Upload
vantram
View
216
Download
2
Embed Size (px)
Citation preview
Company founded by Frank Mohn in 1938
1960s - first company applying submerged hydraulic drive to marine pumps
1970s - entered the North Sea offshore market with hydraulic driven fire water pumps
1980s - introduced our electric submersible pump concept
1990s - started promoting use of caisson installed pumps in FPSOs
for SWL and FWP applications.
1996 - first SWL in caisson on Bluewater/Hess Glas Dowr FPSO
1997 - first submerged FWP in caisson on Mærsk Curlew FPSO
2012 - first SWL to FLNG Shell Prelude
Brief intro on Framo and submersible pumps
Our point of view
• Submersible pumps installed in caissons have substantially lower CAPEX than conventional SWL pumps installed in pump room.
• Risk for uncontrolled flooding eliminated – no large hull penetrations required.
• Installation of suction hoses facilitated by separate caissons
• OPEX for the pump room system is higher than for a system with caisson installed pumps;• Longer pipe routing – higher friction losses – increased power
consumption.• Maintenance on suction valves, strainers, HVAC and other utilities in
pump room
Number of employees: 1300 (Alfa Laval total group ~18.000)Turnover in 2015 : 5,6 Bill NOK (~ 15% of Alfa Laval TT)
CASE STUDY CAPEXPUMP ROOM PUMPS
VS.CAISSON INSTALLED PUMPS
Data and figures for the SWL case taken from a conversion project excecuted 2014/15 and thefigures and calculations are made by Bumi Armada.
The converted FPSO have a storage capacity of 1.7 MMbbl; handle up to 80,000 bbls crude oil
Case study - Sea Water Cooling system
• 3 x 50% SWL each: 2500 m3/h @ 9 barg
• Pump Material: 25 Cr. Duplex
• Power: 11 kV, Motor rating 1500 kW
• Hull depth: ~ 30m
• Distance from pump room to consumers (Main HEX): ~300m
• Distance from caissons to consumers (Main HEX): ~50m
CAPEX Comparison
DESCRIPTIONTECHNICAL COST (USD)
Conventional Submersible Conventional Submersible
1 Unit cost Approx USD 810K per pump Approx. USD 1.5 mil per pump 2,430,000 4,500,000
2 Delivery 40 Weeks 48-52 Weeks.
3 Proposed location Forward machinery space On ship's side within Deck Crane reach
4 Machinery space
Required c/w outfitting stairs, lightings, F&G, telecom, insulation, painting, ventilation, fixed fire protection, etc.Steel (material cost) - USD 1.5 million Steel (labor cost) - USD 1.15 millionAccess way - USD 750KFixed fire protection - CO2 - 100KPainting – 3000 m2 - USDXXX
Not required. However, without machinery space, the diesel lift pumps need to be changed to deep well pumps same as the methanol lift pumps. The containerized fire water pumps will be located on top of temporary refugee on main deck.
Assume additional 100K to change diesel lift pumps
USD750 K to strengthen the temporary refugee to accommodate the firewater pump.
3,500,000 850,000
5 CaissonNot required.
Pumps foundation - USD 100K
Yes with working platform around the caissons on upper deckassume 1200 mm diameterSteel (material cost) -USD 750KSteel (labor cost) - USD 720K
100,000 1,470,000
CAPEX Comparison
6 Seachest
2 new sea chest required, c/w utility pipes like compressed air, hypochlorite, sea chest cover etc.StrainersShipside valves, isolation valves2 SC - Approx. USD 600K (labor)Steel (material cost) - USD 750KUSD80 K (8 tonnes grating labor & material)USD 50K (SC blanks)
Not required
1,480,000 0
7 Material handling
Pumps - lifting beams within machinery space & winches or small davit required on deck.Suction Hose - Winch/davit/crane on deck near to ship's side required5T davit/winchSteel - 10T
Pumps and suction hose within deck crane reach and laydown area. 500,000 0
8 Piping
Approx 300 meter SW pipes & hypochlorite pipes300 m x 2030 = USD 610K (labor)300 m = USD 100K (30" GRE pipes)300 m x 89 = USD 27K (labor)300 m = USD 3K (2" GRE pipes)
Approx. 50 meter pipes & hypochlorite pipes
50 m x 2030 = USD 100K (labor)50 m = USD 20K (30" GRE pipes)50 m x 89 = USD 5K (labor)50 m = USD 1K (2" GRE pipes)
740,000 131,000
CAPEX Comparison
9 Power cables
Approx. 300 meter eachTotal 900 metersAssume 1500 kW motor95 dia cables, 3CCable - 900 x 80 = USD 72 KLabor - 900 x 20 = USD 18 K600W SS Cable Trays - 900 x 250 = USD 225Klabor - 900 x 170 = USD 153 K
Approx 50 meter eachTotal 150 metersAssume 1500 kW motor95 dia cables, 3CMaterial - 150 x 80 = USD 12 KCable - 150 x 20 = USD 3 K600W SS Cable Trays - 150 x 250 = USD 37.5 Klabor - 150 x 170 = USD 25.5 K
468,000 78,000
10 Instrument cables
Approx. 300 meter eachTotal 900 metersCable 25 dia - 900 x 20 = 18Klabor - 900 x 10 = 9K150W SS cable trays - 900 x 190 = 171Klabor - 900 x 120 = 108K
Approx 50 meter eachtotal 150 metersCable 25 dia - 150 x 20 = 3Klabor - 150 x 10 = 1.5K150W SS cable trays - 150 x 190 = 28.5 Klabor - 150 x 120 = 18K
306,000 51,000
11 Potential clashing
100 m suction hose and risers/chains Far away from risers/chains
12 SafetyRisk of uncontrolled flooding due to leakage on seachest piping
Incidental flooding exposure avoided.
TOTAL 9,524,000 7,080,000
Summary
• Submersible SWL pumps for caisson installation will have approx. 35 % lower CAPEX than an conventional SWL pumps for pump room installation confirmed by a third party.
• Additional Engineering not included in the comparison, so the difference most likely higher.
• Also confirming uncontrolled flooding eliminated
• Challenges with suction hoses when using pump room solution
Similar or even bigger differences will be seen on firewater pump systems as even
more interfaces will have to be solved
Similar or even bigger differences will be seen on firewater pump systems as even
more interfaces will have to be solved
When do you need the pumps?
Pump room installation
Caisson installed pumps
Applies for both SWL and FWP
Conclusions
Caisson installation has lower total CAPEX and OPEX Investments (money spent) can be delayed up to a year Provides more time to include last minute process changes By adding spare caisson – or installing large enough caissons,
added capacity can be easier made for future modifications in cases where tie-ins from other fields are included.
Ballast and de-ballast pump should also be arranged in a way that hull penetration is avoided. I.e. pumping water above deck level.
In general; Avoid hull penetration and improve safety & HSE!
Do more for less!