1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
1Preparation Works after Bidding process ( Detail
Drawing, Re-Calc & Shop Drawing etc.) 1 Ls 14 days
2 Foundation AB4
Foundation 9 days
a Concrete Floor Dismantling & Soil Excavation sq.m
b Lean Concrete cu.m 2 days
c Formwork installation sq.m 7 days
d Rebar Installation Kg 7 days
e Concrete Fc'25Mpa cu.m 1 day
Pedestal Column
a Formwork installation sq.m 5 days
b Rebar Installation Kg 5 days
c Anchor Bolt M24 Installation Pcs 2 days
d Concrete Fc'25Mpa cu.m 1 day
3 Steel Structure AB4 ( including Staircase )
a Fabrication Steel Structure in Jakarta Kg 5 Weeks
b Sand Blasting & Painting Steel Structure Kg 1 weeks
c Delivery Steel Structure from Jakarta to Tayan Site Kg 2 weeks
4 Installation & Erection Steel Structure Install & Erection 5-6 weeks
a Column WF300x300 Erection Kg
b Main Beam Erection Kg
c Branch Beam and Joist Erection Kg
d Chequered Plate Floor Installation Kg
e Staircase Erection Kg
No Description of Works QTY UnitMonth 4 Month 5
Schedule Plan AB4 Steel Structure (Civil Works)
RemarksMonth 1 Month 2 Month 3
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4No Description of Works QTY Unit
Month 4 Month 5Remarks
Month 1 Month 2 Month 3
5 Finishing & Commisioning 1 Ls
Electrical Work
1 Panel Installation
a Install SCP Panel 1 Unit
- Foundation Work
- Install Panel
b Install LCP Panel (Panel Hoist, MK, VS) 4 Unit
2 Cabling
a Install Power Cable from LVD - SCP Panel 150 m
b Install Power Cable from SCP Panel - LCP Panel
c Install Power Cable from LCP Panel - Motor
3 Hoist Installation
a Install rail cable hoist 1 Lot
b Install panel hoist 1 Lot
c Install cable hoist 1 Lot
4 Conduit Installation 1 Lot
5 Lighting Installation 1 Lot