1 © 2008 Prentice Hall 8-1 Introduction to Project Management Chapter 8 Managing Project Quality Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George © 2008 Prentice Hall 8-2 Quality According to PMBOK, project quality is defined as “the degree to which a set of inherent characteristics fulfill requirements.” © 2008 Prentice Hall 8-3 Importance of Quality Determined by industry or tolerance for error Critical: health or safety related

Introduction to Project Management - UWI St. Augustine Proj... · Quality Within Project Management • Required in all stages – Initiation and closure • Goals and level of achievement

  • Upload
    vandang

  • View
    219

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Introduction to Project Management - UWI St. Augustine Proj... · Quality Within Project Management • Required in all stages – Initiation and closure • Goals and level of achievement

1

© 2008 Prentice Hall 8-1

Introduction to Project

Management

Chapter 8

Managing Project Quality

Information Systems Project Management: A Process and Team Approach, 1e

Fuller/Valacich/George

© 2008 Prentice Hall 8-2

Quality

• According to PMBOK, project quality is defined

as “the degree to which a set of inherent

characteristics fulfill requirements.”

© 2008 Prentice Hall 8-3

Importance of Quality

• Determined by industry or tolerance for error

• Critical: health or safety related

Page 2: Introduction to Project Management - UWI St. Augustine Proj... · Quality Within Project Management • Required in all stages – Initiation and closure • Goals and level of achievement

2

© 2008 Prentice Hall 8-4

Quality Within Project Management

• Required in all stages

– Initiation and closure

• Goals and level of achievement (lessons learned)

– Planning

• Determine ways to control quality

– Execution and control

• Feedback mechanisms to monitor and adjust

© 2008 Prentice Hall 8-5

Quality

• Can Be Applied To:

– The project team

• Sets performance expectations

– Processes

• Identifies ways to control quality

– Success level

• Allows team to determine the level of quality attainment

© 2008 Prentice Hall 8-6

Pioneers in Quality Management

• Deming

– 14 points of quality

• Juran

– Pareto Principle (80/20 rule)

• Crosby

– 4 absolutes of quality management

• Ishikawa

– Cause and effect diagram (Fishbone diagram)

Page 3: Introduction to Project Management - UWI St. Augustine Proj... · Quality Within Project Management • Required in all stages – Initiation and closure • Goals and level of achievement

3

© 2008 Prentice Hall 8-7

Crosby: Four Absolutes of

Quality Management

© 2008 Prentice Hall 8-8

Balanced Scorecard

• Developed by Kaplan & Norton

• 4 views of organizational activity

– Learning and Growth

– Business Process

– Customer

– Financial

© 2008 Prentice Hall 8-9

Quality Standards

• ISO9000 – Quality management focus

• Customer quality requirements

• Regulatory requirements

• Enhance customer satisfaction

• Continual improvement

– www.iso.org

• Six Sigma – To achieve Six Sigma, a process must not produce

more than 3.4 defects per million opportunities

– Champion, Master Black Belt, Black Belt, Green Belt proficiency designations

Page 4: Introduction to Project Management - UWI St. Augustine Proj... · Quality Within Project Management • Required in all stages – Initiation and closure • Goals and level of achievement

4

© 2008 Prentice Hall 8-10

Certificates/Awards• Baldridge National Quality Program

– Designed to encourage organizations increase their

competitiveness by focusing on:

• Delivering ever improving value to customers

• Improving overall organizational performance

– http://www.quality.nist.gov/

• Total Quality Management (TQM)

– A description of the culture, attitude, and organization

of a company that strives to provide customers with

products and services that satisfy their needs

– Emphasizes processes being done right the first time

and defects and waste eradicated from operations

© 2008 Prentice Hall 8-11

IS/IT Quality

• Where do you focus?

• How do you measure?

• What is the return on investment?

© 2008 Prentice Hall 8-12

Quality Planning

• Quality planning

– The process of identifying relevant quality standards

and developing a plan to ensure the project meets

those standards

Page 5: Introduction to Project Management - UWI St. Augustine Proj... · Quality Within Project Management • Required in all stages – Initiation and closure • Goals and level of achievement

5

© 2008 Prentice Hall 8-13

PMBOKProject Quality Management Inputs, Tools,

and Outputs

© 2008 Prentice Hall 8-14

PMBOK Required Inputs, Tools and Techniques

Used, and Resulting Outputs During Quality

Planning

© 2008 Prentice Hall 8-15

Quality Planning – Inputs

• Enterprise factors

– Government regulations

– Standards or rules specific to organization’s product

or service

• Organizational process assets

– Quality policies/procedures/guidelines

– Lessons learned

• Project scope statement

• Project management plan

Page 6: Introduction to Project Management - UWI St. Augustine Proj... · Quality Within Project Management • Required in all stages – Initiation and closure • Goals and level of achievement

6

© 2008 Prentice Hall 8-16

Quality Planning – Techniques

• Cost/benefit analysis

– An evaluation of the costs and benefits of alternative

approaches to a proposed activity to determine the

best alternative

• Benchmarking

– Study of a competitor’s product or business practices

in order to improve the performance of one’s own

company

• Capability Maturity Model (CMM)

– Used to determine an organization’s capability with

respect to best practices within a specific industry

© 2008 Prentice Hall 8-17

Capability Maturity Model

Quality Planning – Techniques (cont.)

© 2008 Prentice Hall 8-18

Quality Planning – Techniques (cont.)

• Design of experiments

– Application of selected statistical techniques to test

the efficiency of certain project management

approaches by testing factors that may influence a

specific variable

– http://www.isixsigma.com/library/content/c030106a.as

p

Page 7: Introduction to Project Management - UWI St. Augustine Proj... · Quality Within Project Management • Required in all stages – Initiation and closure • Goals and level of achievement

7

© 2008 Prentice Hall 8-19

• Cost of quality analysis (COQ)

– Cost to improve or ensure quality measures, as well

as the cost associated with a lack of quality

– http://www.isixsigma.com/dictionary/Cost_Of_Quality-

497.htm

Quality Planning – Techniques (cont.)

© 2008 Prentice Hall 8-20

Types of Quality Costs

Types of Cost Examples

Cost of conformance

Prevention costs Costs of training staff in design methodologies

Appraisal costs Code inspection and testing

Cost of non-conformance

Internal failure costs Costs of rework in programming

External failure costs Costs of support and maintenance

© 2008 Prentice Hall 8-21

Reducing Software Quality Costs

• Avoiding any failure costs by driving defects to

zero

• Investing in prevention activities to improve

quality

• Reducing appraisal costs as quality improves

• Continuously evaluating and altering preventive

efforts for more improvement

Page 8: Introduction to Project Management - UWI St. Augustine Proj... · Quality Within Project Management • Required in all stages – Initiation and closure • Goals and level of achievement

8

© 2008 Prentice Hall 8-22

Quality Planning – Outputs

• Quality management plan

– A plan specifying how quality measures will be

implemented during a project

• Quality metrics

– Operational definitions of specific, processes, events,

or products, as well as an explanation of how they will

be measured in terms of quality

• Quality checklists

– Tools used to ensure that a specific set of actions has

been correctly performed

© 2008 Prentice Hall 8-23

Quality Planning – Outputs (cont.)

• Process improvement plan

– A plan specifying how to identify wasteful and non-

value added activities

• Quality baseline

– The basis for which project quality is measured and

reported

• Updates to project management plan

– Incorporation of quality management plan outputs into

project management plan

© 2008 Prentice Hall 8-24

Quality Assurance

• The process of ensuring that the project meets

the quality standards outlined during the quality

planning phase

Page 9: Introduction to Project Management - UWI St. Augustine Proj... · Quality Within Project Management • Required in all stages – Initiation and closure • Goals and level of achievement

9

© 2008 Prentice Hall 8-25

PMBOK Required Inputs, Tools and Techniques

Used, and Resulting Outputs

During Quality Assurance

© 2008 Prentice Hall 8-26

Quality Assurance – Inputs

• Quality management plan

• Quality metrics

• Process improvement plans

• Work performance information

• Approved change requests

• Quality control measures

• Implemented – change requests

– corrective actions

– defect repairs

– preventive actions

© 2008 Prentice Hall 8-27

Quality Assurance –

Tools & Techniques

• Quality planning tools and techniques can be

applied

• Quality audits

– Structured and independent review activities

designed to review other quality management

procedures and to identify potential lessons learned

• Process analysis

– Examines how a process is performed

Page 10: Introduction to Project Management - UWI St. Augustine Proj... · Quality Within Project Management • Required in all stages – Initiation and closure • Goals and level of achievement

10

© 2008 Prentice Hall 8-28

Quality Assurance – Outputs

• Requested changes

• Recommended corrective actions

• Updates to organizational process assets

• Updates to the project management plan

© 2008 Prentice Hall 8-29

Quality Control

• The monitoring of project activities in order to

determine if specified quality standards are

being met

© 2008 Prentice Hall 8-30

PMBOK Required Inputs, Tools and Techniques

Used, and Resulting Outputs During Quality

Control

Page 11: Introduction to Project Management - UWI St. Augustine Proj... · Quality Within Project Management • Required in all stages – Initiation and closure • Goals and level of achievement

11

© 2008 Prentice Hall 8-31

Quality Control – Inputs

• Quality management plan

• Quality metrics

• Quality checklists

• Organizational process assets

• Work performance information

• Approved change requests

• Deliverables

© 2008 Prentice Hall 8-32

Work Performance Information

• Status summaries of:

– Project deliverables

– Any collected performance measures

– Implemented changes from the original project

management plan

© 2008 Prentice Hall 8-33

Quality Control –

Tools & Techniques• Cause and effect diagrams (Ishikawa)

• Control charts

• Pareto charts

• Flowcharts

• Histogram

• Run chart

• Scatter diagram

• Statistical sampling

• Inspection review

• Defect repair review

Page 12: Introduction to Project Management - UWI St. Augustine Proj... · Quality Within Project Management • Required in all stages – Initiation and closure • Goals and level of achievement

12

© 2008 Prentice Hall 8-34

Ishikawa (fishbone) Diagram

Sample

© 2008 Prentice Hall 8-35

Control Chart Sample

© 2008 Prentice Hall 8-36

Pareto Chart

Page 13: Introduction to Project Management - UWI St. Augustine Proj... · Quality Within Project Management • Required in all stages – Initiation and closure • Goals and level of achievement

13

© 2008 Prentice Hall 8-37

Quality Control – Outputs

• Quality control measurements

• Validated defect repair

• Updates to the quality baseline

• Recommended correction actions

• Recommended preventative actions

• Requested changes

• Recommended defect repair

• Updates to organizational process assets

• Validated deliverables

• Updates to project management plan

© 2008 Prentice Hall 8-38

Questions?