6 Month Down Progress Meeting Agenda Introduction Mont Progress F. Pilat Safety Issues M. Logue Closing Remarks Mont 21 July 2011 11:30 a.m. - 12:30 p.m. 1:00 p.m. - 2:00 p.m.

Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

6 Month Down Progress Meeting Agenda

Introduction Mont

Progress F. Pilat

Safety Issues M. Logue

Closing Remarks Mont

21 July 2011

11:30 a.m. - 12:30 p.m.1:00 p.m. - 2:00 p.m.

Page 2: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

6-Month Shutdown: Status

Fulvia PilatDeputy Associate Lab Director for Accelerator

Head of the 6MSD Team

All Staff Meeting6MSD Status and Safety

CEBAF Center, July 21, 2011

Page 3: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

Outline

The first 10 weeks (trends, accomplishments, issues..)

Status

• Accelerator

Focus on magnet rework, cryomodules, RF zones

• Civil construction

• Halls

• Facilities

• FEL IR run starts in August

Look ahead

Planning for the rest of the 6MSD and the ensuing physics run

Page 4: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

The First 10 Weeks - Highlights

• Good first ~1/3 (10 weeks down, 18 to go….)

• Magnet rework and reinstallation going very well

went for the “stretch” goal (rework Arc 7 and 9 in East Arc)

and then added Arc 5

• Civil work, Halls, RF installation, LCW, FEL, and major scope of work on track so far

• The production and testing of the first 2 C100 cryomodules is delayed (largely as a result of the micro-phonics measurements and analysis) but we drafted a revised plan that gives high priority to installation and testing of C100-1 and C100-2, and allows for installation of R100 in the tunnel.

• Steering processes, teams and tools (integrated schedule) put in place for the 6MSD are working well.

Page 5: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

(Baseline)

(Stretch)

Add

Refurbish C100-2

Refurbish

C100-1

Accelerator

• East Arc Dipoles

(Arcs 7 & 9) removal

and installation

through SA Bldg

• Cryomodules into SA

bldg and into SLinac

for installation

• West Arc: rework 2-4-6-8, add Arc10

• East Arc: rework Arc 5-7-9

(leave Arc 1 and 3 untouched)

R100

Page 6: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

Magnet Rework Trends

Page 7: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

Magnet De-Installed

Page 8: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

Installation

Page 9: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

Magnet Factory, yesterday….

Page 10: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

RF Zones

Installation and testing of new RF power for the new cryomodules:

SL24 fully installed, SL25 and SL23 in progress….and……

Page 11: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

RF: Hot from the Press….

Zone SL24 successfully tested yesterday!

Page 12: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

Rendering of Hall D Complex – Looking East

Hall DCounting

House

Cryo Plant

Service

Building

Existing

Facilities

Beam Line

N

Tagger Area

Tunnel Extension &

Connection – Phase III

(FY11 Down)

Existing Tunnel

Page 13: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

Trench Box Installation

Weld failure on east cart, south side, bottom rail – Jun 24

Bolt failure on west cart, south side, top rail – Jul 7

3 strut carts

Trench Box

End of NE Stub

Example of

problem

resolution:

•Identify problem

•Stop working

•Investigation(s)

•Remedial plan

•Implementation

•Resume work

•Minimize impacts

Page 14: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

Hall AG2P beam-lines, target and cryo update all progressing well

Page 15: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

Hall B

Page 16: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

Hall C

SOS removal

Qweak target work

Page 17: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

Look Ahead

Challenges/issues for the remaining of the 6MSD:

• Completion Magnet refurbishment and reinstallation

• Weather, possibly causing delays in civil construction

• Accidents

• Cryomodule tests with beam and BBU measurements

• Handover new/refurbished systems to ops, hot check-out

• Bringing back timely the machine to full performance for 6 GeV operations

formally tracked risk

developed an integrated plan

internal review planned for the end of August

Page 18: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

Acknowledgments

The shutdown is a laboratory-wide effort

• Thanks to all Divisions, Groups, and individuals doing the work

• Thanks to the 6MSD Team

Page 19: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

6MD Incidents and

Lessons Learned

Mary Logue

Associate Director, ESH&Q

Page 20: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

Good Day! First Aid Injury Recordable InjuryOther Noteworthy Events

Page 21: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

Incidents Reported

Date Event Disposition

May 16Employee stood up and hit head on rail of strongback resulting in minor laceration

First Aid

May 23Employee was performing repeated “unscrewing” motions resulting in tendonitis

First Aid

June 2Employee’s leatherman tool blade closed and cut tip of index finger resulting in laceration

First Aid

June 13Subcontractor stepped down and 18 inch step and twisted left ankle – was assigned work restrictions

DART

June 20Subcontractor was tilting duct jack upwards and felt sudden pain in his upper back

First Aid

June 20Employee was potentially exposed to lead above the OSHA and ACGIH limit. Medical follow-up reported no uptake

First Aid

June 23Subcontractor was pulling cable when left hand twistedcausing wrist pain.

First Aid

Page 22: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

Incidents Reported

Date Event Disposition

June 23Graduate student experienced inguinal discomfort while lowering a mag drill

First Aid

July 1 Subcontractor was struck on hard hat with hollow spackling tool First Aid

July 6Employee bumped shin against blue metal brace causing abrasion of skin

First Aid

July 7Employee spilled PVC glue which then spilled on co-workers’ face

First Aid

July 7Mechanical fasteners connecting the strut to the linear rail of trench box failed

Event

July 11 Employee punctured their arm on exposed rebar wire ties First Aid

July 11 Subcontractor slipped in a puddle of water spraining right knee First Aid

July 13Subcontractor bent over to pick up geo-technical fabric and experienced back pain

DART

Page 23: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

Safety Observations

• There have been over 270 safety observations made of 6MD work – 75% of them have been recorded as “All Safe”

• Improper use of ladders and housekeeping are the recurrent themes

Page 24: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

Observations

• Observed workers walking alone through ODH 1 areas. Talked to one guy, he had just forgot that the area was an ODH 1. He saw the signs.

• Observed worker driving in reverse all the way from the middle of the South Linac service bldg. past bldg. 50. We stopped and talked to this person; he knew he was wrong but still did it. He promised not to do it again.

Page 25: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff
Page 26: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

So What?• Safety Observations tell us that folks are taking short cuts and

knowingly placing themselves in unsafe situations

• Injuries tell us that we’re seeing more issues with work planning

• When planning work:

– Lots of Physical Work taking place – consider body positioning and need for breaks when planning work

– Consider impact on other work groups

– Take the time to look at your work area before you start work

– Use the best tools for the job and use them correctly

– If the job conditions change – STOP the work and re-plan

– No short cuts!

Page 27: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

Lessons Learned – Potential Lead Exposure

• Work Activity: Remove steel panel from SOS detector platform using arc-plasma cutting

• After 1st panel removed, discovered lead shielding

• Work halted and IH was brought into consult

Page 28: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

Lessons Learned – Potential Lead Exposure

• Job planning completed with additional PPE, including respiratory protection and monitoring and job was restarted

• Later monitoring results indicated potential exposure above OSHA Permissible Exposure Limits

• Further monitoring indicated no uptake

Page 29: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

Lessons Learned – Potential Lead Exposure

• Lessons Learned:– If you encounter

something unexpected, stop the work and re-evaluate – Yea Team!

– Consult with as many people as you can or need to when planning the work

– Create New Hazard Analysis if there are changes to the work scope

Page 30: Introduction Mont Progress F. Pilat Safety Issues M. Logue ... · 6-Month Shutdown: Status Fulvia Pilat Deputy Associate Lab Director for Accelerator Head of the 6MSD Team All Staff

Finally…

A walkthrough of your work area each day keeps the hazards at bay!