Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Internal Monitoring Report
37231-043 May 2016
PAK: Loan 2971: Pakpattan Canal and Suleimanki Barrage Improvement
Project (January- March 2016)
This Internal Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area."
1. LAND ACQUISITION AND RESETTLEMENT PLAN (LARP)
ADB approved the updated LARP for Pakpattan Canal in July 2014. A total of 80 households
have been affected. Implementation of the LARP has been divided into three phases. Phase 1
(Nov, 2014 – Sep, 2015) which involved 33 affected households were completed in April 2015.
The segregation of 80 household were made internally to complete the said work according to
Contractor schedule because the total 80 cases are situated on different locations /RDs of the
Canal and Contractor has started the work at different locations. The remaining 4 cases of
Phase-1 are under process at PMO Punjab Barrages for final payments as Contractor yet not
started work at those locations and due to change in design the work may be deleted at these
locations Phase 2 (Nov, 2015 – Sep, 2016) involves 20 households, while Phase 3 (Nov, 2016 –
Sep, 2017) involves 27 households. PMO and PSSC have targeted to complete Phase 2, and 3 by
June 2016. There is no land acquisition at Sulemanki Barrage but temporary land acquisition is
only at Pakpattan Canal. The compensation is related to temporary land acquisition, structures,
trees etc. of the affected families residing at ROW and nearby by vicinity of canals.
Most of the affected households are illegal settlers on the irrigation land and are compensated
for their losses of assets and are provided with relocation allowance and assistance for
vulnerable households. PMO and PSSC have full-time staff that visit the site on regular basis to
interact with the communities and affected households.
LARP Implementation activities for Tranche 3 relates to Pakpattan Canal System. The LARP
cover the impacts due to the rehabilitation and upgrading of Pakpattan canal Upper/ Lower,
Khadir Branch and Pakpattan Islam Link. Internal monitoring is done by the PMO Environment
& Social Unit (ESU) with support from PSSC and internal monitoring reports in the shape of QPR
are being regularly submitted to the Bank, PMO has selected an independent resettlement
monitor (IM) to cover all tranches (Tranche 2 & 3) of the MFF. He has signed the contract
agreement with PMO Barrages. PMO has sent the same to the ADB for approval which is still
awaited. The IM will be mobilized by May 2016 and he will submit his first external
resettlement monitoring report by July 2016.
2. ADJUSTMENT made in the compensation rate during updating of LARP in 2014.
The LARP of Pakpattan Canal System was prepared in year 2012 but the LARP was not
implemented during 2012-2013. Later on, the adjustment was made in compensation rates of
land, structures and livelihood assistance during updating the LARP in July 2014. The temporary
land occupation rates in three districts of project area are starting from Rs. 40,000 to Rs. 60,000
per acre. These rates are more than market rates because the average rate of one acre is up to
Rs. 40,000. But under the supervision of PSSC and PMO Punjab Barrages, the rates of temporary
land occupations are being provided maximum up to Rs. 60,000 which are already higher side.
The certification from BOR is not required in this regard due to already higher and safer side to
the AFs.
The rates of 2014 are still applicable because they were at upper most side in 2014. Therefore,
there is no much changes recognized up till now. The adjustment made in compensation rates
is given in Annex-A
3. EMPLOYMENT OF THE AFFECTED HOUSEHOLDS IN PROJECT RELATED JOBS.
Complaints register is also maintained by PSSC to record community concerns and there
solutions. Most of the concerns received are related to employment with the Contractor.
According to the contract, the Contractor is bound to hire maximum labors from the locals of
the project area. The Supervision Consultants staff is getting Employment Status of the local
community on monthly basis and fully concerned to provide unskilled labor employment to the
AFs of the project. The status of skilled and unskilled labor employment for the month of
January, February and March 2016 is given in Annex B, C and D which is 77%, 76% and
83% respectively for unskilled labor for the project area.
Out of 33 affected families, 03 persons were willing to do job with the Contractor at RD No. 62
of Pakpattan Canal Upper for stone stud activity. The name of affected person is Hashim Ali S/O
of Sardar Ali. His 02 sons (Sarfraz s/o Hashim Ali, Iqbal s/o Hashim Ali and 01 person (Yaqoob
s/o Rehmat Ali) other AH have been doing jobs with Contractor. Mr. Yaqoob s/o Rehmat Ali is
still working with Contractor at RD 52 of PCU as a watchman for Gauge Reader Hut. Na sons are
doing jobs with the Contractor.
Table 1: AH members employed in project-related jobs (Previous and Current Quarter)
Previous Quarter First Quarter 2016 Remarks
Number of DPs Seeking Project-
related Jobs
Number of DPs who Got Project-
related Jobs
Number of DPs Seeking Project-
related Jobs
Number of DPs who Got Project-
related Jobs
3 3 1 1
Hashim Ali’s 2 sons were working with Contractor namely Sarfraz & Iqbal s/o Hashim Ali. Now only one AP; Mr. Yaqoob s/o Rehmat Ali who is also AH, is still working with Contractor as a Watchman on RD 52 of PCU atGauge Reader Hutt
4. RELOCATION OF AFFECTED HOUSEHOLDS AND THEIR CURRENT LIVING
CONDITION.
Total 80 Affected Households (AHs) will be relocated regarding rehabilitation and upgrading of
Pakpattan Canal System. Out of these, 35 AHs are at Pakpattan Canal Upper, 2 AHs at Pakpattan
Canal Lower, 42 AHs at Khadir Branch and only 1 AH is at P.I Link canal.
During First Phase (Annex-E), 33 AHs, 14 at Pakpattan Canal Upper, 2 at Pakpattan Canal
Lower, 16 at Khadir Branch, 1 at P.I Link Canal. Most of the AHs were shopkeepers having the
business
of selling edibles and general store items. They are living hand to mouth and difficult to live
within that income because they have no alternative source of income. Their family size is too
large to support with the current resources. Similarly in Phase 2 out of 20 cases, 4 cases are
under process for payments and remaining cases are in progress and will be completed before
June 2016. The before conditions of the AFs was presented in internal resettlement monitoring
report of July-September. After condition of the Affected Families are being observed and will
be presented in next report. Status of implementation of LARP is given in Annex-F
Table 2: Status of compensation payments (Previous and Current Quarter) Phase
No. of
AHs
Previous Quarter First Quarter 2016 Remarks
Compen-sated
Not Yet Compen-
sated
Compen-sated
Not yet Compen-
sated
First
33 29 4 Nill Nill Due to change in design during construction stage these cases may be deleted because there is no need of work at these locations therefore the cases are pending in PMO Punjab Barrages for final payments.
Second 20 Nill Nill Nill Nill The second and Third quarters are under process due to re-survey of canals and change in design. After the finalization of new design the remaining cases will be compensated accordingly.
Third 27 Nill Nill Nill Nill As above
Total 80
5. Grievance Redressed Mechanism.
Tranche 3 also has an operational grievance redress mechanism that covers all aspects of the project
activities, including resettlement. Concerns and feedback from residents of the 10 nearby villages are
noted by the ESU and PSSC. On Pakpattan Canal Project site, Contractor has established Grievance
Redressal Mechanism on camp site and each location of work. Mostly complaints arise regarding having
employment of the local persons, sprinkling of water, medicine, mosquitoes spray and late payments. At
Pakpatan Camp and Burewala sites, total 34complaints recorded and 28 have been resolved while 6 are
pending. At Sulemanki Barrage camp, total 31complaints recorded and 28 have been resolved while 3
are pending. The pending cases will be resolved very soon. Status of settlements of complaints is given
in Annex-G
Table 3: Status of Grievance Resoluation (Previous and Current Quarter)1
Type of
Grievance
Previous Quarter First Quarter 2016 Remarks
Number of
Grievances
Received
Number of
Grievances
Resolved
Number
Grievances
Received**
Number of
Grievances
Resolved
LAR-related Nill Nill Nill Nill There is no any
Grievance
related to LR is
received
Environment-related
38 32 Pending grievances will be solved soon
Others 20 16 -Do-
Total 59 49
** Including pending grievances from previous period.
1 These are not limited to LAR_related greivances. These include grievances that are not related to land
acquisition or resettlement which are received from various stakeholders
Annex-A
Adjustment made in Compensation Rates in LARP July,2014
Sr. No. Description Unit Unit Rate of LARP 2012
Unit Rate of updated LARP 2014
Remarks
1 Land Occupation
- Temporary occupation of land for 3 years
Acres 50,000 60,000 The temporary land occupation rates in three districts of project area are started from Rs. 40,000 to Rs. 50,000 per acre. These rates are more than market rates because the average rate of one acre is uptoRs. 40,000. But under the supervision of PSSC and PMO Punjab Barrages the rates of temporary land occupations are being provided maximum uptoRs. 50,000 which are already higher side. The certification from BOR is not required in this regard due to already higher and safer side to the AFs. Therefore the matter of 2015 rates does not applicable on these cases.
2 Residential Structures
- i) Pacca structure
Sq. ft. 720 840
- ii) Semi-pacca structures - Sq. ft. 525 600
- 5 nos.
- iii) Katcha/ thached shed - Sq. ft. 310 360
- 6 nos.
iv) Boundary walls - 6 nos.
Sq. ft. 310 120
3 Commercial Structures (shops/ kiosks)
- i) Semi-pacca structures (shops) - 4 nos.
Sq. ft. 525 600
- ii) Katcha structures/ sheds - 11 nos.
Sq. ft. 310 360
iii) Kiosks/ phatta Nos. 5,000 5,000
4 Community Structures
- Hand Pumps Nos. 10,000 10,000
Electric Motor - 15,000
5 Livelihood Assistance
-
i) Business interruption allowance (for 3 months based on the oficial
Nos. 27,000 31,500
wage rate at Rs. 9,000 per month).
-
ii) Livelihood assistance to Boatmen (for 3 months based on official wage rate at Rs. 9,000 per month.
Nos. 27,000 31,500
-
iii) Shifting/ transport assistance allowance (Rs.5,000) - 7 DPs of residential structures and 7 boatmen for sifting.
Nos. 5,000 5,000
iv) Severe impact allowance
- 10,500
v) Vulnerability allowance (cash allowance for 3 months based on the Officail Wage Rate Rs. 9000 per month as fixed).
Nos. 27,000 31,500
Annex-B
Pakpattan Canal and Suleimanki Barrage Improvement Project (PCSBIP) Employment Status for the Month of January, 2016
Sr. No.
Project Area
Sinohydro-NEL Sub-Contractor Total Remarks
Skilled Un-
Skilled Total Skilled
Un-Skilled
Total Skilled Un-
Skilled Total
1 Pakpattan 80 16 96 30 12 42 110 28 138
During Phase 1 out of 33 AFs, the contractor has employed 3 members of AFs. They were serving with the contractors from July 01, 2015. But from 1st quarter only one AP; Mr. Yaqoob is working with the Contractor
2 Vehari 25 10 35 10 13 23 35 23 58
3 Burewala 65 15 80 25 13 38 90 28 118
4 Arifwala - 40 40 - 7 7 - 47 47
5 Total 170 81 251 65 45 110 235 126 361
6 % age 74% 77%
7
Other from
Project Area
50 25 75 30 13 43 80 38 118
8 % age 25% 23%
9 Total 220 106 326 95 58 153 315 164 479
Note :Local Labor utilized :77% Out of 33 Afs, 3 AF were employed since July 2015 and still working. The type of employment of AFs related to non-skilled labour.
Annex-C
Pakpattan Canal and Suleimanki Barrage Improvement Project (PCSBIP)
Employment Status for the Month of February, 2016
Sr.
No. Project Area
Sinohydro-NEL Sub-Contractor Total
Remarks Skilled
Un-
Skilled Total Skilled
Un-
Skilled Total Skilled
Un-
Skilled Total
1 Pakpattan 80 16 96 30 12 42 110 28 138
During Phase 1
out of 33 AFs,
the contractor
has employed 3
members of
AFs. They were
serving with
the contractors
from Jully 01,
2015 to
onward. But
from 1st quarter
only one AP;
Mr. Yaqoob is
working with
the Contractor
2 Vehari 25 10 35 10 13 23 35 23 58
3 Burewala 65 15 80 25 13 38 90 28 118
4 Arifwala - 40 40 - - - - 40 40
5 Total 170 81 251 65 38 103 235 119 354
6 % age - - - - - - 75% 76% -
7
Other from
Project Area 50 25 75 30 13 43 80 38 118
8 % age - - - - - - 25% 24% -
9 Total 220 106 326 95 51 146 315 157 472
Local Labor utilized :76% Note:Out of 33 Afs, 3 AF were employed since July 2015 and still working. The type of employment of AFs related to non-
Annex -D
Pakpattan Canal and Suleimanki Barrage Improvement Project (PCSBIP)
Employment Status for the Month of March, 2016
Sr.
No. Project Area
Sinohydro-NEL Sub-Contractor Total
Remarks Skilled
Un-
Skilled Total Skilled
Un-
Skilled Total Skilled
Un-
Skilled Total
1 Pakpattan 80 16 96 30 12 42 110 28 138
During Phase 1
out of 33 Afs,
the contractor
has employed 3
memebers of
AFs. They were
serving with
the contractors
from Jully 01,
2015 to
onward. But
from 1st quarter
only one AP;
Mr. Yaqoob is
working with
the Contractor
2 Vehari 25 10 35 10 13 23 35 23 58
3 Burewala 65 15 80 25 13 38 90 28 118
4 Arifwala - 40 40 - 7 7 - 47 47
5 Total 170 81 251 65 45 110 235 126 361
6 % age - - - - - - 74% 83% -
7
Other from
Project Area 50 25 75 30 - 30 80 25 105
8 % age - - - - - - 25% 17% -
9 Total 220 106 326 95 45 140 315 151 466
Local Labor utilized: 83% Note: Out of 33 Afs, 3 AF were employed since July 2015 and still working. The type of employment of AFs related to non-skilled labor
Annex-E
Phase -1 Compensation Payment to the Affectees of PakPattan Canal Sr. No.
Payment Date
Particulars AmountRs.
1 8-Jan-15 Mr. Azhar Farman S/O GhulamHussain 94,300
2 8-Jan-15 Mr. Akeel Ahmad S/O Sultan Ahmad 73,000
3 8-Jan-15 Mr. Muhammad Akram S/O Sayyad Muhammad 41,500
4 8-Jan-15 Mr. Niyaaz Ahmad S/O GhulamHussain 73,000
5 8-Jan-15 Mr. KhadimHussain S/O Ghulam Ali 83,000
6 8-Jan-15 Mr. Muhammad Tufail S/O Ahmad Din 83,000
7 8-Jan-15 Mr. Muhammad JavedIqbal S/O Bahadur Ali 83,000
8 8-Jan-15 Mr. Muhammad JavedIqbal S/O Muhammad Ali 56,500
9 8-Jan-15 Mr. Muhammad Ameer S/O Manzoor Ahmad 41,500
10 8-Jan-15 Mr. Sarfraz Ahmad S/O Muhammad Hussain 73,000
11 8-Jan-15 Mr. Munir Ahmad S/O Lal Muhammad 116,940
12 8-Jan-15 Mr. IrshadHussain S/O Muhammad Rafique 231,500
13 8-Jan-15 Ms. Bashiran Bibi W/o Manzoor Hussain 184,220
14 8-Jan-15 Mr. Hashim Ali S/O Sardar Ali. 623,900
15 8-Jan-15 Mr. Taj Muhammad S/O Din Muhammad 41,500
16 8-Jan-15 Mr. Irshad Shah S/O Khadim Shah 93,000
17 8-Jan-15 Muhammad Ramzan S/O Muhammad Sadiq 73,000
18 8-Jan-15 Mr. Khalid Hussain S/O Qasim Ali 41,500
19 8-Jan-15 Muhammad Saeed S/O Manzoor Ahmad 83,000
20 8-Jan-15 GhulamRasool S/O TalibHussain 73,000
21 8-Jan-15 Muhammad Abbas S/O Cherag Din 41,500
22 8-Jan-15 Muhammad Yaqoob S/O Rehmat Ali 147,800
23 8-Jan-15 Mr. Punnu S/O Noor Ahmad 208,100
24 13-Apr-15 Mr. Liaqat Ai S/O Muhammad Ramzan 73,000
25 13-Apr-15 Mr. Muhammad Afzal S/O Muhammad Akhter 41,500
26 13-Apr-15 Mr. Muhammad Mansha S/O Ahmad Yar 189,480
27 13-Apr-15 Mr. Muhammad Rafique S/O Muhammad Sadiq 73,000
28 13-Apr-15 Mr. Tariq Mehmood S/O Muhammad Ramzan 41,500
29 13-Apr-15 Mr. Muhammad Mumtaz S/O Muhammad Yaseen 83,000
30 Muhammad Ashiq S/O Qasim Ali 50,700
31 Noor Muhammad S/O Qasim Ali 93,000
32 Muhammad Tufail S/O Qasim Ali 211,160
33 Muhammad Ramzan S/O Meero 63,000
TOTAL: 3,580,100
Annex-F
Status of Implementation of LARP for PCSBIP/ICB-01 as of 31-03-2016
Sr. No.
Contract No.
Status of preparation, vetting and approval of
RP
Compensation Due
Implementation % Implementation Remarks
1
Tranch-3, Pakpattan Canal and Suleimanki
Barrage Improvement
Project PCSBIP/ICB-
01
Draft LARP of Pakpattan
Canal system was prepared in 2012 later
on LARP was revised and updated in July, 2014.
No. of
Afs.
Amount Due
Total AFs paid
Amount paid
AFs paid Amount Paid
Status of Civil work
award
Out of 33, payment has been made to 29 AFs
Which is 88%. The Payment
of Phase 2 and 3 in under
process that will
be completed within due
periods.
Phase 1 (Nov 2014
to Sep 2015)
33 3.58 29 3.162 88% 88% Awarded for Phase
1
Phase 2 (Nov 2015
to Sep 2016)
20 In progress
In progress
In progress
In progress
In progress
In progress
Phase 3 (Nov 2016
to Sep 2017)
27 In progress
In progress
In progress
In progress
In progress
In progress
Total 80 3.58 29 3.162 88% 88%
Note:-Phase-II and III are under progress and will be completed before June 2016.
Annex-G
Status of Settlement of Complaints
Sr. No.
Date Complainant Location Sort of Complain Status
01 02-01-2016 Mukhtar Ahmed Camp Burewala
Please improve Mess quality
Resolved
02 03-01-2016 Ramzan Camp Burewala
Security system of camp needs improvement
Resolved
03 03-01-2016 Asim Grassy Lawns of camp need attention
Resolved
04 05-01-2016 M Bakhsh There is need to conduct an entire spray in camp for mosquitoes & flies
Resolved
05 08-01-2016 NasirMehmood RD 399 PC Water sprinkling is seriously required near site areas
Resolved
06 10-01-2016 Pervaiz Machiwal Machinery parking in camp is not proper. All the drivers should be instructed regarding this issue
Resolved
07 14-01-2016 Israr Camp Pakpattan
There should be a badminton court or a free ground for recreational activities.
Pending
08 16-01-2016 Aslam Chak#495 EB In camp dispensary there should be the treatment of Hepatitis & Diabetes.
Pending
09 19-01-2016 Waqas Cam Pakpattan
Sweeper is not performing his duties well
Resolved
10 21-01-2016 Amir RD 449 PC Workers attitude is not good with local community. Please ask them to be good with locality
Resolved
11 24-01-2016 Imran Chak # 48 KB There are not enough sign boards near construction site (RD 275 Khadir Branch)
Resolved
12 25-01-2016 Arslan RD 499 PC Workers at site commit trespass to land & they use to steal fruits from my Orchard
Resolved
13 27-01-2016 Kaleem Chak #122 EB House keeping is not good at site RD 399 PC Upper. Passers by feel difficulty due to rad blockage.
Resolved
14 30-01-2016 Munir Camp Burewala
Concrete water accumulates under batching plant, this may lead to dengue virus. Please ask plant staff to clear it periodically & regularly
Resolved
15 02-02-2016 Khalid Chak# 493 EB I went to dispensary but medicine was not enough there.
Resolved
16 05-02-2016 Adeel Camp Burewala
Mess timings are not being strictly followed
Resolved
17 07-02-2016 Munir Camp Pakpattan
Camp lawns are not being watered properly. Gardener does not take care of plants
Resolved
18 09-02-2016 Mubashar Camp Burewala
Security guard is running short of bullets.
Resolved
19 12-02-2016 Faryaad Camp Pakpattan
We are not getting salary on time. we are facing too much difficulty because of this issue.
Pending
20 14-02-2016 M. Ali Chak # 493 EB
Dispensary is running short of medicines. Please resolve this issue because we are poor people & can't afford doctors in city.
Resolved
21 16-02-2016 Allah Ditta Camp Burewala
Water pump is out of order Facing difficulty for watering of plants.
Resolved
22 18-02-2016 Rizwan Camp Burewala
Security guard was not in uniform. It is therefore difficult to recognize him
Resolved
23 20-02-2016 Awais Camp Water Sprinkling is not Resolved
Pakpattan being conducted at camp so workers are facing dust issues.
24 22-02-2016 Iqrar Camp Burewala
Sitting benches are not being cleaned properly House keeping at Mess area needs improvement.
Resolved
25 02-03-2016 Allah Ditta Camp Burewala
I want two month salary for my wife's treatment. Kindly resolve my issue.
Pending
26 05-03-2016 TozeeulHussan Camp Pakpattan
Camp staff behavior is not good. ask them to be polite with all the visitors or patients that come to camp.
Pending
27 08-03-2016 Adeel Camp Burewala
Camp sweeper is on leave for mor than 4 days. House keeping is being affected.
Resolved
28 10-03-2016 Mussawar RD 301 Khadir Barrication tape is required at site
Resolved
29 13-03-2016 Waseem RD 301 Khadir House keeping is not proper at site
Resolved
30 17-03-2016 IqrarBaig Camp Pakpattan
There is water accumulation problem under batching plant. this may cause dengue virus.
Resolved
31 19-03-2016 Abdul Kareem Chak # 495 EB
Heavy Machinery coming to camp cause road blockage. Ask them to travel during night time or early in the morning.
Resolved
32 23-03-2016 Younas Camp Burewala
Flash lights of camp are not working so there is security issue during night times.
Resolved
33 27-03-2016 Waqas RD 304 Khadir Sign boards have been stolen from site. Please arrange for new boards.
Resolved
34 30-03-2016 Munir RD 286 Khadir My land has been hired on lease. Contract time has been completed so
Pending
i want to renew the contract of my land for furthur 6 months.
Sulemanki Barrage 01 03-01-2016 Shoukatali Camp site Sprinkling should be
done twice a day Resolved
02 07-01-2016 m.bilal Camp site Night time there is an issue of lights on walkways
Resolved
03 07-02-2016 Aslam Working site Lunch is not being provided in time
Resolved
04 11-01-2016 Arsalan Head bazar Tractor drivers are using tape recorders which create disturbance
Resolved
05 13-01-2016 Kashifhussain Machli bazar head
The excavated material from coffers dam is being dumped along the edges of main road. This issue must be resolved soon
Resolved
06 16-01-2016 Javediqbal Camp site Dumper drivers inside the camp during night time using load speakers that disturb their sleep. Early action must be taken.
Resolved
07 19-012016 Jamsheed Camp site Recreational facilities must be provided at camp.
Pending
08 24-012016 Safdar hussain Head bazar Water bowser is not sprinkling the water on peak working hours. He must be advised.
Resolved
09 24-01-2016 Basit Nawaz Working site Drinking water is not enough. At every working location water coolers must be placed.
Resolved
10 25-01-2016 Ibrar Working site I am working as a labor and I don’t have safety shoes. H.S.E staff is not allowing me to work without safety shoes. So please provide me safety shoes.
Resolved
11 25-01-2016 Sajidali Working site The vertical elevation Resolved
on diversion road must be maintained properly.
12 28-01-2016 Mushtaq Camp site Improve the mess quality
Resolved
13 31-01-2016 Asif Camp site Proper pads under the batching plant must be made because during rainy seasons water remains here.
Resolved
14 04-02-2016 Mukhtaar Camp site Mosquito spray must is done in every room.
Resolved
15 05-02-2016 Adnan Working site Lunch is not being provided in time at site
Resolved
16 07-02-2016 Munwar Working site For right under sluice there is no proper passage to carry the equipments.
Resolved
17 10-02-2016 Adil Jamal kot Some drivers during night sales the excavated material near our home that is big problem for us.
Resolved
18 18-02-2016 Sajid Pump head Your staff misbehaves with our employees.
Resolved
19 19-02-2016 Asifali Camp head Dispensary is running short of medicines. Please resolve this issue because we are poor people & can't afford doctors in city.
Resolved
20 21-02-2016 Shahzadalui Working site Drinking water is short and not being provided in time.
Resolved
21 23-02-2016 m.kamran Container pssc
Container office needs two energy savers.
Resolved
22 26-02-2016 Samiullah Chinese workshop
Water Sprinkling is not being conducted at camp so workers are facing dust issues.
Resolved
23 27-02-2016 Allah rakha Labor mess Mess staff attitude is not good with the workers so please advise them.
Resolved
24 05-02-2016 M.younis Working site Traffic congestion disturbs our activities.
Pending
25 07-02-2016 Kamran Camp site During night there Pending
should not be any king of work inside the camp that disturbs our sleep.
26 09-02-2016 Munirhussain Workshop camp
Washing deck cleaning is not being carried out in time.
Resolved
27 15-02-2016 Issrar Working site High speed vehicles causes the dust problem speed breakers must be construct.
resolved
28 17-02-2016 Javedaslam Bazar head House keeping is not proper at site
Resolved
29 21-02-2016 Malik hussain Irrigation colony
Sprinkling must be done.
Resolved
30 27-02-2016 M .usman Camp site Heavy Machinery coming to camp cause road blockage.
Resolved
31 28-02-2016 Ali hasnain Working site Lightning arrangement must be increased.
Resolved