Upload
vukhanh
View
212
Download
0
Embed Size (px)
Citation preview
Northern Arizona University PCI Big Beam Contest Team 1
Northern Arizona UniversityPCI Big Beam Contest 2013
Team 1 (XDF)
Team MembersJunfeng Qian
Qi WangShiyu Wang
Technical AdvisorRobin Tuchscherer, Ph.D., P.E.
Assistant ProfessorConcrete Construction Member Contest SponsorsTpac A Division of Kiewit Western Co. Precast/ Prestressed Concrete InstitutePhoenix, AZ Sika Corporation Special Thanks to David L. Chapin
Page | 1
Northern Arizona University PCI Big Beam Contest Team 1
Table of Contents1. Introduction..........................................................................................................................................3
2. Background..........................................................................................................................................3
3. Concrete Mix........................................................................................................................................5
4. Beam Design.........................................................................................................................................7
5. Final Analysis & Prediction................................................................................................................8
6. Test Set Up..........................................................................................................................................12
6.1 Concrete Cylinder Sample Test................................................................................................12
6.2 Beam Test...................................................................................................................................12
7. Test Result..........................................................................................................................................14
8. Comparison of Prediction and Test Results....................................................................................14
9. Conclusion..........................................................................................................................................15
10. Lessons Learned and Suggestions for the Future.......................................................................15
11. Test Summary Form......................................................................................................................17
Appendix A—Reference
Appendix B—Shop Drawing
Appendix C—Photographs of Field Trip
Appendix D—Photographs of Test Machine
Appendix E—Deflection Prediction
Appendix F—Detail of Final Beam Desgin
Appendix G—Response 2000 Analysis
Appendix H—Design Matrix
Appendix I—Test Machine
Appendix J—Photographs of Beam Test
Appendix K—Concrete Mix Report
Appendix L—Final Calculation (Hand Wirting)
Page | 2
Northern Arizona University PCI Big Beam Contest Team 1
1. IntroductionTeam 1 participates in the PCI Big Beam Contest for the 2013-2013 academic years. In
order to finish this project, the team design and build a prestressed concrete beam which is 20 ft.
long and test as a18 ft. span. The beam has to be designed to meet the contest rules. The team
begins to approach this project by reviewing the contest rules and assign tasks to team members.
In addition, the team asks Dr. Tuchscherer, who is PCI Big Beam Contest technical advisor, for
some suggestions. Based on the information gathered from these resources, the team decides that
the central design of this project should include the cross-sectional geometry, the selection of
possible mix designs, the size of reinforcing bar and prestressed strand, and location of
reinforcing bar and prestressed strand.
This project is a real challenge for the team which is composed of undergraduate
students. The team members have limit knowledge of prestressed concrete beam design.
Therefore, a background research is necessary for the team to complete before the beam design.
During the beam design, the team creates several judging criteria to pick the final design from
the design alternatives. The background, mix design, beam design, and final analysis and
prediction are described in the following section of this report. A description of the testing
process, a discussion of the results, and conclusion are also included.
2. BackgroundAs the contest rule required, the beam should be designed to carry a total factored live
load between 32 kips and 39 kips. In addition, the beam shall not crack under the total applied
service load of 20 kips. If the beam does not meet these requirements, the scores will decrease.
The beam should be loaded by applying two point loads, symmetrically, 7 feet from the center of
each support. Figure 1 shows the permitted load configuration that the team used to test the
Page | 3Figure 1: Permitted Load Configuration
Northern Arizona University PCI Big Beam Contest Team 1
beam. In addition, low cost, low weight, largest measured deflection at midspan, and the
predictions of design load, deflection, and cracking load should be put into consideration in order
to get a high score.
However, based on the understanding of the team, the key criteria that affect our design
should be design load, total cost, and weight. Each of them could have a big effect on the design
of the beam. The unit cost of materials that used in beam design is regulated in the contest rules.
Table 1 shows the unit cost of each material.
Table 1: Unit Cost of Material
Material CostConcrete $100/yd3
Fiber-Strength Concrete $120/yd3
Fiber-Reinforced Concrete $110/yd3Lightweight Concrete add $10/yd3 to the concrete costPrestressing Strand:3/8 in. Diameter $0.17/ft.1/2 in. diameter $0.30/ft.1/3 in. diameter $0.32/ft.0.6 in. diameter $0.42/ft.0.7 in. diameter $0.55/ft.Steel:A615/A706 $0.45/lb.Weld wire $0.50/lb.A1035 $0.70/lb.Plate steel $0.55/lb.
The information of the concrete mix is given by the sponsor company, Tpac Company. A
field trip visit to the Tpac Company gives the team a lot of information about fabrication of
concrete beam. Figure 2 shows the trademark of Tpac Company. The project manager David L.
Chapin of Sponsor Company provides the limitation of strand spacing to 2 inches and the
availability of ½ -inch “special” strands. Only #4 and #5 of A615 steel could be used in beam
design. For the final design of the beam, the team decides to use self-consolidating concrete
which have a 4500 psi specified compressive strength of concrete at the time of initial prestress
(f’ci=4500 psi) and a 8500 psi specified compressive strength of concrete (f’c=8500 psi). In
addition, ASTM Seven-Wire Strand (Grade 270), and ASTM A615/A706 (#5 rebar) are used in
Page | 4
Northern Arizona University PCI Big Beam Contest Team 1
the beam design. The selection of concrete mix, reinforcing bar, and prestressed strand are
explained in the upcoming sections.
Figure 2: Field Trip to Tpac Company in Phoenix
3. Concrete MixThe materials for the mix design were determined by availability. Due to the requirement
of Tpac Company, the concrete material could be selected from lightweight concrete and normal
weight concrete (self-consolidated concrete). Before the decision is rendered, the team creates a
table to compare lightweight concrete and self-consolidating concrete. Table 2 shows the pros
and cons of each concrete.
Page | 5
Northern Arizona University PCI Big Beam Contest Team 1
Table 2: Pros and Cons of Self-Consolidating Concrete and Lightweight Concrete
Self-Consolidating Concrete Lightweight Concrete
Pros
1. Easy to achieve high strength
transfer and ultimate.
2. Low Water Cement ratio assists
with permeability.
3. Easy to place concrete with
maximum consolidation.
4. Proven Performance.
5. High shear values at transfer and
28 days.
1. Low unit weight
2. Good to above average 28 day
compression strength for
lightweight.
3. Low Water Cement ratio
assists with permeability.
4. Easy to place concrete with
maximum consolidation.
5. High fire rating.
Cons
1. High unit weight.
2. No air entrainment for severe
weather conditions.
3. Low fire rating.
1. Low shear values at transfer
and 28 days.
2. Specific gravity of lightweight
material is unstable.
3. Low transfer strengths if
proper curing procedures are
not used.
As can be seen from Table 1, both self-consolidating concrete and lightweight concrete
have advantages and disadvantages. Based on our understanding of this project, a stable
performance, great compressive force, and high shear values are more important for the beam to
meet all the contest rules. Self-consolidating concrete has a proven performance and it is easy to
achieve high strength transfer and ultimate. Additionally, cost is another important factor that the
team put into consideration. From the unit cost table (Figure 2), normal weight concrete (self-
consolidating concrete) is $10 cheaper than lightweight concrete per cubic yard. Therefore, the
team worked with Tpac Company to choose the concrete mix, using a 28-day compressive
strength of 8,500 psi.
The concrete mix design data is provided by Tpac Company. The proportions and
measured weight of concrete mix is shown in Table 3.
Page | 6
Northern Arizona University PCI Big Beam Contest Team 1
Table 3: Final Concrete Mix*
Material Material WeightType II APC (Cement) 655 lb
Class F (fly ash) 240 lbAggregate: WCS Maricopa 1300 lbAggregate: ½” No.7 Rock 1399 lb
Water 325 lbEstimate Air 1.00%
*Chemical admixtures are not listed as they are proprietary
The mixes use Type II cement and a water-to-cement ratio of 0.363 to achieve high
strengths. Fly ash is used to increase the strength of the mix while also decreasing the water
demand. Figure 3 shows the scene of beam fabrication.
Page | 7
Figure 3: Concrete Fabrication
Northern Arizona University PCI Big Beam Contest Team 1
4. Beam DesignConsidering the construct convenient and efficiency, “I” shape is used to design the
beam. Because I shape has less weight, less materials used, and higher strength comparing to the
other same level shapes, such as T shape beam and box shape beam. In order to perform well in
each of the judging criterion and satisfy the provision of ACI-318 code and the PCI Design
Handbook, firstly Team 1 used excel sheet to meet all requirements of the contest, such as
cracking moment, stress at release, and design load. After meet all the requirements, Team 1
tried eight alternatives based on “I” shape by changing the dimension of cross-section of the
beam, number of strand, and number of reinforcement bar to reduce the cost and the weight. As
the table shown below, Team 1 takes three types of I shape beams to as the final comparison to
each other. Table 4 shows comparison of three qualified design options.
Table 4: Three Qualified Design Options with Several Key Variables
Release Stress Live Load ∆ Equiv
Cross Section f'c
(ksi)f'ci
(ksi)# of
strands σtop (ksi) σ bot (ksi) P crack (kip) PU (kip) EI (kip-
in2)
8.5 4.5 3 0.365 -2.198 23.8 33.6 61766449
8.5 4.5 4 0.517 -3.037 34.4 36.8 65442229
8.5 4.5 4 0.356 -2.157 29.8 40.78 68335328
Requirement σtop<7.5√ f ' c σ bot<0.7 f'ci P>20 kips 32 <P<39
(kips)
Page | 8
Northern Arizona University PCI Big Beam Contest Team 1
As the table shows, all of the three type of I shape beams meet the requirements of the
contest. In order to determine the most efficient design, Team 1 did design matrix of the three
different designs of concrete. The elevation view of the beam design is shown in Figure 2. This
final design satisfies ACI-318 tensile and compressive stress checks at release and under service
load. Table 5 shows the design matrix.
Table 5: Design Matrix
Beam 1 Beam 2 Beam 3
Type Percentile Measured Value
Grade Measured Value
Grade Measured Value
Grade
Cost ($) 35 126.5 10 132.5 9 142.5 7
EI* (kip-in2) 30 61766449 8 65442229 9 68335328 7
Weight (lb.) 35 1909.59 10 1900.06 10 1990.31 6
Total (10) 100 9.4 9.35 6.65
*EI= Flexural Stiffness; the lower the EI, the higher the deflection
As the table shown above, “Beam 1” gets the highest score of the three designs. As a
result, team 1 chose this beam design as their final beam design. Figure 4 shows the detail of
cross-section of final design.
Page | 9
Northern Arizona University PCI Big Beam Contest Team 1
Figure 3: Cross-Section of Final Design
As the details shows in Figure 4, the team uses 5 A615 steels (NO.5), 3 prestressing strands, and A615 steel (NO.4) in the final design. The amount and cost of each material are list in Table 6.
Table 6: Detail of Materials used in Final Design
Materials Amount Unit Cost CostNormal Weight Concrete 0.47 cu yd. $ 100/cu yd. $ 47
Prestressing Strand 3*20 ft. $ 0.30/ft. $ 18A615 #5 Rebar 5*20 ft. $ 0.45/lb. $ 47Welded Mesh 25.8 lb. $ 0.50/lb. $ 13
A615 #4 Rebar 4*0.7 ft. $ 0.45/lb. $1.5
Total Cost $ 126.5
Page | 10
Northern Arizona University PCI Big Beam Contest Team 1
5. Final Analysis & PredictionPredicted values of stress at release, cracking moment, moment capacity, design load, and
shear capacity are done by using Excel software and the calculations are checked by hand. The
Tpac Company did the most part of the fabrication process for the team. Tpac Company
provided concrete mix, formwork, longitudinal reinforcement, and tendons to the team.
Response 2000 software is used to perform refined analysis which can generate more accurately
predict strength and deflection values. As the final analysis show, the response values are fairly
close to the Excel values. Figure 5 shows the moment curvature.
After getting the Moment-Curvature response, the team used the method of virtual work
to predict the deflection of the beam. The equation of the virtual-work method is
∆=∫0
l m pmQ
EIdx+∫
0
l
kV p V Q
GAdx.
In this equation, “mQ” is virtual moment produced by virtual moment; “mp” is real
moment; “E” is the modulus of elasticity. “I” is the moment of inertia. “Vp” is real shear force;
“VQ” is shear force produced by virtual load.
Figure 6 shows how the loaded distributed on the beam. The distribution load is the dead
load of the beam, and the concentrated load is the load come from the hydraulic cylinder.
Page | 11
Figure 5: Moment Curvature from Response 2000
Northern Arizona University PCI Big Beam Contest Team 1
The moment equation of the beam is shown below:
When 0<x<7 MQ(x) = (ω (9’) +Pn) x-wdl x2
2
When 7<x<9 MQ(x) = (ω (9’) +Pn) x-wdl x2
2−Pu(x−7)
By using excel sheet, the prediction of the deflection is 1.7 ft. Figure 7 shows the
Microsoft Excel spreadsheet which is used to predict the deflection of the final design.
Page | 12
Figure 6: Load Distribution Diagram
Northern Arizona University PCI Big Beam Contest Team 1 dx mP(x) mQ(x) mP(x)/EI mQmP(x)/EI*dx Ave f f*Dx*dx VQ VP
(in) (kip-in) (kip-in) (rad/in) (in) (rad/in) (in) (kip) (kip)0 0 0 -50 0.5 16.828 7.1386E-052 33.64067 1 -49.49843456 -4.97492E-05 4.97492E-05 -4.9749E-05 -0.000199 0.5 16.81267 7.1386E-054 67.25067 2 -45.85529101 -0.000143031 0.00019278 -4.7677E-05 -0.00038141 0.5 16.79733 7.1321E-056 100.83 3 -42.21547157 -0.000220177 0.000412957 -4.4035E-05 -0.00052842 0.5 16.782 7.1256E-058 134.3787 4 -38.73175817 -0.000283315 0.000696272 -4.0474E-05 -0.00064758 0.5 16.76667 7.1191E-05
10 167.8967 5 -35.82038903 -0.000335485 0.001031757 -3.7276E-05 -0.00074552 0.5 16.75133 7.1126E-0512 201.384 6 -32.91168359 -0.000378026 0.001409783 -3.4366E-05 -0.00082478 0.5 16.736 7.1061E-0514 234.8407 7 -30.00564186 -0.000408963 0.001818746 -3.1459E-05 -0.00088084 0.5 16.72067 7.0996E-0516 268.2667 8 -27.10226383 -0.000428309 0.002247055 -2.8554E-05 -0.00091373 0.5 16.70533 7.0931E-0518 301.662 9 -24.20450909 -0.000436108 0.002683163 -2.5653E-05 -0.00092352 0.5 16.69 7.0865E-0520 335.0267 10 -21.31279562 -0.000432414 0.003115577 -2.2759E-05 -0.00091035 0.5 16.67467 7.08E-0522 368.3607 11 -18.42374004 -0.000417234 0.003532811 -1.9868E-05 -0.0008742 0.5 16.65933 7.0735E-0524 401.664 12 -15.53734233 -0.000390552 0.003923363 -1.6981E-05 -0.00081507 0.5 16.644 7.067E-0526 434.9367 13 -12.6536025 -0.000352387 0.00427575 -1.4095E-05 -0.00073296 0.5 16.62867 7.0605E-0528 468.1787 14 -9.772070409 -0.000302747 0.004578496 -1.1213E-05 -0.00062792 0.5 16.61333 7.054E-0530 501.39 15 -6.89299506 -0.000241643 0.00482014 -8.3325E-06 -0.00049995 0.5 16.598 7.0475E-0532 534.5707 16 -4.01657819 -0.000169098 0.004989238 -5.4548E-06 -0.00034911 0.5 16.58267 7.041E-0534 567.7207 17 -1.1428198 -8.51301E-05 0.005074368 -2.5797E-06 -0.00017542 0.5 16.56733 7.0345E-0536 600.84 18 1.728280112 1.02456E-05 0.005064123 2.9273E-07 2.10766E-05 0.5 16.552 7.028E-0538 633.9287 19 4.597883117 0.000117034 0.004947089 3.16308E-06 0.000240394 0.5 16.53667 7.0215E-0540 666.9867 20 7.464963488 0.000235226 0.004711863 6.03142E-06 0.000482514 0.5 16.52133 7.015E-0542 700.014 21 10.32938418 0.000364784 0.004347079 8.89717E-06 0.000747363 0.5 16.506 7.0085E-0544 733.0107 22 13.19114518 0.000505691 0.003841388 1.17603E-05 0.001034903 0.5 16.49067 7.0019E-0546 765.9767 23 16.05034898 0.000657934 0.003183454 1.46207E-05 0.001345109 0.5 16.47533 6.9954E-0548 798.912 24 18.9080844 0.000821523 0.002361931 1.74792E-05 0.001678005 0.5 16.46 6.9889E-0550 831.8167 25 21.76315892 0.000996445 0.001365485 2.03356E-05 0.002033562 0.5 16.44467 6.9824E-0552 864.6907 26 24.61557257 0.001182658 0.000182828 2.31894E-05 0.002411694 0.5 16.42933 6.9759E-0554 897.534 27 27.46532532 0.001380144 -0.00119732 2.60404E-05 0.002812368 0.5 16.414 6.9694E-0556 930.3467 28 30.57740361 0.001596175 -0.00279349 2.90214E-05 0.003250393 0.5 16.39867 6.9629E-0558 963.1287 29 34.50569564 0.001854868 -0.00464836 3.25415E-05 0.00377482 0.5 16.38333 6.9564E-0560 995.88 30 38.43031286 0.002151612 -0.00679997 3.6468E-05 0.004376161 0.5 16.368 6.9499E-0562 1028.601 31 42.35125528 0.002463838 -0.00926381 4.03908E-05 0.005008457 0.5 16.35267 6.9434E-0564 1061.291 32 49.92745934 0.00290678 -0.01217059 4.61394E-05 0.005905838 0.5 16.33733 6.9369E-0566 1093.95 33 59.67305791 0.003562017 -0.01573261 5.48003E-05 0.007233634 0.5 16.322 6.9304E-0568 1126.579 34 73.42385825 0.004458747 -0.02019135 6.65485E-05 0.00905059 0.5 16.30667 6.9239E-0570 1159.177 35 89.85677907 0.005633182 -0.02582453 8.16403E-05 0.011429645 0.5 16.29133 6.9173E-0572 1191.744 36 108.51396 0.007042161 -0.0328667 9.91854E-05 0.014282693 0.5 16.276 6.9108E-0574 1224.281 37 129.1777008 0.008675746 -0.04154244 0.000118846 0.017589183 0.5 16.26067 6.9043E-0576 1256.787 38 151.8656861 0.010539127 -0.05208157 0.000140522 0.021359297 0.5 16.24533 6.8978E-0578 1289.262 39 177.0772669 0.012664304 -0.06474587 0.000164471 0.02565755 0.5 16.23 6.8913E-0580 1321.707 40 205.3736427 0.015106811 -0.07985268 0.000191225 0.030596073 0.5 16.21467 6.8848E-0582 1354.121 41 239.149896 0.018003203 -0.09785589 0.000222262 0.03645093 0.5 16.19933 6.8783E-0584 1386.504 42 280.9876328 0.021585707 -0.11944159 0.000260069 0.043691552 0.5 16.184 6.8718E-0586 1386.857 43 281.53071 0.02390703 -0.14334862 0.000281259 0.048376577 0.5 0.168667 3.4701E-0588 1387.179 44 282.0265631 0.024514741 -0.16786336 0.000281779 0.04959304 0.5 0.153333 6.8329E-0790 1387.47 45 282.4751921 0.025120328 -0.19298369 0.000282251 0.050805158 0.5 0.138 6.1821E-0792 1387.731 46 282.876597 0.025723506 -0.2187072 0.000282676 0.052012365 0.5 0.122667 5.5314E-0794 1387.961 47 283.2307777 0.026323993 -0.24503119 0.000283054 0.053214093 0.5 0.107333 4.8806E-0796 1388.16 48 283.5377344 0.026921504 -0.2719527 0.000283384 0.054409777 0.5 0.092 4.2299E-0798 1388.329 49 283.797467 0.027515757 -0.29946845 0.000283668 0.05559885 0.5 0.076667 3.5791E-07
100 1388.467 50 284.0099755 0.028106468 -0.32757492 0.000283904 0.056780744 0.5 0.061333 2.9284E-07102 1388.574 51 284.1752598 0.028693354 -0.35626828 0.000284093 0.057954894 0.5 0.046 2.2776E-07104 1388.651 52 284.2933201 0.029276132 -0.38554441 0.000284234 0.059120732 0.5 0.030667 1.6269E-07106 1388.697 53 284.3641562 0.029854518 -0.41539893 0.000284329 0.060277692 0.5 0.015333 9.7613E-08108 1388.712 54 284.3877683 0.030428228 -0.44582715 0.000284376 0.061425208 0.5 1.03E-15 3.2538E-08
Deflection 0.445827154 0.901003148 0.00305221
Total Deflection 1.79876187 0.00610441
Figure 7: Excel Spreadsheet for Beam Deflection
Page | 13
Northern Arizona University PCI Big Beam Contest Team 1
After determining the final design of concrete beam, the team sent the final design to
Tpac Company for fabrication. On February 8, 2013, prestressed concrete beams were fabricated
at Tpac Company.
6. Test Set UpIn Test section, it will address concrete cylinder test and beam test. Cylinder test is to
achieve more accurate value of the modulus of elasticity of concrete, which in turn reduce
differences between theoretical prediction and actual test result. Beam test is a primary process
in the project. During the beam test, beam will be loaded till to failure to obtain values of
cracking load, ultimate load and deflection.
6.1 Concrete Cylinder Sample TestConcrete cylinder sample test was test one day before the beam test. Six 4X8 cylinders
were available to be tested, three of them were conducted by compression test and the other three
were conducted by split cylinder test. The compression test and split tension test were both
conducted with universal testing machine at mechanical material laboratory.
By doing the concrete cylinder sample test, results were recorded in Table 7:
Table 7: Cylinder Sample Test Results
Average calculated compressive pressure
(psi)
Average splitting tensile strength
(psi)
8316 541
Page | 14
Northern Arizona University PCI Big Beam Contest Team 1
6.2 Beam TestThe prestressed concrete beam was tested in the Concrete Lab in Engineering Building at
Northern Arizona University on March 26th, 48 days after the beam was cast at Tpac Company.
Before the test, one beam picture with March 26th newspaper was taken and sent to the Sponsor
Dave to show that the beam was taken on or after March 26th, The basic information of Team 1
prestressed concrete beam and the prediction of applied point load at midspan to cause cracking,
maximum applied point load at midspan, and maximum anticipated deflection due to applied
load only were sent to Dave via email as well before the beam test (for more information, please
see the appendix). The Entire process of the beam test was recorded by video. Weight of the
beam has been measured by Tpac Company. The weight of the beam is 2,000lb. Before testing,
Team 1 has ensured that the beam rested evenly on the test machine.
The test instrument can be illustrated by Figure 8:
As Figure 8 shows, the span length between the two pads is 18ft. The ram is located in the
center of the beam. The two load points are 7 ft. away from the center of the beam.
During the test, all the data, such as deflection and load was collected by using computer
software. The String Potentiometer transfers the deflection of the beam into the computer
software. The load was increased by approximately 10 kip increments until 20 kip. After the
point of 20 kips, the load was increased slowly so that the more accurate date can be achieved.
After every load increment, Team 1 needed to read the deflection and inspect the crack whether
the beam has cracked personally.
When the load came to the maximum load that the beam could hold, a lot of crackles came
out from the side to the midspan. Some cracks had an angle of 45o to the midspan. The failure
Page | 15
Figure 8: Test Instrument
Northern Arizona University PCI Big Beam Contest Team 1
happened when the load came to 41.54 kips. The failure point was on the right side load point of
the beam 4 ft. away from the midspan.
7. Test ResultAll the test results were recorded by using computer software. All the data from the strain
gauges were in electricity and Team 1 transferred it into data by multiplying the string factor.
After getting the data, these data was input into excel sheet to do the comparison to the
prediction. Applied point load at midspan to cause cracking is 23.2kip. The maximum applied
point load at midspan is 41.54 kip. Maximum anticipated deflection due to applied load only is
7.42 in. Figure 9 shows the load-deflection curve.
Figure 9 Deflection of the Beam with Increasing the Load
8. Comparison of Prediction and Test ResultsThe performance of the concrete beam was well predicted by Team 1. As expected, the
prestressed concrete was failure duo to the ultimate load. As anticipated, when going to failure,
the stress and strain curve came to near a horizontal line, then drop slightly to the failure point.
The table below shows the comparison between prediction and test results. The prediction of
point load at crack is pretty close to the actual value. However, the maximum applied point load
at midspan and the maximum anticipated deflection due to applied load are no as accurate as
Page | 16
Northern Arizona University PCI Big Beam Contest Team 1
crack load. The operation of increment of load may cause the error as well. Table 8 shows the
predicted and actual values of the beam with percent errors. In addition, the reason that the
deflection has such a huge difference between the prediction value and the actual value is that the
team did not change the default value of peak strain in Response 2000 computer software. This
mistake made a huge difference in the deflection.
Table 3: Predicted Values VS. Actual Values
Data Description Predicted Actual Percent ErrorPoint Load Cracking (kips) 23.8 23.2 2.52%Maximum Point Load (kips) 36.35 41.54 14.3%
Deflection at Maximum Load (in) 1.703 6.42 335.7%
9. ConclusionIn order to meet the design criteria presented in the 2013 PCI Big Beam Contest, the team
learn the knowledge from all kinds of sources about prestressed concrete and contribute to beam
design. During the beam design, the team makes a lot of changes on the original design to meet
the design restriction and satisfy ACI and PCI provisions. The beam is fabricated by the sponsor
company-Tpac. Therefore, the materials used in the design are limited. However, the use of
wired mesh is the most noticeable feature. The wired mesh resulted in increase the shear capacity
of the prestressed concrete beam and reduces the total weight. Including additional stirrups in the
beam was another characteristic. These stirrups are added to ensure the beam does not fail due to
shear force and all compression steels are hooked up. The results of ultimate load and deflection
have a big differences when compare with the predictions. The main reason that leads to these
differences is that the team did not change the default value of peak strain in Responses 2000
program. However, the result of cracking load is very close to what the team predicts. Due to the
correct Excel spreadsheet, the team get the accurate value when calculate the cracking load.
Ultimately, these design characteristics encompassed an optimized design and a well-understood
concrete beam.
Page | 17
Northern Arizona University PCI Big Beam Contest Team 1
10. Lessons Learned and Suggestions for the FutureParticipating in the PCI Big Beam Contest help the team members to enrich the
knowledge and improve abilities. During the beam design, the team gets the experience on how
to work in a group to study the knowledge of prestressed concrete, computer design, and conduct
the beam test. In order to move the project forward smoothly, each teammate is clear on their
roles which are assigned at the beginning of the project. The roles include beam designer, project
manager, report writer. Each teammate is responsible for a particular project component. When
each component is finished, the entire team goes through the whole process of this project.
Working on this project in a group not only helps each teammate to increase his abilities of
communication, organization, and initiative learning, but also let the teammates recognize their
strengths and weakness.
As undergraduate students, it is a challenge for the team to design a prestressed concrete
beam. First of all, the team needs to learn the knowledge of prestressed concrete. Then, the team
needs to be familiar with ACI-318 code and PCI design handbook in order to meet the design
limitations such as stress at release (ftop, fbottom). During the beam design, the team use Microsoft
Excel to build the dimension of the cross section of the beam and calculate each variable. In
order to achieve the goals of lowest weight, lowest cost, largest deflection, and highest maximum
load , the team is required to understand the effects of cross section dimension, stirrups,
compression steel, prestressed strands, and the location of reinforcement. These individual
components have a big effect on the behavior of concrete beam, which means it is necessary for
the team to learn these important knowledge and concept during the beam design or even before
the project start.
In addition, each teammate learns how to operate a concrete beam test from this project.
The process of setting up the test instrument, installing sensors, design the deflection indicator,
and finally testing the beam is a good learning experience for the team members. Even though
the beam is design to meet the rules and testing criteria assigned in the contest, the knowledge
from the experience can be applied to future design problems.
If the team has another opportunity to participate the PCI Big Beam Contest again, the
team will be carefully notice the operation of Response 2000 program and ultimate load
prediction.
Page | 18
Northern Arizona University PCI Big Beam Contest Team 1
Here are some recommendations from Team 1 for PCI Big Beam Contest:
A discussion of future application of the beam should be required in the contest rules
People who have different academic background could participate in this contest
The contest committee should assign a technical faculty to each team
Page | 19
Northern Arizona University PCI Big Beam Contest Team 1
11. Test Summary Form
Page | 20
Northern Arizona University PCI Big Beam Contest Team 1
Appendix A— ReferencesACI (2011). ACI 318-11: Building Code Requirements for Structural Concrete and
Commentary.
PCI (2010), PCI Design Handbook, Precast and Prestressed Concrete, Seventh Edition.
Page | 21
Northern Arizona University PCI Big Beam Contest Team 1
Appendix B—Shop Drawing
Page | 22
Northern Arizona University PCI Big Beam Contest Team 1
Page | 23
Northern Arizona University PCI Big Beam Contest Team 1
Appendix C— Field Trip Photographs
Page | 24
Northern Arizona University PCI Big Beam Contest Team 1
Page | 25
Northern Arizona University PCI Big Beam Contest Team 1
Appendix D—Photographs of Test Machine
Page | 26
Northern Arizona University PCI Big Beam Contest Team 1
Page | 27
Northern Arizona University PCI Big Beam Contest Team 1
Page | 28
Northern Arizona University PCI Big Beam Contest Team 1
Appendix E —Deflection Prediction dx mP(x) mQ(x) mP(x)/EI mQmP(x)/EI*dx Ave f f*Dx*dx VQ VP
(in) (kip-in) (kip-in) (rad/in) (in) (rad/in) (in) (kip) (kip)0 0 0 -50 0.5 16.828 7.1386E-052 33.64067 1 -49.49843456 -4.97492E-05 4.97492E-05 -4.9749E-05 -0.000199 0.5 16.81267 7.1386E-054 67.25067 2 -45.85529101 -0.000143031 0.00019278 -4.7677E-05 -0.00038141 0.5 16.79733 7.1321E-056 100.83 3 -42.21547157 -0.000220177 0.000412957 -4.4035E-05 -0.00052842 0.5 16.782 7.1256E-058 134.3787 4 -38.73175817 -0.000283315 0.000696272 -4.0474E-05 -0.00064758 0.5 16.76667 7.1191E-05
10 167.8967 5 -35.82038903 -0.000335485 0.001031757 -3.7276E-05 -0.00074552 0.5 16.75133 7.1126E-0512 201.384 6 -32.91168359 -0.000378026 0.001409783 -3.4366E-05 -0.00082478 0.5 16.736 7.1061E-0514 234.8407 7 -30.00564186 -0.000408963 0.001818746 -3.1459E-05 -0.00088084 0.5 16.72067 7.0996E-0516 268.2667 8 -27.10226383 -0.000428309 0.002247055 -2.8554E-05 -0.00091373 0.5 16.70533 7.0931E-0518 301.662 9 -24.20450909 -0.000436108 0.002683163 -2.5653E-05 -0.00092352 0.5 16.69 7.0865E-0520 335.0267 10 -21.31279562 -0.000432414 0.003115577 -2.2759E-05 -0.00091035 0.5 16.67467 7.08E-0522 368.3607 11 -18.42374004 -0.000417234 0.003532811 -1.9868E-05 -0.0008742 0.5 16.65933 7.0735E-0524 401.664 12 -15.53734233 -0.000390552 0.003923363 -1.6981E-05 -0.00081507 0.5 16.644 7.067E-0526 434.9367 13 -12.6536025 -0.000352387 0.00427575 -1.4095E-05 -0.00073296 0.5 16.62867 7.0605E-0528 468.1787 14 -9.772070409 -0.000302747 0.004578496 -1.1213E-05 -0.00062792 0.5 16.61333 7.054E-0530 501.39 15 -6.89299506 -0.000241643 0.00482014 -8.3325E-06 -0.00049995 0.5 16.598 7.0475E-0532 534.5707 16 -4.01657819 -0.000169098 0.004989238 -5.4548E-06 -0.00034911 0.5 16.58267 7.041E-0534 567.7207 17 -1.1428198 -8.51301E-05 0.005074368 -2.5797E-06 -0.00017542 0.5 16.56733 7.0345E-0536 600.84 18 1.728280112 1.02456E-05 0.005064123 2.9273E-07 2.10766E-05 0.5 16.552 7.028E-0538 633.9287 19 4.597883117 0.000117034 0.004947089 3.16308E-06 0.000240394 0.5 16.53667 7.0215E-0540 666.9867 20 7.464963488 0.000235226 0.004711863 6.03142E-06 0.000482514 0.5 16.52133 7.015E-0542 700.014 21 10.32938418 0.000364784 0.004347079 8.89717E-06 0.000747363 0.5 16.506 7.0085E-0544 733.0107 22 13.19114518 0.000505691 0.003841388 1.17603E-05 0.001034903 0.5 16.49067 7.0019E-0546 765.9767 23 16.05034898 0.000657934 0.003183454 1.46207E-05 0.001345109 0.5 16.47533 6.9954E-0548 798.912 24 18.9080844 0.000821523 0.002361931 1.74792E-05 0.001678005 0.5 16.46 6.9889E-0550 831.8167 25 21.76315892 0.000996445 0.001365485 2.03356E-05 0.002033562 0.5 16.44467 6.9824E-0552 864.6907 26 24.61557257 0.001182658 0.000182828 2.31894E-05 0.002411694 0.5 16.42933 6.9759E-0554 897.534 27 27.46532532 0.001380144 -0.00119732 2.60404E-05 0.002812368 0.5 16.414 6.9694E-0556 930.3467 28 30.57740361 0.001596175 -0.00279349 2.90214E-05 0.003250393 0.5 16.39867 6.9629E-0558 963.1287 29 34.50569564 0.001854868 -0.00464836 3.25415E-05 0.00377482 0.5 16.38333 6.9564E-0560 995.88 30 38.43031286 0.002151612 -0.00679997 3.6468E-05 0.004376161 0.5 16.368 6.9499E-0562 1028.601 31 42.35125528 0.002463838 -0.00926381 4.03908E-05 0.005008457 0.5 16.35267 6.9434E-0564 1061.291 32 49.92745934 0.00290678 -0.01217059 4.61394E-05 0.005905838 0.5 16.33733 6.9369E-0566 1093.95 33 59.67305791 0.003562017 -0.01573261 5.48003E-05 0.007233634 0.5 16.322 6.9304E-0568 1126.579 34 73.42385825 0.004458747 -0.02019135 6.65485E-05 0.00905059 0.5 16.30667 6.9239E-0570 1159.177 35 89.85677907 0.005633182 -0.02582453 8.16403E-05 0.011429645 0.5 16.29133 6.9173E-0572 1191.744 36 108.51396 0.007042161 -0.0328667 9.91854E-05 0.014282693 0.5 16.276 6.9108E-0574 1224.281 37 129.1777008 0.008675746 -0.04154244 0.000118846 0.017589183 0.5 16.26067 6.9043E-0576 1256.787 38 151.8656861 0.010539127 -0.05208157 0.000140522 0.021359297 0.5 16.24533 6.8978E-0578 1289.262 39 177.0772669 0.012664304 -0.06474587 0.000164471 0.02565755 0.5 16.23 6.8913E-0580 1321.707 40 205.3736427 0.015106811 -0.07985268 0.000191225 0.030596073 0.5 16.21467 6.8848E-0582 1354.121 41 239.149896 0.018003203 -0.09785589 0.000222262 0.03645093 0.5 16.19933 6.8783E-0584 1386.504 42 280.9876328 0.021585707 -0.11944159 0.000260069 0.043691552 0.5 16.184 6.8718E-0586 1386.857 43 281.53071 0.02390703 -0.14334862 0.000281259 0.048376577 0.5 0.168667 3.4701E-0588 1387.179 44 282.0265631 0.024514741 -0.16786336 0.000281779 0.04959304 0.5 0.153333 6.8329E-0790 1387.47 45 282.4751921 0.025120328 -0.19298369 0.000282251 0.050805158 0.5 0.138 6.1821E-0792 1387.731 46 282.876597 0.025723506 -0.2187072 0.000282676 0.052012365 0.5 0.122667 5.5314E-0794 1387.961 47 283.2307777 0.026323993 -0.24503119 0.000283054 0.053214093 0.5 0.107333 4.8806E-0796 1388.16 48 283.5377344 0.026921504 -0.2719527 0.000283384 0.054409777 0.5 0.092 4.2299E-0798 1388.329 49 283.797467 0.027515757 -0.29946845 0.000283668 0.05559885 0.5 0.076667 3.5791E-07
100 1388.467 50 284.0099755 0.028106468 -0.32757492 0.000283904 0.056780744 0.5 0.061333 2.9284E-07102 1388.574 51 284.1752598 0.028693354 -0.35626828 0.000284093 0.057954894 0.5 0.046 2.2776E-07104 1388.651 52 284.2933201 0.029276132 -0.38554441 0.000284234 0.059120732 0.5 0.030667 1.6269E-07106 1388.697 53 284.3641562 0.029854518 -0.41539893 0.000284329 0.060277692 0.5 0.015333 9.7613E-08108 1388.712 54 284.3877683 0.030428228 -0.44582715 0.000284376 0.061425208 0.5 1.03E-15 3.2538E-08
Deflection 0.445827154 0.901003148 0.00305221
Total Deflection 1.79876187 0.00610441
Page | 29
Northern Arizona University PCI Big Beam Contest Team 1
Appendix F—Detail of Final Beam Design
b1 (in) 10.00
b2 (in) 3.00
b3(in) 8.00
h1 (in) 3.50
h2 (in) 0.00
h3 (in) 8.00
h4 (in) 0.00
h5 (in) 3.50
y1 (in) 13.25
y2(in) 11.50
y3(in) 7.50
y4(in) 3.50
y5(in) 1.75
A1 (in2) 35.00
A2 (in2) 0.00
A3(in2) 24.00
A4(in2) 0.00
A5(in2) 28.00I1 (in4) 6180.42I2 (in4) 0.00I3 (in4) 1478.00I4 (in
4) 0.00I5 (in4) 114.33
Input Variables
Page | 30
H (in) 15
cover (in) 1
dps (in) 0.5
Aps(in2) 0.153
# of strand(0.5in) 4
db (in) 0.625
A's (in2) 0.31
# of bar'5 4
f'c (ksi) 8.5
f'ci(ksi) 4.5
fpi (ksi) 174
fp.cr (ksi) 200
fpu (ksi) 270
L (ft) 18
Es (ksi) 29000
fy (ksi) 60
Input Variables
Northern Arizona University PCI Big Beam Contest Team 1
b1 (in) 0.65C.G. (in) 7.96yb (in) 7.96yt (in) 7.04yp (in) 1.25
y's (in) 13.75d' (in) 1.25d (in) 13.75
Ec (ksi) 5255.14Eci (ksi) 3823.68Ig (in4) 2256.63Ag (in
2) 87.00Fp (kip) 106.49
Fp.cr (kip) 122.40
Fpu (kip) 165.24
fse (ksi) 157.66Ld (in) 32.85
n 7.58yb.tr (in) 8.17Atr (in
2) 99.19Itr (in
4) 2707.55losses (ksi) 187.00wD (kip/ft) 0.09
MD (kip-ft) at transform length 1.83MD (kip-ft) max 3.55
Calculated Variables
Page | 31
Northern Arizona University PCI Big Beam Contest Team 1
e 's 0.00eps 0.01
fp (ksi) 211.19
c (in) 3.94
Cc (kip) 55.56
Cs (kip) 73.69
Tp (kip) 129.25
Tp-Cs-Cc 0.00
Mn (kip-in) 1587.85
Mn (kip-ft) 132.3208567
MLL (kip-ft) 128.772888
P (kip) 18.39612686
Verifiction TRUE
PLL at Ultimate 16
PLL at Max 19.5
Moment Capacity
Design Load
Page | 32
ftop (ksi) 0.52verification TRUE
fbot (ksi) -3.04
verification TRUE
fr (ksi) 0.69MLL (kip-in) 1442.35MLL (kip-ft) 120.20
Pcr (kip) 17.17
Cracking Moment
Stress at Release
Northern Arizona University PCI Big Beam Contest Team 1
dp (in) 13.75
Vd (kip) 0.61
Vi (kip) 15.39
Mmax (kip-ft) 2.15
fpe (ksi) 4.64
e (in) 6.92
fd (ksi) 0.29
Mcre (kip-ft) 152.79Md (kip-ft) at 7 ft 109.85
Vci (kip) at 7ft 1097.70
fpc (ksi) 0.96
Vp (kip) 0.00
Vcw (kip) 21.83
Vc (kip) 21.83
S (in) 11.25
fyt (ksi) 60.00
Av(in2) 0.04
Vs (kip) 8.25
ØVn (kip) 22.56
Vu (kip) 16.00
Verifiction TRUE
Shear Force
Page | 33
dwm (in) 0.00
layers of weld mesh 1.00Area of welded wire
(ft2) 26.67
Unit Weight (lb/ft2) 0.86
Unit Cost ($/lb) 0.50Weight of welded
mesh(lb) 22.93Cost of welded mesh
($) 11.47
Weight of welded mesh(lb)
Northern Arizona University PCI Big Beam Contest Team 1
Appendix G —Response 2000 Analysis
Page | 34
Northern Arizona University PCI Big Beam Contest Team 1
Appendix H — Design Matrix
Beam 1 Beam 2 Beam 3
Type Percentile Measured Value
Grade Measured Value
Grade Measured Value
Grade
Cost ($) 35 126.5 10 132.5 9 142.5 7
EI* (kip-in2) 30 61766449 8 65442229 9 68335328 7
Weight (lb.) 35 1909.59 10 1900.06 10 1990.31 6
Total (10) 100 9.4 9.35 6.65
Page | 35
Northern Arizona University PCI Big Beam Contest Team 1
Appendix I— Test Machine
Page | 36
Northern Arizona University PCI Big Beam Contest Team 1
Appendix J— Details of Test
Page | 37
Northern Arizona University PCI Big Beam Contest Team 1
Page | 38
Northern Arizona University PCI Big Beam Contest Team 1
Appendix K— Concrete Mix Report
Page | 39
Northern Arizona University PCI Big Beam Contest Team 1
Appendix L—Final Calculation (Hand Writing)
Page | 40