PacifiCorp customers 3 Investor owned utility – subsidiary of Berkshire Hathaway Energy 6,447 staff in U.S. 1.8million customers in 6 states Utah (42%) Oregon (25%) Wyoming (17%) Washington (8%) Idaho (6%) California (2%) PacifiCorp Peak Load:12,558 MW PACW: 4354 MW 80+ Ties with other Balancing Areas PACE: 8989 MW 50+ Ties with other Balancing Areas

Citation preview

Page 1: January 14, 2016 PacifiCorp-CAISO-NVE EIM Initiative Overview

January 14, 2016

PacifiCorp-CAISO-NVEEIM Initiative Overview

Page 2: January 14, 2016 PacifiCorp-CAISO-NVE EIM Initiative Overview

Agenda• Introduction• PacifiCorp background• Real-time operations of EIM• Challenges• Current status

Page 3: January 14, 2016 PacifiCorp-CAISO-NVE EIM Initiative Overview

PacifiCorp customers

3

Investor owned utility – subsidiary ofBerkshire Hathaway Energy6,447 staff in U.S.1.8million customers in 6 states

Utah (42%)Oregon (25%)Wyoming (17%)Washington (8%)Idaho (6%)California (2%)

PacifiCorp Peak Load:12,558 MWPACW: 4354 MW80+ Ties with other Balancing AreasPACE: 8989 MW50+ Ties with other Balancing Areas

Page 4: January 14, 2016 PacifiCorp-CAISO-NVE EIM Initiative Overview

EIM FootprintPacifiCorp• 1.7 million customers • 9,500 MW peak demand• 10,600 MW generating capacityNV Energy• 1.2 million customers• 8,148 MW peak demand• 5,815 MW generating capacityCAISO• 11.4 million customers• 50,280 MW peak demand• 58,246 MW generating capacityPSE and AZPS• Coming soon….

Page 5: January 14, 2016 PacifiCorp-CAISO-NVE EIM Initiative Overview

EIM Concept• What is an EIM

– It is not an ISO– It is not balancing our BAA

• EIM in real-time– Generation redispatch– Forward looking transmission management

• BAA’s responsibilities– Not changing– New tools and processes

Page 6: January 14, 2016 PacifiCorp-CAISO-NVE EIM Initiative Overview

Variable Energy Operation

Page 7: January 14, 2016 PacifiCorp-CAISO-NVE EIM Initiative Overview

EIM Real-Time Operations• Timing criticality of a 5 minute system• Base Schedules• Hourly vs. 15 minute vs. 5 minute markets• Dispatches• Transmission congestion• Outages

Page 8: January 14, 2016 PacifiCorp-CAISO-NVE EIM Initiative Overview

Operational Concept Overview• Expansion of CAISO’s current 5 minute market

– Security Constrained Economic Dispatch• Transmission constraint management• Network model visibility and accuracy • Terminology:

– Market Operator, EIM Entity, Participating Resources, Manual Dispatch, Instructed/Uninstructed Imbalance charges, Scheduling Coordinator…..

• Detailed outage reporting and situational awareness

Page 9: January 14, 2016 PacifiCorp-CAISO-NVE EIM Initiative Overview

Base Schedules• Entity must come to the market balanced• Base Schedule (G + I = L) (feasibility check)

– Forecast of load – Forecast of generation– Forecast of interchange

• Submitted by all customers to EIM Entity• Data aggregated and validated by PacifiCorp Grid• Entity retains all BAA responsibilities

Page 10: January 14, 2016 PacifiCorp-CAISO-NVE EIM Initiative Overview

Base Schedule data flow (via SCs)

Page 11: January 14, 2016 PacifiCorp-CAISO-NVE EIM Initiative Overview

Balance and Feasibility Tests• Base Schedule Balancing Test• Bid Range Capacity Test• Flex Ramp Required Sufficiency Test• Transmission Feasibility Test

Page 12: January 14, 2016 PacifiCorp-CAISO-NVE EIM Initiative Overview

Hourly vs. 15 minute vs. 5 minute• Hourly market (HASP)

– Unit start up, shut down, and transitions• 15 minute market (RTPD)

– Market awards, e-tags– Runs approx. 40 minutes ahead

• 5 minute market (RTD)– Dispatches based on 15 min awards– Runs approx. 7.5 minutes before ramp

Page 13: January 14, 2016 PacifiCorp-CAISO-NVE EIM Initiative Overview

Dispatch• Dispatch sent to PacifiCorp’s Ranger (EMS), to RTU,

and to the plant

Page 14: January 14, 2016 PacifiCorp-CAISO-NVE EIM Initiative Overview
Page 15: January 14, 2016 PacifiCorp-CAISO-NVE EIM Initiative Overview

Transmission Congestion• Forward looking congestion management• 15 minute market awards published for 8+

intervals• Correcting limits in state estimator• Collaboration between Energy Grid Operator

(EIM desk) and TO desks

Page 16: January 14, 2016 PacifiCorp-CAISO-NVE EIM Initiative Overview

Outage Reporting Requirements• Outage reporting is critical to SE and dispatches• Planned outages must be submitted at least 7 days in

advance– For EIM, at least seven days

• Forced outages must be reported within 30 minutes– Less imbalance the sooner it is reported

• PAC using COMPASS to interface to CAISO’s OMS • Market run criticality

Page 17: January 14, 2016 PacifiCorp-CAISO-NVE EIM Initiative Overview

PAC and CAISO responsibilities• PAC retains all reliability function responsibility• PAC will balance their ACE, manage reserves (no

impact to NWPP RSG) and manage their voltage • Under EIM, CAISO operates the market and publishes

market results for both PAC and CAISO (the EIM footprint)

• Under EIM, PAC will operate transmission, monitor generation, process outages, and balance ACE for PACW and PACE

Page 18: January 14, 2016 PacifiCorp-CAISO-NVE EIM Initiative Overview

Challenges (go-live)Go-live• Typical IT software refining• Accuracy of generation unit

outages and derates for informing market

• Disciplined generation and interchange resource plan that aligns with market

• Network model accuracy• Change management

Updates• System accuracy increasing

• Reaching granular aspects of base scheduling

• Network model aligned with CAISO and updated monthly

• Evolution of change management– (ongoing but evolving)

Page 19: January 14, 2016 PacifiCorp-CAISO-NVE EIM Initiative Overview

Challenges (current)• Change management evolution

– Understanding market actions• Outage management tools upgrades

– New webOMS system• Seasonal strategies

– Fuel restrictions• NVE incorporation

– New dynamic transfers– Networks the BAAs, rather than radial

Page 20: January 14, 2016 PacifiCorp-CAISO-NVE EIM Initiative Overview

Current Status• Continue updates of network model• Available Balancing Capacity testing

– January• Continued focus on transmission constraints• Solar integration

Page 21: January 14, 2016 PacifiCorp-CAISO-NVE EIM Initiative Overview

Questions