Irvine Ranch Water District
SCAP Energy Committee Meeting
IRWD Biosolids Project Update
1
August 26, 2015
Presentation Agenda
• Introduction to IRWD
• IRWD’s Biosolids Project
• Construction Update
2
Introduction to IRWD
Irvine Ranch Water District
A California Special District Serving Central Orange County
Reliable High-Quality Water & Sewer Service
Efficient. Cost Effective. Environmentally Sensitive
High Level of Customer Satisfaction 4
IRWD Service Area
5
6 Cities
Irvine
Lake Forest
Tustin
Newport Beach
Orange
Costa Mesa
Unincorporated Orange County
20% of Orange County Percent of the county covered by IRWD
181 square miles
Size of District
IRWD Services
Drinking Water 4 Water Treatment Plants; 27 wells;
36 reservoirs; 1,500 miles of water
pipeline
Sewage Collection 1,000 miles of collection pipeline
Recycled Water
2 recycled water plants
500 miles of recycled water pipeline
Urban Runoff Treatment
San Joaquin Marsh &
23 built and 45 planned wetland
treatment sites
6
IRWD Customer Base
500,000
District’s Daytime Population
340,000 Residential Customers
105,688
Service connections
93,037 Acre Feet of Water Served
(FY 2012-2013)
One acre-foot = 325,851 gallons = 1,233 m3
7
Biosolids Dewatering & Energy Recovery Project
8
Cost-effective: IRWD customers save up to
$288 million.
Green and sustainable: biogas used to
fuel facility.
Biosolids are processed into pellets and
beneficially used for fertilizer or fuel.
Provide facilities to meet future solids
handling needs.
IRWD Biosolids and Energy Recovery Project
• IRWD to construct facilities at MWRP for:
Centralized biosolids processing
Biogas management & energy recovery
Odor control system
• IRWD reduce solids treatment costs.
• Maximize renewable resources and minimize environmental impacts from residuals.
Project Objectives:
9
10
Major Biosolids Project Components
• Biosolids thickening, digestion, & dewatering
• Drying to produce pellets for local beneficial reuse
• Biogas conditioning
• Microturbines for energy production - Use at MWWP
• Three-stage odor control system plus RTO for dryer
• Recycle Food Waste/FOG to generate biogas and generate energy
11
Biosolids Process Schematic
PRIMARY CLARIFIER
SECONDARY CLARIFIER ACID-METHANE
PHASE ANAEROBIC DIGESTION
DEWATERING CENTRIFUGE
DIGESTED SLUDGE
STORAGE
MICROTURBINES
BIOGAS
ELECTRICITY
CAKE STORAGE &
LOADOUT
CLASS B CAKE HAUL (BACKUP)
ROTARY DRUM DRYER
PELLET STORAGE & LOADOUT
CLASS A PELLET HAUL
FATS, OILS & GREASE
CENTRATE TREATMENT
TO LIQUID TREATMENT
RECYCLED WATER
PS
WAS
THICKENING CENTRIFUGE
THICKENING CENTRIFUGE
DIGESTER GAS CLEANING
(1 MW)
Top View of Project Site at Completion
12
Solids Handling Bldg.
Digester Complex
FOG Station
Power Generation
Centrate Treatment
Po
lym
er
Sto
rage
Od
or
Co
ntr
ol
Ch
em
ical
St
ora
ge
Digestion Facilities Step 2: Methane phase Egg-Shaped Digesters
Digested Sludge Holding Tanks
Step 1: Acid Phase Digesters
Digester Equipment & Control Bldg.
Fats, Oils & Grease Delivery Area
13
Section Through Digester & Control
Building
14
Biogas & Power Generation
15
Biogas Storage
Biogas Conditioning
Microturbines
RTO Emergency Gen Set
16
IRWD Biosolids Project Update
Key Information / Dates Contractor: Filanc/Balfour-Beatty
Contract Amount: $163,465,940
Change Orders to Date (Thru CCO 31) $ 3,400,148 (2.08%)
Revised Contract Amount to Date: $166,866,088
Contractual Calendar Days: 1,278
Additional Days thru Change Orders: 0
Notice of Award: April 29, 2013
Time Elapsed thru July 2015: 64.4%
Contractual Completion Date: October 28, 2016
17
IRWD Biosolids Project Update Construction Schedule
MILESTONE ORIGINAL REVISED per
June 2015 UPDATE
ACTIVITY
June 3, 2013 Notice to Proceed
1 July 6, 2015 May 6, 2016 WAS & Primary Sludge Processing
2 August 20, 2015 June 29, 2016 Sludge Thickening Facilities
3 September 19, 2015 June 7, 2016 FOG Receiving
4 January 17, 2016 August 18, 2016 Anaerobic Digestion Facilities Online
5 March 2, 2016 September 6, 2016 Produce Class B Biosolids (Cake)
6 June 30, 2016 September 6, 2016 Microturbine Power Generation Online
7 August 29, 2016 December 8, 2016 Produce Class A Biosolids (Pellets)
Final October 28, 2016 January 22, 2017 Project Completion
IRWD Biosolids Project Update
18
Aerial View of Western Half of Biosolids Site – Solids Handling Area
Centrate
Treatment
Sludge
Wet Wells
Liquid
Chemica
l Storage
Bulk
Polymer
Storage
Microturbine Area
Sludge
Receiving
Basement
Dryer
Area
Polymer
Room
Stormwater
Pump Station
Polymer
Room
Electrical
Room
Digester
Gas
Holder
19
Concrete Work – Southeast Corner of Solids Handling Building
IRWD Biosolids Project Update
20
Installation of Carbon Steel Digester Gas Holder
IRWD Biosolids Project Update
21
Bulk Polymer Storage Tanks
IRWD Biosolids Project Update
IRWD Biosolids Project Update
22
Preparation for Coating of Liquid Chemical Storage
23
Concrete Slab of Stormwater Pump Station
IRWD Biosolids Project Update
IRWD Biosolids Project Update
24
Aerial View of Eastern Half of Biosolids Site – Digestion Area
Fats, Oils,
and
Grease
Station
Acid
Digester
Area
Digester
Control
Building
Dewatering Feed
Pump Station
Methane
Digester
No. 1
Methane
Digester
No. 2
Methane
Digester
No. 3
Liquid
Chemical
Storage
Sludge Holding
Tank No. 2
Sludge Holding
Tank No. 1
Digester
Gas
Holder
25
Installation of Carbon Steel Plates – Methane Digesters
IRWD Biosolids Project Update
Methane Digester No. 1
Methane Digester No. 2
26
IRWD Biosolids Project Update Installation of Carbon Steel Plates – Methane Digesters
Methane Digester No. 2
Methane
Digester No. 3
27
IRWD Biosolids Project Update Installation of Carbon Steel Plates – Methane Digesters
Methane
Digester No. 2
Methane
Digester No. 3
Methane
Digester No. 1
28
IRWD Biosolids Project Update Rebar Installation for First Floor of Digester Control Building
Methane
Digester No. 3
Methane
Digester No. 1
Acid Phase
Digester No. 1
29
Construction of Acid Phase Digester No. 3
IRWD Biosolids Project Update
30
Stairwell Above Dewatering Feed Pump Station
IRWD Biosolids Project Update
August 2015 Quarterly Report
31
Planned Activities – August to October 2015
• Continue construction of Solids
Handling Facility and Centrate
Treatment Facility
• Start construction of the
Microturbine Area
• Continue construction of
Methane Digesters, Solids
Holding Tanks and Acid
Digesters and Chemical Area
• Install SCE and Gas Services
IRWD Contact Information:
32
Randy Lee Assistant Director of Recycling Operations
(949) 453-5780