Upload
rose-carter
View
214
Download
0
Embed Size (px)
Citation preview
Interconnector Under Test
Update to TSC Modifications Committee
5th December 2012
Background
• Mod 10 11 raised on 22nd March 2011• Testing Tariffs to apply for Commissioning, Grid Code Compliance or
otherwise
• Meeting 35 • Deferred pending a SEMO Impact Assessment
• Meeting 36 • 3 Options presented• Option 1 was Recommended for Approval
• RA Approval – Letter issued 21st July 2011
Mod 10 11 Implementation Options
FRR dated 28 June 2011 set out the implementation options:
• Option 1 - Market require a facility to designate an Interconnector as Under Test in settlement for a range of trading dates.
• Option 2 - Restriction for submitting bids (definition for a range of testing dates in MPI)
• Option 3 –Inclusion of an Interconnector Unit test profile. This relates to an agreed testing profile between the IA and the SO.
SEMO Assessment SummaryOption Description Incremental
CostTotal Cost
1 Application of Testing Charges to I/C for a range of dates
€59.2k €59.2k
2 Restriction for submitting bids (definition for a range of testing dates in MPI)
€205k €264.2k
3 Inclusion of Testing Profile in Instruction Profiler
€309.3k €573.5k
Modifications Committee Views
• The Committee agreed that Option 1 should be pursued due to the timelines for Intraday Release and EWIC deployment.
• A full solution including Options 1, 2 and 3 was preferable due to uninstructed imbalances arising while under test and restricted bidding.
• In the FRR, the SOs stated that a Modification to Appendix E would be required for Option 3 to be implemented and the SOs would consider raising this Modification in due course.
Mod 10 11 Implementation
• Mod 10 11 (Option 1) implementation date in the CMS was November 2012 release
• Mod 33 11 allowed SEMO to perform workaround to manually apply the Testing Tariffs as per Option 1 from the date of EWIC Commissioning (i.e. July 2012)
• The T&SC was updated to allow Interconnectors Under Test with an effective date for July 2012.
Issues with Option 1
• Not appropriate for Operational Interconnectors– i.e. Not suitable for Interconnector which goes on/off test
• No ability to block bids and offers – Interconnector participants can submit bids/offers even if Interconnector is
under test
• No provision available for test profiles– RA approval required to set DOG and PUG to zero as Interconnector would
be unfairly penalised
Cost of Options 2 and 3 to implement– New vendor quote received for revised design for Options 2 and 3 is now
€307k compared with €504k– Investigated alternate approach
TSOs Recommendation
• Set ATC to zero when an Interconnector is testing – IUN/MIUNs will be zero for Interconnector Users and their bids will not be
taken into consideration – DOG and PUG will need to be set to zero on an annual basis i.e. TSOs will
recommend through annual consultation process for RA approval– Can be implemented immediately
• No further modification to the T&SC is therefore recommended in respect of Interconnector Under Test
• Thank You