66
Corps of Engineers BUILDING STRONG ® Interim Risk Reduction Measures José Hernández, P.E. Regional Geotechnical Engineer U.S. Army Corps of Engineers South Atlantic Division [email protected] Dam Safety Workshop Brasília, Brazil 20-24 May 2013

Interim Risk Reduction Measures

  • Upload
    heidi

  • View
    79

  • Download
    0

Embed Size (px)

DESCRIPTION

José Hernández , P.E. Regional Geotechnical Engineer U.S. Army Corps of Engineers South Atlantic Division [email protected] Dam Safety Workshop Brasília, Brazil 20-24 May 2013. Interim Risk Reduction Measures. Risk Assessment Analytically based. Risk Management - PowerPoint PPT Presentation

Citation preview

Page 1: Interim Risk Reduction Measures

Corps of EngineersBUILDING STRONG®

Interim Risk Reduction MeasuresJosé Hernández, P.E.Regional Geotechnical EngineerU.S. Army Corps of EngineersSouth Atlantic Division [email protected]

Dam Safety WorkshopBrasília, Brazil20-24 May 2013

Page 2: Interim Risk Reduction Measures

(1) IRRMs are a short-term approach to reduce Dam Safety risks while long-term solutions are being pursued.

(2) IRRMs should lower the probability of failure and associated consequences to the maximum extent reasonably.

Risk Management Policy and preference

based

Risk AssessmentAnalytically based

Risk CommunicationInteractive exchange of information, opinions,

and preferences concerning risks

TolerableRisk

Guidelines

IRRMs include and align with USACE’s Dam Safety

Risk Policy

Objective

Page 3: Interim Risk Reduction Measures

Risk DefinitionRisk = Load Probability x Failure Probability Given a Specific Load x

Consequences of Failure

Page 4: Interim Risk Reduction Measures

USACE Dam Safety Portfolio Risk Management

Process

DevelopIRRMP

Modify IRRMP (if necessary)

Modify IRRMP (if necessary)

Page 5: Interim Risk Reduction Measures

Screening Portfolio Risk Analysis (SPRA) FY05-09

Dams identified to have unacceptable risk, “Develop Interim Risk Reduction Measures Plan”

National queue for “Issue Evaluation Study (IES)”

Complete Dam Safety Modification Study (DSMS) (if justified based on IES)

Generalized Risk Management Process

Page 6: Interim Risk Reduction Measures

6

IRRMPRequired

Page 7: Interim Risk Reduction Measures

Principles

It is not appropriate to refer to balancing or trading off public safety with other project benefits.

Instead, it is after public safety tolerable risk guidelines are met that other project purposes and objectives will be considered.

Page 8: Interim Risk Reduction Measures

Principles

The principle of “Do No Harm” should underpin all actions intended to reduce dam safety risk.

Applying this principle will ensure that proposed IRRM implementation would not result in the dam safety being compromised at any point in time or during IRRM implementation.

Page 9: Interim Risk Reduction Measures

Principles

Decisions are risk-informed and not risk-based.

Risk-informed decisions integrate traditional engineering analyses and judgment.

General public safety responsibility requires USACE to assure our projects are adequately safe from catastrophic failure that results in uncontrolled release of the water in the reservoir.

Page 10: Interim Risk Reduction Measures

IRRMs should be tied to a documented area of concern or a potential failure mode.

IRRMs should not be a continued standard maintenance action, or following an established procedure.

IRRMs need to specifically state how a plan reduces the overall risk by decreasing loading, consequences or likelihood of failure.

A study by itself is not an IRRM, and does nothing to reduce risk. If a study is referenced in an IRRM, there needs to be information on how it is to be used to lower the risk.

IRRMs

Page 11: Interim Risk Reduction Measures

IRRMs

Non-Structural IRRMs are just as important as Structural IRRMs.

Local agencies and the public should be informed and have a chance to be involved or made aware of project decisions that could impact them.

Remember that the risk presented by a system can change because an IRRM is implemented, and it will not always go down.

Page 12: Interim Risk Reduction Measures

IRRMs

Pool restrictions must be given serious consideration and explain why (very specific reasons) they are not being implemented.

Water Control Plans (WCPs) need to support IRRMs.

National Environmental Policy Act (NEPA) should be involved early and often in the process and should be discussed as part of the IRRM.

Page 13: Interim Risk Reduction Measures

If the system operations change, pool restrictions are altered, or there are impacts up/downstream of the project outside of the project boundaries, the WCP may need to be revised or an Interim Operations Plan (IOP) should be developed.

IOPs can be used to supplement WCPs for guidance on system operations.

Having an IOP does not relieve the burden of updating the project’s WCP.

IRRMs and WCPs

Page 14: Interim Risk Reduction Measures

Overall IRRM Impacts

Consider changes to the overall project risk when developing an IRRM. Need to make sure that lowering the risk for a

specific failure mode does not increase the overall risk of the project.

Are you introducing new risk to the project by implementing a IRRM?

Page 15: Interim Risk Reduction Measures

What is an IRRM? IRRMs are not intended to be the process for

permanently remediating dam safety concerns. The following factors are used to determine if an IRRM is

appropriate: Timely – Can it be implemented in a timely manner? If

significant time and money is needed to investigate and design, it is not likely an IRRM.

Cost effective – Is the cost within the threshold of a major maintenance (O&M funds) project? If it exceeds the threshold, it is not likely an IRRM.

Risk – Does the measure reduce the overall risk to downstream public? IRRMs should not incur in new risk. Thus may need to do preliminary analysis as a check.

15

Page 16: Interim Risk Reduction Measures

16

IRRM Plan (IRRMP) Guidance Chapter 7, “Interim Risk Reduction Measures For Dam

Safety,” and Appendices M and N in USACE ER 1110-2-1156, “Safety of Dams – Policy and Procedures”

To provide guidance and procedures for developing and implementing IRRMs required for all DSAC I, II and III

Funding for preparation and implementation of the IRRMP comes out from the O&M funds for the project

Page 17: Interim Risk Reduction Measures

Use existing project data (studies, analysis, performance data). Use SPRA findings as a 1st cut on development of IRRM. Follow-on with Potential Failure Mode Analysis (PFMA) to capture

additional significant PFMs. Refine IRRMP based on PFMA findings and new project data. Ensure the Emergency Action Plan (EAP) is current. Engage Public Affairs Officer (PAO) for Risk Communication Plan

development. Train and test internal staff and site personnel on IRRM strategy. Functionally conduct an Emergency Exercise for an initiating

event with state and local officials.

IRRMP Basic Steps

Page 18: Interim Risk Reduction Measures

• Overall project description and purposes.

• Overview of identified “risk-driver” potential failure modes; attach PFMA Report.

• Summary of known consequences associated with each identified PFM to include: loss of life, economic and environmental damages .

• List structural and non-structural IRRM alternatives considered to reduce the probability of failure and/or consequences associated with the failure modes.

IRRMP Contents

Page 19: Interim Risk Reduction Measures

• For each considered IRRM, document general discussion of ability to reduce the likelihood of failure and associated consequences, potential impact on project purposes, environmental impacts, and economic impact to the region associated; both positive and negative.

• Final IRRM recommendations to be implemented for each PFM.

• Schedule to implement and cost to USACE (dam owner) and others (stakeholders) for each IRRM recommendation.

IRRMP Contents

Page 20: Interim Risk Reduction Measures

• DQC/ATR comments and comment resolutions.

• Updated EAP reflecting site-specific risks and emergency exercises for DSAC I, II, and III dams conducted in manners that are appropriate for the risk involved .

• Risk Communication Plan (both internal and external).

IRRMP Appendices

Page 21: Interim Risk Reduction Measures

IRRMPs

Are Living Documents. They should be revised… when conditions change new information is acquired studies are performed after completion of remediation phase

Should focus on “significant” risks when identified in a PFMA as part of a PA, IES, and DSMS.

Page 22: Interim Risk Reduction Measures

Potential Reasons for Rejection of IRRMPs

Inadequate consideration for pool restriction, or justification for no restriction

Automated early warning systems with automatic public notification

Pool releases based on rain forecasts Inadequate description of consequences Got Boils? Better have emergency stockpiles. “Copy and Paste” Waiting for studies . . .

Page 23: Interim Risk Reduction Measures

23

Why use PFMA with IRRM?

All dams are unique and have specific vulnerabilities.

Identify “risk-driver” potential failure modes using a trained facilitator and multi-disciplinary team.

Match the IRRM with the identified potential failure modes, geology, dam design and loading, and determination whether the dam is on a failure continuum.

Page 24: Interim Risk Reduction Measures

PFMA = Blueprint for IRRMP

Page 25: Interim Risk Reduction Measures

1. Operational changes

a. Reservoir restrictionsb. Changes in release patterns

2. Structural IRRMs

3. Non-structural IRRMs

IRRM Alternatives

Page 26: Interim Risk Reduction Measures

A lowered pool level typically provides a reduction in system loading, thus reducing the probability of failure.

Reservoir pool restrictions and modification of reservoir regulation plan must always be included as an option that is addressed in the IRRMP.

If a reservoir restriction has been ruled out, very specific reasons should be included as to why.

Life Safety is Paramount

1. Reservoir Restrictions

Page 27: Interim Risk Reduction Measures

Lower the reservoir water level and maintain at a lower level.A – pool elevation with concern for safetyB - Intermediate pool to reduce “peaks” above seasonal pool

Reservoir “Restrictions”

Page 28: Interim Risk Reduction Measures

Structural IRRM typically improve the system response by reducing the probability of failure.

Structural IRRM generally require a physical modification to the dam or appurtenant structures.

Some structural IRRMs can be incorporated into long-term remedial measures.

2. Structural IRRM

Page 29: Interim Risk Reduction Measures

Target grouting program to slow seepage. Improve seepage collection system. Construct shallow cutoff trench to slow seepage. Construct downstream dike to reduce head

differential. Isolate problem area. Construct downstream seepage/stability berm.

Structural IRRM Examples for Seepage/Stability

Page 30: Interim Risk Reduction Measures

Bolivar Dam

Construction of Emergency Seepage Blanket

Page 31: Interim Risk Reduction Measures

Toe Drainage System Installation

Page 32: Interim Risk Reduction Measures

Non-structural IRRMs may include any short-term actions to reduce risk without physically modifying the dam or appurtenant structures.

Non-structural IRRMs, such as increased monitoring and surveillance and stockpiling materials, help to reduce the likelihood of failure by early detection and improve the ability to intervene should an incident occur.

Another example is testing EAP for better notification and evacuation, updated EAP inundation mapping, etc. All reduce the potential loss of life.

3. Non-Structural IRRMs

Page 33: Interim Risk Reduction Measures

Ridge

Grout Curtain

Spillway

Ravine

Dism

al Cr

eek

DamReservoir

Sinkholes

Expanded Surveillance Area

Nolin Dam

Page 34: Interim Risk Reduction Measures

Reservoir A

Reservoir B

Reservoir C

Reservoir D

System Operational Changes and Cross-Training of Regional Project Staff

Page 35: Interim Risk Reduction Measures

Review Clearing Limits – Ability to Detect

Nolin Dam

Page 36: Interim Risk Reduction Measures

Vegetation Removal

Lewisville Dam

Proctor Dam

Page 37: Interim Risk Reduction Measures

Surveillance and Monitoring

Provides potential for earlier detection of problem

Potentially allows more time to implement EAP and reduce consequences

Should be focused on failure modes

Do NOT just use existing monitoring schedule

Page 38: Interim Risk Reduction Measures

Instrumentation Review - Heightened Monitoring

Page 39: Interim Risk Reduction Measures

An adequate instrumentation and monitoring system is required by the Federal Guidelines for Dam Safety as well as by good engineering practice in order to:

Provide data to validate design assumptions

Provide information on the continuing behavior of the water control structure

Observe the performance of critical features

Advance the state-of-art of dam engineering

Monitoring Principles

Page 40: Interim Risk Reduction Measures

Focus the effort and cost of performance monitoring on those areas where failures are most likely to occur.

Some existing instrumentation and observation systems may be determined to be unnecessary or redundant.

Some additional instrumentation and observation systems may be required.

(after FERC Chapter 14, July 2005)

Monitoring Objectives

Page 41: Interim Risk Reduction Measures

Define future methods and frequency of measuring and/or observing critical parameters that would give early indications of adverse dam performance.

Establish performance limits related to specific failure mode(s) and/or loading condition(s).

Increase the awareness of field personnel for the performance expectations.

(after USBR Comprehensive Facility Review)

Monitoring Objectives

Page 42: Interim Risk Reduction Measures

Upper Portion of Solution Zone

Lower Portion of Solution Zone

Case History: Green River Lake Dike IRRMP

Page 43: Interim Risk Reduction Measures

-0.35

-0.30

-0.25

-0.20

-0.15

-0.10

-0.05

0.00

0.05-2+502+507+5012+5017+5022+50

Station (ft)

Cum

ulat

ive

Mov

emen

t (ft)

(- D

own

/ + U

p)

RM-4

Maximum Settlement = 3.5”(from 1981 to 2008)

Elevation Surveys

Page 44: Interim Risk Reduction Measures

Green River Dike, Cumulative Movement at RM-4 versus Pool Elevation

Record Pool (1979)

Spillw ay Crest 100-yr300-yr

PMF

Dam Crest

Winter Pool

Summer Pool 0.5-yr

1-yr

10-yr

-0.30

-0.25

-0.20

-0.15

-0.10

-0.05

0.00

0.051981 1983 1985 1987 1989 1991 1993 1995 1997 1999 2001 2003 2005 2007 2009 2011

Cum

ulat

ive

Mov

emen

t (ft)

660

670

680

690

700

710

720

730

Poo

l Ele

vatio

n (ft

)

Pool Triggering Elevation?

RM-4 Settlement

Pool

“Trigger” from Survey/Pool Data

Page 45: Interim Risk Reduction Measures

550

600

650

700

750

800

21+7

0

20+8

0

19+7

0

18+8

0

17+8

0

16+9

0

15+9

0

14+9

0

14+0

5

13+3

0

12+5

0

11+7

0

11+1

5

10+3

0

9+40

8+30

7+60

6+50

5+30

4+10

3+20

2+00

0+90

-0+3

0

-1+1

0

-2+0

0

-3+4

0

-4+6

0

-6+8

0

-9+6

0

Station along Dike Centerline

Ele

vatio

n (fe

et)

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

Gro

ut (c

ubic

feet

)

Cubic Feet of Grout Cement Cubic Feet of Grout Sand Cubic Feet of Grout Fly Ash

DC-1 DC-5

DC-6

(translated to centerline)

Bottom of Grout Hole

High Grout Takes

Dike Crest - EL 735

Spillw ay Pool - EL 713

Summer Pool - EL 675

Winter Pool - EL 664

Depth of Know n Weathering

Concrete Bulkhead

Solution Zone

Top of Rock

Highly Weathered Limestone

Top of Grout Hole

RM-4

Triggering Elevation?

“Linking” Geology and High Grout Take Data

Page 46: Interim Risk Reduction Measures

Resulting Surveillance Strategy

Page 47: Interim Risk Reduction Measures

Update EAP

Page 48: Interim Risk Reduction Measures

EAP Hardcopy Map Format(1965-2009)

Page 49: Interim Risk Reduction Measures

Map Sheet – Street Map Series

Page 50: Interim Risk Reduction Measures

Coarse Aggregate

Fine Aggregate

Pre-Position Material Stockpiles

Page 51: Interim Risk Reduction Measures

IRRM Example: StockpilingProctor Dam

Page 52: Interim Risk Reduction Measures

Perform Preventative Maintenance on Instrumentation

Page 53: Interim Risk Reduction Measures

Review Downstream Access for Potential Heroic Measures

Page 54: Interim Risk Reduction Measures

Provide Open/Transparent Communication

Page 55: Interim Risk Reduction Measures

Project-specific potential failure modes Emergency indicators Notification and reporting procedures Temporary controls Long-term studies, investigations, and

possible remedial measures Risk Communication Plan

Train Field Personnel in:

Page 56: Interim Risk Reduction Measures

Level of Exercise Should be Based on DSAC Rating• Functional• Table Top• Contact Call Out

Conduct Emergency Exercises

Page 57: Interim Risk Reduction Measures

57

USACE Guidelines to Conduct Emergency Exercises

Exercises* Classifications

Drill Tabletop Functional Exercise

Full Scale Exercise

DSAC I and High Hazard Potential

Year 1, 3, 5, etc….

Year 2, 4, 6, etc….

At DSO discretion

DSAC II or III and High Hazard Potential

Year 1, 3, 5, etc…

Year 2, 4, 6, etc

At DSO discretion

At DSO discretion

DSAC IV or V Significant Hazard Potential

Year 1 – 4 and 6 - 9. etc….

Year 5, 10, etc…

At DSO discretion

At DSO discretion

Low Hazard Potential At DSO discretion

Page 58: Interim Risk Reduction Measures

Consider Early Warning Systems

Page 59: Interim Risk Reduction Measures

Contrasting IRRMs with Permanent Measures

IRRMs should not induce additional risks beyond existing conditions.

IRRMs should be timely (implemented within ≤ 6 months).

Some IRRMs may become permanent based on IES or DSMS recommendations.

IRRMs are funded from the O&M account and subject to dollar limitations described in Major Rehab guidance.

Page 60: Interim Risk Reduction Measures

               

               

Biweekly Status of IRRM Implementation for Approved Plans

Interim Risk Reduction Measures Plansxxx District Dams

As of 24 November 2011

               

Completed: Incomplete:

               

Click on Tabs at Bottom of Screen for Interim Risk Reduction Measures for Each Dam listed below:

    Project Name Funding for full IRRM Implementation      

    Project A$250K

    Project B$600K

    Project C$275K

    Project D$1.3M

    Project E$530K

    Project F$965K

    Project G$313K

    Project H$320K

    Project I$690K

    Project J$990K

    Project K$600K

    Project L$110K

    Project M$1.2M

             

Red text indicates new information.

               

IRRM Tracking

Excel Spreadsheet developed by Fort Worth District is considered a Best Practice example.

Page 61: Interim Risk Reduction Measures

Completed: Incomplete:

Project A

DSAC: III PM: Secondary POC:

SPRA: 11 Jul 05 Office Phone: Office Phone:

IRRMP Approval Date: 10 Jun 11 Cell: Cell Phone:

Communication Plan Approval Date: 10 Jun 11

PFMA: Not scheduled at this time.

IES: Not scheduled at this time.

Interim Risk Reduction Measure Status Recommendation Scheduled/Completed Action Taken Cost Remarks

Reason Not Fully Implemented

Stockpiling Emergency Materials  

Emergency flood fighting materials such as gravel, sand, geotextile, and riprap should be stockpiled in areas that are fully accessible in a high water event. Potential failure modes related to seepage can progressively erode soil from embankment or is foundation resulting in rapid failure of the dam.

FY13 Waiting on quotes from DLA for materials. $150K   Funding and Resources

Update Surveillance and Monitoring Schedule

 

There are long-established inspection thresholds for different pool elevations. Based on the results of the IES, there may be changes to these thresholds if required.  

FY11Some interim changes are being incorporated at this time. 

$25K    

Communication Plan Implementation

Date Visit/Meeting Notes/Highlights/Issues

4-Nov-11 Congressional Visit PPMD and Operations personnel met with represenatives from Congressman's office to discuss the project, DSAC III Dams, and the USACE Dam Safety Program.

     

               

Page 62: Interim Risk Reduction Measures

Is an interim reduction measures plan (IRRMP) required? (25 points)

Has an IRRMP been prepared AND approved? (9 points)

Has an approved IRRMP been fully implemented and regularly updated (according to the approved IRRMP schedule)? (10 points)

Have all required items in IRRMP been completed? (6 points)

IRRMP in Scorecard

Page 63: Interim Risk Reduction Measures

IRRMs are short-term measures taken to reduce the risk of catastrophic failure to the maximum extent reasonably practical until permanent repairs can be made, or investigations determine that a potential failure mode is not probable.

Focus the effort and cost of IRRMs on “risk-driver” potential failure modes.

Summary

Page 64: Interim Risk Reduction Measures

Pool restrictions and modification of the WCP must be considered for DSAC I, II, or III dams.

Structural IRRMs can be incorporated into long-term repairs.

With any IRRMP, the level of detail should be proportionate with the dam’s overall risk.

Summary

Page 65: Interim Risk Reduction Measures

Non-structural IRRMs can help to reduce the likelihood of failure by early detection and improve the ability to intervene should an incident occur, and they are cost-effective.

Communication with internal and external stakeholders and the public is essential to establish trust and coordinate proper assessment and support.

Summary

Page 66: Interim Risk Reduction Measures

Thank You!Muito Obrigado!

First USACE Dam Safety Workshop