Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
Estimation and Costing and 15CE53T 2020-21
Dept. Of Civil Engineering, GPT Raichur(117) 1
UNIT – 01
INTRODUCTION TO ESTIMATION
1.0 Introduction
An estimate is the anticipated or probable cost of work and is usually prepared before
the construction is taken up. It is indeed calculations or computations of various items
of an engineering work.
1.1 The following requirements are necessary for preparing an
estimate:
Drawings.
Detailed specifications
Standard schedule of rates of the current year
1. Drawings: Drawings like plan, elevation and sections of important points, (If the
drawings are not clear and without complete dimensions it becomes difficult to
estimate)
2. Specifications: Detailed specifications about workmanship& properties of materials
etc. There are two types of specifications:
a) General specification
b) Detailed specification.
a)General Specifications: This gives the nature, quality, class and work and materials
in general terms to be used in various parts of wok.
b) Detailed Specifications: These gives the detailed description of the various items of
work laying down the Quantities and qualities of materials, their proportions, the
method of preparation workmanship and execution of work.
3. Standard schedule of rates of the current year: For preparing the estimate the unit
rates of each item of work are required.
1. For arriving at the unit rates of each item.
2. The rates of various materials to be used in the construction.
3. The cost of transport materials.
4. The wages of labour, skilled or unskilled of masons, carpenters, Mazdoor, etc.
Estimation and Costing and 15CE53T 2020-21
Dept. Of Civil Engineering, GPT Raichur(117) 2
1.2 WHAT ARE THE PURPOSES OF ESTIMATION?
It gives an idea of the cost of the work, i.e whether the project could be taken or
not.
To get administration approvals in case of govt projects
It gives an idea of time required for the completion of the work.
It is required to invite the tenders and Quotations and to arrange contract
It is also required to control the expenditure during the execution of work.
Estimate decides whether the proposed plan matches the funds available or not.
1.3 WHAT IS COMPLETE ESTIMATION?
Most of people think that the estimate of a structure includes cost of land, cost of
materials and labour, but many other direct and indirect costs included ….
Estimation and Costing and 15CE53T 2020-21
Dept. Of Civil Engineering, GPT Raichur(117) 3
1.4 WHAT ARE THE TYPES OF ESTIMATES?
Preliminary Estimate / Approximate/ Rough estimate
Plinth Area estimate
Cube rate estimate
Approximate quantity method estimate
Detailed estimate / Item rate estimate
Revised estimate
Supplementary estimate
Supplementary & revised estimate
Annual repair and maintenance estimate.
Preliminary Estimate / Approximate/ Rough estimate:
Preliminary estimate is made at the very beginning of a project when there is limited
information available ( means there is no drawing and specification not available), it
is prepared with reference to the cost of similar projects.
Plinth Area Estimate:
In this method plinth area should be calculated by taking the external dimensions of
the building at the plinth level. Other open places shouldn’t be counted (
ex:courtyard), thus plinth area is multiplied by plinth area rate to get the approximate
amount.
Plinth area estimate = plinth area X rate
= (floor area + wall area) X rate
Fig: 01
Estimation and Costing and 15CE53T 2020-21
Dept. Of Civil Engineering, GPT Raichur(117) 4
Cube Rate Estimate: Cube Rate Estimate of a building is obtained by
multiplying plinth area with the height of building. Height of building should be
considered from floor level to the top of the roof level.
Thus cubical content of the building ( LXBXD) is multiplied by Cubical rate
Cube rate estimate = cubical content X Rate
= ( L X B X D) X Rate
Fig: 02
Approximate quantity method estimate: In this method Approximate total
length of walls is found in running meter and total length is multiplied by rate per
running meter.
For this method drawing should be available.
Approximate quantity method estimate = Total length of the wall X Rate per meter
Detailed Estimate:
The preparation of detailed estimate consists of working out quantities of various
items of work and then determines the cost of each item. This is prepared in two
stages.
I) Details Of Measurements And Calculation Of Quantities:
The complete work is divided into various items of work such as earth work
concreting, brick work, R.C.C. Plastering etc., The details of measurements are taken
from drawings and entered in respective columns of prescribed preformed. The
Estimation and Costing and 15CE53T 2020-21
Dept. Of Civil Engineering, GPT Raichur(117) 5
quantities are calculated by multiplying the values that are in numbers column to
Depth column as shown below:
II) Abstract of Estimated Cost:
The cost of each item of work is worked out from the quantities that already
computed in the details measurement form at workable rate. But the total cost is
worked out in the prescribed form is known as abstract of estimated form. 3 % to 5%
is added for contingencies ( unforeseen expenditures)
1.5 % to 3% for work charged establishment .
The detailed estimate should accompanied with:
I) Report
ii) Specification
iii) Drawings (plans, elevation, sections)
iv) Design charts and calculations
v)Standard schedule of rates.
Revised Estimate:
It is done under any one of the following circumstances:
When the original estimate exceeds or likely to exceed by more than 5%.
In case where there is a structural alterations
When the sanctioned amount is more than the actual requirement.
Supplementary estimate:
This is required due to material deviation of a structural nature from the design
originally approved.
This is an estimate for additional works only. The abstract shows the original
estimate and total amount of the sanction required including supplementary
amount.
Estimation and Costing and 15CE53T 2020-21
Dept. Of Civil Engineering, GPT Raichur(117) 6
Supplementary estimate is required due to some new works or due to change of
design, so additions or revisions of drawings may be necessary.
Supplementary And Revised Estimate: It is prepared when the volume of
the work increased as well as additional works are incurred in the project. In such
cases additional works estimation being done and there is a need of revision of
originally sanctioned amount.
Annual repair and maintenance estimate:
It is prepared to maintain the structure or work in safe condition, it includes repair
works of buildings, Roads, Bridges and culverts.
1.5 Units of measurements for different items of works:
The units of measurements are mainly categorized for their nature, shape and size and
for making payments to the contractor and also. The principle of units of
measurements normally consists the following:
Single units work like doors, windows, trusses etc., is expressed in numbers.
Works consists linear measurements involve length like cornice, fencing, hand
rail, bands of specified width etc., are expressed in running metres (RM)
Works consists areal surface measurements involve area like plastering, white
washing, partitions of specified thickness etc., are expressed in square meters (m2)
Works consists cubical contents which involve volume like earth work, cement
concrete, Masonry etc are expressed in Cubic metres
Estimation and Costing and 15CE53T 2020-21
Dept. Of Civil Engineering, GPT Raichur(117) 10
1.6 Deduction of openings in different items of work and
measurement as per BIS-2000
Plastering
Plaster work shall be classified according to the material used and each classification
shall be measured separately.
Rules for measurements:
Plastering on roofs, ceilings and walls shall be measured separately.
Removing plaster by scraping or otherwise shall be measured separately in square
metres.
Plastering at a height greater than 10 m above ground/datum level shall be
measured separately in stages of 5-m height except interior plastering in case of
building which shall be measured separately for each storey.
All plastering shall be measured in square metres unless otherwise described.
Rules for Deduction:
For jambs, soffits, sills, etc; for openings not exceeding 0.5 m2 each in area, for ends
of joists, beams, posts, girders, steps, etc, not exceeding 0.5 m2 each in area, and for
openings exceeding 0.5 m2 and not exceeding 3 m2 in each area, deductions and
additions shall be made in the following manner:
No deduction shall be made for ends of joists, beams, posts, etc, and openings not
exceeding 0.5 m2 each and no addition shall be made for reveals, jambs, soffits,
sills, etc, of these openings nor for finish to plaster around ends of joists, beams,
posts, etc.
Deductions for openings exceeding 0.5 m2 but not exceeding 3 m2 each shall be
made as follows and no addition shall be made for reveals,jambs, soffits, sills, etc,
of these openings:
1)When both faces of wall are plastered with same plaster, deduction shall be made
for one face only.
Estimation and Costing and 15CE53T 2020-21
Dept. Of Civil Engineering, GPT Raichur(117) 11
2)When two faces of wall are plastered with different types of plaster or if one face is
plastered and the other pointed, deduction shall be made from the plaster or pointing
on the side on which width of reveals is less than that on the other side but no
deduction shall be made on the other side. Where widths of reveals on both faces of
wall are equal, deduction of 50 percent of area of opening on each face shall be made
from areas of plaster and/or pointing as the case may be.
3)When only one face is plastered and the other face is not, full deduction shall be
made from plaster if width of reveal on plastered side is less than that on unplastered
side hut if widths of reveal on both sides are equal or width of reveal on plastered side
is more, no deduction shall be made.
4) When width of door frame is equal to thickness of wall or is projecting beyond
thickness of wall, full deduction for opening shall be made from each plastered face
of the wall.
In case of openings of area above 3 m2 each, deduction shall be made for opening on
each face but jambs., soffits and sills shall be measured.
1.7 BILL OF QUANTITIES: A bill of quantities (BOQ) is a document used in
tendering in the construction industry / supplies in which materials, parts, and labor
(and their costs) are itemized. It also (ideally) details the terms and conditions of the
construction or repair contract and itemizes all work to enable a contractor to price the
work for which he or she is bidding .The quantities may be measured in number,
length, area, volume, weight or time. Preparing a bill of quantities requires that the
design is complete and a specification has been prepared. The bill of quantities is
issued to tenderers for them to prepare a price for carrying out the works. The bill of
quantities assists tenderers in the calculation of construction costs for their tender,
and, as it means all tendering contractors will be pricing the same quantities (rather
than taking-off quantities from the drawings and specifications themselves), it also
provides a fair and accurate system for tendering.
1.8 SCHEDULE OF RATES:It is available in printed book format, it contains
list of various items of works, including material rate, labour wages and transportation
charges etc..provided by the PWD( Public Works Division)
Estimation and Costing and 15CE53T 2020-21
Dept. Of Civil Engineering, GPT Raichur(117) 12
1.9 LEAD STATEMENT: Lead statement: The distance between the source of
availability of material and construction site is known as "Lead” and is expected in
Km. The cost of conveyance of material depends on lead.
This statement will give the total cost of materials per unit item. It includes first cost,
conveyance loading, unloading stacking, charges etc.