Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
BulletinI s s u e 1
J u l y 2 0 1 9
About the May Road construction siteThe May Road construction site is one of the largest for the Central Interceptor project and will have some level of activity for five and a half years.
The site will be established from 12 August when we will create access roads to the site and manage stormwater. We will construct two deep shafts on the site which will ultimately collect the wastewater from the local sewer pipes and transfer it to the Central Interceptor.
Other activities later in the programme include support for creation of the main tunnel toward Western Springs. This includes handling materials removed from tunnelling such as dirt and rock, and managing tunnel segments before they are installed.
Site locationThe site will be accessed via May and Roma Roads. The site boundary is shown in the map below.
Construction site and access boundary
May
Roa
d
South Western Motorway
Roma Road
Marion Avenue
May Road, 54 Roma Road and 105 May Road
CENTRALINTERCEPTOR
[www.centralinterceptor.co.nz]An Auckland Council Organisation
About the May Road construction site
Any questions?For up to date information please see our website:
www.centralinterceptor.co.nz
You can also email us at:
Or phone
0800 GAJV 02 (0800425802)
Working with you We understand that large projects such as the Central Interceptor can be disruptive as work on site can be noisy and busy at times.We aim to be a good neighbour while we are working in your area and will work to minimise disruption, where possible. We will keep you informed with what’s happening with regular newsletters and will be out in your community during the works to engage face-to-face such as the upcoming ‘Meet the Contractor’ community event.
How will construction affect you?
• General work hours will be between 7am to 6pm, Monday to Friday, and 8am to 6pm on Saturday.
• Traffic management will be in place for the safety of motorists, pedestrians and workers. Our trucks will be operating between 7am and 6pm during the week and between 8am and 6pm on Saturday; however we will limit truck movements between the hours of 7:30–9:00am and 3:00–4:30pm.
• Noise levels and vibration will be managed in accordance with Council requirements. Noise barriers/fences will be used during works to minimise noise. Some activities will also be located in sheds to reduce noise.
• There will be some parking restrictions on Roma Road at times during construction. We will notify surrounding residents in advance of any parking restrictions.
Proposed work programmeOver the next few months, the first activities will be to set up the site and prepare the area. Construction activities will start picking up later this year when we start construction of the shafts.
Below is a table showing activities with a proposed timetable.
Activity
Access and haul roads
construction including site
stormwater worksBuilding
conditionsurvey
Secondary shaft
construction including
plant rooms and links to
local networks
Project completion
Proposed date
April 2019
July 2019
Aug to Oct 2019
Nov 2019 toAug 2020
Primary shaftconstruction
Dates still to be confirmed
May Road to Western
Springs tunnelling
Dates still to be confirmed
Mid 2025
Geotechnical and other
investigations
An Auckland Council Organisation
We are here
Meet the contractorWe would like to invite the local public to meet our contractor – Ghella Abergeldie Joint Venture
Where: Turner Reserve
When: Saturday, 3 August
Time: 11am – 2pm
This is an opportunity to come down and find out more about how we will work with you while we are in your
neighbourhood, find out more about the project, and discuss the
May Road construction activities.
We encourage you to receive these updates electronically – send us your email, your current mailing address and quote “Go sustainable: May Road bulletin” to [email protected]