Introduction to the New Guilford High School State of the Schools May 15, 2013

Introduction to the New Guilford High School

Embed Size (px)

DESCRIPTION

Introduction to the New Guilford High School. State of the Schools May 15, 2013. Current Site & Existing School Structure. Tai Soo Kim Partners Architects. Illustration of Construction on Site. Tai Soo Kim Partners Architects. New Site Plan. New School. - PowerPoint PPT Presentation

Citation preview

Page 1: Introduction to the  New Guilford High School

Introduction to the New Guilford High School

State of the SchoolsMay 15, 2013

Page 2: Introduction to the  New Guilford High School

Current Site & Existing School Structure

Tai Soo Kim Partners Architects

Page 3: Introduction to the  New Guilford High School

Illustration of Construction on Site

Tai Soo Kim Partners Architects

Page 4: Introduction to the  New Guilford High School

New School

New Site Plan

Tai Soo Kim Partners Architects

Page 5: Introduction to the  New Guilford High School

West Entry – Parents & Visitors

Tai Soo Kim Partners Architects

Page 6: Introduction to the  New Guilford High School

Cafeteria/Commons - West Lobby

Tai Soo Kim Partners Architects

Page 7: Introduction to the  New Guilford High School

South Gallery

Tai Soo Kim Partners Architects

Page 8: Introduction to the  New Guilford High School

Dining Terrace / Outdoor Classroom

Tai Soo Kim Partners Architects

Page 9: Introduction to the  New Guilford High School

North Entry – Bus Loop

Tai Soo Kim Partners Architects

Page 10: Introduction to the  New Guilford High School

Bid Period: June – August 2013

Start Site Work : July & August

2013

Start New Building Construction: September

2013

Move into New Building: 2015

Remove Old Building: August – October

2015

Finish Site Work: April 2016

Construction Phase Schedule

Tai Soo Kim Partners Architects

Page 11: Introduction to the  New Guilford High School

Board of Education: Bill Bloss, ChairDr. Paul Freeman, Superintendent of Schools

Guilford HS Committee: Scott Pinckney, Chair

Architect: Tai Soo Kim Partners www.tskp.com

MEP Engineer: Kohler Ronan www.kohlerronan.com

Structural Engineer: Michael Horton & Assocs. www.mha-eng.com

Site / Civil Engineer: Milone & MacBroom www.miloneandmacbroom.com

Landscape Architect: Milone & MacBroom

www.miloneandmacbroom.comMikyoung Kim Design www.mikyoungkim.com

Construction Manager: Fusco Corporation www.fusco.comO&G Industries www.ogind.com

Design & Engineering Team