28
Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn [email protected] 083 379 1735 Please see paper at: www.gsb.uct.ac.za/mir 30 May 2006

Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn [email protected]

Embed Size (px)

Citation preview

Page 1: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

Investment and Uncertainty

Historical experience with power sector investments in South Africa and implications for current challenges

Grové [email protected]

083 379 1735

Please see paper at: www.gsb.uct.ac.za/mir 30 May 2006

Page 2: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

The Electricity Supply Commission ESCOM was established on 6 March

1923. Non-profit statutory corporation Not accountable to parliament, reporting

to line minister Could veto municipal generation

investment

Page 3: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

ESCOM: Initial Strategy

Set out to establish itself as sole supplier of new capacity– Took over Colenso power station from Railways– Agreements that it would construct Congela and

Salt River power stations– Vetoed future VFTPC stations: Witbank, Klip, Vaal

(ESCOM Finance and own, VFTPC to build and operate)

– Expropriated VFTPC on 1 July 1948 for £14.5million - largest transaction in South Africa's history

Page 4: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

Investment: Upscaling and interconnection in 1960/70s. Post war years

– Skills and equipment shortages– Increased demand from gold mining and industry

lead to rationing and load shedding.– Supply to mining shaped ESCOM culture

1960s and early 1970s– Interconnection – national grid– Upscaling – economies of scale– Important implications for generation technology,

plant sizing and locational decisions

Page 5: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

Increased demand and investment in the 1970s

Page 6: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

Increased demand and investment in the 1970s (2)

Page 7: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

Increased demand and investment in the 1970s (3)

– Oil crises– From 1972 to 1975, demand growth outstripped

the rate at which ESCOM could add capacity.– Dramatically increased building programme

• Matla, with six 600MW units, started in October 1974• Drakensberg, with four 250MW units started in January

1975• Duva, with a further six 600MW units started in

November 1975 (decision shortly after the Portuguese lost political power in Mozambique)

• Koeberg also finally started in August 1976 barely two months after the Soweto uprising.

Page 8: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

Second Oil crises in 1979

– Demand growth increased to twelve percent, leading to alarming reduction in reserve margin

– “No time to draw up new designs or go through long tendering processes”

– Lethabo (3 708 MW) was ordered as a copy of Matla

– Tutuka ordered (3 654MW) as a copy of Duva– The supply arrangements were negotiated with the

same turbine and boiler contractors as were used with the original stations

Page 9: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

Problems with up-scaling and capital costs By middle 1970s it was taking fourteen

years between the decision to construct a large six-unit coal fired station and the commissioning of the last unit.

Most of the capital expenditure occurred between year seven and eleven

Page 10: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

ESCOM fixed assets under construction

Page 11: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

Capacity crises and further investment in the early 1980s

– Loss of the 1373 MW of contracted firm capacity from Cahora Bassa

– Commissioning problems were experienced with the new 600MW sets at Matla and Duva

– Unexpected deterioration of availability• From 85% in 1975, to 74.7% in 1980, and 71.9% in 1983• Result of poor initial performance from the new large-scale

generating sets• (Availability levels of over 90 percent during the 1990s when

surplus capacity meant that the system was run at lower load factors)

– Mostly problems at the three largest stations Arnot, Kriel and Matla

Page 12: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

Availability of selected ESCOM power stations

Taaibos Ingagane Grootvlei Arnot Kriel Matla Duva All ESCOM8x60 MW 5x100 MW 6x200 MW 6x350 MW 6x500 MW 6x600 MW 6x600 MW Stations

1973 83.6 89.7 83.4 65.0 82.51974 86.2 93.0 81.7 73.3 83.71975 91.2 94.7 83.6 80.8 85.01976 84.1 87.2 76.4 80.2 68.0 82.31977 86.1 81.3 77.2 66.9 70.6 78.51978 85.3 74.9 76.6 66.0 71.4 77.41979 90.3 87.7 79.9 68.1 81.6 45.9 78.8

1980 87.9 75.8 62.2 66.5 72.0 59.5 78.2 74.71981 88.1 80.5 82.5 73.3 61.8 70.1 55.8 74.21982 88.6 76.4 71.4 82.1 57.7 71.2 79.0 74.31983 86.1 54.8 64.6 74.3 60.5 80.9 72.2 71.9

1979-83 88.2 75.0 72.1 72.9 66.7 65.5 71.3 74.8

Page 13: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

Capacity crises and further investment in the early 1980s (2)

– Supply crises– Unavoidable load shedding with goldmines– Left an indelible impression on the senior engineers

- resolved to ensure that it should happen “never again” (Kok 1999, McRae 1997 and Rubberts 1997).

– Again it was decided to accelerate plans for constructing generation plant. Ian McRae, recalls:

“It would have been the biggest sin to have been responsible for holding back economic growth [by constraining electricity supply] so it was just go, go, go!” (1997).

Page 14: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

Further orders in the early 1980s– By 1982 foreseeing capital expenditure programme of

R65 billion which would treble its capacity to 70 000MW by end of the century (Ryan, 1982).

– Placed boiler and turbine orders for three additional 4000MW class stations, Matimba, Kendal, and Majuba on the basis of the four tenders submitted for Matimba. Also signed a letter of intent for the turbines for a further station, Lekwe.

– All these stations were to utilise “dry” cooling. – By end of 1983, ESCOM had generation plant totalling

22 260 MW under construction or on order. Equivalent to 97 percent of its total plant in commission.

Page 15: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com
Page 16: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com
Page 17: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

ESCOM: Capital expenditure

0

2 000

4 000

6 000

8 000

10 000

12 000

14 000

16 000

Cap

ital

exp

end

itu

re (

Rm

)

199719941991198819851982197919761973

Year

Page 18: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

ESCOM/Eskom’s prices

Page 19: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

Eskom's investments, debt and financing costs

0

3 000

6 000

9 000

12 000

15 000

18 000

1997

1995

1993

1991

1989

1987

1985

1983

1981

1979

Cap

ex &

Fin

ance

(R

mill

ion

)

0

10 000

20 000

30 000

40 000

50 000

60 000

Deb

t (R

mill

ion

)

Net interest bearing debtTotal CapexCapex excl. electrificationNet interest and finance

Page 20: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

Cost contributions per kWh

1986

1984

1982

1980

1978

1976

1974

1972

Year-5.00

0.00

5.00

10.00

15.00

20.00

Co

st c

on

trib

uti

on

s (c

/kW

h)

Surplus (Loss)

General expenses

Distribution oper. & maint.

Generation operating

Electricity purchase

Fuel

Reserve Fund

Total CDF contributions

Loan repayments

Interest

Average price in 1998Rands (using PPI)

Page 21: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

Cost contributions per kWh (2)

Page 22: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

Problems with system planning and project appraisal Irreversability Uncertainty and ignorance rather than

“risk” Incorrect use of discount rates Overlooking the benefits of portfolio

effects and diversity Overlooking the value of flexibility and

options

Page 23: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

Strategies in the face of uncertainty and ignorance Incertitude shifting Incrementalism: “The science of muddling

through” Lindblom (1959 and 1979)– effective response to complexity and uncertainty in

the context of bounded rationality – poses a challenge to the mastery-via-

understanding tradition of Western civilization

Page 24: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

Strategies in the face of uncertainty and ignorance (2)– Flexibility (of an investment)

• allows for trial and error learning (Collingridge, 1992)• enables adaptation to changing circumstances and

therefore reduces the potential costs of errors (Collingridge and James, 1991).

– Diversity (of a system)• promotes beneficial forms of innovation and growth• hedges against exposure to uncertainty and ignorance• mitigates the adverse effects of institutional ‘momentum’

and ‘lock-in’ in technological trajectories• accommodates disparate interests associated with social

choice in modern pluralistic societies. Stirling (1998: 37)

Page 25: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

Moral Hazard

A specific instance of the principal agent problem

From investigating health care insurance incentive problems

E.g. car insurance Four elements of moral hazard:

– Incertitude shifting– Principal agent relationship– Agent incentives diverging from principal interests– Information asymmetry (observability) problems

Page 26: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

On Moral Hazard

Moral hazard is pervasive in the economy. It occurs whenever risk is present, individuals are risk averse, and “effort” is costly to monitor. And it arises not only in insurance markets, but also when insurance is provided by governments, through social institutions, or in principal-agent contracts. (1988: 384, emphasis added)

Arnott and Stiglitz (1988)

Page 27: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

Some findings

Information asymmetry: financial system and pricing does not reveal cost of electric power

Persistent Moral Hazard– Moral Hazard problem exists and is not

recognised

Page 28: Investment and Uncertainty Historical experience with power sector investments in South Africa and implications for current challenges Grové Steyn Grove@TheKnowledgeBridge.com

Implications for policy– Persistent Moral Hazard means that the problem is

bigger than you think.– Policies should focus on:

• Moving exposure to real economic uncertainties back to firms and financiers

• Reducing– ex ante information asymmetries with regard to investment

exposure to real uncertainties and ignorance; and– ex post information asymmetries with respect to the subsequent

performance of these investments.

– Comprehensive public review of: Eskom’s governance and investment decision-making methodologies and procedures; and of its accounting and pricing policies required