Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Japan’s Nuclear Energy Policy
Ministry of Economy, Trade and Industry
Apr. 2018
1. Current Status of Nuclear Energy in Japan
2. Three Key Challenges- Challenge to International Market - Challenge to Decommissioning - Challenge to Nuclear Innovation
“Strategic Energy Plan” (Cabinet Decision in 2014. According to law, it will be revised in early 2018.)I. Nuclear power is an important base-load power source as a low carbon and quasi-
domestic energy source, contributing to stability of energy supply-demand structure.II. Dependency on nuclear power generation will be lowered to the extent possible by energy
saving and introducing renewable energy as well as by improving the efficiency of thermal power generation, etc.
III. The basic policy of Japan is to promote a nuclear fuel cycle that reprocesses spent fuelsand effectively utilizes the plutonium retrieved, from the viewpoint of effective utilization ofresources and reduction of the volume and harmfulness of high-level radioactive waste.
2030
Renewable energy 22~24% (approx.)
LNG 27% (approx.)
Coal26% (approx.)
Oil 3% (approx.)
LNG 27%
Oil 12%
Coal 24%
2001~2010 (average)
Nuclear power 27%
Renewable energy 11%
Nuclear power 22~20% (approx.)
【Source】 extracted (preliminary translation) from documents released in the 11th Long-term Energy Supply and Demand Outlook Subcommittee, Advisory Committee for Natural Resources and Energy, METI
Energy conservation
* Geothermal 1.7~4.6 %Biomass 3.7~4.6 %Wind 1.7 %Solar 7.0 %Hydro 8.8~9.2 %
2010 2013 2030Nuclear 29% 1% 20~22%Renewable* 10% 11% 22~24% Thermal 61% 88% 56%
Target of electricity generationBased on “Strategic Energy Plan”, METI approved “Long-term Energy Supply and Demand Outlook” (so-called Energy Mix) in 2015.
Strategic Energy Plan and Energy Mix as of 2030
2
In Operation Passed NRA Review
Under NRAReview
To be Determined
Decided toDecommission
PWR 7 5 4 1 7BWR 0 2 8 15 11(1 GCR)
3
Tokyo EPCOFukushima Daiicih
Hokkaido EPCOTomari
Tohoku EPCOOnagawa
Chubu EPCOHamaoka
JAPCTokai/Tokai Daini
Tokyo EPCOKashiwazaki Kariwa
Kyushu EPCOSendai
Chugoku EPCOShimane
Hokuriku EPCOShika
JAPCTsuruga
Kansai EPCOTakahama
Kansai EPCOMihama
Tohoku EPCOHigashidori
Tokyo EPCOHigashidori
Kyushu EPCOGenkai
Kansai EPCOOhi
Tokyo EPCOFukushima Daini
J-POWEROhma
11035
11034
11032
11030
13813
5233
8316
139
1107878787846
17
8454
11032
11027
11024
11023
11027
8933
5637
137
8341
5424
36
34 50
56
46
11824
11820
8343
8342
8932
11029
PWR BWR ABWR
Capacity(10MkW)Age
As of 3rd, Apr, 2018
Shikoku EPCOIkata
57 8923
13621
13620
5828
5826
918
12112
11631
11826
11825
8229
11030
11039
8322
11012
138
11424
8733
8732
*Ikata Unit 3 and Sendai Unit 1 are under the periodic inspection. Genkai Unit 3 is under the pre-service inspection
118 118
57
Restart of Nuclear Power Plants in Japan
4
Chugoku EPCOShimane③(ABWR , 1,373MWe)【under construction】93.6% completed Tokyo EPCO
Higashidori①(ABWR , 1,385MWe)
【under construction】9.7% completed
J-POWEROhma
(ABWR , 1,383MWe)【under construction】
37.6% completed
Under Construction Projects
Geological disposal repository
Next reprocessing
plant
( 5.5~6.5tPuf/y Plutonium usage by 16 to 18 MOX fuel load nuclear reactors *Including 1.1tPuf/y plutonium usage by Oma Nuclear Power Plant )
MOX fuel from foreign reprocessors
Plutoniumquantity possessedby electric power supplier(storage in UK and France)
approx.24.5tPuf
Fast Breeder Reactors(FBR)
MOX Fuel
Storing:approx.15,000tU
Storage capacity : approx.21,000tU
NuclearPowerPlant
(Spent fuel pool, etc.)
Waste (from Spent Fuel
Reprocessing) returned fromUK and France
Vitrified Waste Storage Center
Sub-surface disposaltest cavern
Low-Level Radioactive Waste Disposal Center
Storing : approx.2,970tUStorage Capacity : 3,000tU
JNFL: Japan Nuclear Fuel LimitedMOX: Uranium-plutonium mixed oxide
Mutsu:5000tU
Study on implementation of sub-surface disposal for waste from decommissioning (2002FY~)
Spent Fuel
JNFLRokkasho
Reprocessing Plant
Off-site storage facility(Spent Fuel Interim Storage)
MOX Fuel Fabrication Plant
Electric power supplier(Tokyo Electric Power co./Japan Atomic Power co.)
Oma Nuclear Power Plant(utilized fully load MOX fuel)
Waste from operation
Waste from operationand decommissioning
Vitrified Waste
Spent Fuel
JNFL
Plutonium over 4tPuf/y
Current Status of Nuclear Fuel Cycle
Plan of Operation: FY 2022 (the 1st half)
Plan of Operation: FY 2021 (the 1st half)
Plan of Operation: FY 2018 (the latter half)
5
1. Current Status of Nuclear Energy in Japan
2. Three Key Challenges- Challenge to International Market - Challenge to Decommissioning - Challenge to Nuclear Innovation
●In 2012, from its parent companies (E.ON and RWE), HITACHIpurchased all stocks of HORIZON, which has a plan to constructnew nuclear power plants in the UK such as Wylfa (1,350MW, 2reactors) and Oldbury (1,350MW, 2 reactors).
HITACHI plans to construct ABWRs through HORIZON. In Dec 2013, HORIZON agreed with HM Treasury on cooperation
regarding external financing of the building for new NPPs. Wylfa
Sellafield
Heysham
Hinkley Ponit C
Sizewell
Bradwell
Hartlepool
Oldbery
make proactive contributions to improvement of nuclear safety, peaceful use of nuclear power, nuclear non-proliferation and nuclear security in the world, by sharing the experiences and lessons learnt from the TEPCO's Fukushima nuclear accident.
Akkuyu
Turkey
Sinop
In 2013, Japan obtained the exclusive negotiating right for Sinop NPP (4 ATMEA1 reactors are planned).
In 2015, Inter Governmental Agreement (IGA) entered into force.
Feasibility Study for detailed construction plan has been undertaken by MHI.
UK: HORIZON Project
Turkey: Sinop Project
Contribution to Peaceful Use of Nuclear Power in the World
7
Nuclear Projects in UK
(1) France-China Coalition (EDF, CGN) and Japan have own projects.(2) Hitachi (HORIZON) plans to build two ABWRs in Wylfa, Wales.(3) UK strongly expects the success of Hitachi PJ. The PJ is important for Japan in
terms of maintenance of global competitiveness of JP nuclear tech & HRs.
Company Site Reactor type Unit Status
France-China
NNB GenCo
HinkleyPoint C
EPR(1,600MW) 2
<Total cost> £18.2bn<PPA> £92.50MW/h<Investment>EDF66.5%, CGN33.5%
Under construction(start operation in 2025)
Sizewell EPR tbd EDF80%, CGN20%
Bradwell Hualong1(Chinese) tbd EDF33.5%, CGN66.5%
Toshiba NuGen Moorside tbd 3 -Toshiba will sell the PJ-First refusal right to KEPCO
Hitachi
Horizon Nuclear Power
Wylfa ABWR(1,350MW) 2
Planned(start operation in middle 2020s)
Oldbery ABWR tbd Planned
Wylfa
Sellafield
Heysham
Hinkley Ponit C
Sizewell
Bradwell
Hartlepool
Oldbery
8
2012 HITACHI purchased all stocks of HORIZON
2013 Apply for GDA (Generic Design Assessment) ofABWRs in UK2017 approved By ONR and EA
1.HORIZON chronology <Wylfa map & site image>
9
2.Wylfa Project Schedule
2017 Apply for Granted SL (Nuclear Site License)
2020 Start construction (tentative)mid 2020s: Commercial Operation (tentative)
HITACHI plan to construct ABWRs at Wylfaand Oldbury1350MW × 2-3 reactors for each siteSame design as Tokyo EPCO “Kashiwazaki
Kariwa unit 6”
HORIZON Project
6.2 GW → 15 GW (2027)
The Agreement between India and Japan for peaceful uses of nuclear energy came in to effect in July, 2017. Based on the joint statement between both Prime ministers Abe and Modi, Working Group to strengthen bilateral nuclear cooperation was established.
Kakrapar 1、2(PHWR)Kakrapar 3、4(PHWR)
Tarapur 1、2(BWR)
Kaiga 1~4(PHWR)
Tarapur 3、4(PHWR)
Narora 1、2(PHWR)
Rajasthan 1~6(PHWR)
Rajasthan 7、8(PHWR)
Madras 1、2(PHWR)
Kovvada
Kudankulam 3~6(VVER-1000)
Chhaya-Mithi Virdi
(WH)
In Operation(22 reactors)
Under Construction(5reactors)
Planned
Kudankulam 1,2(VVER-1000)
Kalpakkam (PFBR)
Jaitapur 1、2 (EPR)
Nuclear Projects in India
Nuclear Capacity Target
Gorakhpur 1、2(PHWR)
Working Group between Japan and India
<Joint Statement between Japan and India> September, 2017
March, 2018 Kickoff Meeting (Nuclear Liability Law)
The two Prime Ministers expressed satisfaction at the entry into force of the Agreement between the Government of Japan and the Government of the Republic of India…. They looked forward to a working group to strengthen bilateral cooperation in this field …
10
Status of Nuclear Power in ASEAN Countries ASEAN’s nuclear power development: INDONESIA as the leader; MALAYSIA and PHILIPPINES
precede with concrete steps. Partners: overwhelmingly RUSSIA, and CHINA, with long-standing supports incl. R&D and capacity building.
Strong cautiousness on China’s influence. Great expectation to Japan as well.
Malaysia• General election will be held on May 9.• China practically starts its entry in
surrounding business, incl. thermal power.
Viet Num• NPP plan halted.
Expecting resumption.• HR devt with Russia
(eg. test reactor devt, dispatch of experts)
Philippines
Indonesia• ASEAN countries pay attention to Indonesia’s move.• HTGR devt with China’s supports. Recently LWR devt as well.• Russia & China selling float-type or shipboard reactors.
• Duterte has started considering construction of NPP with Russia’s supports, aiming to supply electricity to poor islands
Thailand• MOC in HR devt with CNNC in Sep 2017.• Equity participation of Thailand’s utility in
CGN’s NPP in China in Dec 2015. ( over 100 workers could be dispatched.)
Thailand5.5
Malaysia0.3
Indonesia
1.6
Viet Num0.3
Philippines
1.3
JP utilities develop business in SE Asia (thermal power/ IPP) (total in capacity of each PJ (only JP shares), incl. under construction/planned (unit: GW))
11
1. Current Status of Nuclear Energy in Japan
2. Three Key Challenges- Challenge to International Market - Challenge to Decommissioning - Challenge to Nuclear Innovation
reactors
Decommissioning already decided Other reactors
3+9BeforeThe Earthquake
AftertheEarthquake
40 years Operation
If life extension is approved,60 years maximum
Decommissioning caused by Accident
<Three Challenges for Decommissioning>Negative impact on
local economy(employment, tax revenue etc.)
Negative impact on balance sheet of the operators
Waste disposal(rule-making etc.)
Decommissioning of Nuclear Power Plants in Japan
Fukushima-Daiichi#1 - #6 +
6 reactors
International Workshop on Decommissioning (30, June, 2017)
JPN-U.S. Forum on Decommissioning (7, August, 2018, in Tokyo) ←coming!
sharing lessons learned in strategic planning, management oversight, and stakeholder engagement for further Japan-U.S. commercial cooperation in these areas
learning more about the various efforts from the experienced countries(U.S., UK, France, etc.)
13
International Workshop on Decommissioning of Nuclear Power Plants
For the decommissioning of NPP, the big issues are to carry out dismantling work efficiently with the existing technologies, and optimizing process management and so on.
Therefore the Workshop was held for the purpose of learning more about the various efforts from the experienced countries (USA, UK, France, Russia), and sharing the knowledge and discuss solutions.
1.Purpose
Venue :49th floor of the Mori Tower, 6-10-1 Roppongi Minato-ku, Tokyo Language :English and Japanese.(simultaneous interpretation)Participants: about 400 people
3. Program
■Noriaki Ozawa:Director-General for Energy and Environmental Policy ANRE,METI
■William D. Magwood:Director-General, OECD/NEA
■Toyoaki Yamauchi:Senior Executive Officer,The japan Atomic power Company“Current Status and Issues of D&D of NPPs in Japan”
■Okamoto Koji: Professor, The University of Tokyo“Safety Standards for decommissioning Activities”
■Masahiro Aoki :DG for Nuclear Regulation, NRA“Regulatory Framework for decommissioning of NPP in Japan ”
■Adrian Simper(UK):Strategy and Technology Director, NDA
■Pual T.Dicken(US):Senior Policy Fellow,
Argonne National Laboratory
■Evgeny Komarov(RF)
■Bertrand Martelet(Fr):EDF Senior Vice President
■Arnaud Gay(Fr):Director, International
Operations Recycling Business Unit, New AREVA Holding :Senior Manager, State
Corporation ROSATOM
10:30~ 11:00 Opening ~Keynote(30 min)
11:00~11:45 Current Situation of the Ongoing Decommissioning
OECD/NEA, NDA, CEA, ROSATOM, Energy Solutions, McKinsey &Co. Arthur D Little, The University of Tokyo and So on
<Moderator> ■Jochen Latz:Partner, McKinsey and Co.
<Panelist>■François Gauché (Fr)
■Colin Austin(US):Director CommissariatNuclear Energy Division, CEA
■Mark Rouse(UK):Business Director-Japan,
Cavendish Nuclear Limited
Senior Vice PresidentEnergy Solutions
■Mykyta Konstantinov(RF):Adviser to
Director General JSC
■ Toyoaki Yamauchi:Senior Executive Officer, The japan Atomic power Company
■ Daisuke Matsuno : Director, Nuclear Energy Policy Planning Division, ANRE, METI
15:00~ 15:40 Poster session
15:40~ 17:10 Panel Discussion
17:10~ 17:30 Closing Remarks
【TOPIC】 the Optimizing the decommissioning in japan
2.OutlineDate and Time :June 30th , 2017 , 10:30~17:30
(Roppongi Hills) (Tower hall) (Reception hall)
13:20~15:00 Case Examples from Oversees
Ref. Overview of International Workshop on Decommissioning
14
Contaminated Water
Management
Decommiss-ioning
Off-siteAbove data (mSv/year) is estimated by the rate of air dose under a condition.
Preparation of the environment
for Return・Promoting Fukushima Innovation Coast
Framework.・Supporting the business and livelihood
restoration.・Eliminating reputation damage.・Prepairing Zone Designated for
Reconstruction and Recovery. etc
15
All of the orders of Habitation Restricted Areas and Preparation Areas for Lift of Evacuation Order were lifted by spring 2017, except for the evacuation orders in Okuma town and Futaba town.
Tomioka Town25mSv/year
Dai-ichiNPS
KawamataTown
TamuraCity
Futaba Town
KawauchiVillage
Okuma Town
TomiokaTown
Naraha Town
MinamisomaCity
Iitate Village
KatsuraoVillage Namie Town
Emergency Evacuation-Prepared Areas
Deliberate Evacuation Areas
Restricted Areas
Namie Town16mSv/yearTamura City7mSv/year
Physical decay+Weatheringeffect+Decontamination
0.5mSv/year
1.1mSv/year
1.6mSv/year
2017(6 years after the
accident)
2018(7 years after the
accident)April 2011
(Immediately after the accident)
Tow
ard
Dec
omm
issi
onin
gTo
war
dSu
stai
nabl
e m
easu
res
Tow
ard
Reco
nstr
ucti
on
Future
March 2011(Immediately after the accident)
10,000Bq/Ⅼ※Radioactive materials concentration in surrounding sea area
Less than 1/10,000
Reactor BuildingContaminated Water
Sea-side impermeable wallsLand-side Frozen-soil Walls
Waterproof pavement
Sea
Contaminated Water Management Extremely low and undetectable
(Under 0.7Bq/L)
March 2016(5YEARS after the accident)
IAEA review report(May 2015)• Many important tasks on
decommissioning and contaminated water management has been done. A large improvement was made.
Nuclear Damage Compensation and Decommissioning Facilitation Corporation(Aug. 2014)
International Research Institutefor Nuclear Decommissioning(Aug. 2013)
Mid-and-Long- term Roadmap(Dec. 2011)
Ongoing Activity toward decommissioning-Decide the policy for debris retrieval(Sep.2017)
Removal of fuels from Unit 3 will begin(Mid. FY2018)
Efforts for Contaminated Water Management and Decommissioningat Fukushima Daiichi
KawamataTown
IitateVillage
Soma City
Minamisoma City
ShinchiTown
TamuraCity
KatsuraoVillege Namie
Town
Iwaki City
KawauchiVillege
HironoTown
NarahaTown
TomiokaTown
OkumaTown
FutabaTown Dai-ichi
NPS
Dai-niNPS
Future
×
April 2011(Immediately after the
accident)
JAEA’s Okuma Analysis and Research Center(Okuma Town)
●Lift of evacuation order
・Preparation for return ofevacuees.
Re-designing Fukushima, building on wisdom from
home/abroad
Robot test field(Minamisoma City and Namie Town)
Floating offshore wind fam demonstration project(off Fukushima)
JAEA’s Collaborative Laboratories for Advanced Decommissioning Science(Tomioka Town)
Naraha Remote Technology Development Center(Naraha Town)
Accelerating Fukushima’s reconstruction
:Looking ahead to Tokyo2020
●Fukushima Innovation Coast Framework
・Creating cutting-edge newtechnologies and industries in Hama-dori area.
●Fukushima New Energy-Oriented Society Scheme
・Developing Fukushima into new energy society in the future.
Dai-ichiNPS
KawamataTown
TamuraCity
Futaba Town
KawauchiVillage
Okuma Town
TomiokaTown
Naraha Town
MinamisomaCity
Iitate Village
KatsuraoVillage Namie Town
Restricted Areas
Emergency Evacuation-Prepared Areas
Deliberate Evacuation Areas
the demonstration of National power-to-gas project(Namie Town)
Future in Fukushima
16
1. Current Status of Nuclear Energy in Japan
2. Three Key Challenges- Challenge to International Market - Challenge to Decommissioning - Challenge to Nuclear Innovation
Private-sector-led nuclear innovation
Nuclear Innovation as Key Solution
Financial support• Competitive public research
funds to involve venture companies.
• Supporting R&D and licensing costs in accordance with devtstage.(“Phased approach”)
Regulatory foreseeability• Regulatory policies for innovative
technologies clearly described by regulatory authority.
• Starting consultation from early stage of technology devt with pre-licensing review and reactor design certification.
R&D infrastructure• Providing labs’ test facilities &
sites for demonstration reactor construction to vendors.
• Utilizing research facilities internationally.
18
Selection by marketEmbodying construction PJs thruinvolving utilities & financial inst.
into PJ development.
VisionVision (eg. roadmap) of nuclear R&D
provided by the government.
Discussing revision of Strategic Energy Plan→ Acquiring social trust is indispensable.
Developing reactors with safety, economy, and flexibility as the key
Explore every possibility by utilizing innovative vitality of private sector
Light water reactor (large size) Light water reactor(medium/small size) Non-light water reactor
TWR-P (SFR)600 MWJV bet. Bill Gates and ChinaTerra Power/CNNC
BN-800 (SFR)880 MWOKBM
ASTRID (SFR)600 MWCEA
ATMEA11100 MWFramatome/MHI
Hualong11150 MWCGN&CNNC
VVER-12001200 MWRosatom
ACP100S100 MWCNNC
Nuscale600 MWNuscale
KLT-40S50 MWOKBM
ABWR1350 MWHITACHI/TOSHIBA
EPR1600 MWFramatome
CAP14001400 MWSPIC
HTTR (VHTR)30 MWtJAEA
IMSR-400 (MSR)200 MWTerrestrial
U-battery (VHTR)4 MWDesalination with
high temp.heatURENCO
AP10001000 MWWH/TOSHIBA
Design with passive safety
Ship type SMR
Levitation type plant
Hydrogen production with ultra high temperature 950 ℃
No need for refuelingfor 40 years
Independent operation in depopulated areaswhere transmission lines do not reach
Using the liquid fuel
SMR-160160 MWHoltec
Integrated PWR SMRSF demonstration reactor
SF demonstration reactorduring operation
Latest Reactor Types in the World
19
Prospects of Nuclear Development in the World
20
2030~ 2040~ 2050~
Improved light water reactors(G3+ reactors incl. ABWR; commercial phase)
Near-future reactors(eg. light water SMRs; early development ~ pre-commercial phase)
Next-generation reactors(eg. SFR, MSR; basic research phase)
• Supporting tech devt with competitive research funds
• Tech selection by its future users incl. utilities
Commercializing it with supports for site selection and licensing
• Fundamental R&D for various reactor types with competitive research funds
Concretizing business (incl. construction and operation) thru involving utilities & financial institutions.
• Supporting tech devt with competitive research funds
• Tech selection by its future users incl. utilities
Commercializing it with supports for site selection and licensing
Phased Approach & Selection by Market
21
Level SA(Commercialization)
Level A(Pre-commercialization)
Level B(Early development phase)
Level C(Basic research phase)
○ Phased Approach: Providing supports in accordance with stages of R&D.○ Selection by market: Utilities’ selecting technologies and leading to commercialization
with financial institutions’ engagement
・”Small amount, 90% subsidy” × “Many Cases”
・”Medium amount, 75% subsidy” × “~5 Cases”
・”Large amount, 50% subsidy” × “2~3 Cases”
・Site allocation, Financial supports
Phased Approach Selection by marketConcretizing business (incl. construction & operation) led by utilities & financial institutions
Selecting & supporting promising technologies by utilities as its future user
Image of Shared Strategy to Promote Innovation
JAEA NationalLaboratory
Joyo HTTR TREAT VTR
Government of Japan Government of USA
Othercountry
Light WaterSMR MSRVHTRSFR
• Nuscale• GEH
• MFBR• Terra Power
• X-Energy • Terrestrial Energy
Government
22
Currently, “Strategy Roadmap” is being made in “Strategic Working Group on Fast Reactor development” for specifying the development work in next 10 years.
One of key points is utilizing the best combination of domestic and international resources/facilities.
Experimental Fast Reactor”JOYO”
SFR R&D throughInternational Collaboration
Fast Reactor Development
Large-scale Test Facility“AtheNa”
ASTRID TREAT, VTR
Multi-lateral collaboration in GIF(Generation IV International Forum)
- Application to NRA in March 2017for alteration of reactor installationto verify the conformity to the newregulatory requirement.
- Use for fuel/material irradiationtest, human resource development,etc.
- Dimension of facility:130m x 62m x 55m-height
- Sodium inventory: 240 ton
- Reactor vessel test modelfor thermal-hydraulic test.(tentative plan)
23
Thank you for your attention!