J4 Internal Construction Target Program

Embed Size (px)

Citation preview

  • 7/25/2019 J4 Internal Construction Target Program

    1/3

    ID Task Mode Task Name Duration Start Finish

    1 JUNCTION 4 ACCELERATION PROGRAM - CONSTRUCTIONTARGET PROGRAM

    395 days 23 Feb '15 23 Mar '16

    2 Design Submission 76 days 28 Feb '15 15 May '15

    3 Foundation DD submission to AECOM (D01) 0 days 28 Feb '15 28 Feb '15

    4 Abutment & Pier DD submission to AECOM (D01) 0 days 16 Mar '15 16 Mar '15

    5

    6 Beams DD submission to AECOM (D01) 0 days 30 Apr '15 30 Apr '15

    7 Deck DD submission to AECOM (D01) 0 days 15 May '15 15 May '15

    8

    9 Construction Works 274 days 23 Feb '15 23 Nov '15

    10 Foundation for Abutment 2 35 days 24 Mar '15 27 Apr '15

    11 Foundation for Abutment 1 35 days 30 Mar '15 03 May '15

    12

    13 Elevation Abutment 2 60 days 16 Apr '15 14 Jun '15

    14

    Elevation Abutment 1 69 days 22 Apr '15 29 Jun '15

    15

    16 TM 001 - Preparation of Traffic Management for Phase 1A 37 days 23 Feb '15 31 Mar '15

    17 TM 001 - Submission and Approval of Traffic Management forPhase 1A

    4 days 01 Apr '15 04 Apr '15

    18 TM 001 - Traffic Management Installation Phase 1A 11 days 05 Apr '15 15 Apr '15

    19

    20 Pier 3 125 days 15 Apr '15 17 Aug '15

    21 Excavation for Pier 3 28 days 15 Apr '15 12 May '15

    22 Foundation for Pier 3 including Backfilling 54 days 30 Apr '15 22 Jun '15

    23

    Elevation for Pier 3 84 days 26 May '15 17 Aug '15

    24

    25 TM 007 - Preparation of Traffic Management for Phase 1B 29 days 21 Mar '15 18 Apr '15

    26 TM 007 - Submission and Approval of Traffic Management forPhase 1B

    5 days 19 Apr '15 23 Apr '15

    27 TM 007 - Diversion of Traffic for Phase 1 (CCC Construction)1B

    1 day 25 Apr '15 25 Apr '15

    28

    29 Pier 1 126 days 25 Apr '15 28 Aug '15

    30 Excavation for Pier 1 28 days 25 Apr '15 22 May '15

    31 Foundation for Pier 1 including Backfilling 54 days 10 May '15 02 Jul '15

    32 Elevation for Pier 1 84 days 06 Jun '15 28 Aug '1533

    34 Removal of Street Light Pole & Diversions Cables 60 days 22 Mar '15 20 May '15

    35

    36 Pier 2 Foundation 118 days 21 May '15 15 Sep '15

    37 Slab 4C & 4D 61 days 21 May '15 20 Jul '15

    38 Excavation 21 days 21 May '15 10 Jun '15

    39 Foundation including Backfilling 50 days 01 Jun '15 20 Jul '15

    40 Slab 4A & 4B 56 days 22 Jul '15 15 Sep '15

    41 Excavation, Blinding and waterproofing 21 days 22 Jul '15 11 Aug '15

    42 Foundation including Backfilling 46 days 01 Aug '15 15 Sep '15

    43

    28-02

    16-03

    30-04

    15-05

    S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

    24 Jan '15 28 Feb '15 04 Apr '15 09 May '15 13 Jun '15 18 Jul '15 22 Aug '15 26 Sep '15 31 Oct '15 05 Dec '15 09 Jan '16 13 Feb '16 19 Mar '

    2012

    Page 1

  • 7/25/2019 J4 Internal Construction Target Program

    2/3

    ID Task Mode Task Name Duration Start Finish

    44 Deck slab Works for span 4 & 1 126 days 08 Jul '15 10 Nov '15

    45 Shoring for beam and Diaphragm for Abutment 2, Abutment1, Pier 3 and Pier 1

    67 days 08 Jul '15 12 Sep '15

    46 Erection of Super T Beam Span 4 (40 nos, 4/day) 15 days 03 Sep '15 17 Sep '15

    47 Erection of Super T Beam Span 1 (40 nos, 4/day) 16 days 18 Sep '15 03 Oct '15

    48

    49 Casting of Top Slab Span 4 27 days 10 Sep '15 06 Oct '15

    50 Casting of Top Slab Span 1 24 days 27 Sep '15 20 Oct '15

    51 Casting of Diaphragm Wall at Abutment 2 35 days 28 Sep '15 01 Nov '15

    52 Casting of Diaphragm Wall at Abutment 1 30 days 12 Oct '15 10 Nov '15

    53

    54 Diverting the Traffic through span 2 (4 Lanes) 9 days 29 Aug '15 06 Sep '15

    55

    56 Pier 2 Elevation 78 days 07 Sep '15 23 Nov '15

    57 Elevation 23 days 07 Sep '15 29 Sep '15

    58 Elevation 28 days 22 Sep '15 19 Oct '15

    59 Elevation 28 days 12 Oct '15 08 Nov '15

    60 Elevation 23 days 01 Nov '15 23 Nov '15

    61

    62 Deck slab Works for span 3 86 days 03 Nov '15 27 Jan '16

    63 Shoring for beam and Diaphragm for Pier 3, Pier 2 includingbearing

    34 days 03 Nov '15 06 Dec '15

    64 Erection of Super T Beam Span 3 (40 nos, 4/day) 14 days 06 Dec '15 19 Dec '15

    65

    66 Casting of Top Slab 24 days 13 Dec '15 05 Jan '16

    67 Casting of Diaphragm Wall at Pier 2 31 days 28 Dec '15 27 Jan '16

    68

    69 Diverting the Traffic through span 3 (4 Lanes) 3 days 20 Dec '15 22 Dec '15

    70

    71 Deck slab Works for span 2 270 days 15 Jun '15 10 Mar '16

    72 Shoring for beam and Diaphragm for Pier 1 7 days 23 Dec '15 29 Dec '15

    73 Erection of Super T Beam Span 2 (40 nos, 4/day) 15 days 30 Dec '15 13 Jan '16

    74 Casting of Top Slab 23 days 06 Jan '16 28 Jan '16

    75 Casting of Diaphragm Wall at Pier 2 42 days 20 Jan '16 01 Mar '16

    76 Casting of Diaphragm Wall at Pier 1 42 days 29 Jan '16 10 Mar '16

    77

    78 MSE Wall 2 construction up to Backwall level 62 days 15 Jun '15 15 Aug '15

    79 MSE Wall 1 construction up to Backwall level 62 days 06 Aug '15 06 Oct '15

    80

    81 Backwall Abutment 2 31 days 18 Oct '15 17 Nov '15

    82 Backwall Abutment 2 30 days 27 Oct '15 25 Nov '15

    83

    84 Remaining MSE Wall 2 23 days 18 Nov '15 10 Dec '15

    85 Remaining MSE Wall 1 22 days 10 Dec '15 31 Dec '15

    S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

    24 Jan '15 28 Feb '15 04 Apr '15 09 May '15 13 Jun '15 18 Jul '15 22 Aug '15 26 Sep '15 31 Oct '15 05 Dec '15 09 Jan '16 13 Feb '16 19 Mar '

    2012

    Page 2

  • 7/25/2019 J4 Internal Construction Target Program

    3/3

    ID Task Mode Task Name Duration Start Finish

    86

    87 Parapet Wall 39 days 06 Feb '16 15 Mar '16

    88 Road Works 48 days 05 Feb '16 23 Mar '16