Introduction:
ISO 9001 is now in its fourth edition. Starting with the 1987 initial edition, it changed in 1994and again in 2000. The 2000 change was pretty extensive. It introduced the concept of process
auditing and added a lot of emphasis to the importance of top management to the effectiveness of
quality management systems. In November 2008, the fourth edition was released.
Discussion:
On November 13, 2008, the fourth edition of ISO 9001 became official. It is referred to as ISO9001:2008. The good news is that it contains no substantive changes or new requirements. The
changes that were made were done for two reasons: 1) clarifications to the requirements of ISO
9001:2000; 2) to improve alignment with ISO 14001:2004.
The ANSI-ASQ National Accreditation Board (ANAB) has issued two Heads-up documents that
deal with the changes and transition process for moving from ISO 9001:2000 to ISO 9001:2008.These can be accessed from the ANAB web page www.anab.org. Refer to Heads-up numbers
129 (migration) and 135 (where/how to buy the standard.)
The transition/migration process has the following requirements:
Twelve months after the release of ISO 9001:2008, all new and re-certification auditsmust be done to the ISO 9001:2008 standard. Twenty-four months after release of ISO 9001:2008, all ISO 9001:2000 certificates will
be invalid.
Upgrading from ISO 9001:2000 to ISO 9001:2008 requires a surveillance or re-certification audit to be conducted.
If you are certified to ISO 9001:2000, you can continue with that revision level for a period of
time depending where your organization is within its current three-year certificate cycle. Eachcertification/registration body (CRB) will have its own practices/rules regarding when and underwhat conditions an existing certification can be upgraded to ISO 9001:2008. However, in all
cases, there must be either a surveillance or re-certification audit executed before an ISO
9001:2000 certificate can be upgraded to ISO 9001:2008.
8/4/2019 ISO9001-2008Revisions SQA SedlakConsulting
2/16
How to Use the Checklist:
First and foremost obtain at least one copy of ISO 9001:2008. (See ANAB Heads-upNo. 135 for directions on how to obtain a copy.)
Next, determine if the existing documented QMS and actual practices meet therequirements of ISO 9001:2008. The checklist has three categories:
o Meets this requiremento Needs some modificationo Clause not applicable.
(If you check this box, remember that only sub-clauses in section 7 can beclaimed to be not applicable, and your scope statement and related
documentation must contain justification for such exclusions.)
For each clause/sub-clause, use the Comments/Notation cells to annotate where therequirement is met. This may be a reference to a document, policy, procedure, work
instruction, process document, etc.
When completed, notify your CRB that you are ready to be audited in accordance withthe requirements of ISO 9001:2008. The completed checklist will provide one form of
objective evidence (at the minimum, it will be a solid audit-trail) that your organization
has completed an analysis of ISO 9001:2008 and, if applicable, made required changes to
its QMS.
About Smithers Quality Assessments
Smithers Quality Assessments was established in 1993 as an accredited third-party registrar,
providing manufacturers and service providers quality and environmental management systemcertification services to ISO 9001, ISO 14001 and other industry-specific standards. SQA is
consistently ranked as a leader in customer satisfaction by independent surveys of registered
companies. www.smithersregistrar.com
About J&S Sedlak, LLC (Sedlak Consulting)
For over fifteen years, John Sedlak led Smithers Quality Assessments, a leading
certification/registration body located in Akron, OH. Since retirement, he has established a
training/consulting practice, J&S Sedlak, LLC, specializing in the ISO standards and theiri l i Y l b i h b dl k l i
8/4/2019 ISO9001-2008Revisions SQA SedlakConsulting
3/16
Smithers Quality Assessments 2009: www.smithersregistrar.com Phone: 1-866-688-0134
J&S Sedlak, LLC 2009: www.sedlakconsulting.com Phone: 330-936-3436
ISO 9001:2000 vs. ISO 9001:2008 Analysis Tool* ISO 9001:2008 was released on November 13, 2008
* On or after November 13, 2009, all new certifications and re-certifications must be to ISO 9001:2008.
* On or after November 13, 2010, any existing certification to ISO 9001:2000 will no longer be valid.
Current QMS Documentation & Practice ----
Clause Summary of
change(s)
Comment on
Change(s)
Meets this
Requirement
Needs some
Modification
Clause is not
Applicable
Comments / Notations
4.1 a Very slight change inwording.
4.1 e "where applicable"added to "measure"
these processes.
Provides some
leeway to
organization - not all
process need to be
"measured."
4.1 plus
Notes 1,
2 & 3
If process(es) that
affect quality of
product are
outsourced,
organization must
define controls.
More emphasis on
the need for the
organization to retain
control for
outsourced
processes, and not
rely solely on the
controls of the
organization to which
the process was
outsourced;
"processes" not
limited to product
realization processes.
8/4/2019 ISO9001-2008Revisions SQA SedlakConsulting
4/16
Smithers Quality Assessments 2009: www.smithersregistrar.com Phone: 1-866-688-0134
J&S Sedlak, LLC 2009: www.sedlakconsulting.com Phone: 330-936-3436
Current QMS Documentation & Practice ----
Clause Summary of
change(s)
Comment on
Change(s)
Meets this
Requirement
Needs some
Modification
Clause is not
Applicable
Comments / Notations
4.2.1
c&d
"Records" now
included in these
sub-clauses.
Slight shift in
emphasis to indicate
"procedures" and
"records" are related.
4.2.1,
Note 1
Slight elaboration on
meaning of
"Documented
procedure"
Can be: a stand
alone procedure; one
document containing
more than one
procedure; one
procedure may be
expressed in more
than one document.
4.2.3 f External documents
determined to be
important must be
controlled
Reduces the need to
control all external
documents.
However, places
extra responsibility
on the organization
to define thoseexternal documents
that are important.
4.2.4 Records are to be
controlled.
Added emphasis
from previous
"maintained."
8/4/2019 ISO9001-2008Revisions SQA SedlakConsulting
5/16
Smithers Quality Assessments 2009: www.smithersregistrar.com Phone: 1-866-688-0134
J&S Sedlak, LLC 2009: www.sedlakconsulting.com Phone: 330-936-3436
Current QMS Documentation & Practice ----
Clause Summary of
change(s)
Comment on
Change(s)
Meets this
Requirement
Needs some
Modification
Clause is not
Applicable
Comments / Notations
5.5.2 Management
representative to be
a member of
organization's
management.
Emphasis on the fact
that the
management
representative needs
to be employed bythe organization and
be a member of the
organization's
management team.
6.2.1 Persons that affect
product conformity
requirements to be
competent
"Affecting product
quality
requirements"
applies to any taskwithin the QMS, not
just direct
manufacturing or
service provision
6.2.2
a ,b
Determine
competency of
personnel affecting
productrequirements;
provide training to
achieve needed
competence.
Removed the word
"quality" to indicate
that all requirements
are important, notjust "quality
requirements."
Emphasis on need to
"achieve" and not
just "satisfy"
competency
requirements.
8/4/2019 ISO9001-2008Revisions SQA SedlakConsulting
6/16
Smithers Quality Assessments 2009: www.smithersregistrar.com Phone: 1-866-688-0134
J&S Sedlak, LLC 2009: www.sedlakconsulting.com Phone: 330-936-3436
Current QMS Documentation & Practice ----
Clause Summary of
change(s)
Comment on
Change(s)
Meets this
Requirement
Needs some
Modification
Clause is not
Applicable
Comments / Notations
6.3 Added "information
systems" (IS) to
support services.
Recognized the
importance of IS in
today's environment.
6.4 Added a note to
explain "workenvironment."
Physical factors and
others, e.g., noise,temperature,
humidity, lighting,
weather.
7.1 b Restructure of
grammar.
Grammar only.
7.1 c Added
"measurement" as an
action to beconsidered.
"Measurement"
added to be sure that
this action is includedwhen considering
elements of the QMS
needed to achieve
conformity with
requirements.
7.2.1 c Added word
"applicable."
Added to clarify the
"statutory" as used
applies only toproduct
requirements.
7.2.1 d "Determined"
changed to
"considered
necessary."
Slight shift in
emphasis from
simply taking action
to taking
responsibility.
8/4/2019 ISO9001-2008Revisions SQA SedlakConsulting
7/16
Smithers Quality Assessments 2009: www.smithersregistrar.com Phone: 1-866-688-0134
J&S Sedlak, LLC 2009: www.sedlakconsulting.com Phone: 330-936-3436
Current QMS Documentation & Practice ----
Clause Summary of
change(s)
Comment on
Change(s)
Meets this
Requirement
Needs some
Modification
Clause is not
Applicable
Comments / Notations
7.2.1 New Note. Explains what is
meant by "post
delivery activities."
7.3.1 New Note. Elaborates on thedifferences and
similarities between
design "review,"
"verification" and
"validation;" may be
separate or
combined depending
upon needs ofproduct or
organization.
7.3.2
2nd
para
"These" changed to
"The."
Grammar only.
7.3.3
1st para
Changed "in a form
that enables " to "ina form suitable for"
verification.
Emphasis placed on
suitability of designbeing verified not
simply an arbitrary
acknowledgement
that it can be
verified.
7.3.3 b Eliminated "for." Grammar only.
8/4/2019 ISO9001-2008Revisions SQA SedlakConsulting
8/16
Smithers Quality Assessments 2009: www.smithersregistrar.com Phone: 1-866-688-0134
J&S Sedlak, LLC 2009: www.sedlakconsulting.com Phone: 330-936-3436
Current QMS Documentation & Practice ----
Clause Summary of
change(s)
Comment on
Change(s)
Meets this
Requirement
Needs some
Modification
Clause is not
Applicable
Comments / Notations
7.3.3 New Note Information can
include details on
preservation of
product.
7.3.7
1st &
2nd
para
No text changes -
paragraphs merged.
Grammar only.
7.5.1 d "Devices" changed to
"equipment."
Recognition that
measurements can
be taken with a wide
variety of options.
7.5.1 f Added "product"
before "release."
Clarified that the
subject was release
of product.
7.5.2 Slight change in
wording to
emphasize the needfor process controls
for "special
processes."
The word
"consequences" adds
emphasis to theresponsibility of the
organization to
establish process
controls for "special
processes."
8/4/2019 ISO9001-2008Revisions SQA SedlakConsulting
9/16
Smithers Quality Assessments 2009: www.smithersregistrar.com Phone: 1-866-688-0134
J&S Sedlak, LLC 2009: www.sedlakconsulting.com Phone: 330-936-3436
Current QMS Documentation & Practice ----
Clause Summary of
change(s)
Comment on
Change(s)
Meets this
Requirement
Needs some
Modification
Clause is not
Applicable
Comments / Notations
7.5.3
2nd
para
Expanded
requirement for
inspection
(monitoring and
measuring) statusthroughout the
product realization
process.
Clarified that it is
important for
product to be
identified relative to
its conformancestatus throughout
the product
realization process.
7.5.3
3rd para
Regarding
"traceability:"
changed "record" to
"maintain records."
Emphasis shift from
simple recording to
maintenance of such
records.
7.5.4
1st para
Regarding damaged
or unsuitable
customer supplied
product, minor
rewording.
No substantive
change.
7.5.4
Note
Added "and personal
data."
Slight addition to
indicate that theremay be times when
organizations come
into possession of
personal data from
folks that are not
their employees.
8/4/2019 ISO9001-2008Revisions SQA SedlakConsulting
10/16
Smithers Quality Assessments 2009: www.smithersregistrar.com Phone: 1-866-688-0134
J&S Sedlak, LLC 2009: www.sedlakconsulting.com Phone: 330-936-3436
Current QMS Documentation & Practice ----
Clause Summary of
change(s)
Comment on
Change(s)
Meets this
Requirement
Needs some
Modification
Clause is not
Applicable
Comments / Notations
7.5.5
1st para
Regarding
preservation of
product, added
words to convey that
this applies to"conformity to
requirements."
Expanded to convey
intent of
requirement.
7.6 "Devices" changed to
"equipment."
Recognition that
measurements can
be taken with a wide
variety of options.
7.6 a Added "or both" to"verified or
calibrated."
Clarified thatorganization must
decide all actions,
not just one or the
other.
7.6 c Regarding evidence
of "calibration status'
only a slight re-wording.
Grammar only.
7.6
4th para
Made a separate
paragraph of one
sentence.
Grammar only.
8/4/2019 ISO9001-2008Revisions SQA SedlakConsulting
11/16
Smithers Quality Assessments 2009: www.smithersregistrar.com Phone: 1-866-688-0134
J&S Sedlak, LLC 2009: www.sedlakconsulting.com Phone: 330-936-3436
Current QMS Documentation & Practice ----
Clause Summary of
change(s)
Comment on
Change(s)
Meets this
Requirement
Needs some
Modification
Clause is not
Applicable
Comments / Notations
7.6
Note
Completely
rewritten.
Expanded
explanation of
confirmation and
validation of
computer software;included in actions
associated with
configuration
management.
8.1 Conformity "of the
product" changed to
"to productrequirements."
Change made to
clarify that there may
be other productrequirements that go
beyond those that
simply define the
product.
8.2.1
new
Note
Customer
satisfaction.
Offers hints at
sources for
monitoring customersatisfaction.
8.2.2
2nd
para
Added the word
"The" at the
beginning of 3rd
sentence.
Grammar only.
8/4/2019 ISO9001-2008Revisions SQA SedlakConsulting
12/16
Smithers Quality Assessments 2009: www.smithersregistrar.com Phone: 1-866-688-0134
J&S Sedlak, LLC 2009: www.sedlakconsulting.com Phone: 330-936-3436
Current QMS Documentation & Practice ----
Clause Summary of
change(s)
Comment on
Change(s)
Meets this
Requirement
Needs some
Modification
Clause is not
Applicable
Comments / Notations
8.2.2
new
para
Actually, just a total
rewording dealing
with the need for a
documented
procedure.
Grammar only.
8.2.2
4th para
Simply a move of
part of "old" 3rd
paragraph to a
separate paragraph -
dealing with need to
maintain records.
Grammar only.
8.2.2
5th para
Move of some words,
and added "anynecessary corrections
and corrective."
Clarification of
required actions onthe part of persons
responsible for area
audited to take
action.
8.2.2
Note
Deleted references
to obsolete
documents (ISO
10011-1, -3) andadded reference to
ISO 19011.
Organizations should
obtain a copy of ISO
19011, review and
assess impact oninternal audit
process.
8.2.3
1st para
Deleted "to ensure
conformity of the
product."
This should be self-
evident; also actions
may be taken to
correct the system.
8/4/2019 ISO9001-2008Revisions SQA SedlakConsulting
13/16
Smithers Quality Assessments 2009: www.smithersregistrar.com Phone: 1-866-688-0134
J&S Sedlak, LLC 2009: www.sedlakconsulting.com Phone: 330-936-3436
Current QMS Documentation & Practice ----
Clause Summary of
change(s)
Comment on
Change(s)
Meets this
Requirement
Needs some
Modification
Clause is not
Applicable
Comments / Notations
8.2.3
new
Note
Deals with selection
of monitoring and
measurement
techniques for
processes.
Provides latitude to
management, but
also places onus of
proof that the
defined monitoringand measuring are
the results of a well
executed thought
process.
8.2.4
1st para
Added need to
provide evidence ofproduct conformity.
Just good record
keeping; allowsorganization to use
data for
improvement
actions.
8.2.4
2ndpara
Emphasis on
identification ofperson authorizing
release of product to
the customer.
Someone needs to
say "okay to ship."
8/4/2019 ISO9001-2008Revisions SQA SedlakConsulting
14/16
Smithers Quality Assessments 2009: www.smithersregistrar.com Phone: 1-866-688-0134
J&S Sedlak, LLC 2009: www.sedlakconsulting.com Phone: 330-936-3436
Current QMS Documentation & Practice ----
Clause Summary of
change(s)
Comment on
Change(s)
Meets this
Requirement
Needs some
Modification
Clause is not
Applicable
Comments / Notations
8.2.4
3rd para
Slight change in
word-order dealing
with release of
product to the
customer and suchaction not being
taken until all
required actions are
taken.
No substantive
change.
8.3
1st para
Slight change in
wording of second
sentence dealing
with need for aprocedure for control
of nonconforming
product.
No substantive
change.
8.3
2nd
para
"Where applicable"
added to start of
second applicable.
Recognizes that there
are a myriad of
circumstances that
affect disposition of
nonconformingproduct.
8/4/2019 ISO9001-2008Revisions SQA SedlakConsulting
15/16
Smithers Quality Assessments 2009: www.smithersregistrar.com Phone: 1-866-688-0134
J&S Sedlak, LLC 2009: www.sedlakconsulting.com Phone: 330-936-3436
Current QMS Documentation & Practice ----
Clause Summary of
change(s)
Comment on
Change(s)
Meets this
Requirement
Needs some
Modification
Clause is not
Applicable
Comments / Notations
8.3 d
new
Addresses those
situations where
nonconforming
product may be in
the hands of thecustomer.
Actually, not a new
requirement - simply
a move of the
requirement from
paragraph status tobullet point "d."
8.3
3rd &
4th
paras
Some paragraph
positions changed.
No substantive
change.
8.4 b Deleted reference to
7.2.1; added
reference to 8.2.4.
No substantive
change.
8.4 c Added references to
8.2.3 and 8.2.4
No substantive
change.
8.4 d Added reference to
7.4.
No substantive
change.
8.5.2
1st para
Changed "cause"
(singular) to "causes"
(plural).
Recognized that
there may be one or
more causes for
problems.8.5.2 f Added "the
effectiveness"
Emphasis on the
need for corrective
actions to be
effective - e.g., not
repeat or cause other
issues/problems.
8/4/2019 ISO9001-2008Revisions SQA SedlakConsulting
16/16
Smithers Quality Assessments 2009: www.smithersregistrar.com Phone: 1-866-688-0134
J&S Sedlak, LLC 2009: www.sedlakconsulting.com Phone: 330-936-3436
Current QMS Documentation & Practice ----
Clause Summary of
change(s)
Comment on
Change(s)
Meets this
Requirement
Needs some
Modification
Clause is not
Applicable
Comments / Notations
8.5.3 e Added "the
effectiveness"
Emphasis on the need
for preventive actions
to be effective - e.g.,
truly prevent the
identified potentialproblem and cause
other issues/problems.