Upload
victoria-cooley
View
52
Download
2
Tags:
Embed Size (px)
DESCRIPTION
Interaction Region Vacuum Chamber Upgrades. Presented by: Scott DeBarger Contributors: D. Arnett, B. Bigornia, C. Carr, J. Langton, S. Metcalfe, D. Kharahk, M. Kosovsky, N. Kurita, R. Pope, N. Reeck, A. Sheng, B. Smith. Outline. Forward Q2 Chamber Q1/Q2 HOM Bellows - PowerPoint PPT Presentation
Citation preview
Interaction RegionInteraction RegionVacuum Chamber UpgradesVacuum Chamber Upgrades
Presented by: Scott DeBarger
Contributors: D. Arnett, B. Bigornia, C. Carr,J. Langton, S. Metcalfe, D. Kharahk, M. Kosovsky,
N. Kurita, R. Pope, N. Reeck, A. Sheng, B. Smith
Interaction Region Vacuum Chamber Upgrades p.2 of 25
OutlineOutline
Forward Q2 Chamber
Q1/Q2 HOM Bellows
HER Q4 & Q5 Vacuum Chambers; HOM Absorbing Bellows
LER Q4 R Temporary Chamber
LER Q4 & Q5 Vacuum Chambers
DS-7 Transition
LER 2062 Chamber
LER 2143 Collimator
Interaction Region HOM Absorbers
Additional Diagnostics
HOM Straight Bellows
Interaction Region Vacuum Chamber Upgrades p.3 of 25
Replaced Q2R with a Q2L chamber in 2002 Improve Beam Stay-Clear and reduce HOM
generation (see mask at right) Chamber failed (following operation) due to
material flaw in the GlidCop
Original Q2R chamber reinstalled in 2003 Does not maintain Beam Stay-Clear No evidence that it creates increased HOMs
New Q2R installed March 2006 Opportunistic installation in conjunction with
Q1/Q2 bellows seal Still no effect on HOM generation observed
Forward Q2 ChamberForward Q2 Chamber
Interaction Region Vacuum Chamber Upgrades p.4 of 25
Identified as a critical upgrade at previous review Technically very challenging
Limited space available Anticipated high power loads
Design compromises travel during installation to accommodate new HOM absorption arrangement
61 mm maximum tile/slot length Absorbing tiles are open to the convolutions
No additional tile set needed in bellows cavity HER Arc Bellows features
Spring, Stub, RF shield (See M. Sullivan talk)
Q1/Q2 HOM BellowsQ1/Q2 HOM Bellows
Interaction Region Vacuum Chamber Upgrades p.5 of 25
Q1/Q2 HOM BellowsQ1/Q2 HOM Bellows
RF Seals replaced 22 February 2006(see M. Sullivan talk)
Installed design
New stub in fabrication
•Materials in hand (AlN-SiC tiles, GlidCop, bellows)•Working aggressively to complete new bellows modules•Hope to install during current shutdown
Interaction Region Vacuum Chamber Upgrades p.6 of 25
HER Q4 & Q5 ChambersHER Q4 & Q5 Chambers
HER Q5 & Q4 Chambers General issues
Mechanical & HOM failures in the NEG screens
Beam Stay-Clear (BSC) & Luminosity cone restrictions
Thermal motion of magnets Original Q4 & Q5 are rigid chambers that have minimal to no clearance to their respective
magnets
Global alignment errors between the 10-meter Collimator and Q5 L and between Q5 R and High Power Dump.
History of mask and flange failures due to SR heating
NEG heating during high current operation
Interaction Region Vacuum Chamber Upgrades p.7 of 25
Design goals (achieved) LER: 4.5A, HER 2.2 A operation Respect the defined BSC/Luminosity cone and
existing magnet envelopes. Maintained a 2mm gap to poles and a 3mm gap
to coils
Reduce operating thermal gradients Improve kinematics and stabilize BPMs
Added a bellows between Q4, Q5 Added a flex flange between Q2L & Q4L Replaced beampipe supports
Decrease the RF leakage to the pumps Screen hole diameter reduced to
3 mm and depth increased to 6mm
HER Q4 & Q5 ChambersHER Q4 & Q5 Chambers
Q5 NEG RF Screen
Interaction Region Vacuum Chamber Upgrades p.8 of 25
HER Q4 & Q5 ChambersHER Q4 & Q5 Chambers
HER Q5 L Chamber Installed Fall 2005
HER Q4 & Q5 R and HER Q4 L Chambers
Installed beginning in August 2006
Installation revealed vertical misalignment of ~9 mm at HER High Power Dump (corrected)
Q5 L installation
Aluminum clamshell design Profile matched to available space
Excellent assembly distortion control Straightness in y-z (vertical) plane = +/- .030”
Straightness in x-z (horizontal) plane = +/- .011”
End to end roll = 9 mRad
Interaction Region Vacuum Chamber Upgrades p.9 of 25
Performance of Q5 L ChamberPerformance of Q5 L Chamber
HER Q5 L Installed Fall 2005
Beam induced heating of NEG dramatically reduced
HER Current (Mar 05-Aug 06)
Temperature of Q5 L NEG (Mar 05-Aug 06)
Interaction Region Vacuum Chamber Upgrades p.10 of 25
Q4 side, 10” Q4 side, 10” flangeflange
Q5 side 12” flangeQ5 side 12” flange
GlidCop GlidCop StubStub
Inconel Spring Inconel Spring FingerFinger
GlidCop RFGlidCop RF
Shield FingerShield Finger
Welded Welded BellowsBellows
Cooling – not shownCooling – not shown
Absorbing TileAbsorbing Tile
Mechanically decouples Q4 & Q5 vacuum chambers
Absorbing tiles above and below beam orbit
Q4/Q5 Bellows with AbsorberQ4/Q5 Bellows with Absorber
Interaction Region Vacuum Chamber Upgrades p.11 of 25
LER Q4 Right Temporary ChamberLER Q4 Right Temporary Chamber
LER Q4 R chamber replaced by a straight drift tube on22 February 2006
Concern that the chamber outgassing and/or sparking caused beam aborts (found to be not true).
Interaction Region Vacuum Chamber Upgrades p.12 of 25
LER Q4 & Q5 ChambersLER Q4 & Q5 Chambers
Two major issues addressed in redesign Beam induced NEG heating
(leading to NEG outgassing) Thermal motion of the Q2,4,5 raft/magnets
New design for LER Q4 & Q5 Improved RF screens Added “Flex Flange” at chamber inboard ends Improved mask cooling; also additional cooling
added
Old Screen New Screen
“Flex Flange” detail
Interaction Region Vacuum Chamber Upgrades p.13 of 25
LER Q4 & Q5 ChambersLER Q4 & Q5 Chambers
Status Chamber fabrication and assembly complete
Q4 vacuum processing complete; Q5 chambers are on bake
Ready to begin installation of Q4 when project engineer returns on 26 October
“Flex Flange”prior to final assembly
Interaction Region Vacuum Chamber Upgrades p.14 of 25
LER Q4 & Q5 ChambersLER Q4 & Q5 Chambers
Status Chamber fabrication and assembly complete.
Q4 vacuum processing complete; Q5 chambers are on bake.
Ready to begin installation of Q4 when project engineer returns on 26 October
Interaction Region Vacuum Chamber Upgrades p.15 of 25
DS-7 Octagonal-to-Round TransitionDS-7 Octagonal-to-Round Transition
Chamber absorbs a large amount of LER SR originating near the IP(1.2 kW @ 4.5 A, 3.1 GeV)
Previous DS-7 chamber not well cooled New chamber incorporates GlidCop body and
improved cooling Installed Nov 2005
Interaction Region Vacuum Chamber Upgrades p.16 of 25
LER 2062 ChamberLER 2062 Chamber
Vacuum leak developed on 10 Dec 2005 - sealed temporarily.
LER 2062 chamber replaced1 May 2006
Buttons in nearby chambers fell on 2 & 5 May, prompting effort to remove LER Collimator
Repaired chamber reinstalled on 16 May 2006
2062 chamber
Interaction Region Vacuum Chamber Upgrades p.17 of 25
LER 2143 CollimatorLER 2143 Collimator
LER 2143 Collimator removed 16 May 2006 Intended to control backgrounds in BaBar
HOM generator affecting downstream LER
Damage to the collimating surface being evaluated
Interaction Region Vacuum Chamber Upgrades p.18 of 25
Interaction Region HOM AbsorbersInteraction Region HOM Absorbers
High current running prompts a desire to manage HOM heating in the LER
Two HOM absorbing chambers to be added to the LER (3044 & 1153)
RF Shield 3.5 mm slots in 2.5 mm thick GlidCop
Uses Ceralloy 13740Y (Aln-SiC) tilesMatches existing LER Octagonal cross section
Install November 2006
Absorption (calculated by S. Novokhatski, S. Weathersby):Monopole – 0.0027%Dipole – 54%Other Dipole – 88%Quadrupole – 89%
Design selected for high absorption over a broad frequency rangeAll absorption curves relatively flat – no major spikes or troughs
Interaction Region Vacuum Chamber Upgrades p.19 of 25
Interaction Region HOM Absorber (1153)Interaction Region HOM Absorber (1153)
HOM Absorber
Octagonal to LER Arc Transition (New)
Elliptical to Octagon Transition
Octagonal Bellows
e+
Octagonal to Elliptical Mask (New)
Elliptical VAT Valve (reinstalled)
Improved masking at 1153 location
Interaction Region Vacuum Chamber Upgrades p.20 of 25
Additional DiagnosticsAdditional Diagnostics
Vacuum gauges added 9 additional hot filament gauges distributed through the
Interaction Region
These gauges are less sensitive to non-vacuum beam effects
Interaction Region Vacuum Chamber Upgrades p.21 of 25
Additional DiagnosticsAdditional Diagnostics
Fast(er) data sampling SLAC standard history buffers store at 6 minute intervals
Data Archiver stores specified channels at 1 second intervals
Interaction Region Vacuum Chamber Upgrades p.22 of 25
Additional DiagnosticsAdditional Diagnostics
(Really Fast) Abort Logger Multiple channels sampled
@1kHz for 10 seconds surrounding a beam abort
To date, only in place in IR-2; all other IRs added this downtime
Digital Video Recorder, Rotating Mirror, …
Interaction Region Vacuum Chamber Upgrades p.23 of 25
Goal – to create a HOM absorber in a defined modular space
HOM absorber will damp and absorb the power, preventing neighboring components from absorbing excessive HOM power
Design optimized with MAFIA simulations
Installed one unit on 1 May 2006
Three additional units deployed in Oct 2006
HOM Straight BellowsHOM Straight Bellows
Interaction Region Vacuum Chamber Upgrades p.24 of 25
Modes that leak past the RF shield finger still see the absorber
HOM Straight BellowsHOM Straight Bellows
Measurements confirm that the straight bellows-absorber in Region damped 40% of the available HOM power
Very good agreement with calculated performance of a 7cm length absorber
Interaction Region Vacuum Chamber Upgrades p.25 of 25
SummarySummary
The Interaction Region Vacuum System is receiving a major reworking in 2006
Principal efforts are centered around high current running
Management of synchrotron radiation and higher order mode heating has been addressed
Diagnostic capabilities have been developed and implemented to improve our abilities to understand future problems should they arise
We feel that the Interaction Region vacuum system will be ready to meet the demands of planned PEP-II operations