International ISRU Field Test Accomplishments Crate & Palletize hardware for shipment to Hawaii Pennsylvania Air Force Reserve C130 stopped at Wisconsin, KSC on Friday 1/22/10 to pick up hardware C130 stopped at JSC to pick up hardware on 1/23/10 C130 Departs for Hawaii, expected arrival 1/25/10 Cost of hardware shipment was a tour of KSC for the flight crew. No cost for NASA for transportation. Cultural sensitivities addressed (Hawaiian consider the volcano sacred) by having a local Hawaiian “Priest” conduct a ceremonial blessing of the test site. While this may seem silly to mainlanders, the Hawaiians take this very seriously Issues/Concerns/Resolutions Weather or Maintenance issues could delay hardware arrival in Hawaii No problems so far, but until the plane touches down in Hilo there is always some element of risk Plans for Tomorrow Aircraft off loaded Image of the Day – See following slide Daily Snapshot Date: 1/24/10

International ISRU Field Test

  • Upload
    yetta

  • View
    45

  • Download
    0

Embed Size (px)

DESCRIPTION

International ISRU Field Test. Daily Snapshot. Date : 1/24/10. Images of the day. Crating RESOLVE Experiment Package. Hawaiian “Priest” blesses field test site. AF Reserve C130 Ready for Departure. KSC Equipment Pallet Loading. - PowerPoint PPT Presentation

Citation preview

Page 1: International ISRU Field Test

International ISRU Field Test

Accomplishments• Crate & Palletize hardware for shipment to Hawaii• Pennsylvania Air Force Reserve C130 stopped at

Wisconsin, KSC on Friday 1/22/10 to pick up hardware

• C130 stopped at JSC to pick up hardware on 1/23/10• C130 Departs for Hawaii, expected arrival 1/25/10• Cost of hardware shipment was a tour of KSC for the

flight crew. No cost for NASA for transportation.• Cultural sensitivities addressed (Hawaiian consider

the volcano sacred) by having a local Hawaiian “Priest” conduct a ceremonial blessing of the test site.

• While this may seem silly to mainlanders, the Hawaiians take this very seriously

Issues/Concerns/Resolutions• Weather or Maintenance issues could delay hardware

arrival in Hawaii• No problems so far, but until the plane touches

down in Hilo there is always some element of risk

Plans for Tomorrow• Aircraft off loaded• Local transportation company loads and transports

hardware to the mountain.• Canadians provide trucks to move hardware from

mountain staging area down to the test site

Image of the Day – See following slide

Daily Snapshot Date: 1/24/10

Page 2: International ISRU Field Test

Images of the day

Hawaiian “Priest” blesses field test site Crating RESOLVE Experiment Package

AF Reserve C130 Ready for DepartureKSC Equipment Pallet Loading