Upload
nami
View
47
Download
0
Tags:
Embed Size (px)
DESCRIPTION
ISOLDE Technical report for INTC 21/5/2007. Mats Lindroos. Outline. Change of responsibilities at ISOLDE Shutdown work Off-line upgrade REX status Technical R&D at ISOLDE. New responsibilities at ISOLDE. Technical coordinator Richard Catherall REX ISOLDE superintendent Fredrik Wenander - PowerPoint PPT Presentation
Citation preview
Mats Lindroos
ISOLDETechnical report for
INTC 21/5/2007
Mats Lindroos
Mats Lindroos
Outline
• Change of responsibilities at ISOLDE
• Shutdown work• Off-line upgrade• REX status• Technical R&D at ISOLDE
Mats Lindroos
New responsibilities at ISOLDE
• Technical coordinator– Richard Catherall
• REX ISOLDE superintendent– Fredrik Wenander
• ISOLDE hall superintendent– Erwin Siesling
• New projects and INTC matters– Mats Lindroos
Mats Lindroos
Major 2006/7 Shutdown tasks
• Yearly facility maintenance: water and power (HT)
• Instrumentation: migration to linux of scanners & wiregrids
• Front-Ends: repair of the boris-tubes insulators (R. Catherall)
• Mini-move: mini-ball into the extension 170 (D. Voulot)
• REX maintenance: upgrades and repair (F. Wenander)
• RFQ installation: prim pumps into HRS zone (E. Siesling)
• Various work: laser windows, PLC update, ADC replace,etc.
Mats Lindroos
Improvement on the shutdown
• Dedicated and responsible person appointed for each major task
• Weekly technical shutdown meeting
• Close follow-up and adaptation of the planning
• Daily start-up meeting at beginning of the run
Mats Lindroos
Results
• 2007 smooth start-up• No hardware failures or over-run of
work• Expected software debugging (i.e.
scanner & wiregrids applications)• BUT.. Unexpected (minor) controls
problems (PS wide, AB/CO addressed)
Mats Lindroos
Off-line separator upgrade
• New magnet coils to replace old faulty coils
• Survey points for the alignment of the offline separator installed and documented
• New beam diagnostic chamber with mechanical slit system and “ISOLDE type” scanner installed
• Special thanks to Jerome Sarret, Erik Asen, Antony Newborough, Michel
Duraffourg
Mats Lindroos
• Automatic mass program
• 15 minutes for masses 0-160 with 0.1 mass unit resolution
• Labview based control system communicating directly to PLC’s via RPC server
• Response time: CCV to PLC <900msRefresh rate 100ms
Mats Lindroos
REX low energy stage
• Trap– Operational and in standby mode. Minor improvements
during shutdown. Have delivered some stable beam to Witch.
• EBIS– The general power cut in March partly vented the machine
preventing us from doing further electron beam tests with the post anode.
– The newly inserted cathode did not perform as expected and had to be exchanged.
• The machine is up running with a new cathode. Beam has been injected and extracted through the separator
• The old control system has been exchanged to a AB supported system. – Still running with a temporary application programme
Mats Lindroos
0.0
5.0
10.0
15.0
20.0
0 50 100 150 200 250
A
%
7Li238U
27Al
116Cd
Efficiencies for beams 2006Tot. eff. = Trap × BTS × EBIS × Sep
The constant “quest” for efficiency
REX low energy stage now covers A=7 to >200 with total efficiencies of at least 5%
High current beams can now be charge breed with some efficiency (e.g. 1.8% for a 3nA 7Li+ beam into 7Li3+)
Light ions still difficult to breed ≤5%
-> Charge breeder : generally aiming for 10% total efficiency!
-> Linac efficiency 70-85% (aim for >80% in 2007)
Mats Lindroos
Isotopes and elements run at REX so far…
8Li3+,9,11Li2+
10,11,12Be3+,4+
17F5+
24-29Na7+
29,31Mg9+, 28,30,32Mg8+ 68Ni19+
67-71,73Cu19+,20+,20+,19+
80Zn21+, 74,76,78Zn18+
70Se19+
88,92Kr21+,22+
108In30+
108,110Sn27+,30+
122,124,126Cd30+,31+
138,140,142,144Xe34+
148Pm30+
153Sm28+
156Eu28+
Mats Lindroos New section
Minimove - Phase 1
* Phase 1 = First phase of a full installation (linac upgrade, recoil separator, HIE-Isolde…)
* Goals : 1. create space (linac upgrade, space around experiments) 2. improve shielding from X-ray background at Miniball 3. improve beam properties -> more focussing -> more beam diagnostics -> realignment of beamlines
Installation in progress!
Mats Lindroos
Beam optics calculation 9-GP to MB target* 3MeV/u A/q3.5* 0.6π.mm.mrad normalised* ±1% energy spread
Diploma Thesis by T. Arronsson
Mats Lindroos
Y direction after 2.5m drift0.21 π.mm.mrad @ 2.2MeV/u
Linac emittance measurements
Results* Normalised transverse emittance (2σ RMS) = 0.21±0.07 π.mm.mrad at 2.2MeV/u
* Low intensity few 100pA (no space charge effect in EBIS!)
* Horizontal emittance larger than vertical after the bender (energy spread)
* Emittance increased when going from 1.2 to 2.2 MeV/u (mismatch between IHS and 7gaps?)
* Emittance increased with stripper foils
Energy spread = ±0.03MeV/u@ 2.97MeV/u (±1%)Continuation 2007
* Verify results with uninterrupted measurement series
* Verify influence of EBIS operation conditions on the emittance
* Measure at 3MeV/u and 300keV/u
Mats Lindroos
Technical R&D at ISOLDE
• Dual transfer lines– Merging of neutral
beams
• Mono ECR• Tendering for new
solid state laser for RILIS– Progress on LARIS
installation
• ECR PHOENIX charge breeder development
• RFQ cooler off-line commissioning
ResultsI/I
max
n+
bea
m
Plasma chamber high voltage
1+ beamExtraction
voltage
Noble gasMetallic ions
I/Im
ax n
+ b
eam
Plasma chamber high voltage
1+ beamExtraction
voltage
Noble gasMetallic ions
V tuning Stable backgroundMass Scan
-50
0
50
100
150
200
250
300
350
0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0 12.0 13.0
A/q
I (n
A)
O4+O5+O6+C+C3+H+
Background >5nA 2<A/q<7
CW Pulsed
4<A/q<8=2-7%
CW 86Kr13+ 2.2%132Xe18+ 1%Preliminary
Afterglow
P. Delahaye et al., RSI 77 03B105 (2006)
86Kr13+
RFQ cooler “ISCOOL”
Emittance meter
RFQ cooler
Alkali ion source
Continuous mode
~5·mm·mrad 90% emittance
~30·mm·mrad 90% emittance
as input
Ion transmission
Li+ 17%
Na+ 27%
K+ 60%
Cs+ 70%
• Ongoing tests with the bunching mode• Last off-line tests with a FEBIAD source delivering noble gas ions
E. Mané, H. Frånberg,P. Delahaye