523-11-191 Chiller Plant Medical Center– Phase 1 – Jamaica Plain Project Overview This project is the first project in a multiple-phased approach to the entire Central Air conditioning system at the facility. The final capacity upon completion of the additional phases of the Chiller Plant will be 3600 tons of chilled water per hour. The installation the New Plant will address requirements of the Medical Center for future needs bridging the gap of aged equipment. The project will provide temperature monitoring at the central power plant and remotely control individual rooms by IP address also included is a robust industrial control system interfaced with the building master system and still providing local control to all rooms. The new chiller plant Current Status: October 2015 ~ Foundations have been completed ~ Structural Steel has been completed ~ Appurtenances ladders and stairs etc. pending. ~ Utility connections have been completed ~ Plant under final system completion ~ CMU and Brick façade of Parapet being installed ~ Field testing scheduled to begin next week ~ Final testing pending shutdown schedule approval. Project Milestones VA Contracting Specialist Carol Ahnee (774)-826-1573 Key Personnel Contractor Greenland Enterprises, Inc. Customer Building One – and connected additions VA Project Engineer Thomas Loos (857) 364-4014 Foundations 100% Complete JUL 15 MAY 15 SEP 15 JUN 15 OCT 15 SEP 15 JUN 16 OCT 16 AUG 16 OCT 28 MAR 15 JUN 16 Overall Construction 88% Complete CCD: DEC 16 NTP: MAR 14 Plant system completion 80% Complete Field testing 0% Complete Final testing 0% Complete Structural Steel 100% Complete Utility connections 100% Complete

Jamaica Plain Chiller Plant - Phase 1 - OCT 2015

Embed Size (px)

Citation preview

Page 1: Jamaica Plain Chiller Plant - Phase 1 - OCT 2015

523-11-191Chiller Plant Medical Center– Phase 1 – Jamaica Plain

Project OverviewThis project is the first project in a multiple-phased approach to the entire Central Air conditioning system at the facility. The final capacity upon completion of the additional phases of the Chiller Plant will be 3600 tons of chilled water per hour. The installation the New Plant will address requirements of the Medical Center for future needs bridging the gap of aged equipment. The project will provide temperature monitoring at the central power plant and remotely control individual rooms by IP address also included is a robust industrial control system interfaced with the building master system and still providing local control to all rooms. The new chiller plant (Phase 1) will provide a minimum of 50% of overall needed capacity and will allow for the gradual replacement of aging equipment located in Building 1 and existing buildings attached to Building 1 of the Medical Campus..

Current Status: October 2015~ Foundations have been completed~ Structural Steel has been completed ~ Appurtenances ladders and stairs etc. pending.~ Utility connections have been completed~ Plant under final system completion~ CMU and Brick façade of Parapet being installed~ Field testing scheduled to begin next week~ Final testing pending shutdown schedule approval.

Project Milestones

VA Contracting Specialist

Carol Ahnee(774)-826-1573

Key Personnel

ContractorGreenland Enterprises, Inc.

CustomerBuilding One – and connected additions

VA Project Engineer

Thomas Loos(857) 364-4014

Foundations 100% Complete JUL 15MAY 15

SEP 15JUN 15

OCT 15SEP 15

JUN 16OCT 16

AUG 16OCT 28

MAR 15JUN 16

Overall Construction88% Complete

CCD: DEC 16NTP: MAR 14

Plant system completion 80% Complete

Field testing 0% Complete

Final testing 0% Complete

Structural Steel 100% Complete

Utility connections 100% Complete