Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
IRIS FP7-NMP-2007-LARGE-1
Iris Demonstration Report – Annex A page 1 of 24
D11-1
ANNEX A
PROJECT INFORMATION:
Project Title: INTEGRATED EUROPEAN INDUSTRIAL RISK
REDUCTION SYSTEM
Acronym: IRIS Contract N°: CP-IP 213968-2 Project N°: FP7-NMP-2007-LARGE-1
Project Start: 01 October 2008 Project End: 31 March 2012
REPORT INFORMATION:
Report Title: WP3 DEMONSTRATION REPORT – ANNEX A
Date of Issue: July 2009
Rep. Period: 01 October 2008 – 30 September 2009
Prepared by: VCE Holding GmbH
Authors: Wenzel, Helmut
Veit-Egerer, Robert
Widmann, Monika
Jaornik, Paul
coordinating person:
organisation:
e-mail:
fax:
telephone:
Dr. Helmut Wenzel
VCE Holding GmbH
+43-1-893 86 71
+43-1-897 53 39
IRIS FP7-NMP-2007-LARGE-1
Iris Demonstration Report – Annex A page 2 of 24
IRIS (Integrated European Industrial Risk Reduction
System)
Bridge Object S101
(Reibersdorf / Upper Austria)
Progressive Damage Test
(10. – 13. 12. 2008)
Helmut Wenzel Robert Veit-Egerer
Monika Widmann Paul Jaornik
Carriageway Salzburg
Carriageway Vienna
South North
Cross section where tendons were cut through
Column which was lowered
IRIS FP7-NMP-2007-LARGE-1
Iris Demonstration Report – Annex A page 3 of 24
Introduction
The flyover S101 is a typical prestressed concrete bridge from the early 1960ies. It was
decided to replace it due to insufficient carrying capacity and its maintenance condition
(both visual inspection driven rating). At the same time the bridge did not meet the
current requirements, as the structure did not fit into the overall traffic and
infrastructure concept anymore. In other words demolition was aspired anyway, because
the bridge was to small for the location.
The major objective of the current progressive damage test is to emphasize refined
methods for the analysis of upcoming, slowly progressing damage and its effects on
parameters of dynamic response.
In the course of the IRIS project VCE (together with the Alpine construction company
and the University of Tokyo) takes the opportunity of this certain damage test - given by
the bridge operator ASFINAG - to demonstrate the impact of scientific insight and
findings with regard to reduced uncertainties to support the decision process of
infrastructure owners in the course of cost planning for maintenance and possible
rehabilitation measures in general.
In the present report the followed measurement agenda from the 10th to the 13th of
December 2008 is documented. In the end the structuring of the recorded data into
several measurements is described.
IRIS FP7-NMP-2007-LARGE-1
Iris Demonstration Report – Annex A page 4 of 24
Wednesday 10.12.2008
Weather observation:
Temperature: – 2°C; mist, easterly wind with approx. 2 m/s
Previous day: sunny weather – temp. -9°C in the morning, approx. -2° C at midday
Preparations for the progressive damage test - Evaluation of structural safety
with regard to the pier’s crossbeam and its foundation:
12:56 Start of operation of the BRIMOS-Recorder - placed at the western main
girder in the middle of the main span.
13:08 The supporting pier was hydraulically loaded with 120 t (250 bar – conform
to the bridge pier’s regular normal force)
13:25 The bridge was stressed with a test load of 144 t for a period of 10 min
(measurement S101REIT_081210A_MAINSPAN file S101REIT_01-05).
No cracks or any other indications of damage appeared at the structure
13:40 End of the load test. No reactions at the structure, no cracks or any other
indications of damage. Afterwards the load was taken away from the
supporting pier.
After that the BRIMOS sensor grid was set up and a geodetic levelling was
conducted.
17:16 Start of measurement with a dense BRIMOS sensor grid
IRIS FP7-NMP-2007-LARGE-1
Iris Demonstration Report – Annex A page 5 of 24
Measuring system
Fig. 1: Sensor layout – BRIMOS Recorder; 10th of December 08
Tab. 1: Measurement specification - BRIMOS Recorder – 10th of December 08
Fig. 2: Sensor layout - BRIMOS sensor grid – 10th of December 08
position [m]
length cross
R1 (BRIREC) 28 6.2 Längs length
Quer crossVertikal vertical
sensor channel direction
IRIS FP7-NMP-2007-LARGE-1
Iris Demonstration Report – Annex A page 6 of 24
Tab. 2: Measurement specification – BRIMOS sensor grid – 10th of December 08
position [m]
length cross
E105 56 6.2 weiss_laengs length
weiss_quer cross
weiss_vertikal vertical
E204 50 6.2 gruen_laengs length
gruen_quer cross
gruen_vertikal vertical
E210 47 6.2 braun_laengs length
braun_quer cross
braun_vertikal vertical
E103 44 6.2 gelbgruen_laengs length
gelbgruen_quer cross
gelbgruen_vertikal vertical
E202 40.8 6.2 schwarz_laengs length
schwarz_quer cross
schwarz_vertikal vertical
E201 37.6 6.2 lila_vertikal length
lila_quer cross
lila_vertikal vertical
E205 34.4 6.2 rot_laengs length
rot_quer cross
rot_vertikal vertical
E102 31.2 6.2 gelb_laengs length
gelb_quer cross
gelb_vertikal vertical
E101 28 6.2 blau_laengs length
blau_quer cross
blau_vertikal vertical
E207 28 1 E3_laengs length
E3_quer cross
E3_vertikal vertical
E209 24.8 6.2 E6_laengs length
E6_quer cross
E6_vertikal vertical
E206 21.6 6.2 E2_laengs length
E2_vertikal cross
E2_quer vertical
E203 18.4 6.2 E5_laengs length
E5_quer cross
E5_vertikal vertical
E104 12 6.2 E4_laengs length
E4_quer cross
E4_vertikal vertical
E109 6 6.2 E1_laengs length
E1_quer cross
E1_vertikal vertical
sensor channel direction
Please pay attention to an exception between the German and English channel denomination
Please pay attention to an exception between the German and English channel denomination
IRIS FP7-NMP-2007-LARGE-1
Iris Demonstration Report – Annex A page 7 of 24
Thursday 11.12.2008
Weather observation:
Temperature in the morning: – 1°; mist; no precipitation; no wind.
In the course of the day the temperature increased up to + 1°. The other weather
conditions remained unchanged.
Damage test lowering of a column – Additional restraint loading case:
07:00 preparing of the cutting line at the north-western column by the Seidl
company
07:35 Hydraulic loading of the supporting pier and increase up to 120 t; fixing with
adjusting collars
08:12 Start of cutting through the pier
08:35 the first cut is completed. No reaction, no noise, no spalling. A geodetic
levelling was conducted at the structure to fix the altitude of the points. All
measurement sensors are applied and in operation.
09:07 start of the second cutting – 10 cm above the first one.
09:33 finalisation of the second cut. No restoring forces observed
11:00 first lowering of the pier by 1 cm. The adjusting collar was released and
adjusted to 1 cm. Subsequently the pier was lowered rapidly and displaced at
the adjusting collar. A moderate noise of relaxation coming form the
IRIS FP7-NMP-2007-LARGE-1
Iris Demonstration Report – Annex A page 8 of 24
supporting pier was noticed. No cracks or other indications of damage were
remarked at the structure. The lowering is clearly visible in the signal of the
laser-displacement channel. Alteration at the signals of the measurement
system. A slight decrease of the first eigenfrequency – already after the
cutting and before the first lowering of the pier - was also observed.
The plate of concrete which was cut out of the pier was examined in a
detailed manner. The concrete quality is very good. Only at one corner a
spalling in combination with rust is observable. The concrete reinforcement is
in remarkably good condition. The three bolts with a diameter of 26 mm were
actually at the position marked on the drawing. The quality is better than
having been expected after the visual inspection.
12:00 second step of lowering (second centimetre) analogue to the first step.
During the settling a displacement of 21 mm in direction to the middle of the
bridge was noticed at the column base. That reaction is not conform to the
finite element calculations. According to that there should be just a relatively
small inward reaction.
Within the next 2 hours no change (cracks or other indications of damage)
was noticed.
14:00 third step of lowering (third centimetre)
The lowering causes an additional horizontal displacement 10 mm. Due to the
fact that the elastic limit was reached at 7 mm of vertical deformation, the
total amount of additional 10 mm of lowering could not be accomplished.
Based on the performed static calculations the elastic limit was expected at
32 mm of vertical deformation instead of 27mm obtained in reality. This fact
can probably be explained by the low temperature during the test (influence
of already removed pavement ?). At the intact column – next to the lowered
one - a new horizontal crack appeared. The already existing cracks hadn’t
enlarged. It was decided to wait one hour to declare if phenomena of
structural creeping appear or if the structure remains in the same condition.
15:00 The gap between the adjusting collar and the hydraulic jack did not
disappear. This means that no non-linear processes causing a further
lowering of the column could be expected. Therefore it was decided to stop
the test at this stage.
The bridge was lifted marginally to insert compensating plates. Another
geodetic levelling stated the final altitude of the bridge deck.
The BRIMOS measurement system was prepared for the night and it was
decided to continue with the tests - starting at 8 o’clock the following
morning.
IRIS FP7-NMP-2007-LARGE-1
Iris Demonstration Report – Annex A page 9 of 24
Measuring system
Additionally to the dense BRIMOS sensor grid the following measurement equipment
was installed at the structure during the day:
• The BRIMOS-Recorder - placed at its new position – above the north-western
column (the one to be cut & lowered).
• The laser-displacement unit in the middle of the bridge’s main span above the
western main girder.
• One Etna-Recorder in the middle of the bridge’s main span (at the western
footpath), one on the eastern footpath.
• The team of the University of Tokyo also arranged their measurement system,
which was distributed stepwise all over the structure.
Fig. 3: Sensor layout – overview - 11th of December in 2008
IRIS FP7-NMP-2007-LARGE-1
Iris Demonstration Report – Annex A page 10 of 24
Fig. 4: Sensor layout – Brimos-Recorder and two ETNA-Recorders – 11th of December
08
IRIS FP7-NMP-2007-LARGE-1
Iris Demonstration Report – Annex A page 11 of 24
Tab. 3: Measurement specification - BRIMOS- & ETNA-Recorders – 11th of December 08
Fig. 5: Sensor layout - BRIMOS sensor grid - 11th of December 08
position [m]
length cross
R1 (BRIREC) 44 6.2 Längs length
Quer cross
Vertikal vertical
E1 (Etna) 29.5 6.2 Längs length
Quer cross
Vertikal vertical
E2 (Etna) 29.5 1 Längs length
Quer crossVertikal vertical
sensor channel direction
IRIS FP7-NMP-2007-LARGE-1
Iris Demonstration Report – Annex A page 12 of 24
Tab. 4: Measurement specification - BRIMOS sensor grid – 11th of December 08
position [m]
length cross
E105 56 6.2 weiss_laengs length
weiss_quer cross
weiss_vertikal vertical
E204 50 6.2 gruen_laengs length
gruen_quer cross
gruen_vertikal vertical
E210 47 6.2 braun_laengs length
braun_quer crossbraun_vertikal vertical
E103 44 6.2 gelbgruen_laengs length
gelbgruen_quer crossgelbgruen_vertikal vertical
E202 40.8 6.2 schwarz_laengs length
schwarz_quer crossschwarz_vertikal vertical
E201 37.6 6.2 lila_vertikal length
lila_quer cross
lila_vertikal vertical
E205 34.4 6.2 rot_laengs length
rot_quer cross
rot_vertikal vertical
E102 31.2 6.2 gelb_laengs length
gelb_quer cross
gelb_vertikal vertical
E101 28 6.2 blau_laengs length
blau_quer cross
blau_vertikal vertical
E207 28 1 E3_laengs length
E3_quer cross
E3_vertikal vertical
E209 24.8 6.2 E6_laengs length
E6_quer cross
E6_vertikal vertical
E206 21.6 6.2 E2_laengs length
E2_vertikal cross
E2_quer vertical
E203 18.4 6.2 E5_laengs length
E5_quer crossE5_vertikal vertical
E104 12 6.2 E4_laengs length
E4_quer crossE4_vertikal vertical
E109 6 6.2 E1_laengs length
E1_quer crossE1_vertikal vertical
Laser 28 5 Laser_X cross
Laser_Z vertical
Laser_Z_Glatt vertical-smoothed
sensor channel direction
Please pay attention to an exception between the German and English channel denomination
IRIS FP7-NMP-2007-LARGE-1
Iris Demonstration Report – Annex A page 13 of 24
Friday 12.12.2008
Weather observation:
Temperature: 0°C, partly cloudy, light snowfall during the night, wind velocity 3 m/s
from the west; snow is lying on the structure (this means that the structure’s
temperature is below 0°C)
Damage test lowering of a column:
No settlement of the column during the night, it is still in the elastic region.
No changes were noted
IRIS FP7-NMP-2007-LARGE-1
Iris Demonstration Report – Annex A page 14 of 24
08:00 reinitialization of the measurement system which was running during the
whole night
The laser, the Brimos-Recorder as well as the two Etna-Recorders were set
up again. Identical to the day before the Brimos-Recorder is situated directly
above the column which was cut through, whereas the Etna-Recorders were
situated on both sides midspan.
A levelling was performed.
08:35 Lifting of the column a little bit above the original level, steel plates were
inserted.
A levelling was performed afterwards.
08:49 End of returning the column into its initial position (after the lowering test).
The new level was approx. 6 mm above the original one. A quiet noise caused
by the load distribution was noticed. The cracks at the opposite column are
closed again. This means the reinforced concrete is in successful operation
again. The decisive horizontal cracks move analogue to the deformations.
A levelling was performed afterwards.
12:50 A levelling was performed.
The temperature raised up to 2°C, the snow is melting but remains longer on
the structure itself then in the surrounding area.
IRIS FP7-NMP-2007-LARGE-1
Iris Demonstration Report – Annex A page 15 of 24
Damage test intersecting tendons:
13:10 Start of exposing the cables, which are easy to find by cutting the concrete.
13:43 End of exposing the cables.
The concrete quality is quite good (just as the protection concrete). The
cables are externally undamaged, not rusted and well filled.
13:45 Cutting out of a 10 cm long piece of the first cable. The strands shortened to
2 mm less in length.
No noises were noticed.
Another levelling was made afterwards. A visual inspection was done at the
structure but no cracks or other new indications of damage were found.
In the afternoon a vibrating roller was working next to the bridge (westward)
causing vibrations which were clearly noticeable on the bridge – particularly
after the first cable was cut through.
15:45 The second cable was intersected.
After the second cable was intersected the strands shortened similar to those
of the first one. Single wires were removed to find out whether they corrode
or not. No rust was found. The bridge did not show any indications of
structural changes, cracks etc.
A levelling was done, without any obvious deviation regarding the previous
one.
During the night all 15 sensors of the measurement grid were kept in service
whereas the recorders as well as the laser-based displacement measurement
were removed.
Subsequently to every scheduled step of the experimental campaign a visual inspection
was performed in order to detect possible damage indications. After the first cable was
cut through an extensive inspection was done but no new damages could be found. The
crack formation at the north-eastern column was investigated accurately. Altogether six
cracks in relatively constant distances were observed. After the bridge was returned into
IRIS FP7-NMP-2007-LARGE-1
Iris Demonstration Report – Annex A page 16 of 24
its initial position the cracks were closed again. The distances between the cracks were
measured as follows: 17 + 23 + 30 + 23 + 28 cm.
Conclusions until now:
• The bridge’s manufacturing quality with regard to the used materials is generally
quite good.
• The only apparent defect is the too low reinforced concrete cover (coverage).
• The load bearing capacity seems to be 15% higher than the computed value.
• The structure’s behaviour fully correlates with the expectations, unexpected
effects did not occur.
• Even if the structure was seriously damaged, it still indicated a good, redundand
nature. The analytical investigation predicted local losses (e.g. at the bottom of
the column) which did not occur on site.
• Local damages at the internal prestressing did not induce geodetically confirmed
changes.
• The measurement system had registered all changes and enables an accurate
assessment of changes in the structure’s integrity as well as the load bearing
capacity.
• Bending moments and axial forces related to internal restraint (shrinkage effects
confirmed by frame analysis) were relieved completely due to creeping. No
associated reactions were observed.
IRIS FP7-NMP-2007-LARGE-1
Iris Demonstration Report – Annex A page 17 of 24
Measuring system
Additionally to the dense BRIMOS sensor grid the following measurement equipment
was installed at the structure during the day:
• The BRIMOS-Recorder above the north-western column (the one to be cut &
lowered).
• The laser-displacement unit in the middle of the bridge’s main span above the
western main girder.
• One Etna-Recorder in the middle of the bridge’s main span (at the western
footpath), one on the eastern footpath.
Fig. 6: Sensor layout – overview - 12th of December in 2008
The sensor-layout of the BRIMOS- and ETNA-Recorders as well as the one of
the BRIMOS sensor grid is identical to the one the day before.
IRIS FP7-NMP-2007-LARGE-1
Iris Demonstration Report – Annex A page 18 of 24
Fig. 7: Sensor-layout - BRIMOS- Recorder and two ETNA-Recorder – 12th of December
08
Fig. 8: Sensor layout - BRIMOS sensor grid - 12th of December 08
IRIS FP7-NMP-2007-LARGE-1
Iris Demonstration Report – Annex A page 19 of 24
Saturday 13.12.2008
Weather observation:
Temperature: - 0.5°C, light snowfall during the night, snow is lying on the bridge, high
fog, no wind
Damage test intersecting tendons:
08:20 The third tendon is cut through. The strands shortened as expected. No
noises or other indications of changing conditions. No cracks or other damage
indication arised at the visual inspection.
08:33 In the signal of the laser a shifting is visible. The middle of the structure has
declined for just a few millimetres (structural rearrangement). That’s why it is
decided to stop doing more severe damages.
To control the values of the levelling it was repeated. The output is consistent
with the day before. The cracks at the eastern pier have not changed since
the day before. This means that there was no torsional movement.
10:15 another levelling was done
10:30 Revealing of the fourth strand and removing of the cement injection. Slight
flash rust on the wires (probably due to the installation); afterwards 5 wires
are intersected. The concerned wires shortened. Six more wires are
intersected.
After that the progressive damage test is stopped.
10:50 Start of removing the measurement equipment.
IRIS FP7-NMP-2007-LARGE-1
Iris Demonstration Report – Annex A page 20 of 24
The visual inspection does not indicate any addidional changes.
Another levelling is done – the result does not differ from the one before.
Demolition of the bridge
19:00 embargo of the motorway and preparing of the demolition
20:00 the bridge is cut through in midspan. As expected that doesn’t cause a
structural collapse.
21:00 The southern part of the bridge was removed with a demolition shear and
two hydraulic breakers. The structure offered a lot of resistance. The tendons
got exposed to a great extent, the wires were visible. There were no obvious
damages or rust at the prestressing. The reinforcement worked as intended
and kept all parts together well. A try to cause a collapse of the southern part
of the bridge failed due to the high redundancy of the bridge. The concrete
quality was equally good at all parts of the bridge. The south-eastern column
was broken off but it did not collapse before most of the concrete was
removed.
After the demolition the condition of several parts of the bridge was
documented.
IRIS FP7-NMP-2007-LARGE-1
Iris Demonstration Report – Annex A page 21 of 24
Measuring system
Additionally to the dense BRIMOS sensor grid the following measurement equipment
was installed at the structure during the day:
• The BRIMOS-Recorder above the north-western column (the one to be cut &
lowered) – started at approx. 7:50 am.
• The laser-displacement unit in the middle of the bridge’s main span above the
western main girder.
• One Etna-Recorder in the middle of the bridge’s main span at the western
footpath (started at approx. 08:00 am), one on the eastern one (started at
approx. 8:10 am).
IRIS FP7-NMP-2007-LARGE-1
Iris Demonstration Report – Annex A page 22 of 24
Fig. 9: Sensor layout – overview - 13th of December in 2008
The sensor-layout of the BRIMOS- and ETNA-Recorders as well as the one of
the BRIMOS sensor grid is identical to the one the day before.
Fig. 10: Sensor layout - BRIMOS- Recorder and two ETNA-Recorder – 13th of December
08
Fig. 11: Sensor layout - BRIMOS sensor grid - 13th of December 08
IRIS FP7-NMP-2007-LARGE-1
Iris Demonstration Report – Annex A page 23 of 24
Conclusions:
• Prestressing, concrete quality and reinforcement were in faultless condition
• The system showed an extraordinary redundancy. Even though one column was
removed completely hardly any changes were noticeable.
• The structure showed a great persistence and an excellent behaviour concerning
rearrangement.
• To sum up, sudden failure without any previous indication at a similar structure
of the same quality can be excluded.
The progressive damage campaign established essential knowledge concerning the
assessment of prestressed structures. The structure’s behaviour was better than it was
estimated due to the numerical analysis at all times. First impression into the
measurements indicate, that already very slight artificial damage, induced into the
bridge can be identified and assessed very clearly. Doubts, generally raised with regard
to internally prestressed concrete structures, are unjustifiable in the present case.
IRIS FP7-NMP-2007-LARGE-1
Iris Demonstration Report – Annex A page 24 of 24
Structuring of the recorded data
Due to the huge amount of data they were subdivided into several partial
measurements. Those of the Brimos sensor grid were separated according to the
various damage states – characterised in the measurement description - whereas the
MAINSPAN-measurements in each case contain all the data recorded by one particular
Recorder placed on a precise position of the bridge. Data gaps in the MAINSPAN-
measurements result from the fact that the Recorders were removed during the nights –
unlike the Brimos sensor grid which was constantly measuring from the 10th Dec 08
05:16 PM to the 13th Dec 08 11:14 AM.
measurements with the Brimos sensor grid
S101REIT_081210A_DECK 10.12.2008 05:16 PM 11.12.2008 07:13 AM undamaged structure
S101REIT_081211A_DECK 11.12.2008 07:13 AM 11.12.2008 10:21 AM the north-western column was cut through
S101REIT_081211B_DECK 11.12.2008 10:21 AM 11.12.2008 11:49 AM first step of lowering the column (1cm)
S101REIT_081211C_DECK 11.12.2008 11:49 AM 11.12.2008 01:39 PM second step of lowering the column (2cm)
S101REIT_081211D_DECK 11.12.2008 01:39 PM 11.12.2008 02:45 PM third step of lowering the column (3cm)
S101REIT_081211E_DECK 11.12.2008 02:45 PM 12.12.2008 05:52 AM compensating plates are inserted
S101REIT_081212A_DECK 12.12.2008 08:04 AM 12.12.2008 01:12 PM column returned in original position
S101REIT_081212B_DECK 12.12.2008 01:12 PM 12.12.2008 03:03 PM first tendon intersected
S101REIT_081212C_DECK 12.12.2008 03:03 PM 13.12.2008 05:44 AM second tendon intersected
S101REIT_081213A_DECK 13.12.2008 05:44 AM 13.12.2008 10:08 AM third tendon intersected
S101REIT_081213B_DECK 13.12.2008 10:08 AM 13.12.2008 11:14 AM single wires of the fourth tendon intersected
measurements with the Brimos- and Etna-Recorders
S101REIT_081210A_MAINSPAN 10.12.2008 01:00 PM 10.12.2008 06:02 PMBrimos-Recorder placed in the middle of the
main span
S101REIT_081211A_MAINSPAN 11.12.2008 07:35 AM 13.12.2008 10:50 AMBrimos-Recorder placed above the north-
western column
S101REIT_081211B_MAINSPAN 11.12.2008 08:17 AM 13.12.2008 10:50 AMEtna-Recorder placed in the middle of the main
span at the western footpath
S101REIT_081211C_MAINSPAN 11.12.2008 07:35 AM 13.12.2008 10:56 AMEtna-Recorder placed in the middle of the main
span at the eastern footpath
measurement descripitionmeasurement Start End
Tab. 5: List of all measurements recorded during the progressive damage test from the
10th to the 13th of Dec 08
As the sensors E1, E2, E3, E4, E5 and E6 were recorded by an additional – secondary –
measurement system which is not equipped with a hardware filter an additional
preconditioning of these data is necessary by means of an introductive bandpass-
filtering.