
Peak flood risk management discharges hit 600 m3/s and that matches 1990 releases. From the
John Hart facilities, 480 m3/s was the peak flow over Elk Falls with 120 m3/s passing through the
generating station. The lower Campbell River flow, with the Quinsam River, hit about 660 m3/s.
Pictures show the
480 m3/s peak
flow rate over Elk
Falls. The year-
round minimum
flow rate is 4
m3/s.
Environment
New Stickers: Hatfield Consultants have launched a new series of reward stickers for crews on
site. One, featuring a pic of a Newt, marks the next round of their ‘save a critter’ campaign.
Another, will recognize work done to protect biodiversity, particularly through ongoing weed
management like pulling Scotch broom or managing Japanese knotweed. The last will be a
special ‘gold star’ given out to those who show exemplary environmental care in all aspects of
their work.
Water Everywhere: While October and early November saw record rainfall, the project team’s site
water management work continues to work well. However, the heavy rain and an inadvertent
water discharge due to a broken pipe from one of the water treatment facilities contributed to a
slope failure near the Millennium Trail near the surge towers. The project team has assessed the
impacted area, which is all on BC Hydro property, and the trail remains safe to use.
Pulling Weeds: It’s a good time of year to deal with invasive weeds like Scotch broom, and the
environmental team continues to work at protecting biodiversity throughout the project site. Each
month, time is spent removing broom and other problematic weeds like holly and knotweed.
People Profile – Cesar Velez
Background:
Cesar graduated with a Bachelor Degree in Construction
Management and Science from George Brown College
in Toronto in 2010. He worked at the Waneta Expansion
Project from 2010-2015 as project coordinator doing weekly
and monthly schedules and reports.
Home:
Originally from Colombia, South America, Cesar moved to
Toronto, Ontario in 2003, then onto Trail, BC in 2010 where
he met his wife. They moved to Campbell River in 2015 with
their two daughters ages 4 and 2.
Hobbies:
Outside of work, Cesar spends most of his time with family going for walks along the ocean, biking on weekends and camping in the summers.
Project Responsibility:
As project coordinator working on cost control / scheduling for ASL-JV, Cesar helps to make sure the civil contractor stays on time and on budget. This is supported by a new accounting system called SAP.
“The John Hart project, and hydro projects in general, are very interesting to me because they encompass many different aspects of construction. I’m glad to be a part of it.”
About Cesar
Construction – Point Of Interest
Each month, BC Hydro and InPower BC will provide a construction fact,
occurrence, or situation.
Powerhouse Crane Commissioning.
Installation of the permanent powerhouse crane is a critical step in continuing the progress in
the powerhouse. It’s needed to lift some of the key mechanical components for power
generation into place. The crane is being installed now, and in December, a comprehensive
commissioning program will be done. This includes:
• Testing at 100 and 125 percent the hoist capacity of the main hoist (140MT) and auxiliary
hoist (25 MT);
• Weights are created using trays of concrete blocks and specified configurations. For the
biggest of these lifts, 337,300 pounds of concrete will be loaded; and
• Once properly rigged with the prescribed weight, the crane must travel the full length of the
powerhouse to ensure tracks are ready for work.
The testing will be completed by COH Inc, who manufactured the crane, and follows strict
protocols that protect safety of workers and integrity of the powerhouse.