Introduction to Offshore Petroleum Production System

  • Upload
    joaocos

  • View
    44

  • Download
    2

Embed Size (px)

DESCRIPTION

Introduction to Offshore Petroleum Production System

Citation preview

  • : Introduction to Offshore Petroleum Production System

    Feb. 7, 2012 Yutaek Seo

  • Course Syllabus

    Outcome : To develop broad understanding of fluid properties that determine

    the design parameters : To describe in detail a number of different system in terms of

    advantages and drawbacks of each facility.

    Assessment Attendance (10%) Continuous assessment Assignments (30%) Term project Modeling with provided software (30%) Examination- End-of-Semester examination (30%) Recommended reading Primary Subsea Engineering Handbook Secondary Fields data, Design notes, Reports, etc.

  • Period Contents

    1 Week General introduction, outline, goals, and definition

    2 Week Type of reservoir fluids : Dry gas / Wet gas / Gas condensate / Volatile oil / Black oil

    3 Week PVT laboratory testing : Constant mass expansion / Differential vaporization / Compositional analysis / : Oil densities and viscosity / SARA, Asphaltenes, WAT

    4 Week Fluid sampling : Bottom hole samples / Drill stem test samples

    5 Week Thermodynamics and phase behavior : Ideal gas / Peng-Robinson (PR) / Soave-Redlich-Kwong (SRK) : Peneloux liquid density correction / Mixtures / Properties calculated from EoS + molecular data

    6 Week Piping systems and process pressure vessels : System design / construction

    7 Week Production : Gas production / Oil production / Enhanced oil recovery

    8 Week The well components : Christmas tree / surface wellhead

    9 Week Subsea structures : Subsea control systems / umbilical / flowlines

    10 Week Flow regime : Horizontal and vertical flow / Stratified flow / Annular flow / Dispersed bubble flow / Slug flow

    11 Week Flowline pressure drop : Frictional losses / Elevation losses / Acceleration losses / Errors in P calculation / Pipe wall roughness

    12 Week Liquid hold up : Cause / Prediction / Field & experimental data / Three phase flow

    13 Week Field operation : Operational procedures for offshore petroleum production

    14 Week Application Example: Offshore platform (Pluto fields)

    15 Week Application Example: Floating production system (Ichthys fields)

    16 Week Final Test

  • Energy Market Status

  • Global LNG market

    LNG production was 210 million tone in 2010 and will grow moderately Two major issues Shale gas and Fukushima disaster Asian LNG demand will grow to 190 million tone in 2020, Fukushima

    disaster may result in 9 to 18 mtpa of additional LNG demand by 2020 - The choice of Japan makes in generating electricity will result in differences of

    5 mtpa for future LNG demand - Chinese gas supply to 2030 will be composed of several different options:

    Conventional (22 bcf/d), Shale gas (1.5 bcf/day), Pipeline (12 bcf/d), LNG (50 million ton)

    Australian LNG production capacity is set to increase from 19.5 mpta in 2010 to 38.8 mtpa from 2014.

    4.3 mtpa

    15 mtpa

  • Offshore system growth

  • WA Offshore Gas Fields

    CSIRO.

    Prelude, Ichthys, Browse

    Pluto, Gorgon, Wheatstone

    From Petroleum in Western Australia, April 2011

  • North West Shelf

  • Timor Sea

  • Status of Offshore Market

  • The Offshore Production System

  • Field Development The Building Blocks

    Reservoir Considerations

    Hydrocarbon Production Processing

    Subsea Production Options

    Health, Safety, and Environment

  • Reservoir Considerations

    Reservoir fluids have a huge number of components

    Their phase behaviour is complex compared to single components Instead of a single curve separating liquid from vapour phase, there is a

    broad region where both vapour and liquid exist together The tow-phase region is bounded on one side by the dew point curve and

    on the other side by the bubble point curve PVT analysis and fluid sampling will provide key information for system

    design basis

    Fluid Type C1 mole% API gravity Character Black oil < 60 30-45 Majority of subsea oil reservoirs

    Volatile oil 60 -70 45-70 2-phase region; high gas content Gas

    condensate 70 80 70-100 Gas at reservoir conditions.

    Retrograde behaviour yields light oil Dry gas 90 -100 NA Low MW hydrocarbon mixture

  • PVT laboratory testing - Phase behavior as a function

    of T & P - Composition - Physical properties: viscosity

    & density - Solid analysis: hydrate, wax,

    Asphaltenes, scale

    Fluid sampling

    - Obtaining a representative sample from a deepwater reservoir is the basis for characterization of reservoir fluids; and a big challenge.

    - Downhole fluid sampling - Drill stem test

  • Fluid Phase Behaviour

    Gas-condensate system

  • Thermodynamics Equation of State (EoS)

    Ideal gas law

    - Molecules have zero volume - No attraction between molecules Soave-Redlich-Kwong (SRK) Peng-Robinson (PR)

    VRTP =

    )()(bVV

    TabV

    RTP+

    =

    )()()(

    bVbbVVTa

    bVRTP

    ++

    =

  • Hydrocarbon Production Processing

    Separation & Conditioning Facilities - Land based - Platform based - Floating

    Production Flowlines

    Riser Rigid or Flexible

    Chemicals Distribution

    Comingled Flow Manifold

    Separation

    Oil & Gas

    Water

    100m ~ 100km

  • Subsea Production Options

  • Subsea Production Options

    Subsea well

    Wellhead

    Single Cluster

    Flowline Modular Template

    Production Manifold

    Interfield Gathering Line Multiphase PumpsSingle Phase Pumps

    Pipelines & Manifolds

    Riser Flexible Riser Fixed/Rigid

    Process FacilityProcess Facility

    Floating StorageExport Shuttle Tanker

    Sales Terminal

    Export Storage

    Bottom Founded Options

    Floating Options

    Subsea Separation

  • Typical Field Layout

  • This is what we are dealing with!!

    Norsk Hydro - Ormen Lange Two manifolds (natural gas: 700~2500 million ft3/day)

  • Primary elements

    Trees and Wellheads Manifolds Flowlines and Risers Control systems Umbilicals Topside facilities

    - Master control station with operator interface - Electrical power unit for power conditioning & monitoring - Hydraulic power unit for pressure generation, fluid storage - Topside umbilical junction boxes - Chemical injection skid

    Construction vessels Divers and ROVs Intervention systems

  • Onshore vs Offshore trees

    Onshore Trees..

    Offshore Trees.. can you see??

  • Xmas Tree

    Primary production and safety device for a well Essentially consists of a number of valves to regulate flow and

    isolate the tree from the well, and monitor the production fluids

  • A template is a seabed founded structure that provides a guide for other equipment

    A manifold is a system of piping and associated equipment used to gather produced fluids. Associated equipments may include

    : Isolation valves : Flowline connectors : Xmas tree connectors : Flow control chokes : Umbilical termination and distribution

    Manifold/Template

    Manifold/Template for Ormen Lange

  • PLEM/PLET

    PLEM (Pipeline End Manifold) : Used to comingle 2 or more pipelines together and eliminate

    the need for additional risers PLET (Pipeline End Termination) : Used to link manifold to the production pipeline

  • Flowline

    Transport reservoir fluid to processing facilities Pipelines : horizontal transfer from wellhead : these may be very long : may be rigid or flexible pipe : commonly called flowlines

  • Riser

    Vertical transfer to above surface processing facilities Either Rigid or Flexible Rigid risers normally for fixed platforms : pre-installed inside jacket frame : cost effective and added riser protection Flexible risers mainly for floating production system : Flexibility and reliability : Easy and rapid installation

  • Multiphase flow

    Multiphase flow patterns depend on the gas and liquid properties and velocities and the angle of inclination of the flowline

    There are four basic flow regimes:

  • Under most pipe flow conditions, the liquid moves more slowly than the gas because it is more dense and viscous.

    Both phases would move through the pipe at the same velocity if there were no slip between the gas and liquid.

    Liquid holdup is the volume fraction of the pipe that is liquid. Because of slip, this fraction is generally higher than the fraction of liquid entering the pipe.

    The flowline pressure gradient consists of three elements: - Friction - Elevation changes (can be + or-) - Fluid acceleration (can be + or -)

  • Operating production system

    Its a lot easier to picture what is happening in onshore system But, understanding what is happening in offshore system

    requires experience and inferences Challenges : Hydrates : Corrosion : Wax : Asphaltenes : Scale : Sand (erosion, deposition etc.) : Other issues e.g. emulsion, heavy oil..

  • Typical subsea developments

    Crude oil subsea tieback Crude oil field Wells tied back to existing

    platform 10km away Water depth 150m 20,000 bbl/d 2 * 6 flowlines Water injection required into

    reservoir Fluid composition : Gas Oil Ratio 1000scf/bbl : water cut 20% : Temperature 35~70 oC : Pressure 30~80 bar : Rates 7000~20000 bbl/d

    Gas tieback to LNG plant Gas condensate field Wells tied back to an LNG plant

    150km away Water depth 1200m 1000 MMscfd 10~30 flowline Continuous MEG or MeOH

    injection required at subsea chokes Fluid composition : Condensate gas ratio 5bbl/MMscf : Water gas ratio 1bbl/MMscf : Temperature 3~130 oC : Pressure 75~300 bar : Rates 500~1000 MMscfd

  • Operation challenges

    Crude oil subsea tieback Steady-state operation : System operated at capacity : Wellhead chokes fully open Shutdown : Followed by flowline depressurization : Keep fluid hot to avoid wax & hydrate Restart : Hot oil circulation is required to warm

    enough flowline to prevent hydrates Pigging : may require routine pigging if wax

    deposition is an issue

    Gas tieback to LNG plant Steady-state operation : Gas offtake at required rate : Subsea choking to maintain pressure Shutdown : Followed by MEG injection, but

    maintain pressure and flowline content Restart : May be accompanied by very low

    temperature downstream of choke Pigging : Hopefully is not a routine procedure : Rigorous modelling to control speed

  • Chemical injection

    Crude oil subsea tieback Scale, wax, & corrosion inhibitors may

    require continuous injection Monitoring of chemical injection

    system performance is important both for effectiveness of chemical treatment and cost management

    Introduction of new chemical products should only follow lab testing to verify compatibility

    Gas tieback to LNG plant Continuous MEG injection can result

    in a large complex processing system that may induce operation troubles

    MEG needs to be regenerated and reclaimed to remove salts

  • Case Studies

  • Woodside Pluto project 100% Woodside-owned gas field Discovered in early 2005 at North West Shelf (NWS) area 190km from the Burrup Peninsula Water depth ranging from 400 to 1000m Potential resource 4.1 trillion ft3 gas and small amount of condensate (42mmbl) Potential revenue boost by AUD 5.5 billion and Job creation of more than 4500

  • Criteria Key characteristics

    Hydrocarbon resource size Approximately 116 000 Mm3 (4.1tcf) recoverable dry gas Approximately 6.7Mm3 (42mmbbl) recoverable condensate

    Proposed number of wells Up to 7 wells in 2008 Up to 12 wells in total

    Subsea infrastructure Two manifolds with dual flowlines, 32km

    Offshore platform Unmanned riser platform located in 80~85m water depth

    Offshore gas trunkline A 762~1068 mm (30~42) carbon steel trunkline A 188km length offshore trunkline from platform through Mermaid Sound.

    Onshore gas trunkline Trunkline from landfall to processing plant at Burrurp Peninsula

    Onshore gas processing plant Up to 12 Mtpa

    Gas storage and export facilities

    2 * 160 000m3 LNG cryogenic tanks 2-3 condensate tanks with a combined capacity of up to 130000m3

    First gas End 2010

    Design life Up to 30 years

    Woodside Pluto project (contd)

  • Development concept - Subsea wells tied back, Gas and condensate export pipeline - Onshore LNG gas treatment plant, LNG, LPG and condensate storage tanks - Turning basin and shipping channel, Export jetty - Operational for 20-30 years

    Woodside Pluto project (contd)

    Gas and condensate to an onshore LNG plant via 35

    export line

    Onshore LNG plant (4.8 million ton per year)

    Subsea wells tied back to an offshore platform via

    2*18 flowline

  • Remote Production System

    Avoid!! 120km long tie-back 2700~2900 m

    water depth

  • Emerging issues

  • Four major changes

    1993 Deepwater = 600 m : 3 companies, few wells Hydrate/Wax apprehension Problem magnitude unknown : Wax or Hydrate ? : Time scale unknown Only steady state simulation : Transient was uncertain

    2003 Deepwater > 2000 m : Many companies & wells Hydrate/Wax avoidance Problem identified : Hydrate > Wax > Napthenates : Hydrate (min/hr) vs Wax (wks/mths) Steady state & Transient simulation

  • Flowline/Riser/Service line Design

    Reservoir fluid characteristics dominate design : Pressure drop and cooling causes separation - multiphase regime causes irregular flow and vibration - slugging occurs as velocity decays : Hydrate may form as P and T changes : Waxes may precipitate on cooling : Corrosion may occur as water condenses : Sand may cause plugging : Pigging may be required Emergence of Flow Assurance as an Engineering discipline

  • Flow Assurance

  • Subsea Design Phases

    1. Concept Selection/Feasibility Compare various flowline routes Pipe size and insulation requirements Topsides requirements

    2. FEED Determine most viable flowline route & flowline design Chemicals requirements & umbilical design Operability & topsides requirements

    3. Detailed Design Flowline design meets life time functional requirements Chemicals requirements & umbilical design Operability and topsides design for production & export

    4. Operations Operator training Adjust operating procedures according to reality

  • Fluid Related Issues

    Emulsion / Foam Wax / Asphaltenes

    Scale (salts) Corrosion Gas Hydrates Sand / Erosion

    Multiphase composition

    0

    50

    100

    150

    200

    0 100 200 300

    Multiphase region

    Hyd

    rate

    s

    Pre

    ssu

    re

    Temperature

  • Design Related Issues

    Choke design to minimize pressure loss and erosion

    Pipeline sizing pressure loss vs slugging

    Design of Chemical Injection Systems to minimize risk of hydrates, scale, corrosion etc.

    Thermal Insulation Design to keep fluids warm and minimize risk of hydrates and wax

    Erosion analysis Erosion wear in complex geometries

    Flow assurance is to take precautions to Ensure Deliverability and Operability

  • Flow Assurance : Interface with Reservoir Evaluation and Topsides Design

    Production profiles; FWHP, FWHT, WI rates Reservoir depth, temperature, and pressure Required topside arrival pressure (separator pressure + ~50

    psi) and temperature Separator and slug catcher capacities Capacities and pressure ratings of : Export pumps and compressors : Gas lift compressors : Chemicals pumps : Hydraulic fluid pumps

    Topside piping/equipment temperature ratings Topside storage capacities for oil, diesel, chemicals and water

  • Determine Line Size

    Most offshore pipelines are sized by use of three design criteria : Available pressure drop, allowable velocities, and slugging Line sizes calculated by use of the steady state simulators The maximum allowable pressure drop is constrained by its

    required outlet pressure and available inlet pressure

    Wellbore production: oil 10,000 bpd FWHP = 2900 psi

    Required arrival pressure = 500 psi

  • Key Flow Assurance issues - Hydrate

    Hydrate : An ice-like solid that forms when i) Sufficient water is present ii)Hydrate former is present (i.e. C1, C2, and C3) iii)Right combination of Pressure and Temperature

    Control strategy : maintaining temperature above hydrate formation conditions, by e.g. utilizing DEH : Decreasing the pressure outside the area of possible hydrate formation : Chemical addition or removing the water : Continuous injection of MEG is state of the art for hydrate inhibition of long distance subsea to beach gas-condensate field developments

    CSIRO.

  • Key Flow Assurance Issues - Wax

    Wax : A solid paraffinic hydrocarbon which precipitate from a produced fluid : Forms when the fluid temperature drops below the Wax Appearance

    Temperature (WAT) : Melts at elevated temperature (20oF above the WAT)

    Control strategy : Rate of deposition can be predicted to calculate pigging frequency : Flowline insulation : Wax inhibitor : Major factors - WAT - Fluid temperature - Flowline U-value - n-paraffin content

    CSIRO.

    Wax deposition

  • Key Flow Assurance Issues - Slugging

    Slugging : Periods of low flow followed by periods of high flow (liquid bomb) : Occurs in multiphase flowlines at low gas velocities : Causes - Low fluid velocity - Seabed bathymetry - Riser type

    Control strategy : Increase flowrate (playing with topside valve) : Slug catcher : Gas lift / Gas recirculation

    CSIRO.

  • Key Flow Assurance Issues - Corrosion

    Corrosion : Metal loss caused be corrosive water : Fe = Fe++ + 2e- : Variables - Material - H2S and CO2 level in fluids - Water composition

    Control strategy : Alter chemical environment - Oxygen scavengers - Sulfide scavengers : Alter reactive surface of metal - Corrosion inhibitors - Polymeric liners to flowlines

  • Key Flow Assurance issues

    Asphaltenes : The heavy polar aromatic fraction : Resulting blockage and formation damage : The main causes are - A decrease in the system pressure - Mixing of incompatible crude oils : Require asphaltene inhibitor injection

    Scales : The carbonates or sulphates of calcium, strontium and barium : FeCaCO3, CaCO3 scaling issues in the MEG system : Require scale inhibitor injection

    CSIRO.

    After de-scaling in separator

  • Thank you

    Contact: Yutaek Seo Phone: 042 350 1521 Email: [email protected]

    : Introduction to Offshore Petroleum Production SystemCourse Syllabus 3Energy Market StatusGlobal LNG marketOffshore system growth 7WA Offshore Gas FieldsNorth West ShelfTimor SeaStatus of Offshore MarketThe Offshore Production SystemField Development The Building BlocksReservoir Considerations 15Fluid Phase BehaviourThermodynamics Equation of State (EoS)Hydrocarbon Production ProcessingSubsea Production OptionsSubsea Production OptionsTypical Field LayoutThis is what we are dealing with!!Primary elementsOnshore vs Offshore treesXmas TreeManifold/TemplatePLEM/PLETFlowlineRiserMultiphase flow 31Operating production systemTypical subsea developmentsOperation challengesChemical injectionCase StudiesWoodside Pluto projectWoodside Pluto project (contd)Woodside Pluto project (contd)Remote Production SystemEmerging issuesFour major changesFlowline/Riser/Service line DesignFlow AssuranceSubsea Design PhasesFluid Related IssuesDesign Related IssuesFlow Assurance: Interface with Reservoir Evaluation and Topsides Design Determine Line SizeKey Flow Assurance issues - HydrateKey Flow Assurance Issues - WaxKey Flow Assurance Issues - SluggingKey Flow Assurance Issues - CorrosionKey Flow Assurance issues Thank you