Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Independent Qualified Registered Professional Engineer
Design Assessment Report
For
Tank Farm Infrastructure Upgrades and Storage Pad System for
Tank Side Cesium Removal (TSCR) Project
IQRPE Design Assessment Report
No. DA-316542-01
Rev. 0
Prepared By
12 W. Kennewick Ave.
Kennewick, WA 99336
At the request of
Richland, Washington 99352
Meier Project No. 19-8451
WRPS Subcontract No. 64658, Release 017
September 23, 2019
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 2 of 58
Meier Project No. 19-8451
TABLE OF CONTENTS
1.0 INTRODUCTION ................................................................................................................5 PROJECT DESCRIPTION ........................................................................................5 DESIGN REVIEW REQUIREMENTS ...................................................................28
DESIGN OVERVIEW FOR TSCR UPGRADES PROJECT .................................28 TSCR Upgrades Project: DST 241-AP-106 - Riser 2 .................................29 TSCR Upgrades Project: DST 241-AP-107 - Mixer Pump Pit 241-
AP-07F ........................................................................................................29 TSCR Upgrades Project: DST 241-AP-108 - Riser 15 ...............................31
TSCR Shield Box ........................................................................................32 TSCR Enclosure HIHTL Strongback .........................................................32 Hose-in-Hose Transfer Lines Assemblies (HIHTL) ...................................32 TSCR Process Enclosure Pad .....................................................................33
SCOPE OF IQRPE DESIGN ASSESSMENT .........................................................33 Portions of the TSCR Upgrades Project Included in Scope for
IQRPE Certification ....................................................................................33 Portions of the TSCR Upgrades Project Not Included in Scope for
IQRPE Certification ....................................................................................33
2.0 ASSESSMENT SUMMARY .............................................................................................33 CODES, STANDARDS, AND REGULATIONS ...................................................34
BASIS OF DESIGN .................................................................................................34 Structural Design Standards ........................................................................35
Waste Compatibility....................................................................................41 Corrosion Analysis ......................................................................................42 Anticipated Chemistry and Controls ...........................................................42
Pressure Control System .............................................................................44
Secondary Containment System .................................................................47 Ancillary Equipment Design .......................................................................49 P&ID Review ..............................................................................................49
Corrosion Assessment .................................................................................49
3.0 DESIGN REVIEW ASSESSMENT CERTIFICATIONS..................................................50
4.0 REFERENCES ....................................................................................................................52
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 3 of 58
Meier Project No. 19-8451
Figures
Figure 1-1: Hanford Map Showing the Location of the AP DST Tank Farm in the 200
East Area ..................................................................................................................6
Figure 1-2: AP Farm TSCR Upgrades General Arrangement (H-14-111331, Sheet 1) ..................7
Figure 1-3: Dome Penetrations for Double-Shell Tank 241-AP-106 (H-14-010503, Sheet
6) ..............................................................................................................................8
Figure 1-4: Dome Penetrations for Double-Shell Tank 241-AP-107 (H-14-010503, Sheet
7) ..............................................................................................................................9
Figure 1-5: Dome Penetrations for Double-Shell Tank 241-AP-108 (H-14-010503, Sheet
8) ............................................................................................................................10
Figure 1-6: 241-AP-106 Riser 2 Dropleg Assembly (H-14-111344, Sheet 2) ..............................11
Figure 1-7: 241-AP-106 Riser 2 Shield Box Assembly (H-14-111345, Sheet 1) .........................12
Figure 1-8: 241-AP-07F Cover Plate (H-14-111338, Sheet 1) ......................................................13
Figure 1-9: 241-AP-07F Riser Adapter (H-14-111337, Sheet 1) ..................................................14
Figure 1-10: 241-AP-107 Transfer Pump (SK-AP-07F-001, Sheet 1) ..........................................15
Figure 1-11: 241-AP-07F Dropleg Discharge (H-14-111336, Sheet 1) ........................................16
Figure 1-12: 241-AP-07F Pump Dummy Assembly (H-14-111365, Sheet 1) ..............................17
Figure 1-13: 241-AP-07F Jumper Assembly AP07F-WT-J-[P1-P2-(A)] (H-14-111334,
Sheet 2) ..................................................................................................................18
Figure 1-14: 241-AP-07F Jumper Assembly AP07F-WT-EPDMJ-[A-B] (H-14-111342,
Sheet 1) ..................................................................................................................19
Figure 1-15: 241-AP-07F Jumper Assembly AP07F-WT-EPDMJ-[C-D] (H-14-111335,
Sheet 1) ..................................................................................................................20
Figure 1-16: 241-AP-07F HIHTL Strongback Assembly (H-14-111340, Sheet 2) ......................21
Figure 1-17: 241-AP-07F Shield Box Assembly (H-14-111341, Sheet 1) ....................................22
Figure 1-18: 241-AP-108 Riser 15 Containment (H-14-111347, Sheet 1) ....................................23
Figure 1-19: 241-AP-108 Riser 15 Dropleg Assembly (H-14-111346, Sheet 2) ..........................24
Figure 1-20: 241-AP-108 Riser 15 Containment - Section View (H-14-111331, Sheet 2) ...........25
Figure 1-21: 241-AP TSCR Shield Box Assembly (H-14-111348, Sheet 1) ................................26
Figure 1-22: 241-AP TSCR Enclosure HIHTL Strongback Assembly (H-14-111360,
Sheet 1) ..................................................................................................................27
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 4 of 58
Meier Project No. 19-8451
Tables
Table 1: TSCR Upgrades Project Component Features ................................................................34
Table 2: Materials in Contact with Tank Waste ............................................................................41
Table 3: Select Physical Characteristics of Waste Feed ................................................................43
Table 4: Select Chemical Components of Waste Feed ..................................................................43
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 5 of 58
Meier Project No. 19-8451
1.0 INTRODUCTION
Washington Administrative Code (WAC) 173-303-640, Tank Systems, provides a set of
requirements for owner/operators of dangerous waste tank systems. This Design Assessment
Report is prepared for Washington River Protection Solutions, LLC (WRPS), by an Independent
Qualified Registered Professional Engineer (IQRPE) to certify that the proposed tank system will
have sufficient structural integrity and is acceptable for storing and treating dangerous waste per
WAC 173-303-640(3)(a), Design and Installation of New Tank System and Components.
The IQRPE maintains “independence” at all times, however, comments by others are considered
by the IQRPE during the preparation of reports and plans. Only the IQRPE can implement changes
to the master IQRPE documents.
PROJECT DESCRIPTION
Background
The Direct Feed Low Activity Waste (DFLAW) Project (T1P190) is executing the design and
construction of the necessary upgrades to the Tank Farms to allow the integration and operation
of the Tank Side Cesium Removal (TSCR) Demonstration Project for the processing of tank waste.
Tank supernatant waste will be pretreated in the TSCR Process Enclosure, (Project TD101). Feed
for the TSCR system is provided from Double-Shell Tank (DST) 241-AP-107 and treated waste
will be transferred from TSCR to DST 241-AP-106. For simplicity in this report, this Tank Farm
Infrastructure Upgrades and Storage Pad System for TSCR Project will be hereafter referred to as
the TSCR Upgrades Project. The TSCR Upgrades Project will also enable transferring treated waste
from DST 241-AP-106 to Waste Treatment Plant (WTP) and receiving treated effluent from WTP
into DST 241-AP-102.
TSCR Upgrades Project will modify a subset of the 241-AP Farm DST system, specifically three
(3) AP Tank Farm tanks (241-AP-106, 241-AP-107 and 241-AP-108). TSCR Upgrades will
provide the infrastructure to transfer supernatant waste to TSCR and receive TSCR plant wash
returns (filter backwash, ion exchange column (IXC) caustic/water rinses, and secondary
containment sump pump liquids) and TSCR process vent effluent. The TSCR Upgrades design
will include the routing of hose-in-hose transfer lines (HIHTLs), new jumper arrangements, and
pump installation in pit locations.
The TSCR Upgrades Project will support work that will occur on the Hanford Nuclear Reservation
in the 200 East Area.
IQRPE Scope
Meier Architecture • Engineering (Meier) provided an IQRPE to perform the design assessment
per WRPSs Statement of Work (SOW) No. 316542, IQRPE Design Assessment of Tank Farm
Infrastructure Upgrades Project for Tank Side Cesium Removal System (TSCR). The scope
includes an IQRPE review of the draft and final design media (drawings, specifications,
calculations, etc.) needed to support a Resource Conservation and Recovery Act (RCRA) permit
modification request.
The IQRPE performed this design assessment to the requirements of WAC 173-303-640 for the
applicable Tank Farm Infrastructure Upgrades components.
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 6 of 58
Meier Project No. 19-8451
Figure 1-1: Hanford Map Showing the Location of the AP DST Tank Farm in the 200 East
Area
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 7 of 58
Meier Project No. 19-8451
Figure 1-2: AP Farm TSCR Upgrades General Arrangement (H-14-111331, Sheet 1)
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 8 of 58
Meier Project No. 19-8451
Figure 1-3: Dome Penetrations for Double-Shell Tank 241-AP-106 (H-14-010503, Sheet 6)
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 9 of 58
Meier Project No. 19-8451
Figure 1-4: Dome Penetrations for Double-Shell Tank 241-AP-107 (H-14-010503, Sheet 7)
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 10 of 58
Meier Project No. 19-8451
Figure 1-5: Dome Penetrations for Double-Shell Tank 241-AP-108 (H-14-010503, Sheet 8)
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 11 of 58
Meier Project No. 19-8451
Figure 1-6: 241-AP-106 Riser 2 Dropleg Assembly (H-14-111344, Sheet 2)
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 12 of 58
Meier Project No. 19-8451
Figure 1-7: 241-AP-106 Riser 2 Shield Box Assembly (H-14-111345, Sheet 1)
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 13 of 58
Meier Project No. 19-8451
Figure 1-8: 241-AP-07F Cover Plate (H-14-111338, Sheet 1)
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 14 of 58
Meier Project No. 19-8451
Figure 1-9: 241-AP-07F Riser Adapter (H-14-111337, Sheet 1)
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 15 of 58
Meier Project No. 19-8451
Figure 1-10: 241-AP-107 Transfer Pump (SK-AP-07F-001, Sheet 1)
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 16 of 58
Meier Project No. 19-8451
Figure 1-11: 241-AP-07F Dropleg Discharge (H-14-111336, Sheet 1)
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 17 of 58
Meier Project No. 19-8451
Figure 1-12: 241-AP-07F Pump Dummy Assembly (H-14-111365, Sheet 1)
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 18 of 58
Meier Project No. 19-8451
Figure 1-13: 241-AP-07F Jumper Assembly AP07F-WT-J-[P1-P2-(A)] (H-14-111334, Sheet
2)
NOTE: Pump P2 will not be installed under the design scope covered by this report.
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 19 of 58
Meier Project No. 19-8451
Figure 1-14: 241-AP-07F Jumper Assembly AP07F-WT-EPDMJ-[A-B] (H-14-111342,
Sheet 1)
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 20 of 58
Meier Project No. 19-8451
Figure 1-15: 241-AP-07F Jumper Assembly AP07F-WT-EPDMJ-[C-D] (H-14-111335,
Sheet 1)
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 21 of 58
Meier Project No. 19-8451
Figure 1-16: 241-AP-07F HIHTL Strongback Assembly (H-14-111340, Sheet 2)
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 22 of 58
Meier Project No. 19-8451
Figure 1-17: 241-AP-07F Shield Box Assembly (H-14-111341, Sheet 1)
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 23 of 58
Meier Project No. 19-8451
Figure 1-18: 241-AP-108 Riser 15 Containment (H-14-111347, Sheet 1)
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 24 of 58
Meier Project No. 19-8451
Figure 1-19: 241-AP-108 Riser 15 Dropleg Assembly (H-14-111346, Sheet 2)
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 25 of 58
Meier Project No. 19-8451
Figure 1-20: 241-AP-108 Riser 15 Containment - Section View (H-14-111331, Sheet 2)
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 26 of 58
Meier Project No. 19-8451
Figure 1-21: 241-AP TSCR Shield Box Assembly (H-14-111348, Sheet 1)
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 27 of 58
Meier Project No. 19-8451
Figure 1-22: 241-AP TSCR Enclosure HIHTL Strongback Assembly (H-14-111360, Sheet
1)
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 28 of 58
Meier Project No. 19-8451
DESIGN REVIEW REQUIREMENTS
Many of the TSCR Infrastructure Upgrade components required for the storage, treatment, and
transfer of dangerous or mixed waste are regulated by WAC 173-303-640(3) requirements. WAC
codes require an IQRPE’s review of the design of these components. This design review is
included in a RCRA permit application in order to obtain a permit for installation and operation of
new tank systems.
As a basis for the IQRPE certification, a review is performed on a final version of the document
design package as prepared and reviewed by WRPS. Documents such as drawings, calculations,
Engineering Change Notices (ECNs), Engineering Design Transmittals (EDTs), Technical
Evaluations, and specifications included in the design review package that are marked as final, and
have signatures of the preparer, checker, and approver, are reviewed by the IQRPE as a completed
document. All other documents will be reviewed as preliminary or supportive information.
The IQRPE maintains “independence” at all times. Comments by others may be considered by the
IQRPE during the preparation of reports and plans, but only the IQRPE can implement changes to
the master IQRPE documents.
DESIGN OVERVIEW FOR TSCR UPGRADES PROJECT
This Design Assessment Report is prepared for the Owner by an IQRPE to certify that the proposed
tank system will have sufficient structural integrity, and is acceptable for storing and treating
dangerous waste per WAC 173-303-640(3)(a).
The TSCR Upgrades Project will support the effort to provide a waste feed to the WTP in support
of the DFLAW Project.
The components within the scope of this IQRPE Design Assessment for TSCR Upgrades Project
include only those that are new and/or modified and will be in direct contact, or have the potential
to be in contact, with waste fluids and are situated above the riser level of the DST. These
components include:
DST 241-AP-106 Equipment:
o Riser 2:
Riser 2 Dropleg Assembly
Riser 2 Shield Box
DST 241-AP-107 Equipment:
o Mixer Pump Pit 241-AP-07F:
Cover Plate Assembly
Riser Adapter
Transfer Pump P-001
Dropleg Discharge Assembly
241-AP Pump Dummy Assembly
Jumper Assembly AP07F-WT-J-[P1-P2-(A)]
Jumper Assembly AP07F-WT-EPDMJ-[C-D]
Jumper Assembly AP07F-WT-EPDMJ-[A-B]
HIHTL Strongback
Shield Box Assembly
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 29 of 58
Meier Project No. 19-8451
DST 241-AP-108 Equipment:
o Riser 15:
Riser 15 Containment Assembly
Riser 15 Dropleg Assembly
TSCR Shield Box
TSCR Enclosure HIHTL Strongback
HIHTL Assemblies
Support Pad for TSCR Process Enclosure
The following sections lists and briefly describes each of the TSCR Upgrades Project components
included in this design review.
TSCR Upgrades Project: DST 241-AP-106 - Riser 2
Dropleg Assembly
Dropleg assembly (H-14-111344, AP Farm TSCR Upgrades 241-AP-106 Riser 2 Dropleg
Assembly; H-14-020803, Sheet 14, AP Farm TSCR Upgrades System (WT) P&ID; H-14-010503,
Sheet 6, Dome Penetration Schedules (WST/WSTA) Tank 241-AP-106; ECN-714661, AP106-
WST-Riser-002 Dropleg Installation) is situated inside 4” Riser-002 of DST 241-AP-106. The
dropleg assembly is the discharge point for pretreated LAW from a HIHTL originating from the
TSCR Process Enclosure.
Shield Box
Shield box assembly (H-14-111345, AP Farm TSCR Upgrades 241-AP-106 Riser 2 Shield Box
Assembly; H-14-020803 provides both the cover and shielding over the dropleg assembly (H-14-
111344) situated in Riser-002 of DST 241-AP-106. It also performs a structural function by
protecting the waste-containing dropleg assembly from damage. Only the structural protection
function is within the scope of this design assessment. Both the sides and cover of the shield box
are made from 2” thick ASTM A36 carbon steel plate.
TSCR Upgrades Project: DST 241-AP-107 - Mixer Pump Pit 241-AP-07F
Cover Plate Assembly
Mixer pump pit 241-AP-07F cover plate assembly (H-14-111338, AP Farm TSCR Upgrades 241-
AP-07F Cover Plate Assembly; ECN-714674, Pump Pit 241-AP-07F Equipment Installation)
provides the cover and shielding for the feed pump (SK-AP-07F-001, AP Farm TSCR Upgrades
AP-07F Feed Pump Sketch) and jumpers installed in mixer pump pit 241-AP-07F. It also performs
a structural function by protecting the waste-containing components in the pump pit from damage.
Only this structural protection function is within the scope of this design assessment. The cover
plate assembly is constructed from 4” thick ASTM A36 carbon steel plate.
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 30 of 58
Meier Project No. 19-8451
Riser Adapter
The riser adapter assembly (H-14-111337, AP Farm TSCR Upgrades 241-AP-07F Riser Adapter
Details) is situated at the top of 42” Riser-007 in mixer pump pit 241-AP-07F (H-14-010503, Sheet
7, Dome Penetration Schedules (WST/WSTA) Tank 241-AP-107; ECN-714674, Pump Pit 241-AP-
07F Equipment Installation). The riser adapter assembly is used to position and support the feed
pump assembly P-001 over Riser-007. It is constructed with three (3) openings, one of which can
be used for the future placement of an additional feed pump.
Feed Pump P-001
Feed pump assembly P-001 is a 30 horse power vertical turbine pump with a length of 48’. 6” (SK-
AP-07F-001). The discharge of the pump is routed through Nozzle “P1” which is connected to
jumper assembly AP07F-WT-J-[P1-P2-(A)] (H-14-111334, AP Farm TSCR Upgrades 241-AP-
07F Jumper AP07F-WT-J-[P1-P2-(A)]). The pump is both situated on, and supported by, the riser
adapter assembly (H-14-111337) at the top of 42” Riser-007 in mixer pump pit 241-AP-07F (H-
14-020803).
Dropleg Discharge Assembly
Dropleg discharge assembly (H-14-111336, AP Farm TSCR Upgrades 241-AP-07F Dropleg
Disch Assembly; H-14-020803) is inserted in an opening of the riser adapter assembly (H-14-
111337). The dropleg discharge assembly includes integral PUREX Nozzle “D” which is
connected to jumper assembly AP07F-WT-EPDMJ-[C-D] (H-14-111335, AP Farm TSCR
Upgrades 241-AP-07F Jumper AP07F-WT-EPDMJ-[C-D]) and is the discharge point of a feed
return HIHTL originating from the TSCR Process Enclosure.
241-AP Pump Dummy Assembly
The 241-AP Pump Dummy Assembly (H-14-111365, AP Farm TSCR Upgrades 241-AP Pump
Dummy Assembly) is inserted in one (1) of the three (3) openings in the riser adapter assembly (H-
14-111337). It covers an opening that is available for the future placement of an additional feed
pump (P-002). It includes integral PUREX Nozzle “P2” which is connected to Jumper Assembly
AP07F-WT-J-[P1-P2-(A)] (H-14-111334; H-14-020803).
Jumper Assembly AP07F-WT-J-[P1-P2-(A)]
Jumper Assembly AP07F-WT-J-[P1-P2-(A)] (H-14-111334) incorporates Connectors “P1” and
“P2” and Nozzle “A”. Connector “P1” engages with Nozzle “P1” on Feed Pump Assembly P-
001A. Connector “P2” engages with Nozzle “P2” on Jumper Assembly AP07F-WT-J-[P1-P2-(A)]
(H-14-111334; H-14-020803) for routing flow back to DST 241-AP-107 via the 241-AP pump
dummy assembly (H-14-111365). The jumper assembly is equipped with an integral three-way
ball valve used for routing pump flow from Connector “P1” to either Connector “P2” or to Nozzle
“A”.
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 31 of 58
Meier Project No. 19-8451
Jumper Assembly AP07F-WT-EPDMJ-[A-B]
Jumper assembly AP07F-WT-EPDMJ-[A-B] (H-14-111342) incorporates Connectors “A” and
“B”. Connector “A” engages with Nozzle “A” on jumper assembly AP07F-WT-J-[P1-P2-(A)].
Connector “B” engages with a corresponding nozzle incorporated into the lower end of the
strongback hose support assembly (H-14-111340) for routing pump flow out of pit 241-AP-07F to
the TSCR Process Enclosure. The jumper incorporates a flexible Ethylene Propylene Diene
Monomer (EPDM) hose assembly in its design that meets the requirement of RPP-14859,
Specification for Hose-in-Hose Transfer Lines and Hose Jumpers.
Jumper Assembly AP07F-WT-EPDMJ-[C-D]
Jumper assembly AP07F-WT-EPDMJ-[C-D] (H-14-111335) incorporates Connectors “C” and
“D”. Connector “C” engages with a corresponding nozzle incorporated into the lower end of a
strongback hose support assembly (H-14-111340) and is used for routing flow that originates from
the TSCR Process Enclosure to pit 241-AP-07F (H-14-020803). Connector “D” engages with a
corresponding nozzle incorporated into the dropleg discharge assembly (H-14-111336). The
jumper incorporates a flexible EPDM hose assembly in its design that meets the requirement of
RPP-14859.
HIHTL Strongback
The strongback hose support assemblies (H-14-111340) support the HIHTLs used for conveying
waste liquids as they are routed over the wall of mixer pump pit 241-AP-07F. One (1) of the
assemblies is used to support the HIHTL used for routing waste pumped by feed pump assembly
P-001 to the TSCR Process Enclosure. The second one is used for routing the HIHTL containing
waste return that originate from the TSCR Process Enclosure and are discharged to DST 241-AP-
107. The strongback hose support assemblies incorporates a PUREX nozzle at their lower ends for
a connection point to their respective jumpers in the pit.
Shield Box Assembly
Shield box assembly (H-14-111341, AP Farm TSCR Upgrades 241-AP-07F Shield Box Assembly;
H-14-111343, AP Farm TSCR Upgrades 241-AP-07F Pump Pit Assembly) provides both the cover
and shielding over the strongback hose support assemblies of DST 241-AP-107. It also performs
a structural function by protecting the waste-containing HIHTL that is routed over the strongback
hose support assembly from damage. Only this structural protection function is within the scope
of this design assessment. Both the sides and cover of the shield box are made from 4” thick
ASTM A36 carbon steel plate.
TSCR Upgrades Project: DST 241-AP-108 - Riser 15
Containment Assembly
The containment assembly (H-14-111347, AP Farm TSCR Upgrades 241-AP-108 Riser 15
Contain Assembly; H-14-111331, AP Farm TSCR Upgrades HIHTL Layout General
Arrangement); ECN-714563, ECN-714665, AP108-WST-Riser-015 Installation of TSCR Vent and
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 32 of 58
Meier Project No. 19-8451
Drain Dropleg) is made from a 72” diameter corrugated metal pipe which rests on concrete blocks
and has a 12” thick concrete collar poured around its top end. It is used to create a void space
below ground level that is above and around 12” diameter Riser-015 of 241-AP-108 (H-14-
010503, Sheet 8,) for the installation of the dropleg assembly (H-14-111346, AP Farm TSCR
Upgrades 241-AP-108 Riser 15 Dropleg Assembly) and the HIHTL connections to the dropleg
assembly (H-14-111331, AP Farm TSCR Upgrades HIHTL Layout General Arrangement). It
should be noted that the term “containment” as used in the nomenclature “Containment Assembly”
is for terminology purposes only. The component does not provide the sort of secondary
containment function as would typically be evaluated in the context of this design report.
Secondary containment and leak detection functions are provided integrally by the dropleg
assembly around which the containment assembly is situated.
Dropleg Assembly
The dropleg assembly (H-14-111346, H-14-020803, ECN-714563, ECN-714665) is connected to
the top flange of 12” Riser-015 of DST 241-AP-108. The dropleg assembly has two (2) connection
points for HIHTLs. One (1) of the HIHTL connections is used to route air emissions discharged
from the TSCR Process Enclosure vent manifold and the other for waste liquid discharged from
the TSCR enclosure drain.
TSCR Shield Box
The TSCR shield box (H-14-111348, AP Farm TSCR Upgrades 241-AP TSCR Shield Box
Assembly) provides both the cover and shielding over the TSCR Enclosure HIHTL strongback
situated on the outside of the TSCR Process Enclosure (H-14-111360, AP Farm TSCR Upgrades
241-AP TSCR HIHTL Strbk Assembly). It also performs a structural function by protecting the
waste-containing HIHTLs that are routed over the TSCR enclosure HIHTL strongback assembly
from damage. Only this structural protection function is within the scope of this design assessment.
Both the sides and cover of the shield box are made from 2” thick ASTM A36 carbon steel plate
(H-14-111348).
TSCR Enclosure HIHTL Strongback
The TSCR enclosure HIHTL strongback (H-14-111360) supports the HIHTLs used to convey the
fluids that either originate from DST 241-AP-107 or are being discharged to DST 241-AP-106,
DST 241-AP-107 or DST 241-AP-108. The TSCR Process Enclosure HIHTL strongback secures
and supports the HIHTLs as they are elevated to connect with the five (5) HIHTL fittings situated
on the outside of the TSCR Process Enclosure. It is constructed with sufficient space to
accommodate five (5) separate HIHTLs.
Hose-in-Hose Transfer Lines Assemblies (HIHTL)
HIHTLs (RPP-14859) are used for routing waste feed both to and from TSCR to DST 241-AP-
107 and for transferring pretreated waste from the TSCR Process Enclosure to DST 241-AP-106,
and process vent emissions and drain discharges to DST 241-AP-108 (H-14-020803, Sheet 14).
The HIHTLs consist of a 2” diameter inner primary EPDM hose inside a 4” secondary containment
hose. The various HIHTLs used in this project are detailed in ECN-714679, TSCR HIHTL
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 33 of 58
Meier Project No. 19-8451
Installation; details related to the service life of installed HIHTLs are documented in H-14-106249,
HIHTL Tracking Table.
TSCR Process Enclosure Pad
The general configuration and site location for the TSCR Process Enclosure Pad is shown on H-
14-111607, TSCR IXC Storage Area Civil BOF Pad Enlarged Plan. Drawing H-14-111608, TSCR
IXC Storage Area Civil Security Fence & Pad Dets, depicts the design details for the concrete slab.
SCOPE OF IQRPE DESIGN ASSESSMENT
This design assessment includes a comprehensive review of the design package per WAC 173-
303-640(3).
Portions of the TSCR Upgrades Project Included in Scope for IQRPE Certification
Documents included in this design review for the TSCR Upgrades Project include:
Calculations
Procurement Specifications
Technical Specifications
Design and Fabrication Drawings
ECNs
DCNs
Piping and Instrumentation Drawings (P&IDs)
A list of documents referenced by the IQRPE as part of this Design Assessment Report is included
in Section 4.0.
Portions of the TSCR Upgrades Project Not Included in Scope for IQRPE
Certification
Components that are not within the scope of this IQRPE Design Assessment for the TSCR
Upgrades Project include those that will not be in direct contact with waste fluids, with the
exception of those components that are being relied upon to provide protection to other
components that do contain waste. Other out-of-scope components are those that are situated
below the top surfaces of Riser-002 of DST 241-AP-106; Riser-007 of DST 241-AP-107; and
Riser-015 of DST 241-AP-108. The reason for this delineation is that any waste leakage
originating from these components, or portions of the components, situated below the top surface
of the three (3) risers would return back to the respective DST from where it originated. Thus, all
components of Feed Pump Assembly P-001 situated below the top surface of riser adapter
assembly (H-14-111337) would fall into this category.
2.0 ASSESSMENT SUMMARY
Systems within the IQRPE scope of this assessment are adequately designed to prevent failure
caused by corrosion or by structural loads imposed by the system’s intended service. These
conditions are described in more detail below. The system design complies with the applicable
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 34 of 58
Meier Project No. 19-8451
requirements of WAC 173-303-640(3). Design documents that were reviewed as part of this
assessment are referenced in Section 4.0
CODES, STANDARDS, AND REGULATIONS
The codes, standards, and regulations specifically used during the preparation of this certification
are referenced, as necessary, throughout this report. A complete list of applicable references is
contained in Section 4.0.
Basis of Design
The primary features of the TSCR Upgrades Project s components are presented in Table 1.
Table 1: TSCR Upgrades Project Component Features
Equipment Features
241-AP-106 - Riser 2
Dropleg Assembly
Situated inside 4” Riser-002 of DST 241-AP-106
Discharge point of a HIHTL originating from TSCR
241-AP-106 - Riser 2
Shield Box
Protects waste-containing dropleg assembly from damage
Made of 2” thick carbon steel plate
Pump Pit 241-AP-07F
Cover Plate Assembly
Protects waste-containing components in the pump pit from
damage
Made of 4” thick carbon steel plate
07F Riser Adapter
Situated at top of 42” Riser-007 in mixer pump pit 241-AP-07F
Positions and supports: Feed pump assembly P-001, dropleg
discharge assembly, and 241-AP pump dummy assembly
Feed Pump P-001
30 horse power vertical turbine pump
48’. 6”. overall length below base plate
Minimum head requirement of 360.2’
Minimum flow requirement of 99.6 gpm
Above riser discharge routed through Nozzle “P1” of jumper
assembly AP07F-WT-J-[P1-P2-(A)]
Dropleg Discharge
Assembly
Contains Nozzle “D” connected to jumper assembly AP07F-
WT-EPDMJ-[C-D]
Discharge point of HIHTL from TSCR
241-AP Pump Dummy
Assembly
Covers opening in AP07F riser adapter available for future
placement of feed pump (P-002)
Contains Nozzle “P2” connected to jumper assembly AP07F-
WT-J-[P1-P2-(A)]
Jumper Assembly AP07F-
WT-J-[P1-P2-(A)]
Contains Connectors “P1” and “P2”
Connector “P1” engages with Nozzle “P1” on feed pump P-001
Connector “P2” engages with Nozzle “P2” in 241-AP pump
dummy assembly
Used for routing waste flow in and out of DST 241-AP-107
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 35 of 58
Meier Project No. 19-8451
Equipment Features
Jumper Assembly AP07F-
WT-EPDMJ-[A-B]
Contains Connectors “A” and “B”
Connector “A” engages with Nozzle “A” on jumper assembly
AP07F-WT-J-[P1-P2-(A)]
Connector “B” engages with HIHTL strongback nozzle
Jumper Assembly AP07F-
WT-EPDMJ-[C-D]
Contains Connectors “C” and “D”
Connector “C” engages with HIHTL strongback nozzle
Connector “D” engages with Nozzle “D” on dropleg discharge
assembly
HIHTL Strongback
Incorporates nozzle for connection point to pit jumpers
Supports and routes HIHTL over pit wall maintaining proper
HIHTL bend radius
Shield Box Assembly
Protects waste-containing HIHTL routed over strongback hose
support assembly from damage
Made of 4” thick carbon steel plate
DST 241-AP-108 - Riser
15 Containment Assembly
Creates below ground void space above and around 12”
diameter Riser-015
Made of corrugated steel pipe
Dropleg Assembly Connected to top flange of 12” Riser-015 of DST 241-AP-108
Contains two (2) connection points for HIHTLs
TSCR Shield Box Protects waste-containing HIHTLs routed over TSCR
enclosure HIHTL strongback
TSCR Enclosure HIHTL
Strongback Supports and elevates HIHTLs entering TSCR process
enclosure
HIHTL Assemblies Provide connections among 241-AP-106; -AP-107; -AP-108
and TSCR process enclosure for fluid transfers
TSCR Process Enclosure
Pad Reinforced concrete support pad
Structural Design Standards
WAC 173-303-640(3) requires that an IQRPE certify that the proposed tank system will have
sufficient structural integrity and is acceptable for storing and treating dangerous waste. This
assessment must show, in accordance with WAC 173-303-640(3)(a), that the foundation, structural
support, seams, connections, and pressure controls are adequately designed and that the tank
system has sufficient structural strength, compatibility with the waste to be stored or treated, and
corrosion protection to ensure that it will not collapse, rupture, or fail.
Components of the TSCR Upgrades Project were analyzed and designed in accordance with
established structural requirements. Mechanical calculations performed for the piping systems are
prepared in accordance with piping code requirements in ASME B31.3, Process Piping (RPP-
CALC-62623, ASME B31.3 Evaluation of Riser Adapter and Dropleg Piping for 241-AP-106
Riser 2; RPP-CALC-62624, ASME B31.3 Evaluation of the Jumper and Dropleg Piping for 241-
AP-07F Pump Pit; RPP-CALC-62625, ASME B31.3 Evaluation of Riser Adapter and Dropleg
Piping for 241-AP-108 Riser 15). Calculations include the following areas as applicable:
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 36 of 58
Meier Project No. 19-8451
Pipe wall thickness calculations for pressure.
Stress calculations for sustained loads due to pressure, dead load, and other sources.
Stress calculations for displacement, such as thermal loads.
Stress calculations for occasional loads such as pressure, weight, and earthquake loads.
WAC 173-303(3)(a), Dangerous Waste Regulations, defines backfill requirements to provide
structural support to prevent excessive settlement and corrosion. The corrosion assessment is
addressed in Section 2.2.2 of this report.
The following activities were conducted in the review of design standards for the TSCR Upgrades
Project:
Structural design standards, codes, and criteria were reviewed to ensure clear and specific
references.
Structural calculations were reviewed.
The IQRPE has reviewed the available design package information to ensure that the following
activities have been incorporated into the technical specifications:
Structural calculations are provided for the TSCR Upgrades Project components (RPP-
CALC-62424, Structural Evaluation of the AP Farm TSCR Upgrades Shield Boxes; RPP-
CALC-62646, AP-07F Cover Plate Structural Analysis; RPP-CALC-62647, TSCR
Upgrades – HIHTL Bridge Plate Structural Analysis; RPP-CALC-62669, 241-AP-07F
Riser Adapter Structural Analysis; RPP-CALC-62674, Structural Evaluations of the 241-
AP-07F Dropleg; RPP-CALC-62675, Structural Evaluations of the 241-AP-106 Dropleg
and Riser Adapter; RPP-CALC-62676, Structural Evaluations of the 241-AP-108 Dropleg
and Riser Adapter; RPP-CALC-63192, 241-AP TSCR HIHTL Strong-Back Structural
Analysis; RPP-CALC-63194, 241-AP-108 TSCR Riser Assembly Analysis).
Calculations of thickness account for the assumed corrosion/erosion rate.
Seismic considerations appropriate for the risk zone are included in the structural
calculations.
Foundations are deep enough in the ground to eliminate frost heave per the requirements
of WAC 173-303-640(3)(a)(v)(C). New equipment is either attached to existing tank
structures or designed to accommodate frost heave.
Adequate freeze protection is provided.
The information below highlights the IQRPE structural design standard review for the relevant
TSCR Upgrades Project components and also identifies any specific exceptions to this IQRPE
certification as they relate to the structural review.
The reinforced concrete TSCR Process Enclosure Pad is evaluated in RPP-CALC-63060,
Structural Analysis of TSCR Balance of Facilities (BOF) Pad.
The side walls of both mixer pump pit 241-AP-07F and the 241-AP-108 Riser 15 caisson assembly
are entirely surrounded with earth. The insulation provided by the surrounding earth affords a
measure of protection against freezing temperatures. The bottom of mixer pump pit 241-AP-07F
is situated over five (5) feet below grade (ECN-714674, Pump Pit 241-AP-07F Equipment
Installation), as is the base of the 241-AP-108 Riser 15 caisson assembly (H-14-111347, AP
Farm TSCR Upgrades 241-AP-108 Riser 15 Contain; ECN-714563, AP108-WST-Riser-015
Modification). The frost heaving of foundations and back fill requirements to provide structural
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 37 of 58
Meier Project No. 19-8451
support to prevent excessive settlement will not be an issue due to the depth and configuration of
both the 241-AP-07F mixer pump pit and the 241-AP-108 Riser 15 caisson assembly.
TSCR Upgrades Project: DST 241-AP-106 - Riser 2
Dropleg Assembly
All steel piping components on the dropleg assembly (H-14-111344) are welded and inspected per
ASME B31.3 for the category of normal fluid service. All structural carbon and stainless steel
component are welded in accordance with AWS D1.1 or AWS D1.6 as applicable for statically
loaded criteria. The dropleg assembly was structurally evaluated for lifting and operating loads
(RPP-CALC-62675, Structural Evaluations of the 241-AP-106 Dropleg and Riser Adapter), as
well as for other loadings associated with the ASME B31.3 evaluation (RPP-CALC-62623, ASME
B31.3 Evaluation of Riser Adapter and Dropleg Piping for 241-AP-106 Riser 2). In both
evaluations, the dropleg assembly was found to be acceptable in accommodating the anticipated
loadings.
The dropleg has adequate freeze protection (RPP-CALC-63577).
Shield Box
The structural carbon steel components of the shield box assembly (H-14-111345) are welded and
inspected in accordance with AWS D1.1 for statically loaded criteria. The shield box was
structurally evaluated for operational loads, natural phenomenon loads, and lifting loads. Its
design was found to be acceptable in accommodating those loads (RPP-CALC-62424, Structural
Evaluation of the AP Farm TSCR Upgrades Shield Boxes).
TSCR Upgrades Project: DST 241-AP-107 - Mixer Pump Pit 241-AP-07F
Cover Plate Assembly
The structural carbon steel components of the mixer pump pit 241-AP-07F Cover Plate Assembly
(H-14-111338) are welded and inspected in accordance with AWS D1.1 for statically loaded
criteria. The cover plate assembly was structurally evaluated for operational, seismic, impact and
lifting loads. Its design was found to be acceptable in accommodating those loads (RPP-CALC-
62646, AP-07F Cover Plate Structural Analysis).
Riser Adapter
The structural carbon and stainless steel component of the Riser Adapter Assembly (H-14-111337,
AP Farm TSCR Upgrades 241-AP-07F Riser Adapter Details) are welded in accordance with
AWS D1.1, Structural Welding Code - Steel or AWS D1.6, Structural Welding Code - Stainless
Steel, as applicable, for statically loaded criteria. The Riser Adapter Assembly was structurally
evaluated for both lifting and seismic loads; its design was found to be acceptable in
accommodating those loads (RPP-CALC-62669, 241-AP-07F Riser Adapter Structural Analysis).
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 38 of 58
Meier Project No. 19-8451
Feed Pump P-001
NOTE:
There are no structural design details currently available for feed pump assembly P-001 (SK-AP-
07F-001). Based on typical feed pump assemblies and SK-AP-07F-001, there are no IQRPE
certification exceptions to the structural design of the feed pump assembly.
Dropleg Discharge Assembly
The structural stainless steel component of the dropleg discharge assembly (H-14-111336) are
welded in accordance with AWS D1.6 for statically loaded criteria. The dropleg discharge
assembly was structurally evaluated for lifting and operating/occasional loads. Its design was
found to be acceptable in accommodating those loads (RPP-CALC-62674, Structural Evaluations
of the 241-AP-07F Dropleg).
The dropleg has adequate freeze protection (RPP-CALC-63577).
241-AP Pump Dummy Assembly
The structural carbon and stainless steel component of the 241-AP pump dummy assembly (H-14-
111365) are welded in accordance with AWS D1.1 or AWS D1.6, as applicable, for statically
loaded criteria.
Jumper Assembly AP07F-WT-J-[P1-P2-(A)]
The structural carbon and stainless steel component of jumper assembly AP07F-WT-J-[P1-P2-
(A)] (H-14-111334) are welded in accordance with AWS D1.1 or AWS D1.6, as applicable, for
statically loaded criteria. The jumper is fabricated and tested in accordance with RPP-14541,
Jumper Fabrication and Testing Specification for Tank Farms.) Structural items that were
evaluated were included in the ASME B31.3 analysis that was performed for the jumper (RPP-
CALC-62624, ASME B31.3 Evaluation of the Jumper and Dropleg Piping for 241-AP-07F Pump
Pit). The analysis evaluated loadings which included dead loads, operating loads, thermal loads,
seismic loads, and transient loads. The evaluation determined that the structural integrity of the
components evaluated were acceptable per the requirements of the ASME B31.3 code.
Jumper Assembly AP07F-WT-EPDMJ-[A-B]
The piping of jumper assembly AP07F-WT-EPDMJ-[A-B] (H-14-111342) is welded and
inspected in accordance with ASME B31.3 for the category of normal fluid service. The jumper is
fabricated and tested in accordance with RPP-14541. The flexible hose assembly on the jumper
is procured in accordance with RPP-14859. Structural items that were evaluated were included in
the ASME B31.3 analysis that was performed for the jumper (RPP-CALC-62624). The analysis
evaluated loadings which included dead loads, operating loads, thermal loads, seismic loads, and
transient loads. The evaluation determined that the structural integrity of the components evaluated
were acceptable per the requirements of the ASME B31.3 code.
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 39 of 58
Meier Project No. 19-8451
Jumper Assembly AP07F-WT-EPDMJ-[C-D]
The piping of jumper assembly AP07F-WT-EPDMJ-[C-D] (H-14-111335) is welded and
inspected in accordance with ASME B31.3 for the category of normal fluid service. The jumper is
fabricated and tested in accordance with RPP-14541. The flexible hose assembly on the jumper
is procured in accordance with RPP-14859. Structural items that were evaluated were included in
the ASME B31.3 analysis that was performed for the jumper (RPP-CALC-62624). The analysis
evaluated loadings which included dead loads, operating loads, thermal loads, seismic loads, and
transient loads. The evaluation determined that the structural integrity of the components evaluated
were acceptable per the requirements of the ASME B31.3 code.
HIHTL Strongback
The structural carbon and stainless steel component of the strongback hose support assemblies (H-
14-111340) are welded in accordance with AWS D1.1 or AWS D1.6, as applicable, for statically
loaded criteria. Structural items that were evaluated were included in the ASME B31.3 analysis
that was performed for the piping components of the strongback (RPP-CALC-62624). The analysis
evaluated loadings which included dead loads, operating loads, thermal loads, seismic loads, and
transient loads, as well as lifting loads and flexure while lifting. The evaluation determined that
the structural integrity of the components evaluated were acceptable per the requirements of the
ASME B31.3 code.
The strongback assembly is designed to provide a sufficient HIHTL bend radius that is greater
than the 16” bend radius that the HIHTL must negotiate without experiencing damage or buckling
(RPP-14859).
Shield Box Assembly
The structural carbon steel components of the shield box assembly (H-14-111341) are welded and
inspected in accordance with AWS D1.1 for statically loaded criteria. The shield box was
structurally evaluated for operational loads, natural phenomenon loads, and lifting loads. Its
design was found to be acceptable in accommodating those loads (RPP-CALC-62424).
TSCR Upgrades Project: DST 241-AP-108 - Riser 15
Containment Assembly
The structural carbon steel components of the containment assembly (H-14-111347) are welded
and inspected in accordance with AWS D1.1 for statically loaded structures. The concrete used in
the construction of the containment assembly meets the requirements of RPP-SPEC-62663,
Construction Specification For: TSCR Upgrades, Waste Feed Delivery & TSCR IXC Storage Pad.
RPP-CALC-63194, 241-AP-108 TSCR Riser Assembly Analysis, evaluated the components of the
containment assembly for structural adequacy under various loading scenarios. The component
included the containment lid assembly, concrete collar, corrugated metal pipe (CMP) and the
concrete block used to support the CMP. The components were found to be adequately designed
to support the loads imposed on them.
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 40 of 58
Meier Project No. 19-8451
Dropleg Assembly
All steel piping components on the dropleg assembly (H-14-111346, H-14-020803, ECN-714563,
and ECN-714665) are welded and inspected per ASME B31.3 for the category of normal fluid
service. All structural carbon and stainless steel component are welded in accordance with AWS
D1.1, AWS D1.6, as applicable, for statically loaded criteria. The dropleg assembly was
structurally evaluated for lifting and operating loads (RPP-CALC-62676, Structural Evaluations
of the 241-AP-108 Dropleg and Riser Adapter), as well as for other loadings associated with the
ASME B31.3 evaluation (RPP-CALC-62625, ASME B31.3 Evaluation of Riser Adapter and
Dropleg Piping for 241-AP-108 Riser 15). In both evaluations, the dropleg assembly was found to
be acceptable in accommodating the anticipated loadings.
The dropleg has adequate freeze protection (RPP-CALC-63577).
TSCR Shield Box
The structural carbon steel components of the TSCR shield box (H-14-111348) are welded and
inspected in accordance with AWS D1.1 for statically loaded criteria. The shield box was
structurally evaluated for operational loads, natural phenomenon loads, and lifting loads, its design
was found to be acceptable in accommodating those loads (RPP-CALC-62424).
TSCR Enclosure HIHTL Strongback
The structural carbon steel components of the TSCR enclosure HIHTL strongback (H-14-111360)
are welded and inspected in accordance with AWS D1.1 for statically loaded criteria. The
strongback was structurally evaluated for operational loads, natural phenomenon loads, and lifting
loads. Its design was found to be acceptable in accommodating those loads (RPP-CALC-63192,
241-AP TSCR HIHTL Strong-Back Structural Analysis).
The strongback assembly is designed to provide a sufficient HIHTL bend radius that is greater
than the 16” bend radius that the HIHTL must negotiate without experiencing damage or buckling
(RPP-14859).
Hose-in-Hose Transfer Lines Assemblies
The arrangement of the HIHTL are depicted in H-14-111331, AP Farm TSCR Upgrades HIHTL
Layout General Arrangement. Structural design standards pertaining to the HIHTLs are detailed
in RPP-14859. Cover devices placed over the HIHTLs to protect them along their routing paths
were evaluated for structural considerations (RPP-CALC-62647, TSCR Upgrades – HIHTL Bridge
Plate Structural Analysis). The analysis focused on the loadings that would be imposed by the
largest cranes (150 ton, Grove RT91506) that would travel over the covers and the ability of the
covers to resist any forces that might be imposed upon them from the loading. A recommendation
was made to use 10’ x 4’ x 2” thick steel plates over the HIHTLs where heavy equipment will be
travelling.
The HIHTLs are equipped with integral heat tracing to protect their contents from freezing
temperatures (RPP-14859). In addition to the heat tracing, the HIHTL lines have 2” of Armaflex
insulation and have adequate freeze protection (RPP-CALC-63577).
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 41 of 58
Meier Project No. 19-8451
Structural Design Exceptions
Based on the above review, there are no IQRPE certification exceptions to the structural design of
the components used for the TSCR Upgrades Project.
Except as noted, the IQRPE concurs that this structural design meets the requirements of WAC
173-303-640.
Waste Compatibility
Regulations located in WAC 173-303-640(3)(a) require tank systems be compatible with the
wastes transported or otherwise handled. The compatibility of the TSCR Upgrades Project
components with waste stream products was evaluated.
RPP-RPT-61518, Design of Tank Side Cesium Removal (TSCR) Upgrades Non-Metallic Material
Evaluation, evaluated the compatibility of the TSCR Upgrades Project non-metallic components
with the liquid tank waste and operational environments. All of the non-metallic materials used in
the design were reviewed for their application to the criteria stated in RPP-RPT-61518.
Metallic materials were selected for their performance in contact with waste under normal
processing conditions. All metallic piping and tubing in contact with tank waste is 312 or 403
stainless steel. (Table 3). Based on tank waste processing experience at Hanford, austenitic
stainless steel is adequate for service. Non-metallic materials not in contact with tank waste were
selected based on their chemical compatibility and radiation resistance using the approved
materials specified in RPP-RPT-61518.
Table 2: Materials in Contact with Tank Waste
Part Name Part Material Drawing No.
Gasket Adhesive Neoprene
H-14-111336 Gasket, 1/8” Thk EPDM
Piping A 312 SST
Gasket Adhesive Neoprene H-14-111337
Gasket, 1/8” Thk EPDM
Gasket 2”, Type 1 PTFE
H-14-111334,
H-14-111335,
H-14-111342
Ball Valve 2”, 3-Way EPR, Tefzel, Kynar
740
Electromagnetic Flowmeter, 2”, lining Tefzel
Gasket 1/16” Thk Bluegard 3700 EPDM binder
2" Hose (HIHTL) EPDM
Piping A 312 SS
Elbows & Tee A 403 SS
Gasket Adhesive Neoprene
H-14-111344 Gasket 1/16” Thk Bluegard 3700 EPDM binder
Gasket, 1/4” Thk Neoprene
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 42 of 58
Meier Project No. 19-8451
Part Name Part Material Drawing No.
Piping A 312 SS
Elbow A 403 SS
Gasket Adhesive Neoprene
H-14-111346
Gasket 1/16” Thk Bluegard 3700 EPDM binder
Gasket, 1/4” Thk Neoprene
O-ring EPDM
Piping A 312 SS
Elbow A 403 SS
Gasket Adhesive Neoprene
H-14-111365 Gasket, 1/8” Thk EPDM
Piping A 312 SS
Elbow A 403 SS
2” Primary Flexible Hose. EPDM H-14-111331
All primary piping and components in contact with tank waste supernatant are contained within
secondary containment. Both the metallic and nonmetallic materials used for the TSCR
Upgrades Project components were determined to be suitable for their intended applications.
Corrosion Analysis
The proper selection of materials of construction and corrosion/erosion allowances are important
for safety functions. The ASME B31.3 analysis for the riser adapter and dropleg piping for 241-
AP-106 Riser 2; the jumper and dropleg piping for the 241-AP-07F Pump Pit, and the riser adapter
and dropleg piping for 241-AP-108. Riser 15 utilizes a corrosion-erosion rate for the austenitic
stainless steel piping of 0.2 mils per year for the expected service life of the system (RPP-CALC-
62623, ASME B31.3 Evaluation of Riser Adapter and Dropleg Piping for 241-AP-106 Riser 2;
RPP-CALC-62624, ASME B31.3 Evaluation of the Jumper and Dropleg Piping for 241-AP-07F
Pump Pit; RPP-CALC-62625, ASME B31.3 Evaluation of Riser Adapter and Dropleg Piping for
241-AP-108 Riser 15). When the 0.2 mils per year value is taken over the 25 year design life it
yields a total value of 0.005 in.
Anticipated Chemistry and Controls
Information on the composition of the liquid waste originating from the DST can be found in RPP-
SPEC-61910, Specification for the Tank-Side Cesium Removal Demonstration Project (Project
TD101). Physical characteristics of the expected waste feed streams are presented in Table 4, and
average concentrations of key chemical components expected in the waste feed streams are
presented in Table 5. These values were obtained from Appendix B of RPP-14859.
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 43 of 58
Meier Project No. 19-8451
Table 3: Select Physical Characteristics of Waste Feed
Parameter Unit
Liquid Density 1.05 to 1.5 kg/L
Liquid Viscosity 0.005 to 0.3 g/cm-s (0.5 to 30 cP)
Solids Density 3.0 kg/L maximum
Solids Diameter 9,525 micron maximum
Solids Volume Percent 0 - 30%, Average ~ 5 – 10% as fed to the pump
Abrasiveness, Miller Number Less than 100
Waste Temperature 82°C (180°F) maximum
Table 4: Select Chemical Components of Waste Feed
Component Solution Concentration (mg/L)
A Farm AX Farm AY-102 AP-102
Cl- 9112 9083 4565 13,854
F- 275 386 5377 2760
NO2- 138,953 160,119 126,180 239,730
NO3- 230,078 244,048 334,654 434,285
SO4-2 2,847 2480 12,915 7529
The normal operating temperature for all piping and equipment in waste service during normal
operations is between 20 and 35°C, and the pH of the waste is ~14 based on the hydroxide [OH-]
concentration (RPP-SPEC-61910). The materials of construction are compatible with the expected
waste feeds.
Dissimilar materials are noted on the dunnage of jumper assembly Jumper Assembly AP07F-WT-
J-[P1-P2-(A)] (H-14-111334). The hollow structural steel is carbon steel, which is welded to
austenitic stainless steel channels to support the process piping. Welding austenitic stainless steels
to carbon and low alloy steels are established methods in the process and construction industries.
Post-weld surface coating will ensure that galvanic corrosion cells cannot be set up across the joint
where there is a composition gradient. All exposed carbon steel surfaces will be painted with two
(2) coats of Amercoat®1 220, a water-based acrylic enamel or can be powder-coated as an option
to painting (H-14-111334). Sacrificial corrosion of the carbon steel components in contact with
the jumper assembly is not expected. The stainless steel materials in contact with waste are not at
risk of galvanic corrosion.
The IQRPE concludes that appropriate corrosion considerations have been made.
Compatibility Exceptions
Based on the above review, there are no IQRPE certification exceptions to the anticipated waste
compatibility or corrosion issues with the piping materials used for the TSCR Upgrades Project
that may come into contact with the liquid waste stream.
1 Amercoat is a trademark of PPG Industries Ohio, Inc.,
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 44 of 58
Meier Project No. 19-8451
Pressure Control System
WAC 173-303-640(3)(a) requires that an IQRPE certify that the proposed tank system has been
designed with appropriate pressure control systems. The piping components of the TSCR
Upgrades Project were evaluated for pressure control issues.
TSCR Upgrades Project: DST 241-AP-106 - Riser 2
Dropleg Assembly
The piping of the Dropleg Assembly (H-14-111344, AP Farm TSCR Upgrades 241-AP-106 Riser
2 Dropleg Assembly) is required to be fabricated, welded, inspected, and tested in accordance with
ASME B31.3 for the category of normal fluid service. The design pressure for the piping is 400
psig and the design temperature is 180 °F. The 2” piping on the assembly is required to undergo a
hydrostatic pressure test at 600 psig. The reservoir drain assembly is leak tested to an acceptance
criteria of “drip-wise” or less. The dropleg design was analyzed for compliance with ASME B31.3
requirements and was found to have met those requirements (RPP-CALC-62623, ASME B31.3
Evaluation of Riser Adapter and Dropleg Piping for 241-AP-106 Riser 2).
Shield Box
Pressure control issues are not applicable to the shield box; therefore, the shield box was not
evaluated for any pressure control considerations.
TSCR Upgrades Project: DST 241-AP-107 - Mixer Pump Pit 241-AP-07F
Cover Plate Assembly
Pressure control issues are not applicable to the cover plate assembly, therefore, the cover plate
assembly was not evaluated for any pressure control considerations.
Riser Adapter
Pressure control issues are not applicable to riser adapter, therefore, the riser adapter was not
evaluated for any pressure control considerations.
Feed Pump P-001
The performance requirements of Feed Pump P-001, and also P-002, (SK-AP-07F-001, AP Farm
TSCR Upgrades AP-07F Feed Pump Sketch) were evaluated to assure the pumps would be
properly sized to provide sufficient pressure to maintain a 5 gpm flow rate to the TSCR Processing
Unit. (Note: Pump P-002 will not be installed under the scope of the TSCR Upgrades Project.) The
evaluation determined that the maximum differential head and flow requirements of the pump
would need to be 347.5 ft. at 61.4 gpm. An orifice will be incorporated into the design to maintain
the 5 gpm flow during high head loss conditions (RPP-CALC-62640, Tank Side Cesium Removal
Process Pump Flow Analysis).
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 45 of 58
Meier Project No. 19-8451
A hydraulic transient analysis was performed to evaluate the TSCR piping and component located
in the 241-AP Tank Farm (excluding the TSCR unit) to determine if the internal transient pressures
and forces due to hydraulic transient loads would be within the allowable values of ASME B31.3.
The analysis concluded that all transient events within the TSCR System do not cause transient
pressures or forces in excess of the values allowed by ASME B31.3 (RPP-CALC-62532, Tank
Side Cesium Removal Hydraulic Transient Analysis).
Dropleg Discharge Assembly
The piping of the Dropleg Discharge Assembly (H-14-111336, AP Farm TSCR Upgrades 241-
AP-07F Dropleg Disch Assembly) is required to be fabricated, welded, inspected, and tested in
accordance with ASME B31.3 for the category of normal fluid service. The design pressure for
the piping is 400 psig and the design temperature is 180 °F. The piping on the assembly is required
to undergo a hydrostatic pressure test at 600 psig (H-14-111336). The Dropleg Discharge
Assembly design was analyzed for compliance with ASME B31.3 requirements and was found to
have met those requirements (RPP-CALC-62624, ASME B31.3 Evaluation of the Jumper and
Dropleg Piping for 241-AP-07F Pump Pit). The Dropleg Discharge Assembly utilizes a PUREX
2” male nozzle (H-2-90185, Male Nozzle 2” PUREX).
241-AP Pump Dummy Assembly
The piping of the 241-AP Pump Dummy Assembly (H-14-111365, AP Farm TSCR Upgrades 241-
AP Pump Dummy Assembly) is required to be fabricated, welded, inspected and tested in
accordance with ASME B31.3 for the category of normal fluid service. The design pressure for
the piping is 400 psig and the design temperature is 200 °F. The piping on the assembly is required
to undergo a hydrostatic pressure test at 600 psig (H-14-111365). The 241-AP Pump Dummy
Assembly design was analyzed for compliance with ASME B31.3 requirements and was found to
have met those requirements (RPP-CALC-62624, ASME B31.3 Evaluation of the Jumper and
Dropleg Piping for 241-AP-07F Pump Pit). The 241-AP Pump Dummy Assembly utilizes a
PUREX 2-in. male nozzle (H-2-90185).
Jumper Assembly AP07F-WT-J-[P1-P2-(A)]
Jumper Assembly AP07F-WT-J-[P1-P2-(A)] (H-14-111334, AP Farm TSCR Upgrades 241-AP-
07F Jumper AP07F-WT-J-[P1-P2-(A)])] is fabricated and tested in accordance with RPP-
14541ASCE. The jumper piping is welded and inspected in accordance with ASME B31.3 for the
category of normal fluid service. The design pressure for the jumper assembly piping is 400 psig
and is required to undergo a hydrostatic pressure test at 600 psig (H-14-111334). The design of
the jumper assembly was analyzed for compliance with ASME B31.3 requirements and was found
to have met those requirements (RPP-CALC-62624, ASME B31.3 Evaluation of the Jumper and
Dropleg Piping for 241-AP-07F Pump Pit). The jumper utilizes a PUREX 2”. male nozzle (H-2-
90185). It also contains two (2) vertical PUREX connectors (H-2-32420, Assembly Horizontal &
Vertical 2” Connector).
Jumper Assembly AP07F-WT-EPDMJ-[A-B]
The piping of Jumper Assembly AP07F-WT-EPDMJ-[A-B] (H-14-111342, AP Farm TSCR
Upgrades 241-AP-07F Jumper AP07F-WT-EPDMJ-[A-B]) is welded and inspected in accordance
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 46 of 58
Meier Project No. 19-8451
with ASME B31.3 for the category of normal fluid service. The jumper is fabricated and tested in
accordance with RPP-14541. The flexible hose assembly on the jumper is procured in accordance
with RPP-14859. The design pressure for the jumper assembly piping is 400 psig and the design
temperature is 180 °F. It is required to undergo a hydrostatic pressure test at 600 psig (H-14-
111342). The design of Jumper Assembly AP07F-WT-EPDMJ-[A-B] was analyzed for
compliance with ASME B31.3 requirements and was found to have met those requirements (RPP-
CALC-62624). The jumper utilizes two (2) PUREX 2” horizontal connectors (H-2-32420).
Jumper Assembly AP07F-WT-EPDMJ-[C-D]
The piping of Jumper Assembly AP07F-WT-EPDMJ-[C-D] (H-14-111335, AP Farm TSCR
Upgrades 241-AP-07F Jumper AP07F-WT-EPDMJ-[C-D]) is welded and inspected in accordance
with ASME B31.3 for the category of normal fluid service. The jumper is fabricated and tested in
accordance with RPP-14541. The flexible hose assembly on the jumper is procured in accordance
with RPP-14859. The design pressure for the jumper assembly piping is 400 psig and the design
temperature is 180 °F. It is required to undergo a hydrostatic pressure test at 600 psig. (H-14-
111335). The design of Jumper Assembly AP07F-WT-EPDMJ-[C-D] was analyzed for
compliance with ASME B31.3 requirements and was found to have met those requirements (RPP-
CALC-62624). The jumper utilizes one (1) PUREX 2” horizontal connector and one (1) PUREX
2” vertical connector (H-2-32420).
HIHTL Strongback
The piping of the Strongback Hose Support Assemblies (H-14-111340, AP Farm TSCR Upgrades
241-AP-07F HIHTL Strbk Assembly) is welded and inspected in accordance with ASME B31.3
for the category of normal fluid service. The design pressure for the strongback assembly piping
is 400 psig and the design temperature is 180 °F. It is required to undergo a hydrostatic pressure
test at 600 psig. (H-14-111340). The design of Jumper Assembly AP07F-WT-EPDMJ-[C-D] was
analyzed for compliance with ASME B31.3 requirements and was found to have met those
requirements (RPP-CALC-62624). The strongback utilizes a PUREX 2”. male nozzle (H-2-
90185).
Shield Box Assembly
Pressure control issues are not applicable to the shield box assembly; therefore, the shield box
assembly was not evaluated for any pressure control considerations.
TSCR Upgrades Project: DST 241-AP-108 - Riser 15
Containment Assembly
Pressure control issues are not applicable to the containment assembly; therefore, the containment
assembly was not evaluated for any pressure control considerations.
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 47 of 58
Meier Project No. 19-8451
Dropleg Assembly
The piping of the Dropleg Assembly (H-14-111346, AP Farm TSCR Upgrades 241-AP-108 Riser
15 Dropleg Assembly) is required to be fabricated, welded, inspected, and tested in accordance
with ASME B31.3 for the category of normal fluid service. The design pressure for the piping is
400 psig and the design temperature is 180 °F. The 2” piping on the assembly is required to
undergo a hydrostatic pressure test at 600 psig. (H-14-111346). The reservoir drain assembly is
leak tested to an acceptance criteria of “drip-wise” or less. The dropleg design was analyzed for
compliance with ASME B31.3 requirements and was found to have met those requirements (RPP-
CALC-62625, ASME B31.3 Evaluation of Riser Adapter and Dropleg Piping for 241-AP-108
Riser 15).
TSCR Shield Box
Pressure control issues are not applicable to the TSCR Shield Box; therefore, the TSCR Shield
Box was not evaluated for any pressure control considerations.
TSCR Enclosure HIHTL Strongback
Pressure control issues are not applicable to the TSCR Enclosure HIHTL Strongback; therefore,
the TSCR Enclosure HIHTL Strongback was not evaluated for any pressure control considerations.
Hose-in-Hose Transfer Lines Assemblies (HIHTL)
Pressure requirements for HIHTLs are established in RPP-14859. The maximum rated working
pressure for primary hose assemblies shall not be less than 425 psig for a 2” hose and shall not be
less than 170 psig for the secondary hose assemblies.
Pressure Control System Exceptions
Based on the above review, there are no IQRPE Certification exceptions to the pressure control
system review.
The IQRPE concurs that this design basis meets the requirements of WAC 173-303-640(3) (a).
The IQRPE concludes that the appropriate pressure control considerations for the TSCR Tank
Farm Infrastructure Upgrades have been made.
Secondary Containment System
Secondary containment for tank systems that store, accumulate, or treat dangerous waste must be
designed and installed to meet the requirements of WAC 173-303-640(4)(b). Secondary
containment for the TSCR Upgrades Project is accomplished by: the dropleg assembly installed
above Riser-002 of DST 241-AP-106 (H-14-111344, AP Farm TSCR Upgrades 241-AP-106 Riser
2 Dropleg Assembly), the concrete structure of existing Mixer Pump Pit 241-AP-07F of DST 241-
AP-107, and the dropleg assembly above Riser-015 of DST 241-AP-108 (H-14-111346, AP Farm
TSCR Upgrades 241-AP-108 Riser 15 Dropleg Assembly).
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 48 of 58
Meier Project No. 19-8451
Mixer Pump Pit 241-AP-07F of DST 241-AP-107 is equipped with an integral floor drain to route
any leakage from internal components back to DST 241-AP-107 (H-14-020803, Sheet 14, AP
Farm TSCR Upgrades System (WT) P&ID).
Leak detectors are installed in the two (2) dropleg assemblies and in the mixer pump pit for
monitoring leakage: LDE-006 in the dropleg of DST 241-AP-106; LDE-007 in Mixer Pump Pit
241-AP-07F; and LDE-008 in the dropleg of DST 241-AP-108 (H-14-020803, Sheet 14). Leak
detector placement is consistent with generally accepted engineering practices to provide timely
detection of any leakage from the primary pathway into the secondary containment.
All waste transfer activities that occur outside of the dropleg assembly installed above Riser-002
of DST 241-AP-106, Mixer Pump Pit 241-AP-07F of DST 241-AP-107, and the dropleg assembly
installed above Riser-015 of DST 241-AP-108 are conducted through HIHTLs which provide for
primary piping and secondary encasement.
The HIHTL secondary encasement is open at the two (2) riser droplegs and the pump pit. HIHTLs
4 and 5 (vent and drain lines) are continuously sloped from TSCR to the dropleg at AP-108.
HIHTLs 1, 2, and 3, generally slope from TSCR to the droplegs, but include low-points along the
hose routings where the HIHTLs pass under a crane path (H-14-111357, AP Farm TSCR Upgrades
Piping Hydraulic Diagram). These low points have potential to collect liquid that will not drain
unless operational steps are taken to ensure the lines are purged.
The general slope of the HIHTL routings toward the low points at the riser or pit end allows any
leakage to be transported to the locations where leak detectors are installed. This provides for leak
detection throughout the entire pathway.
Waste transfers undergo review within the scope of waste leak path evaluations, and these are
developed prior to the initial operation of the system.
Conclusions from the review of the design standards for the TSCR Upgrades Project are
summarized below:
The TSCR Upgrades Project is designed to prevent any migration of wastes out of the
secondary containment system to the soil, groundwater, or surface water at any time during
the use of the system.
The system is constructed of materials that are compatible with the wastes to be placed in
the system.
The system has been specified to have sufficient strength to withstand stresses due to static
head during a release, pressure gradients, climatic conditions, and other stresses resulting
from daily operations.
A leak-detection system for liquids has been provided.
The system is sloped or otherwise designed or operated to drain and remove liquids
resulting from leaks, spills, or precipitation.
The IQRPE concludes that the appropriate secondary containment considerations have been made.
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 49 of 58
Meier Project No. 19-8451
Ancillary Equipment Design
WAC 173-303-640 requires that an IQRPE certify that the proposed tank system ancillary
equipment has been designed to meet the requirements of WAC 173-303-640(3)(f) and (4)(f).
WAC 173-303-040 defines “Ancillary Equipment” as any device including, but not limited to,
such devices as piping, fittings, flanges, valves, and pumps, that is used to distribute, meter, or
control the flow of dangerous waste from its point of generation to a storage or treatment tank(s),
between dangerous waste storage and treatment tanks to a point of disposal on-site, or to a point
of shipment for disposal off-site. A review of the ancillary equipment design is normally part of
the IQRPE review. The scope of this review includes components listed as in-scope in Section 1.3
and as described in the review sections above. Piping, fittings, flanges, valves, and pumps have
been evaluated by the IQRPE throughout this report, which includes all ancillary equipment in-
scope for this Design Assessment.
Ancillary Equipment Design Exceptions
Based on the above review, there are no IQRPE certification exceptions to the ancillary equipment
design review.
The IQRPE concurs that this design basis meets the requirements of WAC 173-303-640.
P&ID Review
The P&ID details for the TSCR Upgrades Project are depicted on H-14-020803, Sheet 14, AP
Farm TSCR Upgrades System (WT) P&ID.
The IQRPE concludes that the appropriate P&ID review has been made.
Corrosion Assessment
WAC 173-303-640 requires an IQRPE corrosion assessment of the external portion of the primary
containment that is in direct contact with soil or water and that the tank be compatible with the
waste stored within it. The only waste conveying components in direct contact with the soil are
the HIHTLs which are made of polymer materials and include an external insulating barrier which
makes them suitable for soil contact. All other components are situated in enclosures where they
protected from coming into contact with soil and water.
The IQRPE concludes that appropriate corrosion considerations have been made for the TSCR
Upgrades Project.
Corrosion Assessment Exceptions
Based on the above requirements, there are no IQRPE certification exceptions to the corrosion
assessment review with the materials for the TSCR Upgrades Project.
The IQRPE concurs that this design basis meets the requirements of WAC 173-303-640(3)(a).
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 50 of 58
Meier Project No. 19-8451
3.0 DESIGN REVIEW ASSESSMENT CERTIFICATIONS
The TSCR Upgrades Project design, as previously described, has been reviewed by the IQRPE
and was assessed to be in compliance with the applicable sections of WAC 173-303-640. These
results are based on a review of the applicable codes, standards, and documents.
The individuals listed below participated in the preparation of this design assessment report.
Registered Professional Engineers
Paul M. Giever
- P.E., Civil, Structural Engineering, License No. 28084
Alexander P. Butterfield
- P.E., Mechanical Engineering, License No. 52255
Andrew S. Klein
- P.E., Chemical, Fire Protection, License No. 47831
Michel J. Langevin
- P.E., Mechanical Engineering, License No. 23759
BS Degreed Engineer
Nathaniel R. Weinman
- E.I.T., Mechanical Engineering, Enrollment Number E-11818
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 52 of 58
Meier Project No. 19-8451
4.0 REFERENCES
ASCE 7-10, 2010, Minimum Design Loads for Buildings and Other Structures, American Society
of Civil Engineers, Reston, VA.
ASME B31.3, 2016, Process Piping, American Society of Mechanical Engineers, New York, New
York.
AWS D1.1/D1.1M, 2015, Structural Welding Code - Steel, American Welding Society, Miami,
Florida.
AWS D1.6/D1.6M, 2017, Structural Welding Code - Stainless Steel, American Welding Society,
Miami, Florida.
ECN-714563, 2019, AP108-WST-Riser-015 Modification, Rev. 0, Washington River Protection
Solutions, LLC, Richland, Washington.
ECN-714661, 2019, AP106-WST-Riser-002 Dropleg Installation, Rev. 0, Washington River
Protection Solutions, LLC, Richland, Washington.
ECN-714665, 2019, AP108-WST-Riser-015 Installation of TSCR Vent and Drain Dropleg, Rev.
0, Washington River Protection Solutions, LLC, Richland, Washington.
ECN-714674, 2019, Pump Pit 241-AP-07F Equipment Installation, Rev. 0, Washington River
Protection Solutions, LLC, Richland, Washington.
ECN-714679, 2019, TSCR HIHTL Installation, Rev. 0, Washington River Protection Solutions,
LLC, Richland, Washington.
H-2-32420, 2018, Sheet 1, Assembly Horizontal & Vertical 2” Connector, Rev. 12, Washington
River Protection Solutions, LLC, Richland, Washington.
H-2-90185, 2018, Sheet 1, Male Nozzle 2” PUREX, Rev. 6, Washington River Protection
Solutions, LLC, Richland, Washington.
H-2-90185, 2018, Sheet 2, Male Nozzle 2” PUREX, Rev. 5, Washington River Protection
Solutions, LLC, Richland, Washington.
H-14-010503, 2018, Sheet 6, Dome Penetration Schedules (WST/WSTA) Tank 241-AP-106, Rev.
15, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-010503, 2018, Sheet 7, Dome Penetration Schedules (WST/WSTA) Tank 241-AP-107, Rev.
16, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-010503, 2018, Sheet 8, Dome Penetration Schedules (WST/WSTA) Tank 241-AP-108, Rev.
14, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-020803, 2019, Sheet 14, AP Farm TSCR Upgrades System (WT) P&ID, Rev. 0, Washington
River Protection Solutions, LLC, Richland, Washington.
H-14-106249, 2019, Sheet 1, HIHTL Tracking Table, Rev. 51, Washington River Protection
Solutions, LLC, Richland, Washington.
H-14-111331, 2019, Sheet 1, AP Farm TSCR Upgrades HIHTL Layout General Arrangement,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 53 of 58
Meier Project No. 19-8451
H-14-111331, 2019, Sheet 2, AP Farm TSCR Upgrades HIHTL Layout Sections, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111331, 2019, Sheet 3, AP Farm TSCR Upgrades HIHTL Layout Sections, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111331, 2019, Sheet 4, AP Farm TSCR Upgrades HIHTL Layout Hose Chart, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111334, 2019, Sheet 1, AP Farm TSCR Upgrades 241-AP-07F Jumper AP07F-WT-J-[P1-
P2-(A)], Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111334, 2019, Sheet 2, AP Farm TSCR Upgrades 241-AP-07F Jumper AP07F-WT-J-[P1-
P2-(A)], Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111334, 2019, Sheet 3, AP Farm TSCR Upgrades 241-AP-07F Jumper Assembly, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111334, 2019, Sheet 4, AP Farm TSCR Upgrades 241-AP-07F Jumper Weldment, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111334, 2019, Sheet 5, AP Farm TSCR Upgrades 241-AP-07F Jumper Details, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111334, 2019, Sheet 6, AP Farm TSCR Upgrades 241-AP-07F Jumper Weldment, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111335, 2019, Sheet 1, AP Farm TSCR Upgrades 241-AP-07F Jumper AP07F-WT-EPDMJ-
[C-D], Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111335, 2019, Sheet 2, AP Farm TSCR Upgrades 241-AP-07F Jumper Assembly, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111335, 2019, Sheet 3, AP Farm TSCR Upgrades 241-AP-07F Jumper Weldment, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111336, 2019, Sheet 1, AP Farm TSCR Upgrades 241-AP-07F Dropleg Disch Notes and
Parts List, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111336, 2019, Sheet 2, AP Farm TSCR Upgrades 241-AP-07F Dropleg Disch Assembly,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111336, 2019, Sheet 3, AP Farm TSCR Upgrades 241-AP-07F Dropleg Disch Weldment,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111336, 2019, Sheet 4, AP Farm TSCR Upgrades 241-AP-07F Dropleg Disch Details, Rev.
0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111337, 2019, Sheet 1, AP Farm TSCR Upgrades 241-AP-07F Riser Adapter Notes and
Parts List, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111337, 2019, Sheet 2, AP Farm TSCR Upgrades 241-AP-07F Riser Adapter Weldment,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111337, 2019, Sheet 3, AP Farm TSCR Upgrades 241-AP-07F Riser Adapter Details, Rev.
0, Washington River Protection Solutions, LLC, Richland, Washington.
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 54 of 58
Meier Project No. 19-8451
H-14-111337, 2019, Sheet 4, AP Farm TSCR Upgrades 241-AP-07F Riser Adapter Details, Rev.
0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111337, 2019, Sheet 5, AP Farm TSCR Upgrades 241-AP-07F Riser Adapter Details, Rev.
0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111338, 2019, Sheet 1, AP Farm TSCR Upgrades 241-AP-07F Cover Plate Notes and Parts
List, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111338, 2019, Sheet 2, AP Farm TSCR Upgrades 241-AP-07F Cover Plate Assembly, Rev.
0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111338, 2019, Sheet 3, AP Farm TSCR Upgrades 241-AP-07F Cover Plate Weldment, Rev.
0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111338, 2019, Sheet 4, AP Farm TSCR Upgrades 241-AP-07F Cover Plate Details, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111338, 2019, Sheet 5, AP Farm TSCR Upgrades 241-AP-07F Cover Plate Details, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111338, 2019, Sheet 6, AP Farm TSCR Upgrades 241-AP-07F Cover Plate Details, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111338, 2019, Sheet 7, AP Farm TSCR Upgrades 241-AP-07F Cover Plate Paint Diagram,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111338, 2019, Sheet 8, AP Farm TSCR Upgrades 241-AP-07F Cover Plate Paint Details,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111340, 2019, Sheet 1, AP Farm TSCR Upgrades 241-AP-07F HIHTL Strbk Notes and Parts
List, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111340, 2019, Sheet 2, AP Farm TSCR Upgrades 241-AP-07F HIHTL Strbk Assembly, Rev.
0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111340, 2019, Sheet 3, AP Farm TSCR Upgrades 241-AP-07F HIHTL Strbk Weldment, Rev.
0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111340, 2019, Sheet 4, AP Farm TSCR Upgrades 241-AP-07F HIHTL Strbk Weldment, Rev.
0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111340, 2019, Sheet 5, AP Farm TSCR Upgrades 241-AP-07F HIHTL Strbk Details, Rev.
0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111341, 2019, Sheet 1, AP Farm TSCR Upgrades 241-AP-07F Shield Box Notes and Parts
List, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111341, 2019, Sheet 2, AP Farm TSCR Upgrades 241-AP-07F Shield Box Assembly, Rev.
0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111341, 2019, Sheet 3, AP Farm TSCR Upgrades 241-AP-07F Shield Box Weldment, Rev.
0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111342, 2019, Sheet 1, AP Farm TSCR Upgrades 241-AP-07F Jumper AP07F-WT-EPDMJ-
[A-B], Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 55 of 58
Meier Project No. 19-8451
H-14-111342, 2019, Sheet 2, AP Farm TSCR Upgrades 241-AP-07F Jumper Assembly, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111342, 2019, Sheet 3, AP Farm TSCR Upgrades 241-AP-07F Jumper Weldment, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111343, 2019, Sheet 1, AP Farm TSCR Upgrades 241-AP-07F Pump Pit Notes and Parts
List, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111343, 2019, Sheet 2, AP Farm TSCR Upgrades 241-AP-07F Pump Pit Assembly, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111343, 2019, Sheet 3, AP Farm TSCR Upgrades 241-AP-07F Pump Pit Sections and
Details, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111344, 2019, Sheet 1, AP Farm TSCR Upgrades 241-AP-106 Riser 2 Dropleg Notes and
Parts List, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111344, 2019, Sheet 2, AP Farm TSCR Upgrades 241-AP-106 Riser 2 Dropleg Notes and
Parts List, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111344, 2019, Sheet 3, AP Farm TSCR Upgrades 241-AP-106 Riser 2 Dropleg Assembly,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111344, 2019, Sheet 4, AP Farm TSCR Upgrades 241-AP-106 Riser 2 Dropleg Weldment,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111344, 2019, Sheet 5, AP Farm TSCR Upgrades 241-AP-106 Riser 2 Dropleg Weldment,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111344, 2019, Sheet 6, AP Farm TSCR Upgrades 241-AP-106 Riser 2 Dropleg Weldment/
Details, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111344, 2019, Sheet 7, AP Farm TSCR Upgrades 241-AP-106 Riser 2 Dropleg Details, Rev.
0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111345, 2019, Sheet 1, AP Farm TSCR Upgrades 241-AP-106 Riser 2 Shield Box Notes and
Parts List, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111345, 2019, Sheet 2, AP Farm TSCR Upgrades 241-AP-106 Riser 2 Shield Box Assembly,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111345, 2019, Sheet 3, AP Farm TSCR Upgrades 241-AP-106 Riser 2 Shield Box Weldment,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111345, 2019, Sheet 4, AP Farm TSCR Upgrades 241-AP-106 Riser 2 Shield Box Access
Port Cover, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111346, 2019, Sheet 1, AP Farm TSCR Upgrades 241-AP-108 Riser 15 Dropleg Notes and
Parts List, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111346, 2019, Sheet 2, AP Farm TSCR Upgrades 241-AP-108 Riser 15 Dropleg Notes and
Parts List, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111346, 2019, Sheet 3, AP Farm TSCR Upgrades 241-AP-108 Riser 15 Dropleg Assembly,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 56 of 58
Meier Project No. 19-8451
H-14-111346, 2019, Sheet 4, AP Farm TSCR Upgrades 241-AP-108 Riser 15 Dropleg Assembly,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111346, 2019, Sheet 5, AP Farm TSCR Upgrades 241-AP-108 Riser 15 Dropleg Weldment,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111346, 2019, Sheet 6, AP Farm TSCR Upgrades 241-AP-108 Riser 15 Dropleg Weldment,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111346, 2019, Sheet 7, AP Farm TSCR Upgrades 241-AP-108 Riser 15 Dropleg Weldment,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111346, 2019, Sheet 8, AP Farm TSCR Upgrades 241-AP-108 Riser 15 Dropleg Details,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111347, 2019, Sheet 1, AP Farm TSCR Upgrades 241-AP-108 Riser 15 Contain Notes and
Parts List, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111347, 2019, Sheet 2, AP Farm TSCR Upgrades 241-AP-108 Riser 15 Contain Assembly,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111347, 2019, Sheet 3, AP Farm TSCR Upgrades 241-AP-108 Riser 15 Contain Assembly,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111347, 2019, Sheet 4, AP Farm TSCR Upgrades 241-AP-108 Riser 15 Contain Lid
Assembly/Weldment, Rev. 0, Washington River Protection Solutions, LLC, Richland,
Washington.
H-14-111347, 2019, Sheet 5, AP Farm TSCR Upgrades 241-AP-108 Riser 15 Contain Access Port
Cover, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111347, 2019, Sheet 6, AP Farm TSCR Upgrades 241-AP-108 Riser 15 Contain Details,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111348, 2019, Sheet 1, AP Farm TSCR Upgrades 241-AP TSCR Shield Box Notes and Parts
List, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111348, 2019, Sheet 2, AP Farm TSCR Upgrades 241-AP TSCR Shield Box Assembly, Rev.
0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111348, 2019, Sheet 3, AP Farm TSCR Upgrades 241-AP TSCR Shield Box Weldment, Rev.
0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111348, 2019, Sheet 4, AP Farm TSCR Upgrades 241-AP TSCR Shield Box Details, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111357, 2019, Sheet 1, AP Farm TSCR Upgrades Piping Hydraulic Diagram, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111357, 2019, Sheet 2, AP Farm TSCR Upgrades Piping Hydraulic Diagram, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111360, 2019, Sheet 1, AP Farm TSCR Upgrades 241-AP TSCR HIHTL Strbk Notes and
Parts List, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111360, 2019, Sheet 2, AP Farm TSCR Upgrades 241-AP TSCR HIHTL Strbk Assembly,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 57 of 58
Meier Project No. 19-8451
H-14-111360, 2019, Sheet 3, AP Farm TSCR Upgrades 241-AP TSCR HIHTL Strbk Weldment,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111360, 2019, Sheet 4, AP Farm TSCR Upgrades 241-AP TSCR HIHTL Strbk Details, Rev.
0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111360, 2019, Sheet 5, AP Farm TSCR Upgrades 241-AP TSCR HIHTL Strbk Details, Rev.
0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111365, 2019, Sheet 1, AP Farm TSCR Upgrades 241-AP Pump Dummy Notes and Parts
List, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111365, 2019, Sheet 2, AP Farm TSCR Upgrades 241-AP Pump Dummy Assembly, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111365, 2019, Sheet 3, AP Farm TSCR Upgrades 241-AP Pump Dummy Details, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111365, 2019, Sheet 4, AP Farm TSCR Upgrades 241-AP Pump Dummy Details, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111607, 2019, Sheet 1, TSCR IXC Storage Area Civil BOF Pad Enlarged Plan, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
H-14-111608, 2019, Sheet 1, TSCR IXC Storage Area Civil Security Fence & Pad Dets, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
RPP-14541, 2017, Jumper Fabrication and Testing Specification for Tank Farms, Rev. 8,
Washington River Protection Solutions, LLC, Richland, Washington.
RPP-14859, 2019, Specification for Hose-in-Hose Transfer Lines and Hose Jumpers, Rev. 14,
Washington River Protection Solutions, LLC, Richland, Washington.
RPP-CALC-62424, 2019, Structural Evaluation of the AP Farm TSCR Upgrades Shield Boxes,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
RPP-CALC-62532, 2019, Tank Side Cesium Removal Hydraulic Transient Analysis, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
RPP-CALC-62623, 2019, ASME B31.3 Evaluation of Riser Adapter and Dropleg Piping for 241-
AP-106 Riser 2, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
RPP-CALC-62624, 2019, ASME B31.3 Evaluation of the Jumper and Dropleg Piping for 241-AP-
07F Pump Pit, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
RPP-CALC-62625, 2019, ASME B31.3 Evaluation of Riser Adapter and Dropleg Piping for 241-
AP-108 Riser 15, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
RPP-CALC-62640, 2019, Tank Side Cesium Removal Process Pump Flow Analysis, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
RPP-CALC-62646, 2019, AP-07F Cover Plate Structural Analysis, Rev. 0, Washington River
Protection Solutions, LLC, Richland, Washington.
RPP-CALC-62647, 2019, TSCR Upgrades – HIHTL Bridge Plate Structural Analysis, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
IQRPE Design Assessment Report for DA-316542-01, Rev. 0
TSCR Upgrades Project
WRPS Subcontract No. 64658, Release 017 Page 58 of 58
Meier Project No. 19-8451
RPP-CALC-62669, 2019, 241-AP-07F Riser Adapter Structural Analysis, Rev. 0, Washington
River Protection Solutions, LLC, Richland, Washington.
RPP-CALC-62674, 2019, Structural Evaluations of the 241-AP-07F Dropleg, Rev. 0, Washington
River Protection Solutions, LLC, Richland, Washington.
RPP-CALC-62675, 2019, Structural Evaluations of the 241-AP-106 Dropleg and Riser Adapter,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
RPP-CALC-62676, 2019, Structural Evaluations of the 241-AP-108 Dropleg and Riser Adapter,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
RPP-CALC-63060, 2019, Structural Analysis of TSCR Balance of Facilities (BOF) Pad, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
RPP-CALC-63192, 2019, 241-AP TSCR HIHTL Strong-Back Structural Analysis, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
RPP-CALC-63194, 2019, 241-AP-108 TSCR Riser Assembly Analysis, Rev. 0, Washington River
Protection Solutions, LLC, Richland, Washington.
RPP-CALC-63577, 2019, Uninsulated Pipe Thermal Analysis, Rev A, Draft, Washington River
Protection Solutions, LLC, Richland, Washington.
RPP-RPT-61518, Design of Tank Side Cesium Removal (TSCR) Upgrades Non-Metallic Material
Evaluation, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
RPP-SPEC-61910, 2019, Specification for the Tank-Side Cesium Removal Demonstration Project
(Project TD101), Rev. 2, Washington River Protection Solutions, LLC, Richland, Washington.
RPP-SPEC-62663, 2019, Construction Specification For: TSCR Upgrades, Waste Feed Delivery
& TSCR IXC Storage Pad, Rev. 0, Washington River Protection Solutions, LLC, Richland,
Washington.
SK-AP-07F-001, 2019, Sheet 1, AP Farm TSCR Upgrades AP-07F Feed Pump Sketch, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
WAC 173-303, “Dangerous Waste Regulations,” Washington Administrative Code, as amended.
WAC 173-303-640(3), “Design and Installation of New Tank Systems or Components,”
Washington Administrative Code, as amended.
WAC 173-303-640, “Tank Systems,” Washington Administrative Code, as amended.
WAC 173-303-810(13)(a), “Certification,” Washington Administrative Code, as amended.
Washington River Protection Solutions Statement of Work (SOW) No. 316542, 2019, IQRPE
Design Assessment of Tank Farm Infrastructure Upgrades and Storage Pad System for Tank
Side Cesium Removal System (TSCR), Rev. 0, Washington River Protection Solutions, LLC,
Richland, Washington.