11
ISTS ISGS -I SEB-B drawal Main = (T+U+X) Standby = (V+W+Y) SEB-A drawal Main = (G+H+N+O+Y) Standby = (L+M+Q+R+X) Metering Philosophy under ABT regime Other than NTPC Station ISGS-I injection Main = (F+G+H+J+K) Check=(F'+L+M+J'+K') Standby = (A+B+C+D+E) NTPC Station SEB-B ISGS-II injection Main = (M1+M2) Check=(C1+C2) Standby = (S1+S2) ISGS -I Aux. Aux. ISTS ISTS SEB-A SEB-A A B D E C F F' G H J J' K K' L M SEB-A S T U V W X Y SEB-B N O P Q R C1 C2 M1 M2 S1 S2 Aux. Main Meter Standby Meter Check Meter

ISTS

Embed Size (px)

DESCRIPTION

Metering Philosophy under ABT regime. NTPC Station. Aux. Aux. Aux. M2. M1. B. A. C. D. E. C1. C2. ISGS -I. H. S2. G. S1. F F'. J J'. K K'. L. M. SEB-A. ISTS. S. T. U. W. V. N. O. P. SEB-B. R. ISTS. Q. SEB-B. SEB-A. ISGS-II injection Main = (M1+M2) - PowerPoint PPT Presentation

Citation preview

Page 1: ISTS

ISTS

ISGS -II

SEB-B drawalMain = (T+U+X)

Standby = (V+W+Y)

SEB-A drawalMain = (G+H+N+O+Y)Standby = (L+M+Q+R+X)

Metering Philosophy under ABT regime

Other than NTPC Station

ISGS-I injectionMain = (F+G+H+J+K)Check=(F'+L+M+J'+K')Standby = (A+B+C+D+E)

NTPC Station

SEB-B

ISGS-II injectionMain = (M1+M2)Check=(C1+C2)Standby = (S1+S2)

ISGS -I

Aux. Aux.

ISTS

ISTS

SEB-A

SEB-A

A B D EC

FF'

G HJJ'

KK'

L M

SEB-A

ST U

VW

X

Y

SEB-B

N O P

Q R

C1 C2

M1 M2

S1 S2

Aux.

Main Meter

Standby Meter

Check Meter

Page 2: ISTS

Points for Energy AccountingInjection by NTPC Generating Stations :

Main &check meters on Outgoing feeders Standby meters on HV side of GT/TT

Injection by other Generating Stations :

Main &check meters on HV side of GT/TT Standby meters on Outgoing feeders

Drawl by SEBs

Main -HV side of ICTs at GS and CTU S/S, Receiving end of Lines directly connected to ISGS

Respective ends of Lines connected to other SEBs Standby – LV/ Tertiary side of ICTs

Other end of lines connected to other SEBs

Page 3: ISTS

Special Energy Meter FeaturesSpecial Energy Meter Features

• STATIC TYPE

• COMPOSITE METER

• HIGHEST ACCURACY IN POWER INDUSTRY

• 3 PHASE-4 WIRE CONNECTIONS / MEASUREMENT

• DIRECT MEASUREMENT AS PER CT/PT SECONDARY QUANTITIES

- 110V PH TO PH/63.51 V PH-N

- 1 AMP OR 5 AMP

- VA BURDEN NOT >10 ON ANY OF THE PHASES

• WORKS ON REAL TIME CLOCK

• NO CALIBRATION REQUIRED

• TIME ADJUSTMENT FACILITY

• HIGH SECURITY OF DATA STORAGE

Page 4: ISTS

Raw dataWEEK FROM 0000 HRS OF 06-01-01 TO 0837 HRS OF 15-01-01NP-0185-A 91858.5 99968.5 39195.5 06-01-01 00 51 +21.57 48 +21.68 50 +21.71 49 +21.33 …. 04 19 +20.61 23 +20.80 19 +21.05 00 +21.35 … 08 00 +24.95 00 +24.95 00 +25.09 00 +24.38 … 12 71 +24.38 52 +23.98 30 +23.81 13 +24.03 …16 00 +23.37 00 +23.52 00 +22.87 00 +21.66 … 20 00 +25.75 00 +25.32 00 +25.40 00 +25.37 … NP-0185-A 94117.2 99968.5 40313.5 07-01-01 00 59 +20.94 54 +21.01 59 +20.79 58 +21.05 … 04 33 +20.05 38 +20.17 37 +20.49 28 +20.90 …08 00 +22.99 06 +23.10 00 +22.81 00 +22.94 … 12 85 +20.93 51 +20.65 21 +20.79 00 +19.89 … 16 07 +20.14 01 +20.53 00 +20.72 00 +20.66 …20 05 +23.62 08 +23.23 16 +23.25 27 +23.40 … NP-0185-A 96172.2 99968.5 41236.9 08-01-01 

Page 5: ISTS

Special Energy Meter Various ChecksSpecial Energy Meter Various Checks

CHECKS for DATA VALIDATION :

• NOMINAL VOLTAGE CHECK• FREQUENCY• TIME CORRECTION• WATTHOUR CHECK• PREVIOUS WEEK DATA• ALGEBRAIC SUM

Page 6: ISTS

• RAW DATA IN WHr

• MWhr = RAW DATA x CT RATIO x PT RATIO

• PAIR CHECK DONE FOR MAIN/ CHECK/ STANDBY/ FICTMETERS ( ex. : for both sides of ICTs, Lines, GT side & Line side at ISGS.

Special Energy Meter Data ComputingSpecial Energy Meter Data Computing

Page 7: ISTS

Reactive Energy Accounting

Reactive Energy is measured

when system voltage is

> 103% of Nominal Voltage< 97% of Nominal Voltage

Page 8: ISTS

Loss computations

15 min block-wise % loss =

(Sum of all Injections from ISGS + net IR imports)

X 100

(Sum of all Injections from ISGS + net IR imports) -

(Sum of Drawals by all beneficiaries from Central Grid)

Page 9: ISTS

Use of Notional Loss in scheduling

• % Average loss (15 min. blockwise) aggregated over the last week will be used in Scheduling Process for the next week.

(for arriving at the ex-periphery Drawal Schedules of Beneficiaries)

%loss Graph Loss Table

0.5% REDUCTION MEANS MORE THAN 100 CR ANNUAL SAVINGS0.5% REDUCTION MEANS MORE THAN 100 CR ANNUAL SAVINGS

Page 10: ISTS

Loss for the week Loss % Week applied for

From To   From To

16-Sep-02 22-Sep-02 4.83 30-Sep-02 6-Oct-02

6-Jan-03 12-Jan-03 3.9 20-Jan-03 26-Jan-03

20-Oct-03 26-Oct-03 3.38 3-Nov-03 9-Nov-03

19-Jan-04 25-Jan-04 3.92 2-Feb-04 8-Feb-04

24-May-04 30-May-04 2.55 7-Jun-04 13-Jun-04

9-Aug-04 15-Aug-04 2.54 23-Aug-04 29-Aug-04

17-Jan-05 23-Jan-05 3.25 31-Jan-05 6-Feb-05

7-Feb-05 13-Feb-05 3.04 21-Feb-05 27-Feb-05

30-May-05 5-Jun-05 2.95 13-Jun-05 19-Jun-05

27-Jun-05 3-Jul-05 3.49 11-Jul-05 17-Jul-05

11-Jul-05 17-Jul-05 3.73 25-Jul-05 31-Jul-05

25-Jul-05 31-Jul-05 3.53 8-Aug-05 14-Aug-05

1-Aug-05 7-Aug-05 3.3 15-Aug-05 21-Aug-05

8-Aug-05 14-Aug-05 2.92 22-Aug-05 28-Aug-05

TYPICAL %AVERAGE LOSS FIGURES FOR CENTRAL GRID IN SR

%Average losses In other Regions :

NR 3.5 to 4.5

ER 3.0 to 3.5

WR 5.0 to 6.0

BACK

OTHER REGIONS

Page 11: ISTS

%loss for different weeks from 2003- 2005

1.0

1.5

2.0

2.5

3.0

3.5

4.0

4.5

5.0

1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51

Week No.

%lo

ss

2003-042004-05

2005-06

BACK