Upload
dhruv-gupta
View
216
Download
0
Embed Size (px)
Citation preview
8/11/2019 Issue Tracker 131230
1/1
Legend: Critical Issues Pending
Completed In Progress
S.
No.Issue
Action
Initiated
on
Target
Date
Actual
DateAction By Remarks
19-DecClient: Mr.
Pinto
Contact Ashish at SOPAN
Engineering (09405291918)
20-Dec Sopan: Ashish Pipes are to be laid along the walls
2 Route of pipelines27-Dec 30-Dec 30-Dec Client
The pipelines will be above the false
ceiling
3Electrcial cable route and specifications for
industrial wiring27-Dec 30-Dec
Mr. Manish
Trinitron
The vendor will provide the shop
drawings for cables and cable tray
4Electrcial cable route and specifications for point
wiring26-Dec 26-Dec Architect
RCP along with electrical fixtures
has been sent to client for
confirmation
5 Route of data/voice cables 21-Dec Client Meeting to be arranged with HP
6 Route of security system cables 21-Dec Client Vendor to be finalised
7 Route of fire detection system cables 27-Dec Architect Vendor to be finalised
8 Loading of floor for deciding on the Epoxy Paint' 19-Dec 19-DecClient: Mr.
Pinto
Movement of Manpower & Electrical
Fork lift model upto 1.5 Tons,
Godrej make
9Arrangement of Fans for thermal comfort in Non-
Ac areas19-Dec Architect
Sthapati is asked to provide withoptions/combination of split/cassette
for AC
10Arrangement of ACs , wall mounted ACs have a
throw of 20' maximum27-Dec 30-Dec Client
3.0 TR high wall-mounted industrial
ACs to be used
11 Alternatives for material of the partitions with
painted finish19-Dec 30-Dec Client
Gypsum partition and false ceiling
will be used
12 Initial drawings for partitions & ceilings with
proposed material24-Dec 24-Dec 26-Dec Architect Drawings sent
13 Electrical drawings 19-Dec 19-DecClient: Mr.
PintoSent Electrical drawings
14
High, low pressure piping & electrical
wiring/cables needs to be dropped down to the
machine location. Organise a teleconference.
21-Dec 23-Dec Architect Conference call done
15 Heat being generated in each machine for ACloads
23-Dec 1-Jan-14 Client
Client confirmed there is no heat
load from the machines thus the
dwgs already sent holds good
Issue Tracker Sheet
Project : KLR, Factory, Gurgaon
Load of Piping and the pipe rack of the proposed
lines
1