35
January 6 th , 2011 Operating Board Meeting

January 6th, 2011 Operating Board Meeting

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: January 6th, 2011 Operating Board Meeting

January 6th, 2011 Operating Board Meeting

Page 2: January 6th, 2011 Operating Board Meeting

Projects & Issues to Cover1. Tolt Slide

2. Brightwater Tunneling – 550 Pipeline risk management

3. Cathodic Protection Program

4. CRPL4 – impacts from Sound Transit and City of Renton projects in the Green River Valley

5. Tolt System Improvements completed in 2010

6. Whole Sale Meters

7. Lake Youngs algae management

8. Cedar Treatment Facility – UV valves upgrades

Page 3: January 6th, 2011 Operating Board Meeting
Page 4: January 6th, 2011 Operating Board Meeting

Location

Tolt Slide

Page 5: January 6th, 2011 Operating Board Meeting

Location of Instruments and Monitoring Points

Tolt Slide

Page 6: January 6th, 2011 Operating Board Meeting

Ground movement continues…

Tolt Slide

0.00

0.50

1.00

1.50

2.00

2.50

Inch

es

com

bin

ed

dis

pla

cem

en

t

Tolt 1

Pt 5103

Pt 5106

Pt 5107

Pt 5108

Page 7: January 6th, 2011 Operating Board Meeting

Ground movement continues…

Tolt Slide

0.00

0.50

1.00

1.50

2.00

2.50

3.00

3.50

Inch

es

com

bin

ed

dis

pla

cem

en

t

Tolt 2 and Vicinity

Pin 5001

Pin 5002

USP W 5231

USP E 5232

Pt 5207

B-102

B-103

B-104

Note: B-102, 103, 104 are x-y data only.

Page 8: January 6th, 2011 Operating Board Meeting

Ground movement continues…

Tolt Slide

0.00

0.20

0.40

0.60

0.80

1.00

1.20

1.40

1.60

1.80

2.00

Dis

tan

ce c

ha

ng

e i

nch

es

Tolt 2 Distance Change Across Ball Joints

Distance (inches) between 5231 & 5232

Page 9: January 6th, 2011 Operating Board Meeting

Ground movement - Inclinometers along TPL2

Tolt Slide

B-102 B-103 B-104

Page 10: January 6th, 2011 Operating Board Meeting

Inclinometers along TPL2 – displacement versus time

Tolt Slide

B-102

Page 11: January 6th, 2011 Operating Board Meeting

Inclinometers along TPL2 – displacement versus time

Tolt Slide

B-103

Page 12: January 6th, 2011 Operating Board Meeting

Inclinometers along TPL2 – displacement versus time

Tolt Slide

B-104

Page 13: January 6th, 2011 Operating Board Meeting

Tolt Slide Feasibility study completed in 2010 to identify possible

slide stabilization measures

Ground dewatering identified as a promising, relatively low cost solution

Predesign of a vertical well dewatering system initiated

A limited number of additional geotechnical instruments added to provide data in aide of dewatering system design

Page 14: January 6th, 2011 Operating Board Meeting

Geotechnical Field Work in 2011

Tolt Slide

Two additional Inclinometers installed in 2010

Inclinometers installed in 2009

Groundwater monitoring piezometersinstalled in 2010

Page 15: January 6th, 2011 Operating Board Meeting
Page 16: January 6th, 2011 Operating Board Meeting

Brightwater Tunneling

Page 17: January 6th, 2011 Operating Board Meeting

Brightwater Tunneling Tunneling under the 550 Pipeline to begin in late

January 2011

Risk is very low – experienced contractor, different machine compared to the one that caused a sinkhole

Relative risk is the highest at Lyons Creek – tunnel is “only” 100 feet below surface, soils are sandy

Lyons Creek expected to be reached late April or in May 2011

Settlement monitoring points installed every 500-1,000 feet along the tunnel alignment

Page 18: January 6th, 2011 Operating Board Meeting

Brightwater Tunneling Survey monitoring points at 100 foot spacing set up in

the vicinity of Lyons Creek, and at 200 foot spacing near Lake Forest Reservoir

Weekly updates on BT3C position

Half of Lake Forest Reservoir will be taken off line while tunneling at Lyons Creek is underway

Tunneling under Seattle facilities will be completed by end of July 2011

Page 19: January 6th, 2011 Operating Board Meeting
Page 20: January 6th, 2011 Operating Board Meeting

Cathodic Protection Program

Impressed Current Cathodic Protection (CP) is a key element of our long term Transmission System strategy

CP has been used effectively by Seattle Water on selected segments of steel pipelines since the 1960s

CP is installed where corrosive soils cause repeated leaks on steel pipelines

Recently CP was successfully installed on 3.5 mi of concrete cylinder pipe, after electrically bonding the pipe sticks at every joint

Page 21: January 6th, 2011 Operating Board Meeting

Cathodic Protection Program

Sallal

North Bend

Snoqualmie

Fall City

Ames Lake

Sammamish Plateau

Union Hill

N.E. Sammamish

Cedar River

Seattle

Bellevue

Northshore

Kirkland

Woodinville

Duvall

W.D.90Renton

Kent Soos Creek

W.D.111

Highline

Seattle

W.D.20

W.D.49

Mercer Island

Coal Creek

Issaquah

Redmond

W.D.119

Shoreline

Tukwila

2 0 2 4 6 8 MilesCast Iron

Concrete

Concrete Cylinder

Ductile Iron

Steel

Reinforced Concrete

Regional Water Transmission SystemTransmission Pipeline Material TypesN

Cedar Treatment

Landsburg

Reg Basin

Tolt Treatment

Page 22: January 6th, 2011 Operating Board Meeting

Cost effectiveness of CP varies greatly depending on how well the steel is electrically insulated from the surrounding soil

A rectifier station costing approx. $300k and lasting 20-25 years would protect:

about 1,500 feet of bare steel pipe

About 5 miles of modern well insulated pipe (TPL2)

About 3 miles of Concrete Cylinder (CC) pipe

A pipeline protected by a well run CP system does not corrode (any further)

Cathodic Protection Program

Page 23: January 6th, 2011 Operating Board Meeting

In 1Q2011 a Strategic Transmission Plan will be finalized and presented to the AMC and the Operating Board

The plan will expand on the Transmission System strategy paper from the 2007 Water System Plan

A programmatic business case for the installation of CP on all CC pipelines will follow

CC pipe fails catastrophically, in contrast to steel pipe

Information is already available from a 1990s report on the relative condition of the CC pipelines

Cathodic Protection Program

Page 24: January 6th, 2011 Operating Board Meeting

CP will be installed, starting with the most deteriorated segments

CCP has rubber gaskets at pipe joints

To create an electrically continuous pipe a jumper must be welded to connect across

Jumpers can be installed…

Internally – requires pipe to be empty and out of service

Externally – requires excavation, backfill, restoration

Dense valve spacing on the CC pipelines would reduce extent of outages associated with internal joint bonding

Cathodic Protection Program

Page 25: January 6th, 2011 Operating Board Meeting

CP Economics less clear on steel pipelines

If too many rectifier stations are needed, replacing the pipeline segment may be more economical and full length CP

CP needs to be more selective

Leak frequency is a great indicator of where CP would be beneficial, but…

…internal cement mortar lining delays the manifestation of leaks as it bridges pinholes

Newer tools for Acoustic leak detection may be help

Cathodic Protection Program

Page 26: January 6th, 2011 Operating Board Meeting
Page 27: January 6th, 2011 Operating Board Meeting

CRPL4 Impacts

Page 28: January 6th, 2011 Operating Board Meeting
Page 29: January 6th, 2011 Operating Board Meeting

2010 Tolt System ImprovementsTolt Treatment Facility Clearwell

Existing remote controlled isolation valve

1. Upgraded emergency pump at TESS Junction to 7 MGD, higher head pump capable of pumping up to clearwell

2. Completed the SCADA upgrade such that valves can be operated remotely

Page 30: January 6th, 2011 Operating Board Meeting
Page 31: January 6th, 2011 Operating Board Meeting

Annual testing of Tolt meters is about to start and be completed in 1Q2011

Annual testing of Cedar meters pushed to June-July after a possible algae bloom

Strainer baskets on Protectus meters on the Cedar have been removed

Several Cedar meters in Seattle retail that has not been worked on since the 2010 algae bloom will be tested and opened up to determine if algae buildup from 2010 has dissipated

Whole Sale Meters

Page 32: January 6th, 2011 Operating Board Meeting
Page 33: January 6th, 2011 Operating Board Meeting

Build on experience from 2008 and 2010

Increased bypassing of Lake Youngs during algae blooms

A Key Performance Indicator (KPI) instituted:

Bypass Lake Youngs at least 90 percent of the time when cyclotella bio-volume is above 0.5 mm3/L and Cedar River water quality at Landsburg is OK.

Distribution System Impacts Management Best Practices forum scheduled for February 9, 2011

2010 Lake Youngs Algae Management

Page 34: January 6th, 2011 Operating Board Meeting
Page 35: January 6th, 2011 Operating Board Meeting

Cedar WTP UV Valve Leakage: 2011 Fix