347
Intel Ireland Annual Environmental Report 2010

Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Intel Ireland

Annual Environmental Report 2010

Page 2: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

1 INTRODUCTION

1.1 Site Details 1

1.2 Description of Campus Activities 1

1.2.1 Intel Ireland – Campus Overview 1

1.2.2 Manufacturing Facilities Overview 2

1.2.3 Process Steps Overview 3

1.2.4 Environmental Abatement 5

1.2.5 Support Activities

1.3 Environmental Policy 7

1.4 Environmental Management Organisational Structure 8

2 SUMMARY INFORMATION

2.1 Self Monitoring Data 10

2.1.1 Emissions to Sewer 10

2.1.2 Emissions to Surface Water 12

2.1.3 Emissions to Atmosphere 13

2.1.4 Summary of Waste Data 15

2.2 Agency Monitoring and Enforcement 19

2.2.1 Agency Monitoring Visits 19

2.2.2 Agency Inspections 20

2.3 Resource Management 21

2.3.1 Introduction 21

2.3.2 Design for the Environment 21

2.3.3 Supplier Environmental Targets 24

2.3.4 Water Consumption and Minimisation 24

2.3.5 Energy Consumption 25

2.3.6 Material Efficiency 26

2.4 Environmental Incidents and Complaints 27

Page 3: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

2.4.1 Environmental Incidents 27

2.4.2 Complaints 29

3 MANAGEMENT OF THE ACTIVITY

3.1 Schedule of Environmental Objectives and Targets 30

3.2 Environmental Management Programme (EMP) Report 2010 32

3.3 Environmental Management Programme (EMP) Schedule 2011 43

3.4 Pollution Emissions Register 49 3.4.1 Introduction 49

3.4.2 Summary of Methodology for Substances requiring a full PER 49

3.4.2.1 Copper 49

3.4.2.2 Fluoride 51

3.4.3 Pollution Emission Register (PER) 2010 52

3.4.4 Pollution Emission Register (PER) Proposal for 2011 53

4 LICENCE-SPECIFIC REPORTS

4.1 Groundwater Monitoring Summary Report 54

4.2 River Rye Water Monitoring Report 55

4.3 Louisa Spa Water Quality Monitoring 55

4.4 Bund Testing Summary 56

4.5 Underground Pipe and Tank Integrity Testing 56

4.6 Ambient Air Monitoring Summary 57

4.7 Fugitive Emissions Programme 58

4.8 Perfluorinated Carbon (PFC) Emissions Report 59

4.9 Noise Monitoring Report Summary 63

4.10 Residual Management Plan 63

APPENDIX A Pollutant Release and Transfer Register (PRTR)

APPENDIX B Groundwater Monitoring Report

Page 4: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

APPENDIX C River Rye Monitoring Report

APPENDIX D Louisa Spa Monitoring Report

APPENDIX E Bund Testing Report:

APPENDIX F Underground Pipe Integrity Testing Report: - Fab 24 Process

Effluent Lines

APPENDIX G Underground Tank Integrity Test Report – F10 Upper

Contained Storm Sewer Tank.

APPENDIX H Noise Monitoring Report

Page 5: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Abbreviations

A… Air Emission Points Identified in the Intel IPPC licence

AER Annual Environmental Report

BOD Biochemical Oxygen Demand

C Calculation

C&D Construction and Demolition

C&I Construction and Industrial

C4 Controlled Collapse Chip Connect; (Wafer Finishing Process)

CAP Community Advisor Panel

CCW Concentrated Copper Waste

CFC Chlorofluorocarbon

CMP Chemical Mechanical Polish

CO Carbon Monoxide

COD Chemical Oxygen Demand

Cr Chromium

CRT Construction Response Team

CS Corporate Services

DMW Dilute Metal Waste

E Estimation

EDI Electro-Deionisation

EHS Environmental, Health & Safety

ELRA Environmental Liabilities Risk Assessment

EMP Environmental Management Plan

EMS Environmental Management System

EN

Standard maintained by CEN (European Committee for

Standardisation)

Env Environmental

EPA Environmental Protection Agency

Page 6: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

ERT Emergency Response Team

ESIA European Semi-Conductor Industry Association

EU European Union

F Fluoride

F10/F14/F24 Fab 10/Fab 14/Fab 24

Fab Semi-conductor fabrication (manufacture) facility.

F-gas Regulations Fluorinated Gas Regulations

FMS Facilities Management System

FSM Fab Sort Manufacturing

GC Gas Chromatography

GHG Green House Gas

GWP Global Warming Potential

HAPs Hazardous Air Pollutants

Haz Hazardous

HCFC Hydrochlorofluorocarbon

HCl Hydrochloric Acid

HF Hydrofluoric acid

HFC Hydrofluorocarbon

HVAC House Vacuum

HVM High Volume Manufacturing

IFM Integrated Facilities Management

IFO Ireland Fab Operations (Fab 10 and Fab 14)

IPA Isopropyl alcohol

IPPC Integrated Pollution Prevention and Control

IPPCL Integrated Pollution Prevention and Control Licence

IR Ireland

IR1-IR6 Intel Ireland Office Building Nomenclature

IRCS Ireland Corporate Services

Page 7: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

ISO International Standards Organisation

ISO 14001 Accredited Environmental Management System

JIA Japanese Semiconductor Industry Association

Kg Kilogram

KIA Korean Semiconductor Industry Association

l Litre

LOD Limit of Detection

Ltd Limited

m Metre

M Measurement

m3 Cubic metre

MAH Make-up Air Handler

Maximo

A task management system that controls maintenance

programmes within CS and EHS

mg Milligram

micron Micron, unit of measurement equal to 10-6 meter.

mm Millimetre

MMTCE Million Metric Tonnes Carbon Equivalent

MOM Method of measurement

MREP

Material Request Evaluation Process (Chemical Approval

System for Intel)

MS Mass Spectrometry

MTCE Metric Tonnes Carbon Equivalent

MW Megawatt

MW Monitoring well

N/A Not Applicable

Nm3 Normal cubic metre

NO2 Nitrogen dioxide

Non-haz Non-hazardous

Page 8: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

NOx Nitrogen oxides

NUI National University of Ireland

OHSAS Occupational Health & Safety Advisory Services

Ops Operations

P Phosphorus

PER Pollution Emission Register

PFC Perfluorocarbons or Perfluoro compounds

POU Point of Use

PRTR Pollution Release and Transfer Register

RCTO Rotary Concentrator Thermal Oxidiser

REACH

Registration, Evaluation and Authorisation and Restriction of

Chemical Substances

RMP Residual Management Plan

RODI Reverse Osmosis De-Ionised

S.I. Statutory Instrument

sccm Standard cubic centimetre per minute

SCW Slurry Copper Waste

SIA Semiconductors Industry Association

SOG Spin on glass (process which produces polyimide waste)

Sort Electrical Testing Facility

SRF Solid Recovered Fuel

TA Luft German regulation for air quality standards

TD Technology Development

TOC Total Organic Carbon

UPS Uninterruptible Power Supply

VOC Volatile Organic Compounds

WSC World Semiconductor Council

WWTP Waste Water Treatment Plant

Page 9: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

1

1.0 INTRODUCTION

1.1 SITE DETAILS

Licence Register No: P0207-03

Licensee Name: Intel Ireland

Address: Collinstown Industrial Park, Leixlip, Co. Kildare

1.2 DESCRIPTION OF CAMPUS ACTIVITIES

1.2.1 Intel Ireland – Campus Overview

The Intel Ireland campus is located at Collinstown Industrial Park, Leixlip, in County

Kildare. Intel Ireland Ltd is a subsidiary of Intel Corporation and the site at Leixlip is

Intel's sole manufacturing centre in Europe. The complex plays a significant role in

the company‟s continuing worldwide success. Intel Ireland first decided to locate a

technology campus in Ireland in 1989 and production of motherboards and systems

commenced in the following year. Since then, over $7.5 billion has been invested in

turning the 360 acre former stud farm into the most technologically advanced

industrial location in Europe.

The current IPPC licence (Register No. P0207-03) relates to the activity of the

manufacture of integrated circuits and printed circuit boards, surface coating

activities and the operation of combustion installations with a rated thermal input in

excess of 50 MW.

Three wafer fabrication buildings (or „Fabs‟) currently exist on site including Fab 10

and Fab 14 (collectively known as Ireland Fabrication Operations (‘IFO’) and Fab 24

(including Fab 24 and Fab 24-2). Fab 14 ceased production in late 2009 to position

the factory for future development and any production requirements either ceased or

were moved to the Fab 10 facility. During the course of 2010, Fab 10 was equipped

to run several individual products using 200mm wafer technology to produce logic

devices. Fab 24 processes 300mm wafers on both 90 and 65-nanometer process

technologies.

Page 10: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

2

The campus is also home to other Intel Ireland businesses including the Intel®

Innovation Centre (IIC). The IIC has global responsibility to research and develop

innovative leading-edge IT solutions and technology. It involved a total investment by

Intel Ireland of over €12 million. The IIC is at the forefront of demonstrating how

Information Technology and Intel products can continue to deliver new competitive

advantage through the development of compelling new IT value propositions. The

centre, in partnership with NUI Maynooth, has set up the Innovation Value Institute, a

multi-disciplinary research and education institute, which was designed to help

achieve sustainable economic value from IT and quantify and understand the true

business value of strategic IT investments.

The Technology Research for Independent Living (TRIL) centre is located at the

Leixlip campus and is part of our Digital Health initiative. TRIL brings together world-

class industry and academic experts who are inventing and testing new technologies

with older people and their families to support them in continuing to live healthy and

independent lives. Intel Ireland funds over 50 PhD‟s and works closely with the

CRANN Nanoscience Research Centre in Trinity College Dublin and the Tyndall

National Research Institute in Cork.

Intel Ireland strives to be a trusted, leading corporate citizen. It aims to integrate

social responsibility and uncompromising integrity into everything we do, working to

advance people and better the planet through active commitment to education,

community and environmental sustainability. This is exemplified through initiatives

such as Intel Involved (an employee voluntary scheme for projects within the

community) and Community Advisory Panel (CAP, a group of diverse interests within

the community and Intel representatives which meet to discuss community projects

and issues on a quarterly basis)..

1.2.2 Manufacturing Facilities Overview

In 2010, Intel Ireland consisted of two manufacturing facilities on the site; IFO (Fab

10 and Fab 14) and Fab 24 (Fab 24 and Fab 24-2).

Fab 14 ceased manufacturing in late 2009 and all manufacturing operations which

took place there have either ceased or were moved to the Fab 10 facility. The

purpose of the shut down of Fab 14 was to position the facility for potential future

conversion and reuse. During 2010, a comprehensive decommissioning programme

was carried out at the Fab 14 facility under strict EHS conditions. This involved

Page 11: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

3

decontamination of all production equipment in the cleanroom and all associated

abatement equipment. The majority of production tools and abatement systems

were de-installed and either sent to other Intel sites for reuse or disposed of by

approved waste vendors. The remaining equipment has been retained for future use.

During 2010, Fab 10 manufactured chips using advanced manufacturing technology

at the 0.13 and 0.25 micron node. In lay person‟s terms, at these nodes, millions of

transistors are created on an integrated circuit (chip) the size of a finger-nail.

Fab 24 first began producing the industry‟s most advanced 300mm/12” wafer

technology in 2004. The Fab 24 building is 52,000 square metres in size, which

includes a 15,000 square metre „Class 1‟ clean-room for the manufacture of chips.

Moving to 300mm wafers allows over twice the number of chips to be created on

each wafer compared with 200mm wafers, leading to a 30 per cent improvement in

productivity and costs. The sophistication of the process equipment and the level of

automation involved place Fab 24 at the very forefront of semiconductor

manufacturing which is widely recognised as the summit of manufacturing

technology.

Fab 24 manufactures single and multi-core microprocessors. There are two

manufacturing processes, 90nm (nanometre) which is in production since 2004 and

65nm which started in 2006. Fab 24 is a fully automated plant where all material

handling is fully automated and computer controlled.

Fab 24-2 is a newer facility, completed at the end of 2005. It is connected to Fab 24

and adds an additional 5,000 square metres of manufacturing „Class 1‟ clean-room

space, plus the necessary manufacturing equipment to enable the latest 65nm

technology. Production commenced in Fab 24-2 in the first quarter of 2006.

1.2.3 Process Steps Overview

Fabrication Plants which produce the silicon-based devices use complex processes

involving billions of dollars of equipment and 300-500 operational steps all housed in

an ultra-clean environment. The material does not move through the factory in a

linear fashion from front to back, but loops back on itself, revisiting some areas

sometimes more than twenty times.

The Fab buildings each contain major areas in which wafers are processed. These

areas are referred to as "Functional Areas" and include Diffusion, Lithography, Etch,

Page 12: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

4

Thin Films and Planarization. The general principles of manufacturing

microprocessors are that the wafer is passed between the different areas to build up

a complex 3-dimensional device on the surface of the wafer. External contacts for

the microprocessors are made by what is known as the "Controlled Collapse Chip

Connect" process, also known as the “C4" process.

The manufacturing activities carried out on site fit into a number of categories. These

are:-

Diffusion: Where layers are introduced or „grown‟ on a semiconductor wafer

under high temperature conditions. Implanted chemicals are then introduced

to selectively change the electrical properties of sections of the wafer.

Lithography: creation of patterns for the electrical circuits on the wafer

surface in a process similar to photography using ultraviolet light passing

through apertures in a mask to selectively expose areas of the wafer.

Etch: translates the pattern created by lithography into a three-dimensional

structure by selectively etching channels into the surface substrates.

Thin Films: a film of material is introduced to either create conductive

interconnects between layers, electrical isolation or protection from the

environment.

Planarisation: the surface of the wafer is polished by the use of mechanical

and mild chemical abrasives to achieve a uniform flat layer.

Ion Implantation: used to introduce impurities or „dope‟ the silicon with

materials such as phosphorous, boron or arsenic. Implantation changes the

electrical characteristics of specific areas of the wafer.

The wafer will pass through each of these functional areas many times before

the full three-dimensional structure of each integrated circuit has been built

up. Each wafer may contain several hundred integrated circuit, with each die

forming the basis of a „silicon chip‟.

C4 Process: To allow each integrated circuit to be connected to a printed

circuit board for installation into computers, connections must be created to

connect the circuit to other electrical components on the board. For some

product types, these connections are produced in the "C4" process. During

this step, copper connects are introduced onto the circuit by an electrolytic

process. This process is currently only carried out in F24. Previously, IFO

Page 13: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

5

used tin and lead connects instead of copper. However, C4 operations in IFO

ceased production during 2009.

Sort: Each chip is then electrically tested in a quality assurance step known

as Sort and then distributed to other Intel plants outside Ireland for final

packaging.

1.2.4 Environmental Abatement

Each fabrication building essentially carries out a similar manufacturing process with

progressive refinements for improved technology as smaller dimension technology is

introduced. Some variations do, however, occur in the treatment of waste generated

from certain processes. The major environmentally significant differences in

technology employed in Fab 24 from that in IFO include the following:-

Copper: The introduction of copper metal layers into the planarization, thin

films and C4 processes and the treatment of copper wastes arising.

VOC Abatement: Rotary concentrator / thermal oxidiser (RCTO) units have

been included in Fab 24 (and also retrofitted into Fab 10) to treat the

concentrated solvent exhausts from wafer manufacturing operations.

POU Scrubbers and Hydrofluoric/Phosphoric Acid Waste Treatment:

Additional Point of Use (POU) scrubber systems were introduced to reduce

emissions of perfluorinated compounds (PFCs) and provide enhanced

fluoride removal from air emissions.

Hydrofluoric/Phosphoric Acid process effluent is also produced whereby

fluoride/phosphate containing wastewaters (including the additional POU

systems) are converted to a benign solid waste as per existing practice in

Fab 10.

Ammonia Exhaust System: The introduction of an ammonia exhaust system

has segregated ammonia emissions from the main acid gas scrubber

systems and optimised the removal efficiency of both treatment systems.

This has resulted in a reduction in overall emissions.

Ammonia Wastewater Treatment System: In order to reduce the amount of

ammonia based compounds being discharged to the Leixlip Wastewater

Treatment Plant (WWTP), an Ammonia Wastewater Treatment System has

been installed at Fab 24. A proportion of ammonia based compounds are

Page 14: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

6

collected and converted into ammonium sulphate. The treated wastewater,

which now has a much reduced concentration of ammonia, is then

discharged to Leixlip WWTP. The only other discharge from the Treatment

System is a vent which is classified as a minor emission point.

1.2.5 Support Activities

To support manufacturing operations, a number of on-site utilities including chemical

storage and handling facilities, ultra pure water treatment plant, bulk gas plants,

boilers and chillers along with wastewater treatment plants are required. These

provide the raw materials, conditions and services necessary for the manufacturing

process.

1.3 ENVIRONMENTAL POLICY

Intel Ireland operates a rigorous Environmental Management System (EMS), which

is independently certified to the international environmental management standard,

ISO 14001:2004. An EMS is a requirement of our Integrated Pollution Prevention

and Control (IPPC) licence. Having a certified EMS creates additional confidence in

the standard of our environmental controls.

The aspects of energy management are embedded in our Environmental Systems

and Policy. Hence, the site's Energy Policy is incorporated into the overall

Environmental Policy. The Intel Ireland site received accreditation to the Irish Energy

Management Standard (IS 393:2005) in December 2007 and to EN 16001 in June

2010.

In line with ISO 14001 and EN 16001 requirements, and to demonstrate the sites

commitment to Environmental Management, Intel Ireland has developed an

Environmental Policy. This policy is reviewed, updated and then signed by the site

managers on an annual basis. A copy of the 2011 Environmental Policy is outlined

overleaf.

Page 15: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

7

Page 16: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

8

1.4 ENVIRONMENTAL MANAGEMENT ORGANISATIONAL STRUCTURE

This section details the roles, responsibilities and interrelations of key staff responsible

for environmental activities. The Environmental management structure is represented

below.

Intel Ireland General Manager

The Intel Ireland General Manger has overall responsibility for Environmental

Management on the site. He/She is responsible for the assessment of the site‟s

Environmental performance against its stated targets and objectives. The General

Manager also sets direction during the annual review and facilitates the achievement of

these targets and objectives by attending Environmental Operations (Environmental

Ops) meeting which occur on a formal basis at least once per year. During 2010, the

Intel General Manager, Jim O‟Hara, resigned his position and the role was filled by

Eamonn Sinnott.

Ireland Corporate Services (IRCS) Manager

The IRCS Manager reports to the CS FSM TD Worldwide Manager and has overall

responsibility for Environmental Management in the IRCS area. He/She participates in

the assessment of the site and, in particular, Corporate Services' (IRCS) Environmental

Performance against its stated goals and objectives. The CS Manager sets direction

during the annual review and ensures that the CS targets and objectives are met.

IFO/Fab 24 Factory Managers

The IFO/Fab 24 Factory Managers have overall responsibility for Environmental

Management in their specific plant. He/She participates in the assessment of the site

and, in particular, their plant‟s Environmental performance against its stated targets and

objectives. The Factory Manager sets direction and ensures that the targets and

objectives are met.

Page 17: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

9

Environmental Health and Safety (EHS) and Security Manager

The Intel Ireland EHS and Security Manager reports to the IRCS Manager and is

responsible for the day-to-day management of the Environmental Health and Safety

Department within the site. The EHS Manager has overall responsibility for

Environmental Management across the site and for achieving stated Environmental

targets and objectives. He/She sets direction on environmental matters and ensures that

Intel Ireland remain in compliance with relevant legislation. The EHS manager advises

the IRCS Manager of requirements to ensure sufficient resources are in place to run the

EMS.

Environmental Department

The Environmental Department currently comprises of six engineering or environmental

science graduates whose work is subdivided to deal with many aspects of

environmental programme management including:

Integrated Pollution Prevention and Control Licence (IPPCL)

Greenhouse Gas (GHG) Emissions Permit

Environmental Management System (EMS)

Community and internal environmental awareness

Essentially, the objective is that the operation of the activity complies with all applicable

environmental regulations and policies, and that the site‟s environmental management

system is managed in a sustainable fashion for social, environmental and economic

purposes.

Emergency Response Team (ERT)

The Site Emergency Response Team is responsible for the facility during an

emergency. An ERT leader, who directs operations during an emergency, leads the

team. ERT have specialised training to deal with a range of potential incidents.

Page 18: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

10

2.0 SUMMARY INFORMATION

2.1 SELF-MONITORING DATA

2.1.1 Emissions to Sewer

Wastewater parameters are monitored as per requirements under Schedule C.3.2 of

Intel Ireland‟s IPPC licence on the basis of daily flow-proportional composite sampling.

Flow, pH and temperature are measured on a continuous basis before being discharged

from the site.

Licensed effluent flows and mass emissions to the Kildare County Council Wastewater

Treatment Plant (WWTP) in Leixlip for 2010 are compared with 2009 licensed emissions

data (Tables 2.1 and 2.2).

Table 2.1 - Summary of Licensed Effluent Flow to Sewer for 2010 compared with 2009.

Parameter

Volumetric

Emissions (m3)

2009

Volumetric

Emissions (m3)

2010

Licensed

Volumetric

Emissions (m3)

Flow (m3) 4,230,095 3,590,662 6,022,500

Page 19: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

11

Table 2.2 – Summary of Licensed Effluent Emissions to Sewer for 2010 compared with 2009.

Parameter *Mass Emissions

(Kg) 2009

*Mass Emissions

(Kg) 2010

Licensed Mass

Emissions (Kg)

BOD 92,409 107,845 492,750

COD 85,349 34,722 985,500

Inorganic Suspended Solids Note 1 31,876 985,000

Total Suspended Solids <42,700 <45,676 1505625

Total Dissolved Solids <2,859,953 2,048,580 22,108,050

Total Phosphorus (as P) 4,249 3,835 24,638

Total Nitrogen 70,981 48,657 197,100

Fluoride 16,900 <14,391 58,400

Cyanide - <3.872 493

Tin <17.0 <1.43 1,971

Lead <3.14 <5.97 584

Chromium <6.33 <0.25 493

Nickel <13.6 8.93 986

Copper <177 160 1,478

Arsenic <1.75 <0.78 493

Total Heavy Metals Note 2

<219 <177 4,928

Cobalt <1.57 <0.78 N/A

Sulphates 1,520,000 1,146,432 N/A

Ammonia 52,300 48,587 N/A

Nitrates 8,340 - N/A

* For the purposes of the 2010 Annual Environmental Report and Pollutants Release and Transfer Register (PRTR), Intel Ireland has calculated the annual average wastewater mass emissions of the incoming „City Water‟ and subtracted this from the annual Intel Ireland wastewater mass emissions. Where there is a “less than” value, some results were below the limit of detection for this parameter. A submission to the Agency regarding the modification to the mass calculation method was submitted on the 15

th of March 2005. Where the incoming mass emission has been greater than or equal to

the wastewater mass emission the cell has been left blank.

Note 1: Inorganic Suspended Solids were monitored in 2010 after being added as a licence parameter through a technical amendment received in 2010 (Technical Amendment A to licence register no. P0207-03).

Note 2: Total Heavy Metals is the sum of Arsenic, Tin, Lead, Chromium, Nickel and Copper

Page 20: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

12

Where the concentrations of parameters measured during 2010 were reported as below

the limit of detection, the parameter has been assumed to be equal to the detection limit

to enable average concentrations and annual emission rates to be calculated. The

reported concentrations and emission rates are thus reported as „less than‟ the

calculated values.

A detailed summary of all wastewater emissions to Leixlip WWTP is included in the

PRTR found in Appendix A.

2.1.2 Emissions to Surface Water

Under Condition 6.1 of the IPPC licence, we are required to carry out the monitoring as

detailed in Schedule C.2.3. A summary of the analysis results is detailed in Table 2.3.

Table 2.3 - Summary of Monitoring Results SW1 (Storm Water Emissions), 2009 and 2010

Parameter Monitoring

Frequency

Units Average

Emission 2009

Average

Emission 2010

pH Continuous pH 8.0 7.9

Conductivity Weekly µS/cm 520.9 694.9

COD Weekly mg/l <15.6 <17.9

TOC Weekly mg/l <5.0 <5.4

Arsenic Biannual µg/L <2 <2

Chromium Biannual µg/L <2 <2

Cobalt Biannual µg/L <2 <2

Copper Biannual µg/L 8.5 55

Nickel Biannual µg/L <2 <2

Tin Biannual µg/L <2 <2

Lead Biannual µg/L <2 <2

Page 21: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

13

2.1.3 Emissions to Atmosphere

This section provides a summary of the annual emissions to atmosphere from licensed

emission points identified in Intel‟s IPPC Licence. Emissions are derived from five main

sources including:

boiler and generator emission sources (NOx and CO);

acid scrubber exhausts (acid gases);

specialty exhausts (arsenic and total dusts);

RCTO Emissions (volatile organic compounds, VOC, NOx and CO).

Table 2.4 compares annual average mass emission limits for 2009 and 2010 against

equivalent maximum mass emission limits for those years. The equivalent mass

emission limit was calculated by multiplying the concentration emission limit value by

the flow limit for each emission point. The equivalent mass emission limits calculated

for 2010 excluded licenced emissions for Fab 14 due to the Fab 14 shutdown. Hence,

the 2010 equivalent mass emission limits are slightly lower than the calculated limts

for 2009.

Although there is no equivalent mass emission limit for the site‟s NOx and CO

emissions (from boilers and RCTOs), due to the fact that there are no flow ELVs for

the boilers, all results were below the concentration ELVs for these parameters.

There was an increase in NOx emissions due to an increase in diesel consumption

for the boilers and emergency generators in 2010.

One may observe from the table that the total fluoride, gaseous hydrofluoric acid and

total acids mass emissions from 2010 are approximately double the emissions for

2009. This was due to a change in air monitoring vendor in Q4 2009. The new

vendor employed different sampling methodologies which led to elevated results for

some parameters but all results were within IPPCL limits.

The TA Luft Organics Class 3 and TOC results for 2009 are high due to an

anomalous result for one of the quarterly monitoring events which skewed the mass

emission results for the year.

Page 22: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

14

Table 2.4 – Total Site Annual Mass Emissions to Atmosphere for 2010 compared to 2009 values

Parameter Equivalent Max. Mass Emission Limit 2009 (Kg)

Annual Emission 2009 (Kg)

Equivalent Max. Mass Emission Limit 2010 (Kg)

Annual Emission 2010 (Kg)

Ammonia 10,722 24 10,722 21

NOx (as NO2) N/A 17,514 N/A 33,800

CO N/A 8,072 N/A 8,712

Total Acids (as HCl) 217,806 1,055 58,511 3,595

Gaseous HF 14,702 182 3,949 376

Total Fluorides 5,447 384 4,054 774

TA Luft Organics Class 1 14,296 331 7,358 278

TA Luft Organics Class 2 62,722 245 28,032 233

TA Luft Organics Class 3 122,114 4,005 70,080 2,022

Total Organics (as C) 4,588 3,405 3,504 93

TA Luft Inorganic Dust Particles Class 1 26 1.79 12 0.83

TA Luft Inorganic Dust Particles Class 2 82 2.97 34 1.57

TA Luft Inorganic Dust Particles Class 3 82 4.10 34 7.47

Total Dusts 8,194 62 3,401 152

There was one non-compliance in relation to emissions to atmosphere in 2010, the

details of which are shown in Table 2.5

Page 23: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

15

Table 2.5 - Details of Non-Compliances Relating to Air during 2010

Date Non-compliance Cause Corrective Action

27/04/10 Exceedance of

Volumetric Flow

Limit at Fab 10

and Fab 24 RCTO

Oxidisers

The previous

monitoring vendor

had not corrected the

volumetric flow rate to

18% oxygen, as

stated in condition

4.2.2 of our licence.

This was noticed

when the air

monitoring vendor

was changed.

A technical amendment to

our licence was submitted

and the proposed limit of

4,000 Nm3/hr for the

RCTOs oxidiser emission

points was approved by

the Agency and this may

be referenced as P0207-

03 Technical Amendment

B.

2.1.4 Summary of Waste Data

A summary of the waste data is outlined in Tables 2.6 to 2.8.

Table 2.6 – Summary of Total Waste for 2010 (Tonnes)

Total Waste 7639.48

Total Waste Disposed of 1362.43

Total Waste Recovered 6277.05

Page 24: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

16

Table 2.7 – Summary of Hazardous Waste for 2010 (Tonnes) compared to previous years

Waste Description 2007 2008 2009 2010

Corrosive Lead 3.75 *Note 1 *Note 1 *Note 1

Corrosive Arsenic 14.97 *Note 1 *Note 1 *Note 1

Flammable Arsenic 10.07 *Note 2 *Note 2 *Note 2

Flammable Debris 70.41 86.57 73.41 78.99

Corrosive Debris 167.02 150.30 289.43 519.44

General Solvent 1,814.26 1,728.84 1,380.83 1,147.07

Lead Reclaim Waste 9.91 0.00 14.14 0.00

Reclaim Metal Waste 53.26 18.78 16.42 45.44

Lead/Metal Waste-concentrated 774.21 689.24 648.66 263.38

Copper Waste-concentrated 64.95 71.80 72.06 36.22

Phosphoric Acid Waste 479.42 599.38 510.84 416.08

Ammonium Sulphate Waste 627.74 711.30 700.30 695.00

Fluorescent Lamps and fittings 1.96 2.77 2.40 2.87

Batteries 10.08 58.03 44.19 6.13

Clinical Waste 0.19 0.16 0.14 0.00

Waste Refrigerants 0.00 0.00 0.13 0.17

Used Oil 2.50 4.75 3.00 1.80

Resin 40.55 43.40 21.00 22.72

Carbon 0.00 0.00 0.00 5.1

KD100 8.10 0.00 32.58 19.94

Tank decontamination washings 0.00 0.00 0.00 78.00

Copper Chromate Arsenic Treated Timber 0.00 0.00 2.40 0.00

SOG – Polyimide recovery waste 0.27 0.43 0.00 0.20

Arsenic Slurry Waste 2.92 6.74 3.01 1.52

Labpacks* Note 3

31.91 28.29 88.30 31.30

Page 25: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

17

Table 2.7 (continued) – Summary of Hazardous Waste for 2010 (Tonnes) compared to

previous years

Waste Description 2007 2008 2009 2010

Copper with residual sulphuric acid and copper sludge 6.50 7.58 9.91 9.24

Total Recovered 3,790.19 3,829.01 3,395.72 2,456.98

Total Disposed 537.11 379.35 517.43 923.63

Total Hazardous Waste 4,327.30 4,208.36 3,913.15 3,380.61

% of Total Hazardous Waste Recovered 87.59 90.99 86.78 72.68

*Note 1- The corrosive lead and corrosive arsenic debris numbers was incorporated into the corrosive debris number

*Note 2 - The flammable arsenic debris number was incorporated into the flammable debris number for 2008, 2009 amd 2010

*Note 3 – The definition of lab packs is used to describe the disposal of expired chemicals

Overall the amount of hazardous waste generated in 2010 decreased. This is

predominantly related to the downturn in production. Also Fab 14 ceased production in

late 2009 with no replacement manufacturing process in Fab 14 in 2010. Similarly,

operations in Fab 10 were reduced in 2010. The amount of waste disposed of

increased in 2010 mainly due to Fab 14 de-installation waste shipments in Q1 2010 and

also a reduced volume of waste which is usually recycled at Fab 10 (e.g. solvent waste

tankers). Overall in 2010, corrosive debris increased. This is again related to the Fab 14

de-installation work which generated large volumes of corrosive pipework, tank systems

and tools for breakdown. General solvent waste decreased due to the elimination of

solvent waste flows from Fab 14 and reduced production in Fab 10. Concentrated

lead/metal waste flows reduced due to the discontinuation of the lead process and

associated lead treatment system in Fab 14. Similarly, the amount of resin sent off-site

decreased as the dilute lead waste resin exchange system was removed from Fab 14.

Concentrated copper waste decreased as a new method of removal of CCW sludge was

implemented. This is further described in our EMP section (Table 3.3). The volume of

batteries generated in 2010 was much less than 2009 as in 2009 there was large scale

change out and de-installation of UPS systems at the site.

Page 26: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

18

Table 2.8 – Summary of Non-Hazardous Waste (Tonnes) 2010 compared to previous years

Waste Description 2005 2006 2007 2008 2009 2010

All Paper Recycled 32.89 20.64 10.26 2.99 3.14 13.32

Cardboard Recycled 107.18 141.64 57.68 66.43 36.46 11.22

Metal Recycled 115.92 445.47 291.56 281.58 1,065.36 2,152.6

Plastic Recycled 29.78 37.9 8.32 1.52 79.98 121.86

Wood Recycled 203.34 502.22 239.28 206.14 112.59 109.58

Other Recycled Note 2

1094.9 960.26 2466.90 783.3 2,065.40 1,411.49

General Non-

hazardous

(disposed) 562.29 1078.39 274.23 264.92 319.38 75.98

General Non-

hazardous C&I

(disposed) 287.53 327.34 409.02 291.41 189.4 73.44

General Non-

hazardous C&D

(disposed) 0 0 15.08 0 0 0

Calcium Fluoride

Cake 761.86 966.8 900 845.42 470.42 289.38

Non-Hazardous

Aqueous Waste 193.5 0 0 0 0 0

Page 27: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

19

Table 2.8 (continued) – Summary of Non-Hazardous Waste (Tonnes) 2010 compared to

previous years

Waste Description 2005 2006 2007 2008 2009 2010

Total Recovered 1,584.01 2,435.47 3,074.4 1,341.95 3,362.93 3,820.07

Total Disposed 1,805.18 1,840.25 1,598.32 1,401.75 979.2 438.8

Total Non-

Hazardous Waste 3,389.19 4,275.72 4,672.72 2,743.71 4,342.13 4,258.87

% of Total Non-

Hazardous Waste

Recovered Note 1

46.74 56.96 65.79 48.91 77.45 89.7

Note 1: The above recycling figure for non-hazardous waste includes calcium fluoride cake which is a non hazardous waste.

Note 2: ‘Other Recycled’ includes; Cables, WEEE, Glass, Clothing, Compost, Mixed Packaging, Sludge, Resin, Municipal Mixed Waste, C&I Mixed and C&D mixed waste

In 2010, the volumes of non-hazardous waste generated from site remained similar to

2009 due to on-going de-installation works in the Fab 14 facility. The tonnage of waste

to recovery increased in 2010, while waste volumes to landfill decreased significantly

from 2009 (primarily due to a decrease in calcium fluoride filter cake.) Overall, the

percentage of non-hazardous waste recovered increased from 77.5% in 2009 to 89.7%

in 2010 as a result of an increase in generation of recoverable waste from the Fab 14

de-installation project and continuous improvement in waste segregation at waste

contractor‟s facilities.

A detailed summary of all waste streams sent off-site from Intel Ireland for disposal is

included in the PRTR found in Appendix A.

2.2 AGENCY MONITORING AND ENFORCEMENT

2.2.1 Agency Monitoring Visits

The various monitoring visits made by the Agency during 2010 are outlined in Table

2.9a below.

Page 28: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

20

Table 2.9a - Agency Monitoring Visits 2010

Date of Visit Purpose of Visit

19th January 2010 Surface water and waste water sampling

13th April 2010 Surface water and waste water sampling

5th July 2010 Surface water and waste water sampling

27th September 2010 Air sampling

5th October 2010 Surface water and waste water sampling

In relation to the wastewater and surface water samples taken, a comparison was

carried out between the EPA results and the Intel split samples that were analysed by

an external laboratory. While some differences were noted, none of the detected

parameters were over Intel‟s IPPCL limits.

2.2.2 Agency Inspections

There were four Agency inspections during 2010 which are outlined in Table 2.9b below:

Table 2.9b - Agency Inspection Visits 2010

Date of Visit Purpose of Visit

25th January 2010 EPA Inspectors Audit

2nd

February 2010 EPA and Department of the Environment Visit for PFOS

Regulations

16th April 2010 EPA Site Inspection Visit

22nd

October 2010 EPA Visit for GHG Permit inspection

Page 29: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

21

2.3 RESOURCE MANAGEMENT

2.3.1 Introduction

This section identifies resource and energy use on site and outlines reduction measures

used by the company.

The management systems in place for the design of wafer fabrication facilities and the

associated processes ensure that raw material usage and energy use arising from site

activities are further reduced at source per unit produced for successive generations of

technologies where possible. The environmental goals of minimisation, substitution and

recycling are employed to ensure resource use is minimised and resources are used

efficiently.

Raw material conservation, emission and waste reduction are achieved through a

combination of:-

Cleaner and more efficient process technology to reduce raw material inputs and

produce lower emissions and wastes

Material substitution with lower toxicity alternatives or those that generate lower

emissions such as low volatility chemicals

Recycling or recovery of raw materials and waste products

In addition to chemical and gas consumption minimisation, resource conservation is

focused on the efficient use of electricity, gas and water on the site.

Details of the methods employed and results are briefly described in Sections 2.3.2 to

2.3.3 below.

2.3.2 Design for the Environment (Technology Goals)

Intel Corporation develops and delivers a new chip manufacturing technology

approximately every two years. The development cycle starts typically with six years

external research in universities and government labs, followed by approximately four

years joint research and development between Intel and suppliers followed by two years

process development to produce a fully functional technology before transfer to high

volume manufacturing (Figure 2.1). Intel has recognised that there is an opportunity for

Page 30: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

22

early engagement to effect change for environmental benefit during external and joint

research, in addition to when the process is in high volume manufacturing mode.

However, the optimum time to effect change for environmental design of the process is

during the 2 years of final process development. The Intel Environmental Technology

Development (TD) group is involved throughout this timeframe and has input into

manufacturing process development, chemical selection, waste management, facility

systems design and manufacturing equipment selection.

Figure 2.1 Effecting change during Intel process technology development

For each technology, goals are set for specific types of emissions, for example: - mass

of VOCs or copper emitted per wafer produced. The methodology used for the setting of

these goals is to first evaluate the receiving environment at each of the High Volume

Manufacturing (HVM) sites. Items considered during this review would include existing

site permits, local area regulations, wastewater treatment plant capacity, air and water

quality standards and demographic growth projections. Against this data is set projected

wafer manufacturing capacities at each of the HVMs for each of the technologies. From

this are derived acceptable emissions/wafer figures for each of the HVM sites. To set

the corporate goal, the lowest emission/wafer figure so calculated is used. Once the

Page 31: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

23

goals have been ratified at the appropriate management level, measures are put in

place during the development cycle to ensure the targets are met. Measures include

material selection, material substitution, recipe optimisation, emissions treatment and

waste segregation. In this way, the Corporation aims to ensure that the transfer of

technologies to the HVMs can be successfully transferred without detrimental effect on

the local environment.

Once the technology is transferred to a receiving HVM site, such as Intel Ireland, actual

emissions per unit of product for each parameter are sampled and reported to

development and receiving factory site management to confirm that, when the

technology is run in high volume manufacturing conditions, it performs to the goals that

the Technology Development (TD) group is required to deliver.

The oldest technology being manufactured at the Ireland site (0.35 micron) was

developed in 1995. The latest technology (0.065 micron or 65 nanometres) started

manufacture at Intel Ireland in 2006. The 0.35 micron technology line is now a small

portion of the overall capacity at Intel Ireland. The vast majority of current capacity runs

the more advanced technologies where the benefits of emissions reductions are

realised.

Since the inception of the environmental technology goals process, a number of

additional parameters have been included in the more recent years. Currently Intel has

technology goals for reducing emissions and waste per wafer produced including the

following parameters:

Emissions to Atmosphere:

o PFC, VOC and HAPs

Emissions to Waste Water

o CMP Solids

o Ammonia

o Copper

o Lead

o Nickel

Page 32: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

24

o Cobalt

o Tin

o Fluoride

Waste

o Mass of chemical waste

2.3.3 Supplier Environmental Performance Targets

Equipment or „tool‟ design is a significant area of research for Intel and Intel„s equipment

suppliers. Intel requires that equipment suppliers design tools to minimise environmental

emissions and resource consumption by including specific target emission levels on a

per wafer processed basis in the equipment contractual purchase specifications. This

practice ensures environmental considerations are designed into the process tools from

the conceptual phase. Tool vendors are required to select gases and chemicals that can

meet the target and must then carry out emissions characterisation on exhaust and

waste streams. Since Intel introduced environmental emission targets to equipment

vendor purchase specifications, the vendors have become more aware of the

environmental considerations arising from their tools and are often in a more appropriate

position than Intel to address any issues.

2.3.4 Water Consumption and Minimisation

The usage of water is a function of several variables including production levels and

water conservation measures in place. There is a base loading on the factories that is

independent of production levels arising from systems such as cooling towers and

exhaust air treatment systems. Therefore, when a facility is operating at lower

production rates, water usage expressed in terms of volume per unit produced can be

adversely affected. For this reason total water consumption is provided for the site

overall. There is a marked decrease in water consumption in 2010. This is mainly

related to the shutdown of Fab 14. In addition, in 2010, a water conservation project

was completed which will result in annualized savings of water of 268,440 m3. Details of

Page 33: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

25

this project are outlined in Section 3.2 (Environmental Management Programme Report

2010).

Table 2.10 - Total Water consumption for Site

Parameter 2009 2010

Total Water Usage (m3) 4,239,451 3,758,950

2.3.5 Energy Consumption

Consumption of energy (electricity, natural gas and oil) for 2009 and 2010 are detailed in

Table 2.11, and is followed by a discussion of results.

Table 2.11 - Annual Energy Usage - Electricity, Gas and Oil

Parameter 2009 2010

Total Electricity Usage (MWh) 471,460 404,813

Total Natural Gas Usage (MWh) 168,420 173,400

Total Oil Usage (tonnes) 123 266

Total electricity usage decreased overall in 2010. This is attributable to the de-

installation of the Fab 14 manufacturing area and also the implementation of energy

savings projects. A sample of energy savings projects are provided in our

Environmental Management Programme (EMP) section. Gas consumption slightly

increased due to the damage to the coils of the Fab 24 Heat Recovery System in

February 2010 caused by severe cold weather. The increase in oil consumption

compared to 2009 levels is attributable to the increased running of emergency

generators (due to power disruptions) and running boilers on oil (due to interruptions

in natural gas supply) during 2010.

Page 34: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

26

2.3.6 Material Efficiency

2.3.6.1 Process Optimisation for Material Efficiency

Due to the very minute dimensions that are patterned onto a wafer during

manufacture, process chemical and gas flow set points need to be very exact.

Process optimisation through the statistical „Design of Experiments‟ methodology

is a practice used extensively throughout the process to determine the wafer

processing recipe set points such as gas and chemical flows and power during

technology development.

Using this method, tests are carried out by varying equipment recipe set points

and measuring the result on the wafer. For example, in a dry etch process; set-

point variables for an etchant gas may be tested at flow rates of 10, 12, 14 and

16 sccm. The flow that provides optimum results on the surface of the wafer is

selected. Process optimisation ensures that excess chemicals, gases or energy

are not consumed which conserves resources.

The move from 8 inch to 12 inch wafers has meant significant efficiencies are

achieved in relation to raw materials used per number of product units

manufactured. The 12 inch (or 300mm) wafer carries more than twice the

number of dies that can be produced on an 8 inch wafer. This economy of scale

has given rise to an increase in production without a proportional increase in

consumption of raw materials.

2.3.6.2 Yield Improvements

In all the manufacturing technologies operated on site, yield improvement is a

focus area. This covers the line yield, (the number of wafers that are not

scrapped in line), as well as die yield (which is the number of functioning die

per wafer at end of line). The continuous effort to improve yield gives rise to

more efficient use of raw material, thereby conserving resources.

For example; certain compounds reduce the number of defects on the product

which can cause failures in circuits and reducing die yield. Failed circuits are

discarded at end of process and require replacements. Use of these chemicals

Page 35: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

27

reduce these process losses and makes the manufacturing process more

efficient, thereby reducing overall emissions and resource use per unit of

production.

2.4 ENVIRONMENTAL INCIDENTS AND COMPLAINTS

2.4.1 Environmental Incidents

This section details the Environmental Incidents that occurred in 2010. Condition 11.7

of the Intel Ireland IPPC Licence required that -

The licensee shall submit to the Agency, by the 31st March of each year, an AER

covering the previous calendar year. This report, which shall be to the satisfaction of the

Agency, shall include as a minimum the information specified in Schedule D and shall

be prepared in accordance with any relevant guidelines issued by the Agency.

There was one environmental incident in 2010 as follows:

Exceedance of Volumetric Flow Limit at F10 and F24 RCTO Oxidisers (27th April

2010):

Intel Ireland changed the air monitoring vendor for Q4 2009. During routine air

emissions monitoring by the new air monitoring vendor, it was discovered that the

volumetric flows from the Fab 10 and Fab 24 RCTO oxidiser stacks (when corrected for

Standard Temperature, Pressure, Density and Oxygen) exceeded the volumetric flow

limit specified in the site‟s IPPC licence. Our previous monitoring vendor had not

corrected the volumetric flow rate to 18% oxygen, as stated in condition 4.2.2 of our

licence.

It is important to note that the RCTO abatement system settings and flow rates have

been constant during the vendor change and the pollutant concentrations at the RCTO

units are substantially below the emission limit values as set out in our IPPC licence.

Based on modelled flow rates of 6,000 Nm3/hr, there are no impacts of environmental

significance. Therefore, a Technical Amendment to our licence was submitted to the

EPA to seek a flow limit of 4,000 Nm3/hr. This amendment was approved by the Agency

Page 36: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

28

on the 1st March 2011 and is known as Technical Amendment B to the IPPC licence

(Register No. P0207-03).

In addition to the event above, we also reported the following events relating to

abatement and monitoring equipment to the EPA during 2010 (Tables 2.12 and 2.13). It

is important to note that during abatement system events, the associated monitoring

equipment showed that air emissions remained below licence limits at all times. In the

case of monitoring equipment failure, contingency monitoring showed that all air

emissions were in compliance.

Table 2.12 – Abatement Equipment Downtime 2010

Date Equipment Details

19/01/2010 Fab 10 RCTO RCTO bypass due to bearing failure

16/03/2010 Fab 10 RCTO RCTO bypass due to condensation in the impulse line

19/04/2010 Fab 10 RCTO Annual preventive maintenance

23/04/2010 Fab 10 RCTO RCTO bypass due to inlet damper failure

24/04/2010 Fab 10 RCTO Inlet damper failure

01/05/2010 Fab 10 RCTO Oxidiser chamber fault

06/06/2010 Fab 24 RCTO Fan malfunction

24/06/2010 Fab 24 RCTO Interruption to natural gas supply

13/07/2010 Fab 10 RCTO Interruption to natural gas supply

03/08/2010 Fab 10 RCTO Installation of natural gas pressure switch

15/09/2010 Fab 24 RCTO Planned shutdown

08/12/2010 Fab 10 RCTO Temperature controller issue

Page 37: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

29

Table 2.13 – Monitoring Equipment Downtime 2010

Date Equipment Details

09/03/2010 Fab 10 RCTO

Combustion Gas

Analyser

Unit taken down for essential maintenance

31/05/2010 Fab 10 RCTO TOC

Analyser

Unit taken down for essential maintenance

19/07/2010 Fab 24 RCTO TOC

Analyser

Preventative maintenance

03/12/2010 Fab 24 RCTO TOC

Analyser

Cold temperatures caused moisture in inlet

air to freeze

2.4.2 Complaints

The Corporate Affairs department deals with any complaint received from the public with

support from the environmental department.

Corporate Affairs maintains a log of all environmental complaints received from the

public. This log contains information regarding the complainant and the nature of the

complaint. Each complaint is communicated to the environmental department, the

complaint is investigated and an appropriate response is determined. Details of the

response are held in the complaints log.

There were no complaints of an environmental nature received in 2010.

Page 38: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

30

3.0 MANAGEMENT OF THE ACTIVITY

3.1 SCHEDULE OF ENIVIRONMENTAL OBJECTIVES AND TARGETS

Under Condition 2.2.2.2 of Intel‟s IPPC licence (Register No. P0207-03), Intel is obliged

to do the following:

“The licensee shall maintain a Schedule of Environmental Objectives and

Targets. The Schedule shall as a minimum provide for a review of all operations

and processes, including an evaluation of practicable options, for energy and

resource efficiency, the use of cleaner technology, cleaner production, and the

prevention, reduction and minimisation of waste, and shall include waste

reduction targets. The Schedule shall include time frames for the achievement of

set targets and shall address a five- year period as a minimum. The Schedule

shall be reviewed annually and amendments thereto notified to the Agency for

agreement as part of the Annual Environmental Report (AER)”.

Intel Corporate EHS reviews the company‟s significant aspects and maintains a rolling 5

year objectives and targets plan to reduce the impact on these aspects. The most recent

revision (2009) is detailed in Table 3.1. Intel Ireland reviews and updates the site‟s

significant aspects on an annual basis which takes into account corporate and other

requirements as well as legislative requirements. The Environmental Management Plan

(EMP) status report for 2010 is detailed in Section 3.2 and the proposed objectives and

targets for 2011 are described in Section 3.3.

Page 39: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

31

Table 3.1 - Corporate Environmental Strategic Goals and Performance

Page 40: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

32

3.2 ENVIRONMENTAL MANAGEMENT PROGRAMME (EMP) REPORT 2010

The 2010 Intel Ireland Objectives and Targets were made up of eleven strategic objectives.

Objectives and Targets were chosen in order to establish realistic and meaningful

improvements for that projected period. A report on the progress of these objectives during the

course of 2010 is provided in Tables 3.2 to 3.12.

Projects that are in progress and within the original assigned due date are designated as “In

Progress”. “Open” projects denote projects that are in progress but have exceeded the original

timeline.

Page 41: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

33

Table 3.2 - Objective No. 1 Status Report

Environmental Aspect/Topic: Materials Handling

Description of Activities: Chemical (and chemical waste) storage, handling and transportation

Objective No. 1: Surface Water/Groundwater Protection

Target Project Update 2010 AER Status

1.1 Ensure 100% Compliance with IPPCL (Condition 3.6.6)

1.1.1 Repair outstanding bunds and test in accordance with bund assessment findings carried out in 2009:

Bunds were repaired and tested as outlined in the bund assessment carried out by PM in 2009. Results of hydrostatic testing are included in Appendix E.

Complete

1.2 Ensure 100% Compliance with IPPCL (Condition 3.6)

1.2.1 Install apron to prevent sprays from escaping bunded area for sodium hydroxide bridge scrubber day tank bund.

A second layer of Perspex was installed and all joints sealed preventing any sprays from escaping the bund

Complete

1.2.2 Review protocol and update procedures for emptying bunds and sumps.

Protocol for emptying sumps and bunds onsite was reviewed in conjunction with CS operations and a new procedure developed to cover the emptying of all bunds and sumps onsite including contents testing requirements. Formal training on new procedures is to be rolled out in Q1 2011

Complete

Page 42: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

34

Table 3.3 - Objective No. 2 Status Report

Environmental Aspect/Topic: Hazardous Waste

Description of Activities: Generation, handling, collection, packaging, transportation and recycling of CCW

Objective No. 2: Reduce environmental impact of hazardous waste generated by IR site operations.

Target Project Update 2010 AER Status

2.1 Achieve a measurable target to align with corporate goal of 10% reduction by 2012 based on 2007 levels.

2.1.1 Implement corporate driven projects associated with waste minimisation

No corporate projects were required for completion at the Ireland site in 2010. However, one project was implemented to reduce the volume of CCW waste transported off-site for recovery. Instead of sending this waste as a part sludge and majority liquid, the system for collection of waste was changed to remove the sludge to totes and decant the remaining residual liquid. This will result in annual savings of this waste of approximately 56 tonnes based upon a PM schedule on the CCW system which generates this waste once per quarter.

Complete

Page 43: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

35

Table 3.4 - Objective No. 3 Status Report

Environmental Aspect/Topic: Chemical WasteNote 1

Description of Activities: Generation, collection, storage, transport and landfilling of calcium fluoride/phosphate filter cake.

Objective No. 3: Recycle 80% of chemical waste generated per year

Target Project Update 2010 AER Status

3.1 80% recycling rate for chemical waste (hazardous waste and non-hazardous filter cake)

3.1.1 Find recycling outlet for filter cake - potentially could boost recycling rate by 16%

Overall site recycling for corporate-defined chemical waste was 66% for 2010. The site did not meet the corporate goal due to project-related chemical waste being generated from F14 de-installation. Intel will still actively pursue the recovery of its calcium fluoride filter cake as this is a corporate-derived goal for all sites. Currently no recovery is available to Ireland, China and Israel sites. In 2010, Intel Ireland again approached cement kilns in Ireland and Europe to find a recovery outlet. Intel Ireland has not yet been successful in achieving this goal mainly due to technical issues with sending this waste material to cement kilns and also Ireland generated relatively small volumes for this to be economically viable.

In Progress

Note 1: Chemical waste at Intel Ireland is defined as all chemical type waste. This definition includes calcium fluoride filter cake which is classified as non-hazardous waste in line with Irish and EU legislation.

Page 44: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

36

Table 3.5 - Objective No. 4 Status Report

Environmental Aspect/Topic: Non-Hazardous Waste

Description of Activities: Generation, segregation, collection, storage and recycling of Dried Mixed Recyclables (DMR) - includes all dry recyclable waste

Objective No. 4: Recycle 80% of our solid waste (non-hazardous) generated per year

Target Project Update 2010 AER Status

4.1 Recycle 80% of our solid waste (non-hazardous) generated per year

4.1.1 80% recycling rate for solid waste (non-hazardous waste hairnet and booties)

Accomplished 89.7% non-hazardous waste recycling in 2010. Key contributing factors were a decrease in the volume of calcium fluoride filter cake and a significant increase in metal recycling due to the Fab 14 de-installation project.

Complete

Table 3.6 - Objective No. 5 Status Report

Environmental Aspect/Topic: Non-Hazardous Waste

Description of Activities: All non-hazardous waste activities with the exception of generation, collection, storage, transport and landfilling of calcium fluoride/phosphate filter cake.

Objective No. 5: Seamless Implementation of IFM contract for non-hazardous waste

Target Project Update 2010 AER Status

5.1 Zero non-compliances with IPPCL during implementation

5.1.1 Sustained operational control during Integrated Facilities Management (IFM) transition

Zero non-compliances with IPPCL during implementation of the IFM contract. Primary factors which ensured this target was met were: - continuation of Intel/waste vendor bi-weekly meetings with IFM representative in attendance - frequent internal audits of waste collection were carried out with IFM representative in attendance. - continued direct communications between Intel and our waste vendor on operational issues.

Complete

Page 45: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

37

Table 3.7 - Objective No. 6 Status Report

Environmental Aspect/Topic: Air Emissions

Description of Activities: Discharge of gaseous and particulate acids to atmosphere from acid scrubbers (e.g. HCl, Total fluorides, HF)

Objective No. 6: Ensure Air Quality

Target Project Update 2010 AER Status

6.1 Integrated fluoride monitoring programme

6.1.1 Develop an integrated sampling protocol for vegetation, HF diffusion tubes and filter paper

Proposals for the work developed and quotations received. Housing for filter paper to be installed. The project will then be assessed prior to financial and management review and integrated sampling to commence in Q4 2011.

Open

Table 3.8 - Objective No. 7 Status Report

Environmental Aspect/Topic: Materials Handling

Description of Activities: Chemical Management

Objective No. 7: Ensure compliance with the REACH regulation

Target Project Update 2010 AER Status

7.1 Ensure that all chemical products used by Intel are pre-registered by a Supplier or Only Representative.

7.1.1 Develop a compliance database of site chemicals, pre-registration communications, restrictions and registration deadlines

Database created successfully. Content of database to be migrated to Intel‟s chemical approval system (MREP) for chemical compliance tracking.

Complete

7.2 Launch MREP (Web-based chemical approval system) IT System.

7.2.1

Prepare site chemicals and MSDS‟s for the chemical approval system (MREP) IT System launch.

MREP system is live. New version MSDSs requested from all site suppliers. New system in place to ensure that suppliers send new version MSDSs to an Intel mailbox for processing and indexing in MREP.

Complete

Page 46: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

38

Table 3.9 - Objective No. 8 Status Report

Environmental Aspect/Topic: Air Emissions

Description of Activities: Discharge of CFC's and HCFC's from Refrigeration Equipment

Objective No. 8: Ensure compliance with the revised ODS Regulations and the Irish F-Gas Regulations

Target Project Update 2010 AER Status

8.1 Implementation of Management Systems to ensure compliance with all aspects of the Regulations

8.1.1 Specify a Software System for the management of all refrigerants on site.

A Software System for the management of refrigerant data was identified and evaluated over the course of 2010. The system was placed on order in January 2010 and is expected to be implemented over the course of Q2 2011.

In Progress

Page 47: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

39

Table 3.10 - Objective No. 9 Status Report

Environmental Aspect/Topic: Resource Utilisation

Description of Activities: Use of Electricity

Objective No. 9: Implement Energy Reduction Projects and contribute to the Corporate Goal of 5% normalised energy consumption reduction

Target Project Update 2010 AER Status

9.1 Implement Energy Reduction Projects that provide annualised energy reduction of 1% relative to H'2008 and H1'2009 energy usage (Update 2010 AER – the overall target was achieved. Please refer to individual projects for details)

9.1.1 IR5 Further Reduction to support F10

IR 5 load reductions achieved (included shutdown of some secondary chilled water pump set and set up of PM procedure for running of pump sets to improve efficiencies).

Complete

9.1.2 F10 Facility Load Opportunities

This project was changed to review facility loads from Fab 24. One project was implemented in 2010 which involved shutting off the mixer unit in the Fab 24 Ammonia buffer tank with no impact to the treatment system process.

Complete

9.1.3 F10 Chiller with IR5 Sort Reduction

Load reductions from IR5 Sort area achieved through de-installation of tools from area and recirculations to area shut off. No impact to area noted.

Complete

9.1.4 Compressor Air Efficiency Improvements Survey completed.

Complete

9.1.5 Implement DSUM ION EEM (monitoring system for energy usage)

Implemented at the site. Complete

9.1.6 IR1 York Air Cooled Chiller Optimisation

IR1 compressor dryer upgrade complete. The new model installed has more efficient air purging.

Complete

9.1.7 IR5 HVAC Improvement Electricity savings achieved. Complete

9.1.8 Reduction of F24 RCTO's to N Units

This project was not pursued due to the fact that Intel corporate direction is to maintain N+1 (duty and standby) RCTO units to assure reliability for manufacturing.

Project not pursued

9.1.9 Fab 24 MAH Heat Recovery Implemented Fab 24 heat recovery system to additional two air handling units on-site. Cold weather damaged coils and replacement coils were purchased to rectify.

Complete

Page 48: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

40

Table 3.11 - Objective No. 10 Status Report

Environmental Aspect/Topic: Resource Utilisation

Description of Activities: Use of mains city water

Objective No. 10: Implement water conservation projects and contribute to the corporate goal of reducing normalised water use by 2012 from 2007 levels

Target Project Update 2010 AER Status

10.1 Implement Projects to reduce demand on incoming water by at

least 30 m3/hr

10.1.1 Complete costing for the EDI (Electro-Deionisation) By-Pass Project

Design and initial costing now complete. Complete

10.1.2 Draft White Paper and submit to site management for approval of EDI By-Pass Project.

Unfortunately we will not be in a position to implement this project for the foreseeable future. Following a data review it was deemed to be high risk. With the extra loading that would be forced on the primary mixed beds and increased regenerations, redundancy (N+1) would be compromised. There are also a number of reliability issues throughout the system that need to be addressed first. These prevent reliable quality monitoring. Please note that the site did implement an optimisation project for EDI recovery. The operating parameters of this system have been challenged to recover more water. This will result in annualized savings of water of 268,440 m

3.

Project not pursued

10.1.3 Obtain Management Approval for EDI By-Pass Project.

10.1.4 Implement EDI By-Pass Project (subject to Management Approval)

Page 49: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

41

Table 3.12 - Objective No. 11 Status Report

Environmental Aspect/Topic:

EHS Management System

Description of Activities: All Site Activities

Objective No. 11: Continuously improve our environmental and energy management systems to provide improved performance

Target Project Update 2010 AER Status

11.1 Completion of 7 environmental management projects.

11.1.1 Gain successful certification of the Energy Management System to ISO16001

Intel gained certification to EN 16001 in June 2010 and underwent a certification audit in December 2010.

Complete

11.1.2 Review and update EnvironmentalTraining Classes

The Manufacturing Environmental Awareness Class, New Employee Orientation Class and Contractor Orientation Class were reviewed and updated.

Complete

11.1.3 Review of internal environmental auditing process to provide improvements

The internal auditing process was reviewed with key requirements for an audit tracker defined. Intel Ireland worked with Intel Corporation to seek an audit tool for use by all Intel companies. Unfortunately the development of the tool did not go ahead. Intel Ireland will seek an alternative and see if it is possible to get an improved tool for the site.

Open

11.1.4 Review of ICM document management system files

A new document layout was implemented for Environmental Programmes. A new system of titling document was implemented. Explore if all documents in ICM document management system should be put through the document control process in 2011.

Open

11.1.5 Review of Maximo preventative maintenance work orders for Environmental team and update where necessary

Maximo items were reviewed and updated in 2010 and are available on the document management system (ICM).

Complete

11.1.6 Review of process for corrective and preventative actions

This project was not completed due to work associated with implementation of OHSAS 18001 for 2011. This will be included in system design for implementation and integration of ISO14001 and OHSAS 18001.

Open

Page 50: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

42

Table 3.12 (continued) - Objective No. 11 Status Report

Environmental Aspect/Topic:

EHS Management System

Description of Activities: All Site Activities

Objective No. 11: Continuously improve our environmental and energy management systems to provide improved performance

Target Project Update 2010 AER Status

11.1.7 Review Communications within EHS group to revise and improve

A new corporate services sharepoint was created in 2010. The environmental section of the EHS webpage was reviewed and updated in 2010. An environmental programme owner‟s document was created in 2010 and is issued with communications on the IPPC licence on an annual basis.

Complete

Page 51: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

43

3.3 ENVIRONMENTAL MANAGEMENT PROGRAMME (EMP) SCHEDULE

2011

The 2011 Intel Ireland Objectives and Targets are made up of eleven objectives. The

Register of Aspects was reviewed to take into account any changes in legislation,

incidents or near-misses, corporate or other requirements or any changes to the site

that might have an impact to each aspect score. Based on the highest risks

(significant aspects), the objectives and targets were compiled. In addition, any

objectives and targets required to maintain or improve the environmental

management system were also included.

A summary of the 2011 objectives and targets schedule is provided in Tables 3.13 to

3.23.

Table 3.13 - Objective No. 1 Schedule

Environmental Aspect/Topic: Materials Handling

Description of Activities: Chemical (and Chemical Waste) Storage, Handling and Transportation and Oil Storage, Handling and Transportation

Objective No. 1: Protect surface water and groundwater

Target Project Due Date Owner

1.1 Ensure all bunds onsite that failed hydrostatic tests are repaired and retested.

1.1.1 Complete remedial works for diesel bunds identified in the 2010 bund testing and retest these bunds.

Q3 2011 Env. Engineer

1.1.2 Complete remedial works for chemical bunds identified in the 2010 bund testing and retest these bunds

Q3 2011 Env. Engineer

1.1.3 Complete integrity testing on Fab 14 and Fab 24 Contained Storm System Tanks

Q4 2011 Env. Engineer

Page 52: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

44

Table 3.14 - Objective No. 2 Schedule

Environmental Aspect/Topic: Surface Water

Description of Activities: Discharge of surface waters from the site (e.g. rainfall to roof areas, car park etc.) to the Site Retention Pond and Rye water River.

Objective No. 2: Protect surface water

Target Project Due Date Owner

2.1 Ensure all CS Operations Technicians are trained on new bund and sump emptying procedure

2.1.1 Hold training classes to cover all shifts on the new procedure for emptying bunds and sumps onsite.

Q2 2011 Env. Engineer

2.1.2 Incorporate training into storm water training class

Q2 2011 Env. Engineer

Table 3.15 - Objective No. 3 Schedule

Environmental Aspect/Topic: Air Emissions

Description of Activities: Discharge of gaseous and particulate acids to atmosphere from acid scrubbers (e.g. HCl, Total fluorides, HF)

Objective No. 3: Gain better understanding of fluoride within the scrubbed exhaust system

Target Project Due Date Owner

3.1 Increase understanding of the source of fluoride into and from the Fab 24 Scrubbed Exhaust system.

3.1.1 Characterise inlet and outlet scrubber loads.

Q2 2011 Env. Engineer

3.1.2 Review quality of sampling and analysis methods

Q3 2011 Env. Engineer

3.1.3 Identify the sources of fluoride within the system

Q3 2011 Env. Engineer

Table 3.16 - Objective No. 4 Schedule

Environmental Aspect/Topic: Air Emissions

Description of Activities: Discharge of gaseous and particulate acids to atmosphere from acid scrubbers (e.g. HCl, Total fluorides, HF)

Objective No. 4: Gain better understanding of air quality trends through an integrated approach

Target Project Due Date Owner

4.1 Integrated fluoride monitoring programme

4.1.1 Develop an integrated sampling protocol for vegetation, HF diffusion tubes and filter paper

Q4 2011 Env. Engineer

Page 53: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

45

Table 3.17 - Objective No. 5 Schedule

Environmental Aspect/Topic: Air Emissions

Description of Activities: Discharge of CFCs, HCFCs and HFCs from refrigeration equipment

Objective No. 5: Compliance with CFC, HCFC and HFC regulations

Target Project Due Date Owner

5.1 Implementation of Management Systems to ensure compliance with all aspects of the Regulations

5.1.1 Fully implement the Refrigerant Compliance Management System on site (including transfer of data from old system and training on new system)

Q2 2011 Env. Engineer

Table 3.18 - Objective No. 6 Schedule

Environmental Aspect/Topic: Chemical Waste

Description of Activities: Generation, collection, storage, transport and landfilling of calcium fluoride/phosphate filter cake.

Objective No. 6: Reduce environmental impact of chemical waste generated by IR site operations.

Target Project Due Date Owner

6.1 Recycle 80% of our chemical waste in line with Intel Corporation.

6.1.1 Fab 10 de-installation work is likely to have an impact on our site chemical waste recycling goals. It is unlikely that we will meet the 80% recycling goal in 2011 due to this project. Site project to find an outlet for our calcium fluoride filter cake will be reviewed again in 2011. This is a long term objective at the site which unfortunately due to technical issues and also waste recovery facilities available to Ireland has not been achieved. It remains a focus for Intel Corporation so therefore is included in our projects.

Market Dependent Timeframe

EHS Manager

Note: Chemical waste at Intel Ireland is defined as all chemical type waste. This definition includes calcium

fluoride filter cake which is classified as non-hazardous waste in line with Irish and EU legislation.

Page 54: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

46

Table 3.19 - Objective No. 7 Schedule

Environmental Aspect/Topic: Non-Hazardous Waste

Description of Activities: Generation, collection, storage, transport and tracking of recoverable and disposed non-hazardous waste from the Ireland site

Objective No. 7: Recycle 80% of our solid waste (non-hazardous) generated per year

Target Project Due Date Owner

7.1 Recycle 80% of our non-hazardous waste in line with Intel Corporate targets

7.1.1 Develop re-use of waste cleanroom consumables (Hairnets and booties) as SRF (Solid Recovered Fuel)

Q4 2011 EHS Manager

Table 3.20 - Objective No. 8 Schedule

Environmental Aspect/Topic: Non-Hazardous Waste

Description of Activities: Generation, collection, storage, transport and tracking of recoverable and disposed non-hazardous waste from the Ireland site

Objective No. 8: Manage site non-hazardous waste data effectively

Target Project Due Date Owner

8.1 Single tracking document for all non-hazardous waste permits used by the site

8.1.1 Develop and maintain a controlled tracking document for all non-hazardous waste permits applicable to waste collectors and facilities used by the site

Q2 2011 EHS Manager

8.2 Successful development and implementation of Ireland site Non-Hazardous Waste data management application

8.2.1 Develop, validate and implement a software system which manages all site non-hazardous waste shipment data

Q3 2011 EHS Manager

Page 55: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

47

Table 3.21- Objective No. 9 Schedule

Environmental Aspect/Topic: Resource utilization

Description of Activities: Resource utilization e.g. electricity, natural gas, oil and water.

Objective No. 9: Conserve natural resources

Target Project Due Date Owner

9.1 Provide annualised energy savings of $1.668 million in 2011

9.1.1 IR1 Data Center York Air Cooled Chiller Sequencer. Installation of chiller sequencer panel and associated FMS control. The chillers do not use each available stage. Savings from improved efficiencies on chillers.

Q4 2011 CS Engineer

9.1.2 IR1 Data centre evaporative Cooling. Installation of heat exchange and associated pipework to allow use of cooling tower. Savings from reduced chiller electrical load.

Q4 2011 CS Technician

9.1.3 Installation of FMS lighting control in Fab 24 Scrubber area. Lighting control for scrubber area to be put onto FMS. Modifications to be made to existing photocell control wiring.

Q4 2011 CS Technician

Note: Intel Ireland has a specific project tracker for improvement projects as part of its Energy Management System. This is a live database used to log project ideas. This is updated and new projects added regularly. For the EMP only projects with a high confidence level have been included.

Table 3.22 - Objective No. 10 Schedule

Environmental Aspect/Topic: Materials Handling

Description of Activities: Chemical Management

Objective No. 10: Ensure compliance with the REACH regulation

Target Project Due Date Owner

10.1 Use Intel Chemical Approval System (MREP) as REACH compliance database

10.1.1 Content of REACH compliance database to be migrated to MREP for chemical compliance tracking.

Q4 2011 Corporate EHS Engineer

Page 56: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

48

Table 3.23 - Objective No. 11 Schedule

Environmental Aspect/Topic: Overall Site Management

Description of Activities: EHS Management Systems

Objective No. 11: Maintain and improve our EHS and energy management systems to international standards

Target Project Due Date Owner

11.1 Ensure our management systems meet the requirements of international standards and Intel Corporation.

11.1.1 Implement OHSAS 18001 management system.

Q4 2011 EHS Manager

11.1.2 Review of ISO14001 related procedures (including internal audits, document control and corrective and preventative actions) for completion of ISO14001 recertification audit

Q3 2011 EHS Manager

11.1.3 Track the finalisation of ISO50001, the new international standard for energy management to transition from EN 16001

Q4 2011 Energy Manager

Page 57: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

49

3.4 POLLUTION EMISSION REGISTER

3.4.1 Introduction

This section includes an introduction to Intel‟s PER, a summary of the methodology

used to assess these pollutants and a pollution emission register table.

The Pollution Emission Register (PER) is a requirement of the Integrated Pollution

Prevention and Control Licence (Register No. P0207-03), as issued to Intel Ireland

Ltd. Specifically, under Condition 6.16.1 of the Integrated Pollution Control Licence,

the following is noted:

6.16.1 The licensee shall prepare and maintain a PER for the site. The

substances to be included in the PER shall be agreed by the Agency each

year by reference to the list specified in the Agency’s AER Guidance Note.

The PER shall be prepared in accordance with any relevant guidelines issued

by the Agency and shall be submitted as part of the AER.

As per Condition 6.16.1, Intel Ireland submitted a proposal for the 2010 PER in the

Annual Environmental Report for 2009. This PER includes fluoride and copper and

the rationale for including these parameters has been outlined in the proposal in last

year‟s AER.

3.4.2 Summary of Methodology for Substances Requiring A Full PER

3.4.2.1 Copper

Intel Ireland uses electroplated copper interconnects in the fabrication of

microchips in the 300 mm fabrication facility in F24.

Electroplating facilitates the deposition of a metal film by using current to

provide electrons to convert metal ions to metal atoms at a conductive

interface. A thin copper seed layer is deposited on the silicon wafer prior to

electro-deposition (to provide a conductive layer for the deposition process).

The wafer is then immersed in an electrolytic solution containing copper ions

where deposition of a copper film is accurately controlled by the application of

an electric current. The current is passed between the anode (copper disc)

and the cathode (wafer) where copper metal is deposited on the conductive

seed layer. A copper anode replenishes the electrolytic solution with copper

ions as they are consumed at the cathode.

Page 58: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

50

Two tools sets are employed in the thin films process in F24 to facilitate the

electroplating process. After passing through the electroplating tool set, the

wafers proceed to copper polish where the deposited copper films are

polished down. Several metal layers are deposited on each production wafer.

Copper is also used in the copper bump plating tools in the C4 process.

The Fab 24 electroplating process produces copper contaminated waste.

These waste types include concentrated copper waste (CCW), dilute metal

waste (DMW), slurry copper waste (SCW) and spent copper anodes. The

majority of the CCW waste is treated on-site by electro-winning and copper

balls are produced during this process. Both SCW and DMW waste streams

are dilute copper effluents which are treated by ion-exchange prior to

discharge to process wastewater.

The following table (Table 3.24) summarises the inputs and outputs that are

considered in the copper pollution emission register for 2010.

Table 3.24 - Summary Table of Copper Inputs/Outputs

Inputs Outputs

Copper Make-up Solutions CCW Waste Copper Balls

Copper Anodes Concentrated Copper Waste (CCW) Liquid Waste

Copper Media for CCW Dilute Metal Waste (DMW) Resin.

Slurry Copper Waste (SCW) Resin.

Used/Recovered Copper Anodes

Copper deposited onto the wafer/product

Copper in wastewater discharge to Leixlip WWTP

The mass balance contains theoretical estimated averages of copper plated

on wafers and copper anodes and hence, this will contribute to uncertainty in

the results. Therefore, approximately 7% of the copper is unaccounted for but

this may be explained by the estimations used in the mass balance

calculations.

Page 59: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

51

3.4.2.2 Fluoride

Intel uses compounds containing fluoride in a number of process steps in the

manufacture of semiconductors. During the process, the wafers pass through

each of the functional areas a number of times to build up a complex 3-D

device on the surface of the wafer. Fluoride is used in its different forms in

the following steps:

Diffusion (Hydrogen Fluoride in gaseous and acid form).

Etch (PFC gases and Hydrogen Fluoride acids).

Thin Films (PFC gases).

Fluoride-containing wastewater is treated on-site by precipitation with calcium

hydroxide to form calcium fluoride as a solid waste.

The following potential inputs/outputs (Table 3.25) are considered in the

fluoride mass balance analysis for 2010.

Table 3.25 - Summary Table of Fluoride Inputs/Outputs

Inputs Outputs

PFCs and other fluorinated gases Fluorine, HF and PFCs in atmospheric emissions

Fluorinated liquid chemicals Fluoride in wastewater emissions

Fluoride in solid waste

For the mass balance for fluoride, Intel assumed that the balance of fluoride

was contained in the calcium fluoride cake. Intel was unable to source a

laboratory to conduct the total fluoride analysis and therefore was unable to

validate the amount of fluoride in the cake.

Therefore, there is some uncertainty associated with the mass balance

results for this parameter.

Page 60: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

52

3.4.3 Pollution Emission Register

Facility Identification

Facility Name Intel Ireland Ltd.

Register No. P0207-03

National/Grid Reference 2370(N), 2985(E)

Reporting Period Jan 2010 to Dec 2010

Production units Silicon wafers

Employee No. 4,000

Pollutants Summary

Pollutant

Name

CAS

No.

Input

(Kg)

Gross

Usage

(Kg)

Outputs (Kg)

Air MOM

Liquid

Effluent MOM Waste MOM Product MOM Recovery Treated Unaccounted

Copper

7440-

50-8 10,220 7,186 - - 160 M 4,505 M 3,366 E 2,909 - 721

Fluoride

7782-

41-4 109,350 105,843 7,740 M 14,391 M 83,923 E - - 3,506 - 211

Page 61: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

53

3.4.4 Pollution Emission Register (PER) Proposal for 2011

Section 6.16.1 of Intel Ireland‟s IPPC licence number P0207-03 detailed below,

specifies that an agreed PER list shall be included in the AER.

6.16.1 The licensee shall prepare and maintain a PER for the site. The

substances to be included in the PER shall be agreed by the Agency each

year by reference to the list specified in the Agency’s AER Guidance Note.

The PER shall be prepared in accordance with any relevant guidelines issued

by the Agency and shall be submitted as part of the AER.

Pending the requirement to submit a PER in 2011, we propose the following

substances for a full Pollution Emission Register (PER) mass balance:

Total Fluoride

Copper

These substances have been included due to their potential environmental toxicity.

Page 62: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

54

4.0 LICENCE-SPECIFIC REPORTS

4.1 GROUNDWATER MONITORING SUMMARY REPORT

Condition 6.1 of the IPPC licence requires that:

The licensee shall carry out such sampling, analyses, measurements,

examinations, maintenance and calibrations as set out below and as in

accordance with Schedule C of this licence.

The required monitoring as specified in Schedule C.6.3 is outlined in Table 4.1

below:

Table 4.1 - IPPC Licence Monitoring Schedule C.6.3

Parameter Monitoring Frequency Analysis method/Technique

pH Biannually pH electrode/meter

COD Biannually Standard Method

Nitrate Biannually Standard Method

Total Ammonia Biannually Standard Method

Total Nitrogen Biannually Standard Method

Conductivity Biannually Standard Method

Chloride Biannually Standard Method

Fluoride Biannually Standard Method

OrganohalogensNote 1

Biannually GC-MS

Note 1: Screening for priority pollutant list substances (such as US EPA volatile and/or semi-volatile

compounds.

Intel Ireland commissioned TMS Environmental Ltd. to carry out the groundwater

sampling and analysis and a summary report for both biannual monitoring events is

detailed in Appendix B.

Page 63: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

55

4.2 RIVER RYE WATER MONITORING REPORT

As per Condition 6.1 and Schedule C.6.4 of the IPPC Licence, the River Rye water was

sampled for the following range of parameters:

Intel Ireland commissioned Bord na Móna Environmental Ltd to carry out an assessment of the

quality of surface water at a number of locations along the River Rye, upstream and

downstream of the surface water retention pond outlet (i.e. Intel‟s surface water discharge point

to the river). A summary report for both monitoring events is shown in Appendix C

4.3 LOUISA SPA WATER QUALITY MONITORING REPORT

4.3.1 Introduction

As per Schedule C.6.5 of the site IPPC licence, the following monitoring is required:

Page 64: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

56

The services of TMS Environment Ltd. were employed to carry out the sampling and analysis of

this well and their report is summarised in Appendix D.

4.4 BUND TESTING SUMMARY

Under Condition 3.6.6 of Intel Ireland‟s IPPC licence (Register No. P0207-03), Intel Ireland is

required to carry out bund integrity testing at least every three years. Intel Ireland commissioned

Project Management Ltd. to carry out visual bund inspections by a qualified structural engineer

in 2009. In addition, all bunds were assessed to determine whether it was necessary, safe and

practicable to conduct hydrostatic testing in line with the EPA‟s Guidance Note on Storage and

Transfer of Materials for Scheduled Activities. Following on from this report a number of bunds

were hydrostatically tested across the site, results of which are included in Appendix E of this

report. Five bunds failed the hydrostatic testing and Intel will repair and retest these bunds

during 2011.

4.5 UNDERGOUND PIPE AND TANK INTEGRITY TESTING SUMMARY

Under Condition 6.6 of Intel‟s IPPC licence (Register No. P0207-03), Intel Ireland is required to

ensure that:

6.6 The integrity and water tightness of all underground pipes and tanks and their

resistance to penetration by water or other materials carried or stored therein shall be

Page 65: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

57

tested and demonstrated by the licensee at least once every three years and reported to

the Agency on each occasion. A written record of all integrity tests and any maintenance

or remedial work arising from them shall be maintained by the licensee.

The Fab 24 process effluent pipe integrity testing was completed in 2010. Debris was found in

line during the first survey and the line was cleaned and resurveyed and found to be in

satisfactory condition. Please refer to Appendix F for full report.

In relation to underground tank testing, Intel commissioned AD Analytical Ltd. to conduct a

retesting of the F10 upper yard tank following both valves in tank being replaced. The tank

passed the integrity test and the report is included in Appendix G.

4.6 AMBIENT AIR MONITORING SUMMARY

Ambient Air Monitoring was carried out at the Intel Ireland facilities in accordance with Schedule

C.6.1 of the IPPC Licence.

The parameters to be measured were oxides of nitrogen (continuous), nitrogen dioxide

(biannual), total fluoride (bi-annual) and total acidity (biannual).

A continuous monitor measuring oxides of nitrogen is installed at the on-site weather station

and the results are trended on a monthly basis.

Nitrogen dioxide diffusion tubes are placed at five locations surrounding the site. Results ranged

from below LOD to 32 µg/m3.

In addition, ambient air monitoring surveys were carried for the following periods:-

4th – 11th June 2010

26th November – 2nd December 2010

These surveys were conducted at two sampling locations, A1 and A2. A1 is located close to the

on-site sports centre (to the south west of the facility) while A2 is located in the field to the north

of the facility.

Total acidity (as HCl) ranged from below LOD to 6.1 µg/m3 and total fluoride ranged from below

LOD to 1.5 µg/m3.

Page 66: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

58

4.7 FUGITIVE EMISSIONS PROGRAMME

The company is required under Condition 6.7.2 of the IPPC Licence to maintain a fugitive

emissions program in order to achieve the limits specified in Condition 6.7.1. That condition

specifies that fugitive emission losses shall not exceed 15% of total solvent input.

Fugitive emissions from Intel Ireland are minor and well controlled. They primarily arise from the

use of Isopropyl Alcohol (IPA) used for cleaning of equipment and surfaces within the

cleanrooms. This IPA is used either as saturated wipes or as a liquid in combination with dry

wipes.

On a quarterly basis, “VOC Indicators” are calculated. These calculate the total quantity of

solvents used as well as the fugitive emissions. These calculations confirm that fugitive losses

are well below the limit of 15% (as a percentage of total solvent use) set in Condition 6.7.1. The

company intends to keep in place current controls on the use of IPA to continue to remain in

compliance with this limit.

Furthermore, the company submitted a proposal to the EPA in May 2006 in relation to draft

criteria for shutting down production processes in the event of non-compliance, equipment

failure and/or by-pass. The Agency approved this proposal by letter dated 13th June 2006

subject to a number of conditions including the requirement that “All by-passes (of the VOC

abatement equipment) shall be recorded and included in the fugitive emissions reduction

programme”.

All such by-passes (>1 hour duration) are recorded (and communicated to the Agency) and

these by-passes are included in the calculation of the quarterly VOC Indicators. Every effort is

made to bring the abatement equipment back on line in the shortest possible time.

During 2010, there were 12 periods when VOC abatement equipment was offline across the

site, due to planned shut-downs, preventive maintenance, natural gas interruptions and RCTO

equipment malfunctions. Four of these occurrences ranged from durations of 2 – 6 days, the

remaining 8 occurrences were less than 2 days in duration.

Furthermore, the company retains in place the protocol which was introduced in 2007 to ensure

that by-passes of abatement units are minimised and any by-passes which last for longer than

one week are communicated to and approved by senior site management.

Page 67: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

59

4.8 PERFLUORINATED CARBON (PFC) EMISSIONS REPORT

4.8.1 Methodology of PFC Emissions Calculations

Following correspondence between the EPA and Intel Ireland during 1999, the following

programme was agreed on 17th May 1999 under EPA reference M207/GC/11 in relation to

substances that have a significant global warming potential:

In view of the company’s argument that details of gas usage would place the company at

a competitive disadvantage, details of inputs and outputs need not be given in any

written report to the Agency, but individual annual tonnage figures for Emissions of C2F6,

CF4, and SF6 must be reported separately. A full record of how the figures were

calculated must be available on-site at Intel Ireland Ltd to authorised persons of the

Agency at all times.

The tables at the end of this section (Tables 4.7 to 4.10) give individual annual tonnage figures

for emissions of the three gases required by the Agency (C2F6, CF4, and SF6) and a

consolidated figure for three other fluorinated gases (CHF3, NF3 and C4F8). For ease of

comparison between each of the gases and to allow for comparison from year to year, the

emissions have also been expressed as Million Metric Tonnes Carbon Equivalent (MMTCE)

which is a standard way for expressing emissions of PFCs.

The 2010 data was compiled and computed in the following manner:-

Several companies supply Intel Ireland with speciality gases for their manufacturing

process. These gases are issued on a periodic basis from Intel Ireland‟s chemical and

gas warehouses to the fabrication manufacturing plant. Intel Ireland then produces a

report detailing the number and size of gas cylinders issued to the wafer fabrication

operations.

In calculating emissions, a constantly improved method is periodically agreed between

all European semiconductor-manufacturing facilities. These companies are members of

European Semiconductors Industry Association (ESIA). The data from each company is

then collated by this association on an aggregate basis annually to give one emission

data point notated in MMTCE units. (Million Metric Tonnes Carbon Equivalent – a

universally accepted metric for global warming impact). The collation of the Intel Ireland

Page 68: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

60

data is kept by the Environmental Engineer on a shared drive within the department‟s

EMS data retention system.

For methodical calculations, the assumption currently adopted within the industry and

ratified by the World Semiconductor Council (WSC) is that an agreed documented % of

each gas is consumed efficiently during manufacturing and conversely a fixed % of gas

is emitted to atmosphere (Tier 2). Such generic assumptions are being refined across

the industry globally under the remit of the WSC. A new calculation methodology has

been adopted by ESIA which takes into account the efficiency of removal of GWP gases

from point of use (POU) abatement devices deployed between the tool and the large on-

site gas scrubbers. In calculating the Metric Tonnes Carbon Equivalent (MTCE)

emission data, there are also assumptions taken on the global warming potential of each

gas and the fact that some gases such as C2F6 after use can also form other by-

products such as CF4. All this information is managed within the ESIA excel

spreadsheets and is summarized in terms of emissions as MMTCE in the table below.

The Global Warming Potential (GWP100) for each of the Gases is taken from the

Intergovernmental Panel on Climate Change (IPCC) 4th Assessment Report. The

GWP100 values have been presented below for information purposes.

GWP100 Values from 4th IPCC Assessment Report

C2F6 GWP = 12,200 CHF3 GWP = 14,800

SF6 GWP = 22,800 NF3 GWP = 17,200

CF4 GWP = 7,390 C4F8 GWP = 10,300

4.8.2 Intel Ireland's Emissions of PFCs

Tables 4.2 and 4.3 give details of emissions of PFCs for 2009 and 2010.

Page 69: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

61

Table 4.2 - 2009 Emissions using 4th

IPPC Assessment Report GWP100 Values (Tier 2 Methodology)

Parameter Emissions (Metric Tonnes)

MMTCE

C2F6 4.77 0.016

CF4 0.81 0.002

SF6 0.66 0.004

CHF3, NF3, C4F8 2.57 0.011

Total PFCs 8.81 0.0326

Table 4.3 - 2010 Emissions using 4th

IPPC Assessment Report GWP100 Values (Tier 2 Methodology)

Parameter Emissions (Metric Tonnes)

MMTCE

C2F6 1.85 0.006

CF4 0.70 0.001

SF6 0.44 0.003

CHF3, NF3, C4F8 2.92 0.012

Total PFCs 5.91 0.0227

During 2009 and 2010, Intel Ireland also calculated its emissions using a more precise method

known as "Tier 3". This uses process specific emissions factors for each of the process gases.

This method gives a result which is higher than that calculated by Tier 2. Table 4.4 provides this

data for 2009 while Table 4.5 provides the data for 2010.

Page 70: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

62

Table 4.4 - 2009 Emissions using 4th

IPPC Assessment Report GWP100 Values (Tier 3 Methodology)

Parameter Emissions (Metric Tonnes)

MMTCE

C2F6 5.03 0.017

CF4 2.21 0.004

SF6 1.56 0.010

CHF3, NF3, C4F8 2.55 0.011

Total PFCs 11.35 0.0420

Table 4.5 - 2010 Emissions using 4th

IPPC Assessment Report GWP100 Values (Tier 3 Methodology)

Parameter Emissions (Metric Tonnes)

MMTCE

C2F6 2.36 0.008

CF4 1.52 0.003

SF6 0.93 0.006

CHF3, NF3, C4F8 3.12 0.014

Total PFCs 7.93 0.0304*

* Note: - These calculations do not include losses of HFC refrigerant from the site chillers. The global warming impact of these losses has been estimated at 0.0008 MMTCE. If these losses are included in the "Total PFCs" figure above, then the figure would increase by approximately 2.6%.

For a number of years, Intel Ireland has been pursuing various reduction initiatives such as gas

usage reduction with the introduction of each new process technology, gas substitution, for

example, by the replacement of C2F6, in certain recipes, with alternative gases. During 2009,

Intel Ireland completed its project to replace C2F6 on some tools in IFO with a gas which has a

greater utilization rate. This means that the quantity of gas used and PFC emissions (expressed

as MMTCE) are lowered. The benefits of this process change were carried forward into 2010. In

addition, the reduction in production levels in IFO (the main source of PFC emissions on site)

during 2010 also drove a decrease in PFC emissions for the site. Overall, there were a

reduction of approximately 25% in PFC emissions from the site between 2009 and 2010

irrespective of the calculation methodology used.

Page 71: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

63

Finally, it should be noted that emission calculation methodologies may well change in the

coming years as improved calculation systems are formally adopted and verified by analytical

methods across the semiconductor associations such as SIA (Semiconductor Industry

Association of America), ESIA (European Semiconductor Industry Association), KIA (Korean

Semiconductor Industry Association), JIA (Japanese Semiconductor Industry Association), to

accommodate, for example, for the introduction of new gases, or alternate point of use

abatement technologies.

4.9 NOISE MONITORING REPORT

A copy of the 2010 Annual Noise Monitoring Report is included in Appendix H of this Report.

4.10 RESIDUAL MANAGEMENT PLAN

As per Condition 10 of the site's IPPC licence, a Residuals Management Plan (RMP) is

maintained for the Intel Ireland site. The RMP, including a separate Environmental Liabilities

Risk Assessment (ELRA) was updated during 2010 and submitted to the Agency on the 2nd

September 2010. In addition, a Validation Report for the stand-down works at Fab 14 was

submitted to the Agency on the same date. Finally, a Statement of Financial Provisions was

submitted to the Agency on the 5th October 2010.

All these documents are awaiting the approval of the Agency.

Page 72: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Appendix A

Pollutant Release and Transfer Register

(PRTR)

Page 73: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

4.1 RELEASES TO AIR

SECTION A : SECTOR SPECIFIC PRTR POLLUTANTS

RELEASES TO AIR

Please enter all

quantities in this section

in KGs

POLLUTANT METHOD QUANTITY

Method Used

Acid Gas

Scrubbers

Ammonia

Scrubbers

VOC

Emission

Points

Specilaity

Exhausts

Boilers &

Generators

No.

Annex II Name M/C/E

Method

Code Designation or Description

Emission

Point 1

Emission

Point 2

Emission

Point 3

Emission

Point 4

Emission

Point 5

T (Total)

KG/Year

A (Accidental)

KG/Year F (Fugitive) KG/Year

0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

03

Carbon dioxide

(CO2) C ETS

Guideline for the monitoring

and reporting of greenhouse

gas emissions under the

Emissions Trading Scheme 0.0 0.0

3289500.

0 0.0

296055

00.0 32895000.0 0.0 0.0

02

Carbon monoxide

(CO) C OTH Mass Balance calculation 0.0 0.0 6519.0 0.0 2193.0 8712.0 0.0 0.0

04

Hydro-

fluorocarbons

(HFCs) C OTH

Mass Balance Calculations

and Emission Factors to

IPCC Tier 3. Fugitive losses

based upon estimate of loss

from on-site Chillers 284.62 0.0 0.0 0.0 0.0 2447.62 2163.0 0.0

14

Hydrochlorofluoroc

arbons (HCFCs) E ESTIMATE 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

08

Nitrogen oxides

(NOx/NO2) C OTH Mass Balance calculation 0.0 0.0 1268.0 0.0

32532.

0 33800.0 0.0 0.0

05

Nitrous oxide

(N2O) C MAB

Mass Balance Calculations

and Emission Factors 11713.0 0.0 0.0 0.0 0.0 11713.0 0.0 0.0

09

Perfluorocarbons

(PFCs) C OTH

Mass Balance Calculations

and Emission Factors to

IPCC Tier 3 4485.52 0.0 0.0 0.0 0.0 4485.52 0.0 0.0

10

Sulphur

hexafluoride (SF6) C OTH

Mass Balance Calculations

and Emission Factors to

IPCC Tier 3 930.95 0.0 0.0 0.0 0.0 930.95 0.0 0.0

06 Ammonia (NH3) M OTH Colorimetric analysis 0.0 20.9 0.0 0.0 0.0 20.9 0.0 0.0

Page 74: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

SECTION B : REMAINING PRTR POLLUTANTS

RELEASES TO AIR

Please

enter all

quantities

in this

section in

KGs

POLLUTANT METHOD

QUANTITY

Method Used

Acid Gas

Scrubbers

No. Annex II Name

M/

C/E

Method

Code

Designation or

Description

Emission

Point 1

Emission

Point 2

T (Total)

KG/Year

A

(Accidental)

KG/Year

F

(Fugitiv

e)

KG/Yea

r

84

Fluorine and

inorganic

compounds (as HF) M

ISO/DIS

15713:20

04 815.0 0.0 815.0 0.0 0.0

Page 75: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

SECTION C : REMAINING POLLUTANT EMISSIONS (As required in your Licence)

RELEASES TO AIR

Please

enter all

quantitie

s in this

section

in KGs

POLLUTANT METHOD

QUANTITY

Method Used

Acid Gas

Scrubbers

Ammonia

Scrubbers

VOC

Emission

Points

Speciality

Exhaust

Boilers

&

Genera

tors

Pollutant No. Name

M/

C/E

Method

Code

Designation or

Description

Emission

Point 1

Emission

Point 2

Emission

Point 3

Emission

Point 4

Emissio

n Point

5

T (Total)

KG/Year

A (Accidental)

KG/Year F (Fugitive) KG/Year

227

TA Luft inorganic

dust particles class

1 M CRM

Method based

on USEPA 29 0.0 0.0 0.0 0.83 0.0 0.83 0.0 0.0

228

TA Luft inorganic

dust particles class

2 M CRM

Method based

on USEPA 29 0.0 0.0 0.0 1.57 0.0 1.57 0.0 0.0

229

TA Luft inorganic

dust particles class

3 M CRM

Method based

on USEPA 29 0.0 0.0 0.0 7.47 0.0 7.47 0.0 0.0

230

TA Luft organic

substances class 1 M

EN

13649:20

01 0.0 0.0 278.0 0.0 0.0 278.0 0.0 0.0

231

TA Luft organic

substances class 2 M

EN

13649:20

01 0.0 0.0 233.0 0.0 0.0 233.0 0.0 0.0

232

TA Luft organic

substances class 3 M

EN

13649:20

01 0.0 0.0 2022.0 0.0 0.0 2022.0 0.0 0.0

235 Total acids M

EN 1911-

1 to

3:2003 3595.0 0.0 0.0 0.0 0.0 3595.0 0.0 0.0

351

Total Organic

Carbon (as C) M ALT

Method based

on I.S. EN

13526 0.0 0.0 93.0 0.0 0.0 93.0 0.0 0.0

210 Dust M CRM

Method based

on USEPA 29 0.0 0.0 0.0 152.0 0.0 152.0 0.0 0.0

330 Organic solvents C MAB

Mass balance

calculation 0.0 0.0 0.0 0.0 0.0 3890.0 0.0 3890.0

Page 76: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

8 18 26 34 6 6 6 6 SECTION A : PRTR POLLUTANTS

OFFSITE TRANSFER OF POLLUTANTS DESTINED FOR WASTE-WATER TREATMENT OR SEWER

Please enter all quantities in this section in KGs

POLLUTANT METHOD QUANTITY

Method Used

No. Annex II Name M/C/E

Method Code Designation or Description

Emission Point 1

T (Total) KG/Year

A (Accidental) KG/Year

F (Fugitive) KG/Year

17 Arsenic and compounds (as As) M

CRM

U.S. EPA method 200.8 (supplement 1 rev. 5.4 May 1994) 0.78 0.78 0.0 0.0

19 Chromium and compounds (as Cr) M

CRM

U.S. EPA method 200.8 (supplement 1 rev. 5.4 May 1994) 0.25 0.25 0.0 0.0

20 Copper and compounds (as Cu) M

CRM

U.S. EPA method 200.8 (supplement 1 rev. 5.4 May 1994) 160.0 160.0 0.0 0.0

83 Fluorides (as total F) M OTH

Ion chromatography method based on "Standard Methods for the Examination of Water and Wastewater, 2005, 21st edition, Method 4110B published by the APHA, AWWA and WEF 14400.0 14400.0 0.0 0.0

23 Lead and compounds (as Pb) M

CRM

U.S. EPA method 200.8 (supplement 1 rev. 5.4 May 1994) 5.97 5.97 0.0 0.0

22 Nickel and compounds (as Ni) M

CRM

U.S. EPA method 200.8 (supplement 1 rev. 5.4 May 1994) 8.9 8.9 0.0 0.0

12 Total nitrogen M CRM

U.S. EPA method 200.8 (supplement 1 rev. 5.4 May 1994) 48700.0 48700.0 0.0 0.0

76

Total organic carbon (TOC) (as total C or COD/3) M

OTH

Closed reflux calorimetric method based on APHA, 2005, 21st Edition, Method 5220-D. 34800.0 34800.0 0.0 0.0

13 Total phosphorus M OTH

"Standard Methods for the Examination of Water and Wastewater, 2005, 21st edition, Method 4500-PB and Method 4500-PD published by the APHA, AWWA and WEF 3835.0 3835.0 0.0 0.0

24 Zinc and compounds (as Zn) M

CRM

U.S. EPA method 200.8 (supplement 1 rev. 5.4 May 1994) 142.0 142.0 0.0 0.0

Page 77: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

79 Chlorides (as Cl) M OTH

Ion chromatography method based on "Standard Methods for the Examination of Water and Wastewater, 2005, 21st edition, Method 4110B published by the APHA, AWWA and WEF 156000.0 156000.0 0.0 0.0

SECTION B : REMAINING POLLUTANT EMISSIONS (as required in your Licence)

OFFSITE TRANSFER OF POLLUTANTS DESTINED FOR WASTE-WATER TREATMENT OR SEWER

Please enter all quantities in this section in KGs

POLLUTANT METHOD

QUANTITY

Method Used

Pollutant No. Name M/C/E

Method Code Designation or Description

Emission Point 1

T (Total) KG/Year

A (Accidental) KG/Year

F (Fugitive) KG/Year

238 Ammonia (as N) M OTH

Method based on APHA, 2005, 21st Edition, Method 4500-NH3 F 48600.0 48600.0 0.0 0.0

303 BOD M OTH

Method based on APHA, 2005, 21st Edition, Method 5210-B. 107800.0 107800.0 0.0 0.0

240 Suspended Solids M OTH

Method based on APHA, 2005, 21st Edition, Method 2540-D 45700.0 45700.0 0.0 0.0

343 Sulphate M OTH

Ion chromatography method based on "Standard Methods for the Examination of Water and Wastewater, 2005, 21st edition, Method 4110B published by the APHA, AWWA and WEF 1150000.0

1150000.0 0.0 0.0

358 Tin M CRM

U.S. EPA method 200.8 (supplement 1 rev. 5.4 May 1994) 1.4 1.4 0.0 0.0

363 Total Dissolved Solids M OTH

Method based on APHA, 2005, 21st Edition, Method 2540C 2050000.0

2050000.0 0.0 0.0

347 Total heavy metals M CRM

U.S. EPA method 200.8 (supplement 1 rev. 5.4 May 1994) 177.0 177.0 0.0 0.0

356 Cobalt M CRM

U.S. EPA method 200.8 (supplement 1 rev. 5.4 May 1994) 0.78 0.78 0.0 0.0

0.0 0.0 0.0 0.0

| PRTR# : P0207 | Facility Name : Intel Ireland Limited | Filename : P0207_2010(1).xls | Return Year : 2010 |

30/03/2011 17:34

Page 78: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

5. ONSITE TREATMENT & OFFSITE TRANSFERS OF WASTE

5 99

Please enter all quantities on this sheet in Tonnes

96

Quantity (Tonnes per Year) Method Used

Haz Waste : Name and Licence/Permit No of Next

Destination Facility Non Haz Waste: Name and

Licence/Permit No of Recover/Disposer

Haz Waste : Address of Next Destination Facility

Non Haz Waste: Address of Recover/Disposer

Name and License / Permit No. and Address of Final

Recoverer / Disposer (HAZARDOUS WASTE

ONLY)

Actual Address of Final Destination i.e. Final

Recovery / Disposal Site (HAZARDOUS WASTE

ONLY)

Transfer Destination

European

Waste

Code Hazardou

s Quantity T/Year Description of Waste

Waste Treatment Operation M/C/E

Method Used

Location of

Treatment

Name and Licence / Permit No. of Recoverer / Disposer

/ Broker Address of Recoverer /

Disposer / Broker

Name and Address of Final Destination i.e. Final

Recovery / Disposal Site (HAZARDOUS WASTE

ONLY)

Licence / Permit No. of Final Destination i.e. Final Recovery / Disposal Site (HAZARDOUS WASTE

ONLY)

Within the Country

15 01 01 No 11.22

paper and cardboard packaging R12 M Weighed

Offsite in Ireland

Greenstar West Dublin,W0188-01

MRF West Dublin,Site 14b 3A,Greenogue Industrial Estate,Rathcoole Dublin,Ireland

Within the Country

15 01 02 No 1.26 plastic packaging R12 M Weighed

Offsite in Ireland

Greenstar West Dublin,W0188-01

MRF West Dublin,Site 14b 3A,Greenogue Industrial Estate,Rathcoole Dublin,Ireland

To Other Countries

15 01 02 No 19.37 plastic packaging R3 M Weighed Abroad

Polymer Recovery Ltd.,NCC/E/POL021/EL and NCC/026455

Priory road Prieston ,Boston Lincs,PE22 OJZ,.,United Kingdom

To Other Countries

15 01 02 No 6.84 plastic packaging R3 M Weighed Abroad

Greenstar UK,EPR/FP3396ZN

Plastics Road ,Wilton International,Redcar,TS10 4RG,United Kingdom

Within the Country

15 01 06 No 197.31 mixed packaging R12 M Weighed

Offsite in Ireland

Greenstar West Dublin,W0188-01

MRF West Dublin,Site 14b 3A,Greenogue Industrial Estate,Rathcoole Dublin,Ireland

Within the Country

15 01 06 No 0.59 mixed packaging R12 M Weighed

Offsite in Ireland

Greenstar Millenium Park,W0183-01

Cappagh Road,Ballycoolin,Dublin 11,.,Ireland

Within the Country

15 01 06 No 17.08 mixed packaging R5 M Weighed

Offsite in Ireland

Greyhound Recycling,W0205-01

Crag Avenue Industrial Estate,Clondalkin,Dublin 22,.,Ireland

Within the Country

17 01 07 No 213.44

mixture of concrete, bricks, tiles and ceramics other than those mentioned in 17 01 06 R3 M Weighed

Offsite in Ireland

Premier Waste,WFP-DS-09-0003-01

Unit 6 Premier Business Park,Turnpike Road ,Ballymount,Dublin 6,Ireland

Within the Country

17 02 02 No 7.2 glass R5 M Weighed

Offsite in Ireland

Glassco Recycling Ltd.,WP247-2006

Site 4,Ozberstown Business Park,Naas,Co Kildare,Ireland

Within the Country

19 09 05 No 6.63

saturated or spent ion exchange resins R13 M Weighed

Offsite in Ireland

Greenstar West Dublin,W0188-01

MRF West Dublin,Site 14b 3A,Greenogue Industrial Estate,Rathcoole Dublin,Ireland

Within the Country

19 09 05 No 5.88

saturated or spent ion exchange resins R13 M Weighed

Offsite in Ireland

Greenstar Millenium Park,W0183-01

Cappagh Road,Ballycoolin,Dublin 11,.,Ireland

Within the Country

20 01 01 No 13.32 paper and cardboard R3 M Weighed

Offsite in Ireland Baileys Recycling ,WPT94

Rosemount Business Park,Ballycoolin Road,Dublin 11,.,Ireland

Page 79: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Quantity (Tonnes per Year) Method Used

Haz Waste : Name and Licence/Permit No of Next

Destination Facility Non Haz Waste: Name and

Licence/Permit No of Recover/Disposer

Haz Waste : Address of Next Destination Facility

Non Haz Waste: Address of Recover/Disposer

Name and License / Permit No. and Address of Final

Recoverer / Disposer (HAZARDOUS WASTE

ONLY)

Actual Address of Final Destination i.e. Final

Recovery / Disposal Site (HAZARDOUS WASTE

ONLY)

Transfer Destination

European

Waste

Code Hazardou

s Quantity T/Year Description of Waste

Waste Treatment Operation M/C/E

Method Used

Location of

Treatment

Name and Licence / Permit No. of Recoverer / Disposer

/ Broker Address of Recoverer /

Disposer / Broker

Name and Address of Final Destination i.e. Final

Recovery / Disposal Site (HAZARDOUS WASTE

ONLY)

Licence / Permit No. of Final Destination i.e. Final Recovery / Disposal Site (HAZARDOUS WASTE

ONLY)

Within the Country

20 01 02 No 2.56 glass R13 M Weighed

Offsite in Ireland

Glassco Recycling Ltd.,WP247-2006

Site 4,Ozberstown Business Park,Naas,Co Kildare,Ireland

Within the Country

20 01 02 No 2.0 glass R13 M Weighed

Offsite in Ireland

Greenstar West Dublin,W0188-01

MRF West Dublin,Site 14b 3A,Greenogue Industrial Estate,Rathcoole Dublin,Ireland

Within the Country

20 01 08 No 56.11

biodegradable kitchen and canteen waste R3 M Weighed

Offsite in Ireland

Greenstar West Dublin,W0188-01

MRF West Dublin,Site 14b 3A,Greenogue Industrial Estate,Rathcoole Dublin,Ireland

Within the Country

20 01 08 No 32.4

biodegradable kitchen and canteen waste R9 M Weighed

Offsite in Ireland BEFOS,WMP05/2000

Camphill Ballytobin,Callan,Co. Kilkenny,.,Ireland

Within the Country

20 01 08 No 81.6

biodegradable kitchen and canteen waste R9 M Weighed

Offsite in Ireland

Premier Proteins Ltd,P0045-05

Poolbeg,Balinasloe,Co. Galway,.,Ireland

Within the Country

20 01 11 No 1.07 textiles R3 M Weighed

Offsite in Ireland

Textile Recycling Ltd.,WPR014

Glen Abbey Complex,Begard Road,Tallaght,Dublin 4,Ireland

Within the Country

20 01 11 No 0.22 textiles R3 M Weighed

Offsite in Ireland

Greenstar West Dublin,W0188-01

MRF West Dublin,Site 14b 3A,Greenogue Industrial Estate,Rathcoole Dublin,Ireland

Within the Country

20 01 25 No 5.78 edible oil and fat R9 M Weighed

Offsite in Ireland Frylite Ltd,WPR067

Unit 12 Ballymount Industrial Estate,Ballymount,Dublin 22,.,Ireland

Within the Country

20 01 25 No 0.24 edible oil and fat R3 M Weighed

Offsite in Ireland

Agri Pure/Greenclean Waste Management Ltd,W0222-01

Coldwinters,Blakescross,Lusk,Co. Dublin,Ireland

Within the Country

20 01 36 No 24.99

discarded electrical and electronic equipment other than those mentioned in 20 01 21, 20 01 23 and 20 01 35 R12 M Weighed

Offsite in Ireland

Rehab Recycling,WPR033/2

Unit 77 Broomhill Road,Talaght,Dublin,.,Ireland

Within the Country

20 01 36 No 1.0

discarded electrical and electronic equipment other than those mentioned in 20 01 21, 20 01 23 and 20 01 35 R12 M Weighed

Offsite in Ireland

Greyhound Recycling,W0205-01

Crag Avenue Industrial Estate,Clondalkin,Dublin 22,.,Ireland

Within the Country

20 01 36 No 39.54

discarded electrical and electronic equipment other than those mentioned in 20 01 21, 20 01 23 and 20 01 35 R12 M Weighed

Offsite in Ireland Inmark/Techrec,W0233-01

51 Park West Ind Est.,Nangor Road,Dublin 12,.,Ireland

Page 80: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Within the Country

20 01 38 No 9.02

wood other than that mentioned in 20 01 37 R3 M Weighed

Offsite in Ireland

Greenstar Millenium Park,W0183-01

Cappagh Road,Ballycoolin,Dublin 11,.,Ireland

Within the Country

20 01 38 No 100.56

wood other than that mentioned in 20 01 37 R3 M Weighed

Offsite in Ireland

Greenstar West Dublin,W0188-01

MRF West Dublin,Site 14b 3A,Greenogue Industrial Estate,Rathcoole Dublin,Ireland

Within the Country

20 03 01 No 61.98 mixed municipal waste D5 M Weighed

Offsite in Ireland

Greenstar West Dublin,W0188-01

MRF West Dublin,Site 14b 3A,Greenogue Industrial Estate,Rathcoole Dublin,Ireland

Within the Country

20 03 01 No 309.61 mixed municipal waste R1 M Weighed

Offsite in Ireland

Greyhound Recycling,W0205-01

Crag Avenue Industrial Estate,Clondalkin,Dublin 22,.,Ireland

Within the Country

20 03 06 No 14.0

waste from sewage cleaning D7 M Weighed

Offsite in Ireland

Ringsend Waste Water Treatment Plant,D0034-01

Ringsend ,Dublin 4,.,.,Ireland

Within the Country

20 03 07 No 4.08 bulky waste R12 M Weighed

Offsite in Ireland

Greenstar Millenium Park,W0183-01

Cappagh Road,Ballycoolin,Dublin 11,.,Ireland

Within the Country

20 03 07 No 0.96 bulky waste D5 M Weighed

Offsite in Ireland

Greenstar Millenium Park,W0183-01

Cappagh Road,Ballycoolin,Dublin 11,.,Ireland

Within the Country

20 03 07 No 309.0 bulky waste R12 M Weighed

Offsite in Ireland

Greenstar West Dublin,W0188-01

MRF West Dublin,Site 14b 3A,Greenogue Industrial Estate,Rathcoole Dublin,Ireland

Within the Country

20 03 07 No 72.5 bulky waste D5 M Weighed

Offsite in Ireland

Greenstar West Dublin,W0188-01

MRF West Dublin,Site 14b 3A,Greenogue Industrial Estate,Rathcoole Dublin,Ireland

To Other Countries

11 01 11 Yes 695.0

aqueous rinsing liquids containing dangerous substances (Ammonium sulphate waste) R5 M Weighed Abroad

Koppers UK Ltd.,EA (UK) BV770IL Variation FP3034SE Variation DP3532SR.

Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom

Koppers UK Ltd.,EA (UK) BV770IL Variation FP3034SE Variation DP3532SR.,Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom

Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom

To Other Countries

06 01 01 Yes 36.22

sulphuric acid and sulphurous acid (Concentrated Copper Waste) R6 M Weighed Abroad

Hydrometal SA ,R.I.2/15.97.22 No. DDT/14/MC

Zoning Industrial D Ehein,B-4480,Engis,.,Belgium

Hydrometal SA ,R.I.2/15.97.22 No. DDT/14/MC,Zoning Industrial D Ehein,.,Engis,B-4480,Belgium

Zoning Industrial D Ehein,.,Engis,B-4480,Belgium

To Other Countries

11 01 98 Yes 6.58

other wastes containing dangerous substances (concentrated copper sludge) R4 M Weighed Abroad

Veolia Environmental Services Technical solutions Ltd. (c/o Eco-safe Systems Ltd.),W0054-02

Unit 1A,Allied Industrial Estate ,Kylemore Road Ballyfermot ,D10,Ireland

Mastermelt Refining Services Ltd.,EA (UK) Permit BL132 variation BX127 Variation PP3130LC.,Staden Kane Industrial Estate,Ashbourne Road,Buxton Derbyshire,SK179RZ,United Kingdom

Staden Kane Industrial Estate,Ashbourne Road,Buxton Derbyshire,SK179RZ,United Kingdom

Page 81: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

To Other Countries

06 01 01 Yes 263.38

sulphuric acid and sulphurous acid (concentrated metal waste) R6 M Weighed Abroad

Koppers UK Ltd.,EA (UK) BV770IL Variation FP3034SE Variation DP3532SR.

Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom

Koppers UK Ltd.,EA (UK) BV770IL Variation FP3034SE Variation DP3532SR.,Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom

Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom

To Other Countries

11 02 05 Yes 2.66

wastes from copper hydrometallurgical processes containing dangerous substances (copper balls with residual sulphuric acid) R4 M Weighed Abroad

Veolia Environmental Services Technical solutions Ltd. (c/o Eco-safe Systems Ltd.),W0054-02

Unit 1A,Allied Industrial Estate ,Kylemore Road Ballyfermot ,D10,Ireland

Mastermelt Refining Services Ltd.,EA (UK) Permit BL132 variation BX127 Variation PP3130LC.,Staden Kane Industrial Estate,Ashbourne Road,Buxton Derbyshire,SK179RZ,United Kingdom

Staden Kane Industrial Estate,Ashbourne Road,Buxton Derbyshire,SK179RZ,United Kingdom

Within the Country

11 01 10 No 289.38

sludges and filter cakes other than those mentioned in 11 01 09 (calcium fluoride filter cake) D1 M Weighed

Offsite in Ireland

Greenstar (Knockharley Landfill),W146-03

Kentstown,.,.,Co. Meath,Ireland

Within the Country

20 01 21 Yes 2.18

fluorescent tubes and other mercury-containing waste R4 M Weighed

Offsite in Ireland

Irish lamps Recycling Co. Ltd.,WFP-KE-08-0348-01,Woodstock Ind. Estate ,Kilkenny Road ,Athy,Co. Kildare,Ireland

Woodstock Ind. Estate ,Kilkenny Road ,Athy,Co. Kildare,Ireland

Irish lamps Recycling Co. Ltd.,WFP-KE-08-0348-01,Woodstock Ind. Estate ,Kilkenny Road ,Athy,Co. Kildare,Ireland

Woodstock Ind. Estate ,Kilkenny Road ,Athy,Co. Kildare,Ireland

Within the Country

20 01 35 Yes 0.68

discarded electrical and electronic equipment other than those mentioned in 20 01 21 and and 20 01 23 containing hazardous components (lamp fittings) R4 M Weighed

Offsite in Ireland

Irish lamps Recycling Co. Ltd.,WFP-KE-08-0348-01,Woodstock Ind. Estate ,Kilkenny Road ,Athy,Co. Kildare,Ireland

Woodstock Ind. Estate ,Kilkenny Road ,Athy,Co. Kildare,Ireland

Irish lamps Recycling Co. Ltd.,WFP-KE-08-0348-01,Woodstock Ind. Estate ,Kilkenny Road ,Athy,Co. Kildare,Ireland

Woodstock Ind. Estate ,Kilkenny Road ,Athy,Co. Kildare,Ireland

Within the Country

06 04 04 Yes 0.01

wastes containing mercury (mercury switches) R4 M Weighed

Offsite in Ireland

Irish lamps Recycling Co. Ltd.,WFP-KE-08-0348-01,Woodstock Ind. Estate ,Kilkenny Road ,Athy,Co. Kildare,Ireland

Woodstock Ind. Estate ,Kilkenny Road ,Athy,Co. Kildare,Ireland

Irish lamps Recycling Co. Ltd.,WFP-KE-08-0348-01,Woodstock Ind. Estate ,Kilkenny Road ,Athy,Co. Kildare,Ireland

Woodstock Ind. Estate ,Kilkenny Road ,Athy,Co. Kildare,Ireland

To Other Countries

12 01 16 Yes 1.52

waste blasting material containing dangerous substances (arsenic slurry waste) D10 M Weighed Abroad

Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

Within the Country

06 01 04 Yes 140.36

phosphoric and phosphorous acid D9 M Weighed

Offsite in Ireland

Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

To Other Countries

06 01 04 Yes 275.72

phosphoric and phosphorous acid R6 M Weighed Abroad

Koppers UK Ltd.,EA (UK) BV770IL Variation FP3034SE Variation DP3532SR.,Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom

Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom

Koppers UK Ltd.,EA (UK) BV770IL Variation FP3034SE Variation DP3532SR.,Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom

Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom

Page 82: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

To Other Countries

11 01 06 Yes 45.44

acids not otherwise specified (reclaim metal waste) D9 M Weighed Abroad

Koppers UK Ltd.,EA (UK) BV770IL Variation FP3034SE Variation DP3532SR.,Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom

Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom

Koppers UK Ltd.,EA (UK) BV770IL Variation FP3034SE Variation DP3532SR.,Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom

Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom

Within the Country

11 01 16 Yes 14.45

saturated or spent ion exchange resins (slurry copper waste spent resin) R4 E

Volume Calculation

Offsite in Ireland

Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

To Other Countries

06 13 02 Yes 5.1

spent activated carbon (except 06 07 02) - activated carbon from CCW waste treatment system R1 E

Volume Calculation Abroad Enva Ireland Ltd.,W0041-01

Smithstown Industrial Estate,.,Shannon,Co. Clare,Ireland

Lindenschmidt KG,Waste Disposer code E97095037,Umweltservice,Krombacher Strafe 42-46,57223 Kreuztal,.,Germany

Umweltservice,Krombacher Strafe 42-46,57223 Kreuztal,.,Germany

Within the Country

14 06 03 Yes 1147.07

other solvents and solvent mixtures - mixed solvent waste R2 M Weighed

Offsite in Ireland

Veolia ES Technical Solutions Ltd,W0050-02,Corrin ,.,Fermoy,Co. Cork,Ireland

Veolia ES Technical Solutions Ltd,W0050-02,Corrin Fermoy ,Co. Cork,Ireland

Veolia ES Technical Solutions Ltd,W0050-02,Corrin ,.,Fermoy,Co. Cork,Ireland

Veolia ES Technical Solutions Ltd,W0050-02,Corrin Fermoy ,Co. Cork,Ireland

To Other Countries

11 01 16 Yes 8.27

saturated or spent ion exchange resins D10 M Weighed Abroad

Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

Within the Country

20 01 26 Yes 1.8

oil and fat other than those mentioned in 20 01 25 R9 M Weighed

Offsite in Ireland

Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Enva Ireland Ltd.,W0184-01,Clonminam Industrial Estate ,.,Portlaoise,Co. Laois,Ireland

Clonminam Industrial Estate ,.,Portlaoise,Co. Laois,Ireland

To Other Countries

14 06 01 Yes 0.17

chlorofluorocarbons, HCFC, HFC D10 M Weighed Abroad

Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

Within the Country

17 04 01 No 63.94 copper, bronze, brass R12 M Weighed

Offsite in Ireland Davis Recycling,W0205-01

Hammond Lane Crag Avenue,Clondalkin Ind. Est.,Clondalkin ,Dublin,Ireland

Within the Country

17 04 01 No 28.5 copper, bronze, brass R4 M Weighed

Offsite in Ireland Inmark/Techrec,W0233-01

51 Park West Ind Est.,Nangor Road,Dublin 12,.,Ireland

Within the Country

17 04 01 No 2.42 copper, bronze, brass R4 M Weighed

Offsite in Ireland

Greyhound Recycling,W0205-01

Crag Avenue Industrial Estate,Clondalkin,Dublin 22,.,Ireland

Within the Country

17 04 01 No 15.04 copper, bronze, brass R4 M Weighed

Offsite in Ireland

Hegarty Metals Processors (A1 Metals),ATF WMP007E

Acragar,Mountmellick,Co. Laois,.,Ireland

Within the Country

17 04 02 No 2.26 aluminium R4 M Weighed

Offsite in Ireland

Hegarty Metals Processors (A1 Metals),ATF WMP007E

Acragar,Mountmellick,Co. Laois,.,Ireland

Page 83: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Within the Country

17 04 02 No 353.1 aluminium R4 M Weighed

Offsite in Ireland Davis Recycling,W0205-01

Hammond Lane Crag Avenue,Clondalkin Ind. Est.,Clondalkin ,Dublin,Ireland

Within the Country

17 04 02 No 51.79 aluminium R4 M Weighed

Offsite in Ireland Inmark/Techrec,W0233-01

51 Park West Ind Est.,Nangor Road,Dublin 12,.,Ireland

Within the Country

17 04 05 No 4.67 iron and steel R4 M Weighed

Offsite in Ireland

Hegarty Metals Processors (A1 Metals),ATF WMP007E

Acragar,Mountmellick,Co. Laois,.,Ireland

Within the Country

17 04 05 No 125.02 iron and steel R4 M Weighed

Offsite in Ireland Davis Recycling,W0205-01

Hammond Lane Crag Avenue,Clondalkin Ind. Est.,Clondalkin ,Dublin,Ireland

Within the Country

17 04 05 No 35.24 iron and steel R4 M Weighed

Offsite in Ireland Inmark/Techrec,W0233-01

51 Park West Ind Est.,Nangor Road,Dublin 12,.,Ireland

Within the Country

17 08 02 No 92.72

gypsum-based construction materials other than those mentioned in 17 08 01 R5 M Weighed

Offsite in Ireland Recycle Works,WPT112

Unit 1 Glenroyal Centre,Straffan Road,Maynooth,Co. Kildare,Ireland

Within the Country

19 12 04 No 86.62 plastic and rubber R5 M Weighed

Offsite in Ireland

Greyhound Recycling,W0205-01

Crag Avenue Industrial Estate,Clondalkin,Dublin 22,.,Ireland

Within the Country

19 12 04 No 7.76 plastic and rubber R5 M Weighed

Offsite in Ireland Panda Waste,W0140-03

Neurendale Ltd.,Cappagh Rd,Finglas,Dublin 12,Ireland

Within the Country

20 01 40 No 659.1 metals R4 M Weighed

Offsite in Ireland

Hegarty Metals Processors (A1 Metals),ATF WMP007E

Acragar,Mountmellick,Co. Laois,.,Ireland

Within the Country

20 01 40 No 2.54 metals R12 M Weighed

Offsite in Ireland Baileys Recycling ,WPT94

Rosemount Business Park,Ballycoolin Road,Dublin 11,.,Ireland

Within the Country

20 01 40 No 23.88 metals R4 M Weighed

Offsite in Ireland

Greyhound Recycling,W0205-01

Crag Avenue Industrial Estate,Clondalkin,Dublin 22,.,Ireland

Within the Country

20 01 40 No 635.61 metals R4 M Weighed

Offsite in Ireland Davis Recycling,W0205-01

Hammond Lane Crag Avenue,Clondalkin Ind. Est.,Clondalkin ,Dublin,Ireland

Within the Country

20 01 40 No 15.6 metals R4 M Weighed

Offsite in Ireland Inmark/Techrec,W0233-01

51 Park West Ind Est.,Nangor Road,Dublin 12,.,Ireland

Within the Country

20 01 40 No 5.44 metals R4 M Weighed

Offsite in Ireland

Greenstar Millenium Park,W0183-01

Cappagh Road,Ballycoolin,Dublin 11,.,Ireland

Within the Country

20 01 40 No 55.82 metals R4 M Weighed

Offsite in Ireland

Multi Metals Recycling Ltd.,ESS/15/8/12 (319)

Blessington,Co. Wicklow,.,.,Ireland

Within the Country

20 01 40 No 72.64 metals R4 M Weighed

Offsite in Ireland

Greenstar West Dublin,W0188-01

MRF West Dublin,Site 14b 3A,Greenogue Industrial Estate,Rathcoole Dublin,Ireland

Page 84: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Within the Country

06 01 04 Yes 35.09

phosphoric and phosphorous acid (tank washings) D9 M Weighed

Offsite in Ireland

Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Within the Country

06 02 04 Yes 0.82

sodium and potassium hydroxide (tank washings) D9 M Weighed

Offsite in Ireland

Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Within the Country

11 01 06 Yes 4.09

acids not otherwise specified (tank washings) D9 M Weighed

Offsite in Ireland

Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Within the Country

06 02 01 Yes 26.0

calcium hydroxide (tank washings) D9 M Weighed

Offsite in Ireland

Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Within the Country

06 01 01 Yes 12.0

sulphuric acid and sulphurous acid (tank washings) D9 M Weighed

Offsite in Ireland

Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Within the Country

11 01 11 Yes 19.94

aqueous rinsing liquids containing dangerous substances (tank washings from KD100 system) D9 M Weighed

Offsite in Ireland

Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland

To Other Countries

16 06 02 Yes 2.23 Ni-Cd batteries R4 M Weighed Abroad

Rilta Environmental Ltd.,Waste licence 192-02

Block 402 Greenogue Business Park ,Rathcoole,.,Dublin,Ireland

HJ Enthiren & Sons,EA (UK) BL 5598,Darly Dale Smelter ,South Darley ,Matlock Derbyshire,DE42LP,United Kingdom

Darly Dale Smelter ,South Darley ,Matlock Derbyshire,DE42LP,United Kingdom

Within the Country

16 06 04 No 0.41

alkaline batteries (except 16 06 03) R4 M Weighed

Offsite in Ireland

Rilta Environmental Ltd.,Waste licence 192-02

Block 402 Greenogue Business Park ,Rathcoole,.,Dublin,Ireland

To Other Countries

16 06 01 Yes 3.49 lead batteries R4 M Weighed Abroad

Rilta Environmental Ltd.,Waste licence 192-02

Block 402 Greenogue Business Park ,Rathcoole,.,Dublin,Ireland

HJ Enthiren & Sons,EA (UK) BL 5598,Darly Dale Smelter ,South Darley ,Matlock Derbyshire,DE42LP,United Kingdom

Darly Dale Smelter ,South Darley ,Matlock Derbyshire,DE42LP,United Kingdom

To Other Countries

14 06 03 Yes 0.2

other solvents and solvent mixtures (polimide recovery waste SVG/PRW) D10 M Weighed Abroad

Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

To Other Countries

15 02 02 Yes 5.42

absorbents, filter materials (including oil filters not otherwise specified), wiping cloths, protective clothing contaminated by dangerous substances (corrosive solid waste) D10 M Weighed Abroad

Sava GmbH & Co. Kg,A51G00508,Osterweute 125541,.,Brunsbuttel,.,Germany

Osterweute 125541,.,Brunsbuttel,.,Germany

Sava GmbH & Co. Kg,A51G00508,Osterweute 125541,.,Brunsbuttel,.,Germany

Osterweute 125541,.,Brunsbuttel,.,Germany

To Other Countries

15 02 02 Yes 170.54

absorbents, filter materials (including oil filters not otherwise specified), wiping cloths, protective clothing contaminated by dangerous substances D10 M Weighed Abroad

Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

Page 85: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

(corrosive solid waste)

To Other Countries

14 06 05 Yes 68.81

sludges or solid wastes containing other solvents (flammable solids) D10 M Weighed Abroad

Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

To Other Countries

15 02 02 Yes 10.18

absorbents, filter materials (including oil filters not otherwise specified), wiping cloths, protective clothing contaminated by dangerous substances (flammable solids) D10 M Weighed Abroad

Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

To Other Countries

16 05 09 No 13.5

discarded chemicals other than those mentioned in 16 05 06, 16 05 07 or 16 05 08 D10 M Weighed Abroad

Ekokem Oy Ab,0395Y0270/11181/YSO/99

P.O. Box 181,.,Rihimaki,FIN-11101,Finland

To Other Countries

15 02 02 Yes 22.16

absorbents, filter materials (including oil filters not otherwise specified), wiping cloths, protective clothing contaminated by dangerous substances D10 M Weighed Abroad

Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

To Other Countries

17 09 03 Yes 321.32

other construction and demolition wastes (including mixed wastes) containing dangerous substances D10 M Weighed Abroad

Sava GmbH & Co. Kg,A51G00508,Osterweute 125541,.,Brunsbuttel,.,Germany

Osterweute 125541,.,Brunsbuttel,.,Germany

Sava GmbH & Co. Kg,A51G00508,Osterweute 125541,.,Brunsbuttel,.,Germany

Osterweute 125541,.,Brunsbuttel,.,Germany

To Other Countries

16 05 07 Yes 0.54

discarded inorganic chemicals consisting of or containing dangerous substances (labpacks) D10 M Weighed Abroad

Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

To Other Countries

16 05 09 No 17.26

discarded chemicals other than those mentioned in 16 05 06, 16 05 07 or 16 05 08 (warehouse chemicals) D10 M Weighed Abroad

Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland

Page 86: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Appendix B

Groundwater Monitoring Summary Report

Page 87: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

EXECUTIVE SUMMARY, GROUNDWATER 2010

FOR

INTEL IRELAND LTD, LEIXLIP, CO. KILDARE

RENAITH LYONS

Report Ref: 16925-3

TMS Environment Ltd

21st March 2011

Prepared by: Phoebe Conway

Environmental Consultant

Prepared by

Phoebe Conway

Approved by:

Craig O‟Connor

Senior Consultant

Date:

Approved by

Craig O‟Connor

Senior Consultant

Page 88: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Intel Ireland Ltd: Executive Summary, Groundwater 2010

TMS Environment Ltd Ref. 16925-3

1.0 Scope

This report presents the non-technical executive summary of the analytical results

of groundwater samples collected from monitoring boreholes at the Intel Ireland

Ltd. campus at Leixlip, Co. Kildare in February and August 2010. Sampling was

conducted to satisfy biannual groundwater monitoring requirements as specified in

IPPC Licence reference no. P0207-03.

Full copies of both reports are available through TMS Environment Ltd or Intel

Ireland Ltd. (Report Reference: 16244-1 and 16925-1).

2.0 Executive Summary

Biannual groundwater sampling was carried out on 3rd

, 8th, 9

th and 10

th February

and on 9th, 10

th, 11

th, 12

th and 16

th August 2010 to satisfy the IPPC Licence

requirements of Intel Ireland Ltd. Tables A & B below provide a summary of the

results compared to the EPA Interim Guideline Values (IGVs) and the Drinking

Water Limits (S.I. No. 278 of 2007) for those parameters where available. Results

which exceed the EPA IGVs are shown in bold text.

Historically groundwater on site has shown elevated levels of Conductivity,

Chloride, Total Ammonia and Total Nitrogen have been elevated both up-gradient

and down-gradient of the Intel Ireland Site. This immediately suggests an off-site

source for the elevated concentrations observed. Elevated concentrations are not

uniformly elevated in groundwater across the site, suggesting that it is not a diffuse

source up-gradient of the site. Also, concentrations at individual monitoring points

vary with time, suggesting a discontinuous source with pollution of groundwater

occurring at varying rates (e.g. like a leaking sewer).

On comparison of the 2010 results with the EPA‟s IGVs during 2010, some wells

exceeded the IGV for conductivity during the first monitoring event (MW1, MW4,

MW13, MW14, MW15 and MW16) and the second monitoring event (MW1,

MW4, MW13, MW14, MW15, MW16 and MW17). It is likely that the source of

elevated conductivity originates from off-site due to the fact that MW1 and MW13

are control wells (on the site boundary) and MW14, MW15 and MW16 are

downstream of these wells. In addition, there are no Intel operations between the

site boundary and MW14 and MW15. MW4 has shown historically to have a high

conductivity value above the EPA IGV. MW17 is situated close to MW4 down-

gradient of the site. There has been little change in the background levels for these

wells over the past number of sampling events. The fact that Electrical

Conductivity is elevated both up-gradient and down-gradient of the site

immediately suggests an off-site source for the elevated concentrations observed.

EC concentrations are not uniformly elevated in groundwater across the site,

suggesting that it is not a diffuse source up-gradient of the site. Also,

Page 89: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Intel Ireland Ltd: Executive Summary, Groundwater 2010

TMS Environment Ltd Ref. 16925-3

concentrations at individual monitoring points vary with time, suggesting a

discontinuous source with pollution of groundwater occurring at varying rates (e.g.

like a leaking sewer).

The concentration for chloride recorded in a number of wells exceeded the EPA

IGV of 30mg/l in the first biannual monitoring event (MW1, MW2, MW4, MW7,

MW11, MW12, MW13, MW14, MW15, MW16 and MW19) and the second

biannual monitoring event (MW1, MW2, MW4, MW5, MW7, MW8, MW10,

MW11, MW12, MW13, MW14, MW15, MW16, MW17, MW19 and MW20).

Chloride has been historically elevated above the EPA IGV in MW1, MW2,

MW5, MW13, MW14, MW16 and MW19. It can be demonstrated that the source

of elevated chloride is likely to originate from off-site due to the fact that MW1

and MW13 are control wells (on site boundary) and MW14, MW15 and MW16

are downstream of these well. In addition, there are no Intel operations between

the site boundary and MW14 and MW15. Concentrations above the EPA IGV in

MW4, MW5, MW7, MW8, MW10, MW11, MW12, MW17 and MW20 are not

historically as consistently elevated. On examination of the historical chloride

results for all the wells on site, there is a background level of approximately 25-30

mg/l, as would be expected for this area of Ireland. Chloride concentrations are

consistently elevated in monitoring well MW1 up-gradient of the site and MW14

at the eastern perimeter of the site. Sampling of other wells shows occasionally

elevated concentrations above background, however the elevated concentrations

are not sustained.

Total Ammonia was found to exceed the EPA IGV of 0.15 mg/l as NH4 in six well

during the first biannual monitoring event (MW4 (0.298 mg/l as NH4), MW5

(0.171 mg/l as NH4), MW7 (2.13 mg/l as NH4), MW8 (0.235mg/l as NH4), MW14

(0.224 mg/l as NH4), and MW18 (0.151 mg/l as NH4). The presence of Total

Ammonia in groundwater in the up-gradient wells (MW7 & MW8) suggests an

off-site source of organic pollution. The two possible off-site sources up-gradient

of the site are the Local Authority sewer running along the Maynooth - Leixlip

road and agricultural activity up-gradient of the site. Given that the agricultural

land up-gradient of Intel does not appear to be intensively grazed, the likely source

is the Local Authority sewer. MW14 and MW18 are situated to the north and

north-east of MW7 and as the groundwater flow direction is in a north north-

easterly direction it is suggested that the rise in Total Ammonia at these locations is

due to external factors. There were no exceedances to Total Ammonia during the

second biannual monitoring event.

All results reported for the first biannual monitoring event carried out in February

2010 were below the Drinking Water Limits set out in S.I. No. 278 of 2007 with

the exception of Total Ammonia in MW7. A Total Ammonia concentration of 2.13

mg/L NH4 was recorded in this well. The Drinking Water Limit for Total

Ammonia as NH4 is 0.3 mg/l as NH4. The Total Ammonia level in this well had

Page 90: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Intel Ireland Ltd: Executive Summary, Groundwater 2010

TMS Environment Ltd Ref. 16925-3

reduced to below the laboratory detection limit by the next sampling round in

August 2010. All Total Ammonia results for the second biannual monitoring event

in August were below the Drinking Water Limits set out in S.I. No. 278 of 2007.

No Volatile Organic Compounds (VOCs) were detected above the laboratory

detection limit in any groundwater samples tested during 2010.

All remaining parameters analysed were found to be below the EPA IGV and the

Drinking Water regulations during 2010.

An interesting observation on groundwater quality in the August 2010 monitoring

round was that the pH of groundwater was noticeable lower in most wells than in

previous monitoring rounds. Groundwater from most wells showed a reduction in

pH of between 0.2 - 1.0 from the average value observed over the last 9 sampling

rounds. The slightly reduced pH values are still within the typical range

encountered in shallow Irish aquifers (6.5-9.5). There has been no change in

sampling methodology and pH has been measured in the laboratory in all cases.

Since this trend is seen in most wells in August 2010, it was therefore most likely

due to natural variation in background groundwater quality. No further action is

required.

Page 91: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Intel Ireland Ltd: Executive Summary, Groundwater 2010

TMS Environment Ltd Ref. 16925-3

Table A First Biannual Monitoring Results (February 2010) Summary Table

Parameter Units MW1 MW2 MW3 MW4 MW5 MW7 MW8 MW9 MW10 EPA Interim Guideline

Value (IGV)

Drinking Water Limits (S.I. No. 278

of 2007) pH 7.2 7.7 7.5 7.3 7.4 7.2 7.6 7.3 7.3 ≥6.5 and ≤9.5 ≥6.5 and ≤9.5

Conductivity µS/cm 1149 590 720 1365 770 754 702 602 671 1000 µS/cm 2500 µS/cm

COD mg/l O2 10 <5 9 24 <5 <5 <5 10 9 - -

Nitrate mg/l NO3 2.3 1.3 1.4 3.6 1.5 1.5 14 3.9 1.1 25 mg/l NO3 50 mg/l NO3

Total Ammonia mg/l (as NH4) 0.084 0.042 0.11 0.298 0.171 2.13 0.235 <0.017 <0.017 0.15 mg/l as NH4 0.3 mg/l as NH4

Total Nitrogen mg/l N <1.2 1.8 3.1 3.1 3.3 1.8 3.7 <1.2 2 - -

Chloride mg/l Cl 132 43 29 88 28 33 30 1 27 30 mg/l Cl 250 mg/l Cl

Fluoride mg/l F 0.27 0.37 0.23 0.618 0.86 0.287 0.116 0.2 0.23 1 mg/l F 1.5 mg/l F

Parameter Units MW11 MW12 MW13 MW14 MW15 MW16 MW17 MW18 MW19 MW20 EPA Interim Guideline

Value (IGV)

Drinking Water Limits (S.I. No. 278 of 2007)

pH 7.3 7.4 7.1 7.4 7.2 7.2 7.5 7.5 7.2 7.3 ≥6.5 and ≤9.5 ≥6.5 and ≤9.5 Conductivity µS/cm 723 629 1164 1241 1084 1215 909 346 902 766 1000 µS/cm 2500 µS/cm

COD mg/l O2 66 9 <5 17 24 <5 <5 58 <5 5 - -

Nitrate mg/l NO3 2.4 1.4 1.2 3.5 1 18 1.2 1.2 5.4 26 25 mg/l NO3 50 mg/l NO3

Total Ammonia mg/l (as NH4) <0.017 0.025 0.092 0.224 0.063 <0.013 0.07 0.151 <0.017 <0.017 0.15 mg/l as NH4 0.3 mg/l as NH4

Total Nitrogen mg/l N 1.8 <1.2 4 2.6 3.5 6.3 2.5 2.3 4 7.7 - -

Chloride mg/l Cl 46 33 34 205 34 127 24 11 83 30 30 mg/l Cl 250 mg/l Cl

Fluoride mg/l F 0.36 0.78 0.221 0.735 0.206 0.163 0.455 0.492 0.633 0.19 1 mg/l F 1.5 mg/l F

Page 92: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Intel Ireland Ltd: Executive Summary, Groundwater 2010

TMS Environment Ltd Ref. 16925-3

Table B Second Biannual Monitoring Results (August 2010) Summary Table

Parameter Units MW1 MW2 MW3 MW4 MW5 MW7 MW8 MW9 MW10 EPA Interim Guideline

Value (IGV)

Drinking Water Limits (S.I. No. 278

of 2007) pH 6.59 6.51 6.75 6.58 6.72 6.98 6.57 6.70 6.75 ≥6.5 and ≤9.5 ≥6.5 and ≤9.5 Conductivity µS/cm 1055 638 733 1176 879 660 888 709 729 1000 µS/cm 2500 µS/cm

COD mg/l O2 < 5 6 < 5 < 5 < 5 < 5 < 5 < 5 < 5 - -

Nitrate mg/l NO3 1.78 < 1 1.79 16.9 < 1 2.89 11.9 2.81 1.79 25 mg/l NO3 50 mg/l NO3

Total Ammonia mg/l (as NH4) 0.015 <0.013 <0.013 <0.013 0.094 <0.013 0.026 <0.013 <0.013 0.15 mg/l as NH4 0.3 mg/l as NH4

Total Nitrogen mg/l N 1.4 1.5 < 1.2 3.8 1.2 2.7 2.7 1.4 < 1.2 - -

Chloride mg/l Cl 99 47 29 39 35 34 46 27 34 30 mg/l Cl 250 mg/l Cl

Fluoride mg/l F 0.34 0.33 < 0.02 0.363 0.68 0.220 < 0.02 < 0.02 0.494 1 mg/l F 1.5 mg/l F

Parameter Units MW11 MW12 MW13 MW14 MW15 MW16 MW17 MW18 MW19 MW20 EPA Interim

Guideline Value (IGV)

Drinking Water Limits (S.I. No. 278 of 2007)

pH 6.72 7.24 6.95 7.22 7.13 7.14 7.15 6.96 7.44 6.97 ≥6.5 and ≤9.5 ≥6.5 and ≤9.5 Conductivity µS/cm 728 712 1167 1294 1123 1410 1016 632 930 708 1000 µS/cm 2500 µS/cm

COD mg/l O2 9 < 5 < 5 < 5 < 5 6 8 1485 10 < 5 - -

Nitrate mg/l NO3 8.31 2.36 1.96 3.76 2.01 9.97 2.19 1.85 6.25 7.3 25 mg/l NO3 50 mg/l NO3

Total Ammonia mg/l (as NH4) 0.013 0.017 <0.013 0.084 <0.013 <0.013 0.067 <0.013 <0.013 0.024 0.15 mg/l as NH4 0.3 mg/l as NH4

Total Nitrogen mg/l N 1.9 1.3 1.2 < 1.2 3.2 3.5 < 1.2 1.4 2.2 2.2 - -

Chloride mg/l Cl 47 47 34 202 34 63 40 24 79 34 30 mg/l Cl 250 mg/l Cl

Fluoride mg/l F < 0.02 0.412 < 0.02 0.51 < 0.02 < 0.02 0.337 0.224 0.413 < 0.02 1 mg/l F 1.5 mg/l F

Page 93: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Appendix C

River Rye Monitoring Report

Page 94: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

For the Attention of: Prepared by:

Ms. Renaith Lyons Ms. Linda Lenihan

Intel Ireland Ltd. Environmental Scientist

Leixlip

Co. Kildare

Reviewed by:

Mr. Peter Coogan

Monitoring Team Leader

Ref: ECS3714 –2nd Bi-Annual Event 2010

Monitoring Date: 31st August 2010

Reporting Date: September 2010

This report shall not be reproduced except in full, without the approval of Bord na Móna Technical Services.

All queries concerning the report or its contents should be forwarded to the Monitoring Team leader.

BI-ANNUAL SURVEY OF THE RIVER

RYE AT THE INTEL IRELAND SITE,

COLLINSTOWN INDUSTRIAL PARK

LEIXLIP, CO. KILDARE

Page 95: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Intel (Ireland) Ltd. Report No. ECS3714

Bord na Móna Technical Services Page 2

September, 10

Executive Summary/Certification of Results

Intel (Ireland) Ltd. is required to carry out an assessment on a bi-annual basis, at its site in Leixlip,

Co. Kildare, of the water quality of the River Rye to comply with Schedule C.6.4. (Receiving Water

Monitoring) of its Integrated Pollution Prevention and Control Licence, Reg. No. P0207-03. Bord

na Móna Technical Services was contracted to assess the quality of surface waters at a number of

points along the river, including upstream and downstream of the surface water retention outlet (i.e.

discharge point to the river).

The site was visited by Bord na Móna Environmental Scientists on the 18th

of May and the 31st

of August 2010, to conduct the first and second bi-annual assessments, respectively. A total of

five surface water samples were returned to the laboratory for analysis. Results obtained were

compared with the European Communities “Environmental Objectives (Surface Waters)

Regulations, 2009 (S.I. No. 272 of 2009)”, the European Communities “Quality of Surface

Water Intended for the Abstraction of Drinking Water Regulations, 1989 (S.I. No. 294 of 1989)”

and the European Communities “Quality of Salmonid Waters Regulations, 1988 (S.I. No. 293 of

1988)”.

The surface water samples taken from the River Rye, both upstream and downstream of the Intel

facility, are of good quality; and there are no exceedences of the legislative limits for any of the

parameters measured.

There does not appear to be a deterioration of water quality downstream of the Intel (Ireland)

Ltd. site, indicating that the surface water discharges from this site are not resulting in significant

environmental impacts on the receiving waters.

The results of the investigation carried out by Bord na Móna Technical Services are presented in

Tables 1 and 2 below.

Page 96: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Intel (Ireland) Ltd. Report No. ECS3714

Bord na Móna Technical Services Page 3

September, 10

Table 1: Results of Surface Water Samples for First Bi-annual Analysis (May 2010

ECS3630)

TABLE 1: RESULTS OF SURFACE WATER SAMPLES CHEMICAL ANALYSIS

Surface Water Sampling Locations

Parameter RW-1 RW-2 RW-3 RW-4 RW-5 WQS

pH (pH units) 8.2 8.2 8.2 8.2 8.2 6.0 – 9.0 Note 1

Temperature (°C) 14.0 14.2 14.1 14.0 13.8 25 Note 2

Dissolved Oxygen (%) 132.6 137.9 138.2 135.0 131.6 >80% Note 1

Ammonia-N (mg/l) 0.05 0.07 0.06 0.06 0.13 High Status: ≤ 0.04

Good Status ≤0.065 Note 1

B.O.D. (mg/l) <2 <2 <2 <2 <2 High Status: ≤ 2.2

Good Status: ≤2.6 Note

1

Conductivity (µS/cm @

25°C) 627 618 617 612 614 1000

Note 2

Suspended Solids (mg/l) <5 <5 <5 <5 <5 25Note3

Chloride (mg/l) 25.27 25.21 25.31 25.29 26.11 250 Note 2

Fluoride (mg/l) <0.10 <0.10 <0.10 <0.10 <0.10 1.0 Note 2

Nitrate-N (mg/l) 0.99 0.96 0.96 0.92 0.95 11.29 *

Note 2

Nitrite-N (mg/l) <0.03 <0.03 <0.03 <0.03 <0.03 0.02 Note 3

Total Phosphorus (mg/l) <0.05 <0.05 <0.05 <0.05 <0.05 -

Arsenic (µg/l) <2 <2 <2 <2 <2 50 Note 2

Cobalt (µg/l) <2 <2 <2 <2 <2 -

Copper (µg/l) <2 <2 <2 <2 2 50 Note 2

Lead (µg/l) <2 <2 <2 <2 <2 50 Note 2

Nickel (µg/l) <2 <2 <2 <2 <2 -

Tin (µg/l) <2 <2 <2 <2 <2 -

Chromium (µg/l) <2 <2 <2 <2 <2 50 Note 2

Note: River Rye sampling points located upstream of the Intel surface water discharge point are shaded in blue.

Note 1: European Communities Environmental Objectives (Surface Waters) Regulations, 2009 (S.I. No. 272 of 2009).

Note 2: S.I. 294 of 1989: Water Quality Standard = Water Quality Standards set in the European Communities (Quality of

Surface Water Intended for the Abstraction of Drinking Water) Regulations, 1989. Limit values for A1 waters are shown.

Note 3: European Communities (Quality of Salmonid Waters) Regulations, 1988 (S.I. No. 293 of 1988)

< Indicates less than the laboratory detection limit

WQS = Water Quality Standard

* Converted Water Quality Standard for Nitrite, Nitrate and Ammonia as N (mg/l).

Page 97: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Intel (Ireland) Ltd. Report No. ECS3714

Bord na Móna Technical Services Page 4

September, 10

Table 2: Results of Surface Water Samples for Second Bi-annual Analysis (August 2010

ECS3714)

TABLE 2: RESULTS OF SURFACE WATER SAMPLES CHEMICAL ANALYSIS

Surface Water Sampling Locations

Parameter RW-1 RW-2 RW-3 RW-4 RW-5 WQS

pH (pH units) 7.9 8.1 8.2 8.3 8.3 6.0 – 9.0 Note 1

Temperature (°C) 12.8 12.7 13.0 13.9 13.0 25 Note 2

Dissolved Oxygen (%) 95.8 101.5 115.6 121.5 117.5 >80% Note 1

Ammonia-N (mg/l) 0.02 <0.02 <0.02 0.02 0.02 High Status: ≤ 0.04

Good Status ≤0.065 Note 1

B.O.D. (mg/l) <2 <2 2 <2 <2 High Status: ≤ 2.2

Good Status: ≤2.6 Note

1

Conductivity (µS/cm @

25°C) 725 761 722 662 687 1000

Note 2

Suspended Solids (mg/l) <5 <5 <5 <5 <5 25Note3

Chloride (mg/l) 28.90 28.55 29.64 29.20 31.26 250 Note 2

Fluoride (mg/l) 0.11 <0.10 0.10 0.13 <0.10 1.0 Note 2

Nitrate-N (mg/l) 0.78 0.75 0.71 0.68 0.70 11.29 *

Note 2

Nitrite-N (mg/l) <0.03 <0.03 <0.03 <0.03 <0.03 0.02 Note 3

Total Phosphorus (mg/l) 0.07 0.05 0.05 0.05 0.05 -

Arsenic (µg/l) <2 <2 <2 <2 <2 50 Note 2

Cobalt (µg/l) <2 <2 <2 <2 <2 -

Copper (µg/l) <2 <2 2 <2 <2 50 Note 2

Lead (µg/l) <2 <2 <2 <2 <2 50 Note 2

Nickel (µg/l) <2 2 <2 <2 <2 -

Tin (µg/l) <2 <2 <2 <2 <2 -

Chromium (µg/l) <2 <2 <2 <2 <2 50 Note 2

Note: River Rye sampling points located upstream of the Intel surface water discharge point are shaded in blue.

Note 1: European Communities Environmental Objectives (Surface Waters) Regulations, 2009 (S.I. No. 272 of 2009).

Note 2: S.I. 294 of 1989: Water Quality Standard = Water Quality Standards set in the European Communities (Quality of

Surface Water Intended for the Abstraction of Drinking Water) Regulations, 1989. Limit values for A1 waters are shown.

Note 3: European Communities (Quality of Salmonid Waters) Regulations, 1988 (S.I. No. 293 of 1988)

< Indicates less than the laboratory detection limit WQS = Water Quality Standard

* Converted Water Quality Standard for Nitrite, Nitrate and Ammonia as N (mg/l).

Page 98: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Intel (Ireland) Ltd. Report No. ECS3714

Bord na Móna Technical Services Page 5

September, 10

Respectively submitted,

_______________________ _________________________

Ms. Linda Lenihan Mr. Peter Coogan

Environmental Scientist Monitoring Team Leader

Page 99: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Appendix D

Louisa Spa Monitoring Report

Page 100: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

EXECUTIVE SUMMARY, LOUISA SPA 2010

FOR

INTEL IRELAND LTD, LEIXLIP, CO. KILDARE

RENAITH LYONS

Report Ref: 16955-1

TMS Environment Ltd

21st March 2011

Prepared by: Phoebe Conway

Environmental Consultant

Prepared by

Phoebe Conway

Approved by:

Craig O‟Connor

Senior Consultant

Date:

Approved by

Craig O‟Connor

Senior Consultant

Page 101: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Intel Ireland Ltd: Executive Summary, Louisa Spa 2010

TMS Environment Ltd Ref. 16955-1

1.0 Scope

This report presents the non-technical executive summary of analysis of a sample

collected from the Louisa Spa well at Louisa Bridge, which is east of the Intel

Campus buildings. Sampling was conducted to comply with the annual monitoring

requirements as specified in the sites IPPC Licence Reg. No. P0207-03. A full copy of

the report is available through TMS Environment Ltd or Intel Ireland Ltd. (Report

Reference: 16955).

2.0 Executive Summary

A sample of water was collected from the Louisa Spa Spring at Louisa Bridge, which

is east of the Intel Campus buildings on 16th

August 2010. Sampling was conducted to

comply with the annual monitoring requirements as specified in the sites IPPC

Licence Reg. No. P0207-03.

The water sample was analysed for the following parameters;

Conductivity (field measurement),

pH,

Temperature (field measurement),

Total Ammonia,

Chloride,

Sulphate,

Nitrate,

Nitrite,

Fluoride,

Calcium,

Magnesium,

Sodium,

Potassium,

Total Organic Carbon (TOC) and,

Trace Metals.

Temperature and Conductivity were measured in situ.

The results recorded were compared to the EPA Interim Guideline Values (IGVs) set

in the EPA interim report “Towards Setting Guideline Values for the Protection of

Groundwater in Ireland” and the Irish Drinking Water Limits (S.I. No. 278 of 2007).

The results were found to be within accepted norms with the exception of

Conductivity (1831 µS/cm), Chloride (468 mg/l), Sodium (240 mg/l) and Potassium

(10 mg/l), however these concentrations are similar to the results detected during

previous monitoring events as can be seen from Table 1 below.

Page 102: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Intel Ireland Ltd: Executive Summary, Louisa Spa 2010

TMS Environment Ltd Ref. 16955-1

It may be noted that the Drinking Water limit values are for comparison purposes, and

the spa water is not used as a drinking water source. There has been no significant

change in the monitored water quality to date.

It is unknown whether these elevated concentrations are related to natural background

levels in the groundwater or are due to pollution from up-gradient sources.

Page 103: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Intel Ireland Ltd: Executive Summary, Louisa Spa 2010

TMS Environment Ltd Ref. 16955-1

Table 1: Summary Table of Annual Results

Parameter Unit April 2003

April 2004

April 2005

Oct 2006

April 2007

July 2008

Aug 2009

Aug 2010

EPA Interim Guideline Value (IGV)

Drinking Water Limit (S.I. No. 278 of 2007)

pH - 7.36 7.28 7.41 7.01 7.3 8 8.03 7.85 ≥6.5 and ≤9.5 ≥6.5 and ≤9.5

Conductivity µS/cm @ 25 °C 1670 1746 1711 1634 987 1602 1856 1831 1000 µS/cm 2500 µS/cm

Temperature °C 15.8 16.5 17.2 17.1 15 22.8 18.5 16.7 - -

Total Organic Carbon mg/l C 8.4 - <0.5 1.4 2.8 2.8 3 0.8 No abnormal change No abnormal change

Nitrate mg/l NO3 <1 <5 <1 14 4.3 6.33 1.53 6.97 25 mg/l 50 mg/l

Nitrite mg/l N <0.005 <0.005 <0.005 0.005 <0.005 <0.005 <0.02 0.0231 0.1 mg/l 0.5 mg/l

Chloride mg/l 471 350 31 550 485 435 535 468 30 mg/l 250 mg/l

Sulphate mg/l SO42-

65 55 56 105 58 44 50.5 17.33 200 mg/l 250 mg/l

Fluoride mg/l F 0.49 0.08 0.44 0.19 0.43 0.50 0.39 0.465 1 mg/l 1.5 mg/l

Calcium mg/l 215 169 119 114 65 125 115 116 200 mg/l -

Magnesium mg/l 56 50 30 32 23 31 29 37 50 mg/l -

Sodium mg/l 180 282 222 21 90 210 229 240 150 mg/l 200 mg/l

Potassium mg/l 34.5 8.2 8.8 8 8.1 13 8.4 10 5 mg/l -

Total Ammonia mg/l N 0.5 <0.02 0.08 0.152 0.14 <0.01 0.012 0.011 0.12 mg/l 0.23 mg/l

Copper μg/l 2 <50 <10 - <10 <50 < 50 <50 30 μg/l 2000 μg/l

Tin μg/l <2 <50 <10 110 <10 <10 < 10 <10 - -

Chromium μg/l 3 <50 <10 <5 <5 <5 < 5 <5 30 μg/l 50 μg/l

Cobalt μg/l <0.1 <50 <10 <5 <10 <10 < 10 <10 - -

Lead μg/l <0.5 <50 <5 <10 <10 <10 <10 <10 10 μg/l 25 μg/l

Nickel μg/l <0.6 <50 <10 <10 <20 <20 < 20 <20 20 μg/l 20 μg/l

Iron μg/l 3 <50 370 450 320 <5 < 5 <5 - 200 μg/l

Manganese μg/l 48 <50 54 50 70 <5 < 5 <5 - 50 μg/l

Shaded cells indicate results exceeding the EPA IGV or Drinking Water Limit

< Denotes less than the laboratory detection limit

Page 104: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Appendix E

Bund Test Report

Page 105: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

IR1 Bunds

Page 106: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

2

Company: Intel Ireland Ltd Photo/sketch:

Figure 4.1 – 4.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 4

Bund Location: West side of IR1 compressor

room building

Bund Description: Chemical store

Bund Dimensions: Complex dimensions main

room is 6m x 4.2m. The depth grove in trench is 0.25m

Vessel(s) –

Materials of Construction: Various drums and plastic containers

Bund Materials of Construction: Masonry

blocks Vessel(s) –

Total Storage Volume: Approximately 1200L in bund (Total permissible storage up to maximum of 2000L with maximum container size not to exceed 458L)

Bund Lining Material: Chemical Resistant

Coating (CRC)

Vessel(s) –

110% of Volume of Largest Vessel: 20l

Bund Retention Volume: 504 l

Vessel(s) –

25% of Total Storage Volume: 300l

Tank Contents: Various cleaning fluids

including lime scale remover, hard surface cleaner, cream cleaner, restroom cleaner and floor polish.

R Phrase (WGK Class): Unknown, assume high risk

Contents: High Risk Condition: Good Action: Hydrostatically test (Where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: The bund is a room with grated trenches around the storage area. Bund appears to be generally intact – no visible cracks internally. The bund is clean and tidy (Fig. 4.1).

Bund Drainage System: Local bund - Trenches along floor of bund. This bund is located inside so is not exposed to rainfall.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 107: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

3

Bund ID: West side of IR1 compressor room building ( Chemical store )

Result of Hydrostatic Test: Fail

Date of hydrostatic Test: 25/01/11

Length of test: 18hrs

Measurement at beginning of test: 165mm

Measurement at end of test: 0 mm

Volume Tested to: 3 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Ciaran O Seery Title: Engineering Owner

Page 108: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

4

Company: Intel Ireland Ltd Photo/sketch:

Figure 1.1 – 1.3 Site: Leixlip, Co Kildare

Bund Ref. No.: 1

Bund Location: IR1 - South Of Diesel Storage

Tank

Bund Description: IR1 Fire Pumphouse Diesel

Bund

Bund Dimensions: Complex dimensions

Vessel(s) –

Materials of Construction: Tank plus 2 No. 200L drums

Bund Materials of Construction: Reinforced

concrete kerb

Vessel(s) –

Total Storage Volume: Aprox. 1300L

Bund Lining Material: CRC

Vessel(s) –

110% of Volume of Largest Vessel: 990L

Bund Retention Volume: 850L

Vessel(s) –

25% of Total Storage Volume: 325L

Tank Contents: Diesel

R Phrase (WGK Class): WGK2, R40

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09

Bund & Tank Integrity: The diesel fire pump is located within a reinforced concrete kerbed area within a room and is fully lined with CRC coating. The bund appears to be generally intact – no visible cracks or leaks internally.

Bund Drainage System: Local Bund - If a leak occurs it will be contained in the bund and pumped out manually. This bund is located inside so is not exposed to rainfall.

Result of Visual Inspection: Pass

Housekeeping Issues: There is fire hose and bucket in bund, these should be removed.

Action Required: Investigation should be carried out in relation to the bund capacity not meeting the

requirements of the 110% of the largest vessel in the bund

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 109: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

5

Bund ID: IR1 Fire Pumphouse Diesel bund

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 03/02/11

Length of test: 18hrs

Measurement at beginning of test: 200mm

Measurement at end of test: 200mm

Volume Tested to: 1m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Ciaran O Seery Title: Engineering Owner

Page 110: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

6

Company: Intel Ireland Ltd Photo/sketch:

Figure 2.1 – 2.3 Site: Leixlip, Co Kildare

Bund Ref. No.: 2

Bund Location: IR1 - Adjacent to Compressor

Room

Bund Description: Diesel Storage Tank

Bund Dimensions: 5m x 10m x 1.4mH

(0.3mH to inlet pipe in wall from oil loadiing area)

Vessel(s) –

Materials of Construction: Steel

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 25000L

Bund Lining Material: None Vessel(s) –

110% of Volume of Largest Vessel: 27500L

Bund Retention Volume: 72500L Vessel(s) –

25% of Total Storage Volume: 6250L

Tank Contents: Diesel

R Phrase (WGK Class): R40, WGK 2

Contents: High Risk Condition: Poor in areas Action: Remedial action plus hydrostatic testing

(where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally. However significant mossy growth coverage on base of bund and tree/bush growth into northern corner (Fig. 2.2) therefore could not fully inspect.

Bund Drainage System: Sump Level Detection/Alarm on bund. Local bund that is manually pumped to storm sewer.

General observations: Electrical cabling has fallen off the cable tray on the east bund wall of bund. One cable has fallen into the water in sump area (see Fig. 2.2). No labelling on diesel tank.

Result of Visual Inspection: Fail

Housekeeping Issues:

Bund needs to be cleaned as there is a lot of leaf overgrowth in the bund (Fig. 2.3).

Action Required:

Retained liquid should be tested and disposed of appropriately if not rainwater.

Electrical cabling should be removed if not in use or tidied and made safe.

Bund also needs to be cleaned as there is a lot of overgrowth in the bund and leaves

Tanks require labelling to ensure that the correct fill into the tank during refilling and also to ensure that appropriate handling procedures are undertaken in the event of a spill.

Hydrostatic testing (where possible).

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 111: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

7

Bund ID: IR1 Bulk Diesel Tank

Result of Hydrostatic Test: Fail

Date of hydrostatic Test:

15/2/11

Length of test: 24hrs

Measurement at beginning of test: 610mm

Measurement at end of test: 470mm

Volume Tested to: 27m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Eamon McIvor Title: Engineering Owner

Page 112: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

8

Company: Intel Ireland Ltd Photo/sketch:

Refer to figures 5.1 – 5.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 5

Bund Location: IR1 – Opposite Chemical Store

Bund Description: Transformers bunds

Bund Dimensions: 3.3m x 2.6m x 0.05mH

Vessel(s) –

Materials of Construction: Steel

Bund Materials of Construction: Concrete

with gravel floor

Vessel(s) –

Total Storage Volume: 490L (T1, T2, T3) and 771L (T4) =

2241L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 848L

Bund Retention Volume: 8630L

Vessel(s) –

25% of Total Storage Volume: 560L

Tank Contents: Transformer Oil

R Phrase (WGK Class):

WGK 2, R45

Contents: High Risk Condition: Poor in areas Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Impractical to hydrostatically test bund as filled with gravel and some wires located low down in the bund.

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09

Bund & Tank Integrity: Difficult to fully inspect as no access to rear of tank as in caged area (Fig 5.1). The bund is made up of reinforced concrete slab with reinforced concrete upstand all around. The area around bund dry. No evidence of leak. Containment area appears to be intact in all transformer bunds except T3; a 2mm wide crack is evident at back of bund (This crack is located above where spill would occur and therefore is not significant).

Bund Drainage System: Local bund – this bund is outside and is subject to rainfall.

General observations: Some debris at back of T1 needs to be removed.

Result of Visual Inspection: Pass

Housekeeping Issues: Debris at back of T1 needs to be removed (Fig 5.2).

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 113: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

6

Company: Intel Ireland Ltd Photo/sketch:

Fig 8.1 – 8.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 8

Bund Location: IR1

Bund Description: Petrol Interceptor Tank

Bund Dimensions: 3.2m x 4.4m x Height

unknown (filled with gravel)

Vessel(s) –

Materials of Construction: Plastic vessel

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents: Interceptor Oil R Phrase (WGK Class): R40, WGK 2

Contents: High Risk Condition: Poor in

areas

Action: N/A

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Bund is not currently operating as a bund as it is almost full of gravel and overflowing with water. A petrol interceptor generally does not need to be bunded. They should be checked regularly and kept clean. In this case if the interceptor is not checked regularly and is full then if should be treated as a bund.

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09

Bund & Tank Integrity: Retention in bund (rainwater) which has reduced retention capacity to zero. Full inspection of bund not possible as full of water and leaves (Fig. 8.1). There is pebbles/gravel in this bund (Fig. 8.2).

Bund Drainage System: The bund is full with water and needs to be manually pumped out.

General Observations: No labelling on tank or pipework.

Result of Visual Inspection: Fail

Housekeeping Issues: Ensure that this petrol interceptor is regularly maintained and cleaned or consider

removing the interceptor from this area.

Action Required: It was decided to remove from bund register following on from this assessment

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 114: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

7

Company: Intel Ireland Ltd Photo/sketch:

Figure 102.1 – 102.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 102

Bund Location: IR3 Warehouse

Bund Description: IR1 Sort Lift Station (BSG

Waste Water Tanks)

Bund Dimensions: 2.7m x 5.5m x 0.18mH

Vessel(s) –

Materials of Construction: Steel

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 3.99m3 x 2 No. tanks

Bund Lining Material:

CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 4.389m3

Bund Retention Volume: 4.515m3

Vessel(s) –

25% of Total Storage Volume: 1.995 m3

Tank Contents: AWN tanks includes Silca and

Inert Suspended Solids

R Phrase (WGK Class): Low Risk

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09

Bund & Tank Integrity: Area around bund dry. No evidence of leak or cracks (Fig. 102.1).

Bund Drainage System: Local bund - Sump Level Detection/Alarm on bund. Automatically pumped to lift tanks.

General observations: There is no grate over the drainage sump at the back of the bund. There is also some leaves and debris in this drain (Fig. 102.2).

Result of Visual Inspection: Pass

Housekeeping Issues: Debris in drainage sump should be removed. A grate should be fitted to protect the sump

from further debris getting in.

Action Required: None

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 115: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

8

Company: Intel Ireland Ltd Photo/sketch:

Figure 103.1-103.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 103

Bund Location: IR1 Boiler Room

Bund Description: MPHW/Chilled water (Tank

No. SN182787)

Bund Dimensions: 0.9m x 1.15m x 0.55mH

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 440L

Bund Lining Material: None – plastic bund Vessel(s) –

110% of Volume of Largest Vessel: 484L

Bund Retention Volume: 570l

Vessel(s) –

25% of Total Storage Volume: 110L

Tank Contents: NALCO 8539 (Scale &

corrosion inhibitor for closed cooling/heating)

Sodium Nitrite & Potassium Hydroxide

R Phrase (WGK Class): R35, R36/38, R50

WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09

Bund & Tank Integrity: Bund appears to be generally intact. (Fig. 103.1)

Bund Drainage System: Local Bund - In the event of a spill bund would be pumped out. This bund is located inside so is not exposed to rainfall.

General observations: Absorbent material in bund floor should be cleaned out (see Fig. 103.2).

Result of Visual Inspection: Pass

Housekeeping Issues:

A lot of materials around this bund on floor should be tidied and moved into correct areas.

Action Required:

Bund needs to be cleaned and bund may need to be moved into a CRC coating bund like the other bunds in this areas. This is to prevent chemical spills/splashes outside the plastic bund.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 116: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

9

Bund ID: Bund Ref. No.: 103

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 1/10/10

Length of test: 24 hrs

Measurement at beginning of test: 550mm

Measurement at end of test: 550mm

Volume Tested to: 0.430 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Simon McLain Title: Engineering Owner

Page 117: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

10

Company: Intel Ireland Ltd Photo/sketch:

Figure 104.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 104

Bund Location: IR1 Boiler Room

Bund Description: Nalco Microtreat 3150S

(SN112523)

Bund Dimensions: 0.8m x 1.1m x 0.4mH =

352m3

Vessel(s) –

Materials of Construction: Stainless Steel

Bund Materials of Construction: Stainless

Steel

Vessel(s) –

Total Storage Volume: 280L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 308L

Bund Retention Volume: 352L Vessel(s) –

25% of Total Storage Volume: 70L

Tank Contents:

Sodium Chlorite

R Phrase (WGK Class):

Risk Phrases: R8, R22, R24, R32, R34 WGK 2

Contents: High Risk Condition: Good Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally.

Bund Drainage System: Local Bund - In the event of a spill bund would be pumped out. This bund is located inside so is not exposed to rainfall.

Result of Visual Inspection: Pass

Housekeeping Issues:

None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 118: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

11

Company: Intel Ireland Ltd Photo/sketch:

Figure 105.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 105

Bund Location: IR1 Boiler Room

Bund Description: PCW/CHW Chemical

Dosing (Tank no. SN183762)

Bund Dimensions: 0.9m x 1.15m x 0.55mH

Vessel(s) –

Materials of Construction: Plastic vessel

Bund Materials of Construction: Plastic

(PVC)

Vessel(s) –

Total Storage Volume: 440L

Bund Lining Material: None – plastic bund Vessel(s) –

110% of Volume of Largest Vessel: 484L

Bund Retention Volume: 570l

Vessel(s) –

25% of Total Storage Volume: 110L

Tank Contents:

NALCO 2510 (Biocide for closed cooling)

R Phrase (WGK Class):

NALCO 2510 (R20/22, R38, R43, R41, WGK3) 2,2-Dibromo-3-Nitrilo-Propionamide

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally (Fig. 105.1).

Bund Drainage System: Local Bund - In the event of a spill bund would be pumped out. This bund is located inside so is not exposed to rainfall.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 119: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

12

Bund ID: Bund Ref. No.: 105

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 1/10/10

Length of test: 24 hrs

Measurement at beginning of test: 550mm

Measurement at end of test: 550mm

Volume Tested to: 0.430 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Simon McLain Title: Engineering Owner

Page 120: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

11

Company: Intel Ireland Ltd Photo/sketch:

Figure 106.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 106

Bund Location: IR1 Boiler Room

Bund Description: PCW/CHW Chemical

Dosing (Tank no. SN183575)

Bund Dimensions: 0.9m x 1.15m x 0.55mH

Vessel(s) –

Materials of Construction: Plastic vessel

Bund Materials of Construction: Plastic

(PVC)

Vessel(s) –

Total Storage Volume: 440L

Bund Lining Material: None – plastic bund Vessel(s) –

110% of Volume of Largest Vessel: 484L

Bund Retention Volume: 570l

Vessel(s) –

25% of Total Storage Volume: 110L

Tank Contents:

NALCO 2536 Plus (Scale & corrosion inhibitor for closed cooling/heating)

R Phrase (WGK Class):

NALCO 2536 plus: (R22, R52, WGK2) Sodium Nitrite

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally (Fig. 105.1).

Bund Drainage System: Local Bund - In the event of a spill bund would be pumped out. This bund is located inside so is not exposed to rainfall.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 121: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

12

Bund ID: Bund Ref. No.: 106

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 1/10/10

Length of test: 24 hrs

Measurement at beginning of test: 550mm

Measurement at end of test: 550mm

Volume Tested to: 0.430 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Simon McLain Title: Engineering Owner

Page 122: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

13

Company: Intel Ireland Ltd Photo/sketch:

Figure 6.1-6.4 Site: Leixlip, Co Kildare

Bund Ref. No.: 6

Bund Location: North side of IR1 Compressor

room

Bund Description: IR1 Cooling Tower bund

Bund Dimensions: 9m x 10m x 0.18mH

Vessel(s) –

Materials of Construction: Metal (Aluminium)

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume:

1.2m3

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents: Cooling Tower and pumps

R Phrase (WGK Class): Low Risk

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally. However significant mossy growth coverage on base of bund (Fig. 6.4).

Bund Drainage System: Local - In the event of a spill bund would be pumped out.

General Observations: Pipework to large tanks in poor condition – insulation falling off and pipework rusted (see Fig. 6.2).

Result of Visual Inspection: Pass

Housekeeping Issues: Cone, broken pipes covering and ladder need to be removed from bund (Fig 6.3).. The

broken pipework in the bund needs to be inspected and may need to be repaired or replaced.

Action Required:

Determine vessel volumes

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 123: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

14

Company: Intel Ireland Ltd Photo/sketch:

Figure 3.1 – 3.4

Site: Leixlip, Co Kildare

Bund Ref. No.: 3a

Bund Location: IR1 Compressor Room

Bund Description: Automation Chilled water

system - Nalco 8539 (Tank No. SN183834)

Bund Dimensions: 1.2 x 0.9 x 0.6m = 0.648m3 Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 440L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 484L

Bund Retention Volume: 648L

Vessel(s) –

25% of Total Storage Volume: 110L

Tank Contents: Sodium Nitrite & Potassium

Hydroxide

R Phrase (WGK Class): R35, R36/38, R50

WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears to be generally intact.

Bund Drainage System: Local - In the event of a spill bund would be pumped out. This bund is located inside so is not exposed to rainfall.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 124: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

15

Bund ID: Bund Ref. No.: 3a

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 1/10/10

Length of test: 24 hrs

Measurement at beginning of test: 550mm

Measurement at end of test: 550mm

Volume Tested to: 0.430 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Simon McLain Title: Engineering Owner

Page 125: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

14

Company: Intel Ireland Ltd Photo/sketch:

Figure 3.1 – 3.4

Site: Leixlip, Co Kildare

Bund Ref. No.: 3b

Bund Location: IR1 Compressor Room

Bund Description: Automation Chilled water

system - Nalco 2510 ( Tank No. SN183817)

Bund Dimensions: 0.9 x 1.2 x 0.55m =

0.594m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic bund

Vessel(s) –

Total Storage Volume: 440L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 484L

Bund Retention Volume: 594L

Vessel(s) –

25% of Total Storage Volume: 110L

Tank Contents: 2,2-Dibromo-3-

nitrilopropionamide

R Phrase (WGK Class): R20/22, R38, R43, R41

WGK3

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears to be generally intact.

Bund Drainage System: Local - In the event of a spill bund would be pumped out. This bund is located inside so is not exposed to rainfall.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Bund ID: Bund Ref. No.: 3b

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 1/10/10

Length of test: 24 hrs

Measurement at beginning of test: 550mm

Measurement at end of test: 550mm

Volume Tested to: 0.430 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Simon McLain Title: Engineering Owner

Page 126: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

15

Company: Intel Ireland Ltd Photo/sketch:

Figure 3.1 – 3.4

Site: Leixlip, Co Kildare

Bund Ref. No.: 3c

Bund Location: IR1 Compressor Room

Bund Description: CPCW dosing Nalco

2536+ ( Tank No. SN112254)

Bund Dimensions: 1.1 x 0.8 x 0.4m = 0.392m3 Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction: Metal

Vessel(s) –

Total Storage Volume: ~288L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 316.8L

Bund Retention Volume: 392L

Vessel(s) –

25% of Total Storage Volume: 72L

Tank Contents: Sodium Nitrite

R Phrase (WGK Class): R22, WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears to be generally intact.

Bund Drainage System: Local - In the event of a spill bund would be pumped out. This bund is located inside so is not exposed to rainfall.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Bund ID: Bund Ref. No.: 3c

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 1/10/10

Length of test: 24 hrs

Measurement at beginning of test: 260mm

Measurement at end of test: 260mm

Volume Tested to: 0.275 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Simon McLain Title: Engineering Owner

Page 127: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

16

Company: Intel Ireland Ltd Photo/sketch:

Figure 3.1 – 3.4

Site: Leixlip, Co Kildare

Bund Ref. No.: 3d

Bund Location: IR1 Compressor Room

Bund Description: CPCW dosing - Nalco

2510 ( Tank No. SN112071)

Bund Dimensions: 1.1 x 0.8 x 0.4m = 0.392m3 Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction: Metal bund

Vessel(s) –

Total Storage Volume: ~288L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 316.8L

Bund Retention Volume: 392L

Vessel(s) –

25% of Total Storage Volume: 72L

Tank Contents: 2,2-Dibromo-3-

nitrilopropionamide

R Phrase (WGK Class): R20/22, R38, R43, R41

WGK3

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears to be generally intact.

Bund Drainage System: Local - In the event of a spill bund would be pumped out. This bund is located inside so is not exposed to rainfall.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 128: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

17

Bund ID: Bund Ref. No.: 3d

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 1/10/10

Length of test: 24 hrs

Measurement at beginning of test: 260mm

Measurement at end of test: 260mm

Volume Tested to: 0.275 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Simon McLain Title: Engineering Owner

Page 129: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

18

Company: Intel Ireland Ltd Photo/sketch:

See Fig 9.1 –9.4 Site: Leixlip, Co Kildare

Bund Ref. No.: 9

Bund Location: IR1 Generator Bund

Bund Description: IR1 Emergency Generator

Bund

Bund Dimensions: 6.6m x 17m x 0.255mH

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 2m3

Bund Lining Material: N/A

Vessel(s) –

110% of Volume of Largest Vessel: 2.2m3

Bund Retention Volume: 28.6m3

Vessel(s) –

25% of Total Storage Volume: 0.5m3

Tank Contents: Diesel R Phrase (WGK Class): R40, WGK 2

Contents: High Risk Condition: Poor Action: Remedial action plus hydrostatic testing

(where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 9/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally. However significant mossy growth coverage on base of bund and tree/bush growth therefore could not fully inspect.

Bund Drainage System: Local Bund. Reinforced concrete with upstand all around. Bund is constructed in 2 levels, one adjacent to the other and takes runoff from the contractor oil storage bund 7. Sump area has significant liquid retention (most likely rainwater) (see Fig. 9.4) and drainage channel is filled with leaves and plant growth (see Fig. 9.4). Sump level detection/alarm on bund.

Result of Visual Inspection: Fail

Housekeeping Issues: Debris in bund needs to be removed.

Action Required:

Bund needs to be cleaned.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 130: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

19

Bund ID: IR1 Generator Bund Diesel Day Tanks

EG12/13

Result of Hydrostatic Test: Pass

Date of hydrostatic Test:

15/2/11

Length of test: 24hrs

Measurement at beginning of test: 130mm

Measurement at end of test: 130mm

Volume Tested to: 1.5 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Eamon McIvor Title: Engineering Owner

Page 131: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

20

Company: Intel Ireland Ltd Photo/sketch:

See Fig 7.1 –7.3 Site: Leixlip, Co Kildare

Bund Ref. No.: 7

Bund Location: IR1 Adjacent to cooling towers

Bund Description: Contractor Oil Storage Area

Bund Dimensions: 9m x 6.2m x 0.1mH

Vessel(s) –

Materials of Construction: Mixture of plastic and metal

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: N/A

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: 5.58m3

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents: Diesel/Synthetic

lubricant/Hydraulic Oil 32 (23l)/ Engine Oil/ Barrel Compactor

R Phrase (WGK Class):

R40, WGK2

Contents: High Risk Condition: Poor Action: Remedial action plus hydrostatic

testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Remote bund - Bund is free draining to petrol interceptor bund and therefore would be impractical to hydrostatic test bund.

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally. However significant mossy growth coverage on base of bund and lots of leaves (Fig. 7.1) therefore could not fully inspect.

Bund Drainage System: Remote Bund: There is a drainage channel in bund leading petrol interceptor bund. Sump area has significant liquid retention (most likely rainwater) (see Fig. 7.2) and drainage channel is filled with leaves/mud (see Fig. 7.3).

Result of Visual Inspection: Fail

Housekeeping Issues: Bund needs to be cleaned as there is a lot of moss and leaves in the bund.

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 132: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

21

Company: Intel Ireland Ltd Photo/sketch:

See Fig 148.1 – 148.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 148

Bund Location: IR1 Energy Centre North side

Door S.51

Bund Description: Cooling tower dosing –

Nalco ST49 (Tank No. SN182279)

Bund Dimensions: 0.9 x 1.2 x 0.6m = 0.648m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 440L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 484L

Bund Retention Volume: 648L

Vessel(s) –

25% of Total Storage Volume: 110L

Tank Contents: Sodium Hydroxide & Alkaline

liquid Bromine antimicrobial

R Phrase (WGK Class): R34, R31

WGK 2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Testing would involve taking the primary vessel offline which would impact fab operations

Result of Hydrostatic Test:

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues:

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 133: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

22

Company: Intel Ireland Ltd Photo/sketch:

See Fig 148.1 – 148.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 149

Bund Location: IR1 Energy Centre North side

Door S.51 ((Tank no. SN182874)

Bund Description: Cooling tower dosing –

Nalco 3DT249 (Tank no. SN182874)

Bund Dimensions: 0.9 x 1.2 x 0.6m = 0.648m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 440L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 484L

Bund Retention Volume: 648L

Vessel(s) –

25% of Total Storage Volume: 110L

Tank Contents: Methanol & Sodium

Formaldehyde Bisulphite

R Phrase (WGK Class): WGK 2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Testing would involve taking the primary vessel offline which would impact fab operations

Result of Hydrostatic Test:

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues:

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 134: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

23

Company: Intel Ireland Ltd Photo/sketch:

N/A Site: Leixlip, Co Kildare

Bund Ref. No.: 154

Bund Location: Contractors Compound –

Hegarty‟s

Bund Description: Chemstore 2DVDM

Bund Dimensions: Complex dimensions

Vessel(s) –

Materials of Construction: Various Plastic & Metal

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: ~83L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 25L

Bund Retention Volume: 235L

Vessel(s) –

25% of Total Storage Volume: 21L

Tank Contents: Wood Preserve, Petrol,

Lubricant, Energal HLP

R Phrase (WGK Class): R40, WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 16/9/09

Bund & Tank Integrity: Bund appears in good condition, this is a new bund and was hydrostatically tested before commissioning.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 135: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

24

Bund ID: Bund Ref. No.: 154

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 16/03/11

Length of test: 48 hrs

Measurement at beginning of test: 200mm

Measurement at end of test: 200mm

Volume Tested to: 0.24 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Owen O‟Sullivan Title: Engineering Owner

Page 136: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

25

Company: Intel Ireland Ltd Photo/sketch:

N/A Site: Leixlip, Co Kildare

Bund Ref. No.: 155

Bund Location: Contractors Compound –

Hegarty‟s

Bund Description: Metal Bund No. 2

Bund Dimensions: 2.6 x 1.5 x .5 m

Vessel(s) –

Materials of Construction: Various Plastic & Metal

Bund Materials of Construction: Metal

Vessel(s) –

Total Storage Volume: ~95.5L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 2.2L

Bund Retention Volume: 1950L

Vessel(s) –

25% of Total Storage Volume: 23.875L

Tank Contents: Easy Pour Gel, 91-0002

Activator, Loybond C76 Flooring Adhesive

R Phrase (WGK Class): Assume High Risk

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 16/9/09

Bund & Tank Integrity: Bund appears in good condition,

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Bund ID: Bund Ref. No.: 155

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 16/03/11

Length of test: 48 hrs

Measurement at beginning of test: 200mm

Measurement at end of test: 200mm

Volume Tested to: 0.44 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Owen O‟Sullivan Title: Engineering Owner

Page 137: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

26

Company: Intel Ireland Ltd Photo/sketch:

N/A Site: Leixlip, Co Kildare

Bund Ref. No.: 156

Bund Location: Contractors Compound – P.J.

Hegarty‟s

Bund Description: Metal Bund No. 1

Bund Dimensions: 2.6 x 1.5 x .5 m

Vessel(s) –

Materials of Construction: Various Plastic & Metal

Bund Materials of Construction: Metal

Vessel(s) –

Total Storage Volume: ~200L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 27.5L

Bund Retention Volume: 1950L

Vessel(s) –

25% of Total Storage Volume: 50L

Tank Contents:

F44 Acrylic Adhesive

F41 Tackefier

Penatron 3003 Part B

Penatron 3003 Part A

R Phrase (WGK Class): Assume High Risk

R20, R36/37/38, R42/43

R20, R36/37/38, R42/43

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 16/9/09

Bund & Tank Integrity: Bund appears in good condition,

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 138: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

27

Bund ID: Bund Ref. No.: 156

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 16/03/11

Length of test: 48 hrs

Measurement at beginning of test: 200mm

Measurement at end of test: 200mm

Volume Tested to: 0.44 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Owen O‟Sullivan Title: Engineering Owner

Page 139: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

28

Company: Intel Ireland Ltd Photo/sketch:

N/A Site: Leixlip, Co Kildare

Bund Ref. No.: 157

Bund Location: Contractors Compound –

Mercury

Bund Description: MM12 Chemical Stores

Bund Dimensions: 2.7 x 0.05 x .1.85 m

Vessel(s) –

Materials of Construction: Various Plastic & Metal

Bund Materials of Construction: Metal

Container

Vessel(s) –

Total Storage Volume: ~170L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 6.25L

Bund Retention Volume: 249.75L

Vessel(s) –

25% of Total Storage Volume: 43L

Tank Contents: Old mostly unused chemicals

i.e.

IPS Weld-on P70 clear

Stevens Roofing System: Stevens EP cut edge sealant clean 208638

Tetrahydrofuran

Stevens Roofing System: Stevens EP Seam Cleaner

Xylene

Ethylbenzene

Benzene

PVA Adhesive & Sealer

Mixture of: cis-1,4-Dimethylcyclohexyl dibenzoate and trans-1,4-Dimethylcyclohexyl dibenzoate

Poly Vinyl Alcohol

Tellus Oil

Mobile Synthetic Lubricant

R Phrase (WGK Class): High Risk

R11, R19, R36, R66, R67, WGK1

R11, R19, R36/37, WGK1

R10, R20/21, R38 WGK2

R11, R20, WGK1

R45, R46, R11, R36/38, R48, R23/24/25, R65, WGK3

R53,

R11, R23/25

R40, WGK2

R40, WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 16/9/09

Bund & Tank Integrity: Bund appears in good condition,

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: Quite a lot of the chemicals stored within this container haven‟t been used in some

years. If deemed unnecessary these chemicals should be disposed of appropriately.

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 140: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

29

Bund ID: Bund Ref. No.: 157

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 7/3/11

Length of test: 24 hrs

Measurement at beginning of test: 20mm

Measurement at end of test: 20mm

Volume Tested to: 0.1 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Mick Maher Title: Engineering Owner

Page 141: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

30

Fab 10 Bunds

Page 142: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

31

Company: Intel Ireland Ltd Photo/sketch:

Figure 18.1 - 18.5 Site: Leixlip, Co Kildare

Bund Ref. No.: 18

Bund Location: F10 UPW (In RODI lab fab 10

building and down the stairs)

Bund Description: UPW

Bund Dimensions: Complex Dimensions

Vessel(s) – Materials of Construction: Room with

drainage to Acid Waste Neutralisation (AWN) treatment system and contains individual smaller bunds that are free-draining to AWN via either the room trenches or pipes.

Bund Materials of Construction:

Concrete/Plastic

Vessel(s) –

Total Storage Volume: 6.6m3

Bund Lining Material: Epoxy Paint

Vessel(s) –

110% of Volume of Largest Vessel: 1.62m3

Bund Retention Volume: 104.7m3

Vessel(s) –

25% of Total Storage Volume: 1.65m3

Tank Contents:

Sodium Hypochlorite 14.5% (T-51R-6-1), Sodium Bisulphite,

Sodium Hydroxide,

Organic Scavenger Units,

Hydrochloric Acid

R Phrase (WGK Class):

WGK 2

R22, R31 WGK 1WGK 1, R35

N/A

WGK 1, R34, R37

Contents: High Risk Condition: Poor in areas Action: Remedial Action

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Bund is free-draining to AWN tanks, therefore cannot hydrostatically test bunded area.

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09

Bund & Tank Integrity: Bund appears to be in relatively good condition. There appears to be rusting on the supports of pipework around the room (Fig. 18.3). Sealant also is coming up on bund floor (Fig. 18.4).

Bund Drainage System: Room with trenches in the floor around the tank areas which are free-flowing to Acid Waste Neutralisation (AWN) wastewater treatment system. General observations: Scaffolding in area is temporary while works take place.

Result of Visual Inspection: N/A

Housekeeping Issues: Puddle under the stairs needs to be mopped. General housekeeping in area should be

maintained as boxes and various pieces of equipment lying around on floor (Fig 18.5).

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 143: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

32

Company: Intel Ireland Ltd Photo/sketch:

Figure 17.1 - 17.4 Site: Leixlip, Co Kildare

Bund Ref. No.: 17

Bund Location: F10 Middle yard (south of

F10 UPW)

Bund Description: UPW External Bund

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: Ultrapure water tanks - 2 in No.

97m3, 2 in No.147m

3, and Reverse Osmosis water tank – 1 in

No. 60m3. Total = 548m

3

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 161.7m3

Bund Retention Volume: 35m3

Vessel(s) –

25% of Total Storage Volume: 137m3

Tank Contents:

Di-water Storage tanks

R Phrase (WGK Class): No risk phases assigned

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09

Bund & Tank Integrity: Bund appears to be in relatively good condition. Significant liquid retention in bund from rainwater (Figure 17.2). Slight rusting at join of legs in bund (Figure 17.4).

Bund Drainage System: Local bund - In the event of a spill bund is pumped out. This bund is located outside so is exposed to rainfall. The bund requires regular monitoring to ensure it is kept free of rainwater. This will ensure the retention volume of the bund is not reduced. There is a sump within the bunded area.

Result of Visual Inspection: Pass

Housekeeping Issues: General housekeeping in area should be maintained as timber/metal/drum/plastic and

various pieces of equipment lying around on floor. Mud and leaves should be cleaned out (Figure 17.2). The bund requires regular monitoring to ensure it is kept free of rainwater. Rusting should be monitored.

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 144: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

33

Company: Intel Ireland Ltd Photo/sketch:

Figure 10.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 10

Bund Location: F10 Chemical Warehouse

Bund Description: Flammables

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Various, plastic and metal

container and boxes

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 8m3

Bund Lining Material: CRC coating

Vessel(s) –

110% of Volume of Largest Vessel: 1.1m3

Bund Retention Volume:

16.2m3

Vessel(s) –

25% of Total Storage Volume: 2m3

Tank Contents: Flammables R Phrase (WGK Class): WGK 3

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons: Due to safety issues with chemical

compatibility and also due to issues with emptying the bunds once filled with water as there are no sumps associated with these bunds..

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09

Bund & Tank Integrity: Bund appears to be in relatively good condition. Bund is room with CRC coating and CRC coving at walls and floor junction. Trenches across all vehicles door and step over through the pedestrian doors.

Bund Drainage System: Local bund – Trenches in middle of floor which are pumped out.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: Monitor general wear and tear on the bund floor.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 145: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

34

Company: Intel Ireland Ltd Photo/sketch:

Figures 11.1 to 11.4 Site: Leixlip, Co Kildare

Bund Ref. No.: 11

Bund Location: F10 Chemical Warehouse

Bund Description: Room

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Various, plastic and metal

container and boxes

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 50m3

Bund Lining Material: CRC coating

Vessel(s) –

110% of Volume of Largest Vessel: 1.1m3

Bund Retention Volume:

21m3

Vessel(s) –

25% of Total Storage Volume: 12.5m3

Tank Contents:

Area contains various chemicals including corrosives, oxidisers and hazardous waste

R Phrase (WGK Class): WGK 3, WGK 1, R34

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons: Due to safety issues with chemical

compatibility and also due to issues with emptying the bunds once filled with water as there are no sumps associated with these bunds..

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09

Bund & Tank Integrity: Bund appears to be in relatively good condition. Bund is room with CRC coating and CRC coving at walls and floor junction. Trenches across all vehicles door and step over through the pedestrian doors.

Bund Drainage System: Local bund – Trenches in middle of floor which are pumped out.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: Monitor general wear and tear on the bund floor.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 146: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

35

Company: Intel Ireland Ltd Photo/sketch:

Figure 15.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 15

Bund Location: F10 Chemical Warehouse

Bund Description: Door wells

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Various, plastic and metal

container and boxes

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 50m3 (as per Bund Ref No. 11)

Bund Lining Material: CRC coating

Vessel(s) –

110% of Volume of Largest Vessel: 1.1m3 (as per Bund Ref

No. 11)

Bund Retention Volume:

8m3

Vessel(s) –

25% of Total Storage Volume: 12.5m3 (as per Bund Ref No.

11)

Tank Contents: Door wells area contains

various chemicals

R Phrase (WGK Class): WGK 3

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons: Due to safety issues with

chemical compatibility and also due to issues with emptying the bunds once filled with water as there are no sumps associated with these bunds..

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09

Bund & Tank Integrity: Bund appears to be in relatively good condition. Bund is room with CRC coating and CRC coving at walls and floor junction. Trenches across all vehicles door and step over through the pedestrian doors.

Bund Drainage System: Local bund – Trenches in middle of floor which are pumped out. These are not required to meet bund capacity requirements.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: Monitor general wear and tear on the bund floor.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 147: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

36

1 This is the combined retention volume of the HFW treatment plant and reaction room.

Company: Intel Ireland Ltd Photo/sketch:

Fig. 19.1-19.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 19

Bund Location: F10 AWN PIT

Bund Description: HF Treatment Plant

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Cross lined HDPE

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 15m3 (4No. tanks), Total 60m

3

(Included HF reaction room) giving total of 65m3

Bund Lining Material: CRC coating

Vessel(s) –

110% of Volume of Largest Vessel: 16.5m3

Bund Retention Volume:

17.8m31

Vessel(s) –

25% of Total Storage Volume: 16.25m3

Tank Contents:

Sludge Tank 1 (T-57H-10-1)

Filtrate Tank 1 (T-57H-13-1)

Sludge Tank 2 (T-57H-19-1)

Filtrate Tank 2 (T-57H-25-1)

R Phrase (WGK Class): Calcium Flouride & Calcium

Phosphate

Contents: Assume High Risk Condition: Poor Action: Remedial action plus hydrostatic

testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Re-Testing is not required at this time. Current valid testing sheets exist for this bund post project to complete remedial works.

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09

Bund & Tank Integrity: Maintenance works still in progress therefore unable to do full bund inspection.

Drainage System: Local bund - Sump level detection/alarm which manually pumped to sludge tanks. The bund is located in a room that is lined with CRC and coving to walls, trenches located around the room and are approx. 1m to 1.5m from the wall.

Result of Visual Inspection: Pass (Changed from previous fail- AR‟s closed)

Housekeeping Issues: None

Action Required: Existing test certificate Valid. Retesting planned for 2011

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 148: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

37

2 This is the combined retention volume of the HFW treatment plant and reaction room.

Company: Intel Ireland Ltd Photo/sketch:

See Fig 20.1 – 20.5 Site: Leixlip, Co. Kildare

Bund Ref. No.: 20

Bund Location: F10 AWN PIT (Go through

the HF Treatment Plant room Bund 19)

Bund Description: HF Reaction Room

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: FRP pvdf lined

Bund Materials of Construction:

Concrete

Vessel(s) –

Total Storage Volume: HF Rxn tanks x 2m3, H2SO4 x 1m

3 =

5m3 include 4 No. tanks from treatment plant (15m

3 each) =

65m3

Bund Lining Material:

CRC

Vessel(s) –

110% of Volume of Largest Vessel: 16.5m3

Bund Retention Volume:

17.8m3 2

Vessel(s) –

25% of Total Storage Volume: 16.25m3

Tank Contents:

Reaction Tank 1

Reaction Tank 2

Sulphuric Acid Tank

R Phrase (WGK Class): Very Toxic and Corrosive Chemicals

R23 R24 R25 R35 R36 R37 R38 R49

WGK 1

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Re-Testing is not required at this time. Current valid testing sheets exist for this bund post project to complete remedial works.

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Bund appears in good condition – recently resurfaced with CRC. Generally clean but dusty with no visible leaks or cracks.

The bund was previously noted for having a number of areas to be repaired, all cracks and damaged areas have been repaired.

Drainage System: Remote bund: The bund is located in a room that is lined with CRC and coving to walls. Sump level detection/alarm which is manually pumped to the reaction tanks in the event of a leak/spill.

Result of Visual Inspection: Pass

Housekeeping Issues: As bund repair work recently took place there are a few bits of pipe near the drain

outlet area, these should be removed. The bund should be cleaned regularly to reduce dust. This will help maintain the CRC.

This bund should be monitored for spillages.

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 149: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

38

Company: Intel Ireland Ltd Photo/sketch:

See Fig 98.1 – 98.3 Site: Leixlip, Co. Kildare

Bund Ref. No.: 98

Bund Location: Adjacent to F10 AWN apron

(Beside Bund 20)

Bund Description: F10 Generator/diesel

storage bund (EG2)

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction:

Concrete

Vessel(s) –

Total Storage Volume: 0.9m3

Bund Lining Material:

CRC

Vessel(s) –

110% of Volume of Largest Vessel: 0.99m3

Bund Retention Volume:

Unknown

Vessel(s) –

25% of Total Storage Volume: 0.225m3

Tank Contents: Diesel R Phrase (WGK Class): Risk Phrases: R40, WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing required (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Tank (see Fig. 98.1) is in good condition – no visible cracks or leaks. Bund full with water (Fig 98.2).

Drainage System: Local bund - In the event of a spill bund is pumped out. This bund is located outside so is exposed to rainfall. The bund requires regular monitoring to ensure it is kept free of rainwater. This will ensure the retention volume of the bund is not reduced.

Result of Visual Inspection: Pass

Housekeeping Issues: A grate missing from over sump and build-up of debris and rubbish (Fig 98.3).

Clean out bunded area under grate and around the tank.

The bund requires regular monitoring to ensure it is kept free of rainwater.

Action Required: Determine bund retention volume

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 150: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

39

Bund ID: F10 EG2 Diesel Bund

Result of Hydrostatic Test: Pass

Date of hydrostatic Test:

16/2/11

Length of test: 24hrs

Measurement at beginning of test: 110mm

Measurement at end of test: 110mm

Volume Tested to: 3.5m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Eamon McIvor Title: Engineering Owner

Page 151: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

40

Company: Intel Ireland Ltd Photo/sketch:

See Fig 22.1 – 22.3 Site: Leixlip, Co Kildare

Bund Ref. No.: 22

Bund Location: F10 AWN PIT

Bund Description: Bulk Solvent

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction:

Concrete

Vessel(s) –

Total Storage Volume: 41.6m3

General Solvent (Solvent Waste) (T-58A-1-1): 19m3

Ethyl Lactate (T-58A-1-1) : 11.3m3

NMP (T-58A-1-1):11.3m3

Storage on AWN apron: 2 x 27m3 tankers

Bund Lining Material:

CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 29.7m3

Bund Retention Volume:

33m3

Vessel(s) –

25% of Total Storage Volume: 23.9m3

Tank Contents: (3 Tanks)

General Solvent (Solvent Waste) (T-58A-1-1)

Ethyl Lactate (T-58A-1-1)

N-Methyl-2 pyrrolidone(T-58A-1-1)

R Phrase (WGK Class): Assume high risk

Contents: High Risk Condition: Poor in areas Action: Remedial action plus hydrostatic testing

(where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: Pass (See addendum below for details)

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Bund is made up of slab on grade with 2No. high separation walls and 2No. tall upstand walls. Bund appears in good condition with no visible defects. Rainwater in bund (Fig. 22.3). The sump grate needs to be cleaned - mud and debris build-up. Some rusting of pipes in this area. No evidence of leaks or cracks.

Bund Drainage System: Combined bund - Sump level detection/alarm and capability to manually pumps to solvent tanks or AWN

General Observations: Floor appears discoloured. There is evidence of maintenance work going on as scaffolding and ladders in bund.

Result of Visual Inspection: Pass

Housekeeping Issues: Debris in base of bund. This should be removed (Fig. 22.2).

Action Required:

Rusting should be monitored.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 152: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

41

Bund ID: 22

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 3/3/10

Length of test: 24hrs

Measurement at beginning of test: 140mm

Measurement at end of test: 140mm

Volume Tested to: 21m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Alan Campbell Title: IWS Engineer

Page 153: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

42

Company: Intel Ireland Ltd Photo/sketch:

See Fig 23.1 – 23.4 Site: Leixlip, Co Kildare

Bund Ref. No.: 23

Bund Location: F10 AWN PIT

Bund Description: AWN Tanks

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 27m3 each and total storage volume

of 81m3

Bund Lining Material: CRC Coating Vessel(s) –

110% of Volume of Largest Vessel: 29.7m3

Bund Retention Volume:

207m3

Vessel(s) –

25% of Total Storage Volume: 20.25m3

Tank Contents:

Tank 1(T-56A-1-1)

Tank 2(T-56A-1-2)

Tank 3(T-56A-1-3)

R Phrase (WGK Class):

High risk as other bunds pumped to AWN and this bund also acts as storm water bund.

Contents: High Risk Condition: Poor in areas Action: Remedial action plus hydrostatic testing

(where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons: Hydrostatically test up to 30m3 at

least as this is bund which acts as storm water hold and is link to other free drain bunds.

Result of Hydrostatic Test: Pass (See addendum below for details)

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Bund (Deep pit) appears in reasonable condition. No evidence of leaks or cracks. Some evidence of rainwater (bund is used as overflow for storm water drain).

Bund Drainage System: Combined Bund: Sump in south west corner with level detection/alarm and manually pumped to AWN tanks

Equipment in Bund: No electrical equipment below bund level. All associated piping is contained within bund.

General Observations: There is a lot of debris on the floor of the bund i.e. ladder, scaffolding, piping, absorbent material, broken pipework (Fig 23.2 – 23.3). There is evidence of rushing of pipework (Fig 23.4). Retention volume is more than adequate even ff bund used as overflow for storm water.

Result of Visual Inspection: Pass

Housekeeping Issues: Remove materials/debris from bund. Rusting should be monitored.

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 154: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

43

Bund ID: 23

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 4/3/10

Length of test: 24hrs

Measurement at beginning of test: 137mm

Measurement at end of test: 137mm

Volume Tested to: 40m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Alan Campbell Title: IWS Engineer

Page 155: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

44

Company: Intel Ireland Ltd Photo/sketch:

See Fig 21.1 – 21.3 Site: Leixlip, Co Kildare

Bund Ref. No.: 21

Bund Location: F10 AWN PIT

Bund Description: Hydrofluoric Acid

Wastewater (Bulk)

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Metal vessels

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 3 x Hydrofluoric acid waste and Phosphoric acid waste tanks (27m

3 each) plus one

phosphoric acid tank (18.7 m3) and total storage volume of

99.7m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 29.7m3

Bund Retention Volume:

35m3

Vessel(s) –

25% of Total Storage Volume: 24.95m3

Tank Contents: Hydrofluoric acid / Phosphoric

Acid

R Phrase (WGK Class): WGK 2

R26/27/28 and R34

Contents: High Risk Condition: Poor in

areas

Action: Remedial action plus hydrostatic testing

(where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: Pass (See addendum below for details)

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Bund (Pit with upstand and floor) appears to be generally intact – no visible cracks or leaks internally. However significant debris on base of bund including scaffolding and some water retention from recent rainfall also present (Fig. 21.2). The shower has some water around it (automatically turns on when temperatures get to freezing) (Fig. 21.3).

Bund Drainage System: Local bund - Sump level detection/alarm and manually pumped to collection tanks or AWN.

General observations: The bund is quite dirty and needs to be cleaned out.

Result of Visual Inspection: Pass

Housekeeping Issues: Remove materials/debris from bund.

Action Required: Bund needs to be cleaned out. (Done)

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 156: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

45

Bund ID: 21

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 2/3/10

Length of test: 24hrs

Measurement at beginning of test: 162mm

Measurement at end of test: 162mm

Volume Tested to: 53m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Alan Campbell Title: IWS Engineer

Page 157: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

46

Company: Intel Ireland Ltd Photo/sketch:

See Fig 25.1 – 25.4 Site: Leixlip, Co Kildare

Bund Ref. No.: 25 / 26

Bund Location: F10 AWN PIT

Bund Description: Hydrochloric and Sulphuric

Acid Tanks

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Metal vessels

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 23.9m3 each and total storage

volume of 47.8m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 26.29m3

Bund Retention Volume:

43m3

Vessel(s) –

25% of Total Storage Volume: 11.95m3

Tank Contents:

Hydrochloric Acid (HCI) Tank (T-53A-1-1)

R Phrase (WGK Class):

R34, R37 WGK 1

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Bund (Pit with upstand and floor) appears to be generally intact – no visible cracks or leaks internally. Bund in good condition – no visible cracks or leaks. Some retention of rainwater (Figure 25.3).

Bund Drainage System: Local bund - Sump level detection/alarm and manually pumped to AWN tank.

Result of Visual Inspection: Pass (See addendum below for details)

Housekeeping Issues: The bund is quite dirty and needs to be cleaned out (Figure 25.2) Done

Action Required: None

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 158: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

47

Company: Intel Ireland Ltd Photo/sketch:

See Fig 24.1 – 24.5 Site: Leixlip, Co Kildare

Bund Ref. No.: 24

Bund Location: F10 AWN PIT

Bund Description: NaOH Tanks (5%, 25% and

47%)

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Carbon steel

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 30m3, 30m

3 and 0.9m

3 and total

storage volume of 60.9m3

Bund Lining Material: CRC Coating Vessel(s) –

110% of Volume of Largest Vessel: 33m3

Bund Retention Volume:

66.1m3

Vessel(s) –

25% of Total Storage Volume: 15.23m3

Tank Contents:

Sodium Hydroxide (NaOH) (25%) (T-53A-1-2)

NaOH (47%), NaOH 5%

R Phrase (WGK Class):

R35, WGK 1

Contents: Low Risk Condition: Poor in areas Action: Remedial action plus re-inspection

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Bund (Pit with upstand and floor) appears to be generally intact – no visible cracks or leaks internally. Some retention of rainwater.

Bund Drainage System: Local bund - Sump level detection/alarm and manually pumped to AWN tank.

General observations: Some debris over sump grate needs to be removed. The cladding over some pumps in the bund appears to be broken and removed and the pumps appear rusted (Figure 24.2, 24.3).

All containers should be correctly labelled the bund register states NaOH (25%) is T-53A-2-2 but from photo it is T-53A-1-2. Bund register should be updated accordingly (Fig. 24.1).

Result of Visual Inspection: Pass

Housekeeping Issues: Some debris over sump grate needs to be removed (Fig. 24.5). Some discolouration in

one of the pipes (Fig. 24.3) needs to be investigated

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 159: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

48

Company: Intel Ireland Ltd Photo/sketch:

See Fig 27.1 – 27.3 Site: Leixlip, Co Kildare

Bund Ref. No.: 27

Bund Location: F10 AWN PIT

Bund Description: Regen Waste/NaCI Tank/

HCL Scrubber

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: FRP double thick veil

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume:

Regen Waste 37m3

NaCl 25m3

Tanker storage on AWN apron: 2 x 22.5m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 40.7m3

Bund Retention Volume:

65.6m3

Vessel(s) –

25% of Total Storage Volume: 36m3

Tank Contents:

Regen Waste

NaCI Tanks

HCL Scrubber

R Phrase (WGK Class):

R34, R37

WGK 1, R 36/38

Contents: Tanks empty but

contents will be low risk

Condition: Poor in areas Action: Remedial action prior to commissioning

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: This bund has not been in use for about 1.5yrs but re-commissioning of the bund is due to start in Q2, 2009. Rainwater in bund. There are very old pumps in the bund which are extremely rusted and the red pipelines are extremely rusted and may need to be replaced prior to bund being re-commissioned.

Discolouration on floor of bund. Labelling of the tank has fallen off at one side, this need to be replaced.

Bund Drainage System: Sump level detection/alarm and manually pumped to AWN or tanks.

Result of Visual Inspection: Fail

Housekeeping Issues: The bund would require cleaning and re-inspection before re-use.

Action Required:

All tanks should be correctly labelled.

There are very old pumps in the bund which are extremely rusted and the red pipelines extremely rusted and may need to be replaced prior to bund being re-commissioned.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 160: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

49

Bund ID: F10 AWN PIT ref. 27

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 03/11/10

Length of test: hrs 9

Measurement at beginning of test: mm 146

Measurement at end of test: mm 146

Volume Tested to: m3 11.502

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Thomas Brennan Title: Engineering Owner

Page 161: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

50

Company: Intel Ireland Ltd Photo/sketch:

N/A Site: Leixlip, Co Kildare

Bund Ref. No.: 158

Bund Location: F10 AWN PIT

Bund Description: Phosphoric Acid

Wastewater Tank

Bund Dimensions: N/A – Bund No 21 applies

here

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: See Bund No. 21 Data Sheet

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: N/A

Bund Retention Volume:

Bund No 21 applies here

Vessel(s) –

25% of Total Storage Volume: N/A

Tank Contents: Phosphoric Acid Wastewater

R Phrase (WGK Class): R36/38 WGK1

Contents: Low Risk Condition: Good Contents: Low Risk

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 16/9/09

Bund & Tank Integrity: Bund (Deep pit) appears in reasonable condition.

Bund Drainage System: Free draining into neighbouring HFW Tank Collection bund (Bund 21).

Equipment in Bund: No electrical equipment below bund level.

General Observations: This tank is used only in emergency situations and hasn‟t been used in a number of years. The tank appears generally intact but the bund was not accessible on the day and a visual inspection from the top of the AWN Pit was only carried out.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: None

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 162: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

51

Company: Intel Ireland Ltd Photo/sketch:

See Fig 90.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 90

Bund Location: F10 Subfab

Bund Description: HPM Aqueous Room

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Various vessels (plastic+ metal)

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume:

10m3

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents: Corrosive chemicals including:

Ammonia Hydroxide

Sulphuric Acid

R Phrase (WGK Class): Corrosive/Toxic

R34, R50, WGK 2

R35, WGK 1

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Room with CRC coating on floor and coving to walls. The bund appears in good condition – no visible cracks or leaks and ground around is dry. Some discolouration to floor from movement of containers.

Bund Drainage System: Local bund - Room where any spills drain to trenches along middle of floor.

General Observation: All containers should be correctly labelled.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Bund was not hydrostatically tested as it will be out of commission in by the end of Q2 2011

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 163: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

52

Company: Intel Ireland Ltd Photo/sketch:

See Fig 91.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 91

Bund Location: F10 Subfab

Bund Description: HPM Solvent Room

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Various vessels and drums

(plastic+ metal)

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume:

5m3

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents: Flammable chemicals R Phrase (WGK Class):

Corrosive/Toxic

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Room with CRC coating on floor and coving to walls. The bund appears in good condition – no visible cracks or leaks and ground around is dry. Some discolouration to floor from movement of containers.

Bund Drainage System: Local bund - Room where any spills drain to trenches along middle of floor.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Bund was not hydrostatically tested as it will be out of commission in by the end of Q2 2011

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 164: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

53

Company: Intel Ireland Ltd Photo/sketch:

See Fig 28.1 – 28.4 Site: Leixlip, Co Kildare

Bund Ref. No.: 28

Bund Location: Between F10 middle yard and

F14 Energy Centre

Bund Description: F10 Emergency

Generator/Diesel Storage Bund (EG3, 4 and 6 ).

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Various vessels and drums

(plastic and metal)

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 40m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 44m3

Bund Retention Volume: 140.58m3

Vessel(s) –

25% of Total Storage Volume: 10m3

Tank Contents: 3 diesel storage tanks and 3

Emergency generators diesel day tanks

R Phrase (WGK Class):

R45, WGK 2

Contents: High Risk Condition: Poor in

areas

Action: Remedial action plus hydrostatic testing

(where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Tank (see Fig. 28.1) is in good condition – no visible cracks or leaks and ground around tank dry.

Bund Drainage System: Local bund that drains through grate into bund, appear to have some liquid retention and moss growth, this needs to be clean as may interfere with bund retention volume (Fig. 28.2). Sump level detection/alarm.

There is a water pipe releasing water at back of bund directly to ground and slopes to sump, maybe practical to extend this pipe line to drain (Figure 28.4).

General Observation: All containers should be correctly labelled.

Result of Visual Inspection: Pass

Housekeeping Issues: Debris and moss in drainage channel.

Action Required:

Clean out bunded area under grate and around the generators vessels.

All containers should be correctly labelled.

Hydrostatic testing required.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 165: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

54

Bund ID: F10 Bund Storage for EG3,4 & 6

Result of Hydrostatic Test: Fail

Date of hydrostatic Test:

16/2/11

Length of test: 24hrs

Measurement at beginning of test: 300mm

Measurement at end of test: 150mm

Volume Tested to: 45m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Eamon McIvor Title: Engineering Owner

Page 166: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

55

Company: Intel Ireland Ltd Photo/sketch:

See Fig 16.1 –16.4 Site: Leixlip, Co Kildare

Bund Ref. No.: 16

Bund Location: F10 Middle Yard

Bund Description: Hazardous Waste

Compound

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Metal Drums

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: N/A

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: 17.2m3

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents: Dry hazardous waste, double-

bagged and drummed

R Phrase (WGK Class): Low risk due to packaging.

Contents: Low Risk Condition: Poor in

areas

Action: Remedial action plus re-inspection

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: Free draining.Waste in this area is solid, double bagged and in drums therefore not necessary to hydrostatically test.

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Area appears to be generally intact. There is some subsidence of the concrete in the middle of the floor beside the grate (Fig 16.4), hairline cracking, should be investigate further. There is no sealant or CRC on this floor as the hazardous materials contained here are dry. Some rainwater in the floor (Fig. 16.2).

Bund Drainage System: Area with grated trenches around the storage areas. Drains through F10 upper yard contained storm system tank to the site retention pond. Integrity tests are carried out every 3 years on the F10 upper yard tank.

Result of Visual Inspection: Fail

Housekeeping Issues: Some debris outside bund needs to be removed (Fig. 16.3).

Action Required: It was determined to remove from this bund following on from this assessment

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 167: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

56

Company: Intel Ireland Ltd Photo/sketch:

See Fig 89.1 –89.5 Site: Leixlip, Co Kildare

Bund Ref. No.: 89

Bund Location: F10 Scrubber Deck

Bund Description: F10 Roof: Large Room on

scrubber deck

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: N/A

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: 109m3

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents: 8 acid scrubbers (No. 7

decommissioned) + 1 gaspad scrubber

R Phrase (WGK Class): Harmful & Corrosive

WGK 1, R35

Contents: High Risk Condition: Poor in

areas

Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons: Remote drainiage from room; free

draining to AWN

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09

Bund & Tank Integrity: This area on located on the top floor of F10 (see site layout plan) on the scrubber level (Fig. 89.1). The F10 scrubber deck should not be on the bund register, instead the smaller individual bund within the room should be on the register.i.e.

Bund permaclean ® PC-33 and NALCO ® 2584,

55S Dosing bund containing NALCO 2536 plus and

Sodium Hydroxide, 47%.

Bund Drainage System: Remote drainage from room – free draining to AWN

General Observation: There is a lot of evidence of spills in this area are absorbent materials (Fig. 89.4), the procedures for cleaning up these and general maintenance of the floor needs to improve.

Result of Visual Inspection: N/A

Housekeeping Issues: Debris/rubbish should be removed.

Action Required: Refer to bund numbers 109, 110, 111 and 112 for details on individual bunds in room

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 168: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

57

Company: Intel Ireland Ltd Photo/sketch:

See Fig 150.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 150

Bund Location: F10 Fire Pump House

Bund Description: F10 Firewater Pump with

Diesel tank

Bund Dimensions: Large room -

1..35m x 1m x 1m = 1.35m3

(1350L)

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction:

Metal Bund

Vessel(s) –

Total Storage Volume: 900L

Bund Lining Material: CRC coating

Vessel(s) –

110% of Volume of Largest Vessel: 990L

Bund Retention Volume: 1350L

Vessel(s) –

25% of Total Storage Volume: 225L

Tank Contents: Diesel

R Phrase (WGK Class): R40, R65, R66, R51, R53

WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Bund ID: F10 Fire Pump house

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 25/01/11

Length of test: 18hrs

Measurement at beginning of test: 254mm

Measurement at end of test: 254mm

Volume Tested to: 1 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Ciaran O Seery Title: Engineering Owner

Page 169: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

58

Company: Intel Ireland Ltd Photo/sketch:

See Fig 107.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 107

Bund Location: F10 Subfab: 15F Pump room

(opposite IH lab - door to Engineering labs, 1st on right)

Bund Description: Nalco 2536+

Bund Dimensions: 1.2 x 0.8 x 0.4m = 0.384m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 260L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 286L

Bund Retention Volume: 384L

Vessel(s) –

25% of Total Storage Volume: 65L

Tank Contents: Sodium Nitrite

R Phrase (WGK Class): R22, R52, WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where

possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 170: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

59

Bund ID: Bund Ref. No.: 107

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 2/12/10

Length of test: 24 hrs

Measurement at beginning of test: 550mm

Measurement at end of test: 550mm

Volume Tested to: 0.430 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Simon McLain Title: Engineering Owner

Page 171: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

60

Company: Intel Ireland Ltd Photo/sketch:

N/A Site: Leixlip, Co Kildare

Bund Ref. No.: 160

Bund Location: F10 Subfab: opposite F10 15F

Pump room (Room 3136)

Bund Description: F10 PCD - Planar Chemical

Distribution

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: N/A

Vessel(s) –

Total Storage Volume: 5024L

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 1100L

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: 1256L

Tank Contents: Semi Sparse W2000 – Silca

Slurry ( Silica, Amorphous, Crystalline

Free)

Potassium Hydroxide 10%

R Phrase (WGK Class):

Not classed under the EU legislation but assume low risk as silca is relatively inert

WGK 1, R22, R35

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 16/9/09

Bund & Tank Integrity: Bund appears in good condition. Totes containing planar slurries located in this room.

Bund Drainage: Local Bund: If leak occurs the bund is manually pumped out to AWN

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: Determine bund retention volume

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 172: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

61

Company: Intel Ireland Ltd Photo/sketch:

See Fig 108.1 – 108.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 108

Bund Location: F10 Subfab: F10 PVAC

(adjacent to F10 aqueous room)

Bund Description: PVAC dosing skid - Nalco

8539

Bund Dimensions: 1.05 x 0.75 x 0.4m =

0.315m3

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction: Metal

Vessel(s) –

Total Storage Volume: 270L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 297L

Bund Retention Volume: 315L

Vessel(s) –

25% of Total Storage Volume: 67.5L

Tank Contents: Sodium Nitrite & Potassium

Hydroxide

R Phrase (WGK Class): R25, R36/38, R50

WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where

possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Testing would involve taking the primary vessel offline which would impact fab operations

Result of Hydrostatic Test:

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: Local bund - If a leak occurs the bund is manually pumped out.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 173: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

62

Company: Intel Ireland Ltd Photo/sketch:

See Fig 109.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 109

Bund Location: F10 Scrubber Deck: SICWS

tank

Bund Description: 55S Dosing Skid with Nalco

2536+

Bund Dimensions: 1.05 x 0.8 x 0.4m =

0.336m3

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction: Metal

Vessel(s) –

Total Storage Volume: 297L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 326.7L

Bund Retention Volume: 336L

Vessel(s) –

25% of Total Storage Volume: 74.25L

Tank Contents: Sodium Nitrite, Sodium

Tetraborate, Sodium Metasilicate

R Phrase (WGK Class): R22, WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where

possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: Local bund - If a leak occurs the bund is manually pumped out.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 174: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

63

Bund ID: Bund Ref. No.: 109

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 2/12/10

Length of test: 24 hrs

Measurement at beginning of test: 260mm

Measurement at end of test: 260mm

Volume Tested to: 0.275 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Simon McLain Title: Engineering Owner

Page 175: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

64

Company: Intel Ireland Ltd Photo/sketch:

See Fig 110.1 – 110.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 110

Bund Location: F10 Scrubber Deck

Bund Description: Sodium Hydroxide (47%)

Bund Dimensions: 1 x 1 x 0.27m = 0.27m3 Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction: Metal

Vessel(s) –

Total Storage Volume: 300L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 330L

Bund Retention Volume: 270L

Vessel(s) –

25% of Total Storage Volume: 75L

Tank Contents: Sodium Hydroxide

R Phrase (WGK Class): R35, WGK1

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition. The capacity of the tank excesses the bund capacity.

Bund Drainage: Local bund - If a leak occurs the bund is manually pumped out.

Result of Visual Inspection: Pass

Housekeeping Issues: The bund needs to be cleaned.

Action Required: Check the capacity of vessel compared to bund as the bund retention volume is less than the

total storage capacity of the vessel.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 176: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

65

Company: Intel Ireland Ltd Photo/sketch:

See Fig 111.1 – 111.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 111

Bund Location: F10 Scrubber Deck

Bund Description: Nalco 2584

Bund Dimensions: 1 x 1.2 x 0.4m = 0.48m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 300L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 330L

Bund Retention Volume: 480L

Vessel(s) –

25% of Total Storage Volume: 75L

Tank Contents: Sodium Hydroxide &

Potassium Hydroxide

R Phrase (WGK Class): R35

WGK1

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: Local bund - If a leak occurs the bund is manually pumped out.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: None

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 177: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

66

Company: Intel Ireland Ltd Photo/sketch:

See Fig 111.1 – 111.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 112

Bund Location: F10 Scrubber Deck

Bund Description: PC-33

Bund Dimensions: 1 x 1.2 x 0.4m = 0.48m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 300L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 330L

Bund Retention Volume: 480L

Vessel(s) –

25% of Total Storage Volume: 75L

Tank Contents: Permaclean PC-33,

Tetrasodium EDTA, Sodium Hydroxide

R Phrase (WGK Class): R36/38, WGK1

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: Local bund - If a leak occurs the bund is manually pumped out.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: None

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 178: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

67

Company: Intel Ireland Ltd Photo/sketch:

See Fig 129.1 – 129.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 129

Bund Location: F10 Energy Centre

(Compressor/chiller room)

Bund Description: Cooling Tower Dosing -

Nalco 3DT187

Bund Dimensions: 1.2 x 0.9 x 0.55m =

0.594m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 440L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 484L

Bund Retention Volume: 594L

Vessel(s) –

25% of Total Storage Volume: 110L

Tank Contents: Phosphoric Acid

R Phrase (WGK Class): R36/38 WGK1

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: Local bund - If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 179: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

68

Company: Intel Ireland Ltd Photo/sketch:

See Fig 130.1 - 130.2 Site: Leixlip, Co Kildare

Bund Location: F10 Energy Centre

(Compressor/chiller room)

Bund Description: Cooling Tower Dosing -

Nalco 93033

Bund Dimensions: 1.4 x 1 x 0.7m = 0.98m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 750L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 825L

Bund Retention Volume: 980L

Vessel(s) –

25% of Total Storage Volume: 187.5L

Tank Contents: Sodium Hypochlorite

R Phrase (WGK Class): R31, R34, WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Testing would involve taking the primary vessel offline which would impact fab operations

Result of Hydrostatic Test:

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in general good condition. There is evidence of a leak and absorbent material in the bund floor.

Bund Drainage: Local bund - If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 180: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

69

Company: Intel Ireland Ltd Photo/sketch:

See Fig 131.1 - 131.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 131

Bund Location: F10 Energy Centre

(Compressor/chiller room)

Bund Description: MTHW / Chilled / Glycol

water - Nalco 8539 (F10 Colling Tower Dosing Skid)

Bund Dimensions: 0.75 x 1.1 x 0.4m = 0.33m3 Vessel(s) –

Materials of Construction: Lined Stainless Steel

Bund Materials of Construction: Metal –

Stainless Steel

Vessel(s) –

Total Storage Volume: 270L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 297L

Bund Retention Volume: 330L

Vessel(s) –

25% of Total Storage Volume: 67.5L

Tank Contents: Sodium Nitrite & Potassium

Hydroxide

R Phrase (WGK Class): R25, R36/38, R50

WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Testing would involve taking the primary vessel offline which would impact fab operations

Result of Hydrostatic Test:

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: Local bund - If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 181: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

70

Company: Intel Ireland Ltd Photo/sketch:

See Fig 132.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 132

Bund Location: F10 Nitrogen Plant

Bund Description: Battery Acid

Bund Dimensions: 0.75 x 0.7 x 0.5m Approx. Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: ~100L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 110L

Bund Retention Volume: 226.5L

Vessel(s) –

25% of Total Storage Volume: 25L

Tank Contents: Battery Acid

R Phrase (WGK Class): R34, WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: Local bund - If leak occurs the bund is manually pumped out and cleaned.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Bund ID: Bund Ref. No.: 132

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 08/03/2011

Length of test: 8 hrs

Measurement at beginning of test: 490 mm

Measurement at end of test: 490 mm

Volume Tested to: 0.22 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Brian McCabe Title: Operational Owner

Page 182: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

71

Company: Intel Ireland Ltd Photo/sketch:

See Fig 133.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 133

Bund Location: F10 Nitrogen Plant

Bund Description: Biomate 5702

Bund Dimensions: 0.75 x 0.7 x 0.5m Approx. Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: ~100L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 110L

Bund Retention Volume: 226.5L

Vessel(s) –

25% of Total Storage Volume: 25L

Tank Contents: Biomate 5702: Sodium

carbonate Sodium hypochlorite

R Phrase (WGK Class): R31/34,R35,R36 WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: Local bund - If leak occurs the bund is manually pumped out and cleaned.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Bund ID: Bund Ref. No.: 133

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 08/03/2011

Length of test: 8 hrs

Measurement at beginning of test: 500 mm

Measurement at end of test: 500 mm

Volume Tested to: 0.22 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Brian McCabe Title: Operational Owner

Page 183: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

72

Company: Intel Ireland Ltd Photo/sketch:

See Fig 134.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 134

Bund Location: F10 Nitrogen Plant

Bund Description: Continium AEZ3153 &

Inhibitor AEZ104

Bund Dimensions: 0.75 x 0.7 x 0.5m Approx. Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: ~100L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 110L

Bund Retention Volume: 226.5L

Vessel(s) –

25% of Total Storage Volume: 25L

Tank Contents: Continium AEZ3153 & Inhibitor

AEZ104

R Phrase (WGK Class): Harmful

Contents: Assume High Risk Condition: Good Action: Hydrostatic testing (where

possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: Local bund - If leak occurs the bund is manually pumped out and cleaned.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 184: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

73

Bund ID: Bund Ref. No.: 134

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 08/03/2011

Length of test: 8 hrs

Measurement at beginning of test: 500 mm

Measurement at end of test: 500 mm

Volume Tested to: 0.22 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Brian McCabe Title: Operational Owner

Page 185: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

74

Company: Intel Ireland Ltd Photo/sketch:

See Fig 135.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 135

Bund Location: F10 Nitrogen Plant

Bund Description: Oil Bund

Bund Dimensions: Irregular shape / slopes Vessel(s) –

Materials of Construction: Various drums and plastic

containers

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 20L drum x 2 and 200L drum – total

240L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 220L

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: 60L

Tank Contents: Mobile DTE Light oil

R Phrase (WGK Class): Harmful

Contents: Assume High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: Local bund - If leak occurs the bund is manually pumped out and cleaned.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: Determine bund retention volume and check the capacity of vessel compared to bund.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 186: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

75

Company: Intel Ireland Ltd Photo/sketch:

See Fig 136.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 136

Bund Location: F10 Nitrogen Plant

Bund Description: Transformer Bund

Bund Dimensions: 3.3 x 4.5 x 0.4m = 5.94m3 Vessel(s) –

Materials of Construction: Metal Transformers on gravel

bund

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 429L & 1100L =1529L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 1210L

Bund Retention Volume: 5940L

Vessel(s) –

25% of Total Storage Volume: 382.25L

Tank Contents: Electrical insulating oil

R Phrase (WGK Class): WGK 1

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 187: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

76

Fab 14 Bunds

Page 188: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

77

Company: Intel Ireland Ltd Photo/sketch:

No photos available Site: Leixlip, Co Kildare

Bund Ref. No.: 43

Bund Location: F14 - Tank Farm east of PSB

Bund Description: Concentrated Lead Waste

(C4 System 2 Collection Tanks)

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Large Metal Vessels

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 2 x 18m3 = 36m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 19.8m3

Bund Retention Volume:

33.91m3

Vessel(s) –

25% of Total Storage Volume: 9m3

Tank Contents: Lead Waste R Phrase (WGK Class): R36, R33 Corrosive and Toxic

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Bund no longer exists. All Lead waste plant has been removed from service and de-installed

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Slab on grade and upstand to the east with high separation walls to other sides. Very small amount of liquid retention in base of bund but the bund is mainly dry. No visible cracks or leaks in bund and general in good condition.

Bund Drainage System: Sump level detection on bund and the sump arrangement is as follows, manual pump to tanks with AWN drain. Normal operation during rain is to pump back to collection tanks.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 189: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

78

Company: Intel Ireland Ltd Photo/sketch:

See Fig 44.1 –44.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 44

Bund Location: F14 - Tank Farm east of PSB

Bund Description: HF/H3PO4 Tanks (4 in

No.)

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Large Metal Vessels,

Polypropylene lined FRP

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 4 x 30m3 = 120m

3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 33m3

Bund Retention Volume:

150.66 m3

Vessel(s) –

25% of Total Storage Volume: 30m3

Tank Contents:

Hydrofluoric Acid Waste and Phosphoric Acid

R Phrase (WGK Class):

WGK 2, R26/27/28 and R34

WGK 1, R34

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Bund no longer exists. All HF waste plant has been removed from service and de-installed

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Very small amount of liquid retention in base of bund but the bund is mainly dry. No visible cracks or leaks in bund and general in good condition. The sump has some debris/leaves coving it (Fig. 44.2).

Bund Drainage System: Sump level detection on bund and the sump arrangement is as follows, manual pump to tanks with AWN drain.

Result of Visual Inspection: Pass

Housekeeping Issues: The bund should be cleaned out.

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 190: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

79

Company: Intel Ireland Ltd Photo/sketch:

See Fig 45.1 –45.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 45

Bund Location: F14 - Tank Farm east of PSB

Bund Description: C4 Waste Collection Tanks

(DLW, 2 in No.) C4 System 3

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: FRB

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 18m3 x 2 = 36m

3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 19.8m3

Bund Retention Volume:

52.33m3

Vessel(s) –

25% of Total Storage Volume: 9m3

Tank Contents: Dilute lead waste

R Phrase (WGK Class): R36, R33 Corrosive and Toxic

Contents: Assume High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Bund no longer exists. All waste plant has been removed from service and de-installed

Result of Hydrostatic Test:

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Very small amount of liquid retention in base of bund, most likely rainfall (see Fig. 45.1) but bund mainly dry. No visible cracks or leaks in bund. There is quite a bit of discolouration in this bund (Fig 45.2).

Bund Drainage System: Sump level detection on bund and the sump arrangement is as follows, manual pump to tanks with AWN drain.

Result of Visual Inspection: Pass

Housekeeping Issues: Bund should be monitored for further deterioration in discolouration.

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 191: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

80

Company: Intel Ireland Ltd Photo/sketch:

See Fig 46.1 –46.3 Site: Leixlip, Co Kildare

Bund Ref. No.: 46

Bund Location: F14 - Tank Farm east of PSB

Bund Description: Bulk Sulphuric Acid

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Large Metal Vessels, FRP pvdf

lined

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 26m3 x 2 = 52m

3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 28.6m3

Bund Retention Volume:

58.11m3

Vessel(s) –

25% of Total Storage Volume: 13m3

Tank Contents: Sulphuric acid (96%) R Phrase (WGK Class): R35 , WGK 1

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Very small amount of liquid retention in base of bund, most likely rainfall (see Fig.46.1) but bund mainly dry. No visible cracks or leaks in bund and general in good condition. There appears to be some rusting to the piping supports (Fig. 46.2).

Bund Drainage System: No sump level detection on bund and the sump arrangement is as follows, manual pump to tanks with AWN drain.

Result of Visual Inspection: Pass

Housekeeping Issues: Debris in base of bund (Fig. 46.3). This should be removed.

Action Required:

The rusting should be monitored.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 192: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

81

Company: Intel Ireland Ltd Photo/sketch:

See Fig 47.1 –47.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 47

Bund Location: F14 - Tank Farm east of PSB

Bund Description: General Solvent Tank

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Large Metal Vessels

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 36m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 39.6m3

Bund Retention Volume:

97.37m3

Vessel(s) –

25% of Total Storage Volume: 9m3

Tank Contents: Ethylene Glycol Solvent R Phrase (WGK Class): R10, R36, R37/R38

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Bund no longer exists. All waste plant has been removed from service and de-installed

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Very small amount of liquid retention in base of bund, most likely rainfall (see Fig. 47.2) but bund mainly dry. No visible cracks or leaks in bund and general in good condition.

Bund Drainage System: Sump level detection on bund and the sump arrangement is as follows, manual pump to tanks with AWN drain.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 193: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

82

Company: Intel Ireland Ltd Photo/sketch:

See Fig 29.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 29

Bund Location: F14 UPW

Bund Description: F14 UPW General Floor

area (Basement O)

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Self contained vessels

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents:

RO cleaning chemical bund:

Sodium Hypochlorite,

Hypersperse

Sodium bisulphite

R Phrase (WGK Class):

R31, R34, WGK 1

N/A,

R22, R31 WGK 1

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: No visible cracks or leaks in bund and general in good condition.

Bund Drainage System: Remote bund which drains to the F14 AWN pit - Bunded room with trenches along the floor. The room contains four smaller bunds within F14 UPW – these are assessed individually within this report (Bund 64 and 99).

General Observation: Room generally clean and tidy.

Result of Visual Inspection: Pass

Housekeeping Issues: Monitor UPW for leaks and discolouration.

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 194: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

83

Company: Intel Ireland Ltd Photo/sketch:

See Fig 99.1 – 99.5 Site: Leixlip, Co Kildare

Bund Ref. No.: 99

Bund Location: F14UPW

Bund Description: Sodium bromide

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Plastic Self contained vessels

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents: Sodium bromide R Phrase (WGK Class): WGK 1

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: No visible cracks or leaks in bund and general in good condition (Fig. 99.1). Full visual assessment of this bund was limited due to position of the bund.

Bund Drainage System: In the event of a spill bund would be pumped out. This bund is located inside so is not exposed to rainfall.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: None

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 195: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

84

Company: Intel Ireland Ltd Photo/sketch:

See Fig 33.1 – 33.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 33

Bund Location: F14 west of PSB

Bund Description: HCl Tank

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Vinylester FRP

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 42m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 46.2m3

Bund Retention Volume: 62.57m3 Vessel(s) –

25% of Total Storage Volume: 10.5m3

Tank Contents: Hydrochloric Acid R Phrase (WGK Class): R34, R37

WGK 1

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: No visible cracks or leaks in bund and general in good condition.

Bund Drainage System: Sump level detection on bund and manually pumped to AWN. (See Fig. 33.2).

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: None

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 196: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

85

Company: Intel Ireland Ltd Photo/sketch:

See Fig 34.1 – 34.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 34

Bund Location: F14 west of PSB

Bund Description: NaOH Tank

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Stainless Steel

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 45m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 49.5m3

Bund Retention Volume:

66.09m3

Vessel(s) –

25% of Total Storage Volume: 11.25m3

Tank Contents: Sodium Hydroxide R Phrase (WGK Class): WGK 1

R36, R38

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: No visible cracks or leaks in bund and general in good condition. There is some mossy growth on the base of the bund especially over the sump outlet grate.

Bund Drainage System: Sump level detection on bund and manually drained to AWN. (See Fig. 34.2)

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Mossy growth in bund should be cleaned out. (Done)

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 197: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

86

Company: Intel Ireland Ltd Photo/sketch:

See Fig 32.1 – 32.4 Site: Leixlip, Co Kildare

Bund Ref. No.: 32

Bund Location: F14 west of PSB

Bund Description: Regeneration waste Tank

Bund Dimensions: 9m x 9m x 1.2mH

Vessel(s) –

Materials of Construction: Vinylester FRP

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 61m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 67.1m3

Bund Retention Volume:

93.51m3

Vessel(s) –

25% of Total Storage Volume: 15.25m3

Tank Contents: Regeneration waste R Phrase (WGK Class): R34, R37

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Bund no longer exists. All Lead waste plant has been removed from service and de-installed

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally. However significant mossy growth and a lot of leave coverage on base of bund and tree/bush growth in eastern corner. There is also some tree growth up through the drainage grates along the bund (Fig. 32.1 – 32.4).

Bund Drainage System: No sump level detection on bund and manually drained to AWN. The drain is closed therefore some build up of water (Fig 32.1).

General observations: The pipe leading through the UPW bund appearing in bad condition and is covered in plastic and timber (Fig. 32.2). This should be looked into further.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Mossy growth and shrub growth from grate in bund should be cleaned out.

Pipework should be repaired.Bund wall to be formed against blockwork to required height.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 198: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

87

Company: Intel Ireland Ltd Photo/sketch:

See Fig 31.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 31

Bund Location: F14 west of PSB

Bund Description: UPW External Bund

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents:

2 No. UPW (Ultrapure water tanks)

2 No. ROW (Reverse Osmosis Water tanks)

2 No. IW (Industrial Water tanks)

Vacuum Degasifer (DG-243-1-130)

R Phrase (WGK Class): Low Risk – water

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally. However mossy growth and a lot of leave coverage on base of bund.

Bund Drainage System: Local bund - Bottom outlet valve on bund. The bund also slopes.

Result of Visual Inspection: Pass

Housekeeping Issues: Labelling of all tanks should be clear.

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 199: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

88

Company: Intel Ireland Ltd Photo/sketch:

See Fig 38.1 – 38.4 Site: Leixlip, Co Kildare

Bund Ref. No.: 38

Bund Location: F14 AWN PIT

Bund Description: AWN Tanks & URW Tank

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Vinylester FRP, Metal vessels

(cream in colour)

Bund Materials of Construction: N/A

Vessel(s) –

Total Storage Volume: 60 x 4 = 240m3

Bund Lining Material: CRC Coating Vessel(s) –

110% of Volume of Largest Vessel: 67.1m3

Bund Retention Volume:

254.20m3

Vessel(s) –

25% of Total Storage Volume: 60m3

Tank Contents:

Acid Wastewater

Ultrapure recycled water

R Phrase (WGK Class): Assume high risk as other high risk

areas drain to AWN – These areas no longer drain to AWN as F14 waste treatments systems have been decommissioned

Contents: High Risk Condition: Poor in areas Action: Remedial action plus

hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Bunded area within Pit. Bund appears to be generally intact – no visible cracks or leaks internally. However there is discolouration on the bund floor and AWN tank TK-261-1-120 is corroded on the outside (Fig. 38.1). Rainwater retention is visible in the bund, the bund seems to slope and most has gathered in the back corner of the bund (Fig. 38.2). This will affect the retention volume of the bund and should be pumped out periodically. There is a sump in this corner and because full with water could not be fully inspected. There is some discolouration in the bund due to water build-up (Figure 38.3).

Bund Drainage System: Local bund - Sump level detection on bund and manually drained to AWN. The drainage sump is closed and so build up of water is evident. This bund can take spillages from the contained storm system and there are drains from other areas.

Result of Visual Inspection: Fail

Housekeeping Issues: Maintenance works evident in this area and scaffolding and PPE in bund, if works

complete this should be removed including associated equipment (Fig. 38.4).

Action Required:

Bunds require regular emptying to ensure required storage capacity for spills/leaks

Bund to be tested upon completion of construction works.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 200: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

89

Company: Intel Ireland Ltd Photo/sketch:

See Fig 41.1 – 41.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 41

Bund Location: F14 AWN PIT

Bund Description: HF Waste lift Tank

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Polyproylene lined FRP

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 2m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 2.2m3

Bund Retention Volume:

17.41m3

Vessel(s) –

25% of Total Storage Volume: N/A

Tank Contents: Hydroflouric Acid waste R Phrase (WGK Class): R23/24/25

Contents: High Risk Condition: Poor in

areas

Action: Remedial action plus hydrostatic testing

(where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Bund no longer exists. All waste plant has been removed from service and de-installed

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Bunded area within Pit. Bund appears to be generally intact – no visible cracks or leaks internally. However the floor of the bund is in very poor condition i.e. green discolouration (Figure 41.2).

Bund Drainage System: Local bund - Sump level detection on bund and the sump arrangement is as follows, manual pump to lift tanks or AWN.

General observations: The grate over the sump has a lot of debris and plastic in it, evidence if bund been full of rainwater. The floor of the bund is quite dirty and muddy.

Result of Visual Inspection: Pass

Housekeeping Issues: Debris in bund. This should be removed.

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 201: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

90

Company: Intel Ireland Ltd Photo/sketch:

See Fig 40.1 – 40.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 40

Bund Location: F14 AWN PIT

Bund Description: H3PO4 lift tank

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Polyproylene lined FRP

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 2m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 2.2m3

Bund Retention Volume: 17.4m3

Vessel(s) –

25% of Total Storage Volume: N/A

Tank Contents: Phosphoric Acid R Phrase (WGK Class): R34, WGK 1

Contents: Low Risk Condition: Poor in areas Action: Remedial action plus re-inspection

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Bund no longer exists. All Waste plant has been removed from service and de-installed

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Bunded area within Pit. Bund appears to be generally intact – no visible cracks or leaks internally. However the floor of the bund is in very poor condition i.e. green discolouration (Figure 40.1).

Bund Drainage System: Local bund - Sump level detection on bund and with manual pump to lift tanks or AWN.

General observations: Slight rusting at join of legs in bund that holds piping and ladder.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Monitoring for leaks in interstitial space should be carried out regularly.

Rusting at join of legs to tank should be monitored.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 202: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

91

Company: Intel Ireland Ltd Photo/sketch:

See Fig 42.1 – 42.5 Site: Leixlip, Co Kildare

Bund Ref. No.: 42

Bund Location: F14 AWN PIT

Bund Description: Sulfuric Acid lift tank

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume:

17.41m3

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents: Sulfuric Acid R Phrase (WGK Class): R26, WGK 1

Contents: High Risk Condition: Poor in areas Action: Remedial action plus hydrostatic testing

(where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Bund no longer exists. All Waste plant has been removed from service and de-installed

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Bunded area within Pit. Bund appears to be generally intact – no visible cracks or leaks internally. However the floor of the bund is in very poor condition i.e. green discolouration (Fig 42.2).

Bund Drainage System: Sump level detection on bund and with manual pump to lift tanks or AWN.

General observations: Slight rusting at join of legs in bund that holds piping and ladder (Fig 42.4).

Result of Visual Inspection: Pass

Housekeeping Issues: Debris in bund. This should be removed.

Action Required:

Monitoring for leaks in interstitial space should be carried out regularly.

Rusting at join of legs to tank should be monitored.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 203: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

92

Company: Intel Ireland Ltd Photo/sketch:

See Fig 39.1 – 39.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 39

Bund Location: F14 AWN PIT

Bund Description: KD 100 Lift Tank

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: FRP

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 4m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 4.4m3

Bund Retention Volume: 15.34m3

Vessel(s) –

25% of Total Storage Volume: 1m3

Tank Contents: KD100 Waste R Phrase (WGK Class): R36, R38

Contents: Low Risk Condition: Poor Action: Remedial action plus re-inspection

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Bund no longer exists. All Waste plant has been removed from service and de-installed

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Bunded area within Pit. Bund appears to be generally intact – no visible cracks or leaks internally. However the floor of the bund is in very poor condition i.e. green discolouration (Figure 39.1).

Bund Drainage System: Sump level detection on bund and with manual pump to lift tanks or AWN.

General observations: The grate over the sump has a lot of debris and plastic in it, evidence if bund been full of rainwater. The floor of the bund is quite dirty and muddy (Figure 39.2).

Result of Visual Inspection: Pass

Housekeeping Issues: Debris in bund. This should be removed.

Action Required:

The bund needs to be cleaned and further inspection and monitoring of the discolouration in the bund is also required.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 204: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

93

Company: Intel Ireland Ltd Photo/sketch:

See Fig 36.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 36

Bund Location: HFW/Phos Waste

Bund Description: F14 HFW Treatment Plant

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Mixture drums and plastic

vessels

Bund Materials of Construction: Concrete/self

contained bunds

Vessel(s) –

Total Storage Volume: 15m3 x 2 = 30m

3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 16.5m3

Bund Retention Volume:

23.53m3

Vessel(s) –

25% of Total Storage Volume: 7.5m3

Tank Contents:

Sludge Tank

Filtrate Tank

R Phrase (WGK Class):

Calcium Fluoride

Calcium Phosphate

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Bund no longer exists. All Waste plant has been removed from service and de-installed

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Room with CRC floor and coving to walls, trenches around room 1m to 1.5m from wall. Bund & drums appear in good condition. No evidence of leaks or cracks.

Bund Drainage System: Drain in middle of floor area, all drums on there own bunds and in good condition. Sump level detection on bund and with manual pump to sludge or reaction tanks

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 205: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

94

Company: Intel Ireland Ltd Photo/sketch:

See Fig 35.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 35

Bund Location: F14 HFW Treatment Plant

Bund Description: HF Reaction Room

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: FRP pvdf lined

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: (2 tanks in room) 2.2m3

and 1m3 =

3.2m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 2.42m3

Bund Retention Volume:

13.8m3

Vessel(s) –

25% of Total Storage Volume: 0.8m3

Tank Contents: Reaction Tank & Floc Tanks

HFW & Phos. Waste

R Phrase (WGK Class): WGK 2

R23/24/25 and R34

Very Toxic and Corrosive

Contents: High Risk Condition: Poor in areas Action: Remedial action plus hydrostatic testing

(where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Bund no longer exists. All Waste plant has been removed from service and de-installed

Result of Hydrostatic Test:

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Bund appears in good condition. No evidence of leaks or cracks. The room is lined with CRC coating on floor and coving to walls.

Bund Drainage System: Drain in middle of floor area. Sump level detection on bund and with manual pump to sludge or reaction tanks.

General Observations: Poor labelling of HF waste tank. The grate from the sump has been removed. There is some water in the sump drain and this should be disposed of. The room is very dusty and there a spill/leak from old rusty pumps near one of the exit doors. The pump/pipework may need to be replaced.

Result of Visual Inspection: Pass

Housekeeping Issues: The bund should be cleaned regularly to reduce dust. This will help maintain the CRC.

This bund should be monitored for spillages.

Action Required:

Unlabelled vessels should be clearly identified. The pumps/piping should be investigated for leaks and replaced if necessary.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 206: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

95

Company: Intel Ireland Ltd Photo/sketch:

See Fig 37a.1 – 37a.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 37a

Bund Location: CDS (KD 100)

Bund Description: KD 100 waste collection

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Plastic vessels – 316 SS

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 27m3 x 2No. = 54 m

3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 29.7 m3

Bund Retention Volume:

47.63 m3

Vessel(s) –

25% of Total Storage Volume: 13.5m3

Tank Contents: KD100 Waste R Phrase (WGK Class): R36, R38

Irritant

Contents: Low Risk Condition: Poor Action: Remedial action plus re-inspection

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Bund no longer exists. All Waste plant has been removed from service and de-installed

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Bund appears in good condition. No evidence of leaks or cracks.

Bund Drainage System: In the event of a spill bund would be pumped out. This bund is located inside so is not exposed to rainfall.

Result of Visual Inspection: Pass

Housekeeping Issues: The floor of the bund has some dried in substances indicating leak at some point (Fig.

37a.2). There is also 2 white buckets in the bund. The pipework may need to be replaced to stop this leak in future but should be investigated further.

Housekeeping around outside of bund needs to be improved.

Action Required: None

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 207: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

96

Company: Intel Ireland Ltd Photo/sketch:

See Fig 37.1 – 37.4 Site: Leixlip, Co Kildare

Bund Ref. No.: 37

Bund Location: CDS (KD 100)

Bund Description: KD 100 Plant Room

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Plastic vessels/Metal in room (kd

100 pH tank is Vinlyester FRP)

Bund Materials of Construction:

Concrete

Vessel(s) –

Total Storage Volume: 15.4m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 3.85 m3

Bund Retention Volume:

15.34 m3

Vessel(s) –

25% of Total Storage Volume: 3.85 m3

Tank Contents: (4 tanks and 4 vessels) pH

adjustment tank (T-267-1-280) 3.5m3, pH

adjustment tank (T-267-2-280) 3.5m3, 2 x No.

Descalant tanks (0.2m3 each), Reaction vessel

(RV-266-1-220) 2m3, Reaction vessel (RV-266-

2-220) 2m3, Reaction vessel (RV-266-3-220)

2m3, Reaction vessel (RV-266-4-220) 2m

3

R Phrase (WGK Class): R36, R38

Contents: Low Risk Condition: Poor in areas Action: Remedial action plus re-inspection

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Bund no longer exists. All Waste plant has been removed from service and de-installed

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Bund appears in relatively good condition. No evidence of leaks or cracks.

Bund Drainage System: Local bund - Sump level detection on bund and with manual pump to collection tanks.

General Observations: Water spills on floor of plant room. Pipework extremely corroded and floor needs to be remediated as sealant broken (Fig 37.4). Red liquid in drain should be removed as interferes with retention volume of the bund. Floor around splash guard is discoloured too and should be remediated.

Result of Visual Inspection: Pass

Housekeeping Issues: House keeping around outside of KD 100 waste collection (2 in No.) bund needs to be

improved.

Action Required:

The rusted pipework and floor should be addressed.

Check sump level detection as a lot of liquid in trenches. This requires regular empting and should be included in the site SOP.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 208: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

97

Company: Intel Ireland Ltd Photo/sketch:

See Fig 85.1 – 85.3 Site: Leixlip, Co Kildare

Bund Ref. No.: 85

Bund Location: F14 Haz Waste Loading Dock

Bund Description: C4 (DLW) – IX Treatment

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Rubber lined carbon steel

Bund Materials of Construction:

Concrete

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume:

34.84m3

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents:

Dilute lead waste,

Zeolite resin,

Sodium hypochlorite

Ion exchange resin

R Phrase (WGK Class):

R36/38 Irritant

N/A

R31, R34, WGK 2

N/A

Contents: High Risk Condition: Poor in areas Action: Remedial action plus hydrostatic testing

(where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Bund no longer exists. All Waste plant has been removed from service and de-installed

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Room with door wells and coving at wall-floor interface. Bund appears in relatively good condition. No evidence of leaks or cracks.

Bund Drainage System: Sump level detection on bund – drains along floor with sump in corner.

General Observations: Discoloration on floor around C4 vessels (Fig. 85.2), other than some minor housekeeping issues the bund is in good condition.

Result of Visual Inspection: Pass

Housekeeping Issues: House keeping in bund is not good i.e. loose pipework on ground, lids of vessels,

buckets (Fig. 85.3). General house keeping should be improved

Action Required:

Investigate cause of discolouration on bund floor.

Ensure all containers are clearly labelled.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 209: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

98

Company: Intel Ireland Ltd Photo/sketch:

See Fig 86.1 – 86.3 Site: Leixlip, Co Kildare

Bund Ref. No.: 86

Bund Location: F14 Haz Waste Loading Dock

Bund Description: Lead Reclaim (Heavy metal

reclaim)

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction:

Concrete

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents: Lead R Phrase (WGK Class): Assume high risk as corrosive and

toxic label on vessels

Contents: Assume High Risk Condition: Poor in areas Action: Remedial action plus hydrostatic

testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Bund no longer exists. All Waste plant has been removed from service and de-installed

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Bund appears in relatively good condition. No evidence of leaks. There is a crack along the back wall from the floor to the ceiling (Fig 86.3).

Bund Drainage System: Room with trenches along perimeter and coving at wall-floor interface, bund pumped out if spill occurs.

General Observations: Discoloration on floor (Fig. 86.2), other that some minor housekeeping issues the bund is in good condition.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Investigate cause of discolouration on bund floor.

Ensure all containers are clearly labelled.

Check the capacity of vessel compared to bund.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 210: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

99

Company: Intel Ireland Ltd Photo/sketch:

See Fig 87.1 – 87.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 87

Bund Location: F14 Haz Waste Loading Dock

Bund Description: Solvent Reclaim 1

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction:

Concrete

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents: Solvent waste

R Phrase (WGK Class): R10, R36/37/38

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Bund no longer exists. All Waste plant has been removed from service and de-installed

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Bund appears in relatively good condition. No evidence of leaks (Fig 87.1).

Bund Drainage System: Local Bund - Room with trenches along perimeter and coving at wall-floor interface - bund pumped out if spill occurs.

General Observations: Discoloration on floor (Fig 87.2), other that some minor housekeeping issues the bund is in good condition.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Investigate cause of discolouration on bund floor.

Check the capacity of vessel compared to bund.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 211: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

100

Company: Intel Ireland Ltd Photo/sketch:

See Fig 88.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 88

Bund Location: F14 Haz Waste Loading Dock

Bund Description: Solvent Reclaim 2

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction:

Concrete

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents: Reclaimed Ethyl-Lactate

Reclaimed nMP

R Phrase (WGK Class): Both WGK 1, R10

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Bund no longer exists. All Waste plant has been removed from service and de-installed

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Bund appears in relatively good condition. No evidence of leaks (Fig 88.1).

Bund Drainage System: Local Bund - Room with trenches along perimeter and coving at wall-floor interface - bund pumped out if spill occurs.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 212: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

101

Company: Intel Ireland Ltd Photo/sketch:

See Fig 96.1 – 96.3 Site: Leixlip, Co Kildare

Bund Ref. No.: 96

Bund Location: F14 Basement (Z40)

Bund Description: Acid Exhaust Scrubbers

(No. 1+2)

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume:

19.94m3

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents: Acid Waste R Phrase (WGK Class): R34

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09

Bund & Tank Integrity: Bunded area within the F14 basement. Bund appears in good condition. No evidence of leaks or cracks (Fig 96.1).

Bund Drainage System: Local bunding – drains along floor with sump in corner (Fig. 96.3)

General Observations: Discoloration on floor (fig. 96.2), other that some minor housekeeping issues the bund is in good condition.

Result of Visual Inspection: Pass

Housekeeping Issues:

Action Required:

Monitor discolouration in bund floor. If the bund is cleaned regularly this will increase the life span of the CRC coating. Bund needs to be cleaned.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 213: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

102

Company: Intel Ireland Ltd Photo/sketch:

See Fig 95.1 – 95.3 Site: Leixlip, Co Kildare

Bund Ref. No.: 95

Bund Location: F14 Basement (U40)

Bund Description: Acid Exhaust Scrubbers

(No. 3)

Bund Dimensions: 8.2m x 5m x 0.47mH Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Concrete

bund with plastic container and own bund for NALCO 2584

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: 19.94m3

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents:

NALCO 2584: Contains Sodium Hydroxide & Potassium Hydroxide

Acid Waste

R Phrase (WGK Class):

R35, WGK 1

R34

Contents: Low Risk Condition: Poor in areas Action: Remedial action plus re-inspection

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09

Bund & Tank Integrity: Bunded area within the F14 basement. Bund appears in good condition. No evidence of leaks or cracks (Fig 95.1).

Bund Drainage System: Local bunding – drains along floor with sump in corner. The NALCO 2584 vessel has its own self-contained bund that is pumped out if spills occur. Sand in drainage sump (Fig. 95.2).

General Observations: Discoloration on floor, other than some minor housekeeping issues the bund is in good condition. There is no splash guard in this bund and evidence that during filling chemicals are getting outside the bund (Fig. 95.3).

Result of Visual Inspection: Pass

Housekeeping Issues:

Action Required:

Investigate need for splash guard on this bund.

Sump needs to be unblocked and cleaned out.

Bund needs to be cleaned.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 214: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

103

Company: Intel Ireland Ltd Photo/sketch:

See Fig 94.1 – 94.5 Site: Leixlip, Co Kildare

Bund Ref. No.: 94

Bund Location: F14 Basement (N40)

Bund Description: Acid Exhaust Scrubbers

(No. 5)

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction:

Concrete

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: 19.94m3

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents: Sodium Hydroxide

Acid Waste

R Phrase (WGK Class): R36/38, WGK 1

R34

Contents: Low Risk Condition: Poor in areas Action: Remedial action plus re-inspection

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09

Bund & Tank Integrity: Bunded area within the F14 basement. Bund appears in relatively good condition. No evidence of leaks or cracks (Fig 94.1).

Bund Drainage System: Local bunding – drains along floor with sump in corner.

General Observations: Discoloration on floor (Fig. 94.2). There is a splash guard on the floor.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: The bund should be cleaned.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 215: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

104

Company: Intel Ireland Ltd Photo/sketch:

See Fig 93.1 – 93.3 Site: Leixlip, Co Kildare

Bund Ref. No.: 93

Bund Location: F14 Basement (G40)

Bund Description: Acid Exhaust Scrubbers

(No. 6 + 7)

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction:

Concrete

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: 19.94m3

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents: Sodium Hydroxide

Acid Scrubber Waste

R Phrase (WGK Class): R36/38 WGK 1

Contents: Low Risk Condition: Poor in areas Action: Remedial action plus re-inspection

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09

Bund & Tank Integrity: Bunded area within the F14 basement. Bund appears in relatively good condition. No evidence of leaks or cracks (Fig 93.1).

Bund Drainage System: Local bunding – drains along floor with sump in corner.

General Observations: The bund needs to be cleaned. Some loose cables, timber and piping on floor (Fig 93.2).

Result of Visual Inspection: Pass

Housekeeping Issues:

Action Required: Debris in bund needs to be cleaned.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 216: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

105

Company: Intel Ireland Ltd Photo/sketch:

See Fig 97.1 – 97.3 Site: Leixlip, Co Kildare

Bund Ref. No.: 97

Bund Location: F14 Basement (Located at

Q5 opposite Q43)

Bund Description: C4 System Lift Station

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction: N/A

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: 6320 l

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents:

Sulphuric acid and mehanesulphonic acid waste

Dilute Lead Rinse water /

PB-300 waste

R Phrase (WGK Class):

R35, WGK 1 (Low risk)

(Assumed high risk as contains lead)

R22, R23, R34, R43, R58, R60, R61, WGK 2 (High Risk)

Contents: High Risk Condition: Poor in areas Action: Remedial action plus hydrostatic testing

(where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09

Bund & Tank Integrity: Bunded area within the F14 basement. Bund appears in poor condition. The bund itself has no evidence of leaks or cracks but the splash guard is cracked in areas (fig 97.3).

Bund Drainage System: Local bunding – drains along floor with sump in corner. All tanks in one main open concetre bund.

General Observations: Discoloration on floor (Figure 97.2), other than some minor housekeeping issues the bund is in good condition. The bund needs to be cleaned. Some loose cables, timber and piping on floor.

Result of Visual Inspection: Pass

Housekeeping Issues: Bund needs to be cleaned.

Action Required:

Hydrostatic testing required and general maintenance and cleaning of bund.

Splash guard needs to be repaired.

Discolouration should be monitored.

Check the capacity of vessel compared to bund.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 217: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

106

Company: Intel Ireland Ltd Photo/sketch:

See Fig 92.1 – 92.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 92

Bund Location: F14 Basement (J44)

Bund Description: CCW Lift Tank

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction: N/A

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material:

CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents: CCW Concentrated Copper

Waste

R Phrase (WGK Class): Corrosive and Dangerous, WGK 2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09

Bund & Tank Integrity: Bunded area within the F14 basement. Bund appears in relatively good condition. No evidence of leaks or cracks (Fig 92.1).

Bund Drainage System: Local bunding – drains along floor with sump in corner.

Result of Visual Inspection: Pass

Housekeeping Issues:

Action Required: Check the capacity of vessel compared to bund. Bund needs to be cleaned.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 218: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

107

Company: Intel Ireland Ltd Photo/sketch:

See Fig 101.1 – 101.5 Site: Leixlip, Co Kildare

Bund Ref. No.: 101

Bund Location: F14 Subfab

Bund Description: HPM Rooms (Aqueous

Room)

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Metal/Plastic

Bund Materials of Construction: N/A

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material:

CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents:

Sulphuric Acid,

Hydrogen peroxide 30%

R Phrase (WGK Class):

R35, WGK 1

R5, R8, R20/22, R35, WGK1

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09

Bund & Tank Integrity: Bund appears in relatively good condition. No evidence of leaks or cracks (Fig 101.1).

Bund Drainage System: Room with wide trench perimeter and coving.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: Determine bund retention volume

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 219: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

108

Company: Intel Ireland Ltd Photo/sketch:

N/A Site: Leixlip, Co Kildare

Bund Ref. No.: 159

Bund Location: F14 Subfab

Bund Description: HPM Rooms (Solvent

Room)

Bund Dimensions: Large room bunded trenches under the floor - Complex Dimensions

Vessel(s) –

Materials of Construction: Metal/Plastic

Bund Materials of Construction: N/A

Vessel(s) –

Total Storage Volume: 12,326L

Bund Lining Material:

CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 229L

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: 3081.5L

Tank Contents:

N-Methyl-2-pyrrolidone

AZ C-265 Rinse :

2-Methoxy-1-methylethyl acetate

1 Methoxy-2-propanol

A2-A-515 Developer :

Cyclopentanone

KBR 300:

Ethyl lactate

Baker Positive Resist Striperr (PRS)-3000:

1-Methy-2-Pyrroildinone,

Tetrahydrothiophene-1,1-dioxide

2 Propanol 1-amino

THMR IP2650 HP

THMR IP2650 7CP

Isopropanol

R Phrase (WGK Class):

WGK1, R61, R36/37/38

WGK1, R10, R36

WGK1, R10, R67

WGK1, R10, R36/38

WGK1, R10, R37, R41

WGK1, R22, R36/38

WGK1, R22

WGK1, R34

R10, R20/22, R51/53

R10, R22

R11 R36 R67 WGK 1

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 16/09/09

Bund & Tank Integrity: Bund appears in relatively good condition. No evidence of leaks or cracks

Bund Drainage System: Room with wide trench perimeter and coving.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: Hydrostatic testing (where possible)

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 220: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

109

Company: Intel Ireland Ltd Photo/sketch:

N/A Site: Leixlip, Co Kildare

Bund Ref. No.: 161

Bund Location: F14 PCD

Bund Description: F14 PCD - Planar Chemical

Distribution

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: N/A

Vessel(s) –

Total Storage Volume: 15,000L

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 1387L

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: 3750L

Tank Contents:

PL4217 Oxide Slurry

Silica, Amorphous

Potassium hydroxide

KD100C

Hydrocyanic Acid

R Phrase (WGK Class):

Not classed under the EU legislation but assume low risk as silca is relatively inert

WGK 1, R22, R35

R20/21/22, R52/53, WGK3

Contents: High Risk Condition: Good Action: Hydrostatic testing (where

possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 16/9/09

Bund & Tank Integrity: Bund appears in good condition. Totes containing planar slurries located in this room.

Bund Drainage: Bund drainage unknown, room appears to slope into the middle of the room and open drain located at lowest points.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: Hydrostatic testing (where possible). Determine bund retention volume.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 221: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

110

Company: Intel Ireland Ltd Photo/sketch:

See Fig 30.1 – 30.5 Site: Leixlip, Co Kildare

Bund Ref. No.: 30

Bund Location: North Road Beside Energy

Centre

Bund Description: F14 Emergency Generator

Diesel bund

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: N/A

Bund Materials of Construction: N/A

Vessel(s) –

Total Storage Volume: 2 x 60m3

& 4 x 1m3

= 124m3

Bund Lining Material: N/A

Vessel(s) –

110% of Volume of Largest Vessel: 66m3

Bund Retention Volume: 137.35m3

Vessel(s) –

25% of Total Storage Volume: 31m3

Tank Contents: Waste Oil (Diesel), Diesel

(gas oil), Antifreeze, Waste Oil, Transformers (EG-8, EG-9, EG-10, EG-11)

R Phrase (WGK Class):

Waste Oil Diesel: R40 WGK 2

Diesel Gas Oil: R40, Harmful

Transformer Oil: WGK 2

Risk Phrases: R45

Contents: High Risk Condition: Poor in areas Action: Remedial action plus hydrostatic testing

(where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09

Bund & Tank Integrity: Bund has grate slab with upstand all around. Bund appears to be generally intact – no visible cracks or leaks internally. However significant mossy growth coverage on base of bund and tree/bush growth (Fig. 30.1-30.5) therefore could not fully inspect. There are a lot of leaves in bund and these are blocking the drains along the drainage channels. There is evidence of water in bund but it was quite a wet weekend and it is assumed that this is rainwater. There is evidence of cracks along the kerbs of this bund.

The transformers (x4) have there own metal bund with this larger bund. Covered in moss and filed with water, this needs to be cleaned and water removed.

Bund Drainage System: Local bund. Bund slopes therefore rainwater collecting at one end of bund.

General observations: Tree and shrub growth in bund needs to be removed.

Result of Visual Inspection: Fail

Housekeeping Issues:

Bund needs to be cleaned as there is a lot of overgrowth in the bund including leaves. There are absorbent materials and pallets in bund, these should be removed. The slip mats in the bund are in very poor condition and either need to be cleaned or replaced in some areas as they are covered in moss and are extremely slippy.

Action Required:

Water retention from each transformer bund should be emptied.

The bund needs to be regularly monitored and cleaned.

Cracks along kerb need to be inspected and repaired as necessary.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 222: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

111

Bund ID: F14 Generator Diesel Bund

Result of Hydrostatic Test: Fail

Date of hydrostatic Test: 14/2/11

Length of test: 24hrs

Measurement at beginning of test: 75mm

Measurement at end of test: 0mm (Note:

Holding tank was still full. Above measurements were for surface water. )

Volume Tested to: 66m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Eamon McIvor Title: Engineering Owner

Page 223: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

112

Company: Intel Ireland Ltd Photo/sketch:

See Fig 143.1 – 143.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 143

Bund Location: F14 Basement (M46)

Bund Description: PCW/CPCW Chemical

Dosing (Nalco 2536+)

Bund Dimensions: 1.05 x 0.75 x 0.4m =

0.315m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 280L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 308L

Bund Retention Volume: 315L

Vessel(s) –

25% of Total Storage Volume: 70L

Tank Contents: Sodium Nitrite R Phrase (WGK Class): R22, R52, WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 18/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues:

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 224: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

113

Company: Intel Ireland Ltd Photo/sketch:

See Fig 144.1 – 144.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 144

Bund Location: F14 Basement (S49) Tank

No. SN907042

Bund Description: PVAC Dosing - Nalco

2510

Bund Dimensions: 0.8 x 1.2 x 0.45m =

0.430m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 260L

Bund Lining Material: none

Vessel(s) –

110% of Volume of Largest Vessel: 286L

Bund Retention Volume: 430L

Vessel(s) –

25% of Total Storage Volume: 65L

Tank Contents: 2,2-Dibromo-3-

Nitrilopropionamide

R Phrase (WGK Class): R20/22, R38, R43, R41, WGK3

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: Assess practicality of hydrostatically

testing bunds in basement.

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 18/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues:

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 225: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

114

Company: Intel Ireland Ltd Photo/sketch:

See Fig 145.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 145

Bund Location: F14 Basement (S49)

Bund Description: PVAC Dosing Skid (Nalco

8539) (Tank No. SN182782)

Bund Dimensions: 0.9 x 1.2 x 0.55m =

0.594m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 440L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 484L

Bund Retention Volume: 0.9 x 1.2 x 0.55m =

0.594m3

Vessel(s) –

25% of Total Storage Volume: 110L

Tank Contents: Sodium Nitrite & Potassium

Hydroxide

R Phrase (WGK Class): R25, R36/38, R50

WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 18/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 226: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

115

Company: Intel Ireland Ltd Photo/sketch:

See Fig 146.1 – 146.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 146

Bund Location: F14 Basement (T41) PVAC

Dosing Skid (Tank No. SNJP0061)

Bund Description: Scrubber Cleaning (Nalco

2584)

Bund Dimensions: 1 x 1.4 x 0.7m = 0.98m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 750L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 825L

Bund Retention Volume: 980L

Vessel(s) –

25% of Total Storage Volume: 187.5L

Tank Contents: Sodium Hydroxide &

Potassium Hydroxide

R Phrase (WGK Class): R35

WGK1

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 18/5/09

Bund & Tank Integrity: Bund appears in good condition but there is evidence of leaks in bund, white power and gloves in bund.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: Bund should be cleaned out

Action Required: None

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 227: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

116

Company: Intel Ireland Ltd Photo/sketch:

See Fig 147.1 – 147.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 147

Bund Location: F14 Basement (R43)

Bund Description: DL W Dosing - ST40

Bund Dimensions: 0.9 x 1.2 x 0.55m =

0.594m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 440L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 484L

Bund Retention Volume: 594L

Vessel(s) –

25% of Total Storage Volume: 110L

Tank Contents: Sodium Hydroxide, Sodium

Hypochlorite

R Phrase (WGK Class): R34, R31, WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: Assess practicality of

hydrostatically testing bunds in basement.

Bund no longer exists. All Waste plant has been removed from service and de-installed

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 18/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 228: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

117

Company: Intel Ireland Ltd Photo/sketch:

See Fig 137.1 - 137.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 137

Bund Location: F14 Nitrogen Plant

Bund Description: Transformer Bund

Bund Dimensions: Irregular shape Vessel(s) –

Materials of Construction: Metal Transformers on gravel

bund

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 584L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 642.4L

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: 146L

Tank Contents: Electrical insulating oil

R Phrase (WGK Class): WGK 1

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: Local bund - If leak occurs the bund is manually pumped out and cleaned.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: Determine bund retention volume

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 229: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

118

Company: Intel Ireland Ltd Photo/sketch:

See Fig 138.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 138

Bund Location: F14 UPW

Bund Description: URW Dosing - Nalco

77357 (SN47174)

Bund Dimensions: 1.9 x 3 x 0.4m = 2.28m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 800L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 880L

Bund Retention Volume: 2280L

Vessel(s) –

25% of Total Storage Volume: 200L

Tank Contents: Sodium Bromide

R Phrase (WGK Class): R36, WGK1

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: Local bund - If leak occurs the bund is manually pumped out and cleaned.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: None

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 230: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

119

Company: Intel Ireland Ltd Photo/sketch:

See Fig 139.1 – 139.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 139

Bund Location: F14 UPW

Bund Description: URW Dosing (Nalco

93033)

Bund Dimensions: 1.9 x 1.6 x 0.65m =

1.976m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 1500L

Bund Lining Material: none

Vessel(s) –

110% of Volume of Largest Vessel: 1650L

Bund Retention Volume: 1976L

Vessel(s) –

25% of Total Storage Volume: 375L

Tank Contents: Sodium Hypochlorite

R Phrase (WGK Class): R31, R34, WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: Local bund - If leak occurs the bund is manually pumped out and cleaned.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 231: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

120

Company: Intel Ireland Ltd Photo/sketch:

See Fig 64.1 – 64.3 Site: Leixlip, Co Kildare

Bund Ref. No.: 64

Bund Location: F14 UPW

Bund Description: RO Cleaning Chemical

Bund (3 individual bunds)

Bund Dimensions: Complex dimensions

Vessel(s) –

Materials of Construction: Various plastic/metal vessels

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents:

Anti-Scalant,

Biocide,

Sodium Bisulphite (NaHSO3)

R Phrase (WGK Class):

N/A

R34, R43, R52/53

R22, R31 WGK 1

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09

Bund & Tank Integrity: Bunded area within the F24 UPW room divided into three individual bunds by coated upstands. No visible cracks or leaks in bund and general in good condition.

General Observation: Bund consists of three smaller individual bunds i.e. Anti-Scalant, Biocide and Sodium Bisulphite. Sodium bisulphite bund has some discolouration indicating a leak or spill and integrity should be tested in this bund (Fig. 64.2). In the event of a spill or leak the bund will be manually pumped out.

Result of Visual Inspection: Pass

Housekeeping Issues: Bunds should be cleaned.

Action Required: Determine bund retention volume.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 232: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

121

Company: Intel Ireland Ltd Photo/sketch:

See Fig 125.1 – 125.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 125

Bund Location: F14 Energy Centre OFA &

Condenser Cooling Tower (Tank No. SN182766)

Bund Description: Nalco 3DT188

Bund Dimensions: 0.9 x 1.2 x 0.55m =

0.594m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 440L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 484L

Bund Retention Volume: 594L

Vessel(s) –

25% of Total Storage Volume: 110L

Tank Contents: Phosphoric Acid

R Phrase (WGK Class): R34, WGK 1

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: None

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 233: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

122

Company: Intel Ireland Ltd Photo/sketch:

See Fig 126.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 126

Bund Location: F14 Energy Centre OFA &

Condenser Cooling Tower (Tank No. SN182963)

Bund Description: Nalco 3DT222

Bund Dimensions: 0.9 x 1.2 x 0.55m =

0.594m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 440L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 484L

Bund Retention Volume: 594L

Vessel(s) –

25% of Total Storage Volume: 110L

Tank Contents: Phosphoric Acid &

Hydrochloric Acid & Zinc Chloride

R Phrase (WGK Class): R36/38, R51/53

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Testing would involve taking the primary vessel offline which would impact fab operations

Result of Hydrostatic Test:

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: Local bund - If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 234: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

123

Company: Intel Ireland Ltd Photo/sketch:

See Fig 127.1 – 127.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 127

Bund Location: F14 Energy Centre Chilled

Water/MTHW (Tank No. SNJP0130)

Bund Description: Nalco 93033

Bund Dimensions: 1.4 x 1 x 0.77m = 1.078m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 750L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 825L

Bund Retention Volume: 1078L

Vessel(s) –

25% of Total Storage Volume: 187.5L

Tank Contents: Sodium Hypochlorite

R Phrase (WGK Class): R31, R34, WGK 2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Testing would involve taking the primary vessel offline which would impact fab operations

Result of Hydrostatic Test:

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 235: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

124

Company: Intel Ireland Ltd Photo/sketch:

See Fig 128.1- 128.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 128

Bund Location: F14 Energy Centre

Condenser water

Bund Description: Nalco 00GE056

Bund Dimensions: 0.9 x 1.2 x 0.55m =

0.594m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 440L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 484L

Bund Retention Volume: 594L

Vessel(s) –

25% of Total Storage Volume: 110L

Tank Contents: Disodium Metasilicate, Sodium

Molybdate, Sodium Tetraborate

R Phrase (WGK Class): R36/38

WGK 1

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: None

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 236: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

125

Bund ID: Bund Ref. No.: 128

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 2/12/10

Length of test: 24 hrs

Measurement at beginning of test: 550mm

Measurement at end of test: 550mm

Volume Tested to: 0.430 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Simon McLain Title: Engineering Owner

Page 237: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

126

Fab 24 Bunds

Page 238: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

127

Company: Intel Ireland Ltd Photo/sketch:

See Fig 75.1 – 75.3 Site: Leixlip, Co Kildare

Bund Ref. No.: 75

Bund Location: F24 AWN PIT

Bund Description: F24 AWN

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Vinylester FRP

Bund Materials of Construction: concrete

Vessel(s) –

Total Storage Volume: 103.8m 3

x 7 = 726.6m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 114.18m3

Bund Retention Volume:

355.7m3

Vessel(s) –

25% of Total Storage Volume: 181.65m3

Tank Contents:

AWN and URW/IRW Tanks (7 in No.)

R Phrase (WGK Class): R36/37/38

Contents: Low Risk Condition: Poor in

areas

Action: Remedial action plus re-inspection

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

This is a remote bund for other areas containing high risk substances therefore it should be hydrostatically tested as the risk category is potentially high risk.

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

This bund has a number of critical systems feeding in which cannot be isolated without a factory impact. A practicable bund test cannot be completed

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally. There is some discolouration in the bund (Fig. 75.3) (from leak in past), this should be investigated.

Bund Drainage System: Sump automatically pumped to the AWN. This is a remote bund for other areas containing high risk substances.

General observations: Debris in bund needs to be removed (Fig. 75.2).

Results of Visual Inspection: Pass

Housekeeping Issues:

Bund needs to be cleaned as there is a lot of debris in the bund and bag of construction materials gathered at the base of the bund. (Done)

Action Required:

Discolouration on bund floor should be monitored.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 239: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

128

Company: Intel Ireland Ltd Photo/sketch:

See Fig 82.1

Site: Leixlip, Co Kildare

Bund Ref. No.: 82

Bund Location: F24 AWN PIT

Bund Description: HFW Lift Tank

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Polypropylene lined FRP

Bund Materials of Construction: concrete

Vessel(s) –

Total Storage Volume: 4m3

x 2 = 8m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 4.4m3

Bund Retention Volume:

10.5m3

Vessel(s) –

25% of Total Storage Volume: 2m3

Tank Contents:

HFW Lift Tanks (2 in No.)

R Phrase (WGK Class): R39/26/27/28, R34

WGK 2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: Pass (See addendum below for details)

Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally.

Bund Drainage System: Local bund - sump with auto capability to the HF lift tanks only.

Results of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Bund ID: 82

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 7/3/10

Length of test: 24hrs

Measurement at beginning of test: 138mm

Measurement at end of test: 138mm

Volume Tested to: 3.4m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Alan Campbell Title: IWS Engineer

Page 240: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

129

Company: Intel Ireland Ltd Photo/sketch:

See Fig 81.1 – 81.2

Site: Leixlip, Co Kildare

Bund Ref. No.: 81

Bund Location: F24 AWN PIT

Bund Description: Phosphoric Acid Holding

Tank

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: FRP

Bund Materials of Construction: concrete

Vessel(s) –

Total Storage Volume: 18.7m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 20.57m3

Bund Retention Volume:

49.1m3

Vessel(s) –

25% of Total Storage Volume: 4.675m3

Tank Contents:

Phosphoric Acid Holding Tank containing Phosphoric Acid H3PO4

R Phrase (WGK Class): WGK 1, R20/21/22, R34

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally.

Bund Drainage System: Sump with manual valve that is pumped to AWN or collection tank.

General observations: Debris in bund.

Result of Visual Inspection: Pass

Housekeeping Issues: There is some rainwater and leaves in this bund. Debris in bund needs to be removed

(Fig 81.2). Monitor bund for discolouration.

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 241: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

130

Company: Intel Ireland Ltd Photo/sketch:

No photos available Site: Leixlip, Co Kildare

Bund Ref. No.: 79

Bund Location: F24 AWN PIT

Bund Description: NH4W Lift Tanks

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: FRP

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 10.2m3

x 2 =20.4m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 11.22m3

Bund Retention Volume: 31.1m3

Vessel(s) –

25% of Total Storage Volume: 5.1m3

Tank Contents: NH4 tanks (Ammonium

chloride)

R Phrase (WGK Class): WGK 1, R22, R36

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally.

Bund Drainage System: Sump with automatic valve that is pumped to AWN and lift tank.

Result of Visual Inspection: Pass

Housekeeping Issues:

There is some rainwater and leaves in this bund. Debris in bund needs to be removed.

Action Required: None

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 242: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

131

Company: Intel Ireland Ltd Photo/sketch:

See Fig 78.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 78

Bund Location: F24 AWN PIT

Bund Description: SCW/CCW Bund

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: FRP

Bund Materials of Construction: concrete

Vessel(s) –

Total Storage Volume:

CCW Holding Tank – 19m3

SCW Lift Tank – 7m3

Total = 26m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 20.9 m3

Bund Retention Volume:

51.7 m3

Vessel(s) –

25% of Total Storage Volume: 6.5 m3

Tank Contents:

CCW Holding Tank containing concentrated copper waste

SCW Lift Tank containing slurry copper waste

R Phrase (WGK Class):

R34, WGK2

R36/37/38

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: Pass (See addendum below for details)

Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks.

Bund Drainage System: Sump with manual valve that is pumped to CCW tank and SCW lift tank.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 243: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

132

Bund ID: 78

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 25/3/10

Length of test: 24hrs

Measurement at beginning of test: 68mm

Measurement at end of test: 68mm

Volume Tested to: 7.5m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Alan Campbell Title: IWS Engineer

Page 244: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

133

Company: Intel Ireland Ltd Photo/sketch:

See Fig 77.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 77

Bund Location: F24 AWN PIT

Bund Description: C4 bund

RMW (Reclaim metal waste, DMW (Dilute metal waste), DMW (Divert metal waste), CMW (Concentrated metal waste) (4 in No.)

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 29.1m3 x 4 = 116.4m

3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 32.01m3

Bund Retention Volume: 79.6m3

Vessel(s) –

25% of Total Storage Volume: 29.1m3

Tank Contents:

RMW: C4 reclaim metal waste

Dilute Metal Waste

Divert Metal Waste

CMW: C4 concentrated metal waste

R Phrase (WGK Class):

R33, R34, R58, R60, R61

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: Pass (See addendum below for details)

Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks.

Bund Drainage System: Sump options: Two pumps in bund, east and west pump both manually operated to all tanks within the bund RMW, CMW, DMW and MWD.

General Observations: There is some discolouration on the bund floor.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 245: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

134

Bund ID: 77

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 9/3/10

Length of test: 24hrs

Measurement at beginning of test: 147mm

Measurement at end of test: 147mm

Volume Tested to: 11.7m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Alan Campbell Title: IWS Engineer

Page 246: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

135

Company: Intel Ireland Ltd Photo/sketch:

See Fig 76.1 – 76.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 76

Bund Location: F24 AWN PIT

Bund Description: CSW (Corrosive Solvent

Waste)

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: 22.3m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 24.53m3

Bund Retention Volume: 51.7m3

Vessel(s) –

25% of Total Storage Volume: 5.575m3

Tank Contents:

Corrosive Solvent Waste (CSW) (Sulfolane Tetramethylammonium Hydroxide)

R Phrase (WGK Class): R22, R34, WGK 1

Contents: Low Risk Condition: Poor in

areas

Action: Remedial action plus re-inspection

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks.

Bund Drainage System: Sump with manual valve that is pumped to CSW tank only.

General Observations: There is some discolouration on the bund floor (fig 76.2).

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Investigate the discolouration on the bund floor and remediate if necessary

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 247: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

136

Company: Intel Ireland Ltd Photo/sketch:

See Fig 83.1 – 83.3 Site: Leixlip, Co Kildare

Bund Ref. No.: 83

Bund Location: F24 AWN PIT

Bund Description: Solvent Area

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: N/A

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume: 19.9m3 x 3 = 59.7m

3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 65.67m3

Bund Retention Volume:

123.1m3

Vessel(s) –

25% of Total Storage Volume: 14.925m3

Tank Contents:

General Solvent Collection

General Solvent Divert

SOG

R Phrase (WGK Class): Unknown, assume high risk

Contents: Assume High Risk Condition: Poor in

areas

Action: Remedial action plus hydrostatic testing

(where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: Pass (See hydrostatic Results in addendum below)

Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks. There is some rainwater in this bund.

Bund Drainage System: Sump with manual valve that is pumped to CSW tank only.

General Observations: There is some discolouration on the bund floor (Fig 83.2). The bund needs to be cleaned. There is some white foam need door (Fig. 83.3), this should be cleaned and investigated further.

Result of Visual inspection: Pass

Housekeeping Issues: Some debris in bund. This should be removed.

Action Required:

The bund should be cleaned and any debris and maintenance materials removed.

Investigate foam on wall behind bund door.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 248: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

137

Bund ID: 83

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 11/3/10

Length of test: 24hrs

Measurement at beginning of test: 235mm

Measurement at end of test: 235mm

Volume Tested to: 11m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Alan Campbell Title: IWS Engineer

Page 249: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

138

Company: Intel Ireland Ltd Photo/sketch:

See Fig 80.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 80

Bund Location: F24 AWN Area

Bund Description: C4 Dilute Metal Waste

Treatment

Bund Dimensions: Complex Dimensions Vessel(s) –

Materials of Construction: Plastic and Metal

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume: 3 x IX beds

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume:

1.19m3

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents:

Dilute Metal Waste

R Phrase (WGK Class): Corrosive & Dangerous to the

Environment

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: Pass (See addendum below for results of hydrostatic test)

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks.

Bund Drainage System: Local bund – Bund is checked and manually pumped to AWN as required.

Result of visual Inspection: Pass

Housekeeping Issues: Some loose cabling and wires need to be removed from bund.

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 250: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

139

Bund ID: 80

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 11/3/10

Length of test: 24hrs

Measurement at beginning of test: 56mm

Measurement at end of test: 56mm

Volume Tested to: 4.6m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Alan Campbell Title: IWS Engineer

Page 251: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

140

Company: Intel Ireland Ltd Photo/sketch:

See Fig 72.1 – 72.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 72

Bund Location: F24 AWN AREA

Bund Description: IWW Tanks

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Vinlester FRP

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume: 146.8m3

x 3 = 440.4m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 161.48m3

Bund Retention Volume:

202.6m3

Vessel(s) –

25% of Total Storage Volume: 110.1m3

Tank Contents:

Acid Waste (3 in No.)

R Phrase (WGK Class): R20/21/22

Contents: Low risk Condition: Poor in

areas

Action: Remedial action

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally. However tree/bush growth from grate between TK-261-1-190 & TK-261-2-190 (Fig. 72.2). There is also some discolouration from moss growth in the bund. Liquid retention in bund (rainwater) which is reducing retention capacity.

Bund Drainage System: Local bund - Sump options with manual drain valve to AWN.

Result of Visual Inspection: Pass

Housekeeping Issues:

Bund needs to be cleaned as there is a lot of overgrowth in the bund and leaves.

Action Required:

Bund requires regular emptying to ensure required storage capacity for spills/leaks.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Bund ID: Bund Ref. No.: 72

Result of Hydrostatic Test: Fail

Date of hydrostatic Test: 2/3/11

Length of test: N/A

Measurement at beginning of test: N/A

Measurement at end of test: N/A

Volume Tested to: N/A

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Michelle Cronin Title: Engineering Owner

Page 252: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

141

Company: Intel Ireland Ltd Photo/sketch:

See Fig 74.1 – 74.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 74

Bund Location: F24 AWN AREA

Bund Description: Sodium Hydroxide Bridge

Scrubber Day Tank

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: 316 SS

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume: 1.7m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 1.87 m3

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: N/A

Tank Contents:

Sodium Hydroxide NaOH

R Phrase (WGK Class): R35, WGK 1

Contents: Low Risk Condition: Poor in

areas

Action: Remedial action plus re-inspection

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally. (Fig. 74.1). There is also some discolouration from moss growth in the bund. Pipework to tanks in poor condition – insulation falling off and pipework broken (see Fig. 74.2).

Bund Drainage System: Sump options with manual drain valve to AWN. Grate in corner is extremely rusty and needs to be replaced.

Result of Visual Inspection: Pass

Housekeeping Issues: 7up bottle in outlet pump needs to be removed and bund should be checked for other

housekeeping issues and cleaned accordingly.

Action Required:

Pipework should be fixed and replaced if necessary. Determine bund retention volume.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 253: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

142

Company: Intel Ireland Ltd Photo/sketch:

See Fig 73.1 – 73.3 Site: Leixlip, Co Kildare

Bund Ref. No.: 73

Bund Location: F24 AWN AREA

Bund Description: Sulphuric Acid Bridge Day

Tank

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: FRP pvdf lined

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume: 14.9m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 16.39 m3

Bund Retention Volume:

42.2m3

Vessel(s) –

25% of Total Storage Volume: 3.725 m3

Tank Contents:

Sulphuric Acid

R Phrase (WGK Class): R20/21/22, R35, R41, WGK 1

Contents: Low Risk Condition: Poor in

areas

Action: Remedial action plus re-inspection

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Bund is in poor condition, corrosion in bund appears to have removed some CRC coating and this should be fixed (Fig. 73.3). The bund appears to be generally intact – no other visible cracks. There is also some discolouration from moss growth in the bund. Pipework to tanks in good condition (see Fig. 73.2).

Bund Drainage System: Sump options with manual drain valve to AWN.

Result of Visual Inspection: Fail

Housekeeping Issues: None

Action Required:

The corroded area for the bund mentioned above should be recoated with CRC coating. Bund should be regularly investigated for leaks and monitored for discolouration.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 254: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

143

Company: Intel Ireland Ltd Photo/sketch:

See Fig 67.1 – 67.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 67

Bund Location: F24 PSB Tank Farm

Bund Description: CCW Prep Tank

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: FRP (Fibre reinforced plastic)

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume: 7m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 7.7m3

Bund Retention Volume: 73.76m3

Vessel(s) –

25% of Total Storage Volume: 1.75m3

Tank Contents:

20% H2SO4

5% Cu

5% H2O2

5% NaHSO3

1% HCL

1% CH4SO3

R Phrase (WGK Class): R35, R51/53, WGK 2

Contents: High Risk Condition: Poor in

areas

Action: Remedial action plus hydrostatic testing

(where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: Pass (See addendum below)

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Pipework to tanks in poor condition – pipework broken and rusting (see Fig. 67.2). There is evidence of cracks in this bund on the tank pad and CRC damage.

Bund Drainage System: Sump options with manual pump to AWN and prep tank.

Result of Visual Inspection: Fail

Housekeeping Issues: Bund needs to be cleaned as there is some leaves in the base.

Action Required:

Bund should be monitored for leaks.

CRC and cracks should be repaired.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 255: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

144

Bund ID: 67

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 14/3/10

Length of test: 24hrs

Measurement at beginning of test: 70mm

Measurement at end of test: 70mm

Volume Tested to: 6.7m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Alan Campbell Title: IWS Engineer

Page 256: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

145

Company: Intel Ireland Ltd Photo/sketch:

See Fig 66.1 – 66.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 66

Bund Location: F24 PSB Tank Farm

Bund Description: Ammonium Sulphate

Bund Dimensions: 5.5m x 13.5m x 1mH

Vessel(s) –

Materials of Construction: Metal tank

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume: 21m3 x 2 = 42m

3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 23.1m3

Bund Retention Volume: 145.8m3 Vessel(s) –

25% of Total Storage Volume: 10.5m3

Tank Contents:

Ammonium Sulphate Collection Tanks (2 in No.)

(NH4)2SO2

R Phrase (WGK Class): R36/37/38, WGK 1

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally (Fig. 66.1). There is also some discolouration from moss growth in the bund.

Bund Drainage System: Sump options with automatically drain valve to AWN, NH4W collection tanks and Ammonia sulphate collection tanks.

Result of Visual Inspection: Pass

Housekeeping Issues: Debris in bund should be removed (Fig.66.2).

Action Required: None

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 257: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

146

Company: Intel Ireland Ltd Photo/sketch:

See Fig 60.1 – 60.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 60

Bund Location: F24 PSB Tank Farm

Bund Description: Lime Storage Silo

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Metal tank

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents:

Calcium Hydroxide (CaOH2)

R Phrase (WGK Class): R34, R36/37/38

WGK 1

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally (Fig. 61.1). There is also some rainwater in the bund (Fig. 61.2).

Bund Drainage System: Sump with capability to automatically pump to AWN only.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

All tanks should be clearly labelled with contents. Determine bund retention volume.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 258: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

147

Company: Intel Ireland Ltd Photo/sketch:

See Fig 59.1 – 59.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 59

Bund Location: F24 PSB Tank Farm

Bund Description: HFW Collection/Divert

Tanks

Bund Dimensions: Complex dimensions

Vessel(s) –

Materials of Construction: Polypropylene lined FRP

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume: 158.6m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 174.46m3

Bund Retention Volume:

215.9m3

Vessel(s) –

25% of Total Storage Volume: 39.65m3

Tank Contents: Hydrofluoric acid

R Phrase (WGK Class): R26/27/28, R34

WGK 2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: Pass (See addendum below for results)

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally (Fig. 59.1). There is also some rainwater in the bund. There is some debris including leaves in the area close to outlet sump.

Bund Drainage System: Sump with capability to automatically pump to collection tanks only.

General Observations: Some plastic has fallen from behind the TK-266-2-200 tank and needs to be removed from the bund.

Result of Visual Inspection: Pass

Housekeeping Issues: Debris in bund should be removed (Fig. 59.2).

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 259: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

148

Bund ID: 59

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 14/3/10

Length of test: 24hrs

Measurement at beginning of test: 70mm

Measurement at end of test: 70mm

Volume Tested to: 36m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Alan Campbell Title: IWS Engineer

Page 260: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

149

Company: Intel Ireland Ltd Photo/sketch:

See Fig 63.1 – 63.3 Site: Leixlip, Co Kildare

Bund Ref. No.: 63

Bund Location: F24 PSB Tank Farm

Bund Description: HCI Acid Bulk

Bund Dimensions: Complex dimensions

Vessel(s) –

Materials of Construction: FRP

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume: 11.2m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 12.32m3

Bund Retention Volume:

62.4m3

Vessel(s) –

25% of Total Storage Volume: 2.8m3

Tank Contents: Hydrochloric acid (HCl)

R Phrase (WGK Class): R20/21/R22, R35, R41

WGK 1

Contents: Low Risk Condition: Poor in

areas

Action: Remedial action plus re-inspection

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally (Fig. 63.1). There is also some rainwater in the bund. The grate over the outlet sump is rusted and there appears to be some rusting around the base of the HCl tank (Fig. 63.2). This tank should be investigated further for leaks and checked on a regular basis.

Bund Drainage System: Sump options with manual drain valve to AWN.

Result of Visual Inspection: Pass

Housekeeping Issues: The bund needs to be cleaned.

Action Required:

The bund should be checked for leaks on a regular basis.

Monitor rusting.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 261: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

150

Company: Intel Ireland Ltd Photo/sketch:

See Fig 62.1 – 62.4 Site: Leixlip, Co Kildare

Bund Ref. No.: 62

Bund Location: F24 PSB Tank Farm

Bund Description: Sulphuric Acid Bulk

Bund Dimensions: Complex dimensions

Vessel(s) –

Materials of Construction: FRP pvdf lined

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume: 12.3m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 13.53m3

Bund Retention Volume:

55.6m3

Vessel(s) –

25% of Total Storage Volume: 3.075m3

Tank Contents: Sulphuric acid (H2SO4)

R Phrase (WGK Class): R35, R41, R20, R21, R22

WGK 1

Contents: Low Risk Condition: Poor in areas Action: Remedial action plus re-inspection

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks (Fig. 62.1). There is also some rainwater in the bund. There appears to be rusting on the supports / base plates of the bund (Fig. 62.2). Floor appears discoloured from the rusting supports.

Bund Drainage System: Sump options with manual drain valve to AWN.

General observations: Some pipework appears to be broken.

Result of Visual Inspection: Pass

Housekeeping Issues: Debris in bund should be removed (Fig. 62.4).

Action Required:

Rusting should be monitored and if necessary the base supports should to be replaced.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 262: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

151

Company: Intel Ireland Ltd Photo/sketch:

See Fig 61.1 – 61.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 61

Bund Location: F24 PSB Tank Farm

Bund Description: Sodium Hydroxide Bulk

Tank

Bund Dimensions: Complex dimensions

Vessel(s) –

Materials of Construction: 316 SS

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume: 29.9m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 32.89m3

Bund Retention Volume:

67.7m3

Vessel(s) –

25% of Total Storage Volume: 7.475m3

Tank Contents: Sodium Hydroxide (NaOH)

R Phrase (WGK Class): R35, R41, R20/ R21/ R22

WGK 1

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks (Fig. 61.1). The bund has recently been recoated in certain areas with CRC but there are still some areas where discolouration is evident, this should be monitored for further deterioration (Fig. 61.2).

Bund Drainage System: Sump options with manual drain valve to AWN.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: None

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 263: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

152

Company: Intel Ireland Ltd Photo/sketch:

See Fig 58.1 – 58.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 58

Bund Location: F24 PSB Tank Farm

Bund Description: SCW Buffer Tanks

Bund Dimensions: Complex dimensions

Vessel(s) –

Materials of Construction: FRP

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume: 67.2m3

x 2 = 134.4m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 73.92m3

Bund Retention Volume:

198.2m3

Vessel(s) –

25% of Total Storage Volume: 33.6m3

Tank Contents: Slurry Copper Waste (SCW)

R Phrase (WGK Class): R21/22, R36/38

Contents: Low Risk Condition: Poor in

areas

Action: Remedial action plus re-inspection

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Re-Testing completed

Result of Hydrostatic Test: Pass

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Tanks & bunds appear in good condition. No evidence of cracks or leaks and ground around dry. Liquid retention in both bunds (probably rainwater) which is reducing retention capacity. There appears to be some discolouration from moss growth in the bund (Fig. 58.1).

Bund Drainage System: Sump with auto capability to pump to collection tanks

General Observations: The construction/maintenance materials should be removed from the bund (Fig. 58.2).

Result of Visual Inspection: Pass

Housekeeping Issues: Debris in bund should be removed. (Done)

Action Required:

Rusting should be monitored.

Bunds require regular emptying to ensure required storage capacity for spills/leaks.

Bund should be cleaned.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Bund ID: 58

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 18/3/10

Length of test: 24hrs

Measurement at beginning of test: 75mm

Measurement at end of test: 75mm

Volume Tested to: 30m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Alan Campbell Title: IWS Engineer

Page 264: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

153

Company: Intel Ireland Ltd Photo/sketch:

See Fig 65a.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 65a

Bund Location: F24 PSB

Bund Description: F24 CCW Treatment Plant

Bund Dimensions: Complex dimensions

Vessel(s) –

Materials of Construction: Various metal/plastic containers

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents:

20% H2SO4

20% NaOH

5% Cu

5% NaHSO3

2% CH4SO3

1% H2O2

1% HCL

R Phrase (WGK Class): R35, WGK 2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: Pass (See addendum below)

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Room with coving all around. Trench perimeter except at the roller shutter door Bund appears in good condition. No evidence of leaks or cracks.

Bund Drainage System: Manually operated options to go to AWN and prep tank. Bund is indoors so is not exposed to rainwater.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: Determine bund retention volume.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 265: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

154

Bund ID: 65A

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 11/3/10

Length of test: 24hrs

Measurement at beginning of test: 295mm

Measurement at end of test: 295mm

Volume Tested to: 31.5m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Alan Campbell Title: IWS Engineer

Page 266: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

155

Company: Intel Ireland Ltd Photo/sketch:

See Fig 65.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 65

Bund Location: F24 PSB

Bund Description: F24 HFW and SCW

Treatment Plant

Bund Dimensions: Complex dimensions

Vessel(s) –

Materials of Construction: Various metal/plastic vessels

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume: 49m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: 78m3 Vessel(s) –

25% of Total Storage Volume: 12.25m3

Tank Contents:

Hydrofluoric Acid (HFW) and

Slurry Copper Waste (SCW, NaOH, H2SO4)

R Phrase (WGK Class):

R26/27/28, R34, WGK 2

R20/21/22, R34, R36/38, R41

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: Pass (See addendum Below)

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Trench around equipment, floor falls to trench and coving around. Bund appears in good condition. No evidence of leaks or cracks.

Bund Drainage System: Manually operated options to go to AWN, Sludge tank and collection tanks for HFW bund and automatically piped to collection tanks is applied to the SCW tank. Bund is indoors so is not exposed to rainwater.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Bund ID: 65

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 11/3/10

Length of test: 24hrs

Measurement at beginning of test: 420mm

Measurement at end of test: 420mm

Volume Tested to: 78m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Alan Campbell Title: IWS Engineer

Page 267: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

156

Company: Intel Ireland Ltd Photo/sketch:

See Fig 51.1 – 51.4 Site: Leixlip, Co Kildare

Bund Ref. No.: 51

Bund Location: F24 Middle Yard

Bund Description: Softened Industrial Water

(SIW)

Bund Dimensions: 7.4m x 6.4m x 0.25mH

Vessel(s) –

Materials of Construction: Metal/Plastic

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: 11.84m3 Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents:

Softened Industrial Water

R Phrase (WGK Class): No risk phases assigned

Contents: Low Risk Condition: Poor in

areas

Action: Remedial action plus re-inspection

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: There appears to be rusting on the some of the pipework/support plates in the bund (Fig. 51.2). Floor appears discoloured from the rusting. The top of the bund wall is crumbling (Fig. 51.3) (This defect in the bund wall is not significant in containing material as it is above the bund volume level).

Bund Drainage System: Local bunding - Bottom outlet valve on bund.

General Observations: There is some debris and leaves in the bund (Fig. 51.4)

Result of Visual Inspection: Fail

Housekeeping Issues: Debris in bund should be removed. Rusting and discolouration should be monitored.

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 268: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

157

Company: Intel Ireland Ltd Photo/sketch:

See Fig 52.1 – 52.4 Site: Leixlip, Co Kildare

Bund Ref. No.: 52

Bund Location: F24 Middle Yard

Bund Description: Fuel Oil Tank Bund

Bund Dimensions: 12m x 12m x 1.3mH

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume: 75 m3 x 3 = 225m

3

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 82.5m3

Bund Retention Volume: 158.48m3 Vessel(s) –

25% of Total Storage Volume: 56.25m3

Tank Contents:

Bund containing Fuel Oil Tank, fuel oil delivery pumps, generator fuel oil pumps and boiler fuel oil pumps

R Phrase (WGK Class): R40, WGK2

Contents: High Risk Condition: Poor in

areas

Action: Remedial action plus hydrostatic testing

(where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Grade slab with tall upstand all around. Bund appears to be generally intact – no visible cracks or leaks (Fig. 52.1). Liquid retention in bunds which is reducing retention capacity. Floor appears discoloured from the rusting and moss growth.

Bund Drainage System: Local bunding - Bottom outlet valve on bund.

General Observations: There is some debris in the bund (Fig. 52.3). There is no grate on the sump. The labelling at the front of the bund has faded (Fig. 52.2).

Result of Visual Inspection: Pass

Housekeeping Issues: Debris in bund should be removed.

Action Required:

Tanks require labelling to ensure that the correct chemicals are filled into each tank during refilling and also to ensure that appropriate handling procedures are undertaken in the event of a spill.

Bunds require regular emptying to ensure required storage capacity for spills/leaks.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Bund Ref. No.: 52

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 15/2/11

Length of test: 24hrs

Measurement at beginning of test: 120mm

Measurement at end of test: 120mm

Volume Tested to: 25m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Eamonn McIvor Title: Engineering Owner

Page 269: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

158

Company: Intel Ireland Ltd Photo/sketch:

See Fig 48.1 – 48.4 Site: Leixlip, Co Kildare

Bund Ref. No.: 48

Bund Location: F24 West Yard

Bund Description: Sodium Hydroxide Fab

Scrubber Day Tank

Bund Dimensions: Complex dimensions

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: Unknown Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents:

Sodium Hydroxide (NaOH)

R Phrase (WGK Class):

R21,22

WGK 1, R35

Contents: Low Risk Condition: Poor in areas Action: Remedial action plus re-inspection

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Grade slab with low bund wall all around and plexiglas screen all around. Bund appears to be generally intact – no visible cracks or leaks (Fig. 48.1). The splash guard near the safety shower is broken and needs to be replaced (Fig. 48.2). There is some discolouration on the bund floor i.e. moss.

Bund Drainage System: Local bunding - Bottom outlet valve on bund. Trenches along outside of bund.

General Observations: There is some debris in the bund (Fig. 48.4). Some pipework appears to be broken.

Result of Visual Inspection: Pass

Housekeeping Issues:

Debris/piping in bund should be removed.

Action Required:

Splash guard around the bund needs to be fixed and the general house keeping in this bund needs to be improved. Determine bund retention volume.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 270: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

159

Company: Intel Ireland Ltd Photo/sketch:

See Fig 68.1 – 68.4 Site: Leixlip, Co Kildare

Bund Ref. No.: 68

Bund Location: NH4W Treatment Bund

Bund Description: Ammonia Waste (NH4W)

Treatment Bund

Bund Dimensions: Complex dimensions

Vessel(s) –

Materials of Construction: FRP

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume:

High pH Drain Lift Tank (1 in No.): 0.7m3

Low pH Drain Lift Tank (1 in No.):1.4m3

NH4W Treatment Collection Tanks: 76.8m3 x 2 = 153.6m3

Total = 155.7m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 84.5 m3

Bund Retention Volume: 422.4m3 Vessel(s) –

25% of Total Storage Volume: 38.925 m3

Tank Contents:

<10% NH3, <8% H2O2, NaOH

30-40% (NH4)2SO2

Ammonia wastewater

R Phrase (WGK Class):

R36/37/38 ,

R36/37/38

WGK 2

Contents: High Risk Condition: Poor in areas Action: Remedial action plus hydrostatic testing

(where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons: Cannot be hydrostatically tested as

the trench drains to the hi/lo pH tank sump and this equipment cannot be submerged

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Grade slab with upstand all around. Trench enters below floor level but pipes entering in the trench are cast into a dividing wall. Bund appears to be generally intact – no visible cracks or leaks (Fig. 68.1). There is also some discolouration from moss growth in the bund and some water retention for recent rainfall.

Bund Drainage System: Local Bund - For both tanks there is an auto capability options to collection tanks and AWN

General Observation: There is maintenance works in process in this bund on one of the pumps and the bund has been gritted (Fig. 68.2). There are also boxes in the bund (Fig. 68.3). There is some discolouration in the bund (Fig 68.4).

Result of Visual Inspection: Pass

Housekeeping Issues:

Debris/absorbent mat beside low pH drain lift tanks should be removed from grate. The bund needs to be cleaned.

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 271: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

160

Company: Intel Ireland Ltd Photo/sketch:

See Fig 71.1 – 71.4 Site: Leixlip, Co Kildare

Bund Ref. No.: 71

Bund Location: Scrubber Bund/Stock Room

Roof

Bund Description: F24 Bridge Scrubbers

Bund Dimensions: Complex dimensions

Vessel(s) –

Materials of Construction: Metal Scrubbers: FRP

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume: 1.3m3 x 4 = 5.2m

3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 1.4 m3

Bund Retention Volume:

11.87 m3

Vessel(s) –

25% of Total Storage Volume: 1.3m3

Tank Contents:

Sodium Hydroxide

Ammonia

R Phrase (WGK Class):

WGK 1,

R35, WGK 2

Contents: High Risk Condition: Poor in

areas

Action: Remedial action plus hydrostatic testing

(where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Significant rust in bund could lead to eventual leaks; see Figure 71.2 (Between Scrubbers #3 and #4). There is also moss growth on the base of the bund (Fig. 71.3).

Bund Drainage System: Bund is free draining.

General Observation: There is some piping under the sodium hydroxide tank that should be removed (Fig. 71.4). There is also a ladder and cabling loose on the floor of the bund.

Result of Visual Inspection: Fail

Housekeeping Issues:

Tank is very dirty and there is debris in bottom of bund.

Action Required:

Rusting should be monitored and the bund cleaned.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 272: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

161

Company: Intel Ireland Ltd Photo/sketch:

See Fig 53.1 – 53.3 Site: Leixlip, Co Kildare

Bund Ref. No.: 53

Bund Location: HPM Roof

Bund Description: F24 Gas Pad Scrubbers

Bund Dimensions: 5.1m x 8m x 0.65mH

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: 26.52m3 Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents:

Acid Scrubbers

R Phrase (WGK Class): Assumed Low risk

Contents: Assumed Low risk Condition: Poor in

areas

Action: Remedial action plus re-inspection

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Bund is a little wet with no visible cracks however bund drains into a drainage sump in floor (Fig. 53.3). Bund is in good condition although there is some discolouration near the drainage sump.

Bund Drainage System: Unknown – Intel to confirm.

Result of Visual Inspection: Pass

Housekeeping Issues:

Debris should be removed from bund (loose cables, spade and piping) (Fig. 53.2).

The bund is also very dirty.

Action Required:

Discolouration should be monitored and the bund cleaned.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 273: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

162

Company: Intel Ireland Ltd Photo/sketch:

See Fig 49.1 – 49.4 Site: Leixlip, Co Kildare

Bund Ref. No.: 49

Bund Location: West Yard Scrubber Bund

Bund Description: F24 Fab (west) Scrubbers

(4No.)

Bund Dimensions: Complex dimensions Vessel(s) –

Materials of Construction: FRP

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume: 1.3 x 4 = 5.2m3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 1.4 m3

Bund Retention Volume:

11.87m3

Vessel(s) –

25% of Total Storage Volume: 1.3m3

Tank Contents:

Acid Scrubbers

R Phrase (WGK Class): Assumed Low risk

Contents: Assumed Low risk Condition: Poor in

areas

Action: Remedial action plus re-inspection

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: No visible cracks or leaks internally. Some discolouration on bund floor (Fig. 49.4). This room contains individual tanks with self contained bunds.

Bund Drainage System: Trenches along middle of floor of bunded room.

General Observations: Drums stacked in corner, no labelling on these (Fig. 49.2).

Result of Visual Inspection: Pass

Housekeeping Issues:

Debris should be removed from bund (Fig. 49.3).

Action Required:

Ensure all containers are clearly labelled.

Monitor discolouration on bund floor.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 274: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

163

Company: Intel Ireland Ltd Photo/sketch:

See Fig 50.1 – 50.3 Site: Leixlip, Co Kildare

Bund Ref. No.: 50

Bund Location: F24 Subfab - west

Bund Description: F24 Subfab Emergency

Generator bund

Bund Dimensions: Complex dimensions

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume: 6 x generators (6 x 1m3 day tanks

fed by 3 x 75m3 tanks) = 231m

3

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 1.1m3

Bund Retention Volume: 6m3

Vessel(s) –

25% of Total Storage Volume: 1.5m3

Tank Contents:

Diesel

R Phrase (WGK Class): R40, WGK2

Contents: High Risk Condition: Poor in

areas

Action: Remedial action plus hydrostatic testing

(where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09

Bund & Tank Integrity: Bund appears to be generally intact however the floor of the bund is in very poor condition i.e. cracks (Fig. 50.3). Leak under generator EO15 and EO16. There is also a crack on the back wall.

Bund Drainage System: Trenches along back wall behinds the generators – Local bund.

Result of Visual Inspection: Fail

Housekeeping Issues:

Debris should be removed from bund.

Action Required:

The bund floor and crack on wall should be repaired. The room should be inspected for further deterioration on a regular basis.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 275: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

164

Bund ID: F24 Generator Subfab Diesel Bund

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 15/2/11

Length of test: 24hrs

Measurement at beginning of test: 120mm

Measurement at end of test: 120mm

Volume Tested to: 1.2m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Eamon McIvor Title: Engineering Owner

Page 276: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

165

Company: Intel Ireland Ltd Photo/sketch:

See Fig 69.1 – 69.3 Site: Leixlip, Co Kildare

Bund Ref. No.: 69

Bund Location: F24 Middle Yard

Bund Description: F24 Ammonia Scrubbers

Bund Dimensions: Complex dimensions

Vessel(s) –

Materials of Construction: Metal/Plastic

Bund Materials of Construction: Concrete Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume:

5.92m3

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents:

Ammonia

R Phrase (WGK Class): WGK 2

Contents: High Risk Condition: Poor in

areas

Action: Remedial action plus hydrostatic testing

(where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally. There is also some discolouration from moss growth/rust in the bund (Figure 69.2). Liquid retention in bund (rainwater) which is reducing retention capacity. There appears to be some areas where the CRC coating needs to be recoated (Figure 69.3).

Bund Drainage System: The bund is free draining into the adjacent bund (Bund 68).

Result of Visual Inspection: Fail

Housekeeping Issues: None

Action Required:

Rusting should be monitored and the bund cleaned.

Investigate if CRC coating needs to be fixed.

Need to compare the capacity of the combined bund with the vessel volume.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 277: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

166

Bund ID: Bund Ref. No.: 69

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 02/02/2011

Length of test: 24 hrs

Measurement at beginning of test: 110mm

Measurement at end of test: 110mm

Volume Tested to: m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: PP. Padraig McLoughlin Title: Engineering Owner

Page 278: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

167

Company: Intel Ireland Ltd Photo/sketch:

See Fig 70.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 70

Bund Location: Corrosive Room B1M01/Stock

Room

Bund Description: Corrosives

Bund Dimensions: Complex dimensions

Vessel(s) –

Materials of Construction: Various metal drums and plastic

containers

Bund Materials of Construction:

Concrete/room

Vessel(s) –

Total Storage Volume:

Bund Lining Material: CRC coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: 12.8m3

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents:

Corrosives substances including Sulphuric acid

R Phrase (WGK Class): Toxic and Corrosive

R35, WGK 2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

96% H2SO4 is a stand alone chemical with no standby, cannot do without Fab impact of ~36- 48 hrs as it feeds the ammonia scrubbers

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Bund appears in good condition – no visible cracks or leaks. Bottom of the bund and ground around are dry.

Bund Drainage System: Local bund - Raised floor made of grating and the coving higher than grating.

Result of Visual Inspection: Pass

Housekeeping Issues:

The bund floor consists of green grate mats and appears very dirty.

Action Required:

The bund should be cleaned.

Ensure all containers are clearly labelled.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 279: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

168

Company: Intel Ireland Ltd Photo/sketch:

See Fig 70.1 – 70.5 Site: Leixlip, Co Kildare

Bund Ref. No.: 70a

Bund Location: Stock Room Level 1

Bund Description: Solvents & Refrigerated

Solvents

Bund Dimensions: Complex dimensions

Vessel(s) –

Materials of Construction: Various metal drums and plastic

containers

Bund Materials of Construction:

Concrete/room

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: 5.6m3

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents:

Solvents including:

acetone

N-methyl-2-pyrrolidone

R Phrase (WGK Class):

R11, R36, R66, WGK 1

R61, R36/37/38 WGK 1

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Testing would involve impact to fab operations, to be scheduled during shutdown

Result of Hydrostatic Test:

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Bund appears in good condition – no visible cracks or leaks. Bottom of the bund and ground around are dry.

Bund Drainage System: Local bund - Raised floor made of grating and coving is at a higher level than the grating.

Result of Visual Inspection: Pass

Housekeeping Issues:

The bund floor consists of green grate mats and appears very dirty.

Action Required:

The bund should be cleaned.

Ensure all containers are clearly labelled.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 280: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

169

Company: Intel Ireland Ltd Photo/sketch:

See Fig 55.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 55

Bund Location: HPM Area (Entrance behind

caged area, F24 middle yard)

Bund Description: Aqueous Room

Bund Dimensions: Complex dimensions

Vessel(s) –

Materials of Construction: Various drums and plastic

containers

Bund Materials of Construction:

Concrete/room

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents:

Aqueous Room (53 in No.) including copper/lead

R Phrase (WGK Class): Corrosives, WGK 2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Testing would involve impact to fab operations, to be scheduled during shutdown

Result of Hydrostatic Test:

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Bund appears in good condition – no visible cracks or leaks. Bottom of the bund and ground around are dry.

Bund Drainage System: Local bund - Room with wide trench perimeter, finger trenches and coving.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 281: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

170

Company: Intel Ireland Ltd Photo/sketch:

See Fig 55.1 – 55.5 Site: Leixlip, Co Kildare

Bund Ref. No.: 55a

Bund Location: HPM Area (Entrance behind

caged area, F24 middle yard)

Bund Description: Chemical Store

Bund Dimensions: Complex dimensions

Vessel(s) –

Materials of Construction: Various drums and plastic

containers

Bund Materials of Construction:

Concrete/room

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents:

Chemical Store (19 in No.) including copper/lead

R Phrase (WGK Class): WGK 2, R36, R33 Corrosive and

Toxic

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Testing would involve impact to fab operations, to be scheduled during shutdown

Result of Hydrostatic Test:

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: The bund appears in good condition – no crack visible and ground around is dry.

Bund Drainage System: Local bund - The bund is a room with grated trenches around the storage area.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 282: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

171

Company: Intel Ireland Ltd Photo/sketch:

See Fig 57.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 57

Bund Location: HPM Area (Entrance behind

caged area, F24 middle yard)

Bund Description: Heavy Metals

Bund Dimensions: Complex dimensions

Vessel(s) –

Materials of Construction: Various drums and plastic

containers

Bund Materials of Construction:

Concrete/room

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents:

Heavy Metals (14 in No.) including lead and copper

R Phrase (WGK Class): R36, R33, Corrosive and Toxic,

WGK 2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Testing would involve impact to fab operations, to be scheduled during shutdown

Result of Hydrostatic Test:

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Bund appears in good condition – no visible cracks or leaks. Bottom of the bund and ground around are dry.

Bund Drainage System: Local bund - Room with wide trench perimeter, finger trenches and coving.

Result of visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 283: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

172

Company: Intel Ireland Ltd Photo/sketch:

See Fig 56.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 56

Bund Location: HPM Area (Entrance behind

caged area, F24 middle yard)

Bund Description: Lead Room

Bund Dimensions: Complex dimensions

Vessel(s) –

Materials of Construction: Various drums and plastic

containers

Bund Materials of Construction:

Concrete/room

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: 41m3

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents:

Lead

R Phrase (WGK Class): R36, R33 Corrosive and Toxic,

WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Lift station present, cannot test bund

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Bund appears in good condition – no visible cracks or leaks. Bottom of the bund and ground around are dry.

Bund Drainage System: Local bund - Raised floor made of grating and the coving is higher than the grating.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 284: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

173

Company: Intel Ireland Ltd Photo/sketch:

See Fig 56a.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 56a

Bund Location: HPM Area (Entrance behind

caged area, F24 middle yard)

Bund Description: Copper Room

Bund Dimensions: Complex dimensions

Vessel(s) –

Materials of Construction: Various drums and plastic

containers

Bund Materials of Construction:

Concrete/room

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: 69m3

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents:

Copper interconnect plating solution containing Sulphuric acid and copper sulphate

R Phrase (WGK Class): WGK 3, R35,

R36/38, R51/53

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Lift station present, cannot test bund

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Bund appears in good condition – no visible cracks or leaks. Bottom of the bund and ground around are dry.

Bund Drainage System: Local bund - Room where any spills drain to trenches along the entire floor.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 285: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

174

Company: Intel Ireland Ltd Photo/sketch:

See Fig 54.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 54

Bund Location: HPM Area (Entrance behind

caged area, F24 middle yard)

Bund Description: Solvents Room

Bund Dimensions: Complex dimensions

Vessel(s) –

Materials of Construction: Various drums and plastic

containers

Bund Materials of Construction:

Concrete/room

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: 65.9m3

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents: Various harmful and corrosive

substances

Isopropanol

R Phrase (WGK Class): Assumed high risk as other

chemicals in room could potentially have high risk.

R11 R36 R67 WGK 1

Contents: Assume High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

The F24 solvent room is a designated ATEX area. The room its self is classified as Zone 2 but the trenches are classified as Atex Zone 1.

The liquid leak cables located in the trenches are part of the explosion protection plan and are connected to LSS. Loss of the LSS leak detection for a period of time (>24hrs) is a risk and would not be in line with the site explosion protection plan. Working in the trench (an ATEX zone one location) while the pumpers in the room are operational would also result in an increased safety risk faced by the worker.

(Zone one: A place where a flammable atmosphere is likely to occur in normal operation occasionally)

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Room with CRC coating on floor and coving to walls. The bund appears in good condition – no visible cracks or leaks and ground around are dry.

Bund Drainage System: Local bund - Room where any spills drain to trenches along middle of floor.

Result of Visual Inspection: Pass

Housekeeping Issues: Remove absorbent material from under bund grate in trenches.

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 286: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

175

Company: Intel Ireland Ltd Photo/sketch:

See Fig 84.1 – 84.3 Site: Leixlip, Co Kildare

Bund Ref. No.: 84

Bund Location: F24-2

Bund Description: F24-2 Acid Scrubbers

Bund Dimensions: Complex dimensions

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction: Concrete

Vessel(s) –

Total Storage Volume: Unknown

Bund Lining Material: CRC coating

Vessel(s) –

110% of Volume of Largest Vessel: Unknown

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: Unknown

Tank Contents:

Acid Scrubbers

R Phrase (WGK Class): Assumed low risk

Contents: Assume Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09

Bund & Tank Integrity: Bund appears in good condition – no visible cracks or leaks (Fig. 84.1). Some water retention in the bund from recent rainfall and the sump is full waste (Fig. 84.2).

Bund Drainage: In the event of a spill bund would be pumped out. This bund is located outside so is exposed to rainfall.

General Observation: Broken piping near sump and a stack of non slip mats should be removed. The grate is also rusted (Fig. 84.3).

Result of Visual Inspection: Pass

Housekeeping Issues: Debris in base of bund. This should be removed.

Action Required:

Cleaning of bund and bund requires regular emptying to ensure required storage capacity for spills/leaks. Determine bund retention volume.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 287: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

176

Company: Intel Ireland Ltd Photo/sketch:

See Fig 100.1 – 100.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 100

Bund Location: F24 North Chemical Dock

Bund Description: : F24 North Chemical Dock

Bund Dimensions: Complex dimensions

Vessel(s) –

Materials of Construction: None

Bund Materials of Construction: concrete

Vessel(s) –

Total Storage Volume: No vessels in bund

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: No vessels in bund

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: No vessels in bund

Tank Contents:

Chemical IBC Storage:

Sodium Bisulphite 25% (1000L)

Biomate MBC781 (220L)

Biomate MBC2881E (220L)

R Phrase (WGK Class): No vessels in bund but bund is

potentially high risk

R22, R31 WGK 1

R8, R34, R43, R23/24/25, R36/38, R50/53, R52,53 (WGK3)

R38, R41, R43, R50, R23/25, R20/22 (WGK3)

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09

Bund & Tank Integrity: Bund appears in good condition – no visible cracks or leaks (Fig. 100.1). There were no chemicals at this location during the inspection. It is used as a temporary chemical storage bund. The bund is sloped to a gully along the side of the bund; this is blocked with mud and leaves (Fig. 100.2).

Bund Drainage: Local Bund - Floor with trenches, bund sloped in towards trenches and manually pumped to AWN

Result of Visual Inspection: Pass

Housekeeping Issues: Unblock gully along the edge of the bund and wash the bund down to remove the mud.

Action Required: Determine bund retention volume.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 288: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

177

Company: Intel Ireland Ltd Photo/sketch:

See Fig 140.1 – 140.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 140

Bund Location: F24 West Scrubber dosing –

Chemical store (PCW/CPCW)

Bund Description: Nalco 2536+(Tank no.

SN907025)

Bund Dimensions: 1.2 x 0.8 x 0.4m = 0.384m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 260L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 286L

Bund Retention Volume: 384L

Vessel(s) –

25% of Total Storage Volume: 65L

Tank Contents: Sodium Nitrite

R Phrase (WGK Class): R22, R52, WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Testing would involve impact to fab operations, to be scheduled during shutdown

Result of Hydrostatic Test:

Description and Results of Visual Inspection: Date of Visual Inspection: 18/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: There is a grate inside the room where the bund is stored and outside the bund, this is

full of water and should be pumped out.

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 289: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

178

Company: Intel Ireland Ltd Photo/sketch:

See Fig 141.1 – 141.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 141

Bund Location: F24 West Scrubber dosing –

Chemical store (PCW/CPCw)

Bund Description: Nalco 2510 (Tank no.

SN183583)

Bund Dimensions: 1.2 x 0.9 x 0.55m = 0.59m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 440L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 484L

Bund Retention Volume: 594L

Vessel(s) –

25% of Total Storage Volume: 110L

Tank Contents: 2,2-Dibromo-3-

Nitrilopropionamide

R Phrase (WGK Class): R20/22, R38, R43, R41, WGK3

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Testing would involve impact to fab operations, to be scheduled during shutdown

Result of Hydrostatic Test:

Description and Results of Visual Inspection: Date of Visual Inspection: 18/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 290: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

179

Company: Intel Ireland Ltd Photo/sketch:

See Fig 140.1 – 140.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 142

Bund Location: F24 West Scrubber dosing –

Chemical store SN907004

Bund Description: Nalco 2536 plus (Tank no.

SN907004)

Bund Dimensions: 1.2 x 0.8 x 0.4m = 0.384m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 260L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 286L

Bund Retention Volume: 384L

Vessel(s) –

25% of Total Storage Volume: 65L

Tank Contents: Sodium Nitrite

R Phrase (WGK Class): R22, R52, WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Testing would involve impact to fab operations, to be scheduled during shutdown

Result of Hydrostatic Test:

Description and Results of Visual Inspection: Date of Visual Inspection: 18/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 291: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

180

Company: Intel Ireland Ltd Photo/sketch:

See Fig 113.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 113

Bund Location: NE of site - Adjacent to F24

Fire pump house

Bund Description: F24 Emergency Generator

Diesel tank

Bund Dimensions: TBD

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction: Metal

Vessel(s) –

Total Storage Volume: 5,000L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 5,500L

Bund Retention Volume: 5,500L

Vessel(s) –

25% of Total Storage Volume: 1,250L

Tank Contents:

Diesel

R Phrase (WGK Class): R40, R65, R66, R51, R53

WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: This is a self contained double skinned metal container

Bund Drainage:

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 292: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

181

Company: Intel Ireland Ltd Photo/sketch:

See Fig 114.1 – 114.2 Site: Leixlip, Co Kildare

Bund Ref. No.: 114

Bund Location: NE of site off the North Road

Bund Description: F24 Firewater Pump

House

Bund Dimensions: Large room -

7.25m x 6m x 0.1m = 4.35m3

(4350L)

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction:

Concrete

Vessel(s) –

Total Storage Volume: 280L

Bund Lining Material: CRC coating

Vessel(s) –

110% of Volume of Largest Vessel: 308L

Bund Retention Volume: 4350L

Vessel(s) –

25% of Total Storage Volume: 70L

Tank Contents: Diesel

R Phrase (WGK Class): R40, R65, R66, R51, R53

WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 293: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

182

Company: Intel Ireland Ltd Photo/sketch:

See Fig 115.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 115

Bund Location: F24 Energy Centre (Chiller

room) MTHW - SN183542

Bund Description: Nalco 8539 (Tank

no.SN183542)

Bund Dimensions: 0.9 x 1.2 x 0.55m =

0.594m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 440L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 484L

Bund Retention Volume: 594L

Vessel(s) –

25% of Total Storage Volume: 110L

Tank Contents: Sodium Nitrite & Potassium

Hydroxide

R Phrase (WGK Class): R25, R36/38, R50

WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Bund ID: Bund Ref. No.: 115

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 1/12/10

Length of test: 24 hrs

Measurement at beginning of test: 550mm

Measurement at end of test: 550mm

Volume Tested to: 0.430 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Simon McLain Title: Engineering Owner

Page 294: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

183

Company: Intel Ireland Ltd Photo/sketch:

See Fig 116.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 116

Bund Location: F24 Energy Centre (Chiller

room) Chilled water dosing skid - SN183518

Bund Description: Nalco 2510 (Tank no.

SN183518)

Bund Dimensions: 0.9 x 1.2 x 0.55m =

0.594m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic bund

with splash guard

Vessel(s) –

Total Storage Volume: 440L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 484L

Bund Retention Volume: 594L

Vessel(s) –

25% of Total Storage Volume: 110L

Tank Contents: 2,2-Dibromo-3-

nitrilopropionamide

R Phrase (WGK Class): R20/22, R38, R43, R41

WGK3

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 295: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

184

Bund ID: Bund Ref. No.: 115

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 1/12/10

Length of test: 24 hrs

Measurement at beginning of test: 550mm

Measurement at end of test: 550mm

Volume Tested to: 0.430 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Simon McLain Title: Engineering Owner

Page 296: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

185

Company: Intel Ireland Ltd Photo/sketch:

See Fig 116.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 117

Bund Location: F24 Energy Centre (Chiller

room) Chilled water dosing skid

Bund Description: Nalco 8539 (Tank no.

SN183536)

Bund Dimensions: 0.9 x 1.2 x 0.55m =

0.594m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 440L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 484L

Bund Retention Volume: 594L

Vessel(s) –

25% of Total Storage Volume: 110L

Tank Contents: Sodium Nitrite & Potassium

Hydroxide

R Phrase (WGK Class): R25, R36/38, R50

WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 297: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

186

Bund ID: Bund Ref. No.: 117

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 1/12/10

Length of test: 24 hrs

Measurement at beginning of test: 550mm

Measurement at end of test: 550mm

Volume Tested to: 0.430 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Simon McLain Title: Engineering Owner

Page 298: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

187

Company: Intel Ireland Ltd Photo/sketch:

See Fig 118.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 118

Bund Location: F24 Energy Centre (Chiller

room) Heat recovery System

Bund Description: Nalco 2510 (Tank no.

SN9075487)

Bund Dimensions: 0.9 x 1.2 x 0.55m =

0.594m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic bund

with splash guard

Vessel(s) –

Total Storage Volume: 440L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 484L

Bund Retention Volume: 594L

Vessel(s) –

25% of Total Storage Volume: 110L

Tank Contents: 2,2-Dibromo-3-

nitrilopropionamide

R Phrase (WGK Class): R20/22, R43, R41

WGK3

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 299: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

188

Bund ID: Bund Ref. No.: 118

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 1/12/10

Length of test: 24 hrs

Measurement at beginning of test: 550mm

Measurement at end of test: 550mm

Volume Tested to: 0.430 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Simon McLain Title: Engineering Owner

Page 300: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

189

Company: Intel Ireland Ltd Photo/sketch:

See Fig 118.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 119

Bund Location: F24 Energy Centre (Chiller

room) Heat recovery System

Bund Description: Nalco 8539 (Tank no.

SN907503)

Bund Dimensions: 0.9 x 1.2 x 0.55m =

0.594m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 440L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 484L

Bund Retention Volume: 594L Vessel(s) –

25% of Total Storage Volume: 110L

Tank Contents: Sodium Nitrite & Potassium

Hydroxide

R Phrase (WGK Class): R25, R36/38, R50

WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 301: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

190

Bund ID: Bund Ref. No.: 119

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 1/12/10

Length of test: 24 hrs

Measurement at beginning of test: 550mm

Measurement at end of test: 550mm

Volume Tested to: 0.430 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Simon McLain Title: Engineering Owner

Page 302: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

191

Company: Intel Ireland Ltd Photo/sketch:

See Fig 120.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 120

Bund Location: F24 Energy Centre (Chiller

room) Cooling Tower Dosing

Bund Description: Nalco 93033 (Tank no.

SN90381)

Bund Dimensions: N/A

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic with

splash guard

Vessel(s) –

Total Storage Volume: 750L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 825L

Bund Retention Volume: 825L

Vessel(s) –

25% of Total Storage Volume: 187.5L

Tank Contents: Sodium Hypochlorite

R Phrase (WGK Class): R34, R31

WGK 2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Testing would involve impact to fab operations, to be scheduled during shutdown

Result of Hydrostatic Test:

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 303: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

192

Company: Intel Ireland Ltd Photo/sketch:

See Fig 120.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 121

Bund Location: F24 Energy Centre (Chiller

room) Cooling Tower Dosing

Bund Description: Nalco 3DT249 (Tank no.

SN183663)

Bund Dimensions: 0.9 x 1.2 x 0.55m =

0.594m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 440L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 484L

Bund Retention Volume: 594L

Vessel(s) –

25% of Total Storage Volume: 110L

Tank Contents: Methanol & Sodium

Formaldehyde Bisulfite

R Phrase (WGK Class): WGK 2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Testing would involve impact to fab operations, to be scheduled during shutdown

Result of Hydrostatic Test:

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 304: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

193

Company: Intel Ireland Ltd Photo/sketch:

See Fig 120.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 122

Bund Location: F24 Energy Centre (Boiler

room) Cooling Tower Dosing

Bund Description: Sulphuric Acid

Bund Dimensions: Metal with splash guard

Vessel(s) –

Materials of Construction: Metal

Bund Materials of Construction: Metal

Vessel(s) –

Total Storage Volume: 1500L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 1650L

Bund Retention Volume: 1650L

Vessel(s) –

25% of Total Storage Volume: 375L

Tank Contents: Sulphuric Acid

R Phrase (WGK Class): R35, WGK 2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test:

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 305: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

194

Company: Intel Ireland Ltd Photo/sketch:

See Fig 123.1 – 123.3 Site: Leixlip, Co Kildare

Bund Ref. No.: 123

Bund Location: F24 Subfab – PVAC Dosing

Skid

Bund Description: Nalco 8539 (Tank no.

SN183590)

Bund Dimensions: 0.9 x 1.2 x 0.55m =

0.594m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 440L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 484L

Bund Retention Volume: 594L

Vessel(s) –

25% of Total Storage Volume: 110L

Tank Contents: Sodium Nitrite & Potassium

Hydroxide

R Phrase (WGK Class): R25, R36/38, R50

WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Testing would involve impact to fab operations, to be scheduled during shutdown

Result of Hydrostatic Test:

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 306: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

195

Company: Intel Ireland Ltd Photo/sketch:

Site: Leixlip, Co Kildare

Bund Ref. No.: 124

Bund Location: F24 Subfab – PVAC Dosing

Skid

Bund Description: Nalco 2510 (Tank no.

SN183664)

Bund Dimensions: 0.9 x 1.2 x 0.55m = 0.594m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic bund

with splash guard

Vessel(s) –

Total Storage Volume: 440L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 484L

Bund Retention Volume: 594L

Vessel(s) –

25% of Total Storage Volume: 110L

Tank Contents: 2,2-Dibromo-3-nitrilopropionamide

R Phrase (WGK Class): R20/22, R43, R41

WGK3

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Testing would involve impact to fab operations, to be scheduled during shutdown

Result of Hydrostatic Test:

Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 307: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

196

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Company: Intel Ireland Ltd Photo/sketch:

Figure 151.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 151

Bund Location: F24 UPW

Bund Description: Nalco ST40 (Tank no.

SN70811)

Bund Dimensions: 0.6 x 1.2 x 1.65m = 1.188 m3

Vessel(s) –

Materials of Construction: Metal Tanks

Bund Materials of Construction: Metal bund with

splash guard

Vessel(s) –

Total Storage Volume: 800L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 880L

Bund Retention Volume: 1188L

Vessel(s) –

25% of Total Storage Volume: 200L

Tank Contents: Sodium Hydroxide, Alkaline Liquid

Bromide, Antimicrobial

R Phrase (WGK Class): R34, R31, WGK2

Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? Yes / No

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: See below

Description and Results of Visual Inspection: Date of Visual Inspection: 12/8/2009

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required:

Signed: Ann Marie Keane

Title: Environmental Consultant Date: 21/9/2009

Page 308: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

197

Bund ID: F24 ST 40 Ref. 151

Result of Hydrostatic Test: Pass

Date of hydrostatic Test: 04/11/10

Length of test: hrs 9

Measurement at beginning of test: 114 mm

Measurement at end of test: 114 mm

Volume Tested to: 0.22 m3

Signed: Renaith Lyons Title: Environmental Engineer

Signed: Thomas Brennan Title: Engineering Owner

Page 309: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

198

Company: Intel Ireland Ltd Photo/sketch:

Figure 152.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 152

Bund Location: F24 UPW

Bund Description: Nalco 2584 (Tank no.

CT003384)

Bund Dimensions: 1 x 1.2 x 0.4m = 0.48m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 300L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 330L

Bund Retention Volume: 480L

Vessel(s) –

25% of Total Storage Volume: 75L

Tank Contents: Sodium Hydroxide, Potassium

Hydroxide

R Phrase (WGK Class): R35

WGK1

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 12/8/2009

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: None

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 310: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

199

Company: Intel Ireland Ltd Photo/sketch:

Figure 153.1 Site: Leixlip, Co Kildare

Bund Ref. No.: 153

Bund Location: F24 UPW

Bund Description: Permaclean PC-33 (Tank no.

CT003384)

Bund Dimensions: 1 x 1.2 x 0.4m = 0.48m3

Vessel(s) –

Materials of Construction: Plastic

Bund Materials of Construction: Plastic

Vessel(s) –

Total Storage Volume: 300L

Bund Lining Material: None

Vessel(s) –

110% of Volume of Largest Vessel: 330L

Bund Retention Volume: 480L

Vessel(s) –

25% of Total Storage Volume: 75L

Tank Contents: Tetrasodium EDTA, Sodium

Hydroxide

R Phrase (WGK Class): R36/38, WGK1

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 12/8/2009

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: If leak occurs the bund is manually pumped out and cleaned

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: None

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 311: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

200

Company: Intel Ireland Ltd Photo/sketch:

N/A Site: Leixlip, Co Kildare

Bund Ref. No.: 162

Bund Location: F24 PCD Storage Room 2

Bund Description: F24 PCD - Planar Chemical

Distribution

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Plastic totes & drums

Bund Materials of Construction: N/A

Vessel(s) –

Total Storage Volume: 10,000L

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 1387L

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: 2500L

Tank Contents:

C8800 Slurry

Silica

CMP Cleaner, PSC (Semi Conductor Processing)

Hydrogen Peroxide

MSC Ultralift

CMP Slurry PL7107

Silica gel

R Phrase (WGK Class):

WGK1, Low Risk

R5, R8, R35 , WGK1

WGK1

WGK1

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 16/9/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: Bund drainage unknown, room appears to slope into the middle of the room and open drain located at lowest points.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: Determine bund retention volume.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 312: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

201

Company: Intel Ireland Ltd Photo/sketch:

N/A Site: Leixlip, Co Kildare

Bund Ref. No.: 163

Bund Location: F24 PCD Storage Room 1

(B1JO1A)

Bund Description: F24 PCD - Planar Chemical

Distribution

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Plastic totes & drums

Bund Materials of Construction: N/A

Vessel(s) –

Total Storage Volume: 17,500L

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 1387L

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: 4375L

Tank Contents:

Cu20K – 64

Silca

Potassium Hydroxide

PL4217 Oxide Slurry

Silica, Amorphous

Potassium hydroxide

ASD (Tizox CMP Slurry)

Cerium Oxide

L-Proline

Semi Sperse W200B

CMP Slurry PL7107

Silica gel

PSC – Hydrogen Peroxide

3900RS – Silca Polish

Dynasylon HB-330

R Phrase (WGK Class):

WGK1

WGK 1, R22, R35

Not classed under the EU legislation but assume low risk as silca is relatively inert

WGK 1, R22, R35

WGK1

R43

Not classed under the EU legislation but assume low risk as silca is relatively inert

WGK1

WGK 1, R5, R8, R20/22, R35

WGK1

WGK1, R36/38 – not a hazardous substance according to EC-directives 67/548/EEC or 1999/45/EC

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 16/9/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: This bund has trenches running throughout the room, if a spill occurs it drains into these trenches, and then drains to the AWN.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: Determine bund retention volume.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 313: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

202

Company: Intel Ireland Ltd Photo/sketch:

N/A Site: Leixlip, Co Kildare

Bund Ref. No.: 164

Bund Location: F24-1 Pump Room (PCD

Room)

Bund Description: F24-1 PCD - Planar

Chemical Distribution

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Plastic totes & drums

Bund Materials of Construction: N/A

Vessel(s) –

Total Storage Volume: 15,075L

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 1387L

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: 3768.75L

Tank Contents:

Copper Ready (CU3264)

Tizox CMP

Cerium Oxide

Proline, L-

Glanzox 3900

Ammonia

PL4217 Oxide Slurry

Silica, Amorphous

Potassium hydroxide

Cu20K – 64

Silca

Potassium Hydroxide

Dynasylon HB-330

R Phrase (WGK Class):

Not classed under the EU legislation

WGK1

R43

R20, R36/37/38 WGK1

Not classed under the EU legislation but assume low risk as silca is relatively inert

WGK 1, R22, R35

WGK1

WGK 1, R22, R35

WGK1, R36/38 – not a hazardous substance according to EC-directives 67/548/EEC or 1999/45/EC

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 16/9/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: This bund has trenches running throughout the room, if a spill occurs it drains into these trenches, and then drains to the AWN. The room is also sloped.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: Determine bund retention volume.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 314: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

DATA SHEET: BUNDING STRUCTURES

203

Company: Intel Ireland Ltd Photo/sketch:

N/A Site: Leixlip, Co Kildare

Bund Ref. No.: 165

Bund Location: F24-2 (E1TO3)

Bund Description: F24 PCD Pump Room

Bund Dimensions: Complex Dimensions

Vessel(s) –

Materials of Construction: Plastic totes & drums

Bund Materials of Construction: N/A

Vessel(s) –

Total Storage Volume: 250L

Bund Lining Material: CRC Coating

Vessel(s) –

110% of Volume of Largest Vessel: 27.5L

Bund Retention Volume: Unknown

Vessel(s) –

25% of Total Storage Volume: 62.5L

Tank Contents:

MSC Ultralift

PL7107 Slurry

Silica gel

Cu20K – 64

Silca

Potassium Hydroxide

Copper Ready (CU3264)

R Phrase (WGK Class):

WGK1

WGK1

WGK1

WGK 1, R22, R35

Not classed under the EU legislation

Contents: Low Risk Condition: Good Action: None

Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No

Deemed practicable/safe to conduct hydrostatic test? N/A

If hydrostatic testing is deemed impracticable or unsafe, state reasons:

Result of Hydrostatic Test: N/A

Description and Results of Visual Inspection: Date of Visual Inspection: 16/9/09

Bund & Tank Integrity: Bund appears in good condition.

Bund Drainage: This bund has trenches running throughout the room, if a spill occurs it drains into these trenches.

Result of Visual Inspection: Pass

Housekeeping Issues: None

Action Required: Determine bund retention volume.

Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009

Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009

Page 315: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Appendix F

Underground Pipe Integrity Test Report

(Fab 24 Process Effluent Lines)

Page 316: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

1

112 Elm Road, Western Industrial Estate, Naas Road, Dublin 12

ph. 01 409 7070, fax 01 456 9293

FAB 24 Process Effluent Lines Remedial Works

and Re-Survey

prepared on behalf of

Intel Ireland Limited

October 2010

Page 317: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

2

PROCESS EFFLUENT DRAIN INTEGRITY TESTING

PROGRAMME

TABLE OF CONTENTS

Page No.

1.0 INTRODUCTION……………………….……………………………….. 2

1.1 SCOPE…………...……………………….……………………………….. 2

1.2 METHODOLOGY……………………….……………………………….. 2

1.3 RESULTS AND DISCUSSION………….……………………………….. 3

2.0 CONCLUSION………………………….……………………………….. 3

3.0 RECOMMENDATIONS……………….……………………………….. 3

4.0 RECORDS……. ………………………………………………………….. 3

Page 318: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

3

EXECUTIVE SUMMARY

In September 2010, Super Drain Limited undertook a routine survey of the Process Effluent Line

from the FAB 24 AWN downstream to the EBT. This work was required in order to fulfil EPA

obligations in relation to maintenance of the environmental infrastructure on site.

The survey highlighted the accumulation of scale in the line, causing obstructions in a number of

areas. The survey was more comprehensive than on previous occasions as all inflow was

switched off- allowing a survey from upstream to downstream tank.

Page 319: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

4

PROCESS EFFLUENT DRAIN INTEGRITY TESTING PROGRAMME

1.0 INTRODUCTION

In September 2010, Super Drain Limited was commissioned to survey the F24 process effluent

line. This document reports on the re-survey and associated works

1.1 SCOPE

This report covers the integrity testing and associated works during the re-survey of the process

effluent line from the F24 AWN to the EBT (Appendix 1).

1.2 METHODOLOGY

1.2.1 CCTV Surveying and Cleaning

The method employed the insertion of a wheeled IBAK mainline camera unit, remotely operated

from a dedicated Underground Survey Camera Vehicle. The camera operator entered the

relevant location codes on the CCTV screen and recorded all footage onto Digital Video Disk

(DVD). This disk is subsequently played through the “Wincan 7” registered drain management

package and this generated a report detailing still-frames and exact observations at precise

distances.

There were a number of areas identified that had considerable deposits of scale. These were

Jetted out and removed by means of high pressure jetting. The drain line was re-surveyed to

confirm all corrective actions had been completed satisfactorily.

1.3 RESULTS AND DISCUSSION

F24 Process Effluent Line

Page 320: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

5

Initial Survey:

Upstream tank to MHPE (Manhole-Process Effluent) 30.

Medium encrustation, 10% cross sectional area loss, water level holding 10%

MHPE 30 downstream to MHPE 29

Obstruction at 11.2 meters, leading to 25% cross sectional area loss, increasing to 40% cross

sectional loss when examined from other side of obstruction

MHPE 29 downstream to MHPE 28

Medium encrustation, 10% cross sectional area loss, water level holding 10%.

MHPE 28 downstream to MHPE 27

Medium encrustation, 10% cross sectional area loss, water level holding 10%, increasing to 20%

cross sectional loss when examined from other side of obstruction.

MHPE 28 downstream to MHPE 27

Medium encrustation, 10% cross sectional area loss, water level holding 10%, increasing to 20%

cross sectional loss when examined from other side of obstruction.

MHPE 27 downstream to MHPE 27a

No encrustation

MHPE 27a downstream to MHPE 26

No encrustation

Resurvey

Upstream tank to MHPE (Manhole-Process Effluent) 30.

No encrustation

MHPE 30 downstream to MHPE 29

No encrustation

Page 321: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

6

MHPE 29 downstream to MHPE 28

No encrustation

MHPE 28 downstream to MHPE 27

No encrustation

MHPE 27 downstream to MHPE 27a

No encrustation

MHPE 27a downstream to MHPE 26

No encrustation

2.0 CONCLUSION

This line is free flowing and structurally sound

3.0 RECOMMENDATIONS

There are no further corrective actions outstanding.

4.0 RECORDS

The detailed reports and DVD‟s have been submitted to the EHS department for review.

____________________

Stephen Carter

Super Drain Limited

Page 322: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

7

Appendix G

Underground Tank Integrity Test Report

(Fab 10 Underground Contained Storm System Tank)

Page 323: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

AD Analytical,

8 Terenure Rd. North,

Terenure,

Dublin 6w.

Phone (353-1-

CONFIDENTIAL REPORT

Client: Intel Ireland,

Leixlip,

Co. Kildare.

Attention: Ms. Renaith Lyons

Commencement Date: 30/09/2010 Report Date: 01/10/2010

TITLE: Tank Integrity Assessment Based on

BRITISH STANDARD B.S. 8007 : 1987

Signed: _______________________

Dr. Alyn Deane

Page 324: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Tank/Sump Integrity Assessment INTEL IRELAND 2010

CONTENTS

1.0 Executive Summary

2.0 Scope

3.0 Survey Methodology

3.1 Monitoring Requirements

3.2 Assessment Techniques

3.3 Reporting

4.0 Discussion

Appendix 1. FAB 10

o Upper Surface Water Tank

Page 325: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Tank/Sump Integrity Assessment INTEL IRELAND 2010

1.0 Executive Summary

AD Analytical was commissioned by Intel Ireland to carry out Tank/Sump testing at their

facility in Leixlip, Co. Kildare. The survey was performed on 30th

September 2010. The

areas included in this study were referenced as follows:

1. Upper FAB 10 Surface Water (SW) Tank

day (where process allowed) in accordance with B.S. 8007:1987 section 9 and The above

Tanks/Sumps were tested for liquid tightness for a full working were found to be in

compliance with the test.

Signed:__________________________

Dr. Alyn Deane

Page 326: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Tank/Sump Integrity Assessment INTEL IRELAND 2010

2

.0 Scope

AD Analytical were contracted by Intel Ireland to carry out Tank/Sump Integrity testing

at their facility in Leixlip, Co. Kildare. The scope of the survey is limited to the

following:

a. Identification and inspection of the Tanks/Sumps.

b. Test the Tanks/Sumps for „liquid tightness‟ as specified in section nine of B.S. 8007:

1987.

c. Reporting and interpretation of the assessment results.

3.0 Survey Methodology

3.1 Monitoring requirements

As part of the ongoing assessment of the Tanks/Sumps on site a test was performed to

determine the integrity of the Tanks/Sumps listed below:

Tank I.D.

1. Upper FAB 10 Surface Water (SW) Tank

3.2 Assessment Techniques

AD Analytical staff visually inspected the Tanks/Sumps in September 2010.

The Tanks/Sumps were filled with clean water to the fill level, marked and monitored for

a full working day where process operations allowed.

After stabilisation, the level of the liquid surface was recorded by means of a

measurement & photograph at regular intervals for the test period.

The dimensions of this tank are:

Length = 5.75m

Breadth = 5.5m

Width = 2.8m

Fill volume = 40.13m3

3.3 Reporting

Page 327: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Tank/Sump Integrity Assessment INTEL IRELAND 2010

A Log for the Tanks/Sumps is reported as follows:

Appendix 1. FAB 10

o Upper FAB 10 Surface Water (SW) Tank.

4.0 Discussion

The criteria used for testing of Tanks, tanks and sumps are as follows:

1. A Tank containing one vessel should have a nominal capacity of 110 % of

the vessel‟s maximum capacity.

2. A Tank containing more than one vessel should have a nominal capacity

of 110% of the largest vessel or 25% of the total capacity of all the

vessels, which ever is the greater.

3. Sumps, built with double skins (i.e. an inner and outer layer) should have

no water in between the two layers.

The Tanks/Sumps, as detailed in previous sections, were allowed stabilise and tested.

During the test period the total permissible dip in level (allowing for evaporation) should

not exceed 1/500th of the average water depth of the full Tank in all cases.

The above indicates, therefore, that the Tanks/Sumps detailed in this report were found

to satisfy a „Test‟ for „Liquid Tightness‟, as described in section nine, B.S. 8007: 1987:

Design of Concrete Structures for the retaining Aqueous Liquids.

Page 328: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Tank/Sump Integrity Assessment INTEL IRELAND 2010

APPENDIX 1

Page 329: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Tank/Sump Integrity Assessment INTEL IRELAND 2010

TANK TESTING

CLIENT : Intel Ireland.

TANK LOCATION: Upper FAB 10 Surface Water (SW) Tank

SURVEY DATE : 30/09/2010

PERSONNEL : Dr. Alyn Deane (AD Analytical)

Renaith Lyons (Intel Ireland)

Monitoring Log:

WATER

LEVEL

EVAPORATION Time PERSONNEL

Fill *1531mm 0mm 15.30** AD/RL

Test 1531mm 0mm 08:30 AD/RL

Test 1531mm 0mm 15.30 AD/RL *measured from the top, total fill depth 1269mm.

**Filled on 29/09/2010

COMMENTS

The Upper FAB 10 Surface Water (SW) Tank was tested in accordance to B.S.

8007 : 1987 (Design of concrete structures for the retaining aqueous liquids:

Section Nine - inspection and testing of the structure).

Conformance to B.S. 8007: 1987 Section 9

Compliant (to 40.13m3)

Page 330: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Tank/Sump Integrity Assessment INTEL IRELAND 2010

Location - The Upper FAB 10 Surface Water (SW) Tank

Photo I.D. – Water Level 8.30

Photo I.D. – Water Level 15.30

Page 331: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Appendix H

Noise Monitoring Report

Page 332: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

_____________________________________

Technical Report Prepared For

Intel Ireland Ltd Collinstown Industrial Estate

Leixlip Co. Kildare

_____________________________________ Technical Report Prepared By

James Mangan AMIOA

_____________________________________

Our Reference

JM/10/5043NR01

____________________________________

Date Of Issue

16 June 2010

_____________________________________

INTEL IRELAND IPPC LICENCE

NOISE SURVEY 2010

Page 333: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

JM/10/5043NR01 AWN Consulting Limited

___________________________________________________________________________________________________

_____________________________________________________________________________________________________

Page 2

EXECUTIVE SUMMARY AWN Consulting has been commissioned to measure environmental noise levels in order to establish the noise climate in the vicinity of the Intel Ireland site in accordance with the appropriate Integrated Pollution Prevention and Control (IPPC) Licence. This document reviews the survey data and presents it in a form suitable for submittal to the Environmental Protection Agency (EPA) as part of Intel‟s Annual Environmental Report (AER). Environmental noise surveys have been carried out at a number of locations around the boundary of the site and at noise sensitive locations in the vicinity of the site. Noise levels were measured during daytime and night-time periods. The survey data has been analysed and it may be concluded that this facility is in compliance with Condition 5 of its IPPC Licence. Report Prepared By: Report Checked By:

JAMES MANGAN DAMIAN KELLY Acoustic Consultant Principal Acoustic Consultant

Page 334: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

JM/10/5043NR01 AWN Consulting Limited

___________________________________________________________________________________________________

_____________________________________________________________________________________________________

Page 3

CONTENTS Page

Executive Summary 2

1.0 Introduction 4

2.0 Survey Details and Measured Noise Levels 5

2.1 Measurement Locations 5

2.2 Survey Periods 5

2.3 Personnel and Instrumentation 6

2.4 Procedure 6

2.5 Measurement Parameters 6

2.6 Survey Results and Comments 7

3.0 Discussions 11

4.0 Conclusions 12

Figure 1 – Noise Measurement Locations 13

Appendix A – Noise Measurement Results 1/3 Octave Band 14

Page 335: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

JM/10/5043NR01 AWN Consulting Limited

___________________________________________________________________________________________________

_____________________________________________________________________________________________________

Page 4

1.0 INTRODUCTION

It is a requirement of the Integrated Pollution Prevention and Control (IPPC) Licence, issued by the Environmental Protection Agency (EPA) and held by Intel Ireland that environmental noise levels in the vicinity of the site are monitored on an annual basis. Condition 5 of the Licence sets out the following requirements in relation to noise:

Condition 5: 5.1 No specified emission from the installation shall exceed the emission

limit values set out in Schedule B: Emission Limits of this licence. There shall be no other emissions of environmental significance.

Schedule B4 pertains to noise and specifies the following limits: B.4. Noise Emissions

Daytime dB(A) LAeq (15 minutes) Night-time dB(A) LAeq (15 minutes)

55Note 1

45Note 1

Note 1: There shall be no clearly audible tonal or impulsive component in the noise emission from the site at any noise sensitive location

Paragraph 4.5 of the Interpretation section of the licence also applies to noise:

4.5 Noise from the installation shall not give rise to sound pressure levels (Leq,T) measured at any noise-sensitive location that exceed the specified limit values by more than 2dB(A).

Daytime is taken as 08:00 to 22:00hrs and night-time 22:00 to 08:00hrs as stated in the EPA publication Guidance Note For Noise In Relation To Scheduled Activities, Second Edition (2006). AWN Consulting has been commissioned to conduct a noise survey in accordance with the EPA‟s requirements in order to establish whether the facility is operating in compliance with the criteria outlined above.

Page 336: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

JM/10/5043NR01 AWN Consulting Limited

___________________________________________________________________________________________________

_____________________________________________________________________________________________________

Page 5

2.0 SURVEY DETAILS AND MEASURED NOISE LEVELS A series of environmental noise surveys were conducted in order to quantify the existing noise environment. The surveys were conducted generally in accordance with ISO 1996: 2007: Acoustics – Description, measurement and assessment of environmental noise. Specific details are set out below.

2.1 Measurement Locations Noise measurements were also conducted at seven positions on the site boundary and at noise-sensitive locations. These positions are the monitoring locations stipulated in the current IPPC Licence for the site. These locations are described below and shown on Figure 1. NM01 Near the mechanical „Middle Gate‟ on the eastern boundary of the site

in line with the north façade of IR3. NM02 On the Confey Road to the north of the site, at the entrance to the Intel

soccer grounds. NM03 At Riverview House. Please note that the noise monitoring position for

the 2009 and 2010 surveys have changed slightly when compared to the location adopted for previous years. For the purposes of the annual IPPC assessment the attended noise monitoring position was moved away from the continuous noise monitor location (which is located in a field approximately 40 metres to the east of the house) and positioned adjacent to the façade of the Riverview property itself. This was done as it was noted by survey personnel that water flow noise from the river, as well as wind generated noise on nearby foliage and road traffic from the M4 motorway, were audible to a greater extent at the continuous monitor location than at the location of the house itself. This gives a more realistic indication as to Intel plant noise emissions at the façade of the house, as opposed to at the location of the continuous noise monitor.

NM04 On the Confey Road to the north of the site, adjacent to the B&B. NM05 At the north-eastern corner of the car-park to the east of Fab24. NM06 At the south-eastern corner of the car-park to the east of Fab24. NM07 At noise-sensitive locations beyond the southern boundary of the site.

2.2 Survey Periods Measurements were conducted over the course of the following survey periods:

Night-time NM01 to NM04: 23:03hrs on 26 May to 02:49hrs 27 May 2010;

Night-time NM05 to NM07: 22:04hrs on 26 May to 01:29hrs 27 May 2010;

Daytime NM01 to NM07: 09:42hrs to 17:13hrs on 26 May 2010.

Page 337: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

JM/10/5043NR01 AWN Consulting Limited

___________________________________________________________________________________________________

_____________________________________________________________________________________________________

Page 6

During all of the survey periods noted above, it is understood that the facility was in normal operation. The weather during daytime survey periods was dry and calm, temperatures were in the range 14 to 18 degrees Celsius, wind speeds were in the range 1 to 4 m/s. The weather during night-time survey periods was dry and calm, temperatures were in the range 5 to 8 degrees Celsius, wind speeds were in the range 1 to 2 m/s.

2.3 Personnel and Instrumentation James Mangan and Louis Smith (AWN) conducted the noise level measurements during all survey periods. The measurements were performed using Brüel & Kjær Type 2260 Modular Precision Sound Analysers. Before and after the survey the measurement apparatus was check calibrated using a Brüel & Kjær Type 4231 Sound Level Calibrator.

2.4 Procedure During each of the day-time and night-time periods, measurements were conducted on a cyclical basis. Sample periods were 15 minutes during both the daytime and night-time surveys. The results were saved to the instrument memory for later analysis where appropriate. Survey personnel noted all primary noise sources contributing to noise build-up.

2.5 Measurement Parameters The boundary survey results are presented in terms of the following five parameters:

LAeq is the equivalent continuous sound level. It is a type of average and is used

to describe a fluctuating noise in terms of a single noise level over the sample period.

LAmax is the instantaneous maximum sound level measured during the sample

period. LAmin is the instantaneous minimum sound level measured during the sample

period.

LA10 is the sound level that is exceeded for 10% of the sample period. It is typically used as a descriptor for traffic noise.

LA90 is the sound level that is exceeded for 90% of the sample period. It is

typically used as a descriptor for background noise.

The “A” suffix denotes the fact that the sound levels have been “A-weighted” in order to account for the non-linear nature of human hearing. All sound levels in this report are expressed in terms of decibels (dB) relative to 2x10-5 Pa.

Page 338: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

JM/10/5043NR01 AWN Consulting Limited

___________________________________________________________________________________________________

_____________________________________________________________________________________________________

Page 7

2.6 Survey Results

2.6.1 Location NM01

Table 1 below presents the noise level measurements at Location NM01.

Time (hrs)

Measured Noise Level, dB re 210-5

Pa

LAeq LAmax LAmin LA10 LA90

09:42 – 09:57 52 66 37 55 42

11:07 – 11:22 50 67 36 54 39

12:27 – 12:42 54 71 34 56 38

23:03 – 23:18 40 56 29 42 31

00:18 – 00:33 37 56 30 39 31

01:38 – 01:53 38 58 30 40 31

Table 1 Noise Level Measurements at Location NM01

During the daytime survey periods, distant road traffic movement on the R148 and Kellystown Lane along with occasional aircraft movements were noted as the primary contributors to the noise build-up. Occasional vehicle movements within the site were also audible as was distant plant noise from the Intel site and wind noise on nearby foliage. Noise levels were in the range 50 to 54dB LAeq and 38 to 42dB LA90. During the night-time survey periods, audible noise sources included distant traffic on surrounding roads and distant plant noise from the Intel site. Noise levels were in the range 37 to 40dB LAeq and of the order of 31dB LA90. During all measurement periods local road traffic movements along Kellystown Lane were paused out as far as possible in order to prevent this source from dominating the measured noise levels.

2.6.2 Location NM02

Table 2 below presents the noise level measurements at Location NM02.

Time (hrs)

Measured Noise Level, dB re 210-5

Pa

LAeq LAmax LAmin LA10 LA90

09:59 – 10:14 48 61 30 53 35

11:26 – 11:41 46 64 30 50 33

12:45 – 13:00 47 69 31 51 35

23:21 – 23:36 37 53 27 39 30

00:40 – 01:55 34 55 28 34 29

01:58 – 02:13 37 50 31 39 33

Table 2 Noise Level Measurements at Location NM02

During the daytime survey periods, distant road traffic movements were noted as the primary contributors to the noise build-up. Birdsong and wind noise on nearby foliage were also noted. Plant noise from the Intel site was inaudible during daytime periods at this location. Noise levels were in the range 46 to 48dB LAeq and 33 to 35dB LA90.

Page 339: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

JM/10/5043NR01 AWN Consulting Limited

___________________________________________________________________________________________________

_____________________________________________________________________________________________________

Page 8

During the night-time survey periods, audible noise sources included distant traffic on surrounding roads and very distant plant noise from the Intel site. Noise levels were in the range 34 to 37dB LAeq and 29 to 33dB LA90. During all measurements local road traffic movements were paused out as far as possible in order to prevent this source from dominating the measured noise levels.

2.6.3 Location NM03

Table 3 below presents the noise level measurements at Location NM03.

Time (hrs)

Measured Noise Level, dB re 210-5

Pa

LAeq LAmax LAmin LA10 LA90

10:19 – 10:34 44 59 33 47 36

11:45 – 12:00 48 66 33 49 38

13:03 – 13:18 46 63 34 49 37

23:58 – 00:13 36 61 30 36 32

01:18 – 01:33 36 48 32 36 34

02:34 – 02:49 40 47 36 41 38

Table 3 Noise Level Measurements at Location NM03

During daytime periods at this location, steady plant noise from the Intel site along with birdsong and distant traffic were the dominant noise sources. Noise levels were in the range 44 to 48dB LAeq and 36 to 38dB LA90. During night-time periods, steady plant noise was again the dominant source of noise. Occasional distant traffic movements were also audible. Noise levels were in the range 36 to 40dB LAeq and 32 to 38dB LA90.

2.6.4 Location NM04

Table 4 below presents the noise level measurements at Location NM04.

Time (hrs)

Measured Noise Level, dB re 210-5

Pa

LAeq LAmax LAmin LA10 LA90

10:45 – 11:00 45 64 31 48 35

12:04 – 12:19 48 66 31 53 36

13:23 – 13:38 46 63 32 50 36

23:39 – 23:54 38 56 29 40 31

00:58 – 01:13 35 61 27 38 28

02:16 – 02:31 39 73 33 38 35

Table 4 Noise Level Measurements at Location NM04

During the daytime survey periods, distant road traffic movements were noted as the primary contributor to the noise build-up. Plant noise from the Intel site was not audible at this location. Birdsong and wind noise on nearby foliage were also noted. Noise levels were in the range 45 to 48dB LAeq and 35 to 36dB LA90.

Page 340: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

JM/10/5043NR01 AWN Consulting Limited

___________________________________________________________________________________________________

_____________________________________________________________________________________________________

Page 9

During night-time periods, occasional distant road traffic movements and plant noise from the Intel site were audible. Noise levels were in the range 35 to 39dB LAeq and 28 to 35dB LA90. During all measurements local road traffic movements were paused out as far as possible in order to prevent this source from dominating the measured noise levels.

2.6.5 Location NM05

Table 5 below presents the noise level measurements at Location NM05.

Time (hrs)

Measured Noise Level, dB re 210-5

Pa

LAeq LAmax LAmin LA10 LA90

14:22 – 14:37 42 65 34 44 36

15:28 – 15:43 46 66 32 47 36

16:35 – 16:50 43 66 35 45 38

22:43 – 23:58 39 61 35 41 37

23:52 – 00:07 41 63 36 41 37

00:57 – 01:12 38 62 35 39 36

Table 5 Noise Level Measurements at Location NM05

During the daytime survey periods, distant road traffic movements were noted as the primary contributor to the noise build-up. Plant noise from the Intel site was audible at low level. Birdsong, occasional distant train movements, aircraft movements and wind noise on nearby foliage were also noted. Noise levels were in the range 42 to 46dB LAeq and 36 to 38dB LA90. During the night-time survey periods, broadband plant noise was audible from the rear of the site. Other sources included occasional traffic on the R148 and distant traffic from the direction of the N4. Noise levels were in the range 38 to 41dB LAeq and 36 to 37dB LA90.

2.6.6 Location NM06

Table 6 below presents the noise level measurements at Location NM06.

Time (hrs)

Measured Noise Level, dB re 210-5

Pa

LAeq LAmax LAmin LA10 LA90

14:06 – 14:21 45 64 36 47 40

15:12 – 15:27 44 64 33 46 37

16:17 – 16:32 45 62 36 47 40

23:01 – 23:16 46 59 35 49 38

00:09 – 00:24 41 61 31 44 33

01:14 – 01:29 42 62 36 44 38

Table 6 Noise Level Measurements at Location NM06

During the daytime survey periods, road traffic movements on the R148 were noted as the primary contributor to the noise build-up. Birdsong, occasional train

Page 341: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

JM/10/5043NR01 AWN Consulting Limited

___________________________________________________________________________________________________

_____________________________________________________________________________________________________

Page 10

movements, distant aircraft movements and wind noise on nearby foliage were also noted. Plant noise from the Intel site was barely audible at this location. Noise levels were in the range 44 to 45dB LAeq and 37 to 40dB LA90. During the night-time survey periods, occasional road traffic movements on the R148 and broadband plant noise from the rear of the site were noted as being the primary contributors to the noise build-up. An idling train was the dominant contributory noise source during the first night-time measurement period. Noise levels were in the range 41 to 46dB LAeq and 33 to 38dB LA90.

2.6.7 Location NM07

Table 7 below presents the noise level measurements at Location NM07.

Time (hrs)

Measured Noise Level, dB re 210-5

Pa

LAeq LAmax LAmin LA10 LA90

14:50 – 15:05 55 72 45 57 49

15:53 – 16:08 55 71 46 57 51

16:58 – 17:13 54 72 45 56 49

22:04 – 22:19 44 59 37 44 38

23:26 – 23:41 41 55 35 43 37

00:32 – 00:47 37 55 31 39 33

Table 7 Noise Level Measurements at Location NM07

During the daytime survey periods, birds nesting in nearby trees were the dominant source of noise. Other audible sources included traffic on surrounding roads and occasional train movements. A distant lawnmower was noted during the first measurement period. Plant noise from the Intel site was not audible during the daytime measurement periods. Noise levels were in the range 54 to 55dB LAeq and 49 to 51dB LA90. Distant traffic movements were noted to be the dominant noise source during the night-time periods. Plant noise from the Intel site was not audible during the night-time measurement periods. Noise levels were in the range 37 to 44dB LAeq and 33 to 38dB LA90.

2.6.8 Comment on Measured Noise Levels

The LAeq values are a type of average of the noise level during the measurement period. As it is a logarithmic average, it is especially sensitive to relatively loud noises of short duration. For example, a single passage of a vehicle can govern the LAeq value of a measurement over a period much longer than the time for which the vehicle was audible. Thus, where the noise emissions from the Intel site are steady, as plant items are in continuous operation, the LA90 value better reflects the magnitude of these emissions.

Page 342: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

JM/10/5043NR01 AWN Consulting Limited

___________________________________________________________________________________________________

_____________________________________________________________________________________________________

Page 11

3.0 DISCUSSION The noise levels in terms of the LAeq level are presented in Table 8 below, and compared to the relevant IPPC Licence Criterion.

NSL

Daytime Night-time

LAeq (dB) Limit Value LAeq (dB)

Satisfies? LAeq (dB) Limit Value LAeq (dB)

Satisfies?

NM01 50 – 54

55

37 – 40

45

NM02 46 – 48 34 – 37

NM03 44 – 48 36 – 40

NM04 45 – 48 35 – 39 NM05 42 – 46 38 – 41

NM06 44 – 45 41 – 46*

NM07 54 – 55 37 – 44

Table 8 Measured LAeq levels for day and night-time periods compared to IPPC License criteria. * An idling train was the dominant contributory noise source during this night-time measurement period.

The measured LAeq levels are within the daytime limit value at all locations. However in many instances the LAeq values are governed by source not related to the site such as traffic on public roads, aircraft movements, train movements and birdsong. During the 2009 and 2010 IPPC surveys the measurements were paused as much as possible during local traffic movements and other individual events not associated with the Intel site. This explains the decrease in the reported levels at some locations when compared to surveys conducted in previous years. Due to the nature of the operations carried out at Intel, external noise sources run steadily over 24 hours. For this reason, it is more appropriate to compare the measured LA90 values against the limit values in the IPPC Licence. This is presented in the Table 9 below.

NSL

Daytime Night-time

LA90 (dB) Limit Value LAeq (dB)

Satisfies? LA90 (dB) Limit Value LAeq (dB)

Satisfies?

NM01 38 – 42

55

31

45

NM02 33 – 35 29 – 33

NM03 36 – 38 32 – 38

NM04 35 – 36 28 – 35

NM05 36 – 38 36 – 37

NM06 37 – 40 33 – 38

NM07 49 – 51 33 – 38

Table 9 Measured LA90 levels for day and night-time periods compared to IPPC License criteria It is therefore concluded that site noise emissions from Intel comply with the relevant limit values at all surveyed locations. It is also noted that measured plant noise levels are generally slightly lower than those monitored during the 2009 IPPC noise survey. It is feasible that the reduced noise levels are a result of the decommissioning of various plant items within the FAB 14 building.

Page 343: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

JM/10/5043NR01 AWN Consulting Limited

___________________________________________________________________________________________________

_____________________________________________________________________________________________________

Page 12

An additional review of one-third octave band Leq noise levels has been conducted. One-third octave band measurement results are included in Appendix A. Review of this data has concluded that there is no tonal component to any of the noise levels measured during the 2010 survey.

Page 344: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

JM/10/5043NR01 AWN Consulting Limited

___________________________________________________________________________________________________

_____________________________________________________________________________________________________

Page 13

4.0 CONCLUSIONS Noise levels have been measured at the locations stipulated in the relevant IPPC Licence. Audible noise sources include traffic on surrounding roads, the passage of trains, aircraft movements, birdsong, wind noise on nearby foliage and steady external plant noise from the Intel site. Due to the continuous nature of these external plant noise sources, it is appropriate to compare the measured LA90 which represents the steady background component of the environmental noise climate at each location. At all locations, the LA90 values are within the given limit values, for both day and night-time periods. In addition, review of one-third octave band data confirms that there is no tonal component to measured noise levels. It may therefore be concluded that this facility is in compliance with Condition 5 of the IPPC Licence in respect of noise.

Page 345: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

Project

Intel 2010 IPPC Noise

Monitoring Reference

JM/10/5043NR01

Figure 1

Site Layout and Noise

Monitoring Locations

The Tecpro Building, Clonshaugh Business and Technology Park, Dublin 17

T: +353 1 847 4220 F: +353 1 847 4257

NM01

NM02

NM03

NM04

NM05

NM06

NM07

Page 346: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

_____________________________________________________________________________________________________

Page 15

APPENDIX A

NOISE MEASUREMENT RESULTS 1/3 OCTAVE BAND

Page 347: Intel Ireland - Environmental Protection Agency · 1.2.1 Intel Ireland – Campus Overview 1 1.2.2 ... 3.4.2.2 Fluoride 51 3.4.3 Pollution Emission Register (PER) 2010 52 3.4.4 Pollution

_____________________________________________________________________________________________________

Page 16