Upload
others
View
10
Download
0
Embed Size (px)
Citation preview
JJ--PARC Accelerator Status and Commissioning PlanPARC Accelerator Status and Commissioning PlanPAC meeting, Masakazu Yoshioka (KEK), March 6, 2009PAC meeting, Masakazu Yoshioka (KEK), March 6, 2009
Recent milestones:Recent milestones:December 23, 2008: December 23, 2008:
30 GeV beam acceleration and fast extraction 30 GeV beam acceleration and fast extraction to the beam abort dumpto the beam abort dump
MLF user run (20kW)MLF user run (20kW)January 27, 2009:January 27, 2009:
Beam extraction to the Hadron Experimental hall Beam extraction to the Hadron Experimental hall using slow beam extraction systemusing slow beam extraction system
February 19, 2009:February 19, 2009:Government inspection for radiation safetyGovernment inspection for radiation safety
Beam commissioning has been accomplished Beam commissioning has been accomplished on schedule, BUT without space charge effect.on schedule, BUT without space charge effect.
We should understand its significance, We should understand its significance, BUT should not overestimate.BUT should not overestimate.
Real challenge toward the power frontier machine Real challenge toward the power frontier machine will start from now on.will start from now on.
We still have many We still have many issuesissues (unreliable components, design etc.) to be solved.(unreliable components, design etc.) to be solved.At the same time, we have to provide the At the same time, we have to provide the beam to usersbeam to users (It(It’’s a duty)s a duty)
(MLF, (MLF, HadronHadron, Neutrino)., Neutrino).Additionally, Additionally, power upgradepower upgrade should be also accomplished steadily. should be also accomplished steadily.
Personal Recognition of JPersonal Recognition of J--PARC PARC Accelerator SituationAccelerator Situation
Goal (Mission) and Issues for Goal (Mission) and Issues for 33--step Power Upgrade Scenariostep Power Upgrade Scenario
100kW100kW trial in JFY2009trial in JFY2009JFY2009 ScheduleJFY2009 ScheduleRCS status and plan for MLF user run (Michikazu Kinsho)RCS status and plan for MLF user run (Michikazu Kinsho)MR commissioning status (Tadashi Koseki)MR commissioning status (Tadashi Koseki)Urgent issues to be solvedUrgent issues to be solved
RFQRFQMR Magnet power supplyMR Magnet power supply
Beyond 100kW from 2010: Beyond 100kW from 2010: 100100 750kW(Design)750kW(Design)Space charge effect and collimator scenarioSpace charge effect and collimator scenarioLinac Linac 400 400 MeVMeV energy recovery and upgrade of the RCS injection systemenergy recovery and upgrade of the RCS injection system
LongLong--term plan toward power frontier term plan toward power frontier (~MW(~MW))KEK roadmapKEK roadmap
Contents:Contents:
MLF User run: MLF User run: 110 days110 days
Linac operation total: Linac operation total: 190 days 190 days
33--Month Summer shutdown: Month Summer shutdown: July~September July~September
MR operation schedule:MR operation schedule:Tentative !!!Tentative !!!
Tentative plan for Tentative plan for MLF userMLF user run and MR run in JFY2009run and MR run in JFY2009User Run Machine Study Maintenance
April May June
SunMonTueWedThuFri Sat SunMonTueWedThuFri Sat SunMonTueWedThuFri Sat
1 2 3 4 1 2 1 2 3 4 5 6
5 6 7 8 9 10 11 3 4 5 6 7 8 9 7 8 9 10 11 12 13
12 13 14 15 16 17 18 10 11 12 13 14 15 16 14 15 16 17 18 19 20
19 20 21 22 23 24 25 17 18 19 20 21 22 23 21 22 23 24 25 26 27
26 27 28 29 30 24 25 26 27 28 29 30 28 29 30
0 19 31 15 22
13 21
October November December
SunMonTueWedThuFri Sat SunMonTueWedThuFri Sat SunMonTueWedThuFri Sat
1 2 3 1 2 3 4 5 6 7 1 2 3 4 5
4 5 6 7 8 9 10 8 9 10 11 12 13 14 6 7 8 9 10 11 12
11 12 13 14 15 16 17 15 16 17 18 19 20 21 13 14 15 16 17 18 19
18 19 20 21 22 23 24 22 23 24 25 26 27 28 20 21 22 23 24 25 26
25 26 27 28 29 30 31 29 30 27 28 29 30 31
16 28 19 23 19 24
44/90
SunMonTueWedThuFri Sat SunMonTueWedThuFri Sat SunMonTueWedThuFri Sat
1 2 1 2 3 4 5 6 1 2 3 4 5 6
3 4 5 6 7 8 9 7 8 9 10 11 12 13 7 8 9 10 11 12 13
10 11 12 13 14 15 16 14 15 16 17 18 19 20 14 15 16 17 18 19 20
17 18 19 20 21 22 23 21 22 23 24 25 26 27 21 22 23 24 25 26 27
24 25 26 27 28 29 30 28 28 29 30 31
31 16 20 0 15
14 21 66/100
Januar Februa March
RCSRCS
MR operation includes;MR operation includes;CommissioningCommissioningPower ImprovementPower ImprovementUser RunUser Run
Tentative RCS power up grade plane Tentative RCS power up grade plane for MLF User Run for MLF User Run ((NOT for MR)NOT for MR)
considering the lifetime of mercury targetconsidering the lifetime of mercury target
New RFQ
300 MeVInjection
400 MeVInjection
We need discussionsWe need discussions
MR MR 100kW 100kW
runrun
kWkW
Michikazu KinshoMichikazu Kinsho
MR commissioning statusMR commissioning statusTadashi Koseki for ATAC09Tadashi Koseki for ATAC09
11st st ––stagestage
Summer shutdownSummer shutdown
2nd2nd ––stagestage
3rd3rd ––stagestage
Tadashi Koseki for ATAC09Tadashi Koseki for ATAC09
Tadashi Koseki for ATAC09Tadashi Koseki for ATAC09
Fast extraction Fast extraction tuningtuning
Tadashi Koseki for ATAC09Tadashi Koseki for ATAC09
Slow extraction Slow extraction tuning and beam losstuning and beam loss
It’s a “Ripple extraction” using SX systemIt’s a “Ripple extraction” using SX systemWe need;We need;
further improvement of magnet power supplyfurther improvement of magnet power supplyinstallation of feedback systeminstallation of feedback system
StepsSteps
Tadashi Koseki for ATAC09Tadashi Koseki for ATAC09
Beam loss study for SXBeam loss study for SX
Injection
Extraction
•• (1/6) Hz Test Operation(1/6) Hz Test Operation•• BLM : Max. 2500 Counts / Position BLM : Max. 2500 Counts / Position --------> 2.0E9 protons> 2.0E9 protons•• 17000 Counts / Total 1.4E10 17000 Counts / Total 1.4E10 •• Accelerated : 1.3E11 protons/6 sec (100 W)Accelerated : 1.3E11 protons/6 sec (100 W)•• Extraction Efficiency : ~ 90 %Extraction Efficiency : ~ 90 %•• Max. ~ 1.6 W Loss @ Each PositionMax. ~ 1.6 W Loss @ Each Position•• ===> Residual : 23 ===> Residual : 23 µµSvSv/h Max. /h Max. •• < 1 < 1 mSvmSv/h /h
•• < 70 W (Loss/SX area)< 70 W (Loss/SX area)
0
1
2
3
4
5
6
7
8
0 20000 40000 60000 80000 100000
Calibration of Beam Loss Monitor@ 30 GeV Slow Extraction / 2009. 02. 14
No.
of L
ost P
roto
ns (x
1.0
E10)
Count of Beam Loss Monitor
y = a*(Count)Value
8.0515e-5a0.98109R
Calibration of Beam Loss & Residual Radiation Level @ 30Calibration of Beam Loss & Residual Radiation Level @ 30 GeVGeVResonance ExtractionResonance Extraction
Tadashi Koseki for ATAC09Tadashi Koseki for ATAC09
GuideGuide--line for allowable beam loss line for allowable beam loss at this momentat this momentupper limit < 25W/SX Areaupper limit < 25W/SX Area
& ALARA (& ALARA (AAs s LLow ow AAs s RReasonably easonably AAchievable)chievable)
Radiation Maintenance @ ISISRadiation Maintenance @ ISISFebruary 2009:February 2009:100W/10W loss 100W/10W loss 90% extraction eff.90% extraction eff.
250W/25W loss250W/25W loss
Extraction Efficiency should be upgradedExtraction Efficiency should be upgradedto obtain higher beam powerto obtain higher beam power500W/25W loss 500W/25W loss 95% (BNL Achievement)95% (BNL Achievement)2.5kW/25W loss 2.5kW/25W loss 99%99%~10kW will be coming within the range~10kW will be coming within the range
Only way to achieve the beam power of 100kWOnly way to achieve the beam power of 100kW--class SX,class SX,1.1. improve the extraction efficiency more and more,improve the extraction efficiency more and more,2.2. beam loss should be localized at the ESS and 2beam loss should be localized at the ESS and 2ndnd collimator, andcollimator, and3.3. radiation maintenance technology should be developed.radiation maintenance technology should be developed.
333333µµSv/hSv/h
25W loss25W loss
Plan of MR 100 kW trial in FY2009Plan of MR 100 kW trial in FY20091st Quarter: April, May, June1st Quarter: April, May, June
Fast extraction: establish neutrino primary beam line orbitFast extraction: establish neutrino primary beam line orbitHadron hall: Construction of secondary beam lines Hadron hall: Construction of secondary beam lines
2nd Quarter: July, August, September 2nd Quarter: July, August, September -- Machine ShutdownMachine ShutdownInstallation of EQ and RQ for spill controlInstallation of EQ and RQ for spill controlMaintenance and/or upgrade of troubled componentsMaintenance and/or upgrade of troubled componentsNeutrino Target Station (Installation of horn #2&3 fromNeutrino Target Station (Installation of horn #2&3 from julyjuly))
3rd Quarter: October, November, December3rd Quarter: October, November, DecemberFX: Power upgradeFX: Power upgradeSX: Spill control and power upgrade by reducing beam lossSX: Spill control and power upgrade by reducing beam loss
4th Quarter: January, February, March4th Quarter: January, February, MarchFX : Power upgrade toward 100 kW (for 10FX : Power upgrade toward 100 kW (for 1077 sec)sec)
EQ: Extraction Q to shape up the spill time structure, EQ: Extraction Q to shape up the spill time structure, RQ: Ripple Q to reduce ripple structureRQ: Ripple Q to reduce ripple structure
RFQ problemRFQ problemKazuo Hasegawa for ATAC09Kazuo Hasegawa for ATAC09
PISL:PISL:PiPi--modemodeSStabilizingtabilizingLLoopoop
RFQRFQ
Ion sourceIon source
Kazuo Hasegawa for ATAC09Kazuo Hasegawa for ATAC09
Prototype RFQ (same design)Prototype RFQ (same design)
multipactingmultipacting
Kazuo Hasegawa for ATAC09Kazuo Hasegawa for ATAC09
Beam centerBeam centerVaneVane
VaneVane
Kazuo Hasegawa for ATAC09Kazuo Hasegawa for ATAC09
MR magnet power supply problemsMR magnet power supply problems
Direct frequency conversion Direct frequency conversion from 22kV commercial AC line from 22kV commercial AC line using IGBT/IEGT switching unitusing IGBT/IEGT switching unit
Normal modeNormal modereactorreactor Passive filterPassive filter Active filterActive filter
CatchCatch--phrasephraseof the ambitiousof the ambitiousdesign:design:
CompactCompactHighHigh--efficiencyefficiencyPower factor=1Power factor=1Low noiseLow noise
Risks:Risks:Large switching noise from IGBTLarge switching noise from IGBT
delicate controldelicate control low repetition ratelow repetition rateFragile IGBTFragile IGBT poor availabilitypoor availability
No neutral line (point)No neutral line (point)No symmetric circuitNo symmetric circuit
large common mode large common mode noisenoise rippleripple
Current status;Current status;Ripple, low repetition rate and poor availabilityRipple, low repetition rate and poor availability
Not established technology but world first challengeNot established technology but world first challenge
Ultimate goal of the repetition rate Ultimate goal of the repetition rate 0.5Hz0.5Hz
How to solve problems?How to solve problems?
Add more filter and choke both for Add more filter and choke both for normal and common modesnormal and common modes
reduce ripple from 10reduce ripple from 10--44 to 10to 10--55~10~10--66
and recover better controland recover better controlRemodel (improve) for symmetric circuitRemodel (improve) for symmetric circuit
not only for power cable configurationnot only for power cable configurationbut also circuit itselfbut also circuit itself
0
200
400
600
800
-1 0 1 2 3 4
Ideal circuit by Hiroshi TokiIdeal circuit by Hiroshi Toki(Osaka Univ.)(Osaka Univ.)
Scenario beyond 100kWScenario beyond 100kW100100 750kW(Design)750kW(Design)
Main issue is the Space Charge EffectMain issue is the Space Charge EffectWe have only three knobs for this problem;We have only three knobs for this problem;
Collimator scenario to cut beam halloCollimator scenario to cut beam halloEnough apertureEnough apertureBunching factor Bunching factor
(RF fundamental(RF fundamental--modemode+Higher Harmonic cavities)+Higher Harmonic cavities)
Another parameter, which isAnother parameter, which isindependent from spaceindependent from spacecharge effectcharge effect
increase increase repetition raterepetition rate(magnet power supply issue)(magnet power supply issue)
Receive beam from RCS as much Receive beam from RCS as much as possible, andas possible, and
Accelerate and extract the beam Accelerate and extract the beam with minimum loss as quick aswith minimum loss as quick aspossible.possible.
Current bottleneckCurrent bottleneckPoor collimator capacityPoor collimator capacity
450W450WSmall fast extraction Small fast extraction apertureaperture
Rely on the adiabatic Rely on the adiabatic Damping at RCS and Damping at RCS and
MR @50 GeVMR @50 GeV
Emittance ~ (Emittance ~ (βγβγ))--11
Detuning effect of the low energyspace chargespace charge for J-PARC Main Ring
‘Bare’ working point:Qx0 = 22.428Qy0 = 20.824
Bunching factor ~ 0.2Chamber size = ± 70 mm
Beam power = 1.8kW/bunch(300kW from RCS)
Beam power = 3.6kW/bunch(600kW from RCS)
ORBIT_MPI
30% of design value30% of design value 60% of design value60% of design value
By Alexander MolodojentsevBy Alexander Molodojentsev
Power of LOST beam: wp2 / MRS=54pi
010
20304050
607080
90100
0 5000 10000 15000 20000
Number of Turns
Pow
er o
f LO
ST b
eam
[W]
Particle losses during the full injection process(~120 msec) for the realistic machine parametersfor the beam power of 1.8kW/bunch. (30% of design value)
The MR scraper acceptance is 54 πmm.mrad.Wp#2: 22.30 / 20.92 to avoid 3Qx resonance.VRF = 40kV (fundamental harmonic)
85W/bunch
Estimation of the lost beam power at MR scraper (wp#2)
~ 440 MR_Scr = 60πTR_MisMatched
~ 850MR_Scr = 54πTR_MisMatched
~ 128MR_Scr = 60πTR_matched
~ 400MR_Scr = 54πTR matched
Lost beam power [W]
Machine condition
• 4 batches operation (h=9)• TR_MisMatched -> 10% 10% beta-mismatching
ORBIT_MPI
By Alexander By Alexander MolodojentsevMolodojentsev
Particle losses during the injection process @ scraperParticle losses during the injection process @ scraper
Power of LOST beam
0
5
10
15
20
0 5000 10000 15000 20000 25000
Number of Turns
Pow
er o
f LO
ST b
eam
[Wat
t]
~ 17W/bunch
~ 120 msec
50 100 150 200 250200
300
400
500
600
700
800
900Normalized Acceptance (40GeV) of Fast Extraction Septum
99.9%_NORM_H 99.9%_NORM_V
Nor
m_E
mitt
ance
[pi.m
m.m
rad]
Time [msec]
3 GeV 7.008 GeVParticle losses during the accelerationfor the RF pattern (40kV -> 280kV).MR_Scraper acceptance = 60 πInitial mis-matched beam (10% beta mismatching).
Estimation of the 99.9% emittance after acceleration
Wkin=40GeV (βγ=43.62):εNORM (MAX) ~ 400π.
Then ε99.9% for 40GeV beam ~ 9.2 π
ORBIT_MPI
By Alexander By Alexander MolodojentsevMolodojentsevParticle losses during the acceleration processParticle losses during the acceleration process
Emittance Emittance is growing up to 7 is growing up to 7 GeV GeV and loss is increasingand loss is increasing
30 30 GeV GeV acceptanceacceptance
33--50BT Collimator section is 50BT Collimator section is located under the public roadlocated under the public road“HAKKEN DORO” “HAKKEN DORO” (between the Shrine and (between the Shrine and sea shore)sea shore)
<0.42<0.42µµSv/hSv/h
DistributionDistributionof neutronof neutron
Our baseline scenario to solve the collimator Our baseline scenario to solve the collimator problem problem develop 5 kWdevelop 5 kW--class collimators and class collimators and replace them as early as possiblereplace them as early as possible
22ndnd generation fast extraction devices should be developedgeneration fast extraction devices should be developedand several Qand several Q--magnet aperture should be improved magnet aperture should be improved to obtain enough aperture to obtain enough aperture at 30 at 30 GeVGeV
OriginalDesign
NewDesign
Ratio
MR energy (GeV) 50 30 0.6RCS power (kW) 1000 500 0.5RCS bunch current 1 2 2MR repetition rate 0.275 0.5 1.8Total 1.08
Scenario to achieve the design beam power (750kW) @ 30 Scenario to achieve the design beam power (750kW) @ 30 GeVGeV
In order to increase the RCS bunch current,In order to increase the RCS bunch current,RCS harmonic number should be 1 instead of 2RCS harmonic number should be 1 instead of 2
Risks;Risks;RCS cycle for MR injection: 120 RCS cycle for MR injection: 120 240msec240msecSpace charge force increasesSpace charge force increases
Necessary baseline condition;Necessary baseline condition;New collimator of 5kWNew collimator of 5kW--class capabilityclass capabilityEnough apertureEnough aperture
LongLong--term plan term plan toward MWtoward MW--classclass
power frontierpower frontierKEK roadmapKEK roadmap
2007 2008 2009 2010 2011 2012
KEKB : 1 (ab)-1
ILC R&D EDR
Photon Factory & upgradeoperation
LHC1st resultsoperation
J-PARCconstruction
ERL R&D
KEK RoadmapKEK Roadmap (July, 2007 : KEK Roadmap Panel led by F. Takasaki)(July, 2007 : KEK Roadmap Panel led by F. Takasaki)
operation & completion of 1st goal
power upgrade
upgrading to Super-KEKB
continue R&D and compact ERL
LHC upgrade
operation
continue R&D
DG DG Atsuto Atsuto SuzukiSuzuki
RF system improvement
0.60MW0.28 Hz
1.66MW0.52 Hz
BM power supply
0.91 MW0.57 Hz
•• Shorten acceleration time Shorten acceleration time •• More RF systemMore RF system•• Magnet power systemMagnet power system
•• More beam per pulseMore beam per pulse•• Operation of 3 Operation of 3 GeVGeV RCSRCS
in harmonic number =1in harmonic number =1
LinacLinac : 181 : 181 MeVMeV to 400 to 400 MeVMeV
DG DG Atsuto Atsuto SuzukiSuzuki
OriginalDesign
NewDesign
Ratio
MR energy (GeV) 50 30 0.6RCS power (kW) 1000 500 0.5RCS bunch current 1 2 2MR repetition rate 0.275 0.5 1.8Total 1.08
If we can receive more RCS beam power than 500 kW,If we can receive more RCS beam power than 500 kW,we can obtain higher power than 750 kW.we can obtain higher power than 750 kW.
Extensive studies are necessary;Extensive studies are necessary;Increase MR repetition rate,Increase MR repetition rate,Understand space charge effect,Understand space charge effect,Develop collimator and aperture scenario. Develop collimator and aperture scenario.
SummarySummary
NeutrinoNeutrino1.1. Early achievement of 100kW run (for 10Early achievement of 100kW run (for 1077 sec)sec)2.2. Create strong team to consider and work for the power upgrade scCreate strong team to consider and work for the power upgrade scenario enario
from 100 to 750kW.from 100 to 750kW.3.3. The above second step should be the base of the MWThe above second step should be the base of the MW--class power frontier machine. class power frontier machine.
HadronHadron1.1. Early realization of spill control by;Early realization of spill control by;
1.1. improving magnet power supplies, andimproving magnet power supplies, and2.2. applying feedback system.applying feedback system.
2.2. Early achievement of 10kWEarly achievement of 10kW--class power by;class power by;1.1. understanding and suppressing and/or localizing the beam loss. understanding and suppressing and/or localizing the beam loss.
3.3. In order to realize 100kWIn order to realize 100kW--class slow beam extraction, we have to develop;class slow beam extraction, we have to develop;1.1. excellent extraction efficiency,excellent extraction efficiency,2.2. more beam loss control, andmore beam loss control, and3.3. radiation maintenance technology. radiation maintenance technology.
Backup slidesBackup slides
Date Beam Condition Required items
2008.122008.12-- 20 kW; 5mA/0.1ms/560ns20 kW; 5mA/0.1ms/560ns
2009.052009.05-- 2020--100 kW100 kW-- 100kW; 100kW;
15mA/0.17ms/560ns15mA/0.17ms/560ns
・・Reduction of injection lossReduction of injection loss
2010.102010.10-- 5050--200 kW200 kW-- 100kW : 5100kW : 5--15mA/0.5015mA/0.50--
0.17ms/560ns0.17ms/560ns-- 200kW : 200kW :
10mA/0.50ms/560ns10mA/0.50ms/560ns
・・Cure for foilCure for foil--scattering lossscattering loss・・AC power supply for chromatic correction AC power supply for chromatic correction sextupolessextupoles・・11 sets of RF cavities 11 sets of RF cavities ・・New RFQNew RFQ
20112011-- 100100--300 kW300 kW-- 300kW; 300kW;
15mA/0.50ms/560ns15mA/0.50ms/560ns
・・12 sets of RF cavities12 sets of RF cavities
20132013-- 100100--300 kW300 kW ・・300 300 MeVMeV injection (injection (EEinjinj=300 =300 MeV MeV ((ββ22γγ33))300300/(β/(β22γγ33))181181=1.94)=1.94)
20142014-- 200200--300 kW300 kW
20152015-- 200200--500 kW500 kW-- 500kW; 500kW;
25mA/0.5ms/560ns25mA/0.5ms/560ns
・・400 400 MeVMeV injection (injection (EEinjinj=400 =400 MeV MeV ((ββ22γγ33))400400/(β/(β22γγ33))181181=2.92)=2.92)・・RCS injection system for 400 RCS injection system for 400 MeV MeV
--injection bump, paint bump, and injection bump, paint bump, and ……
Issues for RCS power upgradeIssues for RCS power upgrade
Tadashi Koseki for ATAC09Tadashi Koseki for ATAC09
20% of normal width due to RFQ problem20% of normal width due to RFQ problem
Design repetition is 3.64 secDesign repetition is 3.64 sec
Simultaneously operationSimultaneously operationwith MLFwith MLF
6 second cycle due to6 second cycle due tomagnet power supplymagnet power supplyproblemproblem
Tadashi Koseki for ATAC09Tadashi Koseki for ATAC09
April 2008April 2008
September 2008September 2008
Improvement of BM Power Supply: BL ripple was improved drastically by adoptingsymmetrical power cable configuration between the power supply and the magnet
Frequency (Hz)Frequency (Hz) Frequency (Hz)Frequency (Hz)
Serious problems of MR magnet power Serious problems of MR magnet power Supply were found.Supply were found.
The half year operation of quick and The half year operation of quick and “crazy” work has been carried out !“crazy” work has been carried out !Improvement of Improvement of Power supply itself, andPower supply itself, andPower cable configurationPower cable configuration
BLBL
Current rippleCurrent rippleDrastic improvementDrastic improvement
DetailsDetails see previous PAC talk by A. Andosee previous PAC talk by A. Ando
Tadashi Koseki for ATAC09Tadashi Koseki for ATAC09
ImprovementImprovementof ripple problem of ripple problem
Tadashi Koseki for ATAC09Tadashi Koseki for ATAC09
1. Acceleration and fast extraction1. Acceleration and fast extraction
2. Slow extraction2. Slow extraction
3. Government inspection3. Government inspection
Horizontal and Horizontal and VerticalVertical COD COD CorrectionCorrection
ImprovementImprovementof ripple problem of ripple problem
MayMay
Kazuo Hasegawa for ATAC09Kazuo Hasegawa for ATAC09