Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
IT&C Safety Planning Update
Planning the work to minimize hazards
• IT&C has undergone a third major revision
M1 assy area clear
TMA accepted
Science verification
Initial alignment
M1, M1 cell
Transfer optics coudé
VBI
WFC
TEOA
Transfer optics OSS
DL NIRSP
Cryo-NIRSP
VTF
VISP
FLIOperationalAcceptance
Instrument lab ready
Coudé ready
TEOA pre-assembly
M1 coating prep
M1 Cell pre-assembly
M1 coating
Transfer optics pre-assembly
WFC pre-assembly
AEOS coating lab available
VBI pre-assembly
VISP pre-assembly
VTF pre-assembly
Cryo-NIRSP pre-assembly
DL NIRSP pre-assembly
Non-Critical ActivitiesNon-Critical Activities
Critical Path ActivitiesCritical Path Activities
ATST IT&C Schedule OverviewATST IT&C Schedule Overview
Lower GOS + enclosure install
Upper GOS install
1/1/2017 6/30/2019
4/1/2017 7/1/2017 10/1/2017 1/1/2018 4/1/2018 7/1/2018 10/1/2018 1/1/2019 4/1/2019
Critical Path
Non-Critical Path
Planning the work to minimize hazards
• IT&C has undergone a third major revision
• Level of fidelity in schedule 1-2 week duration
Network Diagram
Currently populated through to FLI December 2018
Sample of Network Diagram
IT&C “Activity Planner” (Work Definition Sheet)
Sample of Network Diagram
Work Definition Part One – General Information
WORK DEFINITION SHEET
WBS Ref: 7.1.2.4.1.6 ISSUE:
Date:
SHEET:
of
WBS Title: IT&C - M1 Assembly
WBS Subordinate To: Telescope IT&C WBS Ref: 7.1.2.4.1
Start Event: M1 CS to TCS integration and testing and rework
WBS Ref: ITC0130
End Event: Calibrate & tune temperature control system
WBS Ref: ITC0170
Work Package Manager:
Organisation Responsible:
ATST
Special Requirements:
Sub-System Status: Specialists: Test/Special Equipment: Handling equip
Enclosure operational Systems PFWFS M1 cell cart
TMA accepted Optics Laser tracker M1 lifter
M1 assembly accepted
Telescope operator
WBS Inputs:
ITC0130 M1 CS to TCS integration and testing and rework
ITC0175 Transport M1 Coated Mirror to ATST
Work Definition Part II – Detailed Work Breakdown
Sub WBS: Description: Safety P/E/n Specialists Equipment Duration
ITC0135 Install M1 assembly into telescope P
M1 cell cart, Laser tracker
ITC0140 Functional test M1 n Laser
tracker
ITC0142
Exchange the M1 Coated Mirror with Dummy Mirror
P/E M1 cell cart, M1 lifter, Laser tracker
ITC0145 Install PFWFS on parent axis P/E PFWFS
ITC0150 Align M1 with respect to PFWFS n PFWFS
ITC0155
Determine optimal M1Z position (night)
n
ITC0160
Check actuator force to figure matrix (night)
n
ITC0165
Create first elevation-figure table (night)
n
ITC0170
Calibrate & tune temperature control system
n
WBS Outputs:
ITC0180 M1 Mirror Integration Complete
Safety: Personnel Equipment ITC0135 Pinch, overhead load None (Dummy mirror)
ITC0142 Pinch, overhead load M1 handling
ITC0145 Working at prime focus PFWFS handling
Hazard Analysis & JHA
Special Circumstances and Risks during IT&C
• More people on site during IT&C than during routine operations. • Pressure to work in parallel to maintain schedule. • Reduced time to complete to maintain schedule. • Many complex activities will be performed for the very first time. • There will be personnel in hazardous areas while systems are energized
and operating. • There will be personnel in hazardous areas while interlocks are disabled. • There will be nighttime work that will need to be performed at very low
light levels, sometimes in precarious positions. • There will be personnel within the telescope enclosure and in close
proximity to the light beam when we are pointing at the sun. While many of these activities are not unique to IT&C, the frequency of exposure to these risks will be highest during IT&C.
Access to Hazardous Areas
• During normal routine observing in the operations phase, access can be controlled and interlocked.
• During ITC many hazardous areas will need to be accessed under a variety of non-optimum conditions.
Safety Mitigation during IT&C
• Detailed planning and scheduling of activities. – Identifying hazardous conditions
• Work prioritization – Close control and coordination of multiple activities.
• Personnel arrival – Briefing
• Absorb best practice from site construction
• Dedicated safety monitoring by IT&C management safety personnel.
Safety Mitigation during IT&C
• Work prioritization
– Close control and coordination of multiple activities.
• Quarterly, Monthly planning meetings
• Weekly briefing – overall activities,
– Hot work permitting
– hazards (who, what, how, when, where? JHAs)
– overall priorities
• Weekly debriefing – What’s planned for next week
Safety Mitigation during IT&C
• Personnel arrival
– Check in with site manager immediately on arrival (or IT&C manager later in the schedule)
– Sign-in/out board (electronic scanning?)
– Must attend daily site briefing before commencement of activities.
• Sign-off sheet
Safety Mitigation during IT&C
• Daily Site briefing. – Close control and coordination of multiple
activities. • Daily briefing
– Brief description of ongoing, new activities. (POD)
– Hot work permitting
– Current hazards (who, what, how, when, where? JHA)
– Priorities of the day
– Sign-off sheet
• Additional briefings if warranted – Late arrivals/shift handover
– Change management
• Site walk rounds by manager and safety personnel
Hazard analysis and recognition
Hazard analysis processes
• SPEC-0061 – Initial analysis uses Mil STD-882, System Safety
– Further analysis if appropriate
• Progression of design hazard analysis – Mil STD-882, System Safety
– ANSI/RIA, 15.06 Robotics Safety
– IEC 62021, Safety of machinery
– EN ISO 13849, Safety of machinery
– IEC 61511, Process Safety …
System Safety MIL-STD 882
Severity/
Probability
Value Category Frequent 1-A 1 2-A 3 3-A 7 4-A 13
1 – 5 High Probable 1-B 2 2-B 5 3-B 9 4-B 16
6 – 9 Serious Occasional 1-C 4 2-C 6 3-C 11 4-C 18
10 – 17 Medium Remote 1-D 8 2-D 10 3-D 14 4-D 19
18 – 20 Low Improbable 1-E 12 2-E 15 3-E 17 4-E 20
CriticalCatastrophic NegligibleMarginal
Hazard Recognition
Mishap Risk Assessment Value
Mishap Risk Category
Mishap Risk Acceptance Level
1 – 5 High AURA / NSF
6 – 9 Serious NSO Director
10 – 17 Medium ATST Program Manager, Director,
System Engineer and Safety
Manager 18 – 20 Low
From SPEC-0061:
Requires: escalation and traceability Electronic approval process
Hazard Analysis Team Update
Hazard Analysis Team
• R. Hubbard is leading the HAT (was S. Shimko)
• Recent key activities
– Getting instrument teams up to speed on Hazard Analysis
– Sun avoidance!
Instrument Teams
• Conduct dual analysis examples with teams
• Review at PDR, CDR
• Liquid Cryogens
– Burn
– Asphyxiation
• All cryogenic applications now use closed cycle refrigeration
– Hazard eliminated
• Vibration issues being addressed (non-HAT activity)
Sun tracking/avoidance
• Direct illumination of the primary mirror must fall within the Heat Stop.
• Hazard
– Outside the heat stop there is a hazard of focusing sunlight on structure (12kW power)
– Fire
– Burn
Prime Focus
Gregorian Focus
Sun tracking/avoidance
• There is a science driver to observe in daylight away from the Sun
• Hazard Analysis
– Mitigation • Mirror covers can only be
open when within 1.5 solar radii or at an angle that the sun will not illuminate the primary mirror
– Failure triggers closure of: • Safety Shutter (SIL 3)
• Mirror Covers
• Enclosure aperture
Sun tracking/avoidance
• There is a science driver to observe in daylight away from the Sun
• Hazard Mitigation A. Within 1.5 solar radii?
• Location detection of solar disc (SIL3 rated)
B. At an angle that the sun will not illuminate the primary mirror? • Calculate exclusion zone based
on current position of Sun (calculated within Allen Bradley Guard Logic system)
• Visual check prior to opening mirror covers
– If A or B false initiate closure sequence.
– Observing efficiency requires TCS to navigate around exclusion zone (non-HAT activity
Questions?