Introduction to Wind Power Generation

Embed Size (px)

Citation preview

  • 8/11/2019 Introduction to Wind Power Generation

    1/27

    Introduction to Wind Energy

    GenerationJulio Lemaitre

    Infrastructure - PowerFebruary 5, 2009

  • 8/11/2019 Introduction to Wind Power Generation

    2/27

    Renewable Generation

    Example of Renewable Sources:

    Hydro (large small)

    Wind

    Geothermal Heat

    Bio-Fuels

    Water Sea Waves, Sea Tides, Rivers

  • 8/11/2019 Introduction to Wind Power Generation

    3/27

    Introduction

    Wind Power:

    Wind Power, derived through the kinetic energy of

    the wind, utilizes wind blowing over the blades of a

    turbine to create a lift which makes the blades

    rotate.

    The turning blades of the wind turbine rotate the

    connected shaft which drives the generator,

    converting the mechanical energy into electricity.

    The power generated in the individual wind turbinegenerators (WTGs) is collected at a substation

    which steps up the voltage to the grid level.

  • 8/11/2019 Introduction to Wind Power Generation

    4/27

    Wind Turbines

    Rotor bladesNacelle

    Tower

    Rotor HubGenerator

    Gear-Box

    Hub height

    One Blade WTG Two Blade WTG Three Blade WTG

    Yaw drive

    System

    Pitch

    System

    The three blade WTG is the predominant technology used

  • 8/11/2019 Introduction to Wind Power Generation

    5/27

    Wind Power

    Wind Poweris determined by:

    oWind speed at hubheight

    oWind direction

    oWind distribution: Weibull k-factor

    oAir density

    oTurbulence

    oPower curve of Wind Turbine GeneratorsoLosses

    oUncertainties

  • 8/11/2019 Introduction to Wind Power Generation

    6/27

    Wind Power (cont.) Wind Power is calculated from:

    P=* air *A*V3*Cp (Watt)

    P = Power (Watt)

    air =air density (kg/m3)A= rotor area (m2)

    V= wind speed (m/s)

    Cp= power coefficient (dimensionless)

    E = Energy (kWh)

    Emax-annual=P*8.76 (kWh)

  • 8/11/2019 Introduction to Wind Power Generation

    7/27

    air = air density (kg/m3) depends mainly on:

    Air temperature (average on site)

    Altitude (topography + hubheight)

    Cp = coefficient depending on WTG design and speed.

    Cp aver= 0.3 to 0.4 (Cp max=0.59 theoretical max)

    V = annual averaged 10minute-average windspeed

    Wind speed is measured using special measurement masts that

    are installed at the wind farm location (usually more than one) to

    register wind speed, wind direction and air temperature.

    Wind mast have anemometers (of a certain accuracy class for

    wind speed measurment) at 2 or 3 altitudes on the mast, a wind

    wane (for wind direction measurement) and thermometers.

    Wind speed is measured at least 1 time each 2 seconds (IEC).

    Wind Power (cont.)

  • 8/11/2019 Introduction to Wind Power Generation

    8/27

    Wind power is directly proportional to: Air density (lower density at higher altitudes)

    Rotor area (harvested wind area in m2)

    (latest average rotor diameters are 80 100m)

    Wind Power (cont.)

    The

    harvested

    power

    increases

    with therotor

    swept

    area

    Source: Danish Wind Industry Association

  • 8/11/2019 Introduction to Wind Power Generation

    9/27

    Wind Power (cont.)

    And increases with the cube of: Wind speed (v3)

    (Wind speed is the key evaluation factor for wind projects, as it

    is water for hydroprojects)

    Definition of Plant Factor (or Capacity Factor):

    The plant factor (pf) is the annual energy output divided by thetheoretical maximum output, if the machine were running at its

    rated (maximum) power during all of the 8766 hours of the year.

    It measures the effective use of the investment (installed power)in the production of energy over a period of time (usually a year).

    pf =Ereal (kWh)/ P (kW)*8766(h)

  • 8/11/2019 Introduction to Wind Power Generation

    10/27

  • 8/11/2019 Introduction to Wind Power Generation

    11/27

    General Layout of a WTG

    WTG with gearbox.

    The gearbox is one

    of most stressed

    components of the

    WTG. It increases the

    Blade/Rotor speed in

    about 40-60 times tooperate the generator.

    The pitch regulation

    allows for optimal

    adjustments of the

    blades to the wind

    conditions (speed).

    The yaw control

    positions the nacelle

    (rotor) to the wind

    direction.

    Source: Dirk Kooman

  • 8/11/2019 Introduction to Wind Power Generation

    12/27

    Power Curve

    0

    500

    1000

    1500

    2000

    2500

    1 3 5 7 911

    13

    15

    17

    19

    21

    23

    25

    PinkW

    Va in m/s

    Cut in Wind speed

    Cut out Wind speed

    Nominal Wind speed

    The power curve

    gives the relation of

    wind speed vs. power

    for a given WTG.

    The WTG requires a

    minimum speed to

    start generating (cut in

    wind speed).

    The power produced

    will depend on the

    wind speed until

    reaching the nominal

    value.

    When the wind

    reaches the cut out

    wind speed, the WTG

    stops generating to

    avoid mechanical

    stresses.

  • 8/11/2019 Introduction to Wind Power Generation

    13/27

    Wind speed is very variable and changes permanently with the

    time of day, the seasons and the years, as well as with the altitudeabove the ground. To evaluate the wind potential at a site, at least

    one year of wind data (speed and direcction) is required (two or

    more years are optimal at hub height of the WTG).

    The measured wind data (1-2 sec sampling) is filtered andaveraged (10-min averages) per wind direction sector.

    The measured wind data is than correlated to a long term data

    source of 5-10 years (e.g. close by metheorological station).

    Once the wind speed data is available, a wind speed distribution is

    calculated at hub height of the specified turbine. From the wind distribution curve, the WTG power curve, the wind

    farm layout + topography, the gross energy production over a

    period of time (usually a year) can be calculated.

    Wind Data and Energy Yield

  • 8/11/2019 Introduction to Wind Power Generation

    14/27

    Using industry software tools (e.g. WASP1), that account for

    topografy, surface roughness, etc., the gross energy yield of thewind farm is calculated.

    The net energy production is calculated after considering all

    elements affecting the energy production (losses, unavailability,

    etc.)

    Wind Data and Energy Yield (cont.)

    The wind speed distribution showsthe frequency (in hours or per unit-pu) of occurrence of the measured

    wind speeds. Combined with the

    power curve of the WTG, the gross

    energy production over a period oftime can be calculated.

    Note 1: WASP is a PC program for predicting wind climates, wind resources and power productions from wind turbines and wind farms.

    Frequency of occurrence

  • 8/11/2019 Introduction to Wind Power Generation

    15/27

    The P50 value corresponds to the annual expected (mean)

    net value calculated from the gross output of the measured

    data minus the losses.

    Main Losses: Range Typical

    - Wake effect (wind shade effect from other WTGs) 3% - 10% (7%)

    - Electrical losses (cables, grid, etc.) 2% - 4% (3%)

    - Non Availability of WTG1 2% - 4% (3%)

    - Non Availability of Grid & SS 1% - 4% (1%)

    - Icing and blade contamination 0.5% - 1% (1%)

    - Others (bird migration, local issues)

    - TOTAL 12% - 18% (14%)Note 1: For Offshore ~ 10%

    Note 2: In some calculations the topographic/roughness effect is included in the total losses increasing them up to ~25%-30%

    Energy Yield

  • 8/11/2019 Introduction to Wind Power Generation

    16/27

    Uncertainties for the calculation of higher probability of

    exceedance values (e.g. P75, P90) are assumedindependent and normal distributed around P50, for 1 year

    and 10 year energy yield periods.

    Main Uncertainties: Typical- Wind speed statistics 5% - 8%

    - Power curve performance 3% - 5%

    - Model (topography, wake effect) 2% - 3%

    - Metering 0.5% - 1%- Others (array losses, special issues)

    - TOTAL Standard Deviation (SD) 11% - 17%

    The main uncertainties result in a SD valueUsually the uncertainty (SD) is calculated for a 1year and a 10year period (SD1year>SD10year)

    Energy Yield (cont.)

  • 8/11/2019 Introduction to Wind Power Generation

    17/27

    Energy Yield (cont.) P50 best estimate 50% probability of exceedance

    Based on a normal distribution and a Standard Deviation (SD),the 75%, 90% or 95% probability of exceedance values can becalculated.

    The SD is calculated from the uncertainties of the data andP50 energy yield calculation.

    P75 = P50 - 0,675*SD P90 = P50 - 1,28*SD

    P95 = P50 - 1,64* SD

    Example: output calculated gross: 100 GWh

    Losses: 13% so P50 = 87 GWh Uncertainty SD calculated as 7.3% =6.35 GWh

    P75 = 87-4.3= 82.7 GWh

    P90 = 87- 8.1=78.9 GWh

    =>In the financial evaluation, the P9010year is often used as the base case with

    sensitivities ensuring that P901year (or P951year) still enables debt service.

  • 8/11/2019 Introduction to Wind Power Generation

    18/27

    Example of Energy YieldTurbine V90 3MW

    Hub Height (m) 105

    Rated Capacity (MW) 3Number of Turbines 52

    Site Capacity (MW) 156

    Hub Height Wind speed (m/s) 7.1

    Gross Wind Farm Energy Production (GWh/annum) 387.3

    Gross Plant Factor 28.3%

    Corrections and Losses

    Topographic/Roughness Effect 0.997

    Wake Losses 0.933

    Electrical Transmission Efficiency 0.980

    Substation Maintenance 0.998Grid downtime 0.990

    Turbine Availability 0.970

    Power Curve Performance 0.980

    Icing and blade degradation 0.995

    Wake from existing wind farms 0.998

    Bird Migration Effect 0.990

    Overall Conversion Efficiency 0.842

    P - Values

    Net P50 Wind Farm Yield (GWh/annum) 325.99

    Net P50 Plant Factor 23.9%

    Uncertainty over 1 year (incl . annual w ind speed variation)

    Standard error in result 17.60%

    P90 Energy Yield over 1 year (GWh/annum) 252.55

    P90 Plant Factor over 1 year 18.5%

    Uncertainty over 10 years (incl. annual wind speed variation)

    Standard error in result 12.00%

    P75 Energy Yield over 10 years (GWh/annum) 299.58

    P75 Plant Factor over 10 years 21.9%

    P90 Energy Yield over 10 years (GWh/annum) 275.92

    P90 Plant Factor over 10 years 20.2%

  • 8/11/2019 Introduction to Wind Power Generation

    19/27

    The final wind farm energy yield calculation can only be done

    once the micrositting has been completed.

    Micrositing is the process of optimally locating the individual WTGs

    in the available land spaces to maximize the wind farm energy

    production and minimize the wake and array losses1.

    Appropiate spacing between WTGs is essential to achieve balance

    between wake losses and construction costs (roads, electrical

    network)

    The adequate ditance will depend on the prevailing wind speed

    and direction distribution at the site (wind rose). A spacing of 5 9 rotor diameters is recommended in the

    prevailing wind direction.

    A spacing of 3 5 rotor diameters is recommended in the

    directions perpendicular to the prevailing wind direction.Note 1: Array losses originate from wind distortions created by close by located WTGs.

    Wind Farm Layout

  • 8/11/2019 Introduction to Wind Power Generation

    20/27

    Wind Farm Layout (cont.)

    Prevailing wind direction

    5-9 rotor diameters apart

    in the wind direction

    3-5 rotor diameters apart

    Source: Danish Wind Industry Association

  • 8/11/2019 Introduction to Wind Power Generation

    21/27

    In the construction and financing of a Wind Farm, several

    contractual arrangements and legal aspects play an important

    role:

    Land Agrements (Lease or Purchase)

    Turbine Supply Agreement (TSA) Engineering, Procurement and Construction (EPC) &

    Installation or Balance of Plant (BOP)

    Operation and Maintenance Agreement (O&M)

    Power Purchase Agreement (PPA) Grid Interconnection Agreement (GIA)

    Warranties and Guaranties, Insurance, etc.

    Contractual Arrangements

  • 8/11/2019 Introduction to Wind Power Generation

    22/27

    Vestas (DENMARK)

    GE Energy (USA)

    Gamesa (SPAIN)Enercon (GERMANY)

    Suzlon (INDIA)

    Siemens (GERMANY)

    Goldw ind (CHINA)

    Sinovel (CHINA)

    Nordex (GERMANY)

    Others

    2007 Market Share of Top 10 Global WTG

    Manufacturers

    Top 10 WTG Manufactures

    21%

    15%

    14%

    13%

    7%

    10%

    21%

    4%

    3%

    3%

    Source: BTM Consult Aps

  • 8/11/2019 Introduction to Wind Power Generation

    23/27

    Based on wind farms developed so far we can comment on

    some reference values for the main topics:

    Investment costs

    O&M costs

    Performance

    Schedule

    Benchmarking Values

  • 8/11/2019 Introduction to Wind Power Generation

    24/27

    Investment Costs

    Benchmarking Values

    Project WTG-Type WTG Total WTG

    MW MW # Total Inv $/kW /kW Hard Cost Soft Cost Non EPC

    $ million % CAPEXKavarna V90 - 3MW 3.0 156.0 52 378.0 2,423 1,731 84% 16% 4.6%(Bulgaria)Totoral V90 - 2MW 2.0 46.0 23 136.0 2,957 2,112 91% 9% 12.0%(Chile)

    Zorlu GE - 2.5MW 2.5 135.0 54 294.0 2,178 1,556 85% 15% 10.0%(Turkey)

    Samana E57 - 0.8MW 0.8 100.8 126 126 1,250 893 N/A N/A 10.0%Saundatti E57 - 0.8MW 0.8 82.4 103 106.0 1,286 919 N/A N/A 10.0%(India)

    Typical 2,000-3,000 1,400-2,200 80% 20% 10%-15%

    1U$ = 1.4 India 1,200-1,600 860 - 1,150

    3.6% Funded +

    Sponsor Support

    7% under PFA

    Funds

    2.8% Development Fee

    CAPEX

    5% Funded +

    Contingency

    Sponsor SupportSponsor Support

  • 8/11/2019 Introduction to Wind Power Generation

    25/27

    O&M Costs (per year)

    Benchmarking Values

    Project WTG-Type WTG Total WTG Total Inv

    MW MW # $ million Type of $/kW $/kWh $/WTG % CAPEX TotalO&M $/year

    Kavarna V90 - 3MW 3.0 156.0 52 378.0 WTG Suppl ier 44.4 2.11 133,135 1.83% 6,923,000(Bulgaria) Own (after 4y) 21.8 1.04 65,520 0.90% 3,407,040

    Totoral V90 - 2MW 2.0 46.0 23 136.0 WTG Suppl ier 43.0 1.80 86,000 1.45% 1,978,000(Chile) Own (after 3y) 33.5 1.40 66,990 1.13% 1,540,770

    Zorlu GE - 2.5MW 2.5 135.0 54 294.0 Own 37.4 1.25 93,411 1.72% 5,044,200(Turkey)

    Samana E57 - 0.8MW 0.8 100.8 126 126 WTG Suppl ier 14.1 0.57 11,288 1.13% 1,422,225Saundatti E57 - 0.8MW 0.8 82.4 103 106.0 WTG Suppl ier 14.1 0.62 11,288 1.10% 1,162,613(India)

    Typical WTG Suppl ier 42 - 46 1.7 - 2.4 80k - 130k 1.5% - 2.5%1U$ = 1.4 Own 20 - 37 1.0 - 1.4 40k - 90k 1.0% - 1.5%

    India 15 - 20 0.5 - 1.0 10k - 30k 1.0% - 1.5%

    O&M

  • 8/11/2019 Introduction to Wind Power Generation

    26/27

    Performance

    Benchmarking Values

    Project WTG-Type WTG Total WTG Total Inv Total Losses Availability Average P50 Energy

    MW MW # $ million % % P50 P90 Wind Speed per MW inst.

    m/s P50 P90 MWh/year

    Kavarna V90 - 3MW 3.0 156.0 52 378.0 15.8% 96.0% 23.9% 20.2% 7.10 326.6 276.0 2094(Bulgaria)

    Totoral V90 - 2MW 2.0 46.0 23 136.0 26.3% 95.0% 27.3% 21.0% 6.65 110.0 84.6 2391(Chile)Zorlu GE - 2.5MW 2.5 135.0 54 294.0 12.6% 95.0% 34.2% 28.1% 7.20 404.2 332.2 2994

    (Turkey)Samana E57 - 0.8MW 0.8 100.8 126 126 20.7% 96.0% 28.5% 22.5% 6.90 251.4 198.4 2492Saundatti E57 - 0.8MW 0.8 82.4 103 106.0 19.2% 96.0% 25.8% 18.7% 6.80 186.5 135.4 2262(India)

    1U$ = 1.4 Typical 12%-18% 95% - 97% 25%-35% 20%-25% 6.0 - 8.0

    * High value due to Topographic/Roughness effect (*) 15%-25%

    Plant Factor - pf Energy

    GWh/year

  • 8/11/2019 Introduction to Wind Power Generation

    27/27

    Project Schedule (*)

    Benchmarking Values

    (*) From Permitting to Commercial Op.

    (Resource Assessment & Site Selection

    could add 6 12 months to the process)

    Project WTG-Type WTG Total WTG Total InvMW MW # $ million

    Kavarna V90 - 3MW 3.0 156.0 52 378.0(Bulgaria)Totoral V90 - 2MW 2.0 46.0 23 136.0(Chile)Zorlu GE - 2.5MW 2.5 135.0 54 294.0(Turkey)

    Samana E57 - 0.8MW 0.8 100.8 126 126

    Saundatti E57 - 0.8MW 0.8 82.4 103 106.0(India)

    Typical1U$ = 1.4

    19 - 22

    23 - 25

    23 - 24

    (Months)

    19 - 22

    Total Project Schedule

    24 - 26

    26 - 27