Upload
donhu
View
215
Download
0
Embed Size (px)
Citation preview
||
Spyros Chatzivasileiadis, Thilo Krause, Göran Andersson
Power Systems Laboratory, ETH Zurich
09.09.2013Spyros Chatzivasileiadis 1
Interaction between AC and DC PowerSystems: the Need for Controllability
||
§ Aging power systeminfrastructure
§ Increased shares of RES*integration
§ Massive cross-border flows dueto electricity trade
09.09.2013Spyros Chatzivasileiadis 2
Challenges
*RES: Renewable Energy Sources
Need for investments in powersystem infrastructure
||
§ Infrastructure Roadmap for the Energy Networks inEurope for the next 40 years
www.irene-40.eu
§ Partners:
§ 5 European Universities:RWTH Aachen, Imperial College, Delft, NTUA, ETH Zurich
§ ABB, Siemens, Alstom, Energy Center of the Netherlands
3
IRENE-40 European Project
09.09.2013Spyros Chatzivasileiadis
|| 4
IRENE-40
§ Identify expansion measureswith respect to:
§ Sustainability à more RES
§ Security
§ Competitiveness à efficientmarket operation
§ Possible Options:§ AC Lines, FACTS devices, HVDC lines, regulatory measures, etc.
09.09.2013Spyros Chatzivasileiadis
||
Which technology improves security and reduces costs?
09.09.2013Spyros Chatzivasileiadis 5
Objective
§ Run Simulations and Compare Results w.r.t.:
§ Network Utilisation
§ Cost of Operation (Generation Dispatch)
§ Cost of Security
||
Some findings from theory and practice:
§ Practice: Application Survey§ Which technology tackles better which problem?§ Findings based on state-of-the-art current practice/expert
knowledge
§ Theory: AC expansion§ Take advantage of the power system properties§ Use the Kirchhoff laws§ Extract “universal truths”
09.09.2013Spyros Chatzivasileiadis 6
But first…
|| 09.09.2013Spyros Chatzivasileiadis 7
§ Practice: Application Survey§ Theory: AC Expansion
§ Case Study
§ Expansion Options for the European System
§ Cost of Operation
§ Cost of Security
§ Comparison of AC+FACTS and DC Options
§ RES curtailment
§ Concepts for the Future
Outline
||
§ Ranking is not straightforward. Each technology performsbetter for certain problems, while it tackles not so well, oreven aggravates, other problems.
09.09.2013Spyros Chatzivasileiadis 8
“Technology Ranking” w.r.t. Security
In general, addition of newlines is the most effectivemeasure for increased powersystem security
§ FACTS contribute significantly inspecific problems
HVDC
AC-400kV
AC-750kV
|| 09.09.2013Spyros Chatzivasileiadis 9
§ Practice: Application Survey
§ Theory: AC Expansion§ Case Study
§ Expansion Options for the European System
§ Cost of Operation
§ Cost of Security
§ Comparison of AC+FACTS and DC Options
§ RES curtailment
§ Concepts for the Future
Outline
|| 09.09.2013Spyros Chatzivasileiadis 10
Supergrid or Local Network Reinforcements?
© IFHT© IFHT
10°W
0°10°E 20°E
30° E
40°N
50°N
60°N
70°N
source: irene-40.eu (RWTH Aachen)
LocalReinforcementsSupergrid
|| 09.09.2013Spyros Chatzivasileiadis 11
AC or HVDC ?
HVDCAC-400kV
AC-750kV
|| 09.09.2013Spyros Chatzivasileiadis 12
|| 09.09.2013Spyros Chatzivasileiadis 13
Assumptions
NTC (INTC) is determineddue to congestions inthe internal network
#2The bottleneck is not inthe interconnection
Internal Networkmore meshed thanthe Interconnection
per unit length#1
||
§ Adding the “same” line as: internal reinforcement, overlayline, and interconnecting line
09.09.2013Spyros Chatzivasileiadis 14
Zint
Znew,int
Zext Zext
Znew,ext
ZintZext
Znew,ext
Zint
Zint
,≤
+, + ,
≤,
≤
Flow through theoverlay line
Flow through the line parallelto the interconnection
Zint Zext
Internal Network Interconnection
A BC
Flow through theinternal reinforcement
A C B A C B A C B
≤
= ∙
||
Assumptions:§ Weakly interconnected meshed networks§ Bottlenecks are inside the networks (not on interconnections)
Findings:§ Overlay networks are preferable: they carry more power
for the same line-kilometers compared to localreinforcements
§ Upper bounds for AC overlay networks:§ One additional cross-border AC-400 kV:
Total NTC cannot increase more than twice§ One additional cross-border AC-750 kV:
Upper bound for total transfer capacity is 2.6*NTC09.09.2013Spyros Chatzivasileiadis 15
Main Findings
|| 09.09.2013Spyros Chatzivasileiadis 16
§ Practice: Application Survey
§ Theory: AC Expansion§ Case Study
§ Expansion Options for the European System
§ Cost of Operation
§ Cost of Security
§ Comparison of AC+FACTS and DC Options
§ RES curtailment
§ Concepts for the Future
Outline
|| 09.09.2013Spyros Chatzivasileiadis 17
Case Study: Maximum Power Transfer from Bus #222
1. Set bus #222 as slack bus
2. Increase active powerconsumption at Bus #123 insteps of 50 MW
3. Run DC Power Flow
4. Calculate the sum of the power flows over theinterconnections
5. If no congestion in the internal network of Area 2, go toStep 1
|| 09.09.2013Spyros Chatzivasileiadis 18
IEEE RTS-96 Two Area System Bus 222: Graduallyincreasing thepower injection
Bus 123: Graduallyincreasing the
power consumption
Maximum PowerTransfer
|| 09.09.2013Spyros Chatzivasileiadis 19
IEEE RTS-96 Two Area System Bus 222: Graduallyincreasing thepower injection
Calculatingthe sum of the powertransferred to Area 1
Bus 123: Graduallyincreasing the
power consumption
Congestionappears
|| 09.09.2013Spyros Chatzivasileiadis 20
IEEE RTS-96 Two Area System Bus 222:Increasing thepower injection
Calculatingthe sum of the powertransferred to Area 1
Bus 123: Increasingthe power
consumption
|| 09.09.2013Spyros Chatzivasileiadis 21
Overlay vs. Local ReinforcementsOne existing interconnection (230 kV)
|| 09.09.2013Spyros Chatzivasileiadis 22
Overlay vs. Local ReinforcementsTwo existing interconnections (230 kV & 138 kV)
|| 09.09.2013Spyros Chatzivasileiadis 23
Overlay vs. Local ReinforcementsThree existing interconnections (2 x 230 kV & 138 kV)
|| 09.09.2013Spyros Chatzivasileiadis 24
Maximum Power Transfer from bus #222All additional lines on the same voltage level
0
200
400
600
800
1000
1200
1400
1600
1800
1 line 2 lines 3 lines
Max
imum
Pow
erTr
ansf
er(M
W)
Number of Existing Interconnections
No expansionLocal Reinforc.Overlay
|| 09.09.2013Spyros Chatzivasileiadis 25
Maximum Power Transfer from bus #222Overlay network on higher voltage level
0
500
1000
1500
2000
2500
3000
3500
1 line 2 lines 3 linesMax
imum
Pow
erTr
ansf
er(M
W)
Number of Existing Interconnections
No expansionLocal Reinforc.OverlayOverlay higher volt.
|| 09.09.2013Spyros Chatzivasileiadis 26
Upper bound on utilization of AC overlay lines
≤ =
Compareline loadings
||
§ Additional Remark: with increasing level of interconnections,the utilization of the AC overlay lines decreases
need for controllable power flows09.09.2013Spyros Chatzivasileiadis 27
Upper bound on utilization of AC overlay lines
0
100
200
300
400
500
600
700
1 line 2 lines 3 lines
Line
Load
ing
(MW
)
Number of Existing Interconnections
Overlay
InterconnectingLine
||
European System
09.09.2013Spyros Chatzivasileiadis 28
§ Single-node per country;real network data(ENTSO-E)
§ Generation Scenario:80% RES in 2050
§ Addition of 19 new AC orHVDC lines
||
0%
20%
40%
60%
80%
100%
120%
AT-DE AT-HU FR-ES FR-CH DE-NL DE-PL DE-CH IT-SI RO-RS
Line
Load
ing
Maximum Utilization of New Lines for DifferentExpansion Options AC-400 kV
AC-750 kVHVDC
Highly Meshed Underlying Grids do not allow highutilization of Overlay AC Networks without FACTS
09.09.2013Spyros Chatzivasileiadis 29
||
§ Analytically shown:For weakly interconnected meshed power systems,overlay networks are preferable.
§ Derived an upper bound on utilization of overlay AC lines(over weakly interconnected meshed power systems)
§ Controllable power flows are necessary over meshedpower systems§ Higher utilization of the installed lines
09.09.2013Spyros Chatzivasileiadis 30
Wrap-up
|| 09.09.2013Spyros Chatzivasileiadis 31
§ Practice: Application Survey
§ Theory: AC Expansion
§ Case Study
§ Expansion Options for the European System§ Cost of Operation§ Cost of Security§ Comparison of AC+FACTS and DC Options§ RES curtailment
§ Concepts for the Future
Outline
||
§ Model based on:Optimal Power Flow (OPF)
andSecurity-Constrained Optimal Power Flow
(SC-OPF)
§ We emulate network and market operations
The SC-OPF takes into account thepost-contingency control capabilitiesof the HVDC lines(Chatzivasileiadis et al., SEPOPE 2012)
Modeling Framework (in brief)
09.09.2013Spyros Chatzivasileiadis 32
||
Generation Scenarios 2050compiled from ECN
EFF-iciencyBAU
CCS DES-ertec RES
“Robust Choices”: Scenarios cover a broad spectrum offuture possible G&D developments
Fina
lEle
ctric
ityD
eman
d(T
wh/
year
)
RES Share (%)
09.09.2013Spyros Chatzivasileiadis 33
||
Three expansion options for 2050 (all for overlay grids):
Long AC-400 kV/3000 MVA with fixed seriescompensation
Long AC-750 kV/3900 MVA with fixed seriescompensation
VSC-HVDC lines 3000 MVA
Note: For all expansion options, the submarine expansionswere always VSC-HVDC cables (9-10 lines in eachgeneration scenario)
09.09.2013Spyros Chatzivasileiadis 34
Expansion Methodology
HVAC
UHVAC
HVDC
||
Cost of Operation (RES 2050)HVAC-400kV
10 AC lines + 9 submarine HVDCs
Generation Cost= 95.3 billion Euros
UHVAC-750kV10 AC lines + 9 submarine HVDCs
Generation Cost= 94.0 billion Euros
HVDC19 HVDC lines
Generation Cost= 88.7 billion Euros
Reduction= 10.3% Reduction= 11.5% Reduction= 16.5%
Minimum Expansion: Generation Cost = 106.31 billion Euros09.09.2013Spyros Chatzivasileiadis 35
|| 09.09.2013Spyros Chatzivasileiadis 36
Operating Cost Reduction of Expansion Options
§ HVDC expansion leads to the lowest Cost of Operation§ Controllability (= FACTS) is necessary in the AC Expansion in
order to be as cost-effective as HVDC
0%
5%
10%
15%
20%
25%
BAU 2050 CCS 2050 EFF 2050 RES 2050 DES 2050
AC 400 kVAC 750 kVHVDC
|| 09.09.2013Spyros Chatzivasileiadis 37
§ Practice: Application Survey§ Theory: AC Expansion
§ Case Study
§ Expansion Options for the European System§ Cost of Operation
§ Cost of Security§ Comparison of AC+FACTS and DC Options
§ RES curtailment
§ Concepts for the Future
Outline
||
§ The “Cost of Security” represents the additionalgeneration dispatch costs, in order to satisfy the N-1criterion.
§ Equivalent to “Redispatch Costs”
§ Goal: find the lowest “Cost of Security”
09.09.2013Spyros Chatzivasileiadis 38
Cost of Security
||
§ HVDC expansion leads to the lowest Cost of Security formost scenarios (~1-2 billion Euros/year less than AC)
09.09.2013Spyros Chatzivasileiadis 39
Cost of Security
§ CCS is anexception
CoS: from 1 to 7 billion Euros/year
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
BAU 2050 CCS 2050 EFF 2050 RES 2050 DES 2050
Billi
ons
ofEu
ros
Cost of SecurityAC 400 kVAC 750 kVHVDC
||
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
CSS 2050 - 85% Loading CCS 2050 - same #contg.
Billi
onso
fEur
os
AC 400 kV
AC 750 kV
HVDC
09.09.2013Spyros Chatzivasileiadis 40
Cost of Security
CCS-2050: All expansions with the samecontingencies in the SC-OPF
|| 09.09.2013Spyros Chatzivasileiadis 41
HVDC with and without Post-Contingency Control (PCC)
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
4.50
AC-400 kV AC-750 kV HVDC - no PCC HVDC
Billi
ons
ofEu
ros
Cost of Security (RES 2050)
HVDCno
PCC
HVDCwithPCC
AC750kV
AC400kV
Post-Contingency Control from HVDC lines results inadditional savings of 1 billion Euros per year
||
% of SnapshotsAC-400 kV 0.0 %AC-750 kV 0.2 %HVDC - no PCC 2.1 %HVDC – with PCC 3.7 %
09.09.2013Spyros Chatzivasileiadis 42
Snapshots with Zero Cost of Security
|| 09.09.2013Spyros Chatzivasileiadis 43
§ Practice: Application Survey§ Theory: AC Expansion
§ Case Study
§ Expansion Options for the European System§ Cost of Operation
§ Cost of Security
§ Comparison of AC+FACTS and DC Options§ RES curtailment
§ Concepts for the Future
Outline
||
0%
1%
2%
3%
4%
5%
6%
7%
UHVAC (750 kV)
WithPSTsand
SVCs;
andFixedSeriesComp.
FixedSeriesComp.
0%
1%
2%
3%
4%
5%
6%
7%
HVDC
MeshedDC grid
DC gridpoint-
to-point
FACTS lead tosignificant cost savings
Radial DC Networksslightly more effective
(but higher installation costs)
Cost Savings: AC+FACTS and DC Options
09.09.2013Spyros Chatzivasileiadis 44
|| 09.09.2013Spyros Chatzivasileiadis 45
§ Practice: Application Survey§ Theory: AC Expansion
§ Case Study
§ Expansion Options for the European System§ Cost of Operation
§ Cost of Security
§ Comparison of AC+FACTS and DC Options
§ RES curtailment§ Concepts for the Future
Outline
|| 46
Ecological Impact –Reduction of Network Congestions (RWTH Aachen)
FACTSHVAC++FACTS
HVDC
UHVACFACTS
HVAC+RES curtailment
HVAC+
09.09.2013Spyros Chatzivasileiadis
|| 47
Ecological Impact –Reduction of Network Congestions (RWTH Aachen)
FACTSHVAC++FACTS
HVDC
UHVACFACTS
HVAC+RES curtailment
HVAC+
09.09.2013Spyros Chatzivasileiadis
Network development is highly necessary to reach CO2reduction targets, especially in case of a high penetration of
renewables
||
§ Upgrade with HVDC is the preferable infrastructure scenariocharacterized byØ reduced RES curtailmentØ lowest cost for security (SC-OPF) AND operation (OPF)
§ Overlay networks are preferable
§ Need for increased controllability is identified in all scenarios i.e.AC+FACTS or HVDC flows
§ Post-contingency control capabilities of HVDC can result insignificant cost savings of redispatching costsNovel operation schemes and control algorithms are necessary.
09.09.2013Spyros Chatzivasileiadis 48
Conclusions
|| 09.09.2013Spyros Chatzivasileiadis 49
§ Practice: Application Survey§ Theory: AC Expansion
§ Case Study
§ Expansion Options for the European System
§ Cost of Operation
§ Cost of Security
§ Comparison of AC+FACTS and DC Options
§ RES curtailment
§ Concepts for the Future
Outline
||
§ Decouple “completely”the Market Operationsfrom the SecurityConsiderations
§ Proof for maximumnumber of controllablelines in a system:
09.09.2013Spyros Chatzivasileiadis 50
Towards a Fully Controllable Power System
SCH, TK, GA, IEEE PES GM 2011
Cost of Security
14 Lines10 Buses
= 5 Max Ctrl Lines
|| 51
The Global Grid
Long transmission lines toharvest remote RES
and connect regional Supergridsin one “Global Grid”
LowLoad
HighWind
HighLoad
Time difference: Transferexcess energy to where it ismostly needed
09.09.2013Spyros Chatzivasileiadis
• Emerging Opportunitiese.g., less storage,
less peak power plants
S.Chatzivasileiadis, D. Ernst, G. Andersson,The Global Grid,
Renewable Energy, vol.57, p. 372-383, 2013
Appendix
||
§ Several studies for a 100% Renewable Energy Future
All these studies suggest the need formore transmission lines:
§ Interconnecting RES increases reliability in supply
§ Long transmission lines can harvest abundant renewablepotential in remote areas
09.09.2013Spyros Chatzivasileiadis 54
|| 09.09.2013Spyros Chatzivasileiadis 55
Cheap RES production over long transmissionlines and Supergrids
Desertec
North-Sea Grid
Gobitec«Google» Project
|| 09.09.2013Spyros Chatzivasileiadis 56
The Global Grid
|| 09.09.2013Spyros Chatzivasileiadis 57
|| 09.09.2013Spyros Chatzivasileiadis 58
Telegraph 1866-1901
1866: First successful submarine cable
1901: Global Telegraphy Network
|| 09.09.2013Spyros Chatzivasileiadis 59
Wind Farm in Greenland
Quebec City
New York City
London
North UK
Faroe IslandsIceland
§ Sell wind power always at peak prices§ Trade electricity with the remaining line capacity
387 km (OHL)
550 km
|| 09.09.2013Spyros Chatzivasileiadis 60
Smoothing out electricitysupply and demand
Load
Load
Wind
||
§ Oportoà New York : 5334 km
§ 5’500 km , 3 GW submarine cable§ Low Cost: $0.023 per delivered kWh§ High Cost: $0.035 per delivered kWh
§ RES Cost in 2020*§ below $0.04 up to $0.13 per delivered KWh
§ Conventional plant cost in 2020 in the US*§ $0.08/kWh, with the social costs: $0.14/kWh
§ Except for the most expensive RES generators, it is moreeconomical for the US to import RES power from Europethat operate its own conventional power plants
09.09.2013Spyros Chatzivasileiadis 61
§ Oportoà Halifax : 4338 km
*Delucchi and Jacobson, 2010
||
§ Alleviate the need for bulk storage
§ Reduce volatility of electricity prices
§ Minimize power reserves and defer the construction ofnew peaking power plants
§ Enhance power systems security
§ and others...
09.09.2013Spyros Chatzivasileiadis 62
Additional Benefits
||
§ Investments§ Investment Mechanisms§ Case of NorNed
§ Operation§ Operation Schemes§ “Global Regulator”§ “Global System Operator”
§ Alternatives to the Global Grid§ Challenges
09.09.2013Spyros Chatzivasileiadis 63
Additional Topics covered within “The Global Grid”
||
§ The Global Grid can be technologically feasible andeconomically competitive for a 100% RES future
§ Several new opportunities emerge
§ Working groups can be established to substantiate thebenefits and identify the risks
S.Chatzivasileiadis, D. Ernst, G. Andersson, The Global Grid.Renewable Energy, vol.57, p. 372-383, 2013. [online]http://arxiv.org/abs/1207.4096v4
09.09.2013Spyros Chatzivasileiadis 64
Conclusions
||
Duration of NTC Line Loadings
Hours per Year
4000 hours
Examples ofLines loadedat 100% formore than4000 hours
0% loading
100% loading
09.09.2013Spyros Chatzivasileiadis 65
|| 09.09.2013Spyros Chatzivasileiadis 66
Reinforcements: Robust Choices
*Reinforcementsidentified based onDuration of LineLoadings
Additional Linesidentified asnecessary* inalmost all 2050scenarios(in red colour)
||
§ Degree of compensation: 40-50%
Total Compensation
AC-400 kV (Gvar) AC-750 kV (Gvar)BAU 2050 14 16CCS 2050 10 11DES 2050 16 18EFF 2050 14 16RES 2050 16 18
Series Compensation
High Costs!
09.09.2013Spyros Chatzivasileiadis 67
||
§ Controllability Index(a vector based on PTDFs)
09.09.2013Spyros Chatzivasileiadis 68
Controllability and Placement
= max. controllability
§ Only dependent on the networkcharacteristics (off-line)
§ Find the vectors that are mostindependent from each other(orthogonality)
||
§ Adding the same line as internal reinforcement or parallelto the interconnection
09.09.2013Spyros Chatzivasileiadis 69
=,
=,
′′ ,
≤′
′ ,
≤
Zint Zext
Zext
Znew,ext
ZintZint
Znew,int
Zext
Internal Network Interconnection
Flow through the internalreinforcement
Flow through the line parallelto the interconnection
A BC
A C B A C B
||
§ Adding the same line as internal reinforcement or parallelto the interconnection
09.09.2013Spyros Chatzivasileiadis 70
Zint Zext
Zext
Znew,ext
ZintZint
Znew,int
Zext
Internal Network Interconnection
A BC
A C B A C B
||
§ Add same line as internal reinforcement or overlay line§ Assume that the existing network has transfer capacity
limited to
09.09.2013Spyros Chatzivasileiadis 71
Supergrid vs. Internal Reinforcements
Zext
Znew,ext
Zint
Zint
≤
Zint
Znew,int
ZextA BCA BC
Overlay networks lead to higher utilizationcompared with internal reinforcements
Flow through theinternal reinforcement
Flow through theoverlay line
||
§ Assume that the existing network has transfer capacitylimited to
09.09.2013Spyros Chatzivasileiadis 72
Overlay Networks: Upper bound on utilization
Zext
Znew,ext
Zint
Zint
≤
Zext
Znew,ext
Zint
Upper bound on utilization for overlay networks:Line with equal length and parallel to the interconnection
A BC A BC
Flow through theoverlay line
Flow through the line parallelto the interconnection
||
§ Existing interconnection: at least one AC-400 kV line
§ Adding one cross-border AC-400 kV: ≤§ Adding one cross-border AC-750 kV: ≤ 1.6 ∙
09.09.2013Spyros Chatzivasileiadis 73
Overlay Networks: Upper bound on utilization
Zext
Znew,ext
Zint
Zint
≤
Zext
Znew,ext
ZintA BC A BC
|| 74
Ecological Impact –Reduction of Network Congestions (RWTH Aachen)
FACTSHVAC++FACTS
HVDC
UHVACFACTS
HVAC+RES curtailment
HVAC+
Network development is highly necessary to reach CO2reduction targets, especially in case of a high penetration of
renewables
09.09.2013Spyros Chatzivasileiadis