Date: 1.5. 2019
Vasundhara Watershed Developmet Agency, Pune
Inter Ministrial Committee on Water Conservation
Efforts of Maharashtra state on water conservation
PMKSY Components and Convergence
I. Accelerated Irrigation Benefits Programme (AIBP)
II. Har Khet ko Pani
III. Per Drop More Crop
IV. Watershed Development
• Convergence Programme with Central and State Schemes
I. Jalyukt Shivar Abhiyan (Field filled with Water)
II. MGNREGS
III. Magel Tyala Shettale (Farm Pond on Demand)
Summary of PMKSY-WDC Maharashtra State---Till 31 March. 2019
Sr. No
Particulars
Year of Appraisal Total Batch-
I (2009-
10)
Batch-II (2010-11)
Batch-III (2011-12)
Batch IV (2012-13)
Batch V (2013-14)
Batch VI (2014-15)
1. No. of Projects for implementation
239 359 212 118 113 121 1162
2. Project Area 9.51 14.52 8.79 4.97 4.93 5.37 48.09
3. Project Cost (Rs. Cr.) 1213 1853 1127 646 634 690 6163
4. Funds received (Rs. in Cr.) Central+ State+Int
800 1174 582 182 111 50 3035
5. Total Expenditure (Rs. in Cr. and %)
799 (99%)
1173 (98%)
580 (97%)
179 (97%)
109 (98%)
48 (96%)
2890 (96%)
6. DPRs sanctioned 239 359 214 113 81 20 1026 7. Projects Cancelled/
Hold 4 11 3 7 34 97 156
8. Phy Ach Lakh Hect 7.21 10.35 4.93 1.31 0.56 0.08 24.44
9 WDF Amt in Cr. 6.51 11.46 17.97
10 Exited Projects Mar 17 Mar -18 Mar- 19 Mar -20 Mar-21 Mar -22
11 Administrative Closure Report
239 348
PMKSY –WD implementation strategy.
• The projects selection based on priority by MRSAC, ground water status, DPAP.
• Project wise release of funds to take up the balance NRM works in projects nearing saturation.
• Targeting of livelihood activities in Batch – III and Batch –IV projects.
• Achieving Convergence with Other schemes viz. MGNREGS, PMKSY –OI, Jalyukt Shivar Abhiyan etc. to complete the targeted Watershed Works.
• Use of GIS, PFMS, MIS technology. • Uploaded 1.5 lakh + field photographs on Bhuvan Srishti
Portal using Drishti mobile Application. • E tendering of NRM works
• Area Treatment.
• Soil moisture conservation activities like Continuous Countour Trenches, Deep Continuous Countour Trenches, Water Absorption Trenches, Compartment Bunding, Terracing, Graded Bunding, Repair of old paddy bunds, Bodi repair.
• Non aerable land -Continuous Countour Trenches, Deep Continuous Countur Trenches, Water Absorption Trenches activeties are taken up on wasteland with cumulative achievement of 46277 ha.
• Aerable land - A series of Compartment bunds divide the area into strips and act as barriers to the flow of water, thus reducing the amount and velocity of the runoff with cumulative achievement of 7.89 lakh ha. Graded bunds act primarily as drainage channel to regulate and conduct excess runoff at non erosive velocity with cumulative achievement of 5.54 lakh ha.
• Terracing reduces the length of the hill side slope, there by reducing sheet and rill erosion and prevents formation of gullies with cumulative achievement of 24945 ha.
• Area under Plantation (Horticulture and afforstation) implementation is about 3018 ha. These activities have helped to reduce the silt flowing to the large reservoirs.
PMKSY –WD implementation strategy (NRM Works).
• Drainage line treatment – Includes structures such as Earthen structures, Loose boulders, Earthen nala bund, Cement nala bund,, Diversion bund etc.
• Among these Cement Nala bund (3000+)& Earthen Nala bund (5000+)act as water harvesting structures. These structures taken in lower reaches are useful for ground water recharge.
• Created capacity of 65000 TCM.
PMKSY –WD implementation strategy (NRM Works).
IWMP -Physical and Financial Progress oF NRM work During Year 2018-19 Sr. no. Name of the NRMActivitiy Unit Total Batch I To VI
Phy. Fin.
I) a Soil Moisture Conservation Activities (Area Treatment)-
1) CCT ha. 1692.00 615.00 2) D•eep CCT(forest) ha. 17.00 1.87 3) Water Absorption Trenches ha. 0.00 0.00 4) Compartment Bunding ha. 74367.00 4793.00 5) Terracing ha. 943.00 677.00 6) Graded Bunding ha. 29833.00 1676.00 7) Repair of old paddy bunds ha. 3260.00 533.00 8) Bodi repair ha. 25.00 8.00 9) Paddy bunding ha. 120.00 33.00 10) Reclamatin of ill drained soils (open trench) ha. 127.00 14.00
Total 110384.00 8350.87
I) b Vegetative and Engineering Structures (Drainage Line Treatment-1)-
1) Earthen Structures No 2771.00 27.00 2) Loose Boulder Structure (Upper reaches) No 50.00 2.00 3) Loose Boulder Structure (Middale reaches) No 2196.00 62.00 4) Gabian Structure No 61.00 7.00 5) Nala training Rmt 11.00 30.00 Total 5089.00 128.00
PMKSY WDC -Physical and Financial Progress oF NRM work During Year 2018-19
I) c Water Harvesting Structures (Drainage Line Treatment-2)-
1) Farm Pond No. 284.00 276.00
2)
Sunken pond
No. 0.00 0.00
3) Jalkund No. 0.00 0.00
4) Cement Nala Bund No. 255.00 2568.00
5) Earthen Nala Bund No. 112.00 468.00
6) D•iversion bund No. 24.00 76.00
7) Well recharge No. 5.00 0.00
8) Nala deepning No. 142.00 354.00
Total 822.00 3742.00 I) d Plantation-
1) Afforestation ha. 0 0 2) Horticulture ha. 12 0 3) Any other ha. 5 9
Total 17.00 9.00 State Total (NRM) 116312.00 12229.87
Sr. No. Quarterly Achievements on Output- Outcome indicators under WDC- PMKSY Indicator During 4th Q Cumul year 2018-19
1 No. of Water harvesting Structures 955
a Newly constructed (Nos.)
i Constructed on private land of SC 3 92
ii Constructed on private land of ST 1 30
iii Constructed on others including public land 34 484
Total 38 606
b Rennovated (Nos.)
i Rennovated on private land of SC 3 53
ii Rennovated on private land of ST 0 37
iii Rennovated on others including public land 59 259
Total 62 349
2 Additional area brought under protective irrigation (in ha.)
a Area belonging to SC 39.62 64.52
b Area belonging to ST 0 0
c Area belonging to others including public land 580.76 5153
Total 620.38 5217.52
3 NO. of farmers benefitted
a SC 78 1575
b ST 31 1706
c Others 518 5103
Total 627 8384
4 Area brought under plantation (Horticulture/Afforestation etc.in ha.)
a SC (Area belonging to SCs) 0 7
b ST (Area belonging to STs) 0 0
c Others (all areas including community/Govt. land brought under plantation except SCs & STs) 0 429.3
Total 0 436.3
5 Area of culturable wasteland treated in completed Watershed Dev.Projects (in ha.)
a SC (Area belonging to SCs) 14.4 580.42
b ST (Area belonging to STs) 54.92 875.92
c Others (all areas including community/Govt. land brought under plantation except SCs & STs) 208.9 2411.03
Total 278.22 3867.37
6 Employment Generated (person-days)
a SC 5108 6228
b ST 12675 13180
c Others 9251 58346
Total 27034 77754
Sr.
no. Name of the NRMActivitiy Unit
Total Batch I to VI
Phy. Fin.
I) a Soil Moisture Conservation Activities (Area Treatment)- 1) CCT ha. 32606 7998
2) D•eep CCT(forest) ha. 1058 133
3) Water Absorption Trenches ha. 12634 859
4) Compartment Bunding ha. 774466 50324
5) Terracing ha. 24945 14453
6) Graded Bunding ha. 554517 32979
7) Repair of old paddy bunds ha. 36942 7430
8) Bodi repair ha. ha. 138 53
9) Paddy bunding 1550 528
10) Reclamatin of ill drained soils (open
trench) ha. 127 14
PMKSY WDC -Physical and Financial Progress oF NRM work Cumulative achievement up to Year 2018-19
Sr.
no. Name of the NRMActivitiy Unit
Total Batch I to VI
Phy. Fin.
I) b Vegetative and Engineering Structures (Drainage Line Treatment-1)-
1) Earthen Structures Cum/No 102103 1083
2) Loose Boulder Structure (Upper reaches) Cum/No 184283 2927
3) Loose Boulder Structure (Middale reaches) Cum/No 64525 1535
4) Gabian Structure Cum/No 1643 55
5) Nala training Rmt 14 51
I) c Water Harvesting Structures (Drainage Line Treatment-2)-
1) Farm Pond No. 1914 1879
2) sunken pond No. 10 5
3) Jalkund No. 39 31
4) Cement Nala Bund No. 3383 27642
5) Earthen Nala Bund No. 5207 18386
6) D•iversion bund No. 469 1253
7) Well recharge No. 47 8
8) Nala deepning No. 759 1653
I) d Plantation-
1) Afforestation ha. 554 118
2) Horticulture ha. 1836 22
State Total (NRM) 171897.0
PMKSY WDC -Physical and Financial Progress oF NRM work Cumulative achievement up to Year 2018-19
Sr. no.
Name of the NRM Activities.
Total Potential area brought
under Protective
Irrigation ha.
Phy.
Fin. Rs. In Lakhs
Water Harvesting
Structures
1 Cement Nala Bund 92 618.17 537.92
2 Earthen Nala Bund 23 56.24 60
Total 115 674.41 537.92
PMKSY-PDMC-OI Achiements reporting till March -19
Annual Action Plan for year 2019-20
(Amount Rs. in Lakh)
Sl.
No. Batch
I st Qtr.
(Apr.-June)
II nd Qtr.
(Jul.-Sept.)
III rd Qtr.
(Oct.-Dec)
IV th Qtr.
(Jan.-Mar.)
Total Fund
requirement for
year 2017-18
(3+4+5+6)
1 2 3 4 5 6 7
1 Batch-IV
(2012-13) 9088 7573 4544 9088 30293
2 Batch-V
(2013-14) 5075 4229 2537 5075 16915
3 Batch-VI
(2014-15) 549 458 275 549 1830
TOTAL: 14711 12260 7356 14711 49038
Potential Treatment Map - Output
Impact Assess Study : MONITORING NRM ACTIVITIES
Analysis of conditions of a watershed before and after implementation of activities.
Compartment Bunding
MWS : 4E8B3c2e 2009 2016
NDVI analysis using Temporal (Pre and Post) Satellite Data
Implementation Use
A Few Photographs of
NRM Activities
Continuous Contour Trenches Village: Pangaon, IWMP project no.: IWMP-27/2011-12, District: Solapur, Block: Barshi Latitude: 18’ 08”31.61”N, Longitude: 75’44”03.25”E,
NRM Works-Compartment Bunding Village:, Junoni IWMP project no.: IWMP-05/2009-10, District: Solapur Block: Sangola Latitude: 17° 14'46.25"N, Longitude: 75°00'30.74"E,
NRM Works-Loose Boulder Structure (LBS)
Village: Rajuri, IWMP project no.: IWMP-8/2010-11, District: Ahmednagar, Block: Jamkhed Latitude: 18’ 19”26.88”N, Longitude: 75˚22’13.32 ̎E,
NRM - EARTHEN NALA BUND (ENB) Village-Anuskura , IWMP Project No- IWMP-KR 59/04/2009-2010 District – Kolhapur , Block – Panhala /Shahuwadi
Project Name-: IWMP- 06 (20110-11) Village-: Burambal Taluka- Radhanagri ,Dist- Kolhapur
Diversion Dam
NRM: Cement Nala Bund (CNB) Village : Nivebh, IWMP : 30/2011-2012 District : Ratnagiri, Block : Sangmeshwer (Devrukh) Latitude : 17° 3'43.08"N Longitude : 73°40'59.19"E
VISION CREATE WATER SECURITY + BOOST AGRICULTURAL INCOME
STRATEGIES Create
awareness about scheme
Establish Public Private and
NGO Partnership
Enhance efficiency with
government support
Build and collect
evidence to measure success
Convergence of existing schemes to meet targets
Provide guidelines and
support to service delivery
partners
JALYUKT SHIVAR ABHIYAN ACTIVITIES
IMMEDIATE OUTCOMES
Enhanced soil fertility
Increased farm productivity
Increased groundwater recharge
Increased water
storage capacity
Reduction in water run off
Sustainably boosting rural income
Water security for drought prone region
Increase in Groiundwater Level
LONG TERM OUTCOMES
IMPACT
Improved Farmers Income
Reduction of Water Scarcity
in Villages
Increased Water Availability
Improved Risk
Management (Drought Resiliance)
Jalyukta Shivar Abhiyan
Jalyukta Shivar Abhiyan – Aim & Objectives
Flagship Program of The Government of Maharashtra
▪ To arrest maximum runoff (insitu water conservation).
▪ To create Decentralized Water Bodies.
▪ To increase the Groundwater Level.
▪ To create new structures of water conservations.
▪ Rejuvenation of the water storage capacity of various existing
structures.
▪ To increase storage capacity of water bodies by removing silt through
People’s Participations.
▪ To sensitize the concept of Water Budgeting.
▪ To encourage Tree Plantation.
▪ To create awareness and encourage people for efficient use of water for
farming.
▪ Village watershed as unit of planning
▪ Water Budgeting module developed by IIT Mumbai (M.S) has been
introduced.
▪ Requirement of water – For Drinking , Animals and Agriculture
▪ Village action Plan maps are used in JSA project using technology of
Remote sensing and GIS.
▪ Treatment Potential Map of watershed is prepared by using various
GIS layer of land slope, land capability, soil erosion ,contour,
geomorphology, lineaments, etc to facilitate village committee to
take decision on best suitable soil and water conservation
treatment for particular site.
▪ Shiwar feri with Treatment Potential Map and PRA by field officers /
Villagers .
▪ Average Rainfall, Runoff, Topography, Availability of Water are major
factor affects preparation of water budget.
Water Budgeting - Action Plan
▪ Collector is captain of the Team at District level. He is responsible for
selection of villages, approval of the plan and implementation of the works.
▪ There is the convergence of various schemes related to Water Conservation
viz, Central & State Government fund , DPC and Peoples contribution,
Convergence of IWMP,MGNREGA,NHM,VIIDP, Adarsh Gaon Yojana,
Koradvahu Sheti Abhiyan,ZP cess fund,MP/MLA fund, NGO /CSR fund
▪
• Apart from regular scheme fund, Special provision is made for the
programme as ‘Gap Fund’ which can be used for all work of JSA.
For 2015-16 Rs. 2000 Cr. ,2016-17 Rs. 2100 Cr. 2017-18 Rs 1200 2018-19 Rs
1500 has been given as Gap Fund.
▪ The Siddhivinayak Trust, Mumbai and Sai Baba Sansthan , Shirdi has given
Rs.1 Cr to each district. Various NGO like Tata Trust, Pani foundation,
Kamalnayan Bajaj foundation and many more NGO are actively supporting
the initiative.
▪ To support NGO initiative, Government has announced Public Private
Partnership (PPP) Policy for Soil and water conservation works especially
desilting
Convergence of Funds
▪ Villages undertaken 22589 .
▪ Program completed villages 15916
▪ Silt excavated 18 Crore cubic meter
▪ Participation of people Rs 612 Crore
▪ Increase Water Storage Capacity-24.35 Lakh TCM
▪ Created Protective Irrigation capacity -34.23 lakh Ha
▪ Gap Funding - 6800 Cr.
Jalyukt Shivar Abhiyan : Outcome
Farm Pond on Demand
• Present Scenario:
• Application received : 4,02,464
• Technically fit site : 2,89,756
• Issued work order : 2,46,070
• In progress : 3,268
• Completed : 1,20,439
• Subsidy Paid Nos : 1,13,221
• The amount of subsidy paid : 539.55 Cr • .
Farm Pond on Demand
MGNREGA - MAHARASHTRA
1
Sr. No. Work Category
No. of Completed works No. of Ongoing
works in FY 2016-17 in FY 2017-18 in FY 2018-19 Since Inception
1 Forest pond 257 151 129 1967 690
2 Counter trench 596 363 284 6277 902
3 Loose Boulder 1310 773 972 15416 1202
4 Earthen Bund 153 65 56 2418 197
5 Mati Nala Bandh 1323 737 743 20713 1084
6 Farm Bunding 1491 861 510 11919 1757
7 Majgi (terracing) 5437 3044 2937 24772 4496
8 Bodi Nutanikaran 1002 488 523 6515 899
9 Gabian Bandhara 121 220 122 720 118
10 Bhumigat Bhandhara 56 16 5 312 64
11 Well recharging 5564 6053 7170 41797 10480
12 Desilting 1715 1072 747 14470 1661
13 Nalla saralikaran 800 631 769 6290 1333
14 Cement Nalla Bhandhara 600 354 265 4566 794
15 Canal Repair 173 128 523 6515 462
16 Recharge Pit 237 240 224 1622 1123
TOTAL 20835 15196 15979 166289 27262
Water conservation Works under MGNREGS
Performance under PMKSY – 2018-19
Per Drop More Crop (Micro Irrigation)
Component
Physical (Area
Ha.) Financial (Rs.crore)
Targets Ach’mnt Fund Received Expenditure
GoI State Total GoI State Total
Drip 111144 77844
343.68 225.05 568.73
185.28 123.52 308.80
Sprinkler 106389 37225 42.73 28.48 71.21
Admin Cost 0 0 6.00 0.00 6.00
Total 217533 115069 343.68 225.05 568.73 234.01 152.00 386.01
Subsidy payment of 57392 application of 2018-19 is under process
PMKSY -AAP 2019-20
Component
Physical Target Financial Provision
(Rs.crore) Area
( Ha.)
Benificieres
(No.) GoI State Total
PDMC (Micro Irrigation)
Drip 110623 121686 272.00 181.33 453.33
Sprinkler 63617 69979 68.00 45.33 113.33
Admin Cost 0 0 20.00 0.00 20.00
AIBP Project 0 0 40.00 26.67 66.67
Total -PDMC 174240 191665 400.00 253.33 653.33
Other Intervention 0.00 0.00 80.00 53.33 133.33
Total AAP for 2019-
20 174240 191665 480.00 306.66 786.66
PMKSY – AIBP
• AIBP was specifically started because a large number of river valley projects – both major and medium – have spilled from plan to plan, mainly because of financial constraints of state governments.
• Some of these projects were in an advanced stage of construction and could provide irrigation benefits in four or five agricultural seasons.
• The completion of these projects, however, was beyond the resources capability of the State Governments.
List of the 26 projects in Maharashtra under PMKSY / AIBP Scheme
Sr.No. Name of the Project Benefited Districts
Priority-I Projects
1 Bawanthadi (IS) Bhandara
2 Lower Panzara Dhule
3 Dongargaon Chandrapur
4 Warna Kolhapur, Sangli
Priority-II Projects
5 Waghur Jalgaon
6 Lower Dudhana Parbhani, Jalna
7 Tillari Sindhudurg
8 Nandur Madhmeshwar Ph-II Aurangabad
9 Khadakpurna Buldhana
Priority-III Projects
10 Lower Wardha Wardha
11 Gosikhurd (NP) Nagpur, Bhandara Chandrapur
12 Upper Pen Ganga Yavatmal, Parbhani, Nanded
13 Bembla - Yavatmal Yavatmal
14 Tarali Satara
15 Dhom Balaakwadi Pune / Satara
16 Arjuna Ratanagiri
17 Upper Kundalika Beed
18 Aruna Sindhudurg
19 Krishna Koyana Lift Solapur, Sangli
20 Gadnadi Ratanagiri
21 Sangola Branch Canal Solapur
22 Morna (Gureghar) Satara
23 Lower Pedhi Amravati, Akola
24 Wang project Satara
25 Naradave
(Mahammadwadi) Sindhudurg
26 Kudali Satara
List of the 26 projects in Maharashtra under PMKSY / AIBP Scheme
40
Secretary Agri. Sec. Soil & Water Conservation
Comm. of Agriculture
Supervisory Authority Divisional Jt. Director (8)
Dist. Superintending Agril.Officer (33) Project Manager
STATE LEVEL
DIVISION LEVEL
DISTRICT LEVEL
PROJECT LEVEL Project Implementing Agency
WC LEVEL
Taluka Agril.Officer (353)
WDT member and sign.autho. WC
Circle Agriculture Officer (885)
Sub Divisional Agril.Officer(90)
Director (6)
ORGANISATION SETUP
Agriculture Supervisor (2726)
Member WC ,15 member Committee
Agri. Dept. Setup PMKSY Setup
Chairman VWDA
CEO V W D A
Director SC &WM
WCDC
Supervisory Authority
WDT
Agril. Asst.
PIA
Member VWDA
03-05-2019 VWDA,Pune 42
PMKSY – CADWM
• The main objective of CAD&WM Programme is to enhance utilization of irrigation potential created and improve agriculture productivity and production on a sustainable basis through integrated and coordinated approach involving multidisciplinary team.
• The programme was launched in 1974-75 and was restructured and renamed as Command Area Development and Water Management (CADWM) Programme in 2004. +
• The scheme has been implemented as a State Sector Scheme during the XI Five Year Plan (2008-09 to 2011-12).
• During XII Plan, the CADWM programme has been implemented pari-passu with Accelerated Irrigation Benefits Programme (AIBP).
List of the projects - Priority
wise
Bawanthadi Irrigation Project
Sr.
No
Description Quantity
1. Project
Estimated Cost
Rs. 867.20
crore
2. ICA
CCA
IP
17537 Ha
25062 Ha
27706 Ha
3. Drinking water
use
6.00 Mcum
4. Project
Expenditure
748.41 Cr.
Priority –
I
A joint venture of Madhya Pradesh & Maharashtra State
River: Bawanthadi, Godavari River Basin.
Madhya Pradesh Part : Dam & LBC (80.52 km)
Maharashtra Part: The construction of RBC (26.61km) system & rehabilitation works.
Inclusion (PMKSY-AIBP) : In 2016-17 as Priority-I project
Benefitted Districts : Balaghat, Bhandara & Gondia.
CADWM: (CCA-25062Ha, Budget-25.03 Cr.)
Completion Date: December 2019
MIS Status : AIBP – Aug 2018 Updated
CADWM – Not Yet Started
Lower Panzara Irrigation Project
• Project Location : Akkalpada - Sakri of District Dhule.
• River : Panzara River, Tapti Basin
• Inclusion (PMKSY/AIBP) : In 2015-16, as in Priority – I project.
• Benefitted Districts : Dhule
• Other benefits : Fisheries, Tourism etc. Population to be benefitted about 84000 peoples, 21 villages are benefitted.
• Major Impact : Out of 7585 ha Ultimate irrigation potential of the project, 6681 ha potential (about 88 % of total command) is covered under area declared as drought prone area (DPA) in Sakri and Dhule talukas of Dhule district.
• CADWM : (CCA – 6785 Ha)
(Budget – 25.03 Cr.)
• Completion Date: December 2019
• MIS Status : AIBP – Aug 2018 Updated
CADWM – Not Yet Started
Sr. No Description Quantity
1. Project Estimated Cost 556.286 Cr.
2. ICA
CCA
IP
7585 Ha
9980 Ha
6785 Ha
3. Drinking water use 21.92 Mcum
4.
5. Industrial Use
Project Expenditure
8.50 Mcum
462.765 Cr.
Priority –
I
Dongargaon Irrigation Project
Sr.
No
Description Quantity
1. Project Estimated Cost 87.77 Cr.
2.
3.
ICA
CCA
IP
Project Expenditure
2576 Ha
2845 Ha
3606 Ha
40.31 Cr.
Priority –
I
Location : Village Dongargaon in
Rajuri tehsil of Chandrapur
River : Nalla (Adichhagar) in
Wardha sub-basin of Godavari Basin.
Inclusion (PMKSY-AIBP) :
Benefitted Districts : Chandarpur
CADWM : Not included
Completion Date: December 2019-
20
MIS Status :AIBP – Aug 2018
Updated
Warna Irrigation
Project
Sr. No Description Quantity
1. Project Estimated Cost 117.498 Cr.
2.
ICA 87000 Ha
3. CCA
98839 Ha
4.
5.
IP
Project Expenditure
74690 Ha
290.09
Priority –
I • Inclusion (PMKSY/AIBP) : Included
in (AIBP) in 2005-06 and recently in PMKSY to complete the remaining canal works.
• District Benefitted : Sangali & Kolhapur
• Category : General
• Indirect/Expected Benefits :
a) Number of sugar factories are developed in command.
b) Economic growth, living status, and educational standard of people have been developed.
c) Ground water table in command is raised. Production of vegetables, fruits, milk, etc. agriculture based product are increased and rural industries are developed.
– CADWM : Not included
– Completion Date: December 2019
– MIS Status : AIBP - Dec 2017 Update
CADWM -Not updated
Waghur Irrigation
Project • Location : Raipur, Taluka - Jalgaon of
district Jalgaon
• River : Waghur, Tapi basin
• Category : DPA
• Inclusion (PMKSY/AIBP) : In 2015-16 as in Priority – II project.
• District Benefitted : Jalgaon & Bhusaval
• CADWM : (CCA – 6678 Ha) (Budget – 25.03 Cr.)
• Completion Date: December 2018
• MIS Status : AIBP – Aug 2018 Updated
CADWM – Not Yet Started
Sr. No Description Quantity
1. Project Estimated Cost 1232.98 Cr.
2.
ICA 49702.22 Ha
3. CCA 39511Ha
4. IP 38570 Ha
5. Domestic Water 54.90 Cumec
6.
7.
Industrial Water
Project Expenditure
9.10 Cumec
818.54 Cr.
Priority –
II
Lower Dudhana
Irrigation Project • Location : Parbhani District of
Maharashtra State
• River : Parbhani, Godavari Basin
• Inclusion (PMKSY/AIBP) : 2015-16
• Benefitted Districts : Parbhani & Jalna
• CADWM : (CCA- 30035 Ha, Budget-
149.44 Cr.)
• Completion Date: December 2018
• MIS Status : AIBP – Aug 2018
Updated
CADWM – Not Yet
Started
Sr.
No
Description Quantity
1. Project Estimated
Cost
2341.67 Cr.
2.
ICA 28698 Ha
3. CCA 38264 Ha
4. IP 44482 Ha
5. Domestic Water Not Included
6.
7.
Industrial Water
Project Expenditure
Not Included
1551.36 Cr.
Priority –
II
Tillari
Irrigation
Project • It is a joint venture of Goa & Maharashtra States
• Location: Sawantwadi – Maharashtra
• Category: DDP
• District Benefitted: Sindhudurg (MH), North Goa (Goa)
• Inclusion (PMKSY/ AIBP): In 2015-16 as in Priority- II projects.
• Other Benefits: Provision to the extent of 57.43 MCM of water was also made for domestic and industries purpose for Goa State
• CADWM: (CCA- 21,197 Ha, Budget- 32.43 Cr.)
• Completion Date: December 2018
• MIS Status : AIBP – Sep 2017 Updated
CADWM – Not Yet Started
Sr. No Description Quantity
1. Project Estimated Cost 1612.15 Cr.
2.
ICA 13651 Ha
3. CCA 14521 Ha
4. IP 12,542 Ha
5. Domestic Water 57.43 Mcum
6.
7.
Industrial Water
Project Expenditure
Not Included
978.918 Cr.
Priority –
II
Nandur Madhmeshwar
Phase-II WAKI
DAM
Sr.
No
Description Quantity
1. Project Estimated
Cost
797.97 Cr.
2. ICA 37603 Ha
3. CCA 54433 Ha
4. IP 45576 Ha
5. Domestic Water Not Included
6.
7.
Industrial Water
Project Expenditure
Not Included
648.68 Cr.
Location: – Waki & Bham Dam in Taluka Igatpuri, District Nashik Maharashtra
River: Godavari Basin
Category: DDP
District Benefitted: Nashik, Aurangabad & Ahmednagar
Inclusion (PMKSY/ AIBP): In 2015-16 as in Priority- II projects.
Other Benefits:
CADWM: (CCA- 23116 Ha, Budget- 49.34 Cr.)
Completion Date: December 2018
MIS Status : AIBP – Aug 2018 Updated
CADWM – Not Yet Started
BHAM
DAM
Priority –
II
Khadakpurna
Irrigation Project Location: Buldhana district - Maharashtra
River:
Category: DDP
District Benefitted:
Inclusion (PMKSY/ AIBP): In as in Priority- II projects.
Other Benefits:
CADWM: (CCA- Ha, Budget- Cr.)
Completion Date: December 2018
MIS Status : AIBP – Aug 2018 Updated
CADWM – Not Yet Started
Sr.
No
Description Quantity
1. Project Estimated Cost 1374.60 Cr.
2. ICA 20720 Ha
3. CCA 25900 Ha
4. IP 24290 Ha
5. Domestic Water 4.772 Mcum
6.
7.
Industrial Water
Project Expenditure
3.10 Mcum
1108.38 Cr.
Priority –
II
Lower Wardha Major Irrigation
Project • Location : Dhanodi, Taluka – Arvi of
district Wardha.
• River : Godavari basin
• Category : DPA
• Inclusion (PMKSY/AIBP) : In 2008-
09 as in Priority – III project.
• District Benefitted : Wardha
• CADWM : (CCA – 63453 ha) (Budget
– 200.86 Cr.)
• Completion Date: December 2019
• MIS Status : AIBP – Aug 2018
Updated
CADWM – Not Yet
Started
Sr. No Description Quantity
1. Project Estimated Cost 2232.41 Cr.
3. CCA 63453 Ha
4. IP 63333 Ha
5. Domestic Water 12.07 Mm3
6.
7.
Industrial Water
Project Expenditure
40.20 Mm3
1691.60 Cr.
Priority –
III
Gosikhurd (Indira Sagar) National Irrigation
Project
• Location : Gosikhurd, of district Bhandara. • River : across river Wainganga
• Category : General
• Inclusion (PMKSY/AIBP) : In 2008-09 as in Priority – III project.
• District Benefitted : Bhandara, Nagpur, Chandrapur.
• CADWM : (CCA – 200000 Ha) (Budget – 7777.85 Cr.)
• Completion Date: December 2019
• MIS Status : AIBP – Aug 2018 Updated
CADWM – Not Yet Started
Sr. No Description Quantity
1. Project Estimated Cost 7777.85 Cr.
2 ICA 1,90,000 Ha
3. CCA 200000 Ha
4. IP 2,50,800 Ha
5. Drinking Purpose 23.69 Mm3
6.
7.
Industrial Purpose
Project Expenditure
100 Mm3
5964.308 Cr.
Priority –
III
Upper Penganga
Project Location : Pusad Taluka – Yavatmal District
River : Penganga, Godavari basin
Category : DPAP
Inclusion (PMKSY/AIBP) : In 2016-17 as in Priority – III project
District Benefitted : Nanded, Hingoli, Yavatmal
CADWM : (CCA –87804Ha) (Budget – 7777.85 Cr.)
Completion Date: December 2019
MIS Status : AIBP – Aug 2018 Updated
CADWM – Not Yet Started
Sr. No Description Quantity
1. Project Estimated Cost 255.81 Cr.
2 ICA 107090 Ha
3. CCA 116728 Ha
4. IP 40800 Ha
5. Drinking Purpose MCum
6.
7.
Industrial Purpose
Expenditure up to 03/2018
Mm3
94.740 Cr.
Priority –
III
Bemla Irrigation
Project Location :– Bhabulagaon,Yavatmal District
River :Bemla, Wardha Tributary – Sub Wardha Basin
Category : DPAP
Inclusion (PMKSY/AIBP) : In 2016-17 as in Priority – III project
District Benefitted : Yavatmal and Wardha
CADWM : (CCA –40170Ha) (Budget – 164.14 Cr.)
Completion Date: December 2019
MIS Status : AIBP – Aug 2018 Updated
CADWM – Not Yet Started
Sr. No Description Quantity
1. Project Estimated Cost 2931.16 Cr.
2 ICA 45713 Ha
3. CCA 60528 Ha
4. IP 52543 Ha
5. Drinking Purpose 23.69 MCum
6.
7.
Industrial Purpose
Expenditure up to 03/2018
100 Mm3
1840.30 Cr.
Priority –
III
Tarali Irrigation
Project Location : Village Dangistewadi ,Patan
Taluka, Satara District - Maharashtra
River : Tarali, Krishna Basin
Category : General
Inclusion (PMKSY/AIBP) : In 2007-08 as in Priority – III project
District Benefitted : Satara, Sangli & Solapur
CADWM : (CCA –13086 Ha) (Budget – 114.80 Cr.)
Completion Date: December 2019
MIS Status : AIBP – Aug 2018 Updated
CADWM – Not Yet Started
Sr. No Description Quantity
1. Project Estimated Cost 1610.32 Cr.
2 ICA 14276 Ha
3. CCA 13086 Ha
4. IP 14276 Ha
5. Drinking Purpose 1.80 TMCum
7. Expenditure up to 03/2018 1080.63 Cr.
Priority –
III
Dhom Balkawadi Tunnel
Irrigation Project Location : Balkawadi Village Wai Taluka,
Satara District - Maharashtra
River : Krishna River
Category : DPAP
Inclusion (PMKSY/AIBP) : In 2007-08 as in
Priority – III project
District Benefitted : Satara, Pune
CADWM : (CCA – 28100 Ha) (Budget – 244.23 Cr.)
Completion Date: December 2019
MIS Status : AIBP – Aug 2018 Updated
CADWM – Not Yet Started
Sr.
No
Description Quantity
1. Project Estimated Cost 1402.51 Cr.
2 ICA 18100 Ha
3. CCA 28100 Ha
4. IP 11653 Ha 5. Drinking Purpose 2.79 TMC 6. Expenditure up to
03/2018
624.29 Cr.
Priority –
III
Arjuna Medium Irrigation
Project Location : Village Karak in Rajapur Taluka
Ratnagiri District - Maharashtra
River : Arjuna that is tributary river of Kodavali
Category : General
Inclusion (PMKSY/AIBP) : In 2016-17 as in Priority – III project
District Benefitted : Ratnagiri
CADWM : (CCA – 5967 Ha) (Budget – 173.44 Cr.)
Completion Date: December 2019
MIS Status : AIBP – Aug 2018 Updated
CADWM – Not Included
Sr.
No
Description Quantity
1. Project Estimated Cost 611.55 Cr.
2 ICA 5704 Ha
3. CCA 5967 Ha
4. IP 5704 Ha
5.
Expenditure up to
03/2018
542.73 Cr.
Priority –
III
Upper Kundlika Medium
Irrigation Project Location : Village Sonna-Khotta ,Taluka
Wadwani District Beed in Maharashtra.
River : Kundlika ,Godavari Basin
Category : DPAP
Inclusion (PMKSY/AIBP) : In 2016-17 as in Priority – III project
District Benefitted : Beed
CADWM : (CCA – 3738 Ha) (Budget – 39.41 Cr.)
MIS Status : AIBP – Sep 2017 Updated
CADWM – Not Yet Started
Sr.
No
Description Quantity
1. Project Estimated Cost 318.99 Cr.
2 ICA 2800 Ha
3. CCA 3738 Ha
4. IP 52543 Ha 5. Drinking Purpose 1.77 MCum
6.
Expenditure up to
03/2018
264.54 Cr.
Priority –
III
Aruna Irrigation
Project Location : Village Het ,Taluka Vaibhav wadi District Sindhudurg
River : Aruna, a tributary of river Waghotan
Category : General
Inclusion (PMKSY/AIBP) : In 2016-17 as in Priority – III project
District Benefitted :Sindhudurga & Ratnagiri
CADWM : (CCA –6378 Ha) (Budget – 150.00 Cr.)
Completion Date: December 2019
MIS Status : AIBP – Aug 2018 Updated
CADWM – Not Included
Sr. No Description Quantity
1. Project Estimated Cost 1689.50 Cr.
2 ICA 5310 Ha
3. CCA 6378 Ha
4. IP 6379 Ha 5. Drinking Purpose 8.84 Mm3 6.
7. Industrial Purpose
Expenditure up to 03/2018
684.86 Cr.
Priority –
III
Krishna Koyana
Lift Irrigation
Scheme - Project
Location : Sangli District - Maharashtra River : Krishna River
Category : DPAP
Inclusion (PMKSY/AIBP) : In 2016-17 as in Priority – III project
District Benefitted : Sangli & Solapur
CADWM : (CCA – 172470 Ha) (Budget – 1068.32 Cr.)
Completion Date: December 2019
MIS Status : AIBP – Aug 2018 Updated
CADWM – Not Updated
Sr. No Description Quantity
1. Project Estimated Cost 2224.76 Cr.
2 ICA 109127 Ha
3. CCA 172470 Ha 4. IP 104167 Ha
5.
Expenditure up to 03/2018
763.86 Cr.
Priority –
III
Gadnadi Medium
Irrigation Project Location : Village Kuchambe in Taluka
Sangameshwar Ratnagiri
River : River Gadnadi a tributary of river Shastri
Category : DPAP
Inclusion (PMKSY/AIBP) : In 2016-17 as in Priority – III project
District Benefitted : Ratnagiri
CADWM : (CCA –3111 Ha) (Budget – 125.64 Cr.)
Completion Date: December 2019
MIS Status : AIBP – Aug 2018 Updated
CADWM – feel Preliminary Info
Sr. No Description Quantity
1. Project Estimated Cost 950.37 Cr.
2 ICA 3111 Ha
3. CCA 3111 Ha
4. IP 2523 Ha
5. Expenditure up to 03/2018 477.11 Cr.
Priority –
III
Sangola Branch Canal -
Project Location : Sangola Taluka, Solapur District
- Maharashtra River : Bhīma Basin , Nira Basin
Category : DPAP
Inclusion (PMKSY/AIBP) : In 2007-08 as in Priority – III project
District Benefitted : Sangola & Solapur
CADWM : (CCA – 13766 Ha) (Budget – 80.00 Cr.)
Completion Date: December 2019
MIS Status : AIBP – Aug 2018 Updated
CADWM – Not updated
Sr. No Description Quantity
1. Project Estimated Cost 742.24 Cr.
2 ICA 6883 Ha
3. CCA 13766 Ha
4. IP 11288 Ha
5. Expenditure up to 03/2018 248.60 Cr.
Priority –
III
Nardave Irrigation
Project
Priority –
III Location : Kankavali Taluka, Sindhudurg
District - MH
River : Gad River
Category : General
Inclusion (PMKSY/AIBP) : In 2007-08 as in Priority – III project
District Benefitted : Sindhudurg
CADWM : Not included
Completion Date: December 2019
MIS Status : AIBP – Aug 2018 Updated
Sr.
No
Description Quantity
1. Project Estimated Cost 1084.66Cr.
2 ICA 8084 Ha
3. CCA 9978 Ha
4. IP 13622 Ha
5. Drinking Purpose 10.606Mm3
6
7.
Expenditure up to
03/2018
Industrial Purpose
624.29 Cr.
5.98 Mm3
Morna
(Gureghar)Irrigation
Project • Location : Gureghar, Taluka – Patan
District - Satara
• River : Morna Tributary of Koyana –
Krishna Basin
• Category : General
• Inclusion (PMKSY/AIBP) : In 2016-17
as in Priority – III project.
• District Benefitted : Satara
• CADWM : (CCA – 4229 ha) (Budget –
1679.58 Cr.)
• Completion Date: December 2019
• MIS Status : AIBP – Aug 2018 Updated
CADWM – Not Yet Started
Priority –
III
Sr.
No
Description Quantity
1. Project Estimated Cost 185.510 Cr.
2 ICA 3075 Ha
3. CCA 4229 Ha
4. IP 3075 Ha
5. Drinking Purpose 28.32 Mm3
6
7.
Expenditure up to
03/2018
Industrial Purpose
81.660 Cr
17.346 Mm3
Kudali Irrigation
Project • Location : Maholi & Hateghar Taluka – Jaoli District - Satara
• River : Kudali & Hateghar– Krishna Basin
• Category : General
• Inclusion (PMKSY/AIBP) : In 2016-17 as in Priority – III project.
• District Benefitted : Satara
• CADWM : (CCA – 6068 ha) (Budget –271.79 Cr.)
• Completion Date: December 2019
• MIS Status : AIBP – Aug 2018 Updated
CADWM – Not Yet Started
Sr.
No
Description Quantity
1. Project Estimated Cost 341.72 Cr.
2 ICA 5327 Ha
3. CCA 5920 Ha
4. IP 8480 Ha
5. Drinking Purpose No provision
6
7.
Expenditure up to
03/2018
Industrial Purpose
79.0 Cr
No provision
Priority –
III
Wang Medium
Irrigation Project • Location : Marathawadi Taluka –
Patan District - Satara
• River : South Wang Krishna Basin
• Category : General
• Inclusion (PMKSY/AIBP) : In 2016-
17 as in Priority – III project.
• District Benefitted : Satara
• CADWM : Not included
• Completion Date: December 2019
• MIS Status : AIBP – Aug 2018
Updated
CADWM – Not
included
Sr.
No
Description Quantity
1. Project Estimated Cost 162.20 Cr
2 ICA 6200 Ha
3. CCA 8547 Ha
4. IP 3505.87 Ha
5. Drinking Purpose 8.46 MCM
6
7.
Expenditure up to
03/2018
Industrial Purpose
113.96 Cr
No provision
Priority –
III
Site
Photographs
Lower Panzara Reservoir U/S Side,
Chinchkhede, Maharashtra,
Lat: 20° 56’ 24’’ Long: 74° 26’ 45.6’’
Nardave Medium Irrigation Project –
Construction of Dam
Lat: 20° 78’ 57’’ Long: 74° 16’ 48.97’’
Lower Dudhana Railway Crossing on RBC at
RD 35.140 km – Karanji (Maharashtra)
Lat 19° 23' 16.8” Long 76° 30' 7.2"
Lower Dudhana Railway Crossing on RBC at
RD 19.02 km – Digras Jahangir (Maharashtra)
Lat 19° 25' 15.6" Long 76° 28' 26.4"
Watermelon production by Mulching Farming at Lat 19° 47' 16.8" Long74° 56' 56.4"
Lower Dudhana Dam U/S Reservoir – Gomewakadi
(Maharashtra) Lat 19° 31' 44.4"Long 76° 23' 34.8"
Lower Dudhana Dam D/S Spillway –
Gomewakadi (Maharashtra) Lat 19° 31' 44.4"
Long 76° 23' 34.8"
BHAM DAM – Bharwaj, MH (Lat - 19° 39'
36", Long - 73° 38' 49.2“)
BHAM DAM – Gaothans - Rehabilitated
Villages, Bharwaj, MH
(Lat - 19° 39' 36", Long - 73° 38' 49.2")
Water bodies covered under RRR in which catchment area treatment is included under PMKSY-WD (erstwhile IWMP)
• Soil moisture conservation activities (Area Treatment) are taken as a part of Natural Resource Management (NRM) subcomponent.
• It includes activities like Continuous Countour Trenches, Deep Continuous Countour Trenches, Water Absorption Trenches, Compartment Bunding, Terracing, Graded Bunding, Repair of old paddy bunds, Bodi repair. Amongst NRM activities Continuous Countour Trenches, Deep Continuous Countur Trenches, Water Absorption Trenches activeties are taken up on wasteland with cumulative achievement of 46277 ha.
• A series of compartment bunds divide the area into strips and act as barriers to the flow of water, thus reducing the amount and velocity of the runoff with cumulative achievement of 7.89 lakh ha. Graded bunds act primarily as drainage channel to regulate and conduct runoff at non erosive velocity with cumulative achievement of 5.54 lakh ha.
• Terracing reduces the length of the hill side slope, there by reducing sheet and rill erosion and prevents formation of gullies with cumulative achievement of 24945 ha.
• Area under Plantation (Horticulture and afforstation) under PMKSY-WDC (erstwhile IWMP) implementation is about 3018 ha. These activities have helped to reduce the silt flowing to the large reservoirs.
Total Number of Water Bodies:
• Drainage line treatment includes various structures namely earthen structures, loose boulders, Cement nala bund, Earthen nala bund, Diversion bund etc. Among these Cement Nala bund & Earthen Nala bund (Mati nala bund) act as water harvesting structures. These structures taken in lower reaches are useful for ground water recharge. Prominent structures viz Cement Nala bund, Earthen nala bund have created capacity of 65000 TCM.
PMKSY WDC -Impact Assessment
Overall well water level found increased by 0.86 m in summer season as compared to pre-project situation.
(Max-1.53 m in IWMP-23 Patan & Min-0.20m In IWMP-17 Man) On an average stream flow duration in project villages found
increased by two months in K. Mahankal & Phaltan. However, no increase in Maan (IWMP-11 & 17) block due to low rainfall.
Stopped dependency on tanker in Project no.IWMP-7 Phaltan &
IWMP-5 of K. Mahankal. No any tanker dependency in Chandgad (7) and Patan (23) projects
either during pre project or post project period.
Increase in duration of stream flow & Availability drinking water
On an average stream flow duration in project villages found increased by one month. Major increase of two months was observed in K. Mahankal & Phaltan by two months. However, no increase in Maan (IWMP-11 & 17) block due to low rainfall.
Stopped dependency on tanker in Project no.IWMP-
7 Phaltan & IWMP-5 of K. Mahankal. No any tanker dependency in Chandgad (7) and
Patan (23) projects either during pre project or post project period.
Average 5.5 months dependency on tanker is found
due to less rainfall in end line year in project no.IWMP-11 & 17 Man
Increase in irrigation potential & Change in land use
Increase in irrigation potential by 0.1 ha per household.
Waste land brought under productive use: Averagely by 183 ha per watershed cluster due to area treatments like terracing & bunding. Major increase of 256 ha in IWMP-7 of Kolhapur and minimal 107 ha in IWMP-7 of Phaltan, Satara.
Change in cropping / land use pattern: On an average area under cropping increased by 208 ha in each project due to area treatments mainly.
• Prioritization of Watersheds, scientific planning, and DPR preparation of ‘Soil
And Water Conservation’.
• Detailed study of a watershed with respect to ‘ridge to valley’ model.
• Optimum area coverage for regional survey.
• The pre-project conditions through project period will form the scientific base
for post-project evaluation and impact assessment studies .
Remote Sensing & GIS for Soil And Water Conservation
Drainage Line Treatment Area Treatment
Layer Integration Treatment Map
In Collaboration With
• The LULC with increased area are Agricultural Plantation, surface waterbodies and built-up
mining activities whereas there is decrease in forest cover and scrubs as presented in the
changed matrix. Afforestation on trances has been observed in T1 land use.
• Total Drishti uploads are in this project are 60 out of which 40 NRM activities are captured.
• The NDVI image shows prominent increase in greenness with high vegetation Index.
• Positive change is observed between 2009-10 and 2013-14 Landuse with respect to increase
in area under Agricultural Plantation and surface waterbodies during impact assessment
study of Aurangabad-IWMP-3/2009-10.
CONCLUSION
Aurangabad-IWMP-3/2009-10- Maharashtra State – Impact Assessment
Report 82
Jalyukta Shivar Abhiyan – Aim & Objectives
Flagship Program of The Government of Maharashtra
▪ To arrest maximum runoff (insitu water conservation).
▪ To create Decentralized Water Bodies.
▪ To increase the Groundwater Level.
▪ To create new structures of water conservations.
▪ Rejuvenation of the water storage capacity of various existing
structures.
▪ To increase storage capacity of water bodies by removing silt through
People’s Participations.
▪ To sensitize the concept of Water Budgeting.
▪ To encourage Tree Plantation.
▪ To create awareness and encourage people for efficient use of water
for farming.
▪ Watershed Development Works Viz, Area Treatment & Drainage line
Treatment activities
▪ Chain of Cement Nalla bandh with deepening and widening of Nalla
▪ Rejuvenation of old Water Bodies
▪ Repair, Renovation and Restoration of existing Minor Irrigation Water bodies
▪ Desilting of Water Conservation Structures viz, Percolation Tank, Village
Tank, Storage Tanks, M M Tank, ENB etc.
▪ Recharging of open dug wells and tube wells
Jalyukta Shivar Abhiyan - Works to be Undertaken
▪ Village watershed as unit of planning
▪ Water Budgeting module developed by IIT Mumbai (M.S) has been
introduced.
▪ Requirement of water – For Drinking , Animals and Agriculture
▪ Village action Plan maps are used in JSA project using technology of
Remote sensing and GIS.
▪ Treatment Potential Map of watershed is prepared by using various
GIS layer of land slope, land capability, soil erosion ,contour,
geomorphology, lineaments, etc to facilitate village committee to take
decision on best suitable soil and water conservation treatment for
particular site.
▪ Shiwar feri with Treatment Potential Map and PRA by field officers /
Villagers .
▪ Average Rainfall, Runoff, Topography, Availability of Water are major
factor affects preparation of water budget.
Water Budgeting - Action Plan
▪ Collector is captain of the Team at District level. He is responsible for
selection of villages, approval of the plan and implementation of the
works.
▪ There is the convergence of various schemes related to Water
Conservation viz, Central & State Government fund , DPC and Peoples
contribution, Convergence of IWMP,MGNREGA,NHM,VIIDP, Adarsh Gaon
Yojana, Koradvahu Sheti Abhiyan,ZP cess fund,MP/MLA fund, NGO /CSR
fund
• Apart from regular scheme fund, Special provision is made for the
programme as ‘Gap Fund’ which can be used for all work of JSA.
For 2015-16 Rs. 2000 Cr. ,2016-17 Rs. 2100 Cr. 2017-18 Rs 1200 2018-19 Rs
1500 has been given as Gap Fund.
▪ The Siddhivinayak Trust, Mumbai and Sai Baba Sansthan , Shirdi has
given Rs.1 Cr to each district. Various NGO like Tata Trust, Pani
foundation, Kamalnayan Bajaj foundation and many more NGO are
actively supporting the initiative.
▪ To support NGO initiative, Government has announced Public Private
Partnership (PPP) Policy for Soil and water conservation works especially
desilting
Convergence of Funds
▪ Concurrent Evaluation by Quality Control Monitors.
▪ Third party Evaluation after completion of works.
▪ Digital GIS based photo uploading – before starting of
work,during work and after completion of work.
▪ Approval of Gram Sabha to action plan of
village and progress of work is reported to
Gram Panchayat.
▪ Disbursement of the final bill only after the approval of
Gram Sabha / G.P.
▪ Sustainability – Exit protocol for villages in JSA.
Quality and Transparency
• Objectives :
• To provide protective irrigation facility in dry spell /
critical stages of crop.
• To overcome the scarcity situation.
• To recharge the ground water.
• To improve agriculture water security
•
Farm Pond on Demand
• Eligibility :-
• Farmer should own at least 0.60 Hectare agriculture land.
• Farmland should be technically fit for the farm pond.
• The applicant should not be a beneficiary of the farm
pond, common farm pond or well for paddy farming.
• Priority to the BPL and suicide farmer.
• For Konkan region minimum land holding is relaxed to
0.20 hectare.
• For Tribal Sub Plan (TSP) minimum land holding is
relaxed to 0.40 hectare.
Farm Pond on Demand
Sr. No. Dimension (Mtr)
Payable Subsidy in Rs
(Side Slope 1:1)
Farm Pond with Inlet and Outlet
Farm Pond without inlet and outlet
1 15x15x3 22110 ---
2 20x15x3 29706 26202
3 20x20x3 40467 36967
4 25x20x3 50000 47728
5 25x25x3 50000 50000
6 30x25x3 50000 50000
7 30x30x3 50000 50000
Dimensions of the Farm Pond and Payable Subsidy:
Types:-
A) With Inlet outlet - B) Without inlet outlet -
Subsidy:
The subsidy of Rs 50,000 or the actual cost of digging the farm pond, whichever is less, is deposited in the bank account of the beneficiary.
Farm Pond on Demand
• Methodology :- • Online applications through ‘Aple Sarkar’.
• The technical verification of the site.
• The taluka committee selects the beneficiaries
• The taluka agriculture officer issues work order.
• The beneficiary start digging.
• The beneficiary submit completion report.
• The Agriculture Officer, visit the site and conduct physical verification.
• GEO-tagged photograph of the farm pond is uploaded to the website.
• The subsidy is transferred to the bank account of the beneficiary.
Farm Pond on Demand
• Evaluation of the Scheme:- •
• 1) The Farm Ponds have resulted in increased water level in the well adjoining farm pond of 29% beneficiaries.
• 2) During the Kharif season, 37% beneficiaries have used the water in Farm Pond as protected irrigation during dry spell of monsoon. On an average 1.70 hectare land was irrigated and crop was saved.
• 3) According to 29% beneficiaries, the Farm Ponds have resulted increase in irrigation during Rabbi Season. The average increase during Rabbi Season was 0.76 hectare.
• 4) The 15% beneficiaries also got the benefits of allied activities such as dairy, livestock, poultry, vegetable, horticulture and fisheries.
• 5) With the help of farm ponds, 33% beneficiaries turned to vegetable, horticulture and fodder, thereby changing the crop pattern.
Farm Pond on Demand
0%
10%
20%
30%
40%
50%
60%
70%
80%
FY 2018-19 FY 2017-18 FY 2016-17 FY 2015-16 FY 2014-15
NRM 71.1% 64.1% 67.7% 65.6% 54.5%
71.1%
64.1% 67.7% 65.6%
54.5%
% o
f N
RM
exp
en
dit
ure
Highest Expenditure (%) in NRM works in last 5 years
0%
10%
20%
30%
40%
50%
60%
70%
80%
FY 2018-19 FY 2017-18 FY 2016-17 FY 2015-16 FY 2014-15
Agri. and allied 77.4% 77.3% 74.1% 66.8% 55.0%
77.4% 77.3% 74.1%
66.8%
55.0%
% o
f ex
pe
nd
itu
re
Highest Expenditure (%) in Agriculture and agriculture allied works in last 5 years
Natural Resource Management Activities under PMKSY –WD (erstwhile IWMP)
Farm Pond Gabian Structure
Nala Deepening Compartment Bunding Gully Plugs
Terracing Continuous contour trenches
Issues
Municipal areas excluded. Waive mandatory WDF on the background of
Drought . Divergence of funds at GoI. Implementation strategy of MGNREGS & PMKSY
WDC. E tender and capacity of WC. Multiplicity in Voluntary Organisation’s
empanelment.