22
Grid Operations and Planning Report Kent Saathoff Board of Directors Meeting Board of Directors Meeting October 18, 2011

Item 04e - Grid Operations and Planning Report · 2014. 6. 23. · September 2011: Generic Transmission Limits (GTLs) GTLs Sep 10 Days CSC Jul 11 Days GTLs Aug 11 Days GTLs Sep 11

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

  • Grid Operations and Planning Report

    Kent Saathoff

    Board of Directors MeetingBoard of Directors MeetingOctober 18, 2011

  • Content

    • SummarySummary

    • September 2011 Operations– Peak Demand: Actual vs. Forecast

    On-line Resources: Total at Peak and Wind– CPS1 Monthly Performance– Historical Peak and Minimum Loads– Day-Ahead Load Forecast PerformanceDay Ahead Load Forecast Performance– Reliability Unit Commitment Capacity (RUC) by weather zone – Generic Transmission Limits (GTLs)– Advisories, Watches and EEAs

    Si ifi t S t I id t– Significant System Incidents

    • Planning Activities– Summary– Generation Interconnection Requests– Wind Capacity– Reliability Must Run Generation Update– Gas Curtailment Risk Study Update

    2

    – Drought Effect on Generation

    October 18, 2011 ERCOT Public

  • Summary

    • September 2011 OperationsSeptember 2011 Operations– The peak demand of 63,160 MW on September 03 was more than the mid-term

    forecast peak of 61,915 MW and more than the September 2010 actual peak demand of 58,201 MW.

    – Day-ahead load forecast error for September was 2.70%– Advisory for Physical Responsive Capability (PRC) below 3000 MW issued 19

    days– No Watches for PRC under 2500 MW issuedo atc es o C u de 500 ssued– No Energy Emergency Alert (EEA) events issued

    • Planning Activities– 185 active generation interconnect requests totaling over 59,000 MW as

    of September 30, 2011. Five fewer requests and 1,000 MW less than August 31, 2011.9 400 MW i d it li S t b 30 2011 N h f– 9,400 MW wind capacity on line September 30, 2011. No change from August 31, 2011

    – Determined Greens Bayou 5 not needed for RMR service

    3 ERCOT PublicOctober 18, 2011

  • September 2011 Daily Peak Demand: Hourly Average Actual vs. Forecast, Wind Day-Ahead COPs & On-line Capacity at Peak

    80,000 Actual Peak LoadA t l O li C it

    70,000

    Actual Online CapacityActual Wind OutputERCOT Load Day-Ahead ForecastWind Day-Ahead COPs

    Peak Demand for the Month: 63,135 MW @ 09/02/11 HE17:00

    50,000

    60,000

    40,000

    MW

    20,000

    30,000

    10,000

    4

    Note: All data are hourly averages during the peak load hour obtained from COPs, and EMMS.ERCOT PublicOctober 18, 2011

    0

  • September 2011: Actual Wind Output plus Curtailments vs. Wind Day-Ahead COPs for All Hours

    5000

    % of Hours when Estimated Uncurtailed Wind Output >= COP HSLs (Target = 50%)

    45%

    4000

    4500

    3000

    3500

    2000

    2500MW

    500

    1000

    1500

    0

    500

    Operating Day

    5

    Note: QSEs must use the AWST 50% probability of exceedance forecast as the HSL in their COPs

    ERCOT PublicOctober 18, 2011

    Daily Averaged Aggregated Wind Output Estimated Wind Curtailment Daily Averaged Day‐Ahead COP HSL

  • September 2011 ERCOT’s CPS1 Monthly Performance

    170170

    160

    170

    160

    170CPS1 12 Month Rolling Average = 146.88%

    140

    150

    140

    150

    vera

    ge

    130130CPS

    1 Av

    110

    120

    110

    120

    100100

    6 ERCOT PublicOctober 18, 2011

    Monthly Average 12 Month Rolling Average

  • September 2011: Monthly Peak Actual Demand

    80,000

    70,000

    20102011

    Peak Demand is Peak Interval Demand

    50,000

    60,000

    MW

    30,000

    40,000 MW

    10 000

    20,000

    -

    10,000

    7 ERCOT PublicOctober 18, 2011

    Month

  • September 2011: Monthly Minimum Actual Demand

    40,000

    35,000

    40,000 2010

    2011Minimum Demand is Valley Interval Demand

    25,000

    30,000

    15,000

    20,000 MW

    10,000

    -

    5,000

    8 ERCOT PublicOctober 18, 2011

    Month

  • Day-Ahead Load Forecast Performance in September 2011

    Mean Absolute Percent Error (MAPE) for ERCOT Mid-Term Load Forecast (MTLF) Run at 14:00 Day Ahead

    2008MAPE

    2009MAPE

    2010MAPE

    2011MAPE

    September 2011MAPE

    AverageAnnual 3.30 3.11 2.83 2.68 2.70MAPE

    LowestMonthly MAPE

    2.45 1.93 2.24 1.63LowestDailyMAPE

    0.70Sep – 15

    HighestMonthly MAPE

    4.99 4.11 3.79 3.55

    Highest DailyMAPE

    7.74Sep – 30

    9 ERCOT PublicOctober 18, 2011

  • Reliability Unit Commitment (RUC) Capacity by weather zone in September 2011

    RUCCommitments byWeather Zone

    25

    30

    RUC Commitments by Weather Zone

    Unit-Days RUC Total Days

    20

    25

    25

    15

    Days

    16

    13

    5

    10

    6

    2

    8

    24

    2 3

    0COAST EAST NORTH CENTRAL SOUTH SOUTH CENTRAL

    10 ERCOT PublicOctober 18, 2011

    Weather Zone

  • September 2011: Generic Transmission Limits (GTLs)

    GTLsSep 10DaysCSC

    Jul 11DaysGTLs

    Aug 11DaysGTLs

    Sep 11DaysGTLs

    Last 12 Months

    Total Days (Aug 10 Aug 11)(Aug 10 – Aug 11)

    North – Houston 8 0 0 0 32

    West – North 15 4 2 11Sep–(4,5,14,15,17,18,22,24,25,2

    9, 30)

    259

    GTL: A transmission flow limit more constraining than a Transmission Element’s normal limit t bli h d t t i fl b t hi f th ERCOT T i i S t th t i

    Valley Import 0 0 0 0 15

    established to constrain flow between geographic areas of the ERCOT Transmission System that is used to enforce stability and voltage constraints that cannot be modeled directly in ERCOT’s transmission security analysis applications.

    Note: This table lists how many times a constraint has been activated to avoid exceeding a GTL limit, it does

    11

    not imply an exceedance of the GTL occurred.

    ERCOT PublicOctober 18, 2011

  • Advisories and Watches in September 2011

    • Advisories issued for Physical Responsive Capability (PRC) below 3000 MW.– Issued 19 Days

    • Watches issued for Physical Responsive Capability (PRC) below 2500 MW.– None

    • Transmission Watches– None

    • Energy Emergency Alerts– None

    12 ERCOT PublicOctober 18, 2011

  • Significant System Incidents in September 2011

    • September 4 9• September 4-9– Wildfires impacted two 345KV lines, sixteen 138KV lines, three 69KV

    lines and two generating stations in the Bastrop area. All lines back in ser ice b September 18in service by September 18.

    – Two 345 KV lines from Jewett to Zenith impacted by a separate wildfire. Back in service by September 9.

    – No significant reliability issues caused by the outages

    13 ERCOT PublicOctober 18, 2011

  • Planning Summary

    • 185 generation interconnection request studies totaling over 59,000 MW are ongoing. This includes almost 34,000 MW of wind generation.wind generation.

    • ERCOT is currently reviewing proposed transmission improvements with a total cost of $117.9 Million

    • Transmission Projects endorsed in 2011 total $579 9 Million• Transmission Projects endorsed in 2011 total $579.9 Million• All projects (in engineering, routing, licensing and

    construction) total approximately $9.8 BillionTransmission Projects energized in 2011 total $694 8 million• Transmission Projects energized in 2011 total $694.8 million

    14October 18, 2011 ERCOT Public

  • County Location of Planned Generation with Interconnection Requests (all fuels) September 2011

    15October 18, 2011 ERCOT Public

  • County Location of Planned Generation with Interconnection Requests (Wind) September 2011

    16October 18, 2011 ERCOT Public

  • Wind Generation

    1,553 1,755 1,755

    9 4009,700 

    10,953 11,155  11,155 

    10,000

    12,000

    MWCumulative MW Installed

    Cumulative Planned (Signed Interconnection Agreement)

    300

    8,005 

    8,916 

    9,400 

    8,000

    ERCOT Wind Installations by Year  (as of September 30, 2011)The data presented here is based upon the latest registration data provided to 

    4,785 

    6,000

    g pERCOT by the resource owners and can change without notice.  Any capacity changes will be reflected in current and subsequent years' totals.   Scheduling delays will also be reflected in the planned projects as that information is received.

    1,854

    2,875 

    2 000

    4,000This chart now reflects planned units in calendar year of installation rather than installation by peak of year shown

    116 

    816  977 1,173 

    1,385 1,854 

    0

    2,000

    17

    2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014

    October 18, 2011 ERCOT Public

  • Generation Interconnection Activity by Fuel

    MW Natural Gas MW Nuclear MW Coal MW Wind MW Solar *

    300120,000

    MW Natural Gas MW Nuclear MW Coal MW Wind MW Solar

    MW Biomass * MW Other Total # Projects # Projects Cancelled

    * Prior to September 2008, Category "Other" included "Solar" and "Biomass"Projects in all phases of interconnection study are reflected in this graphProject cancellation tracking by month began in March 2008

    200

    250

    80,000

    100,000

    15060,000

    Proj

    ect C

    ount

    MW

    Cap

    acity

    50

    100

    20,000

    40,000

    00

    Jan-

    06Fe

    b-06

    Mar

    -06

    Apr

    -06

    May

    -06

    Jun-

    06Ju

    l-06

    Au g

    -06

    Se p

    -06

    Oct

    -06

    Nov

    -06

    Dec

    -06

    Jan-

    07Fe

    b-07

    Mar

    -07

    Apr

    -07

    Ma y

    -07

    Jun-

    07Ju

    l-07

    Au g

    -07

    Se p

    -07

    Oct

    -07

    Nov

    -07

    Dec

    -07

    Jan-

    08Fe

    b-08

    Mar

    -08

    Apr

    -08

    Ma y

    -08

    Jun-

    08Ju

    l-08

    Au g

    -08

    Se p

    -08

    Oct

    -08

    Nov

    -08

    Dec

    -08

    Jan-

    09Fe

    b-09

    Mar

    -09

    Apr

    -09

    Ma y

    -09

    Jun-

    09Ju

    l-09

    Au g

    -09

    Sep

    -09

    Oct

    -09

    Nov

    -09

    Dec

    -09

    Jan-

    10Fe

    b-10

    Mar

    -10

    Apr

    -10

    May

    -10

    Jun-

    10Ju

    l-10

    Au g

    -10

    Se p

    -10

    Oct

    -10

    Nov

    -10

    Dec

    -10

    Jan-

    11Fe

    b-11

    Mar

    -11

    Apr

    -11

    Ma y

    -11

    Jun-

    11Ju

    l-11

    Au g

    -11

    Se p

    -11

    18October 18, 2011 ERCOT Public

  • Generation Interconnection Activity by Project Phase

    # In-Service ** # Signed Interconnect Agreement # Projects Cancelled ***

    120,000

    350

    400

    # Completed Full Study # in Full Study # Screening Study Complete

    # Initial Screening Study MW Capacity Under Study * MW In Commercial Operation **

    * Nameplate capacity will change across time due to additional projects, cancellations, expirations, adjustments from study results, and projects being placed in service.

    80,000

    100,000

    250

    300

    350** Having begun commercial operation since January 2006

    *** Began tracking cancellations by month in March 2008

    60,000200

    250

    MW

    Cap

    acity

    Proj

    ect C

    ount

    20,000

    40,000

    100

    150

    MP

    0

    ,

    0

    50

    an-0

    6eb

    -06

    Mar

    -06

    Apr

    -06

    ay-0

    6un

    -06

    Jul-0

    6ug

    -06

    ep-0

    6O

    ct-0

    6ov

    -06

    ec-0

    6an

    -07

    eb-0

    7M

    ar-0

    7A

    pr-0

    7ay

    -07

    un-0

    7Ju

    l-07

    ug-0

    7ep

    -07

    Oct

    -07

    ov-0

    7ec

    -07

    an-0

    8eb

    -08

    Mar

    -08

    Apr

    -08

    ay-0

    8un

    -08

    Jul-0

    8ug

    -08

    ep-0

    8O

    ct-0

    8ov

    -08

    ec-0

    8an

    -09

    eb-0

    9M

    ar-0

    9A

    pr-0

    9ay

    -09

    un-0

    9Ju

    l-09

    ug-0

    9ep

    -09

    Oct

    -09

    ov-0

    9ec

    -09

    an-1

    0eb

    -10

    Mar

    -10

    Apr

    -10

    ay-1

    0un

    -10

    Jul-1

    0ug

    -10

    ep-1

    0O

    ct-1

    0ov

    -10

    ec-1

    0an

    -11

    eb-1

    1M

    ar-1

    1A

    pr-1

    1ay

    -11

    un-1

    1Ju

    l-11

    ug-1

    1ep

    -11

    19

    Ja Fe M A Ma Ju J Au

    Se O No

    D Ja

    Fe M A Ma Ju J Au

    Se O No

    D Ja

    Fe M A Ma Ju J Au

    Se O No

    D Ja

    Fe M A Ma Ju J Au

    Se O No

    D Ja

    Fe M A Ma Ju J Au

    Se O No

    D Ja

    Fe M A Ma Ju J Au

    Se

    October 18, 2011 ERCOT Public

  • Reliability Must Run Update

    • Greens Bayou 5

    – ERCOT re-evaluated the need to enter into a RMR contract with Greens B 5 (GBY 5)Bayou 5 (GBY 5)

    – GBY 5 assists in resolving the Garrott to Midtown 138 kV overload which tends to occur during shoulder monthsg

    – Determined that other generators can reasonably resolve the constraint until the transmission improvement to remove the constraint is completed in the first quarter of 2012completed in the first quarter of 2012

    – GBY 5 put in mothball status on October 1, 2011

    • Spencer 4 and 5 and SR Bertron 2Spencer 4 and 5 and SR Bertron 2

    – Contracted with owners to return from mothball status the end of August

    Contracts expire October 31 2011

    20

    – Contracts expire October 31, 2011

    October 18, 2011 ERCOT Public

  • Status Update on Gas Curtailment Risk Study

    • Project Managementoject a age e t– Contracting completed on 9/23/2011– Project kick-off meeting on 9/26/11

    • Data Gathering & Analysis• Data Gathering & Analysis– Survey to electric generators sent on 9/20/2011 and 9/28/2011

    • Responses being collected; deadline is 10/07/2011– Additional data requests to ERCOT and RRC underway– Research and analysis of curtailments from 3rd party sources is

    ongoing• Next Steps:

    – Compile information from remaining surveys– Complete database of Historical CurtailmentsComplete database of Historical Curtailments– Complete database of Gas Infrastructure– Analysis of risk of curtailment in defined scenarios

    Results expected January 2012

    21 ERCOT PublicOctober 18, 2011

    • Results expected January 2012

  • Drought Effect on Generation

    • ERCOT has been periodically surveying generators during and since the summer to monitor the effect of drought on generation availability

    • Based on most recent survey:y– Current unavailability due to drought is only 24 MW– If East Texas receives only half of it’s normal winter/spring rainfall,

    unavailability could go up to 434 MW by May– If no significant rainfall received, unavailability is estimated to be as

    much as 3,044 MW by May– Approximately 9,000 MW is dependent on water rights from sources at

    hi i ll l l lhistorically low levels• Mitigation actions being taken:

    – Building of pipelines to remote water sources– Procuring additional water rights– Adding pumping capability

    • ERCOT will continue to monitor the situation as long as the drought i t

    22

    exists

    ERCOT PublicOctober 18, 2011