Introduction to Veja Mate Offshore Project
NER 300 Information Event
15 December 2017, Brussels
Stefan Klett
Co-funded by the NER 300 programme
of the European Union
2
Agenda
Project Introduction
Challenges
Co-funded by the NER 300 programme
of the European Union
3
Key Facts - Overview
GERMANY
DENMARK
NETHERLANDS
BELGIUM
VMOP site
402 MW capacity − 67 x Siemens 6.0-154
~94 Km from shore
Water depth between 39 – 40 m
Average wind speed ~9.9 m/s
8 year FiT @194 EUR/MWh4.7 year add. FiT @154 EUR/MWh
WTG commissioning Jan’17-May’17
15 year service agreement
Co-funded by the NER 300 programme
of the European Union
4
Key Facts – Power Export
Veja Mate feeds in power through its own OSS to the BorWin Beta offshore AC/DC converter station, and then to Diele onshore converter station in Germany
Co-funded by the NER 300 programme
of the European Union
5
Key Facts – Packages EU footprint
GERMANY
DENMARK
NETHERLANDS
BELGIUM
VMOP site
WTGSupply – Siemens (Key contractor)Installation – Fred Olsen, Seajacks
FoundationsSupply – EEW, BladtInstallation – Boskalis (Key contractor),
Volker Stevin In
CablesSupply – JDRInstallation – SIEM (Key contractor)
OSSSupply – FICG (Key contractor)Installation – FICG
Long Term ServiceSiemens
6
Shareholders
Siemens Financial Services
Highland Group Holdings Limited
Co-funded by the NER 300 programme
of the European Union
7
Federal Maritime & Hydrographic Agency (BSH) Offshore Wind Farm Life-Cycle
3
5 1
24Operations
Phase 4• Operational
Release
Decommissioning
Phase 5• Decommissiong Release
BSH Standard7005
Development
Phases 1 & 2
Implementation
Phase 3• 1st Release
• 2nd Release
• 3rd Release
Project Timeline Life-Cycle
Co-funded by the NER 300 programme
of the European Union
8
Project Timeline
* Timeline not to scale
September 2014Highland Group acquires the Veja Mate Project
November 2014CIP (Copenhagen Infrastructure II) enters
negotiation with Highland Group
June 2015Financial Close, CIP and SFS become equity
investors in Veja Mate
April 2016Construction starts with FOU
monopile installation on schedule
June 2016FOU transition piece installation
starts on schedule
September 2016Offshore substation jacket and topside
manufactured, and installed on scheduleOctober 2016
Inter-array cable installation start
August 2016All monopiles installed
ahead of schedule
January 2017Wind turbine installation start
October 2016All transition pieces
installed
May 2017All wind turbines installed and
commissioned
January 2018Conversion date
November 2029FiT period ends
2H 2042Decommissioning
November 2016Veja Mate OSS energized
February 2017Cable laying and trenching
completed ahead of schedule
June 20151st release BSH
December 2017Req.4th release BSH
9
Project Organization
CFO
COO
Environmental PM
Deputy QA/QC Manager Financial Controller
Assist. Contract Manager
Finance Manager
RECQ
Contract Manager
EPC Deputy Director
Information Manager
Project Assistance
Office Manager
CEO
FOU PMWTG PM
WTG Deputy PM
IAC PM Installation PM
Installation Manager
Electrical PM
Electrical Deputy PM
Electrical Engineer
Student Worker
Electrical Engineer
OSS Assistant
Project Assistant
Project Assistance
OSS PM
Reg. & HR Manager
HSE PM
Electrical Engineer
Electrical Inst. Manager
O&M Site Manager
Operations Engineer
Commercial Ops. Mgr.
Tech. Project Manager
O&M PM
WTG Assistant
Planning/ Interface Mgt.
Student Worker Offshore Site Manager
O&M HSE Manager
Co-funded by the NER 300 programme
of the European Union
10
Agenda
Project Introduction
Challenges
Co-funded by the NER 300 programme
of the European Union
11
Challenge Project Timeline
* Timeline not to scale
September 2014Highland Group acquires the Veja Mate Project
November 2014CIP (Copenhagen Infrastructure II) enters
negotiation with Highland Group
June 2015Financial Close, CIP and SFS become equity
investors in Veja Mate
April 2016Construction starts with FOU
monopile installation on schedule
June 2016FOU transition piece installation
starts on schedule
September 2016Offshore substation jacket and topside
manufactured, and installed on scheduleOctober 2016
Inter-array cable installation start
August 2016All monopiles installed
ahead of schedule
January 2017Wind turbine installation start
October 2016All transition pieces
installed
May 2017All wind turbines installed and
commissioned
January 2018Conversion date
November 2029FiT period ends
2H 2042Decommissioning
November 2016Veja Mate OSS energized
February 2017Cable laying and trenching
completed ahead of schedule
June 20151st release BSH
December 2017Req.4th release BSH
12
Obstacles Overcome
UXO clearing provider changed mid-campaign due to underperformance
UXO clearing campaign
Co-funded by the NER 300 programme
of the European Union
13
Obstacles Overcome
Switched NMS providers mid-project due to an inability to meet legal noise limits
Noise mitigation system
performance issues