ISRTP Presentation Jimmy Thompson Tel Aviv Jan 2014

Embed Size (px)

Citation preview

1

Project Location

2

Project Organization

• Privately Funded

• Total Investment 1.28 billion USD

• Build, Operate, Transfer Project

• Korean, European and Turkish Bank Loans

• Design Build Construction Contract

• Contractor is JV of Yapi Merkezi (Turkey) and S&K Construction (Korea)

• Detailed Designer is Parsons Brinckerhoff (USA)

3

Tunnel Long Section

4

TBM Tunnel Cross Section

5

• 12m diameter

• 2 lanes in each direction

• No trucks allowed

• Emergency stairs every 200m

6

TBM Launch Box

• 40m deep

• 160m long

• Secant piles in soft rock

• Piles in rock

7

TBM Launch Box

8

TBM Launch Box

9

TBM Launch Box

10

TBM Launch Box

11

TBM

12

• Herrenknecht

• Slurry Machine

• 13.6m diameter

• 1200 tons total weight

TBM Model

13

TBM Model

14

TBM Model

15

TBM Cutterhead

16

• Cutterheadweighs 350 tons

• Cutterhead is hollow

• Cutterheadallows changing of cutting tools under atmospheric pressure

• Trimix setup for divers to repair cutterhead under 11bar water pressure

Disc Cutter (for Rock)

17

TBM Hollow Cutterhead

• Cutterhead is hollow and allows changing of cutting tools under atmospheric pressure

18

TBM Hollow Cutterhead

19

TBM Front Shield/ Excavation

Chamber

20

TBM segmental liner vacuum

plate

21

TBM Tailshield

22

Segmental Liner Rebar Ladders

23

Segmental Liner Rebar Ladders

24

Fusion Welding of Ladders

25

Allowable Gap At Ring-to-Ring Joints

26

0.E+00

2.E+05

4.E+05

6.E+05

8.E+05

1.E+06

7+700 7+800 7+900 8+000 8+100 8+200 8+300 8+400 8+500 8+600 8+700 8+800

Forc

e (k

N)

1st Set 2nd Set 3rd Set 4th Set 5th Set 6th Set 7th Set 8th Set Average

0.E+00

2.E+05

4.E+05

6.E+05

8.E+05

1.E+06

7+700 7+800 7+900 8+000 8+100 8+200 8+300 8+400 8+500 8+600 8+700 8+800

Forc

e (k

N)

Average - No Wave Passage Effect Average - Wave Passage European to Asian Average - Wave Passage Asian to European

27

Asian to European

No Wave Pass Effects

European to Asian

No Wave Pass Effects

European to Asian Asian to European

No Seismic Joint (Lower Bound Vs Profile)

Seismic Joints (Lower Bound Vs Profile)

28

29