JADWAL PELAKSANAAN

Embed Size (px)

DESCRIPTION

konstruksi

Citation preview

Page 1: JADWAL PELAKSANAAN

1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

1Preparation Works after Bidding process ( Detail

Drawing, Re-Calc & Shop Drawing etc.) 1 Ls 14 days

2 Foundation AB4

Foundation 9 days

a Concrete Floor Dismantling & Soil Excavation sq.m

b Lean Concrete cu.m 2 days

c Formwork installation sq.m 7 days

d Rebar Installation Kg 7 days

e Concrete Fc'25Mpa cu.m 1 day

Pedestal Column

a Formwork installation sq.m 5 days

b Rebar Installation Kg 5 days

c Anchor Bolt M24 Installation Pcs 2 days

d Concrete Fc'25Mpa cu.m 1 day

3 Steel Structure AB4 ( including Staircase )

a Fabrication Steel Structure in Jakarta Kg 5 Weeks

b Sand Blasting & Painting Steel Structure Kg 1 weeks

c Delivery Steel Structure from Jakarta to Tayan Site Kg 2 weeks

4 Installation & Erection Steel Structure Install & Erection 5-6 weeks

a Column WF300x300 Erection Kg

b Main Beam Erection Kg

c Branch Beam and Joist Erection Kg

d Chequered Plate Floor Installation Kg

e Staircase Erection Kg

No Description of Works QTY UnitMonth 4 Month 5

Schedule Plan AB4 Steel Structure (Civil Works)

RemarksMonth 1 Month 2 Month 3

Page 2: JADWAL PELAKSANAAN

1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4No Description of Works QTY Unit

Month 4 Month 5Remarks

Month 1 Month 2 Month 3

5 Finishing & Commisioning 1 Ls

Electrical Work

1 Panel Installation

a Install SCP Panel 1 Unit

- Foundation Work

- Install Panel

b Install LCP Panel (Panel Hoist, MK, VS) 4 Unit

2 Cabling

a Install Power Cable from LVD - SCP Panel 150 m

b Install Power Cable from SCP Panel - LCP Panel

c Install Power Cable from LCP Panel - Motor

3 Hoist Installation

a Install rail cable hoist 1 Lot

b Install panel hoist 1 Lot

c Install cable hoist 1 Lot

4 Conduit Installation 1 Lot

5 Lighting Installation 1 Lot