16
IRED-NEDO Smart Community Showcase 2018 October 16, 2018 © 2015 San Diego Gas & Electric Company. All trademarks belong to their respective owners. All rights reserved. Les Young Project Manager II Vanadium Redox Flow Battery Demonstration at SDG&E

IRED-NEDO Smart Community Showcase 2018

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: IRED-NEDO Smart Community Showcase 2018

IRED-NEDO Smart CommunityShowcase 2018

October 16, 2018

© 2015 San Diego Gas & Electric Company.All trademarks belong to their respective owners. All rights reserved.

Les YoungProject Manager II

Vanadium Redox Flow Battery Demonstration at SDG&E

Page 2: IRED-NEDO Smart Community Showcase 2018

How Storage Fits Within SDG&E’s Mission

2

Our Mission

We improve lives and communities by building the cleanest, safest and most reliable energy company in America.

Page 3: IRED-NEDO Smart Community Showcase 2018

Regulatory Drivers

• CPUC Mandate AB 2514

– Initial energy deployment targets in California for utilities

– Storage goals split between Transmission, Distribution and Customer

domains

– Deployment can be shifted between domains within limits

• AB 2868

– Further deployment of 167 MW of energy storage

– Programs and investments targeted toward public sector and low-income

customers will be prioritized by the CPUC

•Distribution Resource Plan/Integrated Distributed Energy Resources

– Provides the foundation for further evaluation and deployment of DER in

California

– Changes utility systems and processes to establish DER hosting capacity and

benefit streams

Procurement Targets and Current Progress

Transmission Distribution Customer Total

Established Target 80 MW 55 MW 30 MW 165 MW

Page 4: IRED-NEDO Smart Community Showcase 2018

Energy Storage Use Cases

• Likely Use Cases for the Distribution System

– Renewables integration

– Equipment deferral

– Reliability (islanding/grid forming/blackstart)

Source: DOE/EPRI Electricity Storage Handbook

Page 5: IRED-NEDO Smart Community Showcase 2018

Existing & Planned Energy Storage Deployments at SDG&E

Substation Energy Storage – deployed adjacent to the substation interconnecting at either

distribution or transmission level

Community Energy Storage – deployed on the secondary side of a distribution transformer

Market Energy Storage Systems – deployed SES that participate in the CAISO marketplace

Distributed Energy Resource Aggregations– collections of SES and CES aggregations bundled for market

participation

Existing Pending (Approved by CPUC)

– Customer 23.91MW - Distribution 13.5MW

– Distribution 43.65 MW - Transmission 70MW

– Transmission 40MW

Page 6: IRED-NEDO Smart Community Showcase 2018

Existing Energy Storage 44 MW/175 MWh

Ortega Hwy 1 MW/3 MWh

&

Ortega Hwy2 1 MW/3 MWh

Pala 500 kW/1500 kWh

&

Pala2 1 MW/2 MWh

Borrego MG 500 kW/1500 kWh

&

Borrego AES 1 MW/3 MWh

Carmel Valley 1 MW/3 MWh

Redox Flow Battery, Bonita 2 MW/8 MWh

Escondido 30 MW/120 MWh

El Cajon 7.5 MW/30 MWh

Page 7: IRED-NEDO Smart Community Showcase 2018

SDG&E / SEI VRF History

• The Japanese government, via NEDO and Sumitomo Electric, sought a California IOU partner for a United States demonstration project

• NEDO was providing $20M to fund Sumitomo to manufacture and install the battery plant

• NEDO and Sumitomo wanted to provide a full-scale system, between 2-8 MW interconnected and operated on an IOU’s distribution system

• Support any use cases determined by the IOU to be most beneficial

• SDG&E was chosen as the IOU member to partner with Sumitomo.

• Sumitomo Electric and SDG&E signed an agreement in April 2016

• Redox Flow battery was installed at the Miguel substation in Bonita, CA 2MW/8MWh

• The Redox Flow Battery was fully operational June 2017

23

Page 8: IRED-NEDO Smart Community Showcase 2018

SDG&E VRF Connection Network

23

Page 9: IRED-NEDO Smart Community Showcase 2018

VRF – Miguel Substation Installation

Page 10: IRED-NEDO Smart Community Showcase 2018

0

1

2

3

4

5

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Average Hourly Power Profile

January February March April May June July August September October November December

Circuit Information

• Site : Adjacent to SDG&E Substation• Connected feeder line :

• 12 kV Overhead• High PV Penetration, duck curve• Increasing load, needs of deferral

11.85

11.9

11.95

12

12.05

12.1

12.15

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Average Hourly Voltage Profile

January February March April May June July August September October November December

• Battery Size : 2 MW, 8MWh – Two Battery banks

• Functions : peak shaving and base loading, capacity firming, voltage regulation, frequency regulation

Page 11: IRED-NEDO Smart Community Showcase 2018

Substation

Voltage regulation

Voltage regulationCapacity deferralCapacity firm ing

Energy storage

Example of Operation

Page 12: IRED-NEDO Smart Community Showcase 2018

Example of Operation

Peak Shaving & Base Loading (flatten the load curve of feeder)

Connected to the Circuit

Manual setting, not optimized

6/22

8am 10am 12pm 2pm 4pm 6pm 8pm 10pm

6/23

12am 2am 4am 6am 8am 10am 12pm 2pm

2MW

1MW

3MW

Page 13: IRED-NEDO Smart Community Showcase 2018

Example of Operation

6/22

8am10am 12pm

3.116

MW

2.116

MW

1.116

MW

4.116

MW

6/24

12am 2am 4am 6am 8am 10am 12pm 2pm 4pm 6pm 10pm

6/25

12am 2am 8am 10am 12pm 2pm8pm 4am 6am 4pm

Page 14: IRED-NEDO Smart Community Showcase 2018

Summary of Operations from June 2017 to July 2018

Page 15: IRED-NEDO Smart Community Showcase 2018

Summary of Lessons Learned

Needs

- Market participation

- Mitigate intermittency of PV

- Store excess renewables

- Ramp support

Customers

- Bill control

- Outage mitigation

Use Case Drives Technology Choice

- Power vs. energy

- Technology cost

- Technology safety

Challenges & Barriers Exist

Page 16: IRED-NEDO Smart Community Showcase 2018

Questions?

Les Young

Project Manager II

[email protected]

Thank You