Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Intel Ireland
Annual Environmental Report 2010
1 INTRODUCTION
1.1 Site Details 1
1.2 Description of Campus Activities 1
1.2.1 Intel Ireland – Campus Overview 1
1.2.2 Manufacturing Facilities Overview 2
1.2.3 Process Steps Overview 3
1.2.4 Environmental Abatement 5
1.2.5 Support Activities
1.3 Environmental Policy 7
1.4 Environmental Management Organisational Structure 8
2 SUMMARY INFORMATION
2.1 Self Monitoring Data 10
2.1.1 Emissions to Sewer 10
2.1.2 Emissions to Surface Water 12
2.1.3 Emissions to Atmosphere 13
2.1.4 Summary of Waste Data 15
2.2 Agency Monitoring and Enforcement 19
2.2.1 Agency Monitoring Visits 19
2.2.2 Agency Inspections 20
2.3 Resource Management 21
2.3.1 Introduction 21
2.3.2 Design for the Environment 21
2.3.3 Supplier Environmental Targets 24
2.3.4 Water Consumption and Minimisation 24
2.3.5 Energy Consumption 25
2.3.6 Material Efficiency 26
2.4 Environmental Incidents and Complaints 27
2.4.1 Environmental Incidents 27
2.4.2 Complaints 29
3 MANAGEMENT OF THE ACTIVITY
3.1 Schedule of Environmental Objectives and Targets 30
3.2 Environmental Management Programme (EMP) Report 2010 32
3.3 Environmental Management Programme (EMP) Schedule 2011 43
3.4 Pollution Emissions Register 49 3.4.1 Introduction 49
3.4.2 Summary of Methodology for Substances requiring a full PER 49
3.4.2.1 Copper 49
3.4.2.2 Fluoride 51
3.4.3 Pollution Emission Register (PER) 2010 52
3.4.4 Pollution Emission Register (PER) Proposal for 2011 53
4 LICENCE-SPECIFIC REPORTS
4.1 Groundwater Monitoring Summary Report 54
4.2 River Rye Water Monitoring Report 55
4.3 Louisa Spa Water Quality Monitoring 55
4.4 Bund Testing Summary 56
4.5 Underground Pipe and Tank Integrity Testing 56
4.6 Ambient Air Monitoring Summary 57
4.7 Fugitive Emissions Programme 58
4.8 Perfluorinated Carbon (PFC) Emissions Report 59
4.9 Noise Monitoring Report Summary 63
4.10 Residual Management Plan 63
APPENDIX A Pollutant Release and Transfer Register (PRTR)
APPENDIX B Groundwater Monitoring Report
APPENDIX C River Rye Monitoring Report
APPENDIX D Louisa Spa Monitoring Report
APPENDIX E Bund Testing Report:
APPENDIX F Underground Pipe Integrity Testing Report: - Fab 24 Process
Effluent Lines
APPENDIX G Underground Tank Integrity Test Report – F10 Upper
Contained Storm Sewer Tank.
APPENDIX H Noise Monitoring Report
Abbreviations
A… Air Emission Points Identified in the Intel IPPC licence
AER Annual Environmental Report
BOD Biochemical Oxygen Demand
C Calculation
C&D Construction and Demolition
C&I Construction and Industrial
C4 Controlled Collapse Chip Connect; (Wafer Finishing Process)
CAP Community Advisor Panel
CCW Concentrated Copper Waste
CFC Chlorofluorocarbon
CMP Chemical Mechanical Polish
CO Carbon Monoxide
COD Chemical Oxygen Demand
Cr Chromium
CRT Construction Response Team
CS Corporate Services
DMW Dilute Metal Waste
E Estimation
EDI Electro-Deionisation
EHS Environmental, Health & Safety
ELRA Environmental Liabilities Risk Assessment
EMP Environmental Management Plan
EMS Environmental Management System
EN
Standard maintained by CEN (European Committee for
Standardisation)
Env Environmental
EPA Environmental Protection Agency
ERT Emergency Response Team
ESIA European Semi-Conductor Industry Association
EU European Union
F Fluoride
F10/F14/F24 Fab 10/Fab 14/Fab 24
Fab Semi-conductor fabrication (manufacture) facility.
F-gas Regulations Fluorinated Gas Regulations
FMS Facilities Management System
FSM Fab Sort Manufacturing
GC Gas Chromatography
GHG Green House Gas
GWP Global Warming Potential
HAPs Hazardous Air Pollutants
Haz Hazardous
HCFC Hydrochlorofluorocarbon
HCl Hydrochloric Acid
HF Hydrofluoric acid
HFC Hydrofluorocarbon
HVAC House Vacuum
HVM High Volume Manufacturing
IFM Integrated Facilities Management
IFO Ireland Fab Operations (Fab 10 and Fab 14)
IPA Isopropyl alcohol
IPPC Integrated Pollution Prevention and Control
IPPCL Integrated Pollution Prevention and Control Licence
IR Ireland
IR1-IR6 Intel Ireland Office Building Nomenclature
IRCS Ireland Corporate Services
ISO International Standards Organisation
ISO 14001 Accredited Environmental Management System
JIA Japanese Semiconductor Industry Association
Kg Kilogram
KIA Korean Semiconductor Industry Association
l Litre
LOD Limit of Detection
Ltd Limited
m Metre
M Measurement
m3 Cubic metre
MAH Make-up Air Handler
Maximo
A task management system that controls maintenance
programmes within CS and EHS
mg Milligram
micron Micron, unit of measurement equal to 10-6 meter.
mm Millimetre
MMTCE Million Metric Tonnes Carbon Equivalent
MOM Method of measurement
MREP
Material Request Evaluation Process (Chemical Approval
System for Intel)
MS Mass Spectrometry
MTCE Metric Tonnes Carbon Equivalent
MW Megawatt
MW Monitoring well
N/A Not Applicable
Nm3 Normal cubic metre
NO2 Nitrogen dioxide
Non-haz Non-hazardous
NOx Nitrogen oxides
NUI National University of Ireland
OHSAS Occupational Health & Safety Advisory Services
Ops Operations
P Phosphorus
PER Pollution Emission Register
PFC Perfluorocarbons or Perfluoro compounds
POU Point of Use
PRTR Pollution Release and Transfer Register
RCTO Rotary Concentrator Thermal Oxidiser
REACH
Registration, Evaluation and Authorisation and Restriction of
Chemical Substances
RMP Residual Management Plan
RODI Reverse Osmosis De-Ionised
S.I. Statutory Instrument
sccm Standard cubic centimetre per minute
SCW Slurry Copper Waste
SIA Semiconductors Industry Association
SOG Spin on glass (process which produces polyimide waste)
Sort Electrical Testing Facility
SRF Solid Recovered Fuel
TA Luft German regulation for air quality standards
TD Technology Development
TOC Total Organic Carbon
UPS Uninterruptible Power Supply
VOC Volatile Organic Compounds
WSC World Semiconductor Council
WWTP Waste Water Treatment Plant
1
1.0 INTRODUCTION
1.1 SITE DETAILS
Licence Register No: P0207-03
Licensee Name: Intel Ireland
Address: Collinstown Industrial Park, Leixlip, Co. Kildare
1.2 DESCRIPTION OF CAMPUS ACTIVITIES
1.2.1 Intel Ireland – Campus Overview
The Intel Ireland campus is located at Collinstown Industrial Park, Leixlip, in County
Kildare. Intel Ireland Ltd is a subsidiary of Intel Corporation and the site at Leixlip is
Intel's sole manufacturing centre in Europe. The complex plays a significant role in
the company‟s continuing worldwide success. Intel Ireland first decided to locate a
technology campus in Ireland in 1989 and production of motherboards and systems
commenced in the following year. Since then, over $7.5 billion has been invested in
turning the 360 acre former stud farm into the most technologically advanced
industrial location in Europe.
The current IPPC licence (Register No. P0207-03) relates to the activity of the
manufacture of integrated circuits and printed circuit boards, surface coating
activities and the operation of combustion installations with a rated thermal input in
excess of 50 MW.
Three wafer fabrication buildings (or „Fabs‟) currently exist on site including Fab 10
and Fab 14 (collectively known as Ireland Fabrication Operations (‘IFO’) and Fab 24
(including Fab 24 and Fab 24-2). Fab 14 ceased production in late 2009 to position
the factory for future development and any production requirements either ceased or
were moved to the Fab 10 facility. During the course of 2010, Fab 10 was equipped
to run several individual products using 200mm wafer technology to produce logic
devices. Fab 24 processes 300mm wafers on both 90 and 65-nanometer process
technologies.
2
The campus is also home to other Intel Ireland businesses including the Intel®
Innovation Centre (IIC). The IIC has global responsibility to research and develop
innovative leading-edge IT solutions and technology. It involved a total investment by
Intel Ireland of over €12 million. The IIC is at the forefront of demonstrating how
Information Technology and Intel products can continue to deliver new competitive
advantage through the development of compelling new IT value propositions. The
centre, in partnership with NUI Maynooth, has set up the Innovation Value Institute, a
multi-disciplinary research and education institute, which was designed to help
achieve sustainable economic value from IT and quantify and understand the true
business value of strategic IT investments.
The Technology Research for Independent Living (TRIL) centre is located at the
Leixlip campus and is part of our Digital Health initiative. TRIL brings together world-
class industry and academic experts who are inventing and testing new technologies
with older people and their families to support them in continuing to live healthy and
independent lives. Intel Ireland funds over 50 PhD‟s and works closely with the
CRANN Nanoscience Research Centre in Trinity College Dublin and the Tyndall
National Research Institute in Cork.
Intel Ireland strives to be a trusted, leading corporate citizen. It aims to integrate
social responsibility and uncompromising integrity into everything we do, working to
advance people and better the planet through active commitment to education,
community and environmental sustainability. This is exemplified through initiatives
such as Intel Involved (an employee voluntary scheme for projects within the
community) and Community Advisory Panel (CAP, a group of diverse interests within
the community and Intel representatives which meet to discuss community projects
and issues on a quarterly basis)..
1.2.2 Manufacturing Facilities Overview
In 2010, Intel Ireland consisted of two manufacturing facilities on the site; IFO (Fab
10 and Fab 14) and Fab 24 (Fab 24 and Fab 24-2).
Fab 14 ceased manufacturing in late 2009 and all manufacturing operations which
took place there have either ceased or were moved to the Fab 10 facility. The
purpose of the shut down of Fab 14 was to position the facility for potential future
conversion and reuse. During 2010, a comprehensive decommissioning programme
was carried out at the Fab 14 facility under strict EHS conditions. This involved
3
decontamination of all production equipment in the cleanroom and all associated
abatement equipment. The majority of production tools and abatement systems
were de-installed and either sent to other Intel sites for reuse or disposed of by
approved waste vendors. The remaining equipment has been retained for future use.
During 2010, Fab 10 manufactured chips using advanced manufacturing technology
at the 0.13 and 0.25 micron node. In lay person‟s terms, at these nodes, millions of
transistors are created on an integrated circuit (chip) the size of a finger-nail.
Fab 24 first began producing the industry‟s most advanced 300mm/12” wafer
technology in 2004. The Fab 24 building is 52,000 square metres in size, which
includes a 15,000 square metre „Class 1‟ clean-room for the manufacture of chips.
Moving to 300mm wafers allows over twice the number of chips to be created on
each wafer compared with 200mm wafers, leading to a 30 per cent improvement in
productivity and costs. The sophistication of the process equipment and the level of
automation involved place Fab 24 at the very forefront of semiconductor
manufacturing which is widely recognised as the summit of manufacturing
technology.
Fab 24 manufactures single and multi-core microprocessors. There are two
manufacturing processes, 90nm (nanometre) which is in production since 2004 and
65nm which started in 2006. Fab 24 is a fully automated plant where all material
handling is fully automated and computer controlled.
Fab 24-2 is a newer facility, completed at the end of 2005. It is connected to Fab 24
and adds an additional 5,000 square metres of manufacturing „Class 1‟ clean-room
space, plus the necessary manufacturing equipment to enable the latest 65nm
technology. Production commenced in Fab 24-2 in the first quarter of 2006.
1.2.3 Process Steps Overview
Fabrication Plants which produce the silicon-based devices use complex processes
involving billions of dollars of equipment and 300-500 operational steps all housed in
an ultra-clean environment. The material does not move through the factory in a
linear fashion from front to back, but loops back on itself, revisiting some areas
sometimes more than twenty times.
The Fab buildings each contain major areas in which wafers are processed. These
areas are referred to as "Functional Areas" and include Diffusion, Lithography, Etch,
4
Thin Films and Planarization. The general principles of manufacturing
microprocessors are that the wafer is passed between the different areas to build up
a complex 3-dimensional device on the surface of the wafer. External contacts for
the microprocessors are made by what is known as the "Controlled Collapse Chip
Connect" process, also known as the “C4" process.
The manufacturing activities carried out on site fit into a number of categories. These
are:-
Diffusion: Where layers are introduced or „grown‟ on a semiconductor wafer
under high temperature conditions. Implanted chemicals are then introduced
to selectively change the electrical properties of sections of the wafer.
Lithography: creation of patterns for the electrical circuits on the wafer
surface in a process similar to photography using ultraviolet light passing
through apertures in a mask to selectively expose areas of the wafer.
Etch: translates the pattern created by lithography into a three-dimensional
structure by selectively etching channels into the surface substrates.
Thin Films: a film of material is introduced to either create conductive
interconnects between layers, electrical isolation or protection from the
environment.
Planarisation: the surface of the wafer is polished by the use of mechanical
and mild chemical abrasives to achieve a uniform flat layer.
Ion Implantation: used to introduce impurities or „dope‟ the silicon with
materials such as phosphorous, boron or arsenic. Implantation changes the
electrical characteristics of specific areas of the wafer.
The wafer will pass through each of these functional areas many times before
the full three-dimensional structure of each integrated circuit has been built
up. Each wafer may contain several hundred integrated circuit, with each die
forming the basis of a „silicon chip‟.
C4 Process: To allow each integrated circuit to be connected to a printed
circuit board for installation into computers, connections must be created to
connect the circuit to other electrical components on the board. For some
product types, these connections are produced in the "C4" process. During
this step, copper connects are introduced onto the circuit by an electrolytic
process. This process is currently only carried out in F24. Previously, IFO
5
used tin and lead connects instead of copper. However, C4 operations in IFO
ceased production during 2009.
Sort: Each chip is then electrically tested in a quality assurance step known
as Sort and then distributed to other Intel plants outside Ireland for final
packaging.
1.2.4 Environmental Abatement
Each fabrication building essentially carries out a similar manufacturing process with
progressive refinements for improved technology as smaller dimension technology is
introduced. Some variations do, however, occur in the treatment of waste generated
from certain processes. The major environmentally significant differences in
technology employed in Fab 24 from that in IFO include the following:-
Copper: The introduction of copper metal layers into the planarization, thin
films and C4 processes and the treatment of copper wastes arising.
VOC Abatement: Rotary concentrator / thermal oxidiser (RCTO) units have
been included in Fab 24 (and also retrofitted into Fab 10) to treat the
concentrated solvent exhausts from wafer manufacturing operations.
POU Scrubbers and Hydrofluoric/Phosphoric Acid Waste Treatment:
Additional Point of Use (POU) scrubber systems were introduced to reduce
emissions of perfluorinated compounds (PFCs) and provide enhanced
fluoride removal from air emissions.
Hydrofluoric/Phosphoric Acid process effluent is also produced whereby
fluoride/phosphate containing wastewaters (including the additional POU
systems) are converted to a benign solid waste as per existing practice in
Fab 10.
Ammonia Exhaust System: The introduction of an ammonia exhaust system
has segregated ammonia emissions from the main acid gas scrubber
systems and optimised the removal efficiency of both treatment systems.
This has resulted in a reduction in overall emissions.
Ammonia Wastewater Treatment System: In order to reduce the amount of
ammonia based compounds being discharged to the Leixlip Wastewater
Treatment Plant (WWTP), an Ammonia Wastewater Treatment System has
been installed at Fab 24. A proportion of ammonia based compounds are
6
collected and converted into ammonium sulphate. The treated wastewater,
which now has a much reduced concentration of ammonia, is then
discharged to Leixlip WWTP. The only other discharge from the Treatment
System is a vent which is classified as a minor emission point.
1.2.5 Support Activities
To support manufacturing operations, a number of on-site utilities including chemical
storage and handling facilities, ultra pure water treatment plant, bulk gas plants,
boilers and chillers along with wastewater treatment plants are required. These
provide the raw materials, conditions and services necessary for the manufacturing
process.
1.3 ENVIRONMENTAL POLICY
Intel Ireland operates a rigorous Environmental Management System (EMS), which
is independently certified to the international environmental management standard,
ISO 14001:2004. An EMS is a requirement of our Integrated Pollution Prevention
and Control (IPPC) licence. Having a certified EMS creates additional confidence in
the standard of our environmental controls.
The aspects of energy management are embedded in our Environmental Systems
and Policy. Hence, the site's Energy Policy is incorporated into the overall
Environmental Policy. The Intel Ireland site received accreditation to the Irish Energy
Management Standard (IS 393:2005) in December 2007 and to EN 16001 in June
2010.
In line with ISO 14001 and EN 16001 requirements, and to demonstrate the sites
commitment to Environmental Management, Intel Ireland has developed an
Environmental Policy. This policy is reviewed, updated and then signed by the site
managers on an annual basis. A copy of the 2011 Environmental Policy is outlined
overleaf.
7
8
1.4 ENVIRONMENTAL MANAGEMENT ORGANISATIONAL STRUCTURE
This section details the roles, responsibilities and interrelations of key staff responsible
for environmental activities. The Environmental management structure is represented
below.
Intel Ireland General Manager
The Intel Ireland General Manger has overall responsibility for Environmental
Management on the site. He/She is responsible for the assessment of the site‟s
Environmental performance against its stated targets and objectives. The General
Manager also sets direction during the annual review and facilitates the achievement of
these targets and objectives by attending Environmental Operations (Environmental
Ops) meeting which occur on a formal basis at least once per year. During 2010, the
Intel General Manager, Jim O‟Hara, resigned his position and the role was filled by
Eamonn Sinnott.
Ireland Corporate Services (IRCS) Manager
The IRCS Manager reports to the CS FSM TD Worldwide Manager and has overall
responsibility for Environmental Management in the IRCS area. He/She participates in
the assessment of the site and, in particular, Corporate Services' (IRCS) Environmental
Performance against its stated goals and objectives. The CS Manager sets direction
during the annual review and ensures that the CS targets and objectives are met.
IFO/Fab 24 Factory Managers
The IFO/Fab 24 Factory Managers have overall responsibility for Environmental
Management in their specific plant. He/She participates in the assessment of the site
and, in particular, their plant‟s Environmental performance against its stated targets and
objectives. The Factory Manager sets direction and ensures that the targets and
objectives are met.
9
Environmental Health and Safety (EHS) and Security Manager
The Intel Ireland EHS and Security Manager reports to the IRCS Manager and is
responsible for the day-to-day management of the Environmental Health and Safety
Department within the site. The EHS Manager has overall responsibility for
Environmental Management across the site and for achieving stated Environmental
targets and objectives. He/She sets direction on environmental matters and ensures that
Intel Ireland remain in compliance with relevant legislation. The EHS manager advises
the IRCS Manager of requirements to ensure sufficient resources are in place to run the
EMS.
Environmental Department
The Environmental Department currently comprises of six engineering or environmental
science graduates whose work is subdivided to deal with many aspects of
environmental programme management including:
Integrated Pollution Prevention and Control Licence (IPPCL)
Greenhouse Gas (GHG) Emissions Permit
Environmental Management System (EMS)
Community and internal environmental awareness
Essentially, the objective is that the operation of the activity complies with all applicable
environmental regulations and policies, and that the site‟s environmental management
system is managed in a sustainable fashion for social, environmental and economic
purposes.
Emergency Response Team (ERT)
The Site Emergency Response Team is responsible for the facility during an
emergency. An ERT leader, who directs operations during an emergency, leads the
team. ERT have specialised training to deal with a range of potential incidents.
10
2.0 SUMMARY INFORMATION
2.1 SELF-MONITORING DATA
2.1.1 Emissions to Sewer
Wastewater parameters are monitored as per requirements under Schedule C.3.2 of
Intel Ireland‟s IPPC licence on the basis of daily flow-proportional composite sampling.
Flow, pH and temperature are measured on a continuous basis before being discharged
from the site.
Licensed effluent flows and mass emissions to the Kildare County Council Wastewater
Treatment Plant (WWTP) in Leixlip for 2010 are compared with 2009 licensed emissions
data (Tables 2.1 and 2.2).
Table 2.1 - Summary of Licensed Effluent Flow to Sewer for 2010 compared with 2009.
Parameter
Volumetric
Emissions (m3)
2009
Volumetric
Emissions (m3)
2010
Licensed
Volumetric
Emissions (m3)
Flow (m3) 4,230,095 3,590,662 6,022,500
11
Table 2.2 – Summary of Licensed Effluent Emissions to Sewer for 2010 compared with 2009.
Parameter *Mass Emissions
(Kg) 2009
*Mass Emissions
(Kg) 2010
Licensed Mass
Emissions (Kg)
BOD 92,409 107,845 492,750
COD 85,349 34,722 985,500
Inorganic Suspended Solids Note 1 31,876 985,000
Total Suspended Solids <42,700 <45,676 1505625
Total Dissolved Solids <2,859,953 2,048,580 22,108,050
Total Phosphorus (as P) 4,249 3,835 24,638
Total Nitrogen 70,981 48,657 197,100
Fluoride 16,900 <14,391 58,400
Cyanide - <3.872 493
Tin <17.0 <1.43 1,971
Lead <3.14 <5.97 584
Chromium <6.33 <0.25 493
Nickel <13.6 8.93 986
Copper <177 160 1,478
Arsenic <1.75 <0.78 493
Total Heavy Metals Note 2
<219 <177 4,928
Cobalt <1.57 <0.78 N/A
Sulphates 1,520,000 1,146,432 N/A
Ammonia 52,300 48,587 N/A
Nitrates 8,340 - N/A
* For the purposes of the 2010 Annual Environmental Report and Pollutants Release and Transfer Register (PRTR), Intel Ireland has calculated the annual average wastewater mass emissions of the incoming „City Water‟ and subtracted this from the annual Intel Ireland wastewater mass emissions. Where there is a “less than” value, some results were below the limit of detection for this parameter. A submission to the Agency regarding the modification to the mass calculation method was submitted on the 15
th of March 2005. Where the incoming mass emission has been greater than or equal to
the wastewater mass emission the cell has been left blank.
Note 1: Inorganic Suspended Solids were monitored in 2010 after being added as a licence parameter through a technical amendment received in 2010 (Technical Amendment A to licence register no. P0207-03).
Note 2: Total Heavy Metals is the sum of Arsenic, Tin, Lead, Chromium, Nickel and Copper
12
Where the concentrations of parameters measured during 2010 were reported as below
the limit of detection, the parameter has been assumed to be equal to the detection limit
to enable average concentrations and annual emission rates to be calculated. The
reported concentrations and emission rates are thus reported as „less than‟ the
calculated values.
A detailed summary of all wastewater emissions to Leixlip WWTP is included in the
PRTR found in Appendix A.
2.1.2 Emissions to Surface Water
Under Condition 6.1 of the IPPC licence, we are required to carry out the monitoring as
detailed in Schedule C.2.3. A summary of the analysis results is detailed in Table 2.3.
Table 2.3 - Summary of Monitoring Results SW1 (Storm Water Emissions), 2009 and 2010
Parameter Monitoring
Frequency
Units Average
Emission 2009
Average
Emission 2010
pH Continuous pH 8.0 7.9
Conductivity Weekly µS/cm 520.9 694.9
COD Weekly mg/l <15.6 <17.9
TOC Weekly mg/l <5.0 <5.4
Arsenic Biannual µg/L <2 <2
Chromium Biannual µg/L <2 <2
Cobalt Biannual µg/L <2 <2
Copper Biannual µg/L 8.5 55
Nickel Biannual µg/L <2 <2
Tin Biannual µg/L <2 <2
Lead Biannual µg/L <2 <2
13
2.1.3 Emissions to Atmosphere
This section provides a summary of the annual emissions to atmosphere from licensed
emission points identified in Intel‟s IPPC Licence. Emissions are derived from five main
sources including:
boiler and generator emission sources (NOx and CO);
acid scrubber exhausts (acid gases);
specialty exhausts (arsenic and total dusts);
RCTO Emissions (volatile organic compounds, VOC, NOx and CO).
Table 2.4 compares annual average mass emission limits for 2009 and 2010 against
equivalent maximum mass emission limits for those years. The equivalent mass
emission limit was calculated by multiplying the concentration emission limit value by
the flow limit for each emission point. The equivalent mass emission limits calculated
for 2010 excluded licenced emissions for Fab 14 due to the Fab 14 shutdown. Hence,
the 2010 equivalent mass emission limits are slightly lower than the calculated limts
for 2009.
Although there is no equivalent mass emission limit for the site‟s NOx and CO
emissions (from boilers and RCTOs), due to the fact that there are no flow ELVs for
the boilers, all results were below the concentration ELVs for these parameters.
There was an increase in NOx emissions due to an increase in diesel consumption
for the boilers and emergency generators in 2010.
One may observe from the table that the total fluoride, gaseous hydrofluoric acid and
total acids mass emissions from 2010 are approximately double the emissions for
2009. This was due to a change in air monitoring vendor in Q4 2009. The new
vendor employed different sampling methodologies which led to elevated results for
some parameters but all results were within IPPCL limits.
The TA Luft Organics Class 3 and TOC results for 2009 are high due to an
anomalous result for one of the quarterly monitoring events which skewed the mass
emission results for the year.
14
Table 2.4 – Total Site Annual Mass Emissions to Atmosphere for 2010 compared to 2009 values
Parameter Equivalent Max. Mass Emission Limit 2009 (Kg)
Annual Emission 2009 (Kg)
Equivalent Max. Mass Emission Limit 2010 (Kg)
Annual Emission 2010 (Kg)
Ammonia 10,722 24 10,722 21
NOx (as NO2) N/A 17,514 N/A 33,800
CO N/A 8,072 N/A 8,712
Total Acids (as HCl) 217,806 1,055 58,511 3,595
Gaseous HF 14,702 182 3,949 376
Total Fluorides 5,447 384 4,054 774
TA Luft Organics Class 1 14,296 331 7,358 278
TA Luft Organics Class 2 62,722 245 28,032 233
TA Luft Organics Class 3 122,114 4,005 70,080 2,022
Total Organics (as C) 4,588 3,405 3,504 93
TA Luft Inorganic Dust Particles Class 1 26 1.79 12 0.83
TA Luft Inorganic Dust Particles Class 2 82 2.97 34 1.57
TA Luft Inorganic Dust Particles Class 3 82 4.10 34 7.47
Total Dusts 8,194 62 3,401 152
There was one non-compliance in relation to emissions to atmosphere in 2010, the
details of which are shown in Table 2.5
15
Table 2.5 - Details of Non-Compliances Relating to Air during 2010
Date Non-compliance Cause Corrective Action
27/04/10 Exceedance of
Volumetric Flow
Limit at Fab 10
and Fab 24 RCTO
Oxidisers
The previous
monitoring vendor
had not corrected the
volumetric flow rate to
18% oxygen, as
stated in condition
4.2.2 of our licence.
This was noticed
when the air
monitoring vendor
was changed.
A technical amendment to
our licence was submitted
and the proposed limit of
4,000 Nm3/hr for the
RCTOs oxidiser emission
points was approved by
the Agency and this may
be referenced as P0207-
03 Technical Amendment
B.
2.1.4 Summary of Waste Data
A summary of the waste data is outlined in Tables 2.6 to 2.8.
Table 2.6 – Summary of Total Waste for 2010 (Tonnes)
Total Waste 7639.48
Total Waste Disposed of 1362.43
Total Waste Recovered 6277.05
16
Table 2.7 – Summary of Hazardous Waste for 2010 (Tonnes) compared to previous years
Waste Description 2007 2008 2009 2010
Corrosive Lead 3.75 *Note 1 *Note 1 *Note 1
Corrosive Arsenic 14.97 *Note 1 *Note 1 *Note 1
Flammable Arsenic 10.07 *Note 2 *Note 2 *Note 2
Flammable Debris 70.41 86.57 73.41 78.99
Corrosive Debris 167.02 150.30 289.43 519.44
General Solvent 1,814.26 1,728.84 1,380.83 1,147.07
Lead Reclaim Waste 9.91 0.00 14.14 0.00
Reclaim Metal Waste 53.26 18.78 16.42 45.44
Lead/Metal Waste-concentrated 774.21 689.24 648.66 263.38
Copper Waste-concentrated 64.95 71.80 72.06 36.22
Phosphoric Acid Waste 479.42 599.38 510.84 416.08
Ammonium Sulphate Waste 627.74 711.30 700.30 695.00
Fluorescent Lamps and fittings 1.96 2.77 2.40 2.87
Batteries 10.08 58.03 44.19 6.13
Clinical Waste 0.19 0.16 0.14 0.00
Waste Refrigerants 0.00 0.00 0.13 0.17
Used Oil 2.50 4.75 3.00 1.80
Resin 40.55 43.40 21.00 22.72
Carbon 0.00 0.00 0.00 5.1
KD100 8.10 0.00 32.58 19.94
Tank decontamination washings 0.00 0.00 0.00 78.00
Copper Chromate Arsenic Treated Timber 0.00 0.00 2.40 0.00
SOG – Polyimide recovery waste 0.27 0.43 0.00 0.20
Arsenic Slurry Waste 2.92 6.74 3.01 1.52
Labpacks* Note 3
31.91 28.29 88.30 31.30
17
Table 2.7 (continued) – Summary of Hazardous Waste for 2010 (Tonnes) compared to
previous years
Waste Description 2007 2008 2009 2010
Copper with residual sulphuric acid and copper sludge 6.50 7.58 9.91 9.24
Total Recovered 3,790.19 3,829.01 3,395.72 2,456.98
Total Disposed 537.11 379.35 517.43 923.63
Total Hazardous Waste 4,327.30 4,208.36 3,913.15 3,380.61
% of Total Hazardous Waste Recovered 87.59 90.99 86.78 72.68
*Note 1- The corrosive lead and corrosive arsenic debris numbers was incorporated into the corrosive debris number
*Note 2 - The flammable arsenic debris number was incorporated into the flammable debris number for 2008, 2009 amd 2010
*Note 3 – The definition of lab packs is used to describe the disposal of expired chemicals
Overall the amount of hazardous waste generated in 2010 decreased. This is
predominantly related to the downturn in production. Also Fab 14 ceased production in
late 2009 with no replacement manufacturing process in Fab 14 in 2010. Similarly,
operations in Fab 10 were reduced in 2010. The amount of waste disposed of
increased in 2010 mainly due to Fab 14 de-installation waste shipments in Q1 2010 and
also a reduced volume of waste which is usually recycled at Fab 10 (e.g. solvent waste
tankers). Overall in 2010, corrosive debris increased. This is again related to the Fab 14
de-installation work which generated large volumes of corrosive pipework, tank systems
and tools for breakdown. General solvent waste decreased due to the elimination of
solvent waste flows from Fab 14 and reduced production in Fab 10. Concentrated
lead/metal waste flows reduced due to the discontinuation of the lead process and
associated lead treatment system in Fab 14. Similarly, the amount of resin sent off-site
decreased as the dilute lead waste resin exchange system was removed from Fab 14.
Concentrated copper waste decreased as a new method of removal of CCW sludge was
implemented. This is further described in our EMP section (Table 3.3). The volume of
batteries generated in 2010 was much less than 2009 as in 2009 there was large scale
change out and de-installation of UPS systems at the site.
18
Table 2.8 – Summary of Non-Hazardous Waste (Tonnes) 2010 compared to previous years
Waste Description 2005 2006 2007 2008 2009 2010
All Paper Recycled 32.89 20.64 10.26 2.99 3.14 13.32
Cardboard Recycled 107.18 141.64 57.68 66.43 36.46 11.22
Metal Recycled 115.92 445.47 291.56 281.58 1,065.36 2,152.6
Plastic Recycled 29.78 37.9 8.32 1.52 79.98 121.86
Wood Recycled 203.34 502.22 239.28 206.14 112.59 109.58
Other Recycled Note 2
1094.9 960.26 2466.90 783.3 2,065.40 1,411.49
General Non-
hazardous
(disposed) 562.29 1078.39 274.23 264.92 319.38 75.98
General Non-
hazardous C&I
(disposed) 287.53 327.34 409.02 291.41 189.4 73.44
General Non-
hazardous C&D
(disposed) 0 0 15.08 0 0 0
Calcium Fluoride
Cake 761.86 966.8 900 845.42 470.42 289.38
Non-Hazardous
Aqueous Waste 193.5 0 0 0 0 0
19
Table 2.8 (continued) – Summary of Non-Hazardous Waste (Tonnes) 2010 compared to
previous years
Waste Description 2005 2006 2007 2008 2009 2010
Total Recovered 1,584.01 2,435.47 3,074.4 1,341.95 3,362.93 3,820.07
Total Disposed 1,805.18 1,840.25 1,598.32 1,401.75 979.2 438.8
Total Non-
Hazardous Waste 3,389.19 4,275.72 4,672.72 2,743.71 4,342.13 4,258.87
% of Total Non-
Hazardous Waste
Recovered Note 1
46.74 56.96 65.79 48.91 77.45 89.7
Note 1: The above recycling figure for non-hazardous waste includes calcium fluoride cake which is a non hazardous waste.
Note 2: ‘Other Recycled’ includes; Cables, WEEE, Glass, Clothing, Compost, Mixed Packaging, Sludge, Resin, Municipal Mixed Waste, C&I Mixed and C&D mixed waste
In 2010, the volumes of non-hazardous waste generated from site remained similar to
2009 due to on-going de-installation works in the Fab 14 facility. The tonnage of waste
to recovery increased in 2010, while waste volumes to landfill decreased significantly
from 2009 (primarily due to a decrease in calcium fluoride filter cake.) Overall, the
percentage of non-hazardous waste recovered increased from 77.5% in 2009 to 89.7%
in 2010 as a result of an increase in generation of recoverable waste from the Fab 14
de-installation project and continuous improvement in waste segregation at waste
contractor‟s facilities.
A detailed summary of all waste streams sent off-site from Intel Ireland for disposal is
included in the PRTR found in Appendix A.
2.2 AGENCY MONITORING AND ENFORCEMENT
2.2.1 Agency Monitoring Visits
The various monitoring visits made by the Agency during 2010 are outlined in Table
2.9a below.
20
Table 2.9a - Agency Monitoring Visits 2010
Date of Visit Purpose of Visit
19th January 2010 Surface water and waste water sampling
13th April 2010 Surface water and waste water sampling
5th July 2010 Surface water and waste water sampling
27th September 2010 Air sampling
5th October 2010 Surface water and waste water sampling
In relation to the wastewater and surface water samples taken, a comparison was
carried out between the EPA results and the Intel split samples that were analysed by
an external laboratory. While some differences were noted, none of the detected
parameters were over Intel‟s IPPCL limits.
2.2.2 Agency Inspections
There were four Agency inspections during 2010 which are outlined in Table 2.9b below:
Table 2.9b - Agency Inspection Visits 2010
Date of Visit Purpose of Visit
25th January 2010 EPA Inspectors Audit
2nd
February 2010 EPA and Department of the Environment Visit for PFOS
Regulations
16th April 2010 EPA Site Inspection Visit
22nd
October 2010 EPA Visit for GHG Permit inspection
21
2.3 RESOURCE MANAGEMENT
2.3.1 Introduction
This section identifies resource and energy use on site and outlines reduction measures
used by the company.
The management systems in place for the design of wafer fabrication facilities and the
associated processes ensure that raw material usage and energy use arising from site
activities are further reduced at source per unit produced for successive generations of
technologies where possible. The environmental goals of minimisation, substitution and
recycling are employed to ensure resource use is minimised and resources are used
efficiently.
Raw material conservation, emission and waste reduction are achieved through a
combination of:-
Cleaner and more efficient process technology to reduce raw material inputs and
produce lower emissions and wastes
Material substitution with lower toxicity alternatives or those that generate lower
emissions such as low volatility chemicals
Recycling or recovery of raw materials and waste products
In addition to chemical and gas consumption minimisation, resource conservation is
focused on the efficient use of electricity, gas and water on the site.
Details of the methods employed and results are briefly described in Sections 2.3.2 to
2.3.3 below.
2.3.2 Design for the Environment (Technology Goals)
Intel Corporation develops and delivers a new chip manufacturing technology
approximately every two years. The development cycle starts typically with six years
external research in universities and government labs, followed by approximately four
years joint research and development between Intel and suppliers followed by two years
process development to produce a fully functional technology before transfer to high
volume manufacturing (Figure 2.1). Intel has recognised that there is an opportunity for
22
early engagement to effect change for environmental benefit during external and joint
research, in addition to when the process is in high volume manufacturing mode.
However, the optimum time to effect change for environmental design of the process is
during the 2 years of final process development. The Intel Environmental Technology
Development (TD) group is involved throughout this timeframe and has input into
manufacturing process development, chemical selection, waste management, facility
systems design and manufacturing equipment selection.
Figure 2.1 Effecting change during Intel process technology development
For each technology, goals are set for specific types of emissions, for example: - mass
of VOCs or copper emitted per wafer produced. The methodology used for the setting of
these goals is to first evaluate the receiving environment at each of the High Volume
Manufacturing (HVM) sites. Items considered during this review would include existing
site permits, local area regulations, wastewater treatment plant capacity, air and water
quality standards and demographic growth projections. Against this data is set projected
wafer manufacturing capacities at each of the HVMs for each of the technologies. From
this are derived acceptable emissions/wafer figures for each of the HVM sites. To set
the corporate goal, the lowest emission/wafer figure so calculated is used. Once the
23
goals have been ratified at the appropriate management level, measures are put in
place during the development cycle to ensure the targets are met. Measures include
material selection, material substitution, recipe optimisation, emissions treatment and
waste segregation. In this way, the Corporation aims to ensure that the transfer of
technologies to the HVMs can be successfully transferred without detrimental effect on
the local environment.
Once the technology is transferred to a receiving HVM site, such as Intel Ireland, actual
emissions per unit of product for each parameter are sampled and reported to
development and receiving factory site management to confirm that, when the
technology is run in high volume manufacturing conditions, it performs to the goals that
the Technology Development (TD) group is required to deliver.
The oldest technology being manufactured at the Ireland site (0.35 micron) was
developed in 1995. The latest technology (0.065 micron or 65 nanometres) started
manufacture at Intel Ireland in 2006. The 0.35 micron technology line is now a small
portion of the overall capacity at Intel Ireland. The vast majority of current capacity runs
the more advanced technologies where the benefits of emissions reductions are
realised.
Since the inception of the environmental technology goals process, a number of
additional parameters have been included in the more recent years. Currently Intel has
technology goals for reducing emissions and waste per wafer produced including the
following parameters:
Emissions to Atmosphere:
o PFC, VOC and HAPs
Emissions to Waste Water
o CMP Solids
o Ammonia
o Copper
o Lead
o Nickel
24
o Cobalt
o Tin
o Fluoride
Waste
o Mass of chemical waste
2.3.3 Supplier Environmental Performance Targets
Equipment or „tool‟ design is a significant area of research for Intel and Intel„s equipment
suppliers. Intel requires that equipment suppliers design tools to minimise environmental
emissions and resource consumption by including specific target emission levels on a
per wafer processed basis in the equipment contractual purchase specifications. This
practice ensures environmental considerations are designed into the process tools from
the conceptual phase. Tool vendors are required to select gases and chemicals that can
meet the target and must then carry out emissions characterisation on exhaust and
waste streams. Since Intel introduced environmental emission targets to equipment
vendor purchase specifications, the vendors have become more aware of the
environmental considerations arising from their tools and are often in a more appropriate
position than Intel to address any issues.
2.3.4 Water Consumption and Minimisation
The usage of water is a function of several variables including production levels and
water conservation measures in place. There is a base loading on the factories that is
independent of production levels arising from systems such as cooling towers and
exhaust air treatment systems. Therefore, when a facility is operating at lower
production rates, water usage expressed in terms of volume per unit produced can be
adversely affected. For this reason total water consumption is provided for the site
overall. There is a marked decrease in water consumption in 2010. This is mainly
related to the shutdown of Fab 14. In addition, in 2010, a water conservation project
was completed which will result in annualized savings of water of 268,440 m3. Details of
25
this project are outlined in Section 3.2 (Environmental Management Programme Report
2010).
Table 2.10 - Total Water consumption for Site
Parameter 2009 2010
Total Water Usage (m3) 4,239,451 3,758,950
2.3.5 Energy Consumption
Consumption of energy (electricity, natural gas and oil) for 2009 and 2010 are detailed in
Table 2.11, and is followed by a discussion of results.
Table 2.11 - Annual Energy Usage - Electricity, Gas and Oil
Parameter 2009 2010
Total Electricity Usage (MWh) 471,460 404,813
Total Natural Gas Usage (MWh) 168,420 173,400
Total Oil Usage (tonnes) 123 266
Total electricity usage decreased overall in 2010. This is attributable to the de-
installation of the Fab 14 manufacturing area and also the implementation of energy
savings projects. A sample of energy savings projects are provided in our
Environmental Management Programme (EMP) section. Gas consumption slightly
increased due to the damage to the coils of the Fab 24 Heat Recovery System in
February 2010 caused by severe cold weather. The increase in oil consumption
compared to 2009 levels is attributable to the increased running of emergency
generators (due to power disruptions) and running boilers on oil (due to interruptions
in natural gas supply) during 2010.
26
2.3.6 Material Efficiency
2.3.6.1 Process Optimisation for Material Efficiency
Due to the very minute dimensions that are patterned onto a wafer during
manufacture, process chemical and gas flow set points need to be very exact.
Process optimisation through the statistical „Design of Experiments‟ methodology
is a practice used extensively throughout the process to determine the wafer
processing recipe set points such as gas and chemical flows and power during
technology development.
Using this method, tests are carried out by varying equipment recipe set points
and measuring the result on the wafer. For example, in a dry etch process; set-
point variables for an etchant gas may be tested at flow rates of 10, 12, 14 and
16 sccm. The flow that provides optimum results on the surface of the wafer is
selected. Process optimisation ensures that excess chemicals, gases or energy
are not consumed which conserves resources.
The move from 8 inch to 12 inch wafers has meant significant efficiencies are
achieved in relation to raw materials used per number of product units
manufactured. The 12 inch (or 300mm) wafer carries more than twice the
number of dies that can be produced on an 8 inch wafer. This economy of scale
has given rise to an increase in production without a proportional increase in
consumption of raw materials.
2.3.6.2 Yield Improvements
In all the manufacturing technologies operated on site, yield improvement is a
focus area. This covers the line yield, (the number of wafers that are not
scrapped in line), as well as die yield (which is the number of functioning die
per wafer at end of line). The continuous effort to improve yield gives rise to
more efficient use of raw material, thereby conserving resources.
For example; certain compounds reduce the number of defects on the product
which can cause failures in circuits and reducing die yield. Failed circuits are
discarded at end of process and require replacements. Use of these chemicals
27
reduce these process losses and makes the manufacturing process more
efficient, thereby reducing overall emissions and resource use per unit of
production.
2.4 ENVIRONMENTAL INCIDENTS AND COMPLAINTS
2.4.1 Environmental Incidents
This section details the Environmental Incidents that occurred in 2010. Condition 11.7
of the Intel Ireland IPPC Licence required that -
The licensee shall submit to the Agency, by the 31st March of each year, an AER
covering the previous calendar year. This report, which shall be to the satisfaction of the
Agency, shall include as a minimum the information specified in Schedule D and shall
be prepared in accordance with any relevant guidelines issued by the Agency.
There was one environmental incident in 2010 as follows:
Exceedance of Volumetric Flow Limit at F10 and F24 RCTO Oxidisers (27th April
2010):
Intel Ireland changed the air monitoring vendor for Q4 2009. During routine air
emissions monitoring by the new air monitoring vendor, it was discovered that the
volumetric flows from the Fab 10 and Fab 24 RCTO oxidiser stacks (when corrected for
Standard Temperature, Pressure, Density and Oxygen) exceeded the volumetric flow
limit specified in the site‟s IPPC licence. Our previous monitoring vendor had not
corrected the volumetric flow rate to 18% oxygen, as stated in condition 4.2.2 of our
licence.
It is important to note that the RCTO abatement system settings and flow rates have
been constant during the vendor change and the pollutant concentrations at the RCTO
units are substantially below the emission limit values as set out in our IPPC licence.
Based on modelled flow rates of 6,000 Nm3/hr, there are no impacts of environmental
significance. Therefore, a Technical Amendment to our licence was submitted to the
EPA to seek a flow limit of 4,000 Nm3/hr. This amendment was approved by the Agency
28
on the 1st March 2011 and is known as Technical Amendment B to the IPPC licence
(Register No. P0207-03).
In addition to the event above, we also reported the following events relating to
abatement and monitoring equipment to the EPA during 2010 (Tables 2.12 and 2.13). It
is important to note that during abatement system events, the associated monitoring
equipment showed that air emissions remained below licence limits at all times. In the
case of monitoring equipment failure, contingency monitoring showed that all air
emissions were in compliance.
Table 2.12 – Abatement Equipment Downtime 2010
Date Equipment Details
19/01/2010 Fab 10 RCTO RCTO bypass due to bearing failure
16/03/2010 Fab 10 RCTO RCTO bypass due to condensation in the impulse line
19/04/2010 Fab 10 RCTO Annual preventive maintenance
23/04/2010 Fab 10 RCTO RCTO bypass due to inlet damper failure
24/04/2010 Fab 10 RCTO Inlet damper failure
01/05/2010 Fab 10 RCTO Oxidiser chamber fault
06/06/2010 Fab 24 RCTO Fan malfunction
24/06/2010 Fab 24 RCTO Interruption to natural gas supply
13/07/2010 Fab 10 RCTO Interruption to natural gas supply
03/08/2010 Fab 10 RCTO Installation of natural gas pressure switch
15/09/2010 Fab 24 RCTO Planned shutdown
08/12/2010 Fab 10 RCTO Temperature controller issue
29
Table 2.13 – Monitoring Equipment Downtime 2010
Date Equipment Details
09/03/2010 Fab 10 RCTO
Combustion Gas
Analyser
Unit taken down for essential maintenance
31/05/2010 Fab 10 RCTO TOC
Analyser
Unit taken down for essential maintenance
19/07/2010 Fab 24 RCTO TOC
Analyser
Preventative maintenance
03/12/2010 Fab 24 RCTO TOC
Analyser
Cold temperatures caused moisture in inlet
air to freeze
2.4.2 Complaints
The Corporate Affairs department deals with any complaint received from the public with
support from the environmental department.
Corporate Affairs maintains a log of all environmental complaints received from the
public. This log contains information regarding the complainant and the nature of the
complaint. Each complaint is communicated to the environmental department, the
complaint is investigated and an appropriate response is determined. Details of the
response are held in the complaints log.
There were no complaints of an environmental nature received in 2010.
30
3.0 MANAGEMENT OF THE ACTIVITY
3.1 SCHEDULE OF ENIVIRONMENTAL OBJECTIVES AND TARGETS
Under Condition 2.2.2.2 of Intel‟s IPPC licence (Register No. P0207-03), Intel is obliged
to do the following:
“The licensee shall maintain a Schedule of Environmental Objectives and
Targets. The Schedule shall as a minimum provide for a review of all operations
and processes, including an evaluation of practicable options, for energy and
resource efficiency, the use of cleaner technology, cleaner production, and the
prevention, reduction and minimisation of waste, and shall include waste
reduction targets. The Schedule shall include time frames for the achievement of
set targets and shall address a five- year period as a minimum. The Schedule
shall be reviewed annually and amendments thereto notified to the Agency for
agreement as part of the Annual Environmental Report (AER)”.
Intel Corporate EHS reviews the company‟s significant aspects and maintains a rolling 5
year objectives and targets plan to reduce the impact on these aspects. The most recent
revision (2009) is detailed in Table 3.1. Intel Ireland reviews and updates the site‟s
significant aspects on an annual basis which takes into account corporate and other
requirements as well as legislative requirements. The Environmental Management Plan
(EMP) status report for 2010 is detailed in Section 3.2 and the proposed objectives and
targets for 2011 are described in Section 3.3.
31
Table 3.1 - Corporate Environmental Strategic Goals and Performance
32
3.2 ENVIRONMENTAL MANAGEMENT PROGRAMME (EMP) REPORT 2010
The 2010 Intel Ireland Objectives and Targets were made up of eleven strategic objectives.
Objectives and Targets were chosen in order to establish realistic and meaningful
improvements for that projected period. A report on the progress of these objectives during the
course of 2010 is provided in Tables 3.2 to 3.12.
Projects that are in progress and within the original assigned due date are designated as “In
Progress”. “Open” projects denote projects that are in progress but have exceeded the original
timeline.
33
Table 3.2 - Objective No. 1 Status Report
Environmental Aspect/Topic: Materials Handling
Description of Activities: Chemical (and chemical waste) storage, handling and transportation
Objective No. 1: Surface Water/Groundwater Protection
Target Project Update 2010 AER Status
1.1 Ensure 100% Compliance with IPPCL (Condition 3.6.6)
1.1.1 Repair outstanding bunds and test in accordance with bund assessment findings carried out in 2009:
Bunds were repaired and tested as outlined in the bund assessment carried out by PM in 2009. Results of hydrostatic testing are included in Appendix E.
Complete
1.2 Ensure 100% Compliance with IPPCL (Condition 3.6)
1.2.1 Install apron to prevent sprays from escaping bunded area for sodium hydroxide bridge scrubber day tank bund.
A second layer of Perspex was installed and all joints sealed preventing any sprays from escaping the bund
Complete
1.2.2 Review protocol and update procedures for emptying bunds and sumps.
Protocol for emptying sumps and bunds onsite was reviewed in conjunction with CS operations and a new procedure developed to cover the emptying of all bunds and sumps onsite including contents testing requirements. Formal training on new procedures is to be rolled out in Q1 2011
Complete
34
Table 3.3 - Objective No. 2 Status Report
Environmental Aspect/Topic: Hazardous Waste
Description of Activities: Generation, handling, collection, packaging, transportation and recycling of CCW
Objective No. 2: Reduce environmental impact of hazardous waste generated by IR site operations.
Target Project Update 2010 AER Status
2.1 Achieve a measurable target to align with corporate goal of 10% reduction by 2012 based on 2007 levels.
2.1.1 Implement corporate driven projects associated with waste minimisation
No corporate projects were required for completion at the Ireland site in 2010. However, one project was implemented to reduce the volume of CCW waste transported off-site for recovery. Instead of sending this waste as a part sludge and majority liquid, the system for collection of waste was changed to remove the sludge to totes and decant the remaining residual liquid. This will result in annual savings of this waste of approximately 56 tonnes based upon a PM schedule on the CCW system which generates this waste once per quarter.
Complete
35
Table 3.4 - Objective No. 3 Status Report
Environmental Aspect/Topic: Chemical WasteNote 1
Description of Activities: Generation, collection, storage, transport and landfilling of calcium fluoride/phosphate filter cake.
Objective No. 3: Recycle 80% of chemical waste generated per year
Target Project Update 2010 AER Status
3.1 80% recycling rate for chemical waste (hazardous waste and non-hazardous filter cake)
3.1.1 Find recycling outlet for filter cake - potentially could boost recycling rate by 16%
Overall site recycling for corporate-defined chemical waste was 66% for 2010. The site did not meet the corporate goal due to project-related chemical waste being generated from F14 de-installation. Intel will still actively pursue the recovery of its calcium fluoride filter cake as this is a corporate-derived goal for all sites. Currently no recovery is available to Ireland, China and Israel sites. In 2010, Intel Ireland again approached cement kilns in Ireland and Europe to find a recovery outlet. Intel Ireland has not yet been successful in achieving this goal mainly due to technical issues with sending this waste material to cement kilns and also Ireland generated relatively small volumes for this to be economically viable.
In Progress
Note 1: Chemical waste at Intel Ireland is defined as all chemical type waste. This definition includes calcium fluoride filter cake which is classified as non-hazardous waste in line with Irish and EU legislation.
36
Table 3.5 - Objective No. 4 Status Report
Environmental Aspect/Topic: Non-Hazardous Waste
Description of Activities: Generation, segregation, collection, storage and recycling of Dried Mixed Recyclables (DMR) - includes all dry recyclable waste
Objective No. 4: Recycle 80% of our solid waste (non-hazardous) generated per year
Target Project Update 2010 AER Status
4.1 Recycle 80% of our solid waste (non-hazardous) generated per year
4.1.1 80% recycling rate for solid waste (non-hazardous waste hairnet and booties)
Accomplished 89.7% non-hazardous waste recycling in 2010. Key contributing factors were a decrease in the volume of calcium fluoride filter cake and a significant increase in metal recycling due to the Fab 14 de-installation project.
Complete
Table 3.6 - Objective No. 5 Status Report
Environmental Aspect/Topic: Non-Hazardous Waste
Description of Activities: All non-hazardous waste activities with the exception of generation, collection, storage, transport and landfilling of calcium fluoride/phosphate filter cake.
Objective No. 5: Seamless Implementation of IFM contract for non-hazardous waste
Target Project Update 2010 AER Status
5.1 Zero non-compliances with IPPCL during implementation
5.1.1 Sustained operational control during Integrated Facilities Management (IFM) transition
Zero non-compliances with IPPCL during implementation of the IFM contract. Primary factors which ensured this target was met were: - continuation of Intel/waste vendor bi-weekly meetings with IFM representative in attendance - frequent internal audits of waste collection were carried out with IFM representative in attendance. - continued direct communications between Intel and our waste vendor on operational issues.
Complete
37
Table 3.7 - Objective No. 6 Status Report
Environmental Aspect/Topic: Air Emissions
Description of Activities: Discharge of gaseous and particulate acids to atmosphere from acid scrubbers (e.g. HCl, Total fluorides, HF)
Objective No. 6: Ensure Air Quality
Target Project Update 2010 AER Status
6.1 Integrated fluoride monitoring programme
6.1.1 Develop an integrated sampling protocol for vegetation, HF diffusion tubes and filter paper
Proposals for the work developed and quotations received. Housing for filter paper to be installed. The project will then be assessed prior to financial and management review and integrated sampling to commence in Q4 2011.
Open
Table 3.8 - Objective No. 7 Status Report
Environmental Aspect/Topic: Materials Handling
Description of Activities: Chemical Management
Objective No. 7: Ensure compliance with the REACH regulation
Target Project Update 2010 AER Status
7.1 Ensure that all chemical products used by Intel are pre-registered by a Supplier or Only Representative.
7.1.1 Develop a compliance database of site chemicals, pre-registration communications, restrictions and registration deadlines
Database created successfully. Content of database to be migrated to Intel‟s chemical approval system (MREP) for chemical compliance tracking.
Complete
7.2 Launch MREP (Web-based chemical approval system) IT System.
7.2.1
Prepare site chemicals and MSDS‟s for the chemical approval system (MREP) IT System launch.
MREP system is live. New version MSDSs requested from all site suppliers. New system in place to ensure that suppliers send new version MSDSs to an Intel mailbox for processing and indexing in MREP.
Complete
38
Table 3.9 - Objective No. 8 Status Report
Environmental Aspect/Topic: Air Emissions
Description of Activities: Discharge of CFC's and HCFC's from Refrigeration Equipment
Objective No. 8: Ensure compliance with the revised ODS Regulations and the Irish F-Gas Regulations
Target Project Update 2010 AER Status
8.1 Implementation of Management Systems to ensure compliance with all aspects of the Regulations
8.1.1 Specify a Software System for the management of all refrigerants on site.
A Software System for the management of refrigerant data was identified and evaluated over the course of 2010. The system was placed on order in January 2010 and is expected to be implemented over the course of Q2 2011.
In Progress
39
Table 3.10 - Objective No. 9 Status Report
Environmental Aspect/Topic: Resource Utilisation
Description of Activities: Use of Electricity
Objective No. 9: Implement Energy Reduction Projects and contribute to the Corporate Goal of 5% normalised energy consumption reduction
Target Project Update 2010 AER Status
9.1 Implement Energy Reduction Projects that provide annualised energy reduction of 1% relative to H'2008 and H1'2009 energy usage (Update 2010 AER – the overall target was achieved. Please refer to individual projects for details)
9.1.1 IR5 Further Reduction to support F10
IR 5 load reductions achieved (included shutdown of some secondary chilled water pump set and set up of PM procedure for running of pump sets to improve efficiencies).
Complete
9.1.2 F10 Facility Load Opportunities
This project was changed to review facility loads from Fab 24. One project was implemented in 2010 which involved shutting off the mixer unit in the Fab 24 Ammonia buffer tank with no impact to the treatment system process.
Complete
9.1.3 F10 Chiller with IR5 Sort Reduction
Load reductions from IR5 Sort area achieved through de-installation of tools from area and recirculations to area shut off. No impact to area noted.
Complete
9.1.4 Compressor Air Efficiency Improvements Survey completed.
Complete
9.1.5 Implement DSUM ION EEM (monitoring system for energy usage)
Implemented at the site. Complete
9.1.6 IR1 York Air Cooled Chiller Optimisation
IR1 compressor dryer upgrade complete. The new model installed has more efficient air purging.
Complete
9.1.7 IR5 HVAC Improvement Electricity savings achieved. Complete
9.1.8 Reduction of F24 RCTO's to N Units
This project was not pursued due to the fact that Intel corporate direction is to maintain N+1 (duty and standby) RCTO units to assure reliability for manufacturing.
Project not pursued
9.1.9 Fab 24 MAH Heat Recovery Implemented Fab 24 heat recovery system to additional two air handling units on-site. Cold weather damaged coils and replacement coils were purchased to rectify.
Complete
40
Table 3.11 - Objective No. 10 Status Report
Environmental Aspect/Topic: Resource Utilisation
Description of Activities: Use of mains city water
Objective No. 10: Implement water conservation projects and contribute to the corporate goal of reducing normalised water use by 2012 from 2007 levels
Target Project Update 2010 AER Status
10.1 Implement Projects to reduce demand on incoming water by at
least 30 m3/hr
10.1.1 Complete costing for the EDI (Electro-Deionisation) By-Pass Project
Design and initial costing now complete. Complete
10.1.2 Draft White Paper and submit to site management for approval of EDI By-Pass Project.
Unfortunately we will not be in a position to implement this project for the foreseeable future. Following a data review it was deemed to be high risk. With the extra loading that would be forced on the primary mixed beds and increased regenerations, redundancy (N+1) would be compromised. There are also a number of reliability issues throughout the system that need to be addressed first. These prevent reliable quality monitoring. Please note that the site did implement an optimisation project for EDI recovery. The operating parameters of this system have been challenged to recover more water. This will result in annualized savings of water of 268,440 m
3.
Project not pursued
10.1.3 Obtain Management Approval for EDI By-Pass Project.
10.1.4 Implement EDI By-Pass Project (subject to Management Approval)
41
Table 3.12 - Objective No. 11 Status Report
Environmental Aspect/Topic:
EHS Management System
Description of Activities: All Site Activities
Objective No. 11: Continuously improve our environmental and energy management systems to provide improved performance
Target Project Update 2010 AER Status
11.1 Completion of 7 environmental management projects.
11.1.1 Gain successful certification of the Energy Management System to ISO16001
Intel gained certification to EN 16001 in June 2010 and underwent a certification audit in December 2010.
Complete
11.1.2 Review and update EnvironmentalTraining Classes
The Manufacturing Environmental Awareness Class, New Employee Orientation Class and Contractor Orientation Class were reviewed and updated.
Complete
11.1.3 Review of internal environmental auditing process to provide improvements
The internal auditing process was reviewed with key requirements for an audit tracker defined. Intel Ireland worked with Intel Corporation to seek an audit tool for use by all Intel companies. Unfortunately the development of the tool did not go ahead. Intel Ireland will seek an alternative and see if it is possible to get an improved tool for the site.
Open
11.1.4 Review of ICM document management system files
A new document layout was implemented for Environmental Programmes. A new system of titling document was implemented. Explore if all documents in ICM document management system should be put through the document control process in 2011.
Open
11.1.5 Review of Maximo preventative maintenance work orders for Environmental team and update where necessary
Maximo items were reviewed and updated in 2010 and are available on the document management system (ICM).
Complete
11.1.6 Review of process for corrective and preventative actions
This project was not completed due to work associated with implementation of OHSAS 18001 for 2011. This will be included in system design for implementation and integration of ISO14001 and OHSAS 18001.
Open
42
Table 3.12 (continued) - Objective No. 11 Status Report
Environmental Aspect/Topic:
EHS Management System
Description of Activities: All Site Activities
Objective No. 11: Continuously improve our environmental and energy management systems to provide improved performance
Target Project Update 2010 AER Status
11.1.7 Review Communications within EHS group to revise and improve
A new corporate services sharepoint was created in 2010. The environmental section of the EHS webpage was reviewed and updated in 2010. An environmental programme owner‟s document was created in 2010 and is issued with communications on the IPPC licence on an annual basis.
Complete
43
3.3 ENVIRONMENTAL MANAGEMENT PROGRAMME (EMP) SCHEDULE
2011
The 2011 Intel Ireland Objectives and Targets are made up of eleven objectives. The
Register of Aspects was reviewed to take into account any changes in legislation,
incidents or near-misses, corporate or other requirements or any changes to the site
that might have an impact to each aspect score. Based on the highest risks
(significant aspects), the objectives and targets were compiled. In addition, any
objectives and targets required to maintain or improve the environmental
management system were also included.
A summary of the 2011 objectives and targets schedule is provided in Tables 3.13 to
3.23.
Table 3.13 - Objective No. 1 Schedule
Environmental Aspect/Topic: Materials Handling
Description of Activities: Chemical (and Chemical Waste) Storage, Handling and Transportation and Oil Storage, Handling and Transportation
Objective No. 1: Protect surface water and groundwater
Target Project Due Date Owner
1.1 Ensure all bunds onsite that failed hydrostatic tests are repaired and retested.
1.1.1 Complete remedial works for diesel bunds identified in the 2010 bund testing and retest these bunds.
Q3 2011 Env. Engineer
1.1.2 Complete remedial works for chemical bunds identified in the 2010 bund testing and retest these bunds
Q3 2011 Env. Engineer
1.1.3 Complete integrity testing on Fab 14 and Fab 24 Contained Storm System Tanks
Q4 2011 Env. Engineer
44
Table 3.14 - Objective No. 2 Schedule
Environmental Aspect/Topic: Surface Water
Description of Activities: Discharge of surface waters from the site (e.g. rainfall to roof areas, car park etc.) to the Site Retention Pond and Rye water River.
Objective No. 2: Protect surface water
Target Project Due Date Owner
2.1 Ensure all CS Operations Technicians are trained on new bund and sump emptying procedure
2.1.1 Hold training classes to cover all shifts on the new procedure for emptying bunds and sumps onsite.
Q2 2011 Env. Engineer
2.1.2 Incorporate training into storm water training class
Q2 2011 Env. Engineer
Table 3.15 - Objective No. 3 Schedule
Environmental Aspect/Topic: Air Emissions
Description of Activities: Discharge of gaseous and particulate acids to atmosphere from acid scrubbers (e.g. HCl, Total fluorides, HF)
Objective No. 3: Gain better understanding of fluoride within the scrubbed exhaust system
Target Project Due Date Owner
3.1 Increase understanding of the source of fluoride into and from the Fab 24 Scrubbed Exhaust system.
3.1.1 Characterise inlet and outlet scrubber loads.
Q2 2011 Env. Engineer
3.1.2 Review quality of sampling and analysis methods
Q3 2011 Env. Engineer
3.1.3 Identify the sources of fluoride within the system
Q3 2011 Env. Engineer
Table 3.16 - Objective No. 4 Schedule
Environmental Aspect/Topic: Air Emissions
Description of Activities: Discharge of gaseous and particulate acids to atmosphere from acid scrubbers (e.g. HCl, Total fluorides, HF)
Objective No. 4: Gain better understanding of air quality trends through an integrated approach
Target Project Due Date Owner
4.1 Integrated fluoride monitoring programme
4.1.1 Develop an integrated sampling protocol for vegetation, HF diffusion tubes and filter paper
Q4 2011 Env. Engineer
45
Table 3.17 - Objective No. 5 Schedule
Environmental Aspect/Topic: Air Emissions
Description of Activities: Discharge of CFCs, HCFCs and HFCs from refrigeration equipment
Objective No. 5: Compliance with CFC, HCFC and HFC regulations
Target Project Due Date Owner
5.1 Implementation of Management Systems to ensure compliance with all aspects of the Regulations
5.1.1 Fully implement the Refrigerant Compliance Management System on site (including transfer of data from old system and training on new system)
Q2 2011 Env. Engineer
Table 3.18 - Objective No. 6 Schedule
Environmental Aspect/Topic: Chemical Waste
Description of Activities: Generation, collection, storage, transport and landfilling of calcium fluoride/phosphate filter cake.
Objective No. 6: Reduce environmental impact of chemical waste generated by IR site operations.
Target Project Due Date Owner
6.1 Recycle 80% of our chemical waste in line with Intel Corporation.
6.1.1 Fab 10 de-installation work is likely to have an impact on our site chemical waste recycling goals. It is unlikely that we will meet the 80% recycling goal in 2011 due to this project. Site project to find an outlet for our calcium fluoride filter cake will be reviewed again in 2011. This is a long term objective at the site which unfortunately due to technical issues and also waste recovery facilities available to Ireland has not been achieved. It remains a focus for Intel Corporation so therefore is included in our projects.
Market Dependent Timeframe
EHS Manager
Note: Chemical waste at Intel Ireland is defined as all chemical type waste. This definition includes calcium
fluoride filter cake which is classified as non-hazardous waste in line with Irish and EU legislation.
46
Table 3.19 - Objective No. 7 Schedule
Environmental Aspect/Topic: Non-Hazardous Waste
Description of Activities: Generation, collection, storage, transport and tracking of recoverable and disposed non-hazardous waste from the Ireland site
Objective No. 7: Recycle 80% of our solid waste (non-hazardous) generated per year
Target Project Due Date Owner
7.1 Recycle 80% of our non-hazardous waste in line with Intel Corporate targets
7.1.1 Develop re-use of waste cleanroom consumables (Hairnets and booties) as SRF (Solid Recovered Fuel)
Q4 2011 EHS Manager
Table 3.20 - Objective No. 8 Schedule
Environmental Aspect/Topic: Non-Hazardous Waste
Description of Activities: Generation, collection, storage, transport and tracking of recoverable and disposed non-hazardous waste from the Ireland site
Objective No. 8: Manage site non-hazardous waste data effectively
Target Project Due Date Owner
8.1 Single tracking document for all non-hazardous waste permits used by the site
8.1.1 Develop and maintain a controlled tracking document for all non-hazardous waste permits applicable to waste collectors and facilities used by the site
Q2 2011 EHS Manager
8.2 Successful development and implementation of Ireland site Non-Hazardous Waste data management application
8.2.1 Develop, validate and implement a software system which manages all site non-hazardous waste shipment data
Q3 2011 EHS Manager
47
Table 3.21- Objective No. 9 Schedule
Environmental Aspect/Topic: Resource utilization
Description of Activities: Resource utilization e.g. electricity, natural gas, oil and water.
Objective No. 9: Conserve natural resources
Target Project Due Date Owner
9.1 Provide annualised energy savings of $1.668 million in 2011
9.1.1 IR1 Data Center York Air Cooled Chiller Sequencer. Installation of chiller sequencer panel and associated FMS control. The chillers do not use each available stage. Savings from improved efficiencies on chillers.
Q4 2011 CS Engineer
9.1.2 IR1 Data centre evaporative Cooling. Installation of heat exchange and associated pipework to allow use of cooling tower. Savings from reduced chiller electrical load.
Q4 2011 CS Technician
9.1.3 Installation of FMS lighting control in Fab 24 Scrubber area. Lighting control for scrubber area to be put onto FMS. Modifications to be made to existing photocell control wiring.
Q4 2011 CS Technician
Note: Intel Ireland has a specific project tracker for improvement projects as part of its Energy Management System. This is a live database used to log project ideas. This is updated and new projects added regularly. For the EMP only projects with a high confidence level have been included.
Table 3.22 - Objective No. 10 Schedule
Environmental Aspect/Topic: Materials Handling
Description of Activities: Chemical Management
Objective No. 10: Ensure compliance with the REACH regulation
Target Project Due Date Owner
10.1 Use Intel Chemical Approval System (MREP) as REACH compliance database
10.1.1 Content of REACH compliance database to be migrated to MREP for chemical compliance tracking.
Q4 2011 Corporate EHS Engineer
48
Table 3.23 - Objective No. 11 Schedule
Environmental Aspect/Topic: Overall Site Management
Description of Activities: EHS Management Systems
Objective No. 11: Maintain and improve our EHS and energy management systems to international standards
Target Project Due Date Owner
11.1 Ensure our management systems meet the requirements of international standards and Intel Corporation.
11.1.1 Implement OHSAS 18001 management system.
Q4 2011 EHS Manager
11.1.2 Review of ISO14001 related procedures (including internal audits, document control and corrective and preventative actions) for completion of ISO14001 recertification audit
Q3 2011 EHS Manager
11.1.3 Track the finalisation of ISO50001, the new international standard for energy management to transition from EN 16001
Q4 2011 Energy Manager
49
3.4 POLLUTION EMISSION REGISTER
3.4.1 Introduction
This section includes an introduction to Intel‟s PER, a summary of the methodology
used to assess these pollutants and a pollution emission register table.
The Pollution Emission Register (PER) is a requirement of the Integrated Pollution
Prevention and Control Licence (Register No. P0207-03), as issued to Intel Ireland
Ltd. Specifically, under Condition 6.16.1 of the Integrated Pollution Control Licence,
the following is noted:
6.16.1 The licensee shall prepare and maintain a PER for the site. The
substances to be included in the PER shall be agreed by the Agency each
year by reference to the list specified in the Agency’s AER Guidance Note.
The PER shall be prepared in accordance with any relevant guidelines issued
by the Agency and shall be submitted as part of the AER.
As per Condition 6.16.1, Intel Ireland submitted a proposal for the 2010 PER in the
Annual Environmental Report for 2009. This PER includes fluoride and copper and
the rationale for including these parameters has been outlined in the proposal in last
year‟s AER.
3.4.2 Summary of Methodology for Substances Requiring A Full PER
3.4.2.1 Copper
Intel Ireland uses electroplated copper interconnects in the fabrication of
microchips in the 300 mm fabrication facility in F24.
Electroplating facilitates the deposition of a metal film by using current to
provide electrons to convert metal ions to metal atoms at a conductive
interface. A thin copper seed layer is deposited on the silicon wafer prior to
electro-deposition (to provide a conductive layer for the deposition process).
The wafer is then immersed in an electrolytic solution containing copper ions
where deposition of a copper film is accurately controlled by the application of
an electric current. The current is passed between the anode (copper disc)
and the cathode (wafer) where copper metal is deposited on the conductive
seed layer. A copper anode replenishes the electrolytic solution with copper
ions as they are consumed at the cathode.
50
Two tools sets are employed in the thin films process in F24 to facilitate the
electroplating process. After passing through the electroplating tool set, the
wafers proceed to copper polish where the deposited copper films are
polished down. Several metal layers are deposited on each production wafer.
Copper is also used in the copper bump plating tools in the C4 process.
The Fab 24 electroplating process produces copper contaminated waste.
These waste types include concentrated copper waste (CCW), dilute metal
waste (DMW), slurry copper waste (SCW) and spent copper anodes. The
majority of the CCW waste is treated on-site by electro-winning and copper
balls are produced during this process. Both SCW and DMW waste streams
are dilute copper effluents which are treated by ion-exchange prior to
discharge to process wastewater.
The following table (Table 3.24) summarises the inputs and outputs that are
considered in the copper pollution emission register for 2010.
Table 3.24 - Summary Table of Copper Inputs/Outputs
Inputs Outputs
Copper Make-up Solutions CCW Waste Copper Balls
Copper Anodes Concentrated Copper Waste (CCW) Liquid Waste
Copper Media for CCW Dilute Metal Waste (DMW) Resin.
Slurry Copper Waste (SCW) Resin.
Used/Recovered Copper Anodes
Copper deposited onto the wafer/product
Copper in wastewater discharge to Leixlip WWTP
The mass balance contains theoretical estimated averages of copper plated
on wafers and copper anodes and hence, this will contribute to uncertainty in
the results. Therefore, approximately 7% of the copper is unaccounted for but
this may be explained by the estimations used in the mass balance
calculations.
51
3.4.2.2 Fluoride
Intel uses compounds containing fluoride in a number of process steps in the
manufacture of semiconductors. During the process, the wafers pass through
each of the functional areas a number of times to build up a complex 3-D
device on the surface of the wafer. Fluoride is used in its different forms in
the following steps:
Diffusion (Hydrogen Fluoride in gaseous and acid form).
Etch (PFC gases and Hydrogen Fluoride acids).
Thin Films (PFC gases).
Fluoride-containing wastewater is treated on-site by precipitation with calcium
hydroxide to form calcium fluoride as a solid waste.
The following potential inputs/outputs (Table 3.25) are considered in the
fluoride mass balance analysis for 2010.
Table 3.25 - Summary Table of Fluoride Inputs/Outputs
Inputs Outputs
PFCs and other fluorinated gases Fluorine, HF and PFCs in atmospheric emissions
Fluorinated liquid chemicals Fluoride in wastewater emissions
Fluoride in solid waste
For the mass balance for fluoride, Intel assumed that the balance of fluoride
was contained in the calcium fluoride cake. Intel was unable to source a
laboratory to conduct the total fluoride analysis and therefore was unable to
validate the amount of fluoride in the cake.
Therefore, there is some uncertainty associated with the mass balance
results for this parameter.
52
3.4.3 Pollution Emission Register
Facility Identification
Facility Name Intel Ireland Ltd.
Register No. P0207-03
National/Grid Reference 2370(N), 2985(E)
Reporting Period Jan 2010 to Dec 2010
Production units Silicon wafers
Employee No. 4,000
Pollutants Summary
Pollutant
Name
CAS
No.
Input
(Kg)
Gross
Usage
(Kg)
Outputs (Kg)
Air MOM
Liquid
Effluent MOM Waste MOM Product MOM Recovery Treated Unaccounted
Copper
7440-
50-8 10,220 7,186 - - 160 M 4,505 M 3,366 E 2,909 - 721
Fluoride
7782-
41-4 109,350 105,843 7,740 M 14,391 M 83,923 E - - 3,506 - 211
53
3.4.4 Pollution Emission Register (PER) Proposal for 2011
Section 6.16.1 of Intel Ireland‟s IPPC licence number P0207-03 detailed below,
specifies that an agreed PER list shall be included in the AER.
6.16.1 The licensee shall prepare and maintain a PER for the site. The
substances to be included in the PER shall be agreed by the Agency each
year by reference to the list specified in the Agency’s AER Guidance Note.
The PER shall be prepared in accordance with any relevant guidelines issued
by the Agency and shall be submitted as part of the AER.
Pending the requirement to submit a PER in 2011, we propose the following
substances for a full Pollution Emission Register (PER) mass balance:
Total Fluoride
Copper
These substances have been included due to their potential environmental toxicity.
54
4.0 LICENCE-SPECIFIC REPORTS
4.1 GROUNDWATER MONITORING SUMMARY REPORT
Condition 6.1 of the IPPC licence requires that:
The licensee shall carry out such sampling, analyses, measurements,
examinations, maintenance and calibrations as set out below and as in
accordance with Schedule C of this licence.
The required monitoring as specified in Schedule C.6.3 is outlined in Table 4.1
below:
Table 4.1 - IPPC Licence Monitoring Schedule C.6.3
Parameter Monitoring Frequency Analysis method/Technique
pH Biannually pH electrode/meter
COD Biannually Standard Method
Nitrate Biannually Standard Method
Total Ammonia Biannually Standard Method
Total Nitrogen Biannually Standard Method
Conductivity Biannually Standard Method
Chloride Biannually Standard Method
Fluoride Biannually Standard Method
OrganohalogensNote 1
Biannually GC-MS
Note 1: Screening for priority pollutant list substances (such as US EPA volatile and/or semi-volatile
compounds.
Intel Ireland commissioned TMS Environmental Ltd. to carry out the groundwater
sampling and analysis and a summary report for both biannual monitoring events is
detailed in Appendix B.
55
4.2 RIVER RYE WATER MONITORING REPORT
As per Condition 6.1 and Schedule C.6.4 of the IPPC Licence, the River Rye water was
sampled for the following range of parameters:
Intel Ireland commissioned Bord na Móna Environmental Ltd to carry out an assessment of the
quality of surface water at a number of locations along the River Rye, upstream and
downstream of the surface water retention pond outlet (i.e. Intel‟s surface water discharge point
to the river). A summary report for both monitoring events is shown in Appendix C
4.3 LOUISA SPA WATER QUALITY MONITORING REPORT
4.3.1 Introduction
As per Schedule C.6.5 of the site IPPC licence, the following monitoring is required:
56
The services of TMS Environment Ltd. were employed to carry out the sampling and analysis of
this well and their report is summarised in Appendix D.
4.4 BUND TESTING SUMMARY
Under Condition 3.6.6 of Intel Ireland‟s IPPC licence (Register No. P0207-03), Intel Ireland is
required to carry out bund integrity testing at least every three years. Intel Ireland commissioned
Project Management Ltd. to carry out visual bund inspections by a qualified structural engineer
in 2009. In addition, all bunds were assessed to determine whether it was necessary, safe and
practicable to conduct hydrostatic testing in line with the EPA‟s Guidance Note on Storage and
Transfer of Materials for Scheduled Activities. Following on from this report a number of bunds
were hydrostatically tested across the site, results of which are included in Appendix E of this
report. Five bunds failed the hydrostatic testing and Intel will repair and retest these bunds
during 2011.
4.5 UNDERGOUND PIPE AND TANK INTEGRITY TESTING SUMMARY
Under Condition 6.6 of Intel‟s IPPC licence (Register No. P0207-03), Intel Ireland is required to
ensure that:
6.6 The integrity and water tightness of all underground pipes and tanks and their
resistance to penetration by water or other materials carried or stored therein shall be
57
tested and demonstrated by the licensee at least once every three years and reported to
the Agency on each occasion. A written record of all integrity tests and any maintenance
or remedial work arising from them shall be maintained by the licensee.
The Fab 24 process effluent pipe integrity testing was completed in 2010. Debris was found in
line during the first survey and the line was cleaned and resurveyed and found to be in
satisfactory condition. Please refer to Appendix F for full report.
In relation to underground tank testing, Intel commissioned AD Analytical Ltd. to conduct a
retesting of the F10 upper yard tank following both valves in tank being replaced. The tank
passed the integrity test and the report is included in Appendix G.
4.6 AMBIENT AIR MONITORING SUMMARY
Ambient Air Monitoring was carried out at the Intel Ireland facilities in accordance with Schedule
C.6.1 of the IPPC Licence.
The parameters to be measured were oxides of nitrogen (continuous), nitrogen dioxide
(biannual), total fluoride (bi-annual) and total acidity (biannual).
A continuous monitor measuring oxides of nitrogen is installed at the on-site weather station
and the results are trended on a monthly basis.
Nitrogen dioxide diffusion tubes are placed at five locations surrounding the site. Results ranged
from below LOD to 32 µg/m3.
In addition, ambient air monitoring surveys were carried for the following periods:-
4th – 11th June 2010
26th November – 2nd December 2010
These surveys were conducted at two sampling locations, A1 and A2. A1 is located close to the
on-site sports centre (to the south west of the facility) while A2 is located in the field to the north
of the facility.
Total acidity (as HCl) ranged from below LOD to 6.1 µg/m3 and total fluoride ranged from below
LOD to 1.5 µg/m3.
58
4.7 FUGITIVE EMISSIONS PROGRAMME
The company is required under Condition 6.7.2 of the IPPC Licence to maintain a fugitive
emissions program in order to achieve the limits specified in Condition 6.7.1. That condition
specifies that fugitive emission losses shall not exceed 15% of total solvent input.
Fugitive emissions from Intel Ireland are minor and well controlled. They primarily arise from the
use of Isopropyl Alcohol (IPA) used for cleaning of equipment and surfaces within the
cleanrooms. This IPA is used either as saturated wipes or as a liquid in combination with dry
wipes.
On a quarterly basis, “VOC Indicators” are calculated. These calculate the total quantity of
solvents used as well as the fugitive emissions. These calculations confirm that fugitive losses
are well below the limit of 15% (as a percentage of total solvent use) set in Condition 6.7.1. The
company intends to keep in place current controls on the use of IPA to continue to remain in
compliance with this limit.
Furthermore, the company submitted a proposal to the EPA in May 2006 in relation to draft
criteria for shutting down production processes in the event of non-compliance, equipment
failure and/or by-pass. The Agency approved this proposal by letter dated 13th June 2006
subject to a number of conditions including the requirement that “All by-passes (of the VOC
abatement equipment) shall be recorded and included in the fugitive emissions reduction
programme”.
All such by-passes (>1 hour duration) are recorded (and communicated to the Agency) and
these by-passes are included in the calculation of the quarterly VOC Indicators. Every effort is
made to bring the abatement equipment back on line in the shortest possible time.
During 2010, there were 12 periods when VOC abatement equipment was offline across the
site, due to planned shut-downs, preventive maintenance, natural gas interruptions and RCTO
equipment malfunctions. Four of these occurrences ranged from durations of 2 – 6 days, the
remaining 8 occurrences were less than 2 days in duration.
Furthermore, the company retains in place the protocol which was introduced in 2007 to ensure
that by-passes of abatement units are minimised and any by-passes which last for longer than
one week are communicated to and approved by senior site management.
59
4.8 PERFLUORINATED CARBON (PFC) EMISSIONS REPORT
4.8.1 Methodology of PFC Emissions Calculations
Following correspondence between the EPA and Intel Ireland during 1999, the following
programme was agreed on 17th May 1999 under EPA reference M207/GC/11 in relation to
substances that have a significant global warming potential:
In view of the company’s argument that details of gas usage would place the company at
a competitive disadvantage, details of inputs and outputs need not be given in any
written report to the Agency, but individual annual tonnage figures for Emissions of C2F6,
CF4, and SF6 must be reported separately. A full record of how the figures were
calculated must be available on-site at Intel Ireland Ltd to authorised persons of the
Agency at all times.
The tables at the end of this section (Tables 4.7 to 4.10) give individual annual tonnage figures
for emissions of the three gases required by the Agency (C2F6, CF4, and SF6) and a
consolidated figure for three other fluorinated gases (CHF3, NF3 and C4F8). For ease of
comparison between each of the gases and to allow for comparison from year to year, the
emissions have also been expressed as Million Metric Tonnes Carbon Equivalent (MMTCE)
which is a standard way for expressing emissions of PFCs.
The 2010 data was compiled and computed in the following manner:-
Several companies supply Intel Ireland with speciality gases for their manufacturing
process. These gases are issued on a periodic basis from Intel Ireland‟s chemical and
gas warehouses to the fabrication manufacturing plant. Intel Ireland then produces a
report detailing the number and size of gas cylinders issued to the wafer fabrication
operations.
In calculating emissions, a constantly improved method is periodically agreed between
all European semiconductor-manufacturing facilities. These companies are members of
European Semiconductors Industry Association (ESIA). The data from each company is
then collated by this association on an aggregate basis annually to give one emission
data point notated in MMTCE units. (Million Metric Tonnes Carbon Equivalent – a
universally accepted metric for global warming impact). The collation of the Intel Ireland
60
data is kept by the Environmental Engineer on a shared drive within the department‟s
EMS data retention system.
For methodical calculations, the assumption currently adopted within the industry and
ratified by the World Semiconductor Council (WSC) is that an agreed documented % of
each gas is consumed efficiently during manufacturing and conversely a fixed % of gas
is emitted to atmosphere (Tier 2). Such generic assumptions are being refined across
the industry globally under the remit of the WSC. A new calculation methodology has
been adopted by ESIA which takes into account the efficiency of removal of GWP gases
from point of use (POU) abatement devices deployed between the tool and the large on-
site gas scrubbers. In calculating the Metric Tonnes Carbon Equivalent (MTCE)
emission data, there are also assumptions taken on the global warming potential of each
gas and the fact that some gases such as C2F6 after use can also form other by-
products such as CF4. All this information is managed within the ESIA excel
spreadsheets and is summarized in terms of emissions as MMTCE in the table below.
The Global Warming Potential (GWP100) for each of the Gases is taken from the
Intergovernmental Panel on Climate Change (IPCC) 4th Assessment Report. The
GWP100 values have been presented below for information purposes.
GWP100 Values from 4th IPCC Assessment Report
C2F6 GWP = 12,200 CHF3 GWP = 14,800
SF6 GWP = 22,800 NF3 GWP = 17,200
CF4 GWP = 7,390 C4F8 GWP = 10,300
4.8.2 Intel Ireland's Emissions of PFCs
Tables 4.2 and 4.3 give details of emissions of PFCs for 2009 and 2010.
61
Table 4.2 - 2009 Emissions using 4th
IPPC Assessment Report GWP100 Values (Tier 2 Methodology)
Parameter Emissions (Metric Tonnes)
MMTCE
C2F6 4.77 0.016
CF4 0.81 0.002
SF6 0.66 0.004
CHF3, NF3, C4F8 2.57 0.011
Total PFCs 8.81 0.0326
Table 4.3 - 2010 Emissions using 4th
IPPC Assessment Report GWP100 Values (Tier 2 Methodology)
Parameter Emissions (Metric Tonnes)
MMTCE
C2F6 1.85 0.006
CF4 0.70 0.001
SF6 0.44 0.003
CHF3, NF3, C4F8 2.92 0.012
Total PFCs 5.91 0.0227
During 2009 and 2010, Intel Ireland also calculated its emissions using a more precise method
known as "Tier 3". This uses process specific emissions factors for each of the process gases.
This method gives a result which is higher than that calculated by Tier 2. Table 4.4 provides this
data for 2009 while Table 4.5 provides the data for 2010.
62
Table 4.4 - 2009 Emissions using 4th
IPPC Assessment Report GWP100 Values (Tier 3 Methodology)
Parameter Emissions (Metric Tonnes)
MMTCE
C2F6 5.03 0.017
CF4 2.21 0.004
SF6 1.56 0.010
CHF3, NF3, C4F8 2.55 0.011
Total PFCs 11.35 0.0420
Table 4.5 - 2010 Emissions using 4th
IPPC Assessment Report GWP100 Values (Tier 3 Methodology)
Parameter Emissions (Metric Tonnes)
MMTCE
C2F6 2.36 0.008
CF4 1.52 0.003
SF6 0.93 0.006
CHF3, NF3, C4F8 3.12 0.014
Total PFCs 7.93 0.0304*
* Note: - These calculations do not include losses of HFC refrigerant from the site chillers. The global warming impact of these losses has been estimated at 0.0008 MMTCE. If these losses are included in the "Total PFCs" figure above, then the figure would increase by approximately 2.6%.
For a number of years, Intel Ireland has been pursuing various reduction initiatives such as gas
usage reduction with the introduction of each new process technology, gas substitution, for
example, by the replacement of C2F6, in certain recipes, with alternative gases. During 2009,
Intel Ireland completed its project to replace C2F6 on some tools in IFO with a gas which has a
greater utilization rate. This means that the quantity of gas used and PFC emissions (expressed
as MMTCE) are lowered. The benefits of this process change were carried forward into 2010. In
addition, the reduction in production levels in IFO (the main source of PFC emissions on site)
during 2010 also drove a decrease in PFC emissions for the site. Overall, there were a
reduction of approximately 25% in PFC emissions from the site between 2009 and 2010
irrespective of the calculation methodology used.
63
Finally, it should be noted that emission calculation methodologies may well change in the
coming years as improved calculation systems are formally adopted and verified by analytical
methods across the semiconductor associations such as SIA (Semiconductor Industry
Association of America), ESIA (European Semiconductor Industry Association), KIA (Korean
Semiconductor Industry Association), JIA (Japanese Semiconductor Industry Association), to
accommodate, for example, for the introduction of new gases, or alternate point of use
abatement technologies.
4.9 NOISE MONITORING REPORT
A copy of the 2010 Annual Noise Monitoring Report is included in Appendix H of this Report.
4.10 RESIDUAL MANAGEMENT PLAN
As per Condition 10 of the site's IPPC licence, a Residuals Management Plan (RMP) is
maintained for the Intel Ireland site. The RMP, including a separate Environmental Liabilities
Risk Assessment (ELRA) was updated during 2010 and submitted to the Agency on the 2nd
September 2010. In addition, a Validation Report for the stand-down works at Fab 14 was
submitted to the Agency on the same date. Finally, a Statement of Financial Provisions was
submitted to the Agency on the 5th October 2010.
All these documents are awaiting the approval of the Agency.
Appendix A
Pollutant Release and Transfer Register
(PRTR)
4.1 RELEASES TO AIR
SECTION A : SECTOR SPECIFIC PRTR POLLUTANTS
RELEASES TO AIR
Please enter all
quantities in this section
in KGs
POLLUTANT METHOD QUANTITY
Method Used
Acid Gas
Scrubbers
Ammonia
Scrubbers
VOC
Emission
Points
Specilaity
Exhausts
Boilers &
Generators
No.
Annex II Name M/C/E
Method
Code Designation or Description
Emission
Point 1
Emission
Point 2
Emission
Point 3
Emission
Point 4
Emission
Point 5
T (Total)
KG/Year
A (Accidental)
KG/Year F (Fugitive) KG/Year
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
03
Carbon dioxide
(CO2) C ETS
Guideline for the monitoring
and reporting of greenhouse
gas emissions under the
Emissions Trading Scheme 0.0 0.0
3289500.
0 0.0
296055
00.0 32895000.0 0.0 0.0
02
Carbon monoxide
(CO) C OTH Mass Balance calculation 0.0 0.0 6519.0 0.0 2193.0 8712.0 0.0 0.0
04
Hydro-
fluorocarbons
(HFCs) C OTH
Mass Balance Calculations
and Emission Factors to
IPCC Tier 3. Fugitive losses
based upon estimate of loss
from on-site Chillers 284.62 0.0 0.0 0.0 0.0 2447.62 2163.0 0.0
14
Hydrochlorofluoroc
arbons (HCFCs) E ESTIMATE 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
08
Nitrogen oxides
(NOx/NO2) C OTH Mass Balance calculation 0.0 0.0 1268.0 0.0
32532.
0 33800.0 0.0 0.0
05
Nitrous oxide
(N2O) C MAB
Mass Balance Calculations
and Emission Factors 11713.0 0.0 0.0 0.0 0.0 11713.0 0.0 0.0
09
Perfluorocarbons
(PFCs) C OTH
Mass Balance Calculations
and Emission Factors to
IPCC Tier 3 4485.52 0.0 0.0 0.0 0.0 4485.52 0.0 0.0
10
Sulphur
hexafluoride (SF6) C OTH
Mass Balance Calculations
and Emission Factors to
IPCC Tier 3 930.95 0.0 0.0 0.0 0.0 930.95 0.0 0.0
06 Ammonia (NH3) M OTH Colorimetric analysis 0.0 20.9 0.0 0.0 0.0 20.9 0.0 0.0
SECTION B : REMAINING PRTR POLLUTANTS
RELEASES TO AIR
Please
enter all
quantities
in this
section in
KGs
POLLUTANT METHOD
QUANTITY
Method Used
Acid Gas
Scrubbers
No. Annex II Name
M/
C/E
Method
Code
Designation or
Description
Emission
Point 1
Emission
Point 2
T (Total)
KG/Year
A
(Accidental)
KG/Year
F
(Fugitiv
e)
KG/Yea
r
84
Fluorine and
inorganic
compounds (as HF) M
ISO/DIS
15713:20
04 815.0 0.0 815.0 0.0 0.0
SECTION C : REMAINING POLLUTANT EMISSIONS (As required in your Licence)
RELEASES TO AIR
Please
enter all
quantitie
s in this
section
in KGs
POLLUTANT METHOD
QUANTITY
Method Used
Acid Gas
Scrubbers
Ammonia
Scrubbers
VOC
Emission
Points
Speciality
Exhaust
Boilers
&
Genera
tors
Pollutant No. Name
M/
C/E
Method
Code
Designation or
Description
Emission
Point 1
Emission
Point 2
Emission
Point 3
Emission
Point 4
Emissio
n Point
5
T (Total)
KG/Year
A (Accidental)
KG/Year F (Fugitive) KG/Year
227
TA Luft inorganic
dust particles class
1 M CRM
Method based
on USEPA 29 0.0 0.0 0.0 0.83 0.0 0.83 0.0 0.0
228
TA Luft inorganic
dust particles class
2 M CRM
Method based
on USEPA 29 0.0 0.0 0.0 1.57 0.0 1.57 0.0 0.0
229
TA Luft inorganic
dust particles class
3 M CRM
Method based
on USEPA 29 0.0 0.0 0.0 7.47 0.0 7.47 0.0 0.0
230
TA Luft organic
substances class 1 M
EN
13649:20
01 0.0 0.0 278.0 0.0 0.0 278.0 0.0 0.0
231
TA Luft organic
substances class 2 M
EN
13649:20
01 0.0 0.0 233.0 0.0 0.0 233.0 0.0 0.0
232
TA Luft organic
substances class 3 M
EN
13649:20
01 0.0 0.0 2022.0 0.0 0.0 2022.0 0.0 0.0
235 Total acids M
EN 1911-
1 to
3:2003 3595.0 0.0 0.0 0.0 0.0 3595.0 0.0 0.0
351
Total Organic
Carbon (as C) M ALT
Method based
on I.S. EN
13526 0.0 0.0 93.0 0.0 0.0 93.0 0.0 0.0
210 Dust M CRM
Method based
on USEPA 29 0.0 0.0 0.0 152.0 0.0 152.0 0.0 0.0
330 Organic solvents C MAB
Mass balance
calculation 0.0 0.0 0.0 0.0 0.0 3890.0 0.0 3890.0
8 18 26 34 6 6 6 6 SECTION A : PRTR POLLUTANTS
OFFSITE TRANSFER OF POLLUTANTS DESTINED FOR WASTE-WATER TREATMENT OR SEWER
Please enter all quantities in this section in KGs
POLLUTANT METHOD QUANTITY
Method Used
No. Annex II Name M/C/E
Method Code Designation or Description
Emission Point 1
T (Total) KG/Year
A (Accidental) KG/Year
F (Fugitive) KG/Year
17 Arsenic and compounds (as As) M
CRM
U.S. EPA method 200.8 (supplement 1 rev. 5.4 May 1994) 0.78 0.78 0.0 0.0
19 Chromium and compounds (as Cr) M
CRM
U.S. EPA method 200.8 (supplement 1 rev. 5.4 May 1994) 0.25 0.25 0.0 0.0
20 Copper and compounds (as Cu) M
CRM
U.S. EPA method 200.8 (supplement 1 rev. 5.4 May 1994) 160.0 160.0 0.0 0.0
83 Fluorides (as total F) M OTH
Ion chromatography method based on "Standard Methods for the Examination of Water and Wastewater, 2005, 21st edition, Method 4110B published by the APHA, AWWA and WEF 14400.0 14400.0 0.0 0.0
23 Lead and compounds (as Pb) M
CRM
U.S. EPA method 200.8 (supplement 1 rev. 5.4 May 1994) 5.97 5.97 0.0 0.0
22 Nickel and compounds (as Ni) M
CRM
U.S. EPA method 200.8 (supplement 1 rev. 5.4 May 1994) 8.9 8.9 0.0 0.0
12 Total nitrogen M CRM
U.S. EPA method 200.8 (supplement 1 rev. 5.4 May 1994) 48700.0 48700.0 0.0 0.0
76
Total organic carbon (TOC) (as total C or COD/3) M
OTH
Closed reflux calorimetric method based on APHA, 2005, 21st Edition, Method 5220-D. 34800.0 34800.0 0.0 0.0
13 Total phosphorus M OTH
"Standard Methods for the Examination of Water and Wastewater, 2005, 21st edition, Method 4500-PB and Method 4500-PD published by the APHA, AWWA and WEF 3835.0 3835.0 0.0 0.0
24 Zinc and compounds (as Zn) M
CRM
U.S. EPA method 200.8 (supplement 1 rev. 5.4 May 1994) 142.0 142.0 0.0 0.0
79 Chlorides (as Cl) M OTH
Ion chromatography method based on "Standard Methods for the Examination of Water and Wastewater, 2005, 21st edition, Method 4110B published by the APHA, AWWA and WEF 156000.0 156000.0 0.0 0.0
SECTION B : REMAINING POLLUTANT EMISSIONS (as required in your Licence)
OFFSITE TRANSFER OF POLLUTANTS DESTINED FOR WASTE-WATER TREATMENT OR SEWER
Please enter all quantities in this section in KGs
POLLUTANT METHOD
QUANTITY
Method Used
Pollutant No. Name M/C/E
Method Code Designation or Description
Emission Point 1
T (Total) KG/Year
A (Accidental) KG/Year
F (Fugitive) KG/Year
238 Ammonia (as N) M OTH
Method based on APHA, 2005, 21st Edition, Method 4500-NH3 F 48600.0 48600.0 0.0 0.0
303 BOD M OTH
Method based on APHA, 2005, 21st Edition, Method 5210-B. 107800.0 107800.0 0.0 0.0
240 Suspended Solids M OTH
Method based on APHA, 2005, 21st Edition, Method 2540-D 45700.0 45700.0 0.0 0.0
343 Sulphate M OTH
Ion chromatography method based on "Standard Methods for the Examination of Water and Wastewater, 2005, 21st edition, Method 4110B published by the APHA, AWWA and WEF 1150000.0
1150000.0 0.0 0.0
358 Tin M CRM
U.S. EPA method 200.8 (supplement 1 rev. 5.4 May 1994) 1.4 1.4 0.0 0.0
363 Total Dissolved Solids M OTH
Method based on APHA, 2005, 21st Edition, Method 2540C 2050000.0
2050000.0 0.0 0.0
347 Total heavy metals M CRM
U.S. EPA method 200.8 (supplement 1 rev. 5.4 May 1994) 177.0 177.0 0.0 0.0
356 Cobalt M CRM
U.S. EPA method 200.8 (supplement 1 rev. 5.4 May 1994) 0.78 0.78 0.0 0.0
0.0 0.0 0.0 0.0
| PRTR# : P0207 | Facility Name : Intel Ireland Limited | Filename : P0207_2010(1).xls | Return Year : 2010 |
30/03/2011 17:34
5. ONSITE TREATMENT & OFFSITE TRANSFERS OF WASTE
5 99
Please enter all quantities on this sheet in Tonnes
96
Quantity (Tonnes per Year) Method Used
Haz Waste : Name and Licence/Permit No of Next
Destination Facility Non Haz Waste: Name and
Licence/Permit No of Recover/Disposer
Haz Waste : Address of Next Destination Facility
Non Haz Waste: Address of Recover/Disposer
Name and License / Permit No. and Address of Final
Recoverer / Disposer (HAZARDOUS WASTE
ONLY)
Actual Address of Final Destination i.e. Final
Recovery / Disposal Site (HAZARDOUS WASTE
ONLY)
Transfer Destination
European
Waste
Code Hazardou
s Quantity T/Year Description of Waste
Waste Treatment Operation M/C/E
Method Used
Location of
Treatment
Name and Licence / Permit No. of Recoverer / Disposer
/ Broker Address of Recoverer /
Disposer / Broker
Name and Address of Final Destination i.e. Final
Recovery / Disposal Site (HAZARDOUS WASTE
ONLY)
Licence / Permit No. of Final Destination i.e. Final Recovery / Disposal Site (HAZARDOUS WASTE
ONLY)
Within the Country
15 01 01 No 11.22
paper and cardboard packaging R12 M Weighed
Offsite in Ireland
Greenstar West Dublin,W0188-01
MRF West Dublin,Site 14b 3A,Greenogue Industrial Estate,Rathcoole Dublin,Ireland
Within the Country
15 01 02 No 1.26 plastic packaging R12 M Weighed
Offsite in Ireland
Greenstar West Dublin,W0188-01
MRF West Dublin,Site 14b 3A,Greenogue Industrial Estate,Rathcoole Dublin,Ireland
To Other Countries
15 01 02 No 19.37 plastic packaging R3 M Weighed Abroad
Polymer Recovery Ltd.,NCC/E/POL021/EL and NCC/026455
Priory road Prieston ,Boston Lincs,PE22 OJZ,.,United Kingdom
To Other Countries
15 01 02 No 6.84 plastic packaging R3 M Weighed Abroad
Greenstar UK,EPR/FP3396ZN
Plastics Road ,Wilton International,Redcar,TS10 4RG,United Kingdom
Within the Country
15 01 06 No 197.31 mixed packaging R12 M Weighed
Offsite in Ireland
Greenstar West Dublin,W0188-01
MRF West Dublin,Site 14b 3A,Greenogue Industrial Estate,Rathcoole Dublin,Ireland
Within the Country
15 01 06 No 0.59 mixed packaging R12 M Weighed
Offsite in Ireland
Greenstar Millenium Park,W0183-01
Cappagh Road,Ballycoolin,Dublin 11,.,Ireland
Within the Country
15 01 06 No 17.08 mixed packaging R5 M Weighed
Offsite in Ireland
Greyhound Recycling,W0205-01
Crag Avenue Industrial Estate,Clondalkin,Dublin 22,.,Ireland
Within the Country
17 01 07 No 213.44
mixture of concrete, bricks, tiles and ceramics other than those mentioned in 17 01 06 R3 M Weighed
Offsite in Ireland
Premier Waste,WFP-DS-09-0003-01
Unit 6 Premier Business Park,Turnpike Road ,Ballymount,Dublin 6,Ireland
Within the Country
17 02 02 No 7.2 glass R5 M Weighed
Offsite in Ireland
Glassco Recycling Ltd.,WP247-2006
Site 4,Ozberstown Business Park,Naas,Co Kildare,Ireland
Within the Country
19 09 05 No 6.63
saturated or spent ion exchange resins R13 M Weighed
Offsite in Ireland
Greenstar West Dublin,W0188-01
MRF West Dublin,Site 14b 3A,Greenogue Industrial Estate,Rathcoole Dublin,Ireland
Within the Country
19 09 05 No 5.88
saturated or spent ion exchange resins R13 M Weighed
Offsite in Ireland
Greenstar Millenium Park,W0183-01
Cappagh Road,Ballycoolin,Dublin 11,.,Ireland
Within the Country
20 01 01 No 13.32 paper and cardboard R3 M Weighed
Offsite in Ireland Baileys Recycling ,WPT94
Rosemount Business Park,Ballycoolin Road,Dublin 11,.,Ireland
Quantity (Tonnes per Year) Method Used
Haz Waste : Name and Licence/Permit No of Next
Destination Facility Non Haz Waste: Name and
Licence/Permit No of Recover/Disposer
Haz Waste : Address of Next Destination Facility
Non Haz Waste: Address of Recover/Disposer
Name and License / Permit No. and Address of Final
Recoverer / Disposer (HAZARDOUS WASTE
ONLY)
Actual Address of Final Destination i.e. Final
Recovery / Disposal Site (HAZARDOUS WASTE
ONLY)
Transfer Destination
European
Waste
Code Hazardou
s Quantity T/Year Description of Waste
Waste Treatment Operation M/C/E
Method Used
Location of
Treatment
Name and Licence / Permit No. of Recoverer / Disposer
/ Broker Address of Recoverer /
Disposer / Broker
Name and Address of Final Destination i.e. Final
Recovery / Disposal Site (HAZARDOUS WASTE
ONLY)
Licence / Permit No. of Final Destination i.e. Final Recovery / Disposal Site (HAZARDOUS WASTE
ONLY)
Within the Country
20 01 02 No 2.56 glass R13 M Weighed
Offsite in Ireland
Glassco Recycling Ltd.,WP247-2006
Site 4,Ozberstown Business Park,Naas,Co Kildare,Ireland
Within the Country
20 01 02 No 2.0 glass R13 M Weighed
Offsite in Ireland
Greenstar West Dublin,W0188-01
MRF West Dublin,Site 14b 3A,Greenogue Industrial Estate,Rathcoole Dublin,Ireland
Within the Country
20 01 08 No 56.11
biodegradable kitchen and canteen waste R3 M Weighed
Offsite in Ireland
Greenstar West Dublin,W0188-01
MRF West Dublin,Site 14b 3A,Greenogue Industrial Estate,Rathcoole Dublin,Ireland
Within the Country
20 01 08 No 32.4
biodegradable kitchen and canteen waste R9 M Weighed
Offsite in Ireland BEFOS,WMP05/2000
Camphill Ballytobin,Callan,Co. Kilkenny,.,Ireland
Within the Country
20 01 08 No 81.6
biodegradable kitchen and canteen waste R9 M Weighed
Offsite in Ireland
Premier Proteins Ltd,P0045-05
Poolbeg,Balinasloe,Co. Galway,.,Ireland
Within the Country
20 01 11 No 1.07 textiles R3 M Weighed
Offsite in Ireland
Textile Recycling Ltd.,WPR014
Glen Abbey Complex,Begard Road,Tallaght,Dublin 4,Ireland
Within the Country
20 01 11 No 0.22 textiles R3 M Weighed
Offsite in Ireland
Greenstar West Dublin,W0188-01
MRF West Dublin,Site 14b 3A,Greenogue Industrial Estate,Rathcoole Dublin,Ireland
Within the Country
20 01 25 No 5.78 edible oil and fat R9 M Weighed
Offsite in Ireland Frylite Ltd,WPR067
Unit 12 Ballymount Industrial Estate,Ballymount,Dublin 22,.,Ireland
Within the Country
20 01 25 No 0.24 edible oil and fat R3 M Weighed
Offsite in Ireland
Agri Pure/Greenclean Waste Management Ltd,W0222-01
Coldwinters,Blakescross,Lusk,Co. Dublin,Ireland
Within the Country
20 01 36 No 24.99
discarded electrical and electronic equipment other than those mentioned in 20 01 21, 20 01 23 and 20 01 35 R12 M Weighed
Offsite in Ireland
Rehab Recycling,WPR033/2
Unit 77 Broomhill Road,Talaght,Dublin,.,Ireland
Within the Country
20 01 36 No 1.0
discarded electrical and electronic equipment other than those mentioned in 20 01 21, 20 01 23 and 20 01 35 R12 M Weighed
Offsite in Ireland
Greyhound Recycling,W0205-01
Crag Avenue Industrial Estate,Clondalkin,Dublin 22,.,Ireland
Within the Country
20 01 36 No 39.54
discarded electrical and electronic equipment other than those mentioned in 20 01 21, 20 01 23 and 20 01 35 R12 M Weighed
Offsite in Ireland Inmark/Techrec,W0233-01
51 Park West Ind Est.,Nangor Road,Dublin 12,.,Ireland
Within the Country
20 01 38 No 9.02
wood other than that mentioned in 20 01 37 R3 M Weighed
Offsite in Ireland
Greenstar Millenium Park,W0183-01
Cappagh Road,Ballycoolin,Dublin 11,.,Ireland
Within the Country
20 01 38 No 100.56
wood other than that mentioned in 20 01 37 R3 M Weighed
Offsite in Ireland
Greenstar West Dublin,W0188-01
MRF West Dublin,Site 14b 3A,Greenogue Industrial Estate,Rathcoole Dublin,Ireland
Within the Country
20 03 01 No 61.98 mixed municipal waste D5 M Weighed
Offsite in Ireland
Greenstar West Dublin,W0188-01
MRF West Dublin,Site 14b 3A,Greenogue Industrial Estate,Rathcoole Dublin,Ireland
Within the Country
20 03 01 No 309.61 mixed municipal waste R1 M Weighed
Offsite in Ireland
Greyhound Recycling,W0205-01
Crag Avenue Industrial Estate,Clondalkin,Dublin 22,.,Ireland
Within the Country
20 03 06 No 14.0
waste from sewage cleaning D7 M Weighed
Offsite in Ireland
Ringsend Waste Water Treatment Plant,D0034-01
Ringsend ,Dublin 4,.,.,Ireland
Within the Country
20 03 07 No 4.08 bulky waste R12 M Weighed
Offsite in Ireland
Greenstar Millenium Park,W0183-01
Cappagh Road,Ballycoolin,Dublin 11,.,Ireland
Within the Country
20 03 07 No 0.96 bulky waste D5 M Weighed
Offsite in Ireland
Greenstar Millenium Park,W0183-01
Cappagh Road,Ballycoolin,Dublin 11,.,Ireland
Within the Country
20 03 07 No 309.0 bulky waste R12 M Weighed
Offsite in Ireland
Greenstar West Dublin,W0188-01
MRF West Dublin,Site 14b 3A,Greenogue Industrial Estate,Rathcoole Dublin,Ireland
Within the Country
20 03 07 No 72.5 bulky waste D5 M Weighed
Offsite in Ireland
Greenstar West Dublin,W0188-01
MRF West Dublin,Site 14b 3A,Greenogue Industrial Estate,Rathcoole Dublin,Ireland
To Other Countries
11 01 11 Yes 695.0
aqueous rinsing liquids containing dangerous substances (Ammonium sulphate waste) R5 M Weighed Abroad
Koppers UK Ltd.,EA (UK) BV770IL Variation FP3034SE Variation DP3532SR.
Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom
Koppers UK Ltd.,EA (UK) BV770IL Variation FP3034SE Variation DP3532SR.,Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom
Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom
To Other Countries
06 01 01 Yes 36.22
sulphuric acid and sulphurous acid (Concentrated Copper Waste) R6 M Weighed Abroad
Hydrometal SA ,R.I.2/15.97.22 No. DDT/14/MC
Zoning Industrial D Ehein,B-4480,Engis,.,Belgium
Hydrometal SA ,R.I.2/15.97.22 No. DDT/14/MC,Zoning Industrial D Ehein,.,Engis,B-4480,Belgium
Zoning Industrial D Ehein,.,Engis,B-4480,Belgium
To Other Countries
11 01 98 Yes 6.58
other wastes containing dangerous substances (concentrated copper sludge) R4 M Weighed Abroad
Veolia Environmental Services Technical solutions Ltd. (c/o Eco-safe Systems Ltd.),W0054-02
Unit 1A,Allied Industrial Estate ,Kylemore Road Ballyfermot ,D10,Ireland
Mastermelt Refining Services Ltd.,EA (UK) Permit BL132 variation BX127 Variation PP3130LC.,Staden Kane Industrial Estate,Ashbourne Road,Buxton Derbyshire,SK179RZ,United Kingdom
Staden Kane Industrial Estate,Ashbourne Road,Buxton Derbyshire,SK179RZ,United Kingdom
To Other Countries
06 01 01 Yes 263.38
sulphuric acid and sulphurous acid (concentrated metal waste) R6 M Weighed Abroad
Koppers UK Ltd.,EA (UK) BV770IL Variation FP3034SE Variation DP3532SR.
Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom
Koppers UK Ltd.,EA (UK) BV770IL Variation FP3034SE Variation DP3532SR.,Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom
Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom
To Other Countries
11 02 05 Yes 2.66
wastes from copper hydrometallurgical processes containing dangerous substances (copper balls with residual sulphuric acid) R4 M Weighed Abroad
Veolia Environmental Services Technical solutions Ltd. (c/o Eco-safe Systems Ltd.),W0054-02
Unit 1A,Allied Industrial Estate ,Kylemore Road Ballyfermot ,D10,Ireland
Mastermelt Refining Services Ltd.,EA (UK) Permit BL132 variation BX127 Variation PP3130LC.,Staden Kane Industrial Estate,Ashbourne Road,Buxton Derbyshire,SK179RZ,United Kingdom
Staden Kane Industrial Estate,Ashbourne Road,Buxton Derbyshire,SK179RZ,United Kingdom
Within the Country
11 01 10 No 289.38
sludges and filter cakes other than those mentioned in 11 01 09 (calcium fluoride filter cake) D1 M Weighed
Offsite in Ireland
Greenstar (Knockharley Landfill),W146-03
Kentstown,.,.,Co. Meath,Ireland
Within the Country
20 01 21 Yes 2.18
fluorescent tubes and other mercury-containing waste R4 M Weighed
Offsite in Ireland
Irish lamps Recycling Co. Ltd.,WFP-KE-08-0348-01,Woodstock Ind. Estate ,Kilkenny Road ,Athy,Co. Kildare,Ireland
Woodstock Ind. Estate ,Kilkenny Road ,Athy,Co. Kildare,Ireland
Irish lamps Recycling Co. Ltd.,WFP-KE-08-0348-01,Woodstock Ind. Estate ,Kilkenny Road ,Athy,Co. Kildare,Ireland
Woodstock Ind. Estate ,Kilkenny Road ,Athy,Co. Kildare,Ireland
Within the Country
20 01 35 Yes 0.68
discarded electrical and electronic equipment other than those mentioned in 20 01 21 and and 20 01 23 containing hazardous components (lamp fittings) R4 M Weighed
Offsite in Ireland
Irish lamps Recycling Co. Ltd.,WFP-KE-08-0348-01,Woodstock Ind. Estate ,Kilkenny Road ,Athy,Co. Kildare,Ireland
Woodstock Ind. Estate ,Kilkenny Road ,Athy,Co. Kildare,Ireland
Irish lamps Recycling Co. Ltd.,WFP-KE-08-0348-01,Woodstock Ind. Estate ,Kilkenny Road ,Athy,Co. Kildare,Ireland
Woodstock Ind. Estate ,Kilkenny Road ,Athy,Co. Kildare,Ireland
Within the Country
06 04 04 Yes 0.01
wastes containing mercury (mercury switches) R4 M Weighed
Offsite in Ireland
Irish lamps Recycling Co. Ltd.,WFP-KE-08-0348-01,Woodstock Ind. Estate ,Kilkenny Road ,Athy,Co. Kildare,Ireland
Woodstock Ind. Estate ,Kilkenny Road ,Athy,Co. Kildare,Ireland
Irish lamps Recycling Co. Ltd.,WFP-KE-08-0348-01,Woodstock Ind. Estate ,Kilkenny Road ,Athy,Co. Kildare,Ireland
Woodstock Ind. Estate ,Kilkenny Road ,Athy,Co. Kildare,Ireland
To Other Countries
12 01 16 Yes 1.52
waste blasting material containing dangerous substances (arsenic slurry waste) D10 M Weighed Abroad
Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
Within the Country
06 01 04 Yes 140.36
phosphoric and phosphorous acid D9 M Weighed
Offsite in Ireland
Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
To Other Countries
06 01 04 Yes 275.72
phosphoric and phosphorous acid R6 M Weighed Abroad
Koppers UK Ltd.,EA (UK) BV770IL Variation FP3034SE Variation DP3532SR.,Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom
Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom
Koppers UK Ltd.,EA (UK) BV770IL Variation FP3034SE Variation DP3532SR.,Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom
Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom
To Other Countries
11 01 06 Yes 45.44
acids not otherwise specified (reclaim metal waste) D9 M Weighed Abroad
Koppers UK Ltd.,EA (UK) BV770IL Variation FP3034SE Variation DP3532SR.,Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom
Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom
Koppers UK Ltd.,EA (UK) BV770IL Variation FP3034SE Variation DP3532SR.,Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom
Port Clarence Works Huntsman Drive,Huntsman Drive,Port Clarence Middlebrough ,TS21SD ,United Kingdom
Within the Country
11 01 16 Yes 14.45
saturated or spent ion exchange resins (slurry copper waste spent resin) R4 E
Volume Calculation
Offsite in Ireland
Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
To Other Countries
06 13 02 Yes 5.1
spent activated carbon (except 06 07 02) - activated carbon from CCW waste treatment system R1 E
Volume Calculation Abroad Enva Ireland Ltd.,W0041-01
Smithstown Industrial Estate,.,Shannon,Co. Clare,Ireland
Lindenschmidt KG,Waste Disposer code E97095037,Umweltservice,Krombacher Strafe 42-46,57223 Kreuztal,.,Germany
Umweltservice,Krombacher Strafe 42-46,57223 Kreuztal,.,Germany
Within the Country
14 06 03 Yes 1147.07
other solvents and solvent mixtures - mixed solvent waste R2 M Weighed
Offsite in Ireland
Veolia ES Technical Solutions Ltd,W0050-02,Corrin ,.,Fermoy,Co. Cork,Ireland
Veolia ES Technical Solutions Ltd,W0050-02,Corrin Fermoy ,Co. Cork,Ireland
Veolia ES Technical Solutions Ltd,W0050-02,Corrin ,.,Fermoy,Co. Cork,Ireland
Veolia ES Technical Solutions Ltd,W0050-02,Corrin Fermoy ,Co. Cork,Ireland
To Other Countries
11 01 16 Yes 8.27
saturated or spent ion exchange resins D10 M Weighed Abroad
Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
Within the Country
20 01 26 Yes 1.8
oil and fat other than those mentioned in 20 01 25 R9 M Weighed
Offsite in Ireland
Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Enva Ireland Ltd.,W0184-01,Clonminam Industrial Estate ,.,Portlaoise,Co. Laois,Ireland
Clonminam Industrial Estate ,.,Portlaoise,Co. Laois,Ireland
To Other Countries
14 06 01 Yes 0.17
chlorofluorocarbons, HCFC, HFC D10 M Weighed Abroad
Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
Within the Country
17 04 01 No 63.94 copper, bronze, brass R12 M Weighed
Offsite in Ireland Davis Recycling,W0205-01
Hammond Lane Crag Avenue,Clondalkin Ind. Est.,Clondalkin ,Dublin,Ireland
Within the Country
17 04 01 No 28.5 copper, bronze, brass R4 M Weighed
Offsite in Ireland Inmark/Techrec,W0233-01
51 Park West Ind Est.,Nangor Road,Dublin 12,.,Ireland
Within the Country
17 04 01 No 2.42 copper, bronze, brass R4 M Weighed
Offsite in Ireland
Greyhound Recycling,W0205-01
Crag Avenue Industrial Estate,Clondalkin,Dublin 22,.,Ireland
Within the Country
17 04 01 No 15.04 copper, bronze, brass R4 M Weighed
Offsite in Ireland
Hegarty Metals Processors (A1 Metals),ATF WMP007E
Acragar,Mountmellick,Co. Laois,.,Ireland
Within the Country
17 04 02 No 2.26 aluminium R4 M Weighed
Offsite in Ireland
Hegarty Metals Processors (A1 Metals),ATF WMP007E
Acragar,Mountmellick,Co. Laois,.,Ireland
Within the Country
17 04 02 No 353.1 aluminium R4 M Weighed
Offsite in Ireland Davis Recycling,W0205-01
Hammond Lane Crag Avenue,Clondalkin Ind. Est.,Clondalkin ,Dublin,Ireland
Within the Country
17 04 02 No 51.79 aluminium R4 M Weighed
Offsite in Ireland Inmark/Techrec,W0233-01
51 Park West Ind Est.,Nangor Road,Dublin 12,.,Ireland
Within the Country
17 04 05 No 4.67 iron and steel R4 M Weighed
Offsite in Ireland
Hegarty Metals Processors (A1 Metals),ATF WMP007E
Acragar,Mountmellick,Co. Laois,.,Ireland
Within the Country
17 04 05 No 125.02 iron and steel R4 M Weighed
Offsite in Ireland Davis Recycling,W0205-01
Hammond Lane Crag Avenue,Clondalkin Ind. Est.,Clondalkin ,Dublin,Ireland
Within the Country
17 04 05 No 35.24 iron and steel R4 M Weighed
Offsite in Ireland Inmark/Techrec,W0233-01
51 Park West Ind Est.,Nangor Road,Dublin 12,.,Ireland
Within the Country
17 08 02 No 92.72
gypsum-based construction materials other than those mentioned in 17 08 01 R5 M Weighed
Offsite in Ireland Recycle Works,WPT112
Unit 1 Glenroyal Centre,Straffan Road,Maynooth,Co. Kildare,Ireland
Within the Country
19 12 04 No 86.62 plastic and rubber R5 M Weighed
Offsite in Ireland
Greyhound Recycling,W0205-01
Crag Avenue Industrial Estate,Clondalkin,Dublin 22,.,Ireland
Within the Country
19 12 04 No 7.76 plastic and rubber R5 M Weighed
Offsite in Ireland Panda Waste,W0140-03
Neurendale Ltd.,Cappagh Rd,Finglas,Dublin 12,Ireland
Within the Country
20 01 40 No 659.1 metals R4 M Weighed
Offsite in Ireland
Hegarty Metals Processors (A1 Metals),ATF WMP007E
Acragar,Mountmellick,Co. Laois,.,Ireland
Within the Country
20 01 40 No 2.54 metals R12 M Weighed
Offsite in Ireland Baileys Recycling ,WPT94
Rosemount Business Park,Ballycoolin Road,Dublin 11,.,Ireland
Within the Country
20 01 40 No 23.88 metals R4 M Weighed
Offsite in Ireland
Greyhound Recycling,W0205-01
Crag Avenue Industrial Estate,Clondalkin,Dublin 22,.,Ireland
Within the Country
20 01 40 No 635.61 metals R4 M Weighed
Offsite in Ireland Davis Recycling,W0205-01
Hammond Lane Crag Avenue,Clondalkin Ind. Est.,Clondalkin ,Dublin,Ireland
Within the Country
20 01 40 No 15.6 metals R4 M Weighed
Offsite in Ireland Inmark/Techrec,W0233-01
51 Park West Ind Est.,Nangor Road,Dublin 12,.,Ireland
Within the Country
20 01 40 No 5.44 metals R4 M Weighed
Offsite in Ireland
Greenstar Millenium Park,W0183-01
Cappagh Road,Ballycoolin,Dublin 11,.,Ireland
Within the Country
20 01 40 No 55.82 metals R4 M Weighed
Offsite in Ireland
Multi Metals Recycling Ltd.,ESS/15/8/12 (319)
Blessington,Co. Wicklow,.,.,Ireland
Within the Country
20 01 40 No 72.64 metals R4 M Weighed
Offsite in Ireland
Greenstar West Dublin,W0188-01
MRF West Dublin,Site 14b 3A,Greenogue Industrial Estate,Rathcoole Dublin,Ireland
Within the Country
06 01 04 Yes 35.09
phosphoric and phosphorous acid (tank washings) D9 M Weighed
Offsite in Ireland
Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Within the Country
06 02 04 Yes 0.82
sodium and potassium hydroxide (tank washings) D9 M Weighed
Offsite in Ireland
Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Within the Country
11 01 06 Yes 4.09
acids not otherwise specified (tank washings) D9 M Weighed
Offsite in Ireland
Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Within the Country
06 02 01 Yes 26.0
calcium hydroxide (tank washings) D9 M Weighed
Offsite in Ireland
Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Within the Country
06 01 01 Yes 12.0
sulphuric acid and sulphurous acid (tank washings) D9 M Weighed
Offsite in Ireland
Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Within the Country
11 01 11 Yes 19.94
aqueous rinsing liquids containing dangerous substances (tank washings from KD100 system) D9 M Weighed
Offsite in Ireland
Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Enva Ireland Ltd.,W0041-01,Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
Smithstown Industrial Estate,.,Shannon,Co. Clare.,Ireland
To Other Countries
16 06 02 Yes 2.23 Ni-Cd batteries R4 M Weighed Abroad
Rilta Environmental Ltd.,Waste licence 192-02
Block 402 Greenogue Business Park ,Rathcoole,.,Dublin,Ireland
HJ Enthiren & Sons,EA (UK) BL 5598,Darly Dale Smelter ,South Darley ,Matlock Derbyshire,DE42LP,United Kingdom
Darly Dale Smelter ,South Darley ,Matlock Derbyshire,DE42LP,United Kingdom
Within the Country
16 06 04 No 0.41
alkaline batteries (except 16 06 03) R4 M Weighed
Offsite in Ireland
Rilta Environmental Ltd.,Waste licence 192-02
Block 402 Greenogue Business Park ,Rathcoole,.,Dublin,Ireland
To Other Countries
16 06 01 Yes 3.49 lead batteries R4 M Weighed Abroad
Rilta Environmental Ltd.,Waste licence 192-02
Block 402 Greenogue Business Park ,Rathcoole,.,Dublin,Ireland
HJ Enthiren & Sons,EA (UK) BL 5598,Darly Dale Smelter ,South Darley ,Matlock Derbyshire,DE42LP,United Kingdom
Darly Dale Smelter ,South Darley ,Matlock Derbyshire,DE42LP,United Kingdom
To Other Countries
14 06 03 Yes 0.2
other solvents and solvent mixtures (polimide recovery waste SVG/PRW) D10 M Weighed Abroad
Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
To Other Countries
15 02 02 Yes 5.42
absorbents, filter materials (including oil filters not otherwise specified), wiping cloths, protective clothing contaminated by dangerous substances (corrosive solid waste) D10 M Weighed Abroad
Sava GmbH & Co. Kg,A51G00508,Osterweute 125541,.,Brunsbuttel,.,Germany
Osterweute 125541,.,Brunsbuttel,.,Germany
Sava GmbH & Co. Kg,A51G00508,Osterweute 125541,.,Brunsbuttel,.,Germany
Osterweute 125541,.,Brunsbuttel,.,Germany
To Other Countries
15 02 02 Yes 170.54
absorbents, filter materials (including oil filters not otherwise specified), wiping cloths, protective clothing contaminated by dangerous substances D10 M Weighed Abroad
Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
(corrosive solid waste)
To Other Countries
14 06 05 Yes 68.81
sludges or solid wastes containing other solvents (flammable solids) D10 M Weighed Abroad
Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
To Other Countries
15 02 02 Yes 10.18
absorbents, filter materials (including oil filters not otherwise specified), wiping cloths, protective clothing contaminated by dangerous substances (flammable solids) D10 M Weighed Abroad
Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
To Other Countries
16 05 09 No 13.5
discarded chemicals other than those mentioned in 16 05 06, 16 05 07 or 16 05 08 D10 M Weighed Abroad
Ekokem Oy Ab,0395Y0270/11181/YSO/99
P.O. Box 181,.,Rihimaki,FIN-11101,Finland
To Other Countries
15 02 02 Yes 22.16
absorbents, filter materials (including oil filters not otherwise specified), wiping cloths, protective clothing contaminated by dangerous substances D10 M Weighed Abroad
Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
To Other Countries
17 09 03 Yes 321.32
other construction and demolition wastes (including mixed wastes) containing dangerous substances D10 M Weighed Abroad
Sava GmbH & Co. Kg,A51G00508,Osterweute 125541,.,Brunsbuttel,.,Germany
Osterweute 125541,.,Brunsbuttel,.,Germany
Sava GmbH & Co. Kg,A51G00508,Osterweute 125541,.,Brunsbuttel,.,Germany
Osterweute 125541,.,Brunsbuttel,.,Germany
To Other Countries
16 05 07 Yes 0.54
discarded inorganic chemicals consisting of or containing dangerous substances (labpacks) D10 M Weighed Abroad
Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
To Other Countries
16 05 09 No 17.26
discarded chemicals other than those mentioned in 16 05 06, 16 05 07 or 16 05 08 (warehouse chemicals) D10 M Weighed Abroad
Ekokem Oy Ab,0395Y0270/11181/YSO/99,P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
P.O Box 181,FIN-11101,Riihimaki,FIN-11101,Finland
Appendix B
Groundwater Monitoring Summary Report
EXECUTIVE SUMMARY, GROUNDWATER 2010
FOR
INTEL IRELAND LTD, LEIXLIP, CO. KILDARE
RENAITH LYONS
Report Ref: 16925-3
TMS Environment Ltd
21st March 2011
Prepared by: Phoebe Conway
Environmental Consultant
Prepared by
Phoebe Conway
Approved by:
Craig O‟Connor
Senior Consultant
Date:
Approved by
Craig O‟Connor
Senior Consultant
Intel Ireland Ltd: Executive Summary, Groundwater 2010
TMS Environment Ltd Ref. 16925-3
1.0 Scope
This report presents the non-technical executive summary of the analytical results
of groundwater samples collected from monitoring boreholes at the Intel Ireland
Ltd. campus at Leixlip, Co. Kildare in February and August 2010. Sampling was
conducted to satisfy biannual groundwater monitoring requirements as specified in
IPPC Licence reference no. P0207-03.
Full copies of both reports are available through TMS Environment Ltd or Intel
Ireland Ltd. (Report Reference: 16244-1 and 16925-1).
2.0 Executive Summary
Biannual groundwater sampling was carried out on 3rd
, 8th, 9
th and 10
th February
and on 9th, 10
th, 11
th, 12
th and 16
th August 2010 to satisfy the IPPC Licence
requirements of Intel Ireland Ltd. Tables A & B below provide a summary of the
results compared to the EPA Interim Guideline Values (IGVs) and the Drinking
Water Limits (S.I. No. 278 of 2007) for those parameters where available. Results
which exceed the EPA IGVs are shown in bold text.
Historically groundwater on site has shown elevated levels of Conductivity,
Chloride, Total Ammonia and Total Nitrogen have been elevated both up-gradient
and down-gradient of the Intel Ireland Site. This immediately suggests an off-site
source for the elevated concentrations observed. Elevated concentrations are not
uniformly elevated in groundwater across the site, suggesting that it is not a diffuse
source up-gradient of the site. Also, concentrations at individual monitoring points
vary with time, suggesting a discontinuous source with pollution of groundwater
occurring at varying rates (e.g. like a leaking sewer).
On comparison of the 2010 results with the EPA‟s IGVs during 2010, some wells
exceeded the IGV for conductivity during the first monitoring event (MW1, MW4,
MW13, MW14, MW15 and MW16) and the second monitoring event (MW1,
MW4, MW13, MW14, MW15, MW16 and MW17). It is likely that the source of
elevated conductivity originates from off-site due to the fact that MW1 and MW13
are control wells (on the site boundary) and MW14, MW15 and MW16 are
downstream of these wells. In addition, there are no Intel operations between the
site boundary and MW14 and MW15. MW4 has shown historically to have a high
conductivity value above the EPA IGV. MW17 is situated close to MW4 down-
gradient of the site. There has been little change in the background levels for these
wells over the past number of sampling events. The fact that Electrical
Conductivity is elevated both up-gradient and down-gradient of the site
immediately suggests an off-site source for the elevated concentrations observed.
EC concentrations are not uniformly elevated in groundwater across the site,
suggesting that it is not a diffuse source up-gradient of the site. Also,
Intel Ireland Ltd: Executive Summary, Groundwater 2010
TMS Environment Ltd Ref. 16925-3
concentrations at individual monitoring points vary with time, suggesting a
discontinuous source with pollution of groundwater occurring at varying rates (e.g.
like a leaking sewer).
The concentration for chloride recorded in a number of wells exceeded the EPA
IGV of 30mg/l in the first biannual monitoring event (MW1, MW2, MW4, MW7,
MW11, MW12, MW13, MW14, MW15, MW16 and MW19) and the second
biannual monitoring event (MW1, MW2, MW4, MW5, MW7, MW8, MW10,
MW11, MW12, MW13, MW14, MW15, MW16, MW17, MW19 and MW20).
Chloride has been historically elevated above the EPA IGV in MW1, MW2,
MW5, MW13, MW14, MW16 and MW19. It can be demonstrated that the source
of elevated chloride is likely to originate from off-site due to the fact that MW1
and MW13 are control wells (on site boundary) and MW14, MW15 and MW16
are downstream of these well. In addition, there are no Intel operations between
the site boundary and MW14 and MW15. Concentrations above the EPA IGV in
MW4, MW5, MW7, MW8, MW10, MW11, MW12, MW17 and MW20 are not
historically as consistently elevated. On examination of the historical chloride
results for all the wells on site, there is a background level of approximately 25-30
mg/l, as would be expected for this area of Ireland. Chloride concentrations are
consistently elevated in monitoring well MW1 up-gradient of the site and MW14
at the eastern perimeter of the site. Sampling of other wells shows occasionally
elevated concentrations above background, however the elevated concentrations
are not sustained.
Total Ammonia was found to exceed the EPA IGV of 0.15 mg/l as NH4 in six well
during the first biannual monitoring event (MW4 (0.298 mg/l as NH4), MW5
(0.171 mg/l as NH4), MW7 (2.13 mg/l as NH4), MW8 (0.235mg/l as NH4), MW14
(0.224 mg/l as NH4), and MW18 (0.151 mg/l as NH4). The presence of Total
Ammonia in groundwater in the up-gradient wells (MW7 & MW8) suggests an
off-site source of organic pollution. The two possible off-site sources up-gradient
of the site are the Local Authority sewer running along the Maynooth - Leixlip
road and agricultural activity up-gradient of the site. Given that the agricultural
land up-gradient of Intel does not appear to be intensively grazed, the likely source
is the Local Authority sewer. MW14 and MW18 are situated to the north and
north-east of MW7 and as the groundwater flow direction is in a north north-
easterly direction it is suggested that the rise in Total Ammonia at these locations is
due to external factors. There were no exceedances to Total Ammonia during the
second biannual monitoring event.
All results reported for the first biannual monitoring event carried out in February
2010 were below the Drinking Water Limits set out in S.I. No. 278 of 2007 with
the exception of Total Ammonia in MW7. A Total Ammonia concentration of 2.13
mg/L NH4 was recorded in this well. The Drinking Water Limit for Total
Ammonia as NH4 is 0.3 mg/l as NH4. The Total Ammonia level in this well had
Intel Ireland Ltd: Executive Summary, Groundwater 2010
TMS Environment Ltd Ref. 16925-3
reduced to below the laboratory detection limit by the next sampling round in
August 2010. All Total Ammonia results for the second biannual monitoring event
in August were below the Drinking Water Limits set out in S.I. No. 278 of 2007.
No Volatile Organic Compounds (VOCs) were detected above the laboratory
detection limit in any groundwater samples tested during 2010.
All remaining parameters analysed were found to be below the EPA IGV and the
Drinking Water regulations during 2010.
An interesting observation on groundwater quality in the August 2010 monitoring
round was that the pH of groundwater was noticeable lower in most wells than in
previous monitoring rounds. Groundwater from most wells showed a reduction in
pH of between 0.2 - 1.0 from the average value observed over the last 9 sampling
rounds. The slightly reduced pH values are still within the typical range
encountered in shallow Irish aquifers (6.5-9.5). There has been no change in
sampling methodology and pH has been measured in the laboratory in all cases.
Since this trend is seen in most wells in August 2010, it was therefore most likely
due to natural variation in background groundwater quality. No further action is
required.
Intel Ireland Ltd: Executive Summary, Groundwater 2010
TMS Environment Ltd Ref. 16925-3
Table A First Biannual Monitoring Results (February 2010) Summary Table
Parameter Units MW1 MW2 MW3 MW4 MW5 MW7 MW8 MW9 MW10 EPA Interim Guideline
Value (IGV)
Drinking Water Limits (S.I. No. 278
of 2007) pH 7.2 7.7 7.5 7.3 7.4 7.2 7.6 7.3 7.3 ≥6.5 and ≤9.5 ≥6.5 and ≤9.5
Conductivity µS/cm 1149 590 720 1365 770 754 702 602 671 1000 µS/cm 2500 µS/cm
COD mg/l O2 10 <5 9 24 <5 <5 <5 10 9 - -
Nitrate mg/l NO3 2.3 1.3 1.4 3.6 1.5 1.5 14 3.9 1.1 25 mg/l NO3 50 mg/l NO3
Total Ammonia mg/l (as NH4) 0.084 0.042 0.11 0.298 0.171 2.13 0.235 <0.017 <0.017 0.15 mg/l as NH4 0.3 mg/l as NH4
Total Nitrogen mg/l N <1.2 1.8 3.1 3.1 3.3 1.8 3.7 <1.2 2 - -
Chloride mg/l Cl 132 43 29 88 28 33 30 1 27 30 mg/l Cl 250 mg/l Cl
Fluoride mg/l F 0.27 0.37 0.23 0.618 0.86 0.287 0.116 0.2 0.23 1 mg/l F 1.5 mg/l F
Parameter Units MW11 MW12 MW13 MW14 MW15 MW16 MW17 MW18 MW19 MW20 EPA Interim Guideline
Value (IGV)
Drinking Water Limits (S.I. No. 278 of 2007)
pH 7.3 7.4 7.1 7.4 7.2 7.2 7.5 7.5 7.2 7.3 ≥6.5 and ≤9.5 ≥6.5 and ≤9.5 Conductivity µS/cm 723 629 1164 1241 1084 1215 909 346 902 766 1000 µS/cm 2500 µS/cm
COD mg/l O2 66 9 <5 17 24 <5 <5 58 <5 5 - -
Nitrate mg/l NO3 2.4 1.4 1.2 3.5 1 18 1.2 1.2 5.4 26 25 mg/l NO3 50 mg/l NO3
Total Ammonia mg/l (as NH4) <0.017 0.025 0.092 0.224 0.063 <0.013 0.07 0.151 <0.017 <0.017 0.15 mg/l as NH4 0.3 mg/l as NH4
Total Nitrogen mg/l N 1.8 <1.2 4 2.6 3.5 6.3 2.5 2.3 4 7.7 - -
Chloride mg/l Cl 46 33 34 205 34 127 24 11 83 30 30 mg/l Cl 250 mg/l Cl
Fluoride mg/l F 0.36 0.78 0.221 0.735 0.206 0.163 0.455 0.492 0.633 0.19 1 mg/l F 1.5 mg/l F
Intel Ireland Ltd: Executive Summary, Groundwater 2010
TMS Environment Ltd Ref. 16925-3
Table B Second Biannual Monitoring Results (August 2010) Summary Table
Parameter Units MW1 MW2 MW3 MW4 MW5 MW7 MW8 MW9 MW10 EPA Interim Guideline
Value (IGV)
Drinking Water Limits (S.I. No. 278
of 2007) pH 6.59 6.51 6.75 6.58 6.72 6.98 6.57 6.70 6.75 ≥6.5 and ≤9.5 ≥6.5 and ≤9.5 Conductivity µS/cm 1055 638 733 1176 879 660 888 709 729 1000 µS/cm 2500 µS/cm
COD mg/l O2 < 5 6 < 5 < 5 < 5 < 5 < 5 < 5 < 5 - -
Nitrate mg/l NO3 1.78 < 1 1.79 16.9 < 1 2.89 11.9 2.81 1.79 25 mg/l NO3 50 mg/l NO3
Total Ammonia mg/l (as NH4) 0.015 <0.013 <0.013 <0.013 0.094 <0.013 0.026 <0.013 <0.013 0.15 mg/l as NH4 0.3 mg/l as NH4
Total Nitrogen mg/l N 1.4 1.5 < 1.2 3.8 1.2 2.7 2.7 1.4 < 1.2 - -
Chloride mg/l Cl 99 47 29 39 35 34 46 27 34 30 mg/l Cl 250 mg/l Cl
Fluoride mg/l F 0.34 0.33 < 0.02 0.363 0.68 0.220 < 0.02 < 0.02 0.494 1 mg/l F 1.5 mg/l F
Parameter Units MW11 MW12 MW13 MW14 MW15 MW16 MW17 MW18 MW19 MW20 EPA Interim
Guideline Value (IGV)
Drinking Water Limits (S.I. No. 278 of 2007)
pH 6.72 7.24 6.95 7.22 7.13 7.14 7.15 6.96 7.44 6.97 ≥6.5 and ≤9.5 ≥6.5 and ≤9.5 Conductivity µS/cm 728 712 1167 1294 1123 1410 1016 632 930 708 1000 µS/cm 2500 µS/cm
COD mg/l O2 9 < 5 < 5 < 5 < 5 6 8 1485 10 < 5 - -
Nitrate mg/l NO3 8.31 2.36 1.96 3.76 2.01 9.97 2.19 1.85 6.25 7.3 25 mg/l NO3 50 mg/l NO3
Total Ammonia mg/l (as NH4) 0.013 0.017 <0.013 0.084 <0.013 <0.013 0.067 <0.013 <0.013 0.024 0.15 mg/l as NH4 0.3 mg/l as NH4
Total Nitrogen mg/l N 1.9 1.3 1.2 < 1.2 3.2 3.5 < 1.2 1.4 2.2 2.2 - -
Chloride mg/l Cl 47 47 34 202 34 63 40 24 79 34 30 mg/l Cl 250 mg/l Cl
Fluoride mg/l F < 0.02 0.412 < 0.02 0.51 < 0.02 < 0.02 0.337 0.224 0.413 < 0.02 1 mg/l F 1.5 mg/l F
Appendix C
River Rye Monitoring Report
For the Attention of: Prepared by:
Ms. Renaith Lyons Ms. Linda Lenihan
Intel Ireland Ltd. Environmental Scientist
Leixlip
Co. Kildare
Reviewed by:
Mr. Peter Coogan
Monitoring Team Leader
Ref: ECS3714 –2nd Bi-Annual Event 2010
Monitoring Date: 31st August 2010
Reporting Date: September 2010
This report shall not be reproduced except in full, without the approval of Bord na Móna Technical Services.
All queries concerning the report or its contents should be forwarded to the Monitoring Team leader.
BI-ANNUAL SURVEY OF THE RIVER
RYE AT THE INTEL IRELAND SITE,
COLLINSTOWN INDUSTRIAL PARK
LEIXLIP, CO. KILDARE
Intel (Ireland) Ltd. Report No. ECS3714
Bord na Móna Technical Services Page 2
September, 10
Executive Summary/Certification of Results
Intel (Ireland) Ltd. is required to carry out an assessment on a bi-annual basis, at its site in Leixlip,
Co. Kildare, of the water quality of the River Rye to comply with Schedule C.6.4. (Receiving Water
Monitoring) of its Integrated Pollution Prevention and Control Licence, Reg. No. P0207-03. Bord
na Móna Technical Services was contracted to assess the quality of surface waters at a number of
points along the river, including upstream and downstream of the surface water retention outlet (i.e.
discharge point to the river).
The site was visited by Bord na Móna Environmental Scientists on the 18th
of May and the 31st
of August 2010, to conduct the first and second bi-annual assessments, respectively. A total of
five surface water samples were returned to the laboratory for analysis. Results obtained were
compared with the European Communities “Environmental Objectives (Surface Waters)
Regulations, 2009 (S.I. No. 272 of 2009)”, the European Communities “Quality of Surface
Water Intended for the Abstraction of Drinking Water Regulations, 1989 (S.I. No. 294 of 1989)”
and the European Communities “Quality of Salmonid Waters Regulations, 1988 (S.I. No. 293 of
1988)”.
The surface water samples taken from the River Rye, both upstream and downstream of the Intel
facility, are of good quality; and there are no exceedences of the legislative limits for any of the
parameters measured.
There does not appear to be a deterioration of water quality downstream of the Intel (Ireland)
Ltd. site, indicating that the surface water discharges from this site are not resulting in significant
environmental impacts on the receiving waters.
The results of the investigation carried out by Bord na Móna Technical Services are presented in
Tables 1 and 2 below.
Intel (Ireland) Ltd. Report No. ECS3714
Bord na Móna Technical Services Page 3
September, 10
Table 1: Results of Surface Water Samples for First Bi-annual Analysis (May 2010
ECS3630)
TABLE 1: RESULTS OF SURFACE WATER SAMPLES CHEMICAL ANALYSIS
Surface Water Sampling Locations
Parameter RW-1 RW-2 RW-3 RW-4 RW-5 WQS
pH (pH units) 8.2 8.2 8.2 8.2 8.2 6.0 – 9.0 Note 1
Temperature (°C) 14.0 14.2 14.1 14.0 13.8 25 Note 2
Dissolved Oxygen (%) 132.6 137.9 138.2 135.0 131.6 >80% Note 1
Ammonia-N (mg/l) 0.05 0.07 0.06 0.06 0.13 High Status: ≤ 0.04
Good Status ≤0.065 Note 1
B.O.D. (mg/l) <2 <2 <2 <2 <2 High Status: ≤ 2.2
Good Status: ≤2.6 Note
1
Conductivity (µS/cm @
25°C) 627 618 617 612 614 1000
Note 2
Suspended Solids (mg/l) <5 <5 <5 <5 <5 25Note3
Chloride (mg/l) 25.27 25.21 25.31 25.29 26.11 250 Note 2
Fluoride (mg/l) <0.10 <0.10 <0.10 <0.10 <0.10 1.0 Note 2
Nitrate-N (mg/l) 0.99 0.96 0.96 0.92 0.95 11.29 *
Note 2
Nitrite-N (mg/l) <0.03 <0.03 <0.03 <0.03 <0.03 0.02 Note 3
Total Phosphorus (mg/l) <0.05 <0.05 <0.05 <0.05 <0.05 -
Arsenic (µg/l) <2 <2 <2 <2 <2 50 Note 2
Cobalt (µg/l) <2 <2 <2 <2 <2 -
Copper (µg/l) <2 <2 <2 <2 2 50 Note 2
Lead (µg/l) <2 <2 <2 <2 <2 50 Note 2
Nickel (µg/l) <2 <2 <2 <2 <2 -
Tin (µg/l) <2 <2 <2 <2 <2 -
Chromium (µg/l) <2 <2 <2 <2 <2 50 Note 2
Note: River Rye sampling points located upstream of the Intel surface water discharge point are shaded in blue.
Note 1: European Communities Environmental Objectives (Surface Waters) Regulations, 2009 (S.I. No. 272 of 2009).
Note 2: S.I. 294 of 1989: Water Quality Standard = Water Quality Standards set in the European Communities (Quality of
Surface Water Intended for the Abstraction of Drinking Water) Regulations, 1989. Limit values for A1 waters are shown.
Note 3: European Communities (Quality of Salmonid Waters) Regulations, 1988 (S.I. No. 293 of 1988)
< Indicates less than the laboratory detection limit
WQS = Water Quality Standard
* Converted Water Quality Standard for Nitrite, Nitrate and Ammonia as N (mg/l).
Intel (Ireland) Ltd. Report No. ECS3714
Bord na Móna Technical Services Page 4
September, 10
Table 2: Results of Surface Water Samples for Second Bi-annual Analysis (August 2010
ECS3714)
TABLE 2: RESULTS OF SURFACE WATER SAMPLES CHEMICAL ANALYSIS
Surface Water Sampling Locations
Parameter RW-1 RW-2 RW-3 RW-4 RW-5 WQS
pH (pH units) 7.9 8.1 8.2 8.3 8.3 6.0 – 9.0 Note 1
Temperature (°C) 12.8 12.7 13.0 13.9 13.0 25 Note 2
Dissolved Oxygen (%) 95.8 101.5 115.6 121.5 117.5 >80% Note 1
Ammonia-N (mg/l) 0.02 <0.02 <0.02 0.02 0.02 High Status: ≤ 0.04
Good Status ≤0.065 Note 1
B.O.D. (mg/l) <2 <2 2 <2 <2 High Status: ≤ 2.2
Good Status: ≤2.6 Note
1
Conductivity (µS/cm @
25°C) 725 761 722 662 687 1000
Note 2
Suspended Solids (mg/l) <5 <5 <5 <5 <5 25Note3
Chloride (mg/l) 28.90 28.55 29.64 29.20 31.26 250 Note 2
Fluoride (mg/l) 0.11 <0.10 0.10 0.13 <0.10 1.0 Note 2
Nitrate-N (mg/l) 0.78 0.75 0.71 0.68 0.70 11.29 *
Note 2
Nitrite-N (mg/l) <0.03 <0.03 <0.03 <0.03 <0.03 0.02 Note 3
Total Phosphorus (mg/l) 0.07 0.05 0.05 0.05 0.05 -
Arsenic (µg/l) <2 <2 <2 <2 <2 50 Note 2
Cobalt (µg/l) <2 <2 <2 <2 <2 -
Copper (µg/l) <2 <2 2 <2 <2 50 Note 2
Lead (µg/l) <2 <2 <2 <2 <2 50 Note 2
Nickel (µg/l) <2 2 <2 <2 <2 -
Tin (µg/l) <2 <2 <2 <2 <2 -
Chromium (µg/l) <2 <2 <2 <2 <2 50 Note 2
Note: River Rye sampling points located upstream of the Intel surface water discharge point are shaded in blue.
Note 1: European Communities Environmental Objectives (Surface Waters) Regulations, 2009 (S.I. No. 272 of 2009).
Note 2: S.I. 294 of 1989: Water Quality Standard = Water Quality Standards set in the European Communities (Quality of
Surface Water Intended for the Abstraction of Drinking Water) Regulations, 1989. Limit values for A1 waters are shown.
Note 3: European Communities (Quality of Salmonid Waters) Regulations, 1988 (S.I. No. 293 of 1988)
< Indicates less than the laboratory detection limit WQS = Water Quality Standard
* Converted Water Quality Standard for Nitrite, Nitrate and Ammonia as N (mg/l).
Intel (Ireland) Ltd. Report No. ECS3714
Bord na Móna Technical Services Page 5
September, 10
Respectively submitted,
_______________________ _________________________
Ms. Linda Lenihan Mr. Peter Coogan
Environmental Scientist Monitoring Team Leader
Appendix D
Louisa Spa Monitoring Report
EXECUTIVE SUMMARY, LOUISA SPA 2010
FOR
INTEL IRELAND LTD, LEIXLIP, CO. KILDARE
RENAITH LYONS
Report Ref: 16955-1
TMS Environment Ltd
21st March 2011
Prepared by: Phoebe Conway
Environmental Consultant
Prepared by
Phoebe Conway
Approved by:
Craig O‟Connor
Senior Consultant
Date:
Approved by
Craig O‟Connor
Senior Consultant
Intel Ireland Ltd: Executive Summary, Louisa Spa 2010
TMS Environment Ltd Ref. 16955-1
1.0 Scope
This report presents the non-technical executive summary of analysis of a sample
collected from the Louisa Spa well at Louisa Bridge, which is east of the Intel
Campus buildings. Sampling was conducted to comply with the annual monitoring
requirements as specified in the sites IPPC Licence Reg. No. P0207-03. A full copy of
the report is available through TMS Environment Ltd or Intel Ireland Ltd. (Report
Reference: 16955).
2.0 Executive Summary
A sample of water was collected from the Louisa Spa Spring at Louisa Bridge, which
is east of the Intel Campus buildings on 16th
August 2010. Sampling was conducted to
comply with the annual monitoring requirements as specified in the sites IPPC
Licence Reg. No. P0207-03.
The water sample was analysed for the following parameters;
Conductivity (field measurement),
pH,
Temperature (field measurement),
Total Ammonia,
Chloride,
Sulphate,
Nitrate,
Nitrite,
Fluoride,
Calcium,
Magnesium,
Sodium,
Potassium,
Total Organic Carbon (TOC) and,
Trace Metals.
Temperature and Conductivity were measured in situ.
The results recorded were compared to the EPA Interim Guideline Values (IGVs) set
in the EPA interim report “Towards Setting Guideline Values for the Protection of
Groundwater in Ireland” and the Irish Drinking Water Limits (S.I. No. 278 of 2007).
The results were found to be within accepted norms with the exception of
Conductivity (1831 µS/cm), Chloride (468 mg/l), Sodium (240 mg/l) and Potassium
(10 mg/l), however these concentrations are similar to the results detected during
previous monitoring events as can be seen from Table 1 below.
Intel Ireland Ltd: Executive Summary, Louisa Spa 2010
TMS Environment Ltd Ref. 16955-1
It may be noted that the Drinking Water limit values are for comparison purposes, and
the spa water is not used as a drinking water source. There has been no significant
change in the monitored water quality to date.
It is unknown whether these elevated concentrations are related to natural background
levels in the groundwater or are due to pollution from up-gradient sources.
Intel Ireland Ltd: Executive Summary, Louisa Spa 2010
TMS Environment Ltd Ref. 16955-1
Table 1: Summary Table of Annual Results
Parameter Unit April 2003
April 2004
April 2005
Oct 2006
April 2007
July 2008
Aug 2009
Aug 2010
EPA Interim Guideline Value (IGV)
Drinking Water Limit (S.I. No. 278 of 2007)
pH - 7.36 7.28 7.41 7.01 7.3 8 8.03 7.85 ≥6.5 and ≤9.5 ≥6.5 and ≤9.5
Conductivity µS/cm @ 25 °C 1670 1746 1711 1634 987 1602 1856 1831 1000 µS/cm 2500 µS/cm
Temperature °C 15.8 16.5 17.2 17.1 15 22.8 18.5 16.7 - -
Total Organic Carbon mg/l C 8.4 - <0.5 1.4 2.8 2.8 3 0.8 No abnormal change No abnormal change
Nitrate mg/l NO3 <1 <5 <1 14 4.3 6.33 1.53 6.97 25 mg/l 50 mg/l
Nitrite mg/l N <0.005 <0.005 <0.005 0.005 <0.005 <0.005 <0.02 0.0231 0.1 mg/l 0.5 mg/l
Chloride mg/l 471 350 31 550 485 435 535 468 30 mg/l 250 mg/l
Sulphate mg/l SO42-
65 55 56 105 58 44 50.5 17.33 200 mg/l 250 mg/l
Fluoride mg/l F 0.49 0.08 0.44 0.19 0.43 0.50 0.39 0.465 1 mg/l 1.5 mg/l
Calcium mg/l 215 169 119 114 65 125 115 116 200 mg/l -
Magnesium mg/l 56 50 30 32 23 31 29 37 50 mg/l -
Sodium mg/l 180 282 222 21 90 210 229 240 150 mg/l 200 mg/l
Potassium mg/l 34.5 8.2 8.8 8 8.1 13 8.4 10 5 mg/l -
Total Ammonia mg/l N 0.5 <0.02 0.08 0.152 0.14 <0.01 0.012 0.011 0.12 mg/l 0.23 mg/l
Copper μg/l 2 <50 <10 - <10 <50 < 50 <50 30 μg/l 2000 μg/l
Tin μg/l <2 <50 <10 110 <10 <10 < 10 <10 - -
Chromium μg/l 3 <50 <10 <5 <5 <5 < 5 <5 30 μg/l 50 μg/l
Cobalt μg/l <0.1 <50 <10 <5 <10 <10 < 10 <10 - -
Lead μg/l <0.5 <50 <5 <10 <10 <10 <10 <10 10 μg/l 25 μg/l
Nickel μg/l <0.6 <50 <10 <10 <20 <20 < 20 <20 20 μg/l 20 μg/l
Iron μg/l 3 <50 370 450 320 <5 < 5 <5 - 200 μg/l
Manganese μg/l 48 <50 54 50 70 <5 < 5 <5 - 50 μg/l
Shaded cells indicate results exceeding the EPA IGV or Drinking Water Limit
< Denotes less than the laboratory detection limit
Appendix E
Bund Test Report
DATA SHEET: BUNDING STRUCTURES
IR1 Bunds
DATA SHEET: BUNDING STRUCTURES
2
Company: Intel Ireland Ltd Photo/sketch:
Figure 4.1 – 4.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 4
Bund Location: West side of IR1 compressor
room building
Bund Description: Chemical store
Bund Dimensions: Complex dimensions main
room is 6m x 4.2m. The depth grove in trench is 0.25m
Vessel(s) –
Materials of Construction: Various drums and plastic containers
Bund Materials of Construction: Masonry
blocks Vessel(s) –
Total Storage Volume: Approximately 1200L in bund (Total permissible storage up to maximum of 2000L with maximum container size not to exceed 458L)
Bund Lining Material: Chemical Resistant
Coating (CRC)
Vessel(s) –
110% of Volume of Largest Vessel: 20l
Bund Retention Volume: 504 l
Vessel(s) –
25% of Total Storage Volume: 300l
Tank Contents: Various cleaning fluids
including lime scale remover, hard surface cleaner, cream cleaner, restroom cleaner and floor polish.
R Phrase (WGK Class): Unknown, assume high risk
Contents: High Risk Condition: Good Action: Hydrostatically test (Where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: The bund is a room with grated trenches around the storage area. Bund appears to be generally intact – no visible cracks internally. The bund is clean and tidy (Fig. 4.1).
Bund Drainage System: Local bund - Trenches along floor of bund. This bund is located inside so is not exposed to rainfall.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
3
Bund ID: West side of IR1 compressor room building ( Chemical store )
Result of Hydrostatic Test: Fail
Date of hydrostatic Test: 25/01/11
Length of test: 18hrs
Measurement at beginning of test: 165mm
Measurement at end of test: 0 mm
Volume Tested to: 3 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Ciaran O Seery Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
4
Company: Intel Ireland Ltd Photo/sketch:
Figure 1.1 – 1.3 Site: Leixlip, Co Kildare
Bund Ref. No.: 1
Bund Location: IR1 - South Of Diesel Storage
Tank
Bund Description: IR1 Fire Pumphouse Diesel
Bund
Bund Dimensions: Complex dimensions
Vessel(s) –
Materials of Construction: Tank plus 2 No. 200L drums
Bund Materials of Construction: Reinforced
concrete kerb
Vessel(s) –
Total Storage Volume: Aprox. 1300L
Bund Lining Material: CRC
Vessel(s) –
110% of Volume of Largest Vessel: 990L
Bund Retention Volume: 850L
Vessel(s) –
25% of Total Storage Volume: 325L
Tank Contents: Diesel
R Phrase (WGK Class): WGK2, R40
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09
Bund & Tank Integrity: The diesel fire pump is located within a reinforced concrete kerbed area within a room and is fully lined with CRC coating. The bund appears to be generally intact – no visible cracks or leaks internally.
Bund Drainage System: Local Bund - If a leak occurs it will be contained in the bund and pumped out manually. This bund is located inside so is not exposed to rainfall.
Result of Visual Inspection: Pass
Housekeeping Issues: There is fire hose and bucket in bund, these should be removed.
Action Required: Investigation should be carried out in relation to the bund capacity not meeting the
requirements of the 110% of the largest vessel in the bund
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
5
Bund ID: IR1 Fire Pumphouse Diesel bund
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 03/02/11
Length of test: 18hrs
Measurement at beginning of test: 200mm
Measurement at end of test: 200mm
Volume Tested to: 1m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Ciaran O Seery Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
6
Company: Intel Ireland Ltd Photo/sketch:
Figure 2.1 – 2.3 Site: Leixlip, Co Kildare
Bund Ref. No.: 2
Bund Location: IR1 - Adjacent to Compressor
Room
Bund Description: Diesel Storage Tank
Bund Dimensions: 5m x 10m x 1.4mH
(0.3mH to inlet pipe in wall from oil loadiing area)
Vessel(s) –
Materials of Construction: Steel
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 25000L
Bund Lining Material: None Vessel(s) –
110% of Volume of Largest Vessel: 27500L
Bund Retention Volume: 72500L Vessel(s) –
25% of Total Storage Volume: 6250L
Tank Contents: Diesel
R Phrase (WGK Class): R40, WGK 2
Contents: High Risk Condition: Poor in areas Action: Remedial action plus hydrostatic testing
(where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally. However significant mossy growth coverage on base of bund and tree/bush growth into northern corner (Fig. 2.2) therefore could not fully inspect.
Bund Drainage System: Sump Level Detection/Alarm on bund. Local bund that is manually pumped to storm sewer.
General observations: Electrical cabling has fallen off the cable tray on the east bund wall of bund. One cable has fallen into the water in sump area (see Fig. 2.2). No labelling on diesel tank.
Result of Visual Inspection: Fail
Housekeeping Issues:
Bund needs to be cleaned as there is a lot of leaf overgrowth in the bund (Fig. 2.3).
Action Required:
Retained liquid should be tested and disposed of appropriately if not rainwater.
Electrical cabling should be removed if not in use or tidied and made safe.
Bund also needs to be cleaned as there is a lot of overgrowth in the bund and leaves
Tanks require labelling to ensure that the correct fill into the tank during refilling and also to ensure that appropriate handling procedures are undertaken in the event of a spill.
Hydrostatic testing (where possible).
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
7
Bund ID: IR1 Bulk Diesel Tank
Result of Hydrostatic Test: Fail
Date of hydrostatic Test:
15/2/11
Length of test: 24hrs
Measurement at beginning of test: 610mm
Measurement at end of test: 470mm
Volume Tested to: 27m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Eamon McIvor Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
8
Company: Intel Ireland Ltd Photo/sketch:
Refer to figures 5.1 – 5.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 5
Bund Location: IR1 – Opposite Chemical Store
Bund Description: Transformers bunds
Bund Dimensions: 3.3m x 2.6m x 0.05mH
Vessel(s) –
Materials of Construction: Steel
Bund Materials of Construction: Concrete
with gravel floor
Vessel(s) –
Total Storage Volume: 490L (T1, T2, T3) and 771L (T4) =
2241L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 848L
Bund Retention Volume: 8630L
Vessel(s) –
25% of Total Storage Volume: 560L
Tank Contents: Transformer Oil
R Phrase (WGK Class):
WGK 2, R45
Contents: High Risk Condition: Poor in areas Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Impractical to hydrostatically test bund as filled with gravel and some wires located low down in the bund.
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09
Bund & Tank Integrity: Difficult to fully inspect as no access to rear of tank as in caged area (Fig 5.1). The bund is made up of reinforced concrete slab with reinforced concrete upstand all around. The area around bund dry. No evidence of leak. Containment area appears to be intact in all transformer bunds except T3; a 2mm wide crack is evident at back of bund (This crack is located above where spill would occur and therefore is not significant).
Bund Drainage System: Local bund – this bund is outside and is subject to rainfall.
General observations: Some debris at back of T1 needs to be removed.
Result of Visual Inspection: Pass
Housekeeping Issues: Debris at back of T1 needs to be removed (Fig 5.2).
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
6
Company: Intel Ireland Ltd Photo/sketch:
Fig 8.1 – 8.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 8
Bund Location: IR1
Bund Description: Petrol Interceptor Tank
Bund Dimensions: 3.2m x 4.4m x Height
unknown (filled with gravel)
Vessel(s) –
Materials of Construction: Plastic vessel
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents: Interceptor Oil R Phrase (WGK Class): R40, WGK 2
Contents: High Risk Condition: Poor in
areas
Action: N/A
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Bund is not currently operating as a bund as it is almost full of gravel and overflowing with water. A petrol interceptor generally does not need to be bunded. They should be checked regularly and kept clean. In this case if the interceptor is not checked regularly and is full then if should be treated as a bund.
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09
Bund & Tank Integrity: Retention in bund (rainwater) which has reduced retention capacity to zero. Full inspection of bund not possible as full of water and leaves (Fig. 8.1). There is pebbles/gravel in this bund (Fig. 8.2).
Bund Drainage System: The bund is full with water and needs to be manually pumped out.
General Observations: No labelling on tank or pipework.
Result of Visual Inspection: Fail
Housekeeping Issues: Ensure that this petrol interceptor is regularly maintained and cleaned or consider
removing the interceptor from this area.
Action Required: It was decided to remove from bund register following on from this assessment
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
7
Company: Intel Ireland Ltd Photo/sketch:
Figure 102.1 – 102.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 102
Bund Location: IR3 Warehouse
Bund Description: IR1 Sort Lift Station (BSG
Waste Water Tanks)
Bund Dimensions: 2.7m x 5.5m x 0.18mH
Vessel(s) –
Materials of Construction: Steel
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 3.99m3 x 2 No. tanks
Bund Lining Material:
CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 4.389m3
Bund Retention Volume: 4.515m3
Vessel(s) –
25% of Total Storage Volume: 1.995 m3
Tank Contents: AWN tanks includes Silca and
Inert Suspended Solids
R Phrase (WGK Class): Low Risk
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09
Bund & Tank Integrity: Area around bund dry. No evidence of leak or cracks (Fig. 102.1).
Bund Drainage System: Local bund - Sump Level Detection/Alarm on bund. Automatically pumped to lift tanks.
General observations: There is no grate over the drainage sump at the back of the bund. There is also some leaves and debris in this drain (Fig. 102.2).
Result of Visual Inspection: Pass
Housekeeping Issues: Debris in drainage sump should be removed. A grate should be fitted to protect the sump
from further debris getting in.
Action Required: None
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
8
Company: Intel Ireland Ltd Photo/sketch:
Figure 103.1-103.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 103
Bund Location: IR1 Boiler Room
Bund Description: MPHW/Chilled water (Tank
No. SN182787)
Bund Dimensions: 0.9m x 1.15m x 0.55mH
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 440L
Bund Lining Material: None – plastic bund Vessel(s) –
110% of Volume of Largest Vessel: 484L
Bund Retention Volume: 570l
Vessel(s) –
25% of Total Storage Volume: 110L
Tank Contents: NALCO 8539 (Scale &
corrosion inhibitor for closed cooling/heating)
Sodium Nitrite & Potassium Hydroxide
R Phrase (WGK Class): R35, R36/38, R50
WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09
Bund & Tank Integrity: Bund appears to be generally intact. (Fig. 103.1)
Bund Drainage System: Local Bund - In the event of a spill bund would be pumped out. This bund is located inside so is not exposed to rainfall.
General observations: Absorbent material in bund floor should be cleaned out (see Fig. 103.2).
Result of Visual Inspection: Pass
Housekeeping Issues:
A lot of materials around this bund on floor should be tidied and moved into correct areas.
Action Required:
Bund needs to be cleaned and bund may need to be moved into a CRC coating bund like the other bunds in this areas. This is to prevent chemical spills/splashes outside the plastic bund.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
9
Bund ID: Bund Ref. No.: 103
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 1/10/10
Length of test: 24 hrs
Measurement at beginning of test: 550mm
Measurement at end of test: 550mm
Volume Tested to: 0.430 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Simon McLain Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
10
Company: Intel Ireland Ltd Photo/sketch:
Figure 104.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 104
Bund Location: IR1 Boiler Room
Bund Description: Nalco Microtreat 3150S
(SN112523)
Bund Dimensions: 0.8m x 1.1m x 0.4mH =
352m3
Vessel(s) –
Materials of Construction: Stainless Steel
Bund Materials of Construction: Stainless
Steel
Vessel(s) –
Total Storage Volume: 280L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 308L
Bund Retention Volume: 352L Vessel(s) –
25% of Total Storage Volume: 70L
Tank Contents:
Sodium Chlorite
R Phrase (WGK Class):
Risk Phrases: R8, R22, R24, R32, R34 WGK 2
Contents: High Risk Condition: Good Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally.
Bund Drainage System: Local Bund - In the event of a spill bund would be pumped out. This bund is located inside so is not exposed to rainfall.
Result of Visual Inspection: Pass
Housekeeping Issues:
None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
11
Company: Intel Ireland Ltd Photo/sketch:
Figure 105.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 105
Bund Location: IR1 Boiler Room
Bund Description: PCW/CHW Chemical
Dosing (Tank no. SN183762)
Bund Dimensions: 0.9m x 1.15m x 0.55mH
Vessel(s) –
Materials of Construction: Plastic vessel
Bund Materials of Construction: Plastic
(PVC)
Vessel(s) –
Total Storage Volume: 440L
Bund Lining Material: None – plastic bund Vessel(s) –
110% of Volume of Largest Vessel: 484L
Bund Retention Volume: 570l
Vessel(s) –
25% of Total Storage Volume: 110L
Tank Contents:
NALCO 2510 (Biocide for closed cooling)
R Phrase (WGK Class):
NALCO 2510 (R20/22, R38, R43, R41, WGK3) 2,2-Dibromo-3-Nitrilo-Propionamide
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally (Fig. 105.1).
Bund Drainage System: Local Bund - In the event of a spill bund would be pumped out. This bund is located inside so is not exposed to rainfall.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
12
Bund ID: Bund Ref. No.: 105
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 1/10/10
Length of test: 24 hrs
Measurement at beginning of test: 550mm
Measurement at end of test: 550mm
Volume Tested to: 0.430 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Simon McLain Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
11
Company: Intel Ireland Ltd Photo/sketch:
Figure 106.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 106
Bund Location: IR1 Boiler Room
Bund Description: PCW/CHW Chemical
Dosing (Tank no. SN183575)
Bund Dimensions: 0.9m x 1.15m x 0.55mH
Vessel(s) –
Materials of Construction: Plastic vessel
Bund Materials of Construction: Plastic
(PVC)
Vessel(s) –
Total Storage Volume: 440L
Bund Lining Material: None – plastic bund Vessel(s) –
110% of Volume of Largest Vessel: 484L
Bund Retention Volume: 570l
Vessel(s) –
25% of Total Storage Volume: 110L
Tank Contents:
NALCO 2536 Plus (Scale & corrosion inhibitor for closed cooling/heating)
R Phrase (WGK Class):
NALCO 2536 plus: (R22, R52, WGK2) Sodium Nitrite
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally (Fig. 105.1).
Bund Drainage System: Local Bund - In the event of a spill bund would be pumped out. This bund is located inside so is not exposed to rainfall.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
12
Bund ID: Bund Ref. No.: 106
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 1/10/10
Length of test: 24 hrs
Measurement at beginning of test: 550mm
Measurement at end of test: 550mm
Volume Tested to: 0.430 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Simon McLain Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
13
Company: Intel Ireland Ltd Photo/sketch:
Figure 6.1-6.4 Site: Leixlip, Co Kildare
Bund Ref. No.: 6
Bund Location: North side of IR1 Compressor
room
Bund Description: IR1 Cooling Tower bund
Bund Dimensions: 9m x 10m x 0.18mH
Vessel(s) –
Materials of Construction: Metal (Aluminium)
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume:
1.2m3
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents: Cooling Tower and pumps
R Phrase (WGK Class): Low Risk
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally. However significant mossy growth coverage on base of bund (Fig. 6.4).
Bund Drainage System: Local - In the event of a spill bund would be pumped out.
General Observations: Pipework to large tanks in poor condition – insulation falling off and pipework rusted (see Fig. 6.2).
Result of Visual Inspection: Pass
Housekeeping Issues: Cone, broken pipes covering and ladder need to be removed from bund (Fig 6.3).. The
broken pipework in the bund needs to be inspected and may need to be repaired or replaced.
Action Required:
Determine vessel volumes
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
14
Company: Intel Ireland Ltd Photo/sketch:
Figure 3.1 – 3.4
Site: Leixlip, Co Kildare
Bund Ref. No.: 3a
Bund Location: IR1 Compressor Room
Bund Description: Automation Chilled water
system - Nalco 8539 (Tank No. SN183834)
Bund Dimensions: 1.2 x 0.9 x 0.6m = 0.648m3 Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 440L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 484L
Bund Retention Volume: 648L
Vessel(s) –
25% of Total Storage Volume: 110L
Tank Contents: Sodium Nitrite & Potassium
Hydroxide
R Phrase (WGK Class): R35, R36/38, R50
WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears to be generally intact.
Bund Drainage System: Local - In the event of a spill bund would be pumped out. This bund is located inside so is not exposed to rainfall.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
15
Bund ID: Bund Ref. No.: 3a
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 1/10/10
Length of test: 24 hrs
Measurement at beginning of test: 550mm
Measurement at end of test: 550mm
Volume Tested to: 0.430 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Simon McLain Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
14
Company: Intel Ireland Ltd Photo/sketch:
Figure 3.1 – 3.4
Site: Leixlip, Co Kildare
Bund Ref. No.: 3b
Bund Location: IR1 Compressor Room
Bund Description: Automation Chilled water
system - Nalco 2510 ( Tank No. SN183817)
Bund Dimensions: 0.9 x 1.2 x 0.55m =
0.594m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic bund
Vessel(s) –
Total Storage Volume: 440L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 484L
Bund Retention Volume: 594L
Vessel(s) –
25% of Total Storage Volume: 110L
Tank Contents: 2,2-Dibromo-3-
nitrilopropionamide
R Phrase (WGK Class): R20/22, R38, R43, R41
WGK3
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears to be generally intact.
Bund Drainage System: Local - In the event of a spill bund would be pumped out. This bund is located inside so is not exposed to rainfall.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
Bund ID: Bund Ref. No.: 3b
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 1/10/10
Length of test: 24 hrs
Measurement at beginning of test: 550mm
Measurement at end of test: 550mm
Volume Tested to: 0.430 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Simon McLain Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
15
Company: Intel Ireland Ltd Photo/sketch:
Figure 3.1 – 3.4
Site: Leixlip, Co Kildare
Bund Ref. No.: 3c
Bund Location: IR1 Compressor Room
Bund Description: CPCW dosing Nalco
2536+ ( Tank No. SN112254)
Bund Dimensions: 1.1 x 0.8 x 0.4m = 0.392m3 Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction: Metal
Vessel(s) –
Total Storage Volume: ~288L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 316.8L
Bund Retention Volume: 392L
Vessel(s) –
25% of Total Storage Volume: 72L
Tank Contents: Sodium Nitrite
R Phrase (WGK Class): R22, WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears to be generally intact.
Bund Drainage System: Local - In the event of a spill bund would be pumped out. This bund is located inside so is not exposed to rainfall.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
Bund ID: Bund Ref. No.: 3c
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 1/10/10
Length of test: 24 hrs
Measurement at beginning of test: 260mm
Measurement at end of test: 260mm
Volume Tested to: 0.275 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Simon McLain Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
16
Company: Intel Ireland Ltd Photo/sketch:
Figure 3.1 – 3.4
Site: Leixlip, Co Kildare
Bund Ref. No.: 3d
Bund Location: IR1 Compressor Room
Bund Description: CPCW dosing - Nalco
2510 ( Tank No. SN112071)
Bund Dimensions: 1.1 x 0.8 x 0.4m = 0.392m3 Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction: Metal bund
Vessel(s) –
Total Storage Volume: ~288L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 316.8L
Bund Retention Volume: 392L
Vessel(s) –
25% of Total Storage Volume: 72L
Tank Contents: 2,2-Dibromo-3-
nitrilopropionamide
R Phrase (WGK Class): R20/22, R38, R43, R41
WGK3
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears to be generally intact.
Bund Drainage System: Local - In the event of a spill bund would be pumped out. This bund is located inside so is not exposed to rainfall.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
17
Bund ID: Bund Ref. No.: 3d
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 1/10/10
Length of test: 24 hrs
Measurement at beginning of test: 260mm
Measurement at end of test: 260mm
Volume Tested to: 0.275 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Simon McLain Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
18
Company: Intel Ireland Ltd Photo/sketch:
See Fig 9.1 –9.4 Site: Leixlip, Co Kildare
Bund Ref. No.: 9
Bund Location: IR1 Generator Bund
Bund Description: IR1 Emergency Generator
Bund
Bund Dimensions: 6.6m x 17m x 0.255mH
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 2m3
Bund Lining Material: N/A
Vessel(s) –
110% of Volume of Largest Vessel: 2.2m3
Bund Retention Volume: 28.6m3
Vessel(s) –
25% of Total Storage Volume: 0.5m3
Tank Contents: Diesel R Phrase (WGK Class): R40, WGK 2
Contents: High Risk Condition: Poor Action: Remedial action plus hydrostatic testing
(where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 9/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally. However significant mossy growth coverage on base of bund and tree/bush growth therefore could not fully inspect.
Bund Drainage System: Local Bund. Reinforced concrete with upstand all around. Bund is constructed in 2 levels, one adjacent to the other and takes runoff from the contractor oil storage bund 7. Sump area has significant liquid retention (most likely rainwater) (see Fig. 9.4) and drainage channel is filled with leaves and plant growth (see Fig. 9.4). Sump level detection/alarm on bund.
Result of Visual Inspection: Fail
Housekeeping Issues: Debris in bund needs to be removed.
Action Required:
Bund needs to be cleaned.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
19
Bund ID: IR1 Generator Bund Diesel Day Tanks
EG12/13
Result of Hydrostatic Test: Pass
Date of hydrostatic Test:
15/2/11
Length of test: 24hrs
Measurement at beginning of test: 130mm
Measurement at end of test: 130mm
Volume Tested to: 1.5 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Eamon McIvor Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
20
Company: Intel Ireland Ltd Photo/sketch:
See Fig 7.1 –7.3 Site: Leixlip, Co Kildare
Bund Ref. No.: 7
Bund Location: IR1 Adjacent to cooling towers
Bund Description: Contractor Oil Storage Area
Bund Dimensions: 9m x 6.2m x 0.1mH
Vessel(s) –
Materials of Construction: Mixture of plastic and metal
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: N/A
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: 5.58m3
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents: Diesel/Synthetic
lubricant/Hydraulic Oil 32 (23l)/ Engine Oil/ Barrel Compactor
R Phrase (WGK Class):
R40, WGK2
Contents: High Risk Condition: Poor Action: Remedial action plus hydrostatic
testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Remote bund - Bund is free draining to petrol interceptor bund and therefore would be impractical to hydrostatic test bund.
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally. However significant mossy growth coverage on base of bund and lots of leaves (Fig. 7.1) therefore could not fully inspect.
Bund Drainage System: Remote Bund: There is a drainage channel in bund leading petrol interceptor bund. Sump area has significant liquid retention (most likely rainwater) (see Fig. 7.2) and drainage channel is filled with leaves/mud (see Fig. 7.3).
Result of Visual Inspection: Fail
Housekeeping Issues: Bund needs to be cleaned as there is a lot of moss and leaves in the bund.
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
21
Company: Intel Ireland Ltd Photo/sketch:
See Fig 148.1 – 148.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 148
Bund Location: IR1 Energy Centre North side
Door S.51
Bund Description: Cooling tower dosing –
Nalco ST49 (Tank No. SN182279)
Bund Dimensions: 0.9 x 1.2 x 0.6m = 0.648m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 440L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 484L
Bund Retention Volume: 648L
Vessel(s) –
25% of Total Storage Volume: 110L
Tank Contents: Sodium Hydroxide & Alkaline
liquid Bromine antimicrobial
R Phrase (WGK Class): R34, R31
WGK 2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Testing would involve taking the primary vessel offline which would impact fab operations
Result of Hydrostatic Test:
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues:
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
22
Company: Intel Ireland Ltd Photo/sketch:
See Fig 148.1 – 148.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 149
Bund Location: IR1 Energy Centre North side
Door S.51 ((Tank no. SN182874)
Bund Description: Cooling tower dosing –
Nalco 3DT249 (Tank no. SN182874)
Bund Dimensions: 0.9 x 1.2 x 0.6m = 0.648m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 440L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 484L
Bund Retention Volume: 648L
Vessel(s) –
25% of Total Storage Volume: 110L
Tank Contents: Methanol & Sodium
Formaldehyde Bisulphite
R Phrase (WGK Class): WGK 2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Testing would involve taking the primary vessel offline which would impact fab operations
Result of Hydrostatic Test:
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues:
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
23
Company: Intel Ireland Ltd Photo/sketch:
N/A Site: Leixlip, Co Kildare
Bund Ref. No.: 154
Bund Location: Contractors Compound –
Hegarty‟s
Bund Description: Chemstore 2DVDM
Bund Dimensions: Complex dimensions
Vessel(s) –
Materials of Construction: Various Plastic & Metal
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: ~83L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 25L
Bund Retention Volume: 235L
Vessel(s) –
25% of Total Storage Volume: 21L
Tank Contents: Wood Preserve, Petrol,
Lubricant, Energal HLP
R Phrase (WGK Class): R40, WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 16/9/09
Bund & Tank Integrity: Bund appears in good condition, this is a new bund and was hydrostatically tested before commissioning.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
24
Bund ID: Bund Ref. No.: 154
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 16/03/11
Length of test: 48 hrs
Measurement at beginning of test: 200mm
Measurement at end of test: 200mm
Volume Tested to: 0.24 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Owen O‟Sullivan Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
25
Company: Intel Ireland Ltd Photo/sketch:
N/A Site: Leixlip, Co Kildare
Bund Ref. No.: 155
Bund Location: Contractors Compound –
Hegarty‟s
Bund Description: Metal Bund No. 2
Bund Dimensions: 2.6 x 1.5 x .5 m
Vessel(s) –
Materials of Construction: Various Plastic & Metal
Bund Materials of Construction: Metal
Vessel(s) –
Total Storage Volume: ~95.5L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 2.2L
Bund Retention Volume: 1950L
Vessel(s) –
25% of Total Storage Volume: 23.875L
Tank Contents: Easy Pour Gel, 91-0002
Activator, Loybond C76 Flooring Adhesive
R Phrase (WGK Class): Assume High Risk
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 16/9/09
Bund & Tank Integrity: Bund appears in good condition,
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
Bund ID: Bund Ref. No.: 155
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 16/03/11
Length of test: 48 hrs
Measurement at beginning of test: 200mm
Measurement at end of test: 200mm
Volume Tested to: 0.44 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Owen O‟Sullivan Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
26
Company: Intel Ireland Ltd Photo/sketch:
N/A Site: Leixlip, Co Kildare
Bund Ref. No.: 156
Bund Location: Contractors Compound – P.J.
Hegarty‟s
Bund Description: Metal Bund No. 1
Bund Dimensions: 2.6 x 1.5 x .5 m
Vessel(s) –
Materials of Construction: Various Plastic & Metal
Bund Materials of Construction: Metal
Vessel(s) –
Total Storage Volume: ~200L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 27.5L
Bund Retention Volume: 1950L
Vessel(s) –
25% of Total Storage Volume: 50L
Tank Contents:
F44 Acrylic Adhesive
F41 Tackefier
Penatron 3003 Part B
Penatron 3003 Part A
R Phrase (WGK Class): Assume High Risk
R20, R36/37/38, R42/43
R20, R36/37/38, R42/43
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 16/9/09
Bund & Tank Integrity: Bund appears in good condition,
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
27
Bund ID: Bund Ref. No.: 156
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 16/03/11
Length of test: 48 hrs
Measurement at beginning of test: 200mm
Measurement at end of test: 200mm
Volume Tested to: 0.44 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Owen O‟Sullivan Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
28
Company: Intel Ireland Ltd Photo/sketch:
N/A Site: Leixlip, Co Kildare
Bund Ref. No.: 157
Bund Location: Contractors Compound –
Mercury
Bund Description: MM12 Chemical Stores
Bund Dimensions: 2.7 x 0.05 x .1.85 m
Vessel(s) –
Materials of Construction: Various Plastic & Metal
Bund Materials of Construction: Metal
Container
Vessel(s) –
Total Storage Volume: ~170L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 6.25L
Bund Retention Volume: 249.75L
Vessel(s) –
25% of Total Storage Volume: 43L
Tank Contents: Old mostly unused chemicals
i.e.
IPS Weld-on P70 clear
Stevens Roofing System: Stevens EP cut edge sealant clean 208638
Tetrahydrofuran
Stevens Roofing System: Stevens EP Seam Cleaner
Xylene
Ethylbenzene
Benzene
PVA Adhesive & Sealer
Mixture of: cis-1,4-Dimethylcyclohexyl dibenzoate and trans-1,4-Dimethylcyclohexyl dibenzoate
Poly Vinyl Alcohol
Tellus Oil
Mobile Synthetic Lubricant
R Phrase (WGK Class): High Risk
R11, R19, R36, R66, R67, WGK1
R11, R19, R36/37, WGK1
R10, R20/21, R38 WGK2
R11, R20, WGK1
R45, R46, R11, R36/38, R48, R23/24/25, R65, WGK3
R53,
R11, R23/25
R40, WGK2
R40, WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 16/9/09
Bund & Tank Integrity: Bund appears in good condition,
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: Quite a lot of the chemicals stored within this container haven‟t been used in some
years. If deemed unnecessary these chemicals should be disposed of appropriately.
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
29
Bund ID: Bund Ref. No.: 157
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 7/3/11
Length of test: 24 hrs
Measurement at beginning of test: 20mm
Measurement at end of test: 20mm
Volume Tested to: 0.1 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Mick Maher Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
30
Fab 10 Bunds
DATA SHEET: BUNDING STRUCTURES
31
Company: Intel Ireland Ltd Photo/sketch:
Figure 18.1 - 18.5 Site: Leixlip, Co Kildare
Bund Ref. No.: 18
Bund Location: F10 UPW (In RODI lab fab 10
building and down the stairs)
Bund Description: UPW
Bund Dimensions: Complex Dimensions
Vessel(s) – Materials of Construction: Room with
drainage to Acid Waste Neutralisation (AWN) treatment system and contains individual smaller bunds that are free-draining to AWN via either the room trenches or pipes.
Bund Materials of Construction:
Concrete/Plastic
Vessel(s) –
Total Storage Volume: 6.6m3
Bund Lining Material: Epoxy Paint
Vessel(s) –
110% of Volume of Largest Vessel: 1.62m3
Bund Retention Volume: 104.7m3
Vessel(s) –
25% of Total Storage Volume: 1.65m3
Tank Contents:
Sodium Hypochlorite 14.5% (T-51R-6-1), Sodium Bisulphite,
Sodium Hydroxide,
Organic Scavenger Units,
Hydrochloric Acid
R Phrase (WGK Class):
WGK 2
R22, R31 WGK 1WGK 1, R35
N/A
WGK 1, R34, R37
Contents: High Risk Condition: Poor in areas Action: Remedial Action
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Bund is free-draining to AWN tanks, therefore cannot hydrostatically test bunded area.
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09
Bund & Tank Integrity: Bund appears to be in relatively good condition. There appears to be rusting on the supports of pipework around the room (Fig. 18.3). Sealant also is coming up on bund floor (Fig. 18.4).
Bund Drainage System: Room with trenches in the floor around the tank areas which are free-flowing to Acid Waste Neutralisation (AWN) wastewater treatment system. General observations: Scaffolding in area is temporary while works take place.
Result of Visual Inspection: N/A
Housekeeping Issues: Puddle under the stairs needs to be mopped. General housekeeping in area should be
maintained as boxes and various pieces of equipment lying around on floor (Fig 18.5).
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
32
Company: Intel Ireland Ltd Photo/sketch:
Figure 17.1 - 17.4 Site: Leixlip, Co Kildare
Bund Ref. No.: 17
Bund Location: F10 Middle yard (south of
F10 UPW)
Bund Description: UPW External Bund
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: Ultrapure water tanks - 2 in No.
97m3, 2 in No.147m
3, and Reverse Osmosis water tank – 1 in
No. 60m3. Total = 548m
3
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 161.7m3
Bund Retention Volume: 35m3
Vessel(s) –
25% of Total Storage Volume: 137m3
Tank Contents:
Di-water Storage tanks
R Phrase (WGK Class): No risk phases assigned
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09
Bund & Tank Integrity: Bund appears to be in relatively good condition. Significant liquid retention in bund from rainwater (Figure 17.2). Slight rusting at join of legs in bund (Figure 17.4).
Bund Drainage System: Local bund - In the event of a spill bund is pumped out. This bund is located outside so is exposed to rainfall. The bund requires regular monitoring to ensure it is kept free of rainwater. This will ensure the retention volume of the bund is not reduced. There is a sump within the bunded area.
Result of Visual Inspection: Pass
Housekeeping Issues: General housekeeping in area should be maintained as timber/metal/drum/plastic and
various pieces of equipment lying around on floor. Mud and leaves should be cleaned out (Figure 17.2). The bund requires regular monitoring to ensure it is kept free of rainwater. Rusting should be monitored.
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
33
Company: Intel Ireland Ltd Photo/sketch:
Figure 10.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 10
Bund Location: F10 Chemical Warehouse
Bund Description: Flammables
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Various, plastic and metal
container and boxes
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 8m3
Bund Lining Material: CRC coating
Vessel(s) –
110% of Volume of Largest Vessel: 1.1m3
Bund Retention Volume:
16.2m3
Vessel(s) –
25% of Total Storage Volume: 2m3
Tank Contents: Flammables R Phrase (WGK Class): WGK 3
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons: Due to safety issues with chemical
compatibility and also due to issues with emptying the bunds once filled with water as there are no sumps associated with these bunds..
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09
Bund & Tank Integrity: Bund appears to be in relatively good condition. Bund is room with CRC coating and CRC coving at walls and floor junction. Trenches across all vehicles door and step over through the pedestrian doors.
Bund Drainage System: Local bund – Trenches in middle of floor which are pumped out.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: Monitor general wear and tear on the bund floor.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
34
Company: Intel Ireland Ltd Photo/sketch:
Figures 11.1 to 11.4 Site: Leixlip, Co Kildare
Bund Ref. No.: 11
Bund Location: F10 Chemical Warehouse
Bund Description: Room
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Various, plastic and metal
container and boxes
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 50m3
Bund Lining Material: CRC coating
Vessel(s) –
110% of Volume of Largest Vessel: 1.1m3
Bund Retention Volume:
21m3
Vessel(s) –
25% of Total Storage Volume: 12.5m3
Tank Contents:
Area contains various chemicals including corrosives, oxidisers and hazardous waste
R Phrase (WGK Class): WGK 3, WGK 1, R34
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons: Due to safety issues with chemical
compatibility and also due to issues with emptying the bunds once filled with water as there are no sumps associated with these bunds..
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09
Bund & Tank Integrity: Bund appears to be in relatively good condition. Bund is room with CRC coating and CRC coving at walls and floor junction. Trenches across all vehicles door and step over through the pedestrian doors.
Bund Drainage System: Local bund – Trenches in middle of floor which are pumped out.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: Monitor general wear and tear on the bund floor.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
35
Company: Intel Ireland Ltd Photo/sketch:
Figure 15.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 15
Bund Location: F10 Chemical Warehouse
Bund Description: Door wells
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Various, plastic and metal
container and boxes
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 50m3 (as per Bund Ref No. 11)
Bund Lining Material: CRC coating
Vessel(s) –
110% of Volume of Largest Vessel: 1.1m3 (as per Bund Ref
No. 11)
Bund Retention Volume:
8m3
Vessel(s) –
25% of Total Storage Volume: 12.5m3 (as per Bund Ref No.
11)
Tank Contents: Door wells area contains
various chemicals
R Phrase (WGK Class): WGK 3
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons: Due to safety issues with
chemical compatibility and also due to issues with emptying the bunds once filled with water as there are no sumps associated with these bunds..
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09
Bund & Tank Integrity: Bund appears to be in relatively good condition. Bund is room with CRC coating and CRC coving at walls and floor junction. Trenches across all vehicles door and step over through the pedestrian doors.
Bund Drainage System: Local bund – Trenches in middle of floor which are pumped out. These are not required to meet bund capacity requirements.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: Monitor general wear and tear on the bund floor.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
36
1 This is the combined retention volume of the HFW treatment plant and reaction room.
Company: Intel Ireland Ltd Photo/sketch:
Fig. 19.1-19.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 19
Bund Location: F10 AWN PIT
Bund Description: HF Treatment Plant
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Cross lined HDPE
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 15m3 (4No. tanks), Total 60m
3
(Included HF reaction room) giving total of 65m3
Bund Lining Material: CRC coating
Vessel(s) –
110% of Volume of Largest Vessel: 16.5m3
Bund Retention Volume:
17.8m31
Vessel(s) –
25% of Total Storage Volume: 16.25m3
Tank Contents:
Sludge Tank 1 (T-57H-10-1)
Filtrate Tank 1 (T-57H-13-1)
Sludge Tank 2 (T-57H-19-1)
Filtrate Tank 2 (T-57H-25-1)
R Phrase (WGK Class): Calcium Flouride & Calcium
Phosphate
Contents: Assume High Risk Condition: Poor Action: Remedial action plus hydrostatic
testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Re-Testing is not required at this time. Current valid testing sheets exist for this bund post project to complete remedial works.
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09
Bund & Tank Integrity: Maintenance works still in progress therefore unable to do full bund inspection.
Drainage System: Local bund - Sump level detection/alarm which manually pumped to sludge tanks. The bund is located in a room that is lined with CRC and coving to walls, trenches located around the room and are approx. 1m to 1.5m from the wall.
Result of Visual Inspection: Pass (Changed from previous fail- AR‟s closed)
Housekeeping Issues: None
Action Required: Existing test certificate Valid. Retesting planned for 2011
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
37
2 This is the combined retention volume of the HFW treatment plant and reaction room.
Company: Intel Ireland Ltd Photo/sketch:
See Fig 20.1 – 20.5 Site: Leixlip, Co. Kildare
Bund Ref. No.: 20
Bund Location: F10 AWN PIT (Go through
the HF Treatment Plant room Bund 19)
Bund Description: HF Reaction Room
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: FRP pvdf lined
Bund Materials of Construction:
Concrete
Vessel(s) –
Total Storage Volume: HF Rxn tanks x 2m3, H2SO4 x 1m
3 =
5m3 include 4 No. tanks from treatment plant (15m
3 each) =
65m3
Bund Lining Material:
CRC
Vessel(s) –
110% of Volume of Largest Vessel: 16.5m3
Bund Retention Volume:
17.8m3 2
Vessel(s) –
25% of Total Storage Volume: 16.25m3
Tank Contents:
Reaction Tank 1
Reaction Tank 2
Sulphuric Acid Tank
R Phrase (WGK Class): Very Toxic and Corrosive Chemicals
R23 R24 R25 R35 R36 R37 R38 R49
WGK 1
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Re-Testing is not required at this time. Current valid testing sheets exist for this bund post project to complete remedial works.
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Bund appears in good condition – recently resurfaced with CRC. Generally clean but dusty with no visible leaks or cracks.
The bund was previously noted for having a number of areas to be repaired, all cracks and damaged areas have been repaired.
Drainage System: Remote bund: The bund is located in a room that is lined with CRC and coving to walls. Sump level detection/alarm which is manually pumped to the reaction tanks in the event of a leak/spill.
Result of Visual Inspection: Pass
Housekeeping Issues: As bund repair work recently took place there are a few bits of pipe near the drain
outlet area, these should be removed. The bund should be cleaned regularly to reduce dust. This will help maintain the CRC.
This bund should be monitored for spillages.
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
38
Company: Intel Ireland Ltd Photo/sketch:
See Fig 98.1 – 98.3 Site: Leixlip, Co. Kildare
Bund Ref. No.: 98
Bund Location: Adjacent to F10 AWN apron
(Beside Bund 20)
Bund Description: F10 Generator/diesel
storage bund (EG2)
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction:
Concrete
Vessel(s) –
Total Storage Volume: 0.9m3
Bund Lining Material:
CRC
Vessel(s) –
110% of Volume of Largest Vessel: 0.99m3
Bund Retention Volume:
Unknown
Vessel(s) –
25% of Total Storage Volume: 0.225m3
Tank Contents: Diesel R Phrase (WGK Class): Risk Phrases: R40, WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing required (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Tank (see Fig. 98.1) is in good condition – no visible cracks or leaks. Bund full with water (Fig 98.2).
Drainage System: Local bund - In the event of a spill bund is pumped out. This bund is located outside so is exposed to rainfall. The bund requires regular monitoring to ensure it is kept free of rainwater. This will ensure the retention volume of the bund is not reduced.
Result of Visual Inspection: Pass
Housekeeping Issues: A grate missing from over sump and build-up of debris and rubbish (Fig 98.3).
Clean out bunded area under grate and around the tank.
The bund requires regular monitoring to ensure it is kept free of rainwater.
Action Required: Determine bund retention volume
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
39
Bund ID: F10 EG2 Diesel Bund
Result of Hydrostatic Test: Pass
Date of hydrostatic Test:
16/2/11
Length of test: 24hrs
Measurement at beginning of test: 110mm
Measurement at end of test: 110mm
Volume Tested to: 3.5m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Eamon McIvor Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
40
Company: Intel Ireland Ltd Photo/sketch:
See Fig 22.1 – 22.3 Site: Leixlip, Co Kildare
Bund Ref. No.: 22
Bund Location: F10 AWN PIT
Bund Description: Bulk Solvent
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction:
Concrete
Vessel(s) –
Total Storage Volume: 41.6m3
General Solvent (Solvent Waste) (T-58A-1-1): 19m3
Ethyl Lactate (T-58A-1-1) : 11.3m3
NMP (T-58A-1-1):11.3m3
Storage on AWN apron: 2 x 27m3 tankers
Bund Lining Material:
CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 29.7m3
Bund Retention Volume:
33m3
Vessel(s) –
25% of Total Storage Volume: 23.9m3
Tank Contents: (3 Tanks)
General Solvent (Solvent Waste) (T-58A-1-1)
Ethyl Lactate (T-58A-1-1)
N-Methyl-2 pyrrolidone(T-58A-1-1)
R Phrase (WGK Class): Assume high risk
Contents: High Risk Condition: Poor in areas Action: Remedial action plus hydrostatic testing
(where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: Pass (See addendum below for details)
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Bund is made up of slab on grade with 2No. high separation walls and 2No. tall upstand walls. Bund appears in good condition with no visible defects. Rainwater in bund (Fig. 22.3). The sump grate needs to be cleaned - mud and debris build-up. Some rusting of pipes in this area. No evidence of leaks or cracks.
Bund Drainage System: Combined bund - Sump level detection/alarm and capability to manually pumps to solvent tanks or AWN
General Observations: Floor appears discoloured. There is evidence of maintenance work going on as scaffolding and ladders in bund.
Result of Visual Inspection: Pass
Housekeeping Issues: Debris in base of bund. This should be removed (Fig. 22.2).
Action Required:
Rusting should be monitored.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
41
Bund ID: 22
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 3/3/10
Length of test: 24hrs
Measurement at beginning of test: 140mm
Measurement at end of test: 140mm
Volume Tested to: 21m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Alan Campbell Title: IWS Engineer
DATA SHEET: BUNDING STRUCTURES
42
Company: Intel Ireland Ltd Photo/sketch:
See Fig 23.1 – 23.4 Site: Leixlip, Co Kildare
Bund Ref. No.: 23
Bund Location: F10 AWN PIT
Bund Description: AWN Tanks
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 27m3 each and total storage volume
of 81m3
Bund Lining Material: CRC Coating Vessel(s) –
110% of Volume of Largest Vessel: 29.7m3
Bund Retention Volume:
207m3
Vessel(s) –
25% of Total Storage Volume: 20.25m3
Tank Contents:
Tank 1(T-56A-1-1)
Tank 2(T-56A-1-2)
Tank 3(T-56A-1-3)
R Phrase (WGK Class):
High risk as other bunds pumped to AWN and this bund also acts as storm water bund.
Contents: High Risk Condition: Poor in areas Action: Remedial action plus hydrostatic testing
(where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons: Hydrostatically test up to 30m3 at
least as this is bund which acts as storm water hold and is link to other free drain bunds.
Result of Hydrostatic Test: Pass (See addendum below for details)
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Bund (Deep pit) appears in reasonable condition. No evidence of leaks or cracks. Some evidence of rainwater (bund is used as overflow for storm water drain).
Bund Drainage System: Combined Bund: Sump in south west corner with level detection/alarm and manually pumped to AWN tanks
Equipment in Bund: No electrical equipment below bund level. All associated piping is contained within bund.
General Observations: There is a lot of debris on the floor of the bund i.e. ladder, scaffolding, piping, absorbent material, broken pipework (Fig 23.2 – 23.3). There is evidence of rushing of pipework (Fig 23.4). Retention volume is more than adequate even ff bund used as overflow for storm water.
Result of Visual Inspection: Pass
Housekeeping Issues: Remove materials/debris from bund. Rusting should be monitored.
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
43
Bund ID: 23
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 4/3/10
Length of test: 24hrs
Measurement at beginning of test: 137mm
Measurement at end of test: 137mm
Volume Tested to: 40m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Alan Campbell Title: IWS Engineer
DATA SHEET: BUNDING STRUCTURES
44
Company: Intel Ireland Ltd Photo/sketch:
See Fig 21.1 – 21.3 Site: Leixlip, Co Kildare
Bund Ref. No.: 21
Bund Location: F10 AWN PIT
Bund Description: Hydrofluoric Acid
Wastewater (Bulk)
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Metal vessels
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 3 x Hydrofluoric acid waste and Phosphoric acid waste tanks (27m
3 each) plus one
phosphoric acid tank (18.7 m3) and total storage volume of
99.7m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 29.7m3
Bund Retention Volume:
35m3
Vessel(s) –
25% of Total Storage Volume: 24.95m3
Tank Contents: Hydrofluoric acid / Phosphoric
Acid
R Phrase (WGK Class): WGK 2
R26/27/28 and R34
Contents: High Risk Condition: Poor in
areas
Action: Remedial action plus hydrostatic testing
(where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: Pass (See addendum below for details)
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Bund (Pit with upstand and floor) appears to be generally intact – no visible cracks or leaks internally. However significant debris on base of bund including scaffolding and some water retention from recent rainfall also present (Fig. 21.2). The shower has some water around it (automatically turns on when temperatures get to freezing) (Fig. 21.3).
Bund Drainage System: Local bund - Sump level detection/alarm and manually pumped to collection tanks or AWN.
General observations: The bund is quite dirty and needs to be cleaned out.
Result of Visual Inspection: Pass
Housekeeping Issues: Remove materials/debris from bund.
Action Required: Bund needs to be cleaned out. (Done)
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
45
Bund ID: 21
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 2/3/10
Length of test: 24hrs
Measurement at beginning of test: 162mm
Measurement at end of test: 162mm
Volume Tested to: 53m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Alan Campbell Title: IWS Engineer
DATA SHEET: BUNDING STRUCTURES
46
Company: Intel Ireland Ltd Photo/sketch:
See Fig 25.1 – 25.4 Site: Leixlip, Co Kildare
Bund Ref. No.: 25 / 26
Bund Location: F10 AWN PIT
Bund Description: Hydrochloric and Sulphuric
Acid Tanks
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Metal vessels
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 23.9m3 each and total storage
volume of 47.8m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 26.29m3
Bund Retention Volume:
43m3
Vessel(s) –
25% of Total Storage Volume: 11.95m3
Tank Contents:
Hydrochloric Acid (HCI) Tank (T-53A-1-1)
R Phrase (WGK Class):
R34, R37 WGK 1
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Bund (Pit with upstand and floor) appears to be generally intact – no visible cracks or leaks internally. Bund in good condition – no visible cracks or leaks. Some retention of rainwater (Figure 25.3).
Bund Drainage System: Local bund - Sump level detection/alarm and manually pumped to AWN tank.
Result of Visual Inspection: Pass (See addendum below for details)
Housekeeping Issues: The bund is quite dirty and needs to be cleaned out (Figure 25.2) Done
Action Required: None
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
47
Company: Intel Ireland Ltd Photo/sketch:
See Fig 24.1 – 24.5 Site: Leixlip, Co Kildare
Bund Ref. No.: 24
Bund Location: F10 AWN PIT
Bund Description: NaOH Tanks (5%, 25% and
47%)
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Carbon steel
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 30m3, 30m
3 and 0.9m
3 and total
storage volume of 60.9m3
Bund Lining Material: CRC Coating Vessel(s) –
110% of Volume of Largest Vessel: 33m3
Bund Retention Volume:
66.1m3
Vessel(s) –
25% of Total Storage Volume: 15.23m3
Tank Contents:
Sodium Hydroxide (NaOH) (25%) (T-53A-1-2)
NaOH (47%), NaOH 5%
R Phrase (WGK Class):
R35, WGK 1
Contents: Low Risk Condition: Poor in areas Action: Remedial action plus re-inspection
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Bund (Pit with upstand and floor) appears to be generally intact – no visible cracks or leaks internally. Some retention of rainwater.
Bund Drainage System: Local bund - Sump level detection/alarm and manually pumped to AWN tank.
General observations: Some debris over sump grate needs to be removed. The cladding over some pumps in the bund appears to be broken and removed and the pumps appear rusted (Figure 24.2, 24.3).
All containers should be correctly labelled the bund register states NaOH (25%) is T-53A-2-2 but from photo it is T-53A-1-2. Bund register should be updated accordingly (Fig. 24.1).
Result of Visual Inspection: Pass
Housekeeping Issues: Some debris over sump grate needs to be removed (Fig. 24.5). Some discolouration in
one of the pipes (Fig. 24.3) needs to be investigated
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
48
Company: Intel Ireland Ltd Photo/sketch:
See Fig 27.1 – 27.3 Site: Leixlip, Co Kildare
Bund Ref. No.: 27
Bund Location: F10 AWN PIT
Bund Description: Regen Waste/NaCI Tank/
HCL Scrubber
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: FRP double thick veil
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume:
Regen Waste 37m3
NaCl 25m3
Tanker storage on AWN apron: 2 x 22.5m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 40.7m3
Bund Retention Volume:
65.6m3
Vessel(s) –
25% of Total Storage Volume: 36m3
Tank Contents:
Regen Waste
NaCI Tanks
HCL Scrubber
R Phrase (WGK Class):
R34, R37
WGK 1, R 36/38
Contents: Tanks empty but
contents will be low risk
Condition: Poor in areas Action: Remedial action prior to commissioning
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: This bund has not been in use for about 1.5yrs but re-commissioning of the bund is due to start in Q2, 2009. Rainwater in bund. There are very old pumps in the bund which are extremely rusted and the red pipelines are extremely rusted and may need to be replaced prior to bund being re-commissioned.
Discolouration on floor of bund. Labelling of the tank has fallen off at one side, this need to be replaced.
Bund Drainage System: Sump level detection/alarm and manually pumped to AWN or tanks.
Result of Visual Inspection: Fail
Housekeeping Issues: The bund would require cleaning and re-inspection before re-use.
Action Required:
All tanks should be correctly labelled.
There are very old pumps in the bund which are extremely rusted and the red pipelines extremely rusted and may need to be replaced prior to bund being re-commissioned.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
49
Bund ID: F10 AWN PIT ref. 27
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 03/11/10
Length of test: hrs 9
Measurement at beginning of test: mm 146
Measurement at end of test: mm 146
Volume Tested to: m3 11.502
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Thomas Brennan Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
50
Company: Intel Ireland Ltd Photo/sketch:
N/A Site: Leixlip, Co Kildare
Bund Ref. No.: 158
Bund Location: F10 AWN PIT
Bund Description: Phosphoric Acid
Wastewater Tank
Bund Dimensions: N/A – Bund No 21 applies
here
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: See Bund No. 21 Data Sheet
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: N/A
Bund Retention Volume:
Bund No 21 applies here
Vessel(s) –
25% of Total Storage Volume: N/A
Tank Contents: Phosphoric Acid Wastewater
R Phrase (WGK Class): R36/38 WGK1
Contents: Low Risk Condition: Good Contents: Low Risk
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 16/9/09
Bund & Tank Integrity: Bund (Deep pit) appears in reasonable condition.
Bund Drainage System: Free draining into neighbouring HFW Tank Collection bund (Bund 21).
Equipment in Bund: No electrical equipment below bund level.
General Observations: This tank is used only in emergency situations and hasn‟t been used in a number of years. The tank appears generally intact but the bund was not accessible on the day and a visual inspection from the top of the AWN Pit was only carried out.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: None
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
51
Company: Intel Ireland Ltd Photo/sketch:
See Fig 90.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 90
Bund Location: F10 Subfab
Bund Description: HPM Aqueous Room
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Various vessels (plastic+ metal)
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume:
10m3
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents: Corrosive chemicals including:
Ammonia Hydroxide
Sulphuric Acid
R Phrase (WGK Class): Corrosive/Toxic
R34, R50, WGK 2
R35, WGK 1
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Room with CRC coating on floor and coving to walls. The bund appears in good condition – no visible cracks or leaks and ground around is dry. Some discolouration to floor from movement of containers.
Bund Drainage System: Local bund - Room where any spills drain to trenches along middle of floor.
General Observation: All containers should be correctly labelled.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Bund was not hydrostatically tested as it will be out of commission in by the end of Q2 2011
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
52
Company: Intel Ireland Ltd Photo/sketch:
See Fig 91.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 91
Bund Location: F10 Subfab
Bund Description: HPM Solvent Room
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Various vessels and drums
(plastic+ metal)
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume:
5m3
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents: Flammable chemicals R Phrase (WGK Class):
Corrosive/Toxic
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Room with CRC coating on floor and coving to walls. The bund appears in good condition – no visible cracks or leaks and ground around is dry. Some discolouration to floor from movement of containers.
Bund Drainage System: Local bund - Room where any spills drain to trenches along middle of floor.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Bund was not hydrostatically tested as it will be out of commission in by the end of Q2 2011
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
53
Company: Intel Ireland Ltd Photo/sketch:
See Fig 28.1 – 28.4 Site: Leixlip, Co Kildare
Bund Ref. No.: 28
Bund Location: Between F10 middle yard and
F14 Energy Centre
Bund Description: F10 Emergency
Generator/Diesel Storage Bund (EG3, 4 and 6 ).
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Various vessels and drums
(plastic and metal)
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 40m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 44m3
Bund Retention Volume: 140.58m3
Vessel(s) –
25% of Total Storage Volume: 10m3
Tank Contents: 3 diesel storage tanks and 3
Emergency generators diesel day tanks
R Phrase (WGK Class):
R45, WGK 2
Contents: High Risk Condition: Poor in
areas
Action: Remedial action plus hydrostatic testing
(where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Tank (see Fig. 28.1) is in good condition – no visible cracks or leaks and ground around tank dry.
Bund Drainage System: Local bund that drains through grate into bund, appear to have some liquid retention and moss growth, this needs to be clean as may interfere with bund retention volume (Fig. 28.2). Sump level detection/alarm.
There is a water pipe releasing water at back of bund directly to ground and slopes to sump, maybe practical to extend this pipe line to drain (Figure 28.4).
General Observation: All containers should be correctly labelled.
Result of Visual Inspection: Pass
Housekeeping Issues: Debris and moss in drainage channel.
Action Required:
Clean out bunded area under grate and around the generators vessels.
All containers should be correctly labelled.
Hydrostatic testing required.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
54
Bund ID: F10 Bund Storage for EG3,4 & 6
Result of Hydrostatic Test: Fail
Date of hydrostatic Test:
16/2/11
Length of test: 24hrs
Measurement at beginning of test: 300mm
Measurement at end of test: 150mm
Volume Tested to: 45m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Eamon McIvor Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
55
Company: Intel Ireland Ltd Photo/sketch:
See Fig 16.1 –16.4 Site: Leixlip, Co Kildare
Bund Ref. No.: 16
Bund Location: F10 Middle Yard
Bund Description: Hazardous Waste
Compound
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Metal Drums
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: N/A
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: 17.2m3
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents: Dry hazardous waste, double-
bagged and drummed
R Phrase (WGK Class): Low risk due to packaging.
Contents: Low Risk Condition: Poor in
areas
Action: Remedial action plus re-inspection
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: Free draining.Waste in this area is solid, double bagged and in drums therefore not necessary to hydrostatically test.
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Area appears to be generally intact. There is some subsidence of the concrete in the middle of the floor beside the grate (Fig 16.4), hairline cracking, should be investigate further. There is no sealant or CRC on this floor as the hazardous materials contained here are dry. Some rainwater in the floor (Fig. 16.2).
Bund Drainage System: Area with grated trenches around the storage areas. Drains through F10 upper yard contained storm system tank to the site retention pond. Integrity tests are carried out every 3 years on the F10 upper yard tank.
Result of Visual Inspection: Fail
Housekeeping Issues: Some debris outside bund needs to be removed (Fig. 16.3).
Action Required: It was determined to remove from this bund following on from this assessment
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
56
Company: Intel Ireland Ltd Photo/sketch:
See Fig 89.1 –89.5 Site: Leixlip, Co Kildare
Bund Ref. No.: 89
Bund Location: F10 Scrubber Deck
Bund Description: F10 Roof: Large Room on
scrubber deck
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: N/A
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: 109m3
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents: 8 acid scrubbers (No. 7
decommissioned) + 1 gaspad scrubber
R Phrase (WGK Class): Harmful & Corrosive
WGK 1, R35
Contents: High Risk Condition: Poor in
areas
Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons: Remote drainiage from room; free
draining to AWN
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09
Bund & Tank Integrity: This area on located on the top floor of F10 (see site layout plan) on the scrubber level (Fig. 89.1). The F10 scrubber deck should not be on the bund register, instead the smaller individual bund within the room should be on the register.i.e.
Bund permaclean ® PC-33 and NALCO ® 2584,
55S Dosing bund containing NALCO 2536 plus and
Sodium Hydroxide, 47%.
Bund Drainage System: Remote drainage from room – free draining to AWN
General Observation: There is a lot of evidence of spills in this area are absorbent materials (Fig. 89.4), the procedures for cleaning up these and general maintenance of the floor needs to improve.
Result of Visual Inspection: N/A
Housekeeping Issues: Debris/rubbish should be removed.
Action Required: Refer to bund numbers 109, 110, 111 and 112 for details on individual bunds in room
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
57
Company: Intel Ireland Ltd Photo/sketch:
See Fig 150.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 150
Bund Location: F10 Fire Pump House
Bund Description: F10 Firewater Pump with
Diesel tank
Bund Dimensions: Large room -
1..35m x 1m x 1m = 1.35m3
(1350L)
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction:
Metal Bund
Vessel(s) –
Total Storage Volume: 900L
Bund Lining Material: CRC coating
Vessel(s) –
110% of Volume of Largest Vessel: 990L
Bund Retention Volume: 1350L
Vessel(s) –
25% of Total Storage Volume: 225L
Tank Contents: Diesel
R Phrase (WGK Class): R40, R65, R66, R51, R53
WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
Bund ID: F10 Fire Pump house
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 25/01/11
Length of test: 18hrs
Measurement at beginning of test: 254mm
Measurement at end of test: 254mm
Volume Tested to: 1 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Ciaran O Seery Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
58
Company: Intel Ireland Ltd Photo/sketch:
See Fig 107.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 107
Bund Location: F10 Subfab: 15F Pump room
(opposite IH lab - door to Engineering labs, 1st on right)
Bund Description: Nalco 2536+
Bund Dimensions: 1.2 x 0.8 x 0.4m = 0.384m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 260L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 286L
Bund Retention Volume: 384L
Vessel(s) –
25% of Total Storage Volume: 65L
Tank Contents: Sodium Nitrite
R Phrase (WGK Class): R22, R52, WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where
possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
59
Bund ID: Bund Ref. No.: 107
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 2/12/10
Length of test: 24 hrs
Measurement at beginning of test: 550mm
Measurement at end of test: 550mm
Volume Tested to: 0.430 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Simon McLain Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
60
Company: Intel Ireland Ltd Photo/sketch:
N/A Site: Leixlip, Co Kildare
Bund Ref. No.: 160
Bund Location: F10 Subfab: opposite F10 15F
Pump room (Room 3136)
Bund Description: F10 PCD - Planar Chemical
Distribution
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: N/A
Vessel(s) –
Total Storage Volume: 5024L
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 1100L
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: 1256L
Tank Contents: Semi Sparse W2000 – Silca
Slurry ( Silica, Amorphous, Crystalline
Free)
Potassium Hydroxide 10%
R Phrase (WGK Class):
Not classed under the EU legislation but assume low risk as silca is relatively inert
WGK 1, R22, R35
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 16/9/09
Bund & Tank Integrity: Bund appears in good condition. Totes containing planar slurries located in this room.
Bund Drainage: Local Bund: If leak occurs the bund is manually pumped out to AWN
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: Determine bund retention volume
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
61
Company: Intel Ireland Ltd Photo/sketch:
See Fig 108.1 – 108.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 108
Bund Location: F10 Subfab: F10 PVAC
(adjacent to F10 aqueous room)
Bund Description: PVAC dosing skid - Nalco
8539
Bund Dimensions: 1.05 x 0.75 x 0.4m =
0.315m3
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction: Metal
Vessel(s) –
Total Storage Volume: 270L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 297L
Bund Retention Volume: 315L
Vessel(s) –
25% of Total Storage Volume: 67.5L
Tank Contents: Sodium Nitrite & Potassium
Hydroxide
R Phrase (WGK Class): R25, R36/38, R50
WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where
possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Testing would involve taking the primary vessel offline which would impact fab operations
Result of Hydrostatic Test:
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: Local bund - If a leak occurs the bund is manually pumped out.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
62
Company: Intel Ireland Ltd Photo/sketch:
See Fig 109.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 109
Bund Location: F10 Scrubber Deck: SICWS
tank
Bund Description: 55S Dosing Skid with Nalco
2536+
Bund Dimensions: 1.05 x 0.8 x 0.4m =
0.336m3
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction: Metal
Vessel(s) –
Total Storage Volume: 297L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 326.7L
Bund Retention Volume: 336L
Vessel(s) –
25% of Total Storage Volume: 74.25L
Tank Contents: Sodium Nitrite, Sodium
Tetraborate, Sodium Metasilicate
R Phrase (WGK Class): R22, WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where
possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: Local bund - If a leak occurs the bund is manually pumped out.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
63
Bund ID: Bund Ref. No.: 109
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 2/12/10
Length of test: 24 hrs
Measurement at beginning of test: 260mm
Measurement at end of test: 260mm
Volume Tested to: 0.275 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Simon McLain Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
64
Company: Intel Ireland Ltd Photo/sketch:
See Fig 110.1 – 110.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 110
Bund Location: F10 Scrubber Deck
Bund Description: Sodium Hydroxide (47%)
Bund Dimensions: 1 x 1 x 0.27m = 0.27m3 Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction: Metal
Vessel(s) –
Total Storage Volume: 300L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 330L
Bund Retention Volume: 270L
Vessel(s) –
25% of Total Storage Volume: 75L
Tank Contents: Sodium Hydroxide
R Phrase (WGK Class): R35, WGK1
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition. The capacity of the tank excesses the bund capacity.
Bund Drainage: Local bund - If a leak occurs the bund is manually pumped out.
Result of Visual Inspection: Pass
Housekeeping Issues: The bund needs to be cleaned.
Action Required: Check the capacity of vessel compared to bund as the bund retention volume is less than the
total storage capacity of the vessel.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
65
Company: Intel Ireland Ltd Photo/sketch:
See Fig 111.1 – 111.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 111
Bund Location: F10 Scrubber Deck
Bund Description: Nalco 2584
Bund Dimensions: 1 x 1.2 x 0.4m = 0.48m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 300L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 330L
Bund Retention Volume: 480L
Vessel(s) –
25% of Total Storage Volume: 75L
Tank Contents: Sodium Hydroxide &
Potassium Hydroxide
R Phrase (WGK Class): R35
WGK1
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: Local bund - If a leak occurs the bund is manually pumped out.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: None
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
66
Company: Intel Ireland Ltd Photo/sketch:
See Fig 111.1 – 111.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 112
Bund Location: F10 Scrubber Deck
Bund Description: PC-33
Bund Dimensions: 1 x 1.2 x 0.4m = 0.48m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 300L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 330L
Bund Retention Volume: 480L
Vessel(s) –
25% of Total Storage Volume: 75L
Tank Contents: Permaclean PC-33,
Tetrasodium EDTA, Sodium Hydroxide
R Phrase (WGK Class): R36/38, WGK1
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: Local bund - If a leak occurs the bund is manually pumped out.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: None
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
67
Company: Intel Ireland Ltd Photo/sketch:
See Fig 129.1 – 129.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 129
Bund Location: F10 Energy Centre
(Compressor/chiller room)
Bund Description: Cooling Tower Dosing -
Nalco 3DT187
Bund Dimensions: 1.2 x 0.9 x 0.55m =
0.594m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 440L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 484L
Bund Retention Volume: 594L
Vessel(s) –
25% of Total Storage Volume: 110L
Tank Contents: Phosphoric Acid
R Phrase (WGK Class): R36/38 WGK1
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: Local bund - If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
68
Company: Intel Ireland Ltd Photo/sketch:
See Fig 130.1 - 130.2 Site: Leixlip, Co Kildare
Bund Location: F10 Energy Centre
(Compressor/chiller room)
Bund Description: Cooling Tower Dosing -
Nalco 93033
Bund Dimensions: 1.4 x 1 x 0.7m = 0.98m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 750L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 825L
Bund Retention Volume: 980L
Vessel(s) –
25% of Total Storage Volume: 187.5L
Tank Contents: Sodium Hypochlorite
R Phrase (WGK Class): R31, R34, WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Testing would involve taking the primary vessel offline which would impact fab operations
Result of Hydrostatic Test:
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in general good condition. There is evidence of a leak and absorbent material in the bund floor.
Bund Drainage: Local bund - If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
69
Company: Intel Ireland Ltd Photo/sketch:
See Fig 131.1 - 131.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 131
Bund Location: F10 Energy Centre
(Compressor/chiller room)
Bund Description: MTHW / Chilled / Glycol
water - Nalco 8539 (F10 Colling Tower Dosing Skid)
Bund Dimensions: 0.75 x 1.1 x 0.4m = 0.33m3 Vessel(s) –
Materials of Construction: Lined Stainless Steel
Bund Materials of Construction: Metal –
Stainless Steel
Vessel(s) –
Total Storage Volume: 270L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 297L
Bund Retention Volume: 330L
Vessel(s) –
25% of Total Storage Volume: 67.5L
Tank Contents: Sodium Nitrite & Potassium
Hydroxide
R Phrase (WGK Class): R25, R36/38, R50
WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Testing would involve taking the primary vessel offline which would impact fab operations
Result of Hydrostatic Test:
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: Local bund - If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
70
Company: Intel Ireland Ltd Photo/sketch:
See Fig 132.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 132
Bund Location: F10 Nitrogen Plant
Bund Description: Battery Acid
Bund Dimensions: 0.75 x 0.7 x 0.5m Approx. Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: ~100L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 110L
Bund Retention Volume: 226.5L
Vessel(s) –
25% of Total Storage Volume: 25L
Tank Contents: Battery Acid
R Phrase (WGK Class): R34, WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: Local bund - If leak occurs the bund is manually pumped out and cleaned.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
Bund ID: Bund Ref. No.: 132
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 08/03/2011
Length of test: 8 hrs
Measurement at beginning of test: 490 mm
Measurement at end of test: 490 mm
Volume Tested to: 0.22 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Brian McCabe Title: Operational Owner
DATA SHEET: BUNDING STRUCTURES
71
Company: Intel Ireland Ltd Photo/sketch:
See Fig 133.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 133
Bund Location: F10 Nitrogen Plant
Bund Description: Biomate 5702
Bund Dimensions: 0.75 x 0.7 x 0.5m Approx. Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: ~100L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 110L
Bund Retention Volume: 226.5L
Vessel(s) –
25% of Total Storage Volume: 25L
Tank Contents: Biomate 5702: Sodium
carbonate Sodium hypochlorite
R Phrase (WGK Class): R31/34,R35,R36 WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: Local bund - If leak occurs the bund is manually pumped out and cleaned.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
Bund ID: Bund Ref. No.: 133
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 08/03/2011
Length of test: 8 hrs
Measurement at beginning of test: 500 mm
Measurement at end of test: 500 mm
Volume Tested to: 0.22 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Brian McCabe Title: Operational Owner
DATA SHEET: BUNDING STRUCTURES
72
Company: Intel Ireland Ltd Photo/sketch:
See Fig 134.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 134
Bund Location: F10 Nitrogen Plant
Bund Description: Continium AEZ3153 &
Inhibitor AEZ104
Bund Dimensions: 0.75 x 0.7 x 0.5m Approx. Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: ~100L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 110L
Bund Retention Volume: 226.5L
Vessel(s) –
25% of Total Storage Volume: 25L
Tank Contents: Continium AEZ3153 & Inhibitor
AEZ104
R Phrase (WGK Class): Harmful
Contents: Assume High Risk Condition: Good Action: Hydrostatic testing (where
possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: Local bund - If leak occurs the bund is manually pumped out and cleaned.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
73
Bund ID: Bund Ref. No.: 134
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 08/03/2011
Length of test: 8 hrs
Measurement at beginning of test: 500 mm
Measurement at end of test: 500 mm
Volume Tested to: 0.22 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Brian McCabe Title: Operational Owner
DATA SHEET: BUNDING STRUCTURES
74
Company: Intel Ireland Ltd Photo/sketch:
See Fig 135.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 135
Bund Location: F10 Nitrogen Plant
Bund Description: Oil Bund
Bund Dimensions: Irregular shape / slopes Vessel(s) –
Materials of Construction: Various drums and plastic
containers
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 20L drum x 2 and 200L drum – total
240L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 220L
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: 60L
Tank Contents: Mobile DTE Light oil
R Phrase (WGK Class): Harmful
Contents: Assume High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: Local bund - If leak occurs the bund is manually pumped out and cleaned.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: Determine bund retention volume and check the capacity of vessel compared to bund.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
75
Company: Intel Ireland Ltd Photo/sketch:
See Fig 136.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 136
Bund Location: F10 Nitrogen Plant
Bund Description: Transformer Bund
Bund Dimensions: 3.3 x 4.5 x 0.4m = 5.94m3 Vessel(s) –
Materials of Construction: Metal Transformers on gravel
bund
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 429L & 1100L =1529L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 1210L
Bund Retention Volume: 5940L
Vessel(s) –
25% of Total Storage Volume: 382.25L
Tank Contents: Electrical insulating oil
R Phrase (WGK Class): WGK 1
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
76
Fab 14 Bunds
DATA SHEET: BUNDING STRUCTURES
77
Company: Intel Ireland Ltd Photo/sketch:
No photos available Site: Leixlip, Co Kildare
Bund Ref. No.: 43
Bund Location: F14 - Tank Farm east of PSB
Bund Description: Concentrated Lead Waste
(C4 System 2 Collection Tanks)
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Large Metal Vessels
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 2 x 18m3 = 36m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 19.8m3
Bund Retention Volume:
33.91m3
Vessel(s) –
25% of Total Storage Volume: 9m3
Tank Contents: Lead Waste R Phrase (WGK Class): R36, R33 Corrosive and Toxic
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Bund no longer exists. All Lead waste plant has been removed from service and de-installed
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Slab on grade and upstand to the east with high separation walls to other sides. Very small amount of liquid retention in base of bund but the bund is mainly dry. No visible cracks or leaks in bund and general in good condition.
Bund Drainage System: Sump level detection on bund and the sump arrangement is as follows, manual pump to tanks with AWN drain. Normal operation during rain is to pump back to collection tanks.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
78
Company: Intel Ireland Ltd Photo/sketch:
See Fig 44.1 –44.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 44
Bund Location: F14 - Tank Farm east of PSB
Bund Description: HF/H3PO4 Tanks (4 in
No.)
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Large Metal Vessels,
Polypropylene lined FRP
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 4 x 30m3 = 120m
3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 33m3
Bund Retention Volume:
150.66 m3
Vessel(s) –
25% of Total Storage Volume: 30m3
Tank Contents:
Hydrofluoric Acid Waste and Phosphoric Acid
R Phrase (WGK Class):
WGK 2, R26/27/28 and R34
WGK 1, R34
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Bund no longer exists. All HF waste plant has been removed from service and de-installed
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Very small amount of liquid retention in base of bund but the bund is mainly dry. No visible cracks or leaks in bund and general in good condition. The sump has some debris/leaves coving it (Fig. 44.2).
Bund Drainage System: Sump level detection on bund and the sump arrangement is as follows, manual pump to tanks with AWN drain.
Result of Visual Inspection: Pass
Housekeeping Issues: The bund should be cleaned out.
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
79
Company: Intel Ireland Ltd Photo/sketch:
See Fig 45.1 –45.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 45
Bund Location: F14 - Tank Farm east of PSB
Bund Description: C4 Waste Collection Tanks
(DLW, 2 in No.) C4 System 3
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: FRB
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 18m3 x 2 = 36m
3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 19.8m3
Bund Retention Volume:
52.33m3
Vessel(s) –
25% of Total Storage Volume: 9m3
Tank Contents: Dilute lead waste
R Phrase (WGK Class): R36, R33 Corrosive and Toxic
Contents: Assume High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Bund no longer exists. All waste plant has been removed from service and de-installed
Result of Hydrostatic Test:
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Very small amount of liquid retention in base of bund, most likely rainfall (see Fig. 45.1) but bund mainly dry. No visible cracks or leaks in bund. There is quite a bit of discolouration in this bund (Fig 45.2).
Bund Drainage System: Sump level detection on bund and the sump arrangement is as follows, manual pump to tanks with AWN drain.
Result of Visual Inspection: Pass
Housekeeping Issues: Bund should be monitored for further deterioration in discolouration.
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
80
Company: Intel Ireland Ltd Photo/sketch:
See Fig 46.1 –46.3 Site: Leixlip, Co Kildare
Bund Ref. No.: 46
Bund Location: F14 - Tank Farm east of PSB
Bund Description: Bulk Sulphuric Acid
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Large Metal Vessels, FRP pvdf
lined
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 26m3 x 2 = 52m
3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 28.6m3
Bund Retention Volume:
58.11m3
Vessel(s) –
25% of Total Storage Volume: 13m3
Tank Contents: Sulphuric acid (96%) R Phrase (WGK Class): R35 , WGK 1
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Very small amount of liquid retention in base of bund, most likely rainfall (see Fig.46.1) but bund mainly dry. No visible cracks or leaks in bund and general in good condition. There appears to be some rusting to the piping supports (Fig. 46.2).
Bund Drainage System: No sump level detection on bund and the sump arrangement is as follows, manual pump to tanks with AWN drain.
Result of Visual Inspection: Pass
Housekeeping Issues: Debris in base of bund (Fig. 46.3). This should be removed.
Action Required:
The rusting should be monitored.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
81
Company: Intel Ireland Ltd Photo/sketch:
See Fig 47.1 –47.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 47
Bund Location: F14 - Tank Farm east of PSB
Bund Description: General Solvent Tank
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Large Metal Vessels
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 36m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 39.6m3
Bund Retention Volume:
97.37m3
Vessel(s) –
25% of Total Storage Volume: 9m3
Tank Contents: Ethylene Glycol Solvent R Phrase (WGK Class): R10, R36, R37/R38
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Bund no longer exists. All waste plant has been removed from service and de-installed
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Very small amount of liquid retention in base of bund, most likely rainfall (see Fig. 47.2) but bund mainly dry. No visible cracks or leaks in bund and general in good condition.
Bund Drainage System: Sump level detection on bund and the sump arrangement is as follows, manual pump to tanks with AWN drain.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
82
Company: Intel Ireland Ltd Photo/sketch:
See Fig 29.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 29
Bund Location: F14 UPW
Bund Description: F14 UPW General Floor
area (Basement O)
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Self contained vessels
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents:
RO cleaning chemical bund:
Sodium Hypochlorite,
Hypersperse
Sodium bisulphite
R Phrase (WGK Class):
R31, R34, WGK 1
N/A,
R22, R31 WGK 1
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: No visible cracks or leaks in bund and general in good condition.
Bund Drainage System: Remote bund which drains to the F14 AWN pit - Bunded room with trenches along the floor. The room contains four smaller bunds within F14 UPW – these are assessed individually within this report (Bund 64 and 99).
General Observation: Room generally clean and tidy.
Result of Visual Inspection: Pass
Housekeeping Issues: Monitor UPW for leaks and discolouration.
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
83
Company: Intel Ireland Ltd Photo/sketch:
See Fig 99.1 – 99.5 Site: Leixlip, Co Kildare
Bund Ref. No.: 99
Bund Location: F14UPW
Bund Description: Sodium bromide
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Plastic Self contained vessels
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents: Sodium bromide R Phrase (WGK Class): WGK 1
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: No visible cracks or leaks in bund and general in good condition (Fig. 99.1). Full visual assessment of this bund was limited due to position of the bund.
Bund Drainage System: In the event of a spill bund would be pumped out. This bund is located inside so is not exposed to rainfall.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: None
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
84
Company: Intel Ireland Ltd Photo/sketch:
See Fig 33.1 – 33.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 33
Bund Location: F14 west of PSB
Bund Description: HCl Tank
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Vinylester FRP
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 42m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 46.2m3
Bund Retention Volume: 62.57m3 Vessel(s) –
25% of Total Storage Volume: 10.5m3
Tank Contents: Hydrochloric Acid R Phrase (WGK Class): R34, R37
WGK 1
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: No visible cracks or leaks in bund and general in good condition.
Bund Drainage System: Sump level detection on bund and manually pumped to AWN. (See Fig. 33.2).
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: None
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
85
Company: Intel Ireland Ltd Photo/sketch:
See Fig 34.1 – 34.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 34
Bund Location: F14 west of PSB
Bund Description: NaOH Tank
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Stainless Steel
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 45m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 49.5m3
Bund Retention Volume:
66.09m3
Vessel(s) –
25% of Total Storage Volume: 11.25m3
Tank Contents: Sodium Hydroxide R Phrase (WGK Class): WGK 1
R36, R38
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: No visible cracks or leaks in bund and general in good condition. There is some mossy growth on the base of the bund especially over the sump outlet grate.
Bund Drainage System: Sump level detection on bund and manually drained to AWN. (See Fig. 34.2)
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Mossy growth in bund should be cleaned out. (Done)
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
86
Company: Intel Ireland Ltd Photo/sketch:
See Fig 32.1 – 32.4 Site: Leixlip, Co Kildare
Bund Ref. No.: 32
Bund Location: F14 west of PSB
Bund Description: Regeneration waste Tank
Bund Dimensions: 9m x 9m x 1.2mH
Vessel(s) –
Materials of Construction: Vinylester FRP
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 61m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 67.1m3
Bund Retention Volume:
93.51m3
Vessel(s) –
25% of Total Storage Volume: 15.25m3
Tank Contents: Regeneration waste R Phrase (WGK Class): R34, R37
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Bund no longer exists. All Lead waste plant has been removed from service and de-installed
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally. However significant mossy growth and a lot of leave coverage on base of bund and tree/bush growth in eastern corner. There is also some tree growth up through the drainage grates along the bund (Fig. 32.1 – 32.4).
Bund Drainage System: No sump level detection on bund and manually drained to AWN. The drain is closed therefore some build up of water (Fig 32.1).
General observations: The pipe leading through the UPW bund appearing in bad condition and is covered in plastic and timber (Fig. 32.2). This should be looked into further.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Mossy growth and shrub growth from grate in bund should be cleaned out.
Pipework should be repaired.Bund wall to be formed against blockwork to required height.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
87
Company: Intel Ireland Ltd Photo/sketch:
See Fig 31.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 31
Bund Location: F14 west of PSB
Bund Description: UPW External Bund
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents:
2 No. UPW (Ultrapure water tanks)
2 No. ROW (Reverse Osmosis Water tanks)
2 No. IW (Industrial Water tanks)
Vacuum Degasifer (DG-243-1-130)
R Phrase (WGK Class): Low Risk – water
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally. However mossy growth and a lot of leave coverage on base of bund.
Bund Drainage System: Local bund - Bottom outlet valve on bund. The bund also slopes.
Result of Visual Inspection: Pass
Housekeeping Issues: Labelling of all tanks should be clear.
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
88
Company: Intel Ireland Ltd Photo/sketch:
See Fig 38.1 – 38.4 Site: Leixlip, Co Kildare
Bund Ref. No.: 38
Bund Location: F14 AWN PIT
Bund Description: AWN Tanks & URW Tank
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Vinylester FRP, Metal vessels
(cream in colour)
Bund Materials of Construction: N/A
Vessel(s) –
Total Storage Volume: 60 x 4 = 240m3
Bund Lining Material: CRC Coating Vessel(s) –
110% of Volume of Largest Vessel: 67.1m3
Bund Retention Volume:
254.20m3
Vessel(s) –
25% of Total Storage Volume: 60m3
Tank Contents:
Acid Wastewater
Ultrapure recycled water
R Phrase (WGK Class): Assume high risk as other high risk
areas drain to AWN – These areas no longer drain to AWN as F14 waste treatments systems have been decommissioned
Contents: High Risk Condition: Poor in areas Action: Remedial action plus
hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Bunded area within Pit. Bund appears to be generally intact – no visible cracks or leaks internally. However there is discolouration on the bund floor and AWN tank TK-261-1-120 is corroded on the outside (Fig. 38.1). Rainwater retention is visible in the bund, the bund seems to slope and most has gathered in the back corner of the bund (Fig. 38.2). This will affect the retention volume of the bund and should be pumped out periodically. There is a sump in this corner and because full with water could not be fully inspected. There is some discolouration in the bund due to water build-up (Figure 38.3).
Bund Drainage System: Local bund - Sump level detection on bund and manually drained to AWN. The drainage sump is closed and so build up of water is evident. This bund can take spillages from the contained storm system and there are drains from other areas.
Result of Visual Inspection: Fail
Housekeeping Issues: Maintenance works evident in this area and scaffolding and PPE in bund, if works
complete this should be removed including associated equipment (Fig. 38.4).
Action Required:
Bunds require regular emptying to ensure required storage capacity for spills/leaks
Bund to be tested upon completion of construction works.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
89
Company: Intel Ireland Ltd Photo/sketch:
See Fig 41.1 – 41.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 41
Bund Location: F14 AWN PIT
Bund Description: HF Waste lift Tank
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Polyproylene lined FRP
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 2m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 2.2m3
Bund Retention Volume:
17.41m3
Vessel(s) –
25% of Total Storage Volume: N/A
Tank Contents: Hydroflouric Acid waste R Phrase (WGK Class): R23/24/25
Contents: High Risk Condition: Poor in
areas
Action: Remedial action plus hydrostatic testing
(where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Bund no longer exists. All waste plant has been removed from service and de-installed
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Bunded area within Pit. Bund appears to be generally intact – no visible cracks or leaks internally. However the floor of the bund is in very poor condition i.e. green discolouration (Figure 41.2).
Bund Drainage System: Local bund - Sump level detection on bund and the sump arrangement is as follows, manual pump to lift tanks or AWN.
General observations: The grate over the sump has a lot of debris and plastic in it, evidence if bund been full of rainwater. The floor of the bund is quite dirty and muddy.
Result of Visual Inspection: Pass
Housekeeping Issues: Debris in bund. This should be removed.
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
90
Company: Intel Ireland Ltd Photo/sketch:
See Fig 40.1 – 40.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 40
Bund Location: F14 AWN PIT
Bund Description: H3PO4 lift tank
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Polyproylene lined FRP
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 2m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 2.2m3
Bund Retention Volume: 17.4m3
Vessel(s) –
25% of Total Storage Volume: N/A
Tank Contents: Phosphoric Acid R Phrase (WGK Class): R34, WGK 1
Contents: Low Risk Condition: Poor in areas Action: Remedial action plus re-inspection
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Bund no longer exists. All Waste plant has been removed from service and de-installed
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Bunded area within Pit. Bund appears to be generally intact – no visible cracks or leaks internally. However the floor of the bund is in very poor condition i.e. green discolouration (Figure 40.1).
Bund Drainage System: Local bund - Sump level detection on bund and with manual pump to lift tanks or AWN.
General observations: Slight rusting at join of legs in bund that holds piping and ladder.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Monitoring for leaks in interstitial space should be carried out regularly.
Rusting at join of legs to tank should be monitored.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
91
Company: Intel Ireland Ltd Photo/sketch:
See Fig 42.1 – 42.5 Site: Leixlip, Co Kildare
Bund Ref. No.: 42
Bund Location: F14 AWN PIT
Bund Description: Sulfuric Acid lift tank
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume:
17.41m3
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents: Sulfuric Acid R Phrase (WGK Class): R26, WGK 1
Contents: High Risk Condition: Poor in areas Action: Remedial action plus hydrostatic testing
(where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Bund no longer exists. All Waste plant has been removed from service and de-installed
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Bunded area within Pit. Bund appears to be generally intact – no visible cracks or leaks internally. However the floor of the bund is in very poor condition i.e. green discolouration (Fig 42.2).
Bund Drainage System: Sump level detection on bund and with manual pump to lift tanks or AWN.
General observations: Slight rusting at join of legs in bund that holds piping and ladder (Fig 42.4).
Result of Visual Inspection: Pass
Housekeeping Issues: Debris in bund. This should be removed.
Action Required:
Monitoring for leaks in interstitial space should be carried out regularly.
Rusting at join of legs to tank should be monitored.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
92
Company: Intel Ireland Ltd Photo/sketch:
See Fig 39.1 – 39.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 39
Bund Location: F14 AWN PIT
Bund Description: KD 100 Lift Tank
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: FRP
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 4m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 4.4m3
Bund Retention Volume: 15.34m3
Vessel(s) –
25% of Total Storage Volume: 1m3
Tank Contents: KD100 Waste R Phrase (WGK Class): R36, R38
Contents: Low Risk Condition: Poor Action: Remedial action plus re-inspection
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Bund no longer exists. All Waste plant has been removed from service and de-installed
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Bunded area within Pit. Bund appears to be generally intact – no visible cracks or leaks internally. However the floor of the bund is in very poor condition i.e. green discolouration (Figure 39.1).
Bund Drainage System: Sump level detection on bund and with manual pump to lift tanks or AWN.
General observations: The grate over the sump has a lot of debris and plastic in it, evidence if bund been full of rainwater. The floor of the bund is quite dirty and muddy (Figure 39.2).
Result of Visual Inspection: Pass
Housekeeping Issues: Debris in bund. This should be removed.
Action Required:
The bund needs to be cleaned and further inspection and monitoring of the discolouration in the bund is also required.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
93
Company: Intel Ireland Ltd Photo/sketch:
See Fig 36.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 36
Bund Location: HFW/Phos Waste
Bund Description: F14 HFW Treatment Plant
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Mixture drums and plastic
vessels
Bund Materials of Construction: Concrete/self
contained bunds
Vessel(s) –
Total Storage Volume: 15m3 x 2 = 30m
3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 16.5m3
Bund Retention Volume:
23.53m3
Vessel(s) –
25% of Total Storage Volume: 7.5m3
Tank Contents:
Sludge Tank
Filtrate Tank
R Phrase (WGK Class):
Calcium Fluoride
Calcium Phosphate
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Bund no longer exists. All Waste plant has been removed from service and de-installed
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Room with CRC floor and coving to walls, trenches around room 1m to 1.5m from wall. Bund & drums appear in good condition. No evidence of leaks or cracks.
Bund Drainage System: Drain in middle of floor area, all drums on there own bunds and in good condition. Sump level detection on bund and with manual pump to sludge or reaction tanks
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
94
Company: Intel Ireland Ltd Photo/sketch:
See Fig 35.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 35
Bund Location: F14 HFW Treatment Plant
Bund Description: HF Reaction Room
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: FRP pvdf lined
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: (2 tanks in room) 2.2m3
and 1m3 =
3.2m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 2.42m3
Bund Retention Volume:
13.8m3
Vessel(s) –
25% of Total Storage Volume: 0.8m3
Tank Contents: Reaction Tank & Floc Tanks
HFW & Phos. Waste
R Phrase (WGK Class): WGK 2
R23/24/25 and R34
Very Toxic and Corrosive
Contents: High Risk Condition: Poor in areas Action: Remedial action plus hydrostatic testing
(where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Bund no longer exists. All Waste plant has been removed from service and de-installed
Result of Hydrostatic Test:
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Bund appears in good condition. No evidence of leaks or cracks. The room is lined with CRC coating on floor and coving to walls.
Bund Drainage System: Drain in middle of floor area. Sump level detection on bund and with manual pump to sludge or reaction tanks.
General Observations: Poor labelling of HF waste tank. The grate from the sump has been removed. There is some water in the sump drain and this should be disposed of. The room is very dusty and there a spill/leak from old rusty pumps near one of the exit doors. The pump/pipework may need to be replaced.
Result of Visual Inspection: Pass
Housekeeping Issues: The bund should be cleaned regularly to reduce dust. This will help maintain the CRC.
This bund should be monitored for spillages.
Action Required:
Unlabelled vessels should be clearly identified. The pumps/piping should be investigated for leaks and replaced if necessary.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
95
Company: Intel Ireland Ltd Photo/sketch:
See Fig 37a.1 – 37a.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 37a
Bund Location: CDS (KD 100)
Bund Description: KD 100 waste collection
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Plastic vessels – 316 SS
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 27m3 x 2No. = 54 m
3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 29.7 m3
Bund Retention Volume:
47.63 m3
Vessel(s) –
25% of Total Storage Volume: 13.5m3
Tank Contents: KD100 Waste R Phrase (WGK Class): R36, R38
Irritant
Contents: Low Risk Condition: Poor Action: Remedial action plus re-inspection
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Bund no longer exists. All Waste plant has been removed from service and de-installed
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Bund appears in good condition. No evidence of leaks or cracks.
Bund Drainage System: In the event of a spill bund would be pumped out. This bund is located inside so is not exposed to rainfall.
Result of Visual Inspection: Pass
Housekeeping Issues: The floor of the bund has some dried in substances indicating leak at some point (Fig.
37a.2). There is also 2 white buckets in the bund. The pipework may need to be replaced to stop this leak in future but should be investigated further.
Housekeeping around outside of bund needs to be improved.
Action Required: None
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
96
Company: Intel Ireland Ltd Photo/sketch:
See Fig 37.1 – 37.4 Site: Leixlip, Co Kildare
Bund Ref. No.: 37
Bund Location: CDS (KD 100)
Bund Description: KD 100 Plant Room
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Plastic vessels/Metal in room (kd
100 pH tank is Vinlyester FRP)
Bund Materials of Construction:
Concrete
Vessel(s) –
Total Storage Volume: 15.4m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 3.85 m3
Bund Retention Volume:
15.34 m3
Vessel(s) –
25% of Total Storage Volume: 3.85 m3
Tank Contents: (4 tanks and 4 vessels) pH
adjustment tank (T-267-1-280) 3.5m3, pH
adjustment tank (T-267-2-280) 3.5m3, 2 x No.
Descalant tanks (0.2m3 each), Reaction vessel
(RV-266-1-220) 2m3, Reaction vessel (RV-266-
2-220) 2m3, Reaction vessel (RV-266-3-220)
2m3, Reaction vessel (RV-266-4-220) 2m
3
R Phrase (WGK Class): R36, R38
Contents: Low Risk Condition: Poor in areas Action: Remedial action plus re-inspection
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Bund no longer exists. All Waste plant has been removed from service and de-installed
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Bund appears in relatively good condition. No evidence of leaks or cracks.
Bund Drainage System: Local bund - Sump level detection on bund and with manual pump to collection tanks.
General Observations: Water spills on floor of plant room. Pipework extremely corroded and floor needs to be remediated as sealant broken (Fig 37.4). Red liquid in drain should be removed as interferes with retention volume of the bund. Floor around splash guard is discoloured too and should be remediated.
Result of Visual Inspection: Pass
Housekeeping Issues: House keeping around outside of KD 100 waste collection (2 in No.) bund needs to be
improved.
Action Required:
The rusted pipework and floor should be addressed.
Check sump level detection as a lot of liquid in trenches. This requires regular empting and should be included in the site SOP.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
97
Company: Intel Ireland Ltd Photo/sketch:
See Fig 85.1 – 85.3 Site: Leixlip, Co Kildare
Bund Ref. No.: 85
Bund Location: F14 Haz Waste Loading Dock
Bund Description: C4 (DLW) – IX Treatment
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Rubber lined carbon steel
Bund Materials of Construction:
Concrete
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume:
34.84m3
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents:
Dilute lead waste,
Zeolite resin,
Sodium hypochlorite
Ion exchange resin
R Phrase (WGK Class):
R36/38 Irritant
N/A
R31, R34, WGK 2
N/A
Contents: High Risk Condition: Poor in areas Action: Remedial action plus hydrostatic testing
(where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Bund no longer exists. All Waste plant has been removed from service and de-installed
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Room with door wells and coving at wall-floor interface. Bund appears in relatively good condition. No evidence of leaks or cracks.
Bund Drainage System: Sump level detection on bund – drains along floor with sump in corner.
General Observations: Discoloration on floor around C4 vessels (Fig. 85.2), other than some minor housekeeping issues the bund is in good condition.
Result of Visual Inspection: Pass
Housekeeping Issues: House keeping in bund is not good i.e. loose pipework on ground, lids of vessels,
buckets (Fig. 85.3). General house keeping should be improved
Action Required:
Investigate cause of discolouration on bund floor.
Ensure all containers are clearly labelled.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
98
Company: Intel Ireland Ltd Photo/sketch:
See Fig 86.1 – 86.3 Site: Leixlip, Co Kildare
Bund Ref. No.: 86
Bund Location: F14 Haz Waste Loading Dock
Bund Description: Lead Reclaim (Heavy metal
reclaim)
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction:
Concrete
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents: Lead R Phrase (WGK Class): Assume high risk as corrosive and
toxic label on vessels
Contents: Assume High Risk Condition: Poor in areas Action: Remedial action plus hydrostatic
testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Bund no longer exists. All Waste plant has been removed from service and de-installed
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Bund appears in relatively good condition. No evidence of leaks. There is a crack along the back wall from the floor to the ceiling (Fig 86.3).
Bund Drainage System: Room with trenches along perimeter and coving at wall-floor interface, bund pumped out if spill occurs.
General Observations: Discoloration on floor (Fig. 86.2), other that some minor housekeeping issues the bund is in good condition.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Investigate cause of discolouration on bund floor.
Ensure all containers are clearly labelled.
Check the capacity of vessel compared to bund.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
99
Company: Intel Ireland Ltd Photo/sketch:
See Fig 87.1 – 87.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 87
Bund Location: F14 Haz Waste Loading Dock
Bund Description: Solvent Reclaim 1
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction:
Concrete
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents: Solvent waste
R Phrase (WGK Class): R10, R36/37/38
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Bund no longer exists. All Waste plant has been removed from service and de-installed
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Bund appears in relatively good condition. No evidence of leaks (Fig 87.1).
Bund Drainage System: Local Bund - Room with trenches along perimeter and coving at wall-floor interface - bund pumped out if spill occurs.
General Observations: Discoloration on floor (Fig 87.2), other that some minor housekeeping issues the bund is in good condition.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Investigate cause of discolouration on bund floor.
Check the capacity of vessel compared to bund.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
100
Company: Intel Ireland Ltd Photo/sketch:
See Fig 88.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 88
Bund Location: F14 Haz Waste Loading Dock
Bund Description: Solvent Reclaim 2
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction:
Concrete
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents: Reclaimed Ethyl-Lactate
Reclaimed nMP
R Phrase (WGK Class): Both WGK 1, R10
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Bund no longer exists. All Waste plant has been removed from service and de-installed
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Bund appears in relatively good condition. No evidence of leaks (Fig 88.1).
Bund Drainage System: Local Bund - Room with trenches along perimeter and coving at wall-floor interface - bund pumped out if spill occurs.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
101
Company: Intel Ireland Ltd Photo/sketch:
See Fig 96.1 – 96.3 Site: Leixlip, Co Kildare
Bund Ref. No.: 96
Bund Location: F14 Basement (Z40)
Bund Description: Acid Exhaust Scrubbers
(No. 1+2)
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume:
19.94m3
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents: Acid Waste R Phrase (WGK Class): R34
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09
Bund & Tank Integrity: Bunded area within the F14 basement. Bund appears in good condition. No evidence of leaks or cracks (Fig 96.1).
Bund Drainage System: Local bunding – drains along floor with sump in corner (Fig. 96.3)
General Observations: Discoloration on floor (fig. 96.2), other that some minor housekeeping issues the bund is in good condition.
Result of Visual Inspection: Pass
Housekeeping Issues:
Action Required:
Monitor discolouration in bund floor. If the bund is cleaned regularly this will increase the life span of the CRC coating. Bund needs to be cleaned.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
102
Company: Intel Ireland Ltd Photo/sketch:
See Fig 95.1 – 95.3 Site: Leixlip, Co Kildare
Bund Ref. No.: 95
Bund Location: F14 Basement (U40)
Bund Description: Acid Exhaust Scrubbers
(No. 3)
Bund Dimensions: 8.2m x 5m x 0.47mH Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Concrete
bund with plastic container and own bund for NALCO 2584
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: 19.94m3
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents:
NALCO 2584: Contains Sodium Hydroxide & Potassium Hydroxide
Acid Waste
R Phrase (WGK Class):
R35, WGK 1
R34
Contents: Low Risk Condition: Poor in areas Action: Remedial action plus re-inspection
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09
Bund & Tank Integrity: Bunded area within the F14 basement. Bund appears in good condition. No evidence of leaks or cracks (Fig 95.1).
Bund Drainage System: Local bunding – drains along floor with sump in corner. The NALCO 2584 vessel has its own self-contained bund that is pumped out if spills occur. Sand in drainage sump (Fig. 95.2).
General Observations: Discoloration on floor, other than some minor housekeeping issues the bund is in good condition. There is no splash guard in this bund and evidence that during filling chemicals are getting outside the bund (Fig. 95.3).
Result of Visual Inspection: Pass
Housekeeping Issues:
Action Required:
Investigate need for splash guard on this bund.
Sump needs to be unblocked and cleaned out.
Bund needs to be cleaned.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
103
Company: Intel Ireland Ltd Photo/sketch:
See Fig 94.1 – 94.5 Site: Leixlip, Co Kildare
Bund Ref. No.: 94
Bund Location: F14 Basement (N40)
Bund Description: Acid Exhaust Scrubbers
(No. 5)
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction:
Concrete
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: 19.94m3
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents: Sodium Hydroxide
Acid Waste
R Phrase (WGK Class): R36/38, WGK 1
R34
Contents: Low Risk Condition: Poor in areas Action: Remedial action plus re-inspection
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09
Bund & Tank Integrity: Bunded area within the F14 basement. Bund appears in relatively good condition. No evidence of leaks or cracks (Fig 94.1).
Bund Drainage System: Local bunding – drains along floor with sump in corner.
General Observations: Discoloration on floor (Fig. 94.2). There is a splash guard on the floor.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: The bund should be cleaned.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
104
Company: Intel Ireland Ltd Photo/sketch:
See Fig 93.1 – 93.3 Site: Leixlip, Co Kildare
Bund Ref. No.: 93
Bund Location: F14 Basement (G40)
Bund Description: Acid Exhaust Scrubbers
(No. 6 + 7)
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction:
Concrete
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: 19.94m3
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents: Sodium Hydroxide
Acid Scrubber Waste
R Phrase (WGK Class): R36/38 WGK 1
Contents: Low Risk Condition: Poor in areas Action: Remedial action plus re-inspection
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09
Bund & Tank Integrity: Bunded area within the F14 basement. Bund appears in relatively good condition. No evidence of leaks or cracks (Fig 93.1).
Bund Drainage System: Local bunding – drains along floor with sump in corner.
General Observations: The bund needs to be cleaned. Some loose cables, timber and piping on floor (Fig 93.2).
Result of Visual Inspection: Pass
Housekeeping Issues:
Action Required: Debris in bund needs to be cleaned.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
105
Company: Intel Ireland Ltd Photo/sketch:
See Fig 97.1 – 97.3 Site: Leixlip, Co Kildare
Bund Ref. No.: 97
Bund Location: F14 Basement (Located at
Q5 opposite Q43)
Bund Description: C4 System Lift Station
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction: N/A
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: 6320 l
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents:
Sulphuric acid and mehanesulphonic acid waste
Dilute Lead Rinse water /
PB-300 waste
R Phrase (WGK Class):
R35, WGK 1 (Low risk)
(Assumed high risk as contains lead)
R22, R23, R34, R43, R58, R60, R61, WGK 2 (High Risk)
Contents: High Risk Condition: Poor in areas Action: Remedial action plus hydrostatic testing
(where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09
Bund & Tank Integrity: Bunded area within the F14 basement. Bund appears in poor condition. The bund itself has no evidence of leaks or cracks but the splash guard is cracked in areas (fig 97.3).
Bund Drainage System: Local bunding – drains along floor with sump in corner. All tanks in one main open concetre bund.
General Observations: Discoloration on floor (Figure 97.2), other than some minor housekeeping issues the bund is in good condition. The bund needs to be cleaned. Some loose cables, timber and piping on floor.
Result of Visual Inspection: Pass
Housekeeping Issues: Bund needs to be cleaned.
Action Required:
Hydrostatic testing required and general maintenance and cleaning of bund.
Splash guard needs to be repaired.
Discolouration should be monitored.
Check the capacity of vessel compared to bund.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
106
Company: Intel Ireland Ltd Photo/sketch:
See Fig 92.1 – 92.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 92
Bund Location: F14 Basement (J44)
Bund Description: CCW Lift Tank
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction: N/A
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material:
CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents: CCW Concentrated Copper
Waste
R Phrase (WGK Class): Corrosive and Dangerous, WGK 2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09
Bund & Tank Integrity: Bunded area within the F14 basement. Bund appears in relatively good condition. No evidence of leaks or cracks (Fig 92.1).
Bund Drainage System: Local bunding – drains along floor with sump in corner.
Result of Visual Inspection: Pass
Housekeeping Issues:
Action Required: Check the capacity of vessel compared to bund. Bund needs to be cleaned.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
107
Company: Intel Ireland Ltd Photo/sketch:
See Fig 101.1 – 101.5 Site: Leixlip, Co Kildare
Bund Ref. No.: 101
Bund Location: F14 Subfab
Bund Description: HPM Rooms (Aqueous
Room)
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Metal/Plastic
Bund Materials of Construction: N/A
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material:
CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents:
Sulphuric Acid,
Hydrogen peroxide 30%
R Phrase (WGK Class):
R35, WGK 1
R5, R8, R20/22, R35, WGK1
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09
Bund & Tank Integrity: Bund appears in relatively good condition. No evidence of leaks or cracks (Fig 101.1).
Bund Drainage System: Room with wide trench perimeter and coving.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: Determine bund retention volume
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
108
Company: Intel Ireland Ltd Photo/sketch:
N/A Site: Leixlip, Co Kildare
Bund Ref. No.: 159
Bund Location: F14 Subfab
Bund Description: HPM Rooms (Solvent
Room)
Bund Dimensions: Large room bunded trenches under the floor - Complex Dimensions
Vessel(s) –
Materials of Construction: Metal/Plastic
Bund Materials of Construction: N/A
Vessel(s) –
Total Storage Volume: 12,326L
Bund Lining Material:
CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 229L
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: 3081.5L
Tank Contents:
N-Methyl-2-pyrrolidone
AZ C-265 Rinse :
2-Methoxy-1-methylethyl acetate
1 Methoxy-2-propanol
A2-A-515 Developer :
Cyclopentanone
KBR 300:
Ethyl lactate
Baker Positive Resist Striperr (PRS)-3000:
1-Methy-2-Pyrroildinone,
Tetrahydrothiophene-1,1-dioxide
2 Propanol 1-amino
THMR IP2650 HP
THMR IP2650 7CP
Isopropanol
R Phrase (WGK Class):
WGK1, R61, R36/37/38
WGK1, R10, R36
WGK1, R10, R67
WGK1, R10, R36/38
WGK1, R10, R37, R41
WGK1, R22, R36/38
WGK1, R22
WGK1, R34
R10, R20/22, R51/53
R10, R22
R11 R36 R67 WGK 1
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 16/09/09
Bund & Tank Integrity: Bund appears in relatively good condition. No evidence of leaks or cracks
Bund Drainage System: Room with wide trench perimeter and coving.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: Hydrostatic testing (where possible)
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
109
Company: Intel Ireland Ltd Photo/sketch:
N/A Site: Leixlip, Co Kildare
Bund Ref. No.: 161
Bund Location: F14 PCD
Bund Description: F14 PCD - Planar Chemical
Distribution
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: N/A
Vessel(s) –
Total Storage Volume: 15,000L
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 1387L
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: 3750L
Tank Contents:
PL4217 Oxide Slurry
Silica, Amorphous
Potassium hydroxide
KD100C
Hydrocyanic Acid
R Phrase (WGK Class):
Not classed under the EU legislation but assume low risk as silca is relatively inert
WGK 1, R22, R35
R20/21/22, R52/53, WGK3
Contents: High Risk Condition: Good Action: Hydrostatic testing (where
possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 16/9/09
Bund & Tank Integrity: Bund appears in good condition. Totes containing planar slurries located in this room.
Bund Drainage: Bund drainage unknown, room appears to slope into the middle of the room and open drain located at lowest points.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: Hydrostatic testing (where possible). Determine bund retention volume.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
110
Company: Intel Ireland Ltd Photo/sketch:
See Fig 30.1 – 30.5 Site: Leixlip, Co Kildare
Bund Ref. No.: 30
Bund Location: North Road Beside Energy
Centre
Bund Description: F14 Emergency Generator
Diesel bund
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: N/A
Bund Materials of Construction: N/A
Vessel(s) –
Total Storage Volume: 2 x 60m3
& 4 x 1m3
= 124m3
Bund Lining Material: N/A
Vessel(s) –
110% of Volume of Largest Vessel: 66m3
Bund Retention Volume: 137.35m3
Vessel(s) –
25% of Total Storage Volume: 31m3
Tank Contents: Waste Oil (Diesel), Diesel
(gas oil), Antifreeze, Waste Oil, Transformers (EG-8, EG-9, EG-10, EG-11)
R Phrase (WGK Class):
Waste Oil Diesel: R40 WGK 2
Diesel Gas Oil: R40, Harmful
Transformer Oil: WGK 2
Risk Phrases: R45
Contents: High Risk Condition: Poor in areas Action: Remedial action plus hydrostatic testing
(where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 19/1/09
Bund & Tank Integrity: Bund has grate slab with upstand all around. Bund appears to be generally intact – no visible cracks or leaks internally. However significant mossy growth coverage on base of bund and tree/bush growth (Fig. 30.1-30.5) therefore could not fully inspect. There are a lot of leaves in bund and these are blocking the drains along the drainage channels. There is evidence of water in bund but it was quite a wet weekend and it is assumed that this is rainwater. There is evidence of cracks along the kerbs of this bund.
The transformers (x4) have there own metal bund with this larger bund. Covered in moss and filed with water, this needs to be cleaned and water removed.
Bund Drainage System: Local bund. Bund slopes therefore rainwater collecting at one end of bund.
General observations: Tree and shrub growth in bund needs to be removed.
Result of Visual Inspection: Fail
Housekeeping Issues:
Bund needs to be cleaned as there is a lot of overgrowth in the bund including leaves. There are absorbent materials and pallets in bund, these should be removed. The slip mats in the bund are in very poor condition and either need to be cleaned or replaced in some areas as they are covered in moss and are extremely slippy.
Action Required:
Water retention from each transformer bund should be emptied.
The bund needs to be regularly monitored and cleaned.
Cracks along kerb need to be inspected and repaired as necessary.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
111
Bund ID: F14 Generator Diesel Bund
Result of Hydrostatic Test: Fail
Date of hydrostatic Test: 14/2/11
Length of test: 24hrs
Measurement at beginning of test: 75mm
Measurement at end of test: 0mm (Note:
Holding tank was still full. Above measurements were for surface water. )
Volume Tested to: 66m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Eamon McIvor Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
112
Company: Intel Ireland Ltd Photo/sketch:
See Fig 143.1 – 143.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 143
Bund Location: F14 Basement (M46)
Bund Description: PCW/CPCW Chemical
Dosing (Nalco 2536+)
Bund Dimensions: 1.05 x 0.75 x 0.4m =
0.315m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 280L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 308L
Bund Retention Volume: 315L
Vessel(s) –
25% of Total Storage Volume: 70L
Tank Contents: Sodium Nitrite R Phrase (WGK Class): R22, R52, WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 18/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues:
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
113
Company: Intel Ireland Ltd Photo/sketch:
See Fig 144.1 – 144.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 144
Bund Location: F14 Basement (S49) Tank
No. SN907042
Bund Description: PVAC Dosing - Nalco
2510
Bund Dimensions: 0.8 x 1.2 x 0.45m =
0.430m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 260L
Bund Lining Material: none
Vessel(s) –
110% of Volume of Largest Vessel: 286L
Bund Retention Volume: 430L
Vessel(s) –
25% of Total Storage Volume: 65L
Tank Contents: 2,2-Dibromo-3-
Nitrilopropionamide
R Phrase (WGK Class): R20/22, R38, R43, R41, WGK3
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: Assess practicality of hydrostatically
testing bunds in basement.
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 18/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues:
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
114
Company: Intel Ireland Ltd Photo/sketch:
See Fig 145.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 145
Bund Location: F14 Basement (S49)
Bund Description: PVAC Dosing Skid (Nalco
8539) (Tank No. SN182782)
Bund Dimensions: 0.9 x 1.2 x 0.55m =
0.594m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 440L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 484L
Bund Retention Volume: 0.9 x 1.2 x 0.55m =
0.594m3
Vessel(s) –
25% of Total Storage Volume: 110L
Tank Contents: Sodium Nitrite & Potassium
Hydroxide
R Phrase (WGK Class): R25, R36/38, R50
WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 18/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
115
Company: Intel Ireland Ltd Photo/sketch:
See Fig 146.1 – 146.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 146
Bund Location: F14 Basement (T41) PVAC
Dosing Skid (Tank No. SNJP0061)
Bund Description: Scrubber Cleaning (Nalco
2584)
Bund Dimensions: 1 x 1.4 x 0.7m = 0.98m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 750L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 825L
Bund Retention Volume: 980L
Vessel(s) –
25% of Total Storage Volume: 187.5L
Tank Contents: Sodium Hydroxide &
Potassium Hydroxide
R Phrase (WGK Class): R35
WGK1
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 18/5/09
Bund & Tank Integrity: Bund appears in good condition but there is evidence of leaks in bund, white power and gloves in bund.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: Bund should be cleaned out
Action Required: None
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
116
Company: Intel Ireland Ltd Photo/sketch:
See Fig 147.1 – 147.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 147
Bund Location: F14 Basement (R43)
Bund Description: DL W Dosing - ST40
Bund Dimensions: 0.9 x 1.2 x 0.55m =
0.594m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 440L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 484L
Bund Retention Volume: 594L
Vessel(s) –
25% of Total Storage Volume: 110L
Tank Contents: Sodium Hydroxide, Sodium
Hypochlorite
R Phrase (WGK Class): R34, R31, WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: Assess practicality of
hydrostatically testing bunds in basement.
Bund no longer exists. All Waste plant has been removed from service and de-installed
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 18/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
117
Company: Intel Ireland Ltd Photo/sketch:
See Fig 137.1 - 137.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 137
Bund Location: F14 Nitrogen Plant
Bund Description: Transformer Bund
Bund Dimensions: Irregular shape Vessel(s) –
Materials of Construction: Metal Transformers on gravel
bund
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 584L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 642.4L
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: 146L
Tank Contents: Electrical insulating oil
R Phrase (WGK Class): WGK 1
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: Local bund - If leak occurs the bund is manually pumped out and cleaned.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: Determine bund retention volume
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
118
Company: Intel Ireland Ltd Photo/sketch:
See Fig 138.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 138
Bund Location: F14 UPW
Bund Description: URW Dosing - Nalco
77357 (SN47174)
Bund Dimensions: 1.9 x 3 x 0.4m = 2.28m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 800L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 880L
Bund Retention Volume: 2280L
Vessel(s) –
25% of Total Storage Volume: 200L
Tank Contents: Sodium Bromide
R Phrase (WGK Class): R36, WGK1
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: Local bund - If leak occurs the bund is manually pumped out and cleaned.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: None
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
119
Company: Intel Ireland Ltd Photo/sketch:
See Fig 139.1 – 139.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 139
Bund Location: F14 UPW
Bund Description: URW Dosing (Nalco
93033)
Bund Dimensions: 1.9 x 1.6 x 0.65m =
1.976m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 1500L
Bund Lining Material: none
Vessel(s) –
110% of Volume of Largest Vessel: 1650L
Bund Retention Volume: 1976L
Vessel(s) –
25% of Total Storage Volume: 375L
Tank Contents: Sodium Hypochlorite
R Phrase (WGK Class): R31, R34, WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? N/A
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: Local bund - If leak occurs the bund is manually pumped out and cleaned.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
120
Company: Intel Ireland Ltd Photo/sketch:
See Fig 64.1 – 64.3 Site: Leixlip, Co Kildare
Bund Ref. No.: 64
Bund Location: F14 UPW
Bund Description: RO Cleaning Chemical
Bund (3 individual bunds)
Bund Dimensions: Complex dimensions
Vessel(s) –
Materials of Construction: Various plastic/metal vessels
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents:
Anti-Scalant,
Biocide,
Sodium Bisulphite (NaHSO3)
R Phrase (WGK Class):
N/A
R34, R43, R52/53
R22, R31 WGK 1
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09
Bund & Tank Integrity: Bunded area within the F24 UPW room divided into three individual bunds by coated upstands. No visible cracks or leaks in bund and general in good condition.
General Observation: Bund consists of three smaller individual bunds i.e. Anti-Scalant, Biocide and Sodium Bisulphite. Sodium bisulphite bund has some discolouration indicating a leak or spill and integrity should be tested in this bund (Fig. 64.2). In the event of a spill or leak the bund will be manually pumped out.
Result of Visual Inspection: Pass
Housekeeping Issues: Bunds should be cleaned.
Action Required: Determine bund retention volume.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
121
Company: Intel Ireland Ltd Photo/sketch:
See Fig 125.1 – 125.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 125
Bund Location: F14 Energy Centre OFA &
Condenser Cooling Tower (Tank No. SN182766)
Bund Description: Nalco 3DT188
Bund Dimensions: 0.9 x 1.2 x 0.55m =
0.594m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 440L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 484L
Bund Retention Volume: 594L
Vessel(s) –
25% of Total Storage Volume: 110L
Tank Contents: Phosphoric Acid
R Phrase (WGK Class): R34, WGK 1
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: None
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
122
Company: Intel Ireland Ltd Photo/sketch:
See Fig 126.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 126
Bund Location: F14 Energy Centre OFA &
Condenser Cooling Tower (Tank No. SN182963)
Bund Description: Nalco 3DT222
Bund Dimensions: 0.9 x 1.2 x 0.55m =
0.594m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 440L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 484L
Bund Retention Volume: 594L
Vessel(s) –
25% of Total Storage Volume: 110L
Tank Contents: Phosphoric Acid &
Hydrochloric Acid & Zinc Chloride
R Phrase (WGK Class): R36/38, R51/53
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Testing would involve taking the primary vessel offline which would impact fab operations
Result of Hydrostatic Test:
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: Local bund - If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
123
Company: Intel Ireland Ltd Photo/sketch:
See Fig 127.1 – 127.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 127
Bund Location: F14 Energy Centre Chilled
Water/MTHW (Tank No. SNJP0130)
Bund Description: Nalco 93033
Bund Dimensions: 1.4 x 1 x 0.77m = 1.078m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 750L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 825L
Bund Retention Volume: 1078L
Vessel(s) –
25% of Total Storage Volume: 187.5L
Tank Contents: Sodium Hypochlorite
R Phrase (WGK Class): R31, R34, WGK 2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Testing would involve taking the primary vessel offline which would impact fab operations
Result of Hydrostatic Test:
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
124
Company: Intel Ireland Ltd Photo/sketch:
See Fig 128.1- 128.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 128
Bund Location: F14 Energy Centre
Condenser water
Bund Description: Nalco 00GE056
Bund Dimensions: 0.9 x 1.2 x 0.55m =
0.594m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 440L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 484L
Bund Retention Volume: 594L
Vessel(s) –
25% of Total Storage Volume: 110L
Tank Contents: Disodium Metasilicate, Sodium
Molybdate, Sodium Tetraborate
R Phrase (WGK Class): R36/38
WGK 1
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: None
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
125
Bund ID: Bund Ref. No.: 128
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 2/12/10
Length of test: 24 hrs
Measurement at beginning of test: 550mm
Measurement at end of test: 550mm
Volume Tested to: 0.430 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Simon McLain Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
126
Fab 24 Bunds
DATA SHEET: BUNDING STRUCTURES
127
Company: Intel Ireland Ltd Photo/sketch:
See Fig 75.1 – 75.3 Site: Leixlip, Co Kildare
Bund Ref. No.: 75
Bund Location: F24 AWN PIT
Bund Description: F24 AWN
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Vinylester FRP
Bund Materials of Construction: concrete
Vessel(s) –
Total Storage Volume: 103.8m 3
x 7 = 726.6m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 114.18m3
Bund Retention Volume:
355.7m3
Vessel(s) –
25% of Total Storage Volume: 181.65m3
Tank Contents:
AWN and URW/IRW Tanks (7 in No.)
R Phrase (WGK Class): R36/37/38
Contents: Low Risk Condition: Poor in
areas
Action: Remedial action plus re-inspection
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
This is a remote bund for other areas containing high risk substances therefore it should be hydrostatically tested as the risk category is potentially high risk.
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
This bund has a number of critical systems feeding in which cannot be isolated without a factory impact. A practicable bund test cannot be completed
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally. There is some discolouration in the bund (Fig. 75.3) (from leak in past), this should be investigated.
Bund Drainage System: Sump automatically pumped to the AWN. This is a remote bund for other areas containing high risk substances.
General observations: Debris in bund needs to be removed (Fig. 75.2).
Results of Visual Inspection: Pass
Housekeeping Issues:
Bund needs to be cleaned as there is a lot of debris in the bund and bag of construction materials gathered at the base of the bund. (Done)
Action Required:
Discolouration on bund floor should be monitored.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
128
Company: Intel Ireland Ltd Photo/sketch:
See Fig 82.1
Site: Leixlip, Co Kildare
Bund Ref. No.: 82
Bund Location: F24 AWN PIT
Bund Description: HFW Lift Tank
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Polypropylene lined FRP
Bund Materials of Construction: concrete
Vessel(s) –
Total Storage Volume: 4m3
x 2 = 8m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 4.4m3
Bund Retention Volume:
10.5m3
Vessel(s) –
25% of Total Storage Volume: 2m3
Tank Contents:
HFW Lift Tanks (2 in No.)
R Phrase (WGK Class): R39/26/27/28, R34
WGK 2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: Pass (See addendum below for details)
Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally.
Bund Drainage System: Local bund - sump with auto capability to the HF lift tanks only.
Results of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
Bund ID: 82
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 7/3/10
Length of test: 24hrs
Measurement at beginning of test: 138mm
Measurement at end of test: 138mm
Volume Tested to: 3.4m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Alan Campbell Title: IWS Engineer
DATA SHEET: BUNDING STRUCTURES
129
Company: Intel Ireland Ltd Photo/sketch:
See Fig 81.1 – 81.2
Site: Leixlip, Co Kildare
Bund Ref. No.: 81
Bund Location: F24 AWN PIT
Bund Description: Phosphoric Acid Holding
Tank
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: FRP
Bund Materials of Construction: concrete
Vessel(s) –
Total Storage Volume: 18.7m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 20.57m3
Bund Retention Volume:
49.1m3
Vessel(s) –
25% of Total Storage Volume: 4.675m3
Tank Contents:
Phosphoric Acid Holding Tank containing Phosphoric Acid H3PO4
R Phrase (WGK Class): WGK 1, R20/21/22, R34
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally.
Bund Drainage System: Sump with manual valve that is pumped to AWN or collection tank.
General observations: Debris in bund.
Result of Visual Inspection: Pass
Housekeeping Issues: There is some rainwater and leaves in this bund. Debris in bund needs to be removed
(Fig 81.2). Monitor bund for discolouration.
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
130
Company: Intel Ireland Ltd Photo/sketch:
No photos available Site: Leixlip, Co Kildare
Bund Ref. No.: 79
Bund Location: F24 AWN PIT
Bund Description: NH4W Lift Tanks
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: FRP
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 10.2m3
x 2 =20.4m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 11.22m3
Bund Retention Volume: 31.1m3
Vessel(s) –
25% of Total Storage Volume: 5.1m3
Tank Contents: NH4 tanks (Ammonium
chloride)
R Phrase (WGK Class): WGK 1, R22, R36
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally.
Bund Drainage System: Sump with automatic valve that is pumped to AWN and lift tank.
Result of Visual Inspection: Pass
Housekeeping Issues:
There is some rainwater and leaves in this bund. Debris in bund needs to be removed.
Action Required: None
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
131
Company: Intel Ireland Ltd Photo/sketch:
See Fig 78.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 78
Bund Location: F24 AWN PIT
Bund Description: SCW/CCW Bund
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: FRP
Bund Materials of Construction: concrete
Vessel(s) –
Total Storage Volume:
CCW Holding Tank – 19m3
SCW Lift Tank – 7m3
Total = 26m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 20.9 m3
Bund Retention Volume:
51.7 m3
Vessel(s) –
25% of Total Storage Volume: 6.5 m3
Tank Contents:
CCW Holding Tank containing concentrated copper waste
SCW Lift Tank containing slurry copper waste
R Phrase (WGK Class):
R34, WGK2
R36/37/38
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: Pass (See addendum below for details)
Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks.
Bund Drainage System: Sump with manual valve that is pumped to CCW tank and SCW lift tank.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
132
Bund ID: 78
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 25/3/10
Length of test: 24hrs
Measurement at beginning of test: 68mm
Measurement at end of test: 68mm
Volume Tested to: 7.5m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Alan Campbell Title: IWS Engineer
DATA SHEET: BUNDING STRUCTURES
133
Company: Intel Ireland Ltd Photo/sketch:
See Fig 77.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 77
Bund Location: F24 AWN PIT
Bund Description: C4 bund
RMW (Reclaim metal waste, DMW (Dilute metal waste), DMW (Divert metal waste), CMW (Concentrated metal waste) (4 in No.)
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 29.1m3 x 4 = 116.4m
3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 32.01m3
Bund Retention Volume: 79.6m3
Vessel(s) –
25% of Total Storage Volume: 29.1m3
Tank Contents:
RMW: C4 reclaim metal waste
Dilute Metal Waste
Divert Metal Waste
CMW: C4 concentrated metal waste
R Phrase (WGK Class):
R33, R34, R58, R60, R61
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: Pass (See addendum below for details)
Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks.
Bund Drainage System: Sump options: Two pumps in bund, east and west pump both manually operated to all tanks within the bund RMW, CMW, DMW and MWD.
General Observations: There is some discolouration on the bund floor.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
134
Bund ID: 77
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 9/3/10
Length of test: 24hrs
Measurement at beginning of test: 147mm
Measurement at end of test: 147mm
Volume Tested to: 11.7m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Alan Campbell Title: IWS Engineer
DATA SHEET: BUNDING STRUCTURES
135
Company: Intel Ireland Ltd Photo/sketch:
See Fig 76.1 – 76.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 76
Bund Location: F24 AWN PIT
Bund Description: CSW (Corrosive Solvent
Waste)
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: 22.3m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 24.53m3
Bund Retention Volume: 51.7m3
Vessel(s) –
25% of Total Storage Volume: 5.575m3
Tank Contents:
Corrosive Solvent Waste (CSW) (Sulfolane Tetramethylammonium Hydroxide)
R Phrase (WGK Class): R22, R34, WGK 1
Contents: Low Risk Condition: Poor in
areas
Action: Remedial action plus re-inspection
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks.
Bund Drainage System: Sump with manual valve that is pumped to CSW tank only.
General Observations: There is some discolouration on the bund floor (fig 76.2).
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Investigate the discolouration on the bund floor and remediate if necessary
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
136
Company: Intel Ireland Ltd Photo/sketch:
See Fig 83.1 – 83.3 Site: Leixlip, Co Kildare
Bund Ref. No.: 83
Bund Location: F24 AWN PIT
Bund Description: Solvent Area
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: N/A
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume: 19.9m3 x 3 = 59.7m
3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 65.67m3
Bund Retention Volume:
123.1m3
Vessel(s) –
25% of Total Storage Volume: 14.925m3
Tank Contents:
General Solvent Collection
General Solvent Divert
SOG
R Phrase (WGK Class): Unknown, assume high risk
Contents: Assume High Risk Condition: Poor in
areas
Action: Remedial action plus hydrostatic testing
(where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: Pass (See hydrostatic Results in addendum below)
Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks. There is some rainwater in this bund.
Bund Drainage System: Sump with manual valve that is pumped to CSW tank only.
General Observations: There is some discolouration on the bund floor (Fig 83.2). The bund needs to be cleaned. There is some white foam need door (Fig. 83.3), this should be cleaned and investigated further.
Result of Visual inspection: Pass
Housekeeping Issues: Some debris in bund. This should be removed.
Action Required:
The bund should be cleaned and any debris and maintenance materials removed.
Investigate foam on wall behind bund door.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
137
Bund ID: 83
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 11/3/10
Length of test: 24hrs
Measurement at beginning of test: 235mm
Measurement at end of test: 235mm
Volume Tested to: 11m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Alan Campbell Title: IWS Engineer
DATA SHEET: BUNDING STRUCTURES
138
Company: Intel Ireland Ltd Photo/sketch:
See Fig 80.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 80
Bund Location: F24 AWN Area
Bund Description: C4 Dilute Metal Waste
Treatment
Bund Dimensions: Complex Dimensions Vessel(s) –
Materials of Construction: Plastic and Metal
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume: 3 x IX beds
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume:
1.19m3
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents:
Dilute Metal Waste
R Phrase (WGK Class): Corrosive & Dangerous to the
Environment
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: Pass (See addendum below for results of hydrostatic test)
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks.
Bund Drainage System: Local bund – Bund is checked and manually pumped to AWN as required.
Result of visual Inspection: Pass
Housekeeping Issues: Some loose cabling and wires need to be removed from bund.
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
139
Bund ID: 80
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 11/3/10
Length of test: 24hrs
Measurement at beginning of test: 56mm
Measurement at end of test: 56mm
Volume Tested to: 4.6m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Alan Campbell Title: IWS Engineer
DATA SHEET: BUNDING STRUCTURES
140
Company: Intel Ireland Ltd Photo/sketch:
See Fig 72.1 – 72.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 72
Bund Location: F24 AWN AREA
Bund Description: IWW Tanks
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Vinlester FRP
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume: 146.8m3
x 3 = 440.4m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 161.48m3
Bund Retention Volume:
202.6m3
Vessel(s) –
25% of Total Storage Volume: 110.1m3
Tank Contents:
Acid Waste (3 in No.)
R Phrase (WGK Class): R20/21/22
Contents: Low risk Condition: Poor in
areas
Action: Remedial action
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally. However tree/bush growth from grate between TK-261-1-190 & TK-261-2-190 (Fig. 72.2). There is also some discolouration from moss growth in the bund. Liquid retention in bund (rainwater) which is reducing retention capacity.
Bund Drainage System: Local bund - Sump options with manual drain valve to AWN.
Result of Visual Inspection: Pass
Housekeeping Issues:
Bund needs to be cleaned as there is a lot of overgrowth in the bund and leaves.
Action Required:
Bund requires regular emptying to ensure required storage capacity for spills/leaks.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
Bund ID: Bund Ref. No.: 72
Result of Hydrostatic Test: Fail
Date of hydrostatic Test: 2/3/11
Length of test: N/A
Measurement at beginning of test: N/A
Measurement at end of test: N/A
Volume Tested to: N/A
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Michelle Cronin Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
141
Company: Intel Ireland Ltd Photo/sketch:
See Fig 74.1 – 74.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 74
Bund Location: F24 AWN AREA
Bund Description: Sodium Hydroxide Bridge
Scrubber Day Tank
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: 316 SS
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume: 1.7m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 1.87 m3
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: N/A
Tank Contents:
Sodium Hydroxide NaOH
R Phrase (WGK Class): R35, WGK 1
Contents: Low Risk Condition: Poor in
areas
Action: Remedial action plus re-inspection
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally. (Fig. 74.1). There is also some discolouration from moss growth in the bund. Pipework to tanks in poor condition – insulation falling off and pipework broken (see Fig. 74.2).
Bund Drainage System: Sump options with manual drain valve to AWN. Grate in corner is extremely rusty and needs to be replaced.
Result of Visual Inspection: Pass
Housekeeping Issues: 7up bottle in outlet pump needs to be removed and bund should be checked for other
housekeeping issues and cleaned accordingly.
Action Required:
Pipework should be fixed and replaced if necessary. Determine bund retention volume.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
142
Company: Intel Ireland Ltd Photo/sketch:
See Fig 73.1 – 73.3 Site: Leixlip, Co Kildare
Bund Ref. No.: 73
Bund Location: F24 AWN AREA
Bund Description: Sulphuric Acid Bridge Day
Tank
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: FRP pvdf lined
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume: 14.9m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 16.39 m3
Bund Retention Volume:
42.2m3
Vessel(s) –
25% of Total Storage Volume: 3.725 m3
Tank Contents:
Sulphuric Acid
R Phrase (WGK Class): R20/21/22, R35, R41, WGK 1
Contents: Low Risk Condition: Poor in
areas
Action: Remedial action plus re-inspection
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Bund is in poor condition, corrosion in bund appears to have removed some CRC coating and this should be fixed (Fig. 73.3). The bund appears to be generally intact – no other visible cracks. There is also some discolouration from moss growth in the bund. Pipework to tanks in good condition (see Fig. 73.2).
Bund Drainage System: Sump options with manual drain valve to AWN.
Result of Visual Inspection: Fail
Housekeeping Issues: None
Action Required:
The corroded area for the bund mentioned above should be recoated with CRC coating. Bund should be regularly investigated for leaks and monitored for discolouration.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
143
Company: Intel Ireland Ltd Photo/sketch:
See Fig 67.1 – 67.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 67
Bund Location: F24 PSB Tank Farm
Bund Description: CCW Prep Tank
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: FRP (Fibre reinforced plastic)
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume: 7m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 7.7m3
Bund Retention Volume: 73.76m3
Vessel(s) –
25% of Total Storage Volume: 1.75m3
Tank Contents:
20% H2SO4
5% Cu
5% H2O2
5% NaHSO3
1% HCL
1% CH4SO3
R Phrase (WGK Class): R35, R51/53, WGK 2
Contents: High Risk Condition: Poor in
areas
Action: Remedial action plus hydrostatic testing
(where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: Pass (See addendum below)
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Pipework to tanks in poor condition – pipework broken and rusting (see Fig. 67.2). There is evidence of cracks in this bund on the tank pad and CRC damage.
Bund Drainage System: Sump options with manual pump to AWN and prep tank.
Result of Visual Inspection: Fail
Housekeeping Issues: Bund needs to be cleaned as there is some leaves in the base.
Action Required:
Bund should be monitored for leaks.
CRC and cracks should be repaired.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
144
Bund ID: 67
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 14/3/10
Length of test: 24hrs
Measurement at beginning of test: 70mm
Measurement at end of test: 70mm
Volume Tested to: 6.7m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Alan Campbell Title: IWS Engineer
DATA SHEET: BUNDING STRUCTURES
145
Company: Intel Ireland Ltd Photo/sketch:
See Fig 66.1 – 66.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 66
Bund Location: F24 PSB Tank Farm
Bund Description: Ammonium Sulphate
Bund Dimensions: 5.5m x 13.5m x 1mH
Vessel(s) –
Materials of Construction: Metal tank
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume: 21m3 x 2 = 42m
3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 23.1m3
Bund Retention Volume: 145.8m3 Vessel(s) –
25% of Total Storage Volume: 10.5m3
Tank Contents:
Ammonium Sulphate Collection Tanks (2 in No.)
(NH4)2SO2
R Phrase (WGK Class): R36/37/38, WGK 1
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally (Fig. 66.1). There is also some discolouration from moss growth in the bund.
Bund Drainage System: Sump options with automatically drain valve to AWN, NH4W collection tanks and Ammonia sulphate collection tanks.
Result of Visual Inspection: Pass
Housekeeping Issues: Debris in bund should be removed (Fig.66.2).
Action Required: None
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
146
Company: Intel Ireland Ltd Photo/sketch:
See Fig 60.1 – 60.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 60
Bund Location: F24 PSB Tank Farm
Bund Description: Lime Storage Silo
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Metal tank
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents:
Calcium Hydroxide (CaOH2)
R Phrase (WGK Class): R34, R36/37/38
WGK 1
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally (Fig. 61.1). There is also some rainwater in the bund (Fig. 61.2).
Bund Drainage System: Sump with capability to automatically pump to AWN only.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
All tanks should be clearly labelled with contents. Determine bund retention volume.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
147
Company: Intel Ireland Ltd Photo/sketch:
See Fig 59.1 – 59.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 59
Bund Location: F24 PSB Tank Farm
Bund Description: HFW Collection/Divert
Tanks
Bund Dimensions: Complex dimensions
Vessel(s) –
Materials of Construction: Polypropylene lined FRP
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume: 158.6m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 174.46m3
Bund Retention Volume:
215.9m3
Vessel(s) –
25% of Total Storage Volume: 39.65m3
Tank Contents: Hydrofluoric acid
R Phrase (WGK Class): R26/27/28, R34
WGK 2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: Pass (See addendum below for results)
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally (Fig. 59.1). There is also some rainwater in the bund. There is some debris including leaves in the area close to outlet sump.
Bund Drainage System: Sump with capability to automatically pump to collection tanks only.
General Observations: Some plastic has fallen from behind the TK-266-2-200 tank and needs to be removed from the bund.
Result of Visual Inspection: Pass
Housekeeping Issues: Debris in bund should be removed (Fig. 59.2).
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
148
Bund ID: 59
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 14/3/10
Length of test: 24hrs
Measurement at beginning of test: 70mm
Measurement at end of test: 70mm
Volume Tested to: 36m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Alan Campbell Title: IWS Engineer
DATA SHEET: BUNDING STRUCTURES
149
Company: Intel Ireland Ltd Photo/sketch:
See Fig 63.1 – 63.3 Site: Leixlip, Co Kildare
Bund Ref. No.: 63
Bund Location: F24 PSB Tank Farm
Bund Description: HCI Acid Bulk
Bund Dimensions: Complex dimensions
Vessel(s) –
Materials of Construction: FRP
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume: 11.2m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 12.32m3
Bund Retention Volume:
62.4m3
Vessel(s) –
25% of Total Storage Volume: 2.8m3
Tank Contents: Hydrochloric acid (HCl)
R Phrase (WGK Class): R20/21/R22, R35, R41
WGK 1
Contents: Low Risk Condition: Poor in
areas
Action: Remedial action plus re-inspection
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally (Fig. 63.1). There is also some rainwater in the bund. The grate over the outlet sump is rusted and there appears to be some rusting around the base of the HCl tank (Fig. 63.2). This tank should be investigated further for leaks and checked on a regular basis.
Bund Drainage System: Sump options with manual drain valve to AWN.
Result of Visual Inspection: Pass
Housekeeping Issues: The bund needs to be cleaned.
Action Required:
The bund should be checked for leaks on a regular basis.
Monitor rusting.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
150
Company: Intel Ireland Ltd Photo/sketch:
See Fig 62.1 – 62.4 Site: Leixlip, Co Kildare
Bund Ref. No.: 62
Bund Location: F24 PSB Tank Farm
Bund Description: Sulphuric Acid Bulk
Bund Dimensions: Complex dimensions
Vessel(s) –
Materials of Construction: FRP pvdf lined
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume: 12.3m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 13.53m3
Bund Retention Volume:
55.6m3
Vessel(s) –
25% of Total Storage Volume: 3.075m3
Tank Contents: Sulphuric acid (H2SO4)
R Phrase (WGK Class): R35, R41, R20, R21, R22
WGK 1
Contents: Low Risk Condition: Poor in areas Action: Remedial action plus re-inspection
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks (Fig. 62.1). There is also some rainwater in the bund. There appears to be rusting on the supports / base plates of the bund (Fig. 62.2). Floor appears discoloured from the rusting supports.
Bund Drainage System: Sump options with manual drain valve to AWN.
General observations: Some pipework appears to be broken.
Result of Visual Inspection: Pass
Housekeeping Issues: Debris in bund should be removed (Fig. 62.4).
Action Required:
Rusting should be monitored and if necessary the base supports should to be replaced.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
151
Company: Intel Ireland Ltd Photo/sketch:
See Fig 61.1 – 61.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 61
Bund Location: F24 PSB Tank Farm
Bund Description: Sodium Hydroxide Bulk
Tank
Bund Dimensions: Complex dimensions
Vessel(s) –
Materials of Construction: 316 SS
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume: 29.9m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 32.89m3
Bund Retention Volume:
67.7m3
Vessel(s) –
25% of Total Storage Volume: 7.475m3
Tank Contents: Sodium Hydroxide (NaOH)
R Phrase (WGK Class): R35, R41, R20/ R21/ R22
WGK 1
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks (Fig. 61.1). The bund has recently been recoated in certain areas with CRC but there are still some areas where discolouration is evident, this should be monitored for further deterioration (Fig. 61.2).
Bund Drainage System: Sump options with manual drain valve to AWN.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: None
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
152
Company: Intel Ireland Ltd Photo/sketch:
See Fig 58.1 – 58.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 58
Bund Location: F24 PSB Tank Farm
Bund Description: SCW Buffer Tanks
Bund Dimensions: Complex dimensions
Vessel(s) –
Materials of Construction: FRP
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume: 67.2m3
x 2 = 134.4m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 73.92m3
Bund Retention Volume:
198.2m3
Vessel(s) –
25% of Total Storage Volume: 33.6m3
Tank Contents: Slurry Copper Waste (SCW)
R Phrase (WGK Class): R21/22, R36/38
Contents: Low Risk Condition: Poor in
areas
Action: Remedial action plus re-inspection
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Re-Testing completed
Result of Hydrostatic Test: Pass
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Tanks & bunds appear in good condition. No evidence of cracks or leaks and ground around dry. Liquid retention in both bunds (probably rainwater) which is reducing retention capacity. There appears to be some discolouration from moss growth in the bund (Fig. 58.1).
Bund Drainage System: Sump with auto capability to pump to collection tanks
General Observations: The construction/maintenance materials should be removed from the bund (Fig. 58.2).
Result of Visual Inspection: Pass
Housekeeping Issues: Debris in bund should be removed. (Done)
Action Required:
Rusting should be monitored.
Bunds require regular emptying to ensure required storage capacity for spills/leaks.
Bund should be cleaned.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
Bund ID: 58
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 18/3/10
Length of test: 24hrs
Measurement at beginning of test: 75mm
Measurement at end of test: 75mm
Volume Tested to: 30m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Alan Campbell Title: IWS Engineer
DATA SHEET: BUNDING STRUCTURES
153
Company: Intel Ireland Ltd Photo/sketch:
See Fig 65a.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 65a
Bund Location: F24 PSB
Bund Description: F24 CCW Treatment Plant
Bund Dimensions: Complex dimensions
Vessel(s) –
Materials of Construction: Various metal/plastic containers
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents:
20% H2SO4
20% NaOH
5% Cu
5% NaHSO3
2% CH4SO3
1% H2O2
1% HCL
R Phrase (WGK Class): R35, WGK 2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: Pass (See addendum below)
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Room with coving all around. Trench perimeter except at the roller shutter door Bund appears in good condition. No evidence of leaks or cracks.
Bund Drainage System: Manually operated options to go to AWN and prep tank. Bund is indoors so is not exposed to rainwater.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: Determine bund retention volume.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
154
Bund ID: 65A
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 11/3/10
Length of test: 24hrs
Measurement at beginning of test: 295mm
Measurement at end of test: 295mm
Volume Tested to: 31.5m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Alan Campbell Title: IWS Engineer
DATA SHEET: BUNDING STRUCTURES
155
Company: Intel Ireland Ltd Photo/sketch:
See Fig 65.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 65
Bund Location: F24 PSB
Bund Description: F24 HFW and SCW
Treatment Plant
Bund Dimensions: Complex dimensions
Vessel(s) –
Materials of Construction: Various metal/plastic vessels
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume: 49m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: 78m3 Vessel(s) –
25% of Total Storage Volume: 12.25m3
Tank Contents:
Hydrofluoric Acid (HFW) and
Slurry Copper Waste (SCW, NaOH, H2SO4)
R Phrase (WGK Class):
R26/27/28, R34, WGK 2
R20/21/22, R34, R36/38, R41
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: Pass (See addendum Below)
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Trench around equipment, floor falls to trench and coving around. Bund appears in good condition. No evidence of leaks or cracks.
Bund Drainage System: Manually operated options to go to AWN, Sludge tank and collection tanks for HFW bund and automatically piped to collection tanks is applied to the SCW tank. Bund is indoors so is not exposed to rainwater.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
Bund ID: 65
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 11/3/10
Length of test: 24hrs
Measurement at beginning of test: 420mm
Measurement at end of test: 420mm
Volume Tested to: 78m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Alan Campbell Title: IWS Engineer
DATA SHEET: BUNDING STRUCTURES
156
Company: Intel Ireland Ltd Photo/sketch:
See Fig 51.1 – 51.4 Site: Leixlip, Co Kildare
Bund Ref. No.: 51
Bund Location: F24 Middle Yard
Bund Description: Softened Industrial Water
(SIW)
Bund Dimensions: 7.4m x 6.4m x 0.25mH
Vessel(s) –
Materials of Construction: Metal/Plastic
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: 11.84m3 Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents:
Softened Industrial Water
R Phrase (WGK Class): No risk phases assigned
Contents: Low Risk Condition: Poor in
areas
Action: Remedial action plus re-inspection
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: There appears to be rusting on the some of the pipework/support plates in the bund (Fig. 51.2). Floor appears discoloured from the rusting. The top of the bund wall is crumbling (Fig. 51.3) (This defect in the bund wall is not significant in containing material as it is above the bund volume level).
Bund Drainage System: Local bunding - Bottom outlet valve on bund.
General Observations: There is some debris and leaves in the bund (Fig. 51.4)
Result of Visual Inspection: Fail
Housekeeping Issues: Debris in bund should be removed. Rusting and discolouration should be monitored.
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
157
Company: Intel Ireland Ltd Photo/sketch:
See Fig 52.1 – 52.4 Site: Leixlip, Co Kildare
Bund Ref. No.: 52
Bund Location: F24 Middle Yard
Bund Description: Fuel Oil Tank Bund
Bund Dimensions: 12m x 12m x 1.3mH
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume: 75 m3 x 3 = 225m
3
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 82.5m3
Bund Retention Volume: 158.48m3 Vessel(s) –
25% of Total Storage Volume: 56.25m3
Tank Contents:
Bund containing Fuel Oil Tank, fuel oil delivery pumps, generator fuel oil pumps and boiler fuel oil pumps
R Phrase (WGK Class): R40, WGK2
Contents: High Risk Condition: Poor in
areas
Action: Remedial action plus hydrostatic testing
(where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Grade slab with tall upstand all around. Bund appears to be generally intact – no visible cracks or leaks (Fig. 52.1). Liquid retention in bunds which is reducing retention capacity. Floor appears discoloured from the rusting and moss growth.
Bund Drainage System: Local bunding - Bottom outlet valve on bund.
General Observations: There is some debris in the bund (Fig. 52.3). There is no grate on the sump. The labelling at the front of the bund has faded (Fig. 52.2).
Result of Visual Inspection: Pass
Housekeeping Issues: Debris in bund should be removed.
Action Required:
Tanks require labelling to ensure that the correct chemicals are filled into each tank during refilling and also to ensure that appropriate handling procedures are undertaken in the event of a spill.
Bunds require regular emptying to ensure required storage capacity for spills/leaks.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
Bund Ref. No.: 52
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 15/2/11
Length of test: 24hrs
Measurement at beginning of test: 120mm
Measurement at end of test: 120mm
Volume Tested to: 25m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Eamonn McIvor Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
158
Company: Intel Ireland Ltd Photo/sketch:
See Fig 48.1 – 48.4 Site: Leixlip, Co Kildare
Bund Ref. No.: 48
Bund Location: F24 West Yard
Bund Description: Sodium Hydroxide Fab
Scrubber Day Tank
Bund Dimensions: Complex dimensions
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: Unknown Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents:
Sodium Hydroxide (NaOH)
R Phrase (WGK Class):
R21,22
WGK 1, R35
Contents: Low Risk Condition: Poor in areas Action: Remedial action plus re-inspection
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Grade slab with low bund wall all around and plexiglas screen all around. Bund appears to be generally intact – no visible cracks or leaks (Fig. 48.1). The splash guard near the safety shower is broken and needs to be replaced (Fig. 48.2). There is some discolouration on the bund floor i.e. moss.
Bund Drainage System: Local bunding - Bottom outlet valve on bund. Trenches along outside of bund.
General Observations: There is some debris in the bund (Fig. 48.4). Some pipework appears to be broken.
Result of Visual Inspection: Pass
Housekeeping Issues:
Debris/piping in bund should be removed.
Action Required:
Splash guard around the bund needs to be fixed and the general house keeping in this bund needs to be improved. Determine bund retention volume.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
159
Company: Intel Ireland Ltd Photo/sketch:
See Fig 68.1 – 68.4 Site: Leixlip, Co Kildare
Bund Ref. No.: 68
Bund Location: NH4W Treatment Bund
Bund Description: Ammonia Waste (NH4W)
Treatment Bund
Bund Dimensions: Complex dimensions
Vessel(s) –
Materials of Construction: FRP
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume:
High pH Drain Lift Tank (1 in No.): 0.7m3
Low pH Drain Lift Tank (1 in No.):1.4m3
NH4W Treatment Collection Tanks: 76.8m3 x 2 = 153.6m3
Total = 155.7m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 84.5 m3
Bund Retention Volume: 422.4m3 Vessel(s) –
25% of Total Storage Volume: 38.925 m3
Tank Contents:
<10% NH3, <8% H2O2, NaOH
30-40% (NH4)2SO2
Ammonia wastewater
R Phrase (WGK Class):
R36/37/38 ,
R36/37/38
WGK 2
Contents: High Risk Condition: Poor in areas Action: Remedial action plus hydrostatic testing
(where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons: Cannot be hydrostatically tested as
the trench drains to the hi/lo pH tank sump and this equipment cannot be submerged
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Grade slab with upstand all around. Trench enters below floor level but pipes entering in the trench are cast into a dividing wall. Bund appears to be generally intact – no visible cracks or leaks (Fig. 68.1). There is also some discolouration from moss growth in the bund and some water retention for recent rainfall.
Bund Drainage System: Local Bund - For both tanks there is an auto capability options to collection tanks and AWN
General Observation: There is maintenance works in process in this bund on one of the pumps and the bund has been gritted (Fig. 68.2). There are also boxes in the bund (Fig. 68.3). There is some discolouration in the bund (Fig 68.4).
Result of Visual Inspection: Pass
Housekeeping Issues:
Debris/absorbent mat beside low pH drain lift tanks should be removed from grate. The bund needs to be cleaned.
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
160
Company: Intel Ireland Ltd Photo/sketch:
See Fig 71.1 – 71.4 Site: Leixlip, Co Kildare
Bund Ref. No.: 71
Bund Location: Scrubber Bund/Stock Room
Roof
Bund Description: F24 Bridge Scrubbers
Bund Dimensions: Complex dimensions
Vessel(s) –
Materials of Construction: Metal Scrubbers: FRP
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume: 1.3m3 x 4 = 5.2m
3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 1.4 m3
Bund Retention Volume:
11.87 m3
Vessel(s) –
25% of Total Storage Volume: 1.3m3
Tank Contents:
Sodium Hydroxide
Ammonia
R Phrase (WGK Class):
WGK 1,
R35, WGK 2
Contents: High Risk Condition: Poor in
areas
Action: Remedial action plus hydrostatic testing
(where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Significant rust in bund could lead to eventual leaks; see Figure 71.2 (Between Scrubbers #3 and #4). There is also moss growth on the base of the bund (Fig. 71.3).
Bund Drainage System: Bund is free draining.
General Observation: There is some piping under the sodium hydroxide tank that should be removed (Fig. 71.4). There is also a ladder and cabling loose on the floor of the bund.
Result of Visual Inspection: Fail
Housekeeping Issues:
Tank is very dirty and there is debris in bottom of bund.
Action Required:
Rusting should be monitored and the bund cleaned.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
161
Company: Intel Ireland Ltd Photo/sketch:
See Fig 53.1 – 53.3 Site: Leixlip, Co Kildare
Bund Ref. No.: 53
Bund Location: HPM Roof
Bund Description: F24 Gas Pad Scrubbers
Bund Dimensions: 5.1m x 8m x 0.65mH
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: 26.52m3 Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents:
Acid Scrubbers
R Phrase (WGK Class): Assumed Low risk
Contents: Assumed Low risk Condition: Poor in
areas
Action: Remedial action plus re-inspection
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Bund is a little wet with no visible cracks however bund drains into a drainage sump in floor (Fig. 53.3). Bund is in good condition although there is some discolouration near the drainage sump.
Bund Drainage System: Unknown – Intel to confirm.
Result of Visual Inspection: Pass
Housekeeping Issues:
Debris should be removed from bund (loose cables, spade and piping) (Fig. 53.2).
The bund is also very dirty.
Action Required:
Discolouration should be monitored and the bund cleaned.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
162
Company: Intel Ireland Ltd Photo/sketch:
See Fig 49.1 – 49.4 Site: Leixlip, Co Kildare
Bund Ref. No.: 49
Bund Location: West Yard Scrubber Bund
Bund Description: F24 Fab (west) Scrubbers
(4No.)
Bund Dimensions: Complex dimensions Vessel(s) –
Materials of Construction: FRP
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume: 1.3 x 4 = 5.2m3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 1.4 m3
Bund Retention Volume:
11.87m3
Vessel(s) –
25% of Total Storage Volume: 1.3m3
Tank Contents:
Acid Scrubbers
R Phrase (WGK Class): Assumed Low risk
Contents: Assumed Low risk Condition: Poor in
areas
Action: Remedial action plus re-inspection
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: No visible cracks or leaks internally. Some discolouration on bund floor (Fig. 49.4). This room contains individual tanks with self contained bunds.
Bund Drainage System: Trenches along middle of floor of bunded room.
General Observations: Drums stacked in corner, no labelling on these (Fig. 49.2).
Result of Visual Inspection: Pass
Housekeeping Issues:
Debris should be removed from bund (Fig. 49.3).
Action Required:
Ensure all containers are clearly labelled.
Monitor discolouration on bund floor.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
163
Company: Intel Ireland Ltd Photo/sketch:
See Fig 50.1 – 50.3 Site: Leixlip, Co Kildare
Bund Ref. No.: 50
Bund Location: F24 Subfab - west
Bund Description: F24 Subfab Emergency
Generator bund
Bund Dimensions: Complex dimensions
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume: 6 x generators (6 x 1m3 day tanks
fed by 3 x 75m3 tanks) = 231m
3
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 1.1m3
Bund Retention Volume: 6m3
Vessel(s) –
25% of Total Storage Volume: 1.5m3
Tank Contents:
Diesel
R Phrase (WGK Class): R40, WGK2
Contents: High Risk Condition: Poor in
areas
Action: Remedial action plus hydrostatic testing
(where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 20/1/09
Bund & Tank Integrity: Bund appears to be generally intact however the floor of the bund is in very poor condition i.e. cracks (Fig. 50.3). Leak under generator EO15 and EO16. There is also a crack on the back wall.
Bund Drainage System: Trenches along back wall behinds the generators – Local bund.
Result of Visual Inspection: Fail
Housekeeping Issues:
Debris should be removed from bund.
Action Required:
The bund floor and crack on wall should be repaired. The room should be inspected for further deterioration on a regular basis.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
164
Bund ID: F24 Generator Subfab Diesel Bund
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 15/2/11
Length of test: 24hrs
Measurement at beginning of test: 120mm
Measurement at end of test: 120mm
Volume Tested to: 1.2m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Eamon McIvor Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
165
Company: Intel Ireland Ltd Photo/sketch:
See Fig 69.1 – 69.3 Site: Leixlip, Co Kildare
Bund Ref. No.: 69
Bund Location: F24 Middle Yard
Bund Description: F24 Ammonia Scrubbers
Bund Dimensions: Complex dimensions
Vessel(s) –
Materials of Construction: Metal/Plastic
Bund Materials of Construction: Concrete Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume:
5.92m3
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents:
Ammonia
R Phrase (WGK Class): WGK 2
Contents: High Risk Condition: Poor in
areas
Action: Remedial action plus hydrostatic testing
(where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Bund appears to be generally intact – no visible cracks or leaks internally. There is also some discolouration from moss growth/rust in the bund (Figure 69.2). Liquid retention in bund (rainwater) which is reducing retention capacity. There appears to be some areas where the CRC coating needs to be recoated (Figure 69.3).
Bund Drainage System: The bund is free draining into the adjacent bund (Bund 68).
Result of Visual Inspection: Fail
Housekeeping Issues: None
Action Required:
Rusting should be monitored and the bund cleaned.
Investigate if CRC coating needs to be fixed.
Need to compare the capacity of the combined bund with the vessel volume.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
166
Bund ID: Bund Ref. No.: 69
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 02/02/2011
Length of test: 24 hrs
Measurement at beginning of test: 110mm
Measurement at end of test: 110mm
Volume Tested to: m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: PP. Padraig McLoughlin Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
167
Company: Intel Ireland Ltd Photo/sketch:
See Fig 70.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 70
Bund Location: Corrosive Room B1M01/Stock
Room
Bund Description: Corrosives
Bund Dimensions: Complex dimensions
Vessel(s) –
Materials of Construction: Various metal drums and plastic
containers
Bund Materials of Construction:
Concrete/room
Vessel(s) –
Total Storage Volume:
Bund Lining Material: CRC coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: 12.8m3
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents:
Corrosives substances including Sulphuric acid
R Phrase (WGK Class): Toxic and Corrosive
R35, WGK 2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
96% H2SO4 is a stand alone chemical with no standby, cannot do without Fab impact of ~36- 48 hrs as it feeds the ammonia scrubbers
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Bund appears in good condition – no visible cracks or leaks. Bottom of the bund and ground around are dry.
Bund Drainage System: Local bund - Raised floor made of grating and the coving higher than grating.
Result of Visual Inspection: Pass
Housekeeping Issues:
The bund floor consists of green grate mats and appears very dirty.
Action Required:
The bund should be cleaned.
Ensure all containers are clearly labelled.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
168
Company: Intel Ireland Ltd Photo/sketch:
See Fig 70.1 – 70.5 Site: Leixlip, Co Kildare
Bund Ref. No.: 70a
Bund Location: Stock Room Level 1
Bund Description: Solvents & Refrigerated
Solvents
Bund Dimensions: Complex dimensions
Vessel(s) –
Materials of Construction: Various metal drums and plastic
containers
Bund Materials of Construction:
Concrete/room
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: 5.6m3
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents:
Solvents including:
acetone
N-methyl-2-pyrrolidone
R Phrase (WGK Class):
R11, R36, R66, WGK 1
R61, R36/37/38 WGK 1
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Testing would involve impact to fab operations, to be scheduled during shutdown
Result of Hydrostatic Test:
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Bund appears in good condition – no visible cracks or leaks. Bottom of the bund and ground around are dry.
Bund Drainage System: Local bund - Raised floor made of grating and coving is at a higher level than the grating.
Result of Visual Inspection: Pass
Housekeeping Issues:
The bund floor consists of green grate mats and appears very dirty.
Action Required:
The bund should be cleaned.
Ensure all containers are clearly labelled.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
169
Company: Intel Ireland Ltd Photo/sketch:
See Fig 55.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 55
Bund Location: HPM Area (Entrance behind
caged area, F24 middle yard)
Bund Description: Aqueous Room
Bund Dimensions: Complex dimensions
Vessel(s) –
Materials of Construction: Various drums and plastic
containers
Bund Materials of Construction:
Concrete/room
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents:
Aqueous Room (53 in No.) including copper/lead
R Phrase (WGK Class): Corrosives, WGK 2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Testing would involve impact to fab operations, to be scheduled during shutdown
Result of Hydrostatic Test:
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Bund appears in good condition – no visible cracks or leaks. Bottom of the bund and ground around are dry.
Bund Drainage System: Local bund - Room with wide trench perimeter, finger trenches and coving.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
170
Company: Intel Ireland Ltd Photo/sketch:
See Fig 55.1 – 55.5 Site: Leixlip, Co Kildare
Bund Ref. No.: 55a
Bund Location: HPM Area (Entrance behind
caged area, F24 middle yard)
Bund Description: Chemical Store
Bund Dimensions: Complex dimensions
Vessel(s) –
Materials of Construction: Various drums and plastic
containers
Bund Materials of Construction:
Concrete/room
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents:
Chemical Store (19 in No.) including copper/lead
R Phrase (WGK Class): WGK 2, R36, R33 Corrosive and
Toxic
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Testing would involve impact to fab operations, to be scheduled during shutdown
Result of Hydrostatic Test:
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: The bund appears in good condition – no crack visible and ground around is dry.
Bund Drainage System: Local bund - The bund is a room with grated trenches around the storage area.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
171
Company: Intel Ireland Ltd Photo/sketch:
See Fig 57.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 57
Bund Location: HPM Area (Entrance behind
caged area, F24 middle yard)
Bund Description: Heavy Metals
Bund Dimensions: Complex dimensions
Vessel(s) –
Materials of Construction: Various drums and plastic
containers
Bund Materials of Construction:
Concrete/room
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents:
Heavy Metals (14 in No.) including lead and copper
R Phrase (WGK Class): R36, R33, Corrosive and Toxic,
WGK 2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Testing would involve impact to fab operations, to be scheduled during shutdown
Result of Hydrostatic Test:
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Bund appears in good condition – no visible cracks or leaks. Bottom of the bund and ground around are dry.
Bund Drainage System: Local bund - Room with wide trench perimeter, finger trenches and coving.
Result of visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
172
Company: Intel Ireland Ltd Photo/sketch:
See Fig 56.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 56
Bund Location: HPM Area (Entrance behind
caged area, F24 middle yard)
Bund Description: Lead Room
Bund Dimensions: Complex dimensions
Vessel(s) –
Materials of Construction: Various drums and plastic
containers
Bund Materials of Construction:
Concrete/room
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: 41m3
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents:
Lead
R Phrase (WGK Class): R36, R33 Corrosive and Toxic,
WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Lift station present, cannot test bund
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Bund appears in good condition – no visible cracks or leaks. Bottom of the bund and ground around are dry.
Bund Drainage System: Local bund - Raised floor made of grating and the coving is higher than the grating.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
173
Company: Intel Ireland Ltd Photo/sketch:
See Fig 56a.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 56a
Bund Location: HPM Area (Entrance behind
caged area, F24 middle yard)
Bund Description: Copper Room
Bund Dimensions: Complex dimensions
Vessel(s) –
Materials of Construction: Various drums and plastic
containers
Bund Materials of Construction:
Concrete/room
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: 69m3
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents:
Copper interconnect plating solution containing Sulphuric acid and copper sulphate
R Phrase (WGK Class): WGK 3, R35,
R36/38, R51/53
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Lift station present, cannot test bund
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Bund appears in good condition – no visible cracks or leaks. Bottom of the bund and ground around are dry.
Bund Drainage System: Local bund - Room where any spills drain to trenches along the entire floor.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
174
Company: Intel Ireland Ltd Photo/sketch:
See Fig 54.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 54
Bund Location: HPM Area (Entrance behind
caged area, F24 middle yard)
Bund Description: Solvents Room
Bund Dimensions: Complex dimensions
Vessel(s) –
Materials of Construction: Various drums and plastic
containers
Bund Materials of Construction:
Concrete/room
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: 65.9m3
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents: Various harmful and corrosive
substances
Isopropanol
R Phrase (WGK Class): Assumed high risk as other
chemicals in room could potentially have high risk.
R11 R36 R67 WGK 1
Contents: Assume High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
The F24 solvent room is a designated ATEX area. The room its self is classified as Zone 2 but the trenches are classified as Atex Zone 1.
The liquid leak cables located in the trenches are part of the explosion protection plan and are connected to LSS. Loss of the LSS leak detection for a period of time (>24hrs) is a risk and would not be in line with the site explosion protection plan. Working in the trench (an ATEX zone one location) while the pumpers in the room are operational would also result in an increased safety risk faced by the worker.
(Zone one: A place where a flammable atmosphere is likely to occur in normal operation occasionally)
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Room with CRC coating on floor and coving to walls. The bund appears in good condition – no visible cracks or leaks and ground around are dry.
Bund Drainage System: Local bund - Room where any spills drain to trenches along middle of floor.
Result of Visual Inspection: Pass
Housekeeping Issues: Remove absorbent material from under bund grate in trenches.
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
175
Company: Intel Ireland Ltd Photo/sketch:
See Fig 84.1 – 84.3 Site: Leixlip, Co Kildare
Bund Ref. No.: 84
Bund Location: F24-2
Bund Description: F24-2 Acid Scrubbers
Bund Dimensions: Complex dimensions
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction: Concrete
Vessel(s) –
Total Storage Volume: Unknown
Bund Lining Material: CRC coating
Vessel(s) –
110% of Volume of Largest Vessel: Unknown
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: Unknown
Tank Contents:
Acid Scrubbers
R Phrase (WGK Class): Assumed low risk
Contents: Assume Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons: N/A
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 21/1/09
Bund & Tank Integrity: Bund appears in good condition – no visible cracks or leaks (Fig. 84.1). Some water retention in the bund from recent rainfall and the sump is full waste (Fig. 84.2).
Bund Drainage: In the event of a spill bund would be pumped out. This bund is located outside so is exposed to rainfall.
General Observation: Broken piping near sump and a stack of non slip mats should be removed. The grate is also rusted (Fig. 84.3).
Result of Visual Inspection: Pass
Housekeeping Issues: Debris in base of bund. This should be removed.
Action Required:
Cleaning of bund and bund requires regular emptying to ensure required storage capacity for spills/leaks. Determine bund retention volume.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
176
Company: Intel Ireland Ltd Photo/sketch:
See Fig 100.1 – 100.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 100
Bund Location: F24 North Chemical Dock
Bund Description: : F24 North Chemical Dock
Bund Dimensions: Complex dimensions
Vessel(s) –
Materials of Construction: None
Bund Materials of Construction: concrete
Vessel(s) –
Total Storage Volume: No vessels in bund
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: No vessels in bund
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: No vessels in bund
Tank Contents:
Chemical IBC Storage:
Sodium Bisulphite 25% (1000L)
Biomate MBC781 (220L)
Biomate MBC2881E (220L)
R Phrase (WGK Class): No vessels in bund but bund is
potentially high risk
R22, R31 WGK 1
R8, R34, R43, R23/24/25, R36/38, R50/53, R52,53 (WGK3)
R38, R41, R43, R50, R23/25, R20/22 (WGK3)
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 22/1/09
Bund & Tank Integrity: Bund appears in good condition – no visible cracks or leaks (Fig. 100.1). There were no chemicals at this location during the inspection. It is used as a temporary chemical storage bund. The bund is sloped to a gully along the side of the bund; this is blocked with mud and leaves (Fig. 100.2).
Bund Drainage: Local Bund - Floor with trenches, bund sloped in towards trenches and manually pumped to AWN
Result of Visual Inspection: Pass
Housekeeping Issues: Unblock gully along the edge of the bund and wash the bund down to remove the mud.
Action Required: Determine bund retention volume.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
177
Company: Intel Ireland Ltd Photo/sketch:
See Fig 140.1 – 140.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 140
Bund Location: F24 West Scrubber dosing –
Chemical store (PCW/CPCW)
Bund Description: Nalco 2536+(Tank no.
SN907025)
Bund Dimensions: 1.2 x 0.8 x 0.4m = 0.384m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 260L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 286L
Bund Retention Volume: 384L
Vessel(s) –
25% of Total Storage Volume: 65L
Tank Contents: Sodium Nitrite
R Phrase (WGK Class): R22, R52, WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Testing would involve impact to fab operations, to be scheduled during shutdown
Result of Hydrostatic Test:
Description and Results of Visual Inspection: Date of Visual Inspection: 18/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: There is a grate inside the room where the bund is stored and outside the bund, this is
full of water and should be pumped out.
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
178
Company: Intel Ireland Ltd Photo/sketch:
See Fig 141.1 – 141.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 141
Bund Location: F24 West Scrubber dosing –
Chemical store (PCW/CPCw)
Bund Description: Nalco 2510 (Tank no.
SN183583)
Bund Dimensions: 1.2 x 0.9 x 0.55m = 0.59m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 440L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 484L
Bund Retention Volume: 594L
Vessel(s) –
25% of Total Storage Volume: 110L
Tank Contents: 2,2-Dibromo-3-
Nitrilopropionamide
R Phrase (WGK Class): R20/22, R38, R43, R41, WGK3
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Testing would involve impact to fab operations, to be scheduled during shutdown
Result of Hydrostatic Test:
Description and Results of Visual Inspection: Date of Visual Inspection: 18/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
179
Company: Intel Ireland Ltd Photo/sketch:
See Fig 140.1 – 140.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 142
Bund Location: F24 West Scrubber dosing –
Chemical store SN907004
Bund Description: Nalco 2536 plus (Tank no.
SN907004)
Bund Dimensions: 1.2 x 0.8 x 0.4m = 0.384m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 260L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 286L
Bund Retention Volume: 384L
Vessel(s) –
25% of Total Storage Volume: 65L
Tank Contents: Sodium Nitrite
R Phrase (WGK Class): R22, R52, WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Testing would involve impact to fab operations, to be scheduled during shutdown
Result of Hydrostatic Test:
Description and Results of Visual Inspection: Date of Visual Inspection: 18/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
180
Company: Intel Ireland Ltd Photo/sketch:
See Fig 113.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 113
Bund Location: NE of site - Adjacent to F24
Fire pump house
Bund Description: F24 Emergency Generator
Diesel tank
Bund Dimensions: TBD
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction: Metal
Vessel(s) –
Total Storage Volume: 5,000L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 5,500L
Bund Retention Volume: 5,500L
Vessel(s) –
25% of Total Storage Volume: 1,250L
Tank Contents:
Diesel
R Phrase (WGK Class): R40, R65, R66, R51, R53
WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: This is a self contained double skinned metal container
Bund Drainage:
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
181
Company: Intel Ireland Ltd Photo/sketch:
See Fig 114.1 – 114.2 Site: Leixlip, Co Kildare
Bund Ref. No.: 114
Bund Location: NE of site off the North Road
Bund Description: F24 Firewater Pump
House
Bund Dimensions: Large room -
7.25m x 6m x 0.1m = 4.35m3
(4350L)
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction:
Concrete
Vessel(s) –
Total Storage Volume: 280L
Bund Lining Material: CRC coating
Vessel(s) –
110% of Volume of Largest Vessel: 308L
Bund Retention Volume: 4350L
Vessel(s) –
25% of Total Storage Volume: 70L
Tank Contents: Diesel
R Phrase (WGK Class): R40, R65, R66, R51, R53
WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
182
Company: Intel Ireland Ltd Photo/sketch:
See Fig 115.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 115
Bund Location: F24 Energy Centre (Chiller
room) MTHW - SN183542
Bund Description: Nalco 8539 (Tank
no.SN183542)
Bund Dimensions: 0.9 x 1.2 x 0.55m =
0.594m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 440L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 484L
Bund Retention Volume: 594L
Vessel(s) –
25% of Total Storage Volume: 110L
Tank Contents: Sodium Nitrite & Potassium
Hydroxide
R Phrase (WGK Class): R25, R36/38, R50
WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
Bund ID: Bund Ref. No.: 115
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 1/12/10
Length of test: 24 hrs
Measurement at beginning of test: 550mm
Measurement at end of test: 550mm
Volume Tested to: 0.430 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Simon McLain Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
183
Company: Intel Ireland Ltd Photo/sketch:
See Fig 116.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 116
Bund Location: F24 Energy Centre (Chiller
room) Chilled water dosing skid - SN183518
Bund Description: Nalco 2510 (Tank no.
SN183518)
Bund Dimensions: 0.9 x 1.2 x 0.55m =
0.594m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic bund
with splash guard
Vessel(s) –
Total Storage Volume: 440L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 484L
Bund Retention Volume: 594L
Vessel(s) –
25% of Total Storage Volume: 110L
Tank Contents: 2,2-Dibromo-3-
nitrilopropionamide
R Phrase (WGK Class): R20/22, R38, R43, R41
WGK3
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
184
Bund ID: Bund Ref. No.: 115
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 1/12/10
Length of test: 24 hrs
Measurement at beginning of test: 550mm
Measurement at end of test: 550mm
Volume Tested to: 0.430 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Simon McLain Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
185
Company: Intel Ireland Ltd Photo/sketch:
See Fig 116.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 117
Bund Location: F24 Energy Centre (Chiller
room) Chilled water dosing skid
Bund Description: Nalco 8539 (Tank no.
SN183536)
Bund Dimensions: 0.9 x 1.2 x 0.55m =
0.594m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 440L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 484L
Bund Retention Volume: 594L
Vessel(s) –
25% of Total Storage Volume: 110L
Tank Contents: Sodium Nitrite & Potassium
Hydroxide
R Phrase (WGK Class): R25, R36/38, R50
WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
186
Bund ID: Bund Ref. No.: 117
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 1/12/10
Length of test: 24 hrs
Measurement at beginning of test: 550mm
Measurement at end of test: 550mm
Volume Tested to: 0.430 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Simon McLain Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
187
Company: Intel Ireland Ltd Photo/sketch:
See Fig 118.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 118
Bund Location: F24 Energy Centre (Chiller
room) Heat recovery System
Bund Description: Nalco 2510 (Tank no.
SN9075487)
Bund Dimensions: 0.9 x 1.2 x 0.55m =
0.594m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic bund
with splash guard
Vessel(s) –
Total Storage Volume: 440L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 484L
Bund Retention Volume: 594L
Vessel(s) –
25% of Total Storage Volume: 110L
Tank Contents: 2,2-Dibromo-3-
nitrilopropionamide
R Phrase (WGK Class): R20/22, R43, R41
WGK3
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
188
Bund ID: Bund Ref. No.: 118
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 1/12/10
Length of test: 24 hrs
Measurement at beginning of test: 550mm
Measurement at end of test: 550mm
Volume Tested to: 0.430 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Simon McLain Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
189
Company: Intel Ireland Ltd Photo/sketch:
See Fig 118.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 119
Bund Location: F24 Energy Centre (Chiller
room) Heat recovery System
Bund Description: Nalco 8539 (Tank no.
SN907503)
Bund Dimensions: 0.9 x 1.2 x 0.55m =
0.594m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 440L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 484L
Bund Retention Volume: 594L Vessel(s) –
25% of Total Storage Volume: 110L
Tank Contents: Sodium Nitrite & Potassium
Hydroxide
R Phrase (WGK Class): R25, R36/38, R50
WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
190
Bund ID: Bund Ref. No.: 119
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 1/12/10
Length of test: 24 hrs
Measurement at beginning of test: 550mm
Measurement at end of test: 550mm
Volume Tested to: 0.430 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Simon McLain Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
191
Company: Intel Ireland Ltd Photo/sketch:
See Fig 120.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 120
Bund Location: F24 Energy Centre (Chiller
room) Cooling Tower Dosing
Bund Description: Nalco 93033 (Tank no.
SN90381)
Bund Dimensions: N/A
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic with
splash guard
Vessel(s) –
Total Storage Volume: 750L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 825L
Bund Retention Volume: 825L
Vessel(s) –
25% of Total Storage Volume: 187.5L
Tank Contents: Sodium Hypochlorite
R Phrase (WGK Class): R34, R31
WGK 2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Testing would involve impact to fab operations, to be scheduled during shutdown
Result of Hydrostatic Test:
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
192
Company: Intel Ireland Ltd Photo/sketch:
See Fig 120.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 121
Bund Location: F24 Energy Centre (Chiller
room) Cooling Tower Dosing
Bund Description: Nalco 3DT249 (Tank no.
SN183663)
Bund Dimensions: 0.9 x 1.2 x 0.55m =
0.594m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 440L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 484L
Bund Retention Volume: 594L
Vessel(s) –
25% of Total Storage Volume: 110L
Tank Contents: Methanol & Sodium
Formaldehyde Bisulfite
R Phrase (WGK Class): WGK 2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Testing would involve impact to fab operations, to be scheduled during shutdown
Result of Hydrostatic Test:
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
193
Company: Intel Ireland Ltd Photo/sketch:
See Fig 120.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 122
Bund Location: F24 Energy Centre (Boiler
room) Cooling Tower Dosing
Bund Description: Sulphuric Acid
Bund Dimensions: Metal with splash guard
Vessel(s) –
Materials of Construction: Metal
Bund Materials of Construction: Metal
Vessel(s) –
Total Storage Volume: 1500L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 1650L
Bund Retention Volume: 1650L
Vessel(s) –
25% of Total Storage Volume: 375L
Tank Contents: Sulphuric Acid
R Phrase (WGK Class): R35, WGK 2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test:
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
194
Company: Intel Ireland Ltd Photo/sketch:
See Fig 123.1 – 123.3 Site: Leixlip, Co Kildare
Bund Ref. No.: 123
Bund Location: F24 Subfab – PVAC Dosing
Skid
Bund Description: Nalco 8539 (Tank no.
SN183590)
Bund Dimensions: 0.9 x 1.2 x 0.55m =
0.594m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 440L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 484L
Bund Retention Volume: 594L
Vessel(s) –
25% of Total Storage Volume: 110L
Tank Contents: Sodium Nitrite & Potassium
Hydroxide
R Phrase (WGK Class): R25, R36/38, R50
WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Testing would involve impact to fab operations, to be scheduled during shutdown
Result of Hydrostatic Test:
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
195
Company: Intel Ireland Ltd Photo/sketch:
Site: Leixlip, Co Kildare
Bund Ref. No.: 124
Bund Location: F24 Subfab – PVAC Dosing
Skid
Bund Description: Nalco 2510 (Tank no.
SN183664)
Bund Dimensions: 0.9 x 1.2 x 0.55m = 0.594m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic bund
with splash guard
Vessel(s) –
Total Storage Volume: 440L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 484L
Bund Retention Volume: 594L
Vessel(s) –
25% of Total Storage Volume: 110L
Tank Contents: 2,2-Dibromo-3-nitrilopropionamide
R Phrase (WGK Class): R20/22, R43, R41
WGK3
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Testing would involve impact to fab operations, to be scheduled during shutdown
Result of Hydrostatic Test:
Description and Results of Visual Inspection: Date of Visual Inspection: 11/5/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
196
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
Company: Intel Ireland Ltd Photo/sketch:
Figure 151.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 151
Bund Location: F24 UPW
Bund Description: Nalco ST40 (Tank no.
SN70811)
Bund Dimensions: 0.6 x 1.2 x 1.65m = 1.188 m3
Vessel(s) –
Materials of Construction: Metal Tanks
Bund Materials of Construction: Metal bund with
splash guard
Vessel(s) –
Total Storage Volume: 800L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 880L
Bund Retention Volume: 1188L
Vessel(s) –
25% of Total Storage Volume: 200L
Tank Contents: Sodium Hydroxide, Alkaline Liquid
Bromide, Antimicrobial
R Phrase (WGK Class): R34, R31, WGK2
Contents: High Risk Condition: Good Action: Hydrostatic testing (where possible)
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? Yes / No
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: See below
Description and Results of Visual Inspection: Date of Visual Inspection: 12/8/2009
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required:
Signed: Ann Marie Keane
Title: Environmental Consultant Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
197
Bund ID: F24 ST 40 Ref. 151
Result of Hydrostatic Test: Pass
Date of hydrostatic Test: 04/11/10
Length of test: hrs 9
Measurement at beginning of test: 114 mm
Measurement at end of test: 114 mm
Volume Tested to: 0.22 m3
Signed: Renaith Lyons Title: Environmental Engineer
Signed: Thomas Brennan Title: Engineering Owner
DATA SHEET: BUNDING STRUCTURES
198
Company: Intel Ireland Ltd Photo/sketch:
Figure 152.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 152
Bund Location: F24 UPW
Bund Description: Nalco 2584 (Tank no.
CT003384)
Bund Dimensions: 1 x 1.2 x 0.4m = 0.48m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 300L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 330L
Bund Retention Volume: 480L
Vessel(s) –
25% of Total Storage Volume: 75L
Tank Contents: Sodium Hydroxide, Potassium
Hydroxide
R Phrase (WGK Class): R35
WGK1
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 12/8/2009
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: None
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
199
Company: Intel Ireland Ltd Photo/sketch:
Figure 153.1 Site: Leixlip, Co Kildare
Bund Ref. No.: 153
Bund Location: F24 UPW
Bund Description: Permaclean PC-33 (Tank no.
CT003384)
Bund Dimensions: 1 x 1.2 x 0.4m = 0.48m3
Vessel(s) –
Materials of Construction: Plastic
Bund Materials of Construction: Plastic
Vessel(s) –
Total Storage Volume: 300L
Bund Lining Material: None
Vessel(s) –
110% of Volume of Largest Vessel: 330L
Bund Retention Volume: 480L
Vessel(s) –
25% of Total Storage Volume: 75L
Tank Contents: Tetrasodium EDTA, Sodium
Hydroxide
R Phrase (WGK Class): R36/38, WGK1
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 12/8/2009
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: If leak occurs the bund is manually pumped out and cleaned
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: None
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
200
Company: Intel Ireland Ltd Photo/sketch:
N/A Site: Leixlip, Co Kildare
Bund Ref. No.: 162
Bund Location: F24 PCD Storage Room 2
Bund Description: F24 PCD - Planar Chemical
Distribution
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Plastic totes & drums
Bund Materials of Construction: N/A
Vessel(s) –
Total Storage Volume: 10,000L
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 1387L
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: 2500L
Tank Contents:
C8800 Slurry
Silica
CMP Cleaner, PSC (Semi Conductor Processing)
Hydrogen Peroxide
MSC Ultralift
CMP Slurry PL7107
Silica gel
R Phrase (WGK Class):
WGK1, Low Risk
R5, R8, R35 , WGK1
WGK1
WGK1
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 16/9/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: Bund drainage unknown, room appears to slope into the middle of the room and open drain located at lowest points.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: Determine bund retention volume.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
201
Company: Intel Ireland Ltd Photo/sketch:
N/A Site: Leixlip, Co Kildare
Bund Ref. No.: 163
Bund Location: F24 PCD Storage Room 1
(B1JO1A)
Bund Description: F24 PCD - Planar Chemical
Distribution
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Plastic totes & drums
Bund Materials of Construction: N/A
Vessel(s) –
Total Storage Volume: 17,500L
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 1387L
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: 4375L
Tank Contents:
Cu20K – 64
Silca
Potassium Hydroxide
PL4217 Oxide Slurry
Silica, Amorphous
Potassium hydroxide
ASD (Tizox CMP Slurry)
Cerium Oxide
L-Proline
Semi Sperse W200B
CMP Slurry PL7107
Silica gel
PSC – Hydrogen Peroxide
3900RS – Silca Polish
Dynasylon HB-330
R Phrase (WGK Class):
WGK1
WGK 1, R22, R35
Not classed under the EU legislation but assume low risk as silca is relatively inert
WGK 1, R22, R35
WGK1
R43
Not classed under the EU legislation but assume low risk as silca is relatively inert
WGK1
WGK 1, R5, R8, R20/22, R35
WGK1
WGK1, R36/38 – not a hazardous substance according to EC-directives 67/548/EEC or 1999/45/EC
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 16/9/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: This bund has trenches running throughout the room, if a spill occurs it drains into these trenches, and then drains to the AWN.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: Determine bund retention volume.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
202
Company: Intel Ireland Ltd Photo/sketch:
N/A Site: Leixlip, Co Kildare
Bund Ref. No.: 164
Bund Location: F24-1 Pump Room (PCD
Room)
Bund Description: F24-1 PCD - Planar
Chemical Distribution
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Plastic totes & drums
Bund Materials of Construction: N/A
Vessel(s) –
Total Storage Volume: 15,075L
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 1387L
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: 3768.75L
Tank Contents:
Copper Ready (CU3264)
Tizox CMP
Cerium Oxide
Proline, L-
Glanzox 3900
Ammonia
PL4217 Oxide Slurry
Silica, Amorphous
Potassium hydroxide
Cu20K – 64
Silca
Potassium Hydroxide
Dynasylon HB-330
R Phrase (WGK Class):
Not classed under the EU legislation
WGK1
R43
R20, R36/37/38 WGK1
Not classed under the EU legislation but assume low risk as silca is relatively inert
WGK 1, R22, R35
WGK1
WGK 1, R22, R35
WGK1, R36/38 – not a hazardous substance according to EC-directives 67/548/EEC or 1999/45/EC
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 16/9/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: This bund has trenches running throughout the room, if a spill occurs it drains into these trenches, and then drains to the AWN. The room is also sloped.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: Determine bund retention volume.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
DATA SHEET: BUNDING STRUCTURES
203
Company: Intel Ireland Ltd Photo/sketch:
N/A Site: Leixlip, Co Kildare
Bund Ref. No.: 165
Bund Location: F24-2 (E1TO3)
Bund Description: F24 PCD Pump Room
Bund Dimensions: Complex Dimensions
Vessel(s) –
Materials of Construction: Plastic totes & drums
Bund Materials of Construction: N/A
Vessel(s) –
Total Storage Volume: 250L
Bund Lining Material: CRC Coating
Vessel(s) –
110% of Volume of Largest Vessel: 27.5L
Bund Retention Volume: Unknown
Vessel(s) –
25% of Total Storage Volume: 62.5L
Tank Contents:
MSC Ultralift
PL7107 Slurry
Silica gel
Cu20K – 64
Silca
Potassium Hydroxide
Copper Ready (CU3264)
R Phrase (WGK Class):
WGK1
WGK1
WGK1
WGK 1, R22, R35
Not classed under the EU legislation
Contents: Low Risk Condition: Good Action: None
Deemed necessary to conduct hydrostatic test based on Risk Assessment? Yes / No
Deemed practicable/safe to conduct hydrostatic test? N/A
If hydrostatic testing is deemed impracticable or unsafe, state reasons:
Result of Hydrostatic Test: N/A
Description and Results of Visual Inspection: Date of Visual Inspection: 16/9/09
Bund & Tank Integrity: Bund appears in good condition.
Bund Drainage: This bund has trenches running throughout the room, if a spill occurs it drains into these trenches.
Result of Visual Inspection: Pass
Housekeeping Issues: None
Action Required: Determine bund retention volume.
Signed: Ann Marie Keane Title: Environmental Consultant Date: 21/9/2009
Signed: Niall O’Loughlin Title: Chartered Engineer Date: 21/9/2009
Appendix F
Underground Pipe Integrity Test Report
(Fab 24 Process Effluent Lines)
1
112 Elm Road, Western Industrial Estate, Naas Road, Dublin 12
ph. 01 409 7070, fax 01 456 9293
FAB 24 Process Effluent Lines Remedial Works
and Re-Survey
prepared on behalf of
Intel Ireland Limited
October 2010
2
PROCESS EFFLUENT DRAIN INTEGRITY TESTING
PROGRAMME
TABLE OF CONTENTS
Page No.
1.0 INTRODUCTION……………………….……………………………….. 2
1.1 SCOPE…………...……………………….……………………………….. 2
1.2 METHODOLOGY……………………….……………………………….. 2
1.3 RESULTS AND DISCUSSION………….……………………………….. 3
2.0 CONCLUSION………………………….……………………………….. 3
3.0 RECOMMENDATIONS……………….……………………………….. 3
4.0 RECORDS……. ………………………………………………………….. 3
3
EXECUTIVE SUMMARY
In September 2010, Super Drain Limited undertook a routine survey of the Process Effluent Line
from the FAB 24 AWN downstream to the EBT. This work was required in order to fulfil EPA
obligations in relation to maintenance of the environmental infrastructure on site.
The survey highlighted the accumulation of scale in the line, causing obstructions in a number of
areas. The survey was more comprehensive than on previous occasions as all inflow was
switched off- allowing a survey from upstream to downstream tank.
4
PROCESS EFFLUENT DRAIN INTEGRITY TESTING PROGRAMME
1.0 INTRODUCTION
In September 2010, Super Drain Limited was commissioned to survey the F24 process effluent
line. This document reports on the re-survey and associated works
1.1 SCOPE
This report covers the integrity testing and associated works during the re-survey of the process
effluent line from the F24 AWN to the EBT (Appendix 1).
1.2 METHODOLOGY
1.2.1 CCTV Surveying and Cleaning
The method employed the insertion of a wheeled IBAK mainline camera unit, remotely operated
from a dedicated Underground Survey Camera Vehicle. The camera operator entered the
relevant location codes on the CCTV screen and recorded all footage onto Digital Video Disk
(DVD). This disk is subsequently played through the “Wincan 7” registered drain management
package and this generated a report detailing still-frames and exact observations at precise
distances.
There were a number of areas identified that had considerable deposits of scale. These were
Jetted out and removed by means of high pressure jetting. The drain line was re-surveyed to
confirm all corrective actions had been completed satisfactorily.
1.3 RESULTS AND DISCUSSION
F24 Process Effluent Line
5
Initial Survey:
Upstream tank to MHPE (Manhole-Process Effluent) 30.
Medium encrustation, 10% cross sectional area loss, water level holding 10%
MHPE 30 downstream to MHPE 29
Obstruction at 11.2 meters, leading to 25% cross sectional area loss, increasing to 40% cross
sectional loss when examined from other side of obstruction
MHPE 29 downstream to MHPE 28
Medium encrustation, 10% cross sectional area loss, water level holding 10%.
MHPE 28 downstream to MHPE 27
Medium encrustation, 10% cross sectional area loss, water level holding 10%, increasing to 20%
cross sectional loss when examined from other side of obstruction.
MHPE 28 downstream to MHPE 27
Medium encrustation, 10% cross sectional area loss, water level holding 10%, increasing to 20%
cross sectional loss when examined from other side of obstruction.
MHPE 27 downstream to MHPE 27a
No encrustation
MHPE 27a downstream to MHPE 26
No encrustation
Resurvey
Upstream tank to MHPE (Manhole-Process Effluent) 30.
No encrustation
MHPE 30 downstream to MHPE 29
No encrustation
6
MHPE 29 downstream to MHPE 28
No encrustation
MHPE 28 downstream to MHPE 27
No encrustation
MHPE 27 downstream to MHPE 27a
No encrustation
MHPE 27a downstream to MHPE 26
No encrustation
2.0 CONCLUSION
This line is free flowing and structurally sound
3.0 RECOMMENDATIONS
There are no further corrective actions outstanding.
4.0 RECORDS
The detailed reports and DVD‟s have been submitted to the EHS department for review.
____________________
Stephen Carter
Super Drain Limited
7
Appendix G
Underground Tank Integrity Test Report
(Fab 10 Underground Contained Storm System Tank)
AD Analytical,
8 Terenure Rd. North,
Terenure,
Dublin 6w.
Phone (353-1-
CONFIDENTIAL REPORT
Client: Intel Ireland,
Leixlip,
Co. Kildare.
Attention: Ms. Renaith Lyons
Commencement Date: 30/09/2010 Report Date: 01/10/2010
TITLE: Tank Integrity Assessment Based on
BRITISH STANDARD B.S. 8007 : 1987
Signed: _______________________
Dr. Alyn Deane
Tank/Sump Integrity Assessment INTEL IRELAND 2010
CONTENTS
1.0 Executive Summary
2.0 Scope
3.0 Survey Methodology
3.1 Monitoring Requirements
3.2 Assessment Techniques
3.3 Reporting
4.0 Discussion
Appendix 1. FAB 10
o Upper Surface Water Tank
Tank/Sump Integrity Assessment INTEL IRELAND 2010
1.0 Executive Summary
AD Analytical was commissioned by Intel Ireland to carry out Tank/Sump testing at their
facility in Leixlip, Co. Kildare. The survey was performed on 30th
September 2010. The
areas included in this study were referenced as follows:
1. Upper FAB 10 Surface Water (SW) Tank
day (where process allowed) in accordance with B.S. 8007:1987 section 9 and The above
Tanks/Sumps were tested for liquid tightness for a full working were found to be in
compliance with the test.
Signed:__________________________
Dr. Alyn Deane
Tank/Sump Integrity Assessment INTEL IRELAND 2010
2
.0 Scope
AD Analytical were contracted by Intel Ireland to carry out Tank/Sump Integrity testing
at their facility in Leixlip, Co. Kildare. The scope of the survey is limited to the
following:
a. Identification and inspection of the Tanks/Sumps.
b. Test the Tanks/Sumps for „liquid tightness‟ as specified in section nine of B.S. 8007:
1987.
c. Reporting and interpretation of the assessment results.
3.0 Survey Methodology
3.1 Monitoring requirements
As part of the ongoing assessment of the Tanks/Sumps on site a test was performed to
determine the integrity of the Tanks/Sumps listed below:
Tank I.D.
1. Upper FAB 10 Surface Water (SW) Tank
3.2 Assessment Techniques
AD Analytical staff visually inspected the Tanks/Sumps in September 2010.
The Tanks/Sumps were filled with clean water to the fill level, marked and monitored for
a full working day where process operations allowed.
After stabilisation, the level of the liquid surface was recorded by means of a
measurement & photograph at regular intervals for the test period.
The dimensions of this tank are:
Length = 5.75m
Breadth = 5.5m
Width = 2.8m
Fill volume = 40.13m3
3.3 Reporting
Tank/Sump Integrity Assessment INTEL IRELAND 2010
A Log for the Tanks/Sumps is reported as follows:
Appendix 1. FAB 10
o Upper FAB 10 Surface Water (SW) Tank.
4.0 Discussion
The criteria used for testing of Tanks, tanks and sumps are as follows:
1. A Tank containing one vessel should have a nominal capacity of 110 % of
the vessel‟s maximum capacity.
2. A Tank containing more than one vessel should have a nominal capacity
of 110% of the largest vessel or 25% of the total capacity of all the
vessels, which ever is the greater.
3. Sumps, built with double skins (i.e. an inner and outer layer) should have
no water in between the two layers.
The Tanks/Sumps, as detailed in previous sections, were allowed stabilise and tested.
During the test period the total permissible dip in level (allowing for evaporation) should
not exceed 1/500th of the average water depth of the full Tank in all cases.
The above indicates, therefore, that the Tanks/Sumps detailed in this report were found
to satisfy a „Test‟ for „Liquid Tightness‟, as described in section nine, B.S. 8007: 1987:
Design of Concrete Structures for the retaining Aqueous Liquids.
Tank/Sump Integrity Assessment INTEL IRELAND 2010
APPENDIX 1
Tank/Sump Integrity Assessment INTEL IRELAND 2010
TANK TESTING
CLIENT : Intel Ireland.
TANK LOCATION: Upper FAB 10 Surface Water (SW) Tank
SURVEY DATE : 30/09/2010
PERSONNEL : Dr. Alyn Deane (AD Analytical)
Renaith Lyons (Intel Ireland)
Monitoring Log:
WATER
LEVEL
EVAPORATION Time PERSONNEL
Fill *1531mm 0mm 15.30** AD/RL
Test 1531mm 0mm 08:30 AD/RL
Test 1531mm 0mm 15.30 AD/RL *measured from the top, total fill depth 1269mm.
**Filled on 29/09/2010
COMMENTS
The Upper FAB 10 Surface Water (SW) Tank was tested in accordance to B.S.
8007 : 1987 (Design of concrete structures for the retaining aqueous liquids:
Section Nine - inspection and testing of the structure).
Conformance to B.S. 8007: 1987 Section 9
Compliant (to 40.13m3)
Tank/Sump Integrity Assessment INTEL IRELAND 2010
Location - The Upper FAB 10 Surface Water (SW) Tank
Photo I.D. – Water Level 8.30
Photo I.D. – Water Level 15.30
Appendix H
Noise Monitoring Report
_____________________________________
Technical Report Prepared For
Intel Ireland Ltd Collinstown Industrial Estate
Leixlip Co. Kildare
_____________________________________ Technical Report Prepared By
James Mangan AMIOA
_____________________________________
Our Reference
JM/10/5043NR01
____________________________________
Date Of Issue
16 June 2010
_____________________________________
INTEL IRELAND IPPC LICENCE
NOISE SURVEY 2010
JM/10/5043NR01 AWN Consulting Limited
___________________________________________________________________________________________________
_____________________________________________________________________________________________________
Page 2
EXECUTIVE SUMMARY AWN Consulting has been commissioned to measure environmental noise levels in order to establish the noise climate in the vicinity of the Intel Ireland site in accordance with the appropriate Integrated Pollution Prevention and Control (IPPC) Licence. This document reviews the survey data and presents it in a form suitable for submittal to the Environmental Protection Agency (EPA) as part of Intel‟s Annual Environmental Report (AER). Environmental noise surveys have been carried out at a number of locations around the boundary of the site and at noise sensitive locations in the vicinity of the site. Noise levels were measured during daytime and night-time periods. The survey data has been analysed and it may be concluded that this facility is in compliance with Condition 5 of its IPPC Licence. Report Prepared By: Report Checked By:
JAMES MANGAN DAMIAN KELLY Acoustic Consultant Principal Acoustic Consultant
JM/10/5043NR01 AWN Consulting Limited
___________________________________________________________________________________________________
_____________________________________________________________________________________________________
Page 3
CONTENTS Page
Executive Summary 2
1.0 Introduction 4
2.0 Survey Details and Measured Noise Levels 5
2.1 Measurement Locations 5
2.2 Survey Periods 5
2.3 Personnel and Instrumentation 6
2.4 Procedure 6
2.5 Measurement Parameters 6
2.6 Survey Results and Comments 7
3.0 Discussions 11
4.0 Conclusions 12
Figure 1 – Noise Measurement Locations 13
Appendix A – Noise Measurement Results 1/3 Octave Band 14
JM/10/5043NR01 AWN Consulting Limited
___________________________________________________________________________________________________
_____________________________________________________________________________________________________
Page 4
1.0 INTRODUCTION
It is a requirement of the Integrated Pollution Prevention and Control (IPPC) Licence, issued by the Environmental Protection Agency (EPA) and held by Intel Ireland that environmental noise levels in the vicinity of the site are monitored on an annual basis. Condition 5 of the Licence sets out the following requirements in relation to noise:
Condition 5: 5.1 No specified emission from the installation shall exceed the emission
limit values set out in Schedule B: Emission Limits of this licence. There shall be no other emissions of environmental significance.
Schedule B4 pertains to noise and specifies the following limits: B.4. Noise Emissions
Daytime dB(A) LAeq (15 minutes) Night-time dB(A) LAeq (15 minutes)
55Note 1
45Note 1
Note 1: There shall be no clearly audible tonal or impulsive component in the noise emission from the site at any noise sensitive location
Paragraph 4.5 of the Interpretation section of the licence also applies to noise:
4.5 Noise from the installation shall not give rise to sound pressure levels (Leq,T) measured at any noise-sensitive location that exceed the specified limit values by more than 2dB(A).
Daytime is taken as 08:00 to 22:00hrs and night-time 22:00 to 08:00hrs as stated in the EPA publication Guidance Note For Noise In Relation To Scheduled Activities, Second Edition (2006). AWN Consulting has been commissioned to conduct a noise survey in accordance with the EPA‟s requirements in order to establish whether the facility is operating in compliance with the criteria outlined above.
JM/10/5043NR01 AWN Consulting Limited
___________________________________________________________________________________________________
_____________________________________________________________________________________________________
Page 5
2.0 SURVEY DETAILS AND MEASURED NOISE LEVELS A series of environmental noise surveys were conducted in order to quantify the existing noise environment. The surveys were conducted generally in accordance with ISO 1996: 2007: Acoustics – Description, measurement and assessment of environmental noise. Specific details are set out below.
2.1 Measurement Locations Noise measurements were also conducted at seven positions on the site boundary and at noise-sensitive locations. These positions are the monitoring locations stipulated in the current IPPC Licence for the site. These locations are described below and shown on Figure 1. NM01 Near the mechanical „Middle Gate‟ on the eastern boundary of the site
in line with the north façade of IR3. NM02 On the Confey Road to the north of the site, at the entrance to the Intel
soccer grounds. NM03 At Riverview House. Please note that the noise monitoring position for
the 2009 and 2010 surveys have changed slightly when compared to the location adopted for previous years. For the purposes of the annual IPPC assessment the attended noise monitoring position was moved away from the continuous noise monitor location (which is located in a field approximately 40 metres to the east of the house) and positioned adjacent to the façade of the Riverview property itself. This was done as it was noted by survey personnel that water flow noise from the river, as well as wind generated noise on nearby foliage and road traffic from the M4 motorway, were audible to a greater extent at the continuous monitor location than at the location of the house itself. This gives a more realistic indication as to Intel plant noise emissions at the façade of the house, as opposed to at the location of the continuous noise monitor.
NM04 On the Confey Road to the north of the site, adjacent to the B&B. NM05 At the north-eastern corner of the car-park to the east of Fab24. NM06 At the south-eastern corner of the car-park to the east of Fab24. NM07 At noise-sensitive locations beyond the southern boundary of the site.
2.2 Survey Periods Measurements were conducted over the course of the following survey periods:
Night-time NM01 to NM04: 23:03hrs on 26 May to 02:49hrs 27 May 2010;
Night-time NM05 to NM07: 22:04hrs on 26 May to 01:29hrs 27 May 2010;
Daytime NM01 to NM07: 09:42hrs to 17:13hrs on 26 May 2010.
JM/10/5043NR01 AWN Consulting Limited
___________________________________________________________________________________________________
_____________________________________________________________________________________________________
Page 6
During all of the survey periods noted above, it is understood that the facility was in normal operation. The weather during daytime survey periods was dry and calm, temperatures were in the range 14 to 18 degrees Celsius, wind speeds were in the range 1 to 4 m/s. The weather during night-time survey periods was dry and calm, temperatures were in the range 5 to 8 degrees Celsius, wind speeds were in the range 1 to 2 m/s.
2.3 Personnel and Instrumentation James Mangan and Louis Smith (AWN) conducted the noise level measurements during all survey periods. The measurements were performed using Brüel & Kjær Type 2260 Modular Precision Sound Analysers. Before and after the survey the measurement apparatus was check calibrated using a Brüel & Kjær Type 4231 Sound Level Calibrator.
2.4 Procedure During each of the day-time and night-time periods, measurements were conducted on a cyclical basis. Sample periods were 15 minutes during both the daytime and night-time surveys. The results were saved to the instrument memory for later analysis where appropriate. Survey personnel noted all primary noise sources contributing to noise build-up.
2.5 Measurement Parameters The boundary survey results are presented in terms of the following five parameters:
LAeq is the equivalent continuous sound level. It is a type of average and is used
to describe a fluctuating noise in terms of a single noise level over the sample period.
LAmax is the instantaneous maximum sound level measured during the sample
period. LAmin is the instantaneous minimum sound level measured during the sample
period.
LA10 is the sound level that is exceeded for 10% of the sample period. It is typically used as a descriptor for traffic noise.
LA90 is the sound level that is exceeded for 90% of the sample period. It is
typically used as a descriptor for background noise.
The “A” suffix denotes the fact that the sound levels have been “A-weighted” in order to account for the non-linear nature of human hearing. All sound levels in this report are expressed in terms of decibels (dB) relative to 2x10-5 Pa.
JM/10/5043NR01 AWN Consulting Limited
___________________________________________________________________________________________________
_____________________________________________________________________________________________________
Page 7
2.6 Survey Results
2.6.1 Location NM01
Table 1 below presents the noise level measurements at Location NM01.
Time (hrs)
Measured Noise Level, dB re 210-5
Pa
LAeq LAmax LAmin LA10 LA90
09:42 – 09:57 52 66 37 55 42
11:07 – 11:22 50 67 36 54 39
12:27 – 12:42 54 71 34 56 38
23:03 – 23:18 40 56 29 42 31
00:18 – 00:33 37 56 30 39 31
01:38 – 01:53 38 58 30 40 31
Table 1 Noise Level Measurements at Location NM01
During the daytime survey periods, distant road traffic movement on the R148 and Kellystown Lane along with occasional aircraft movements were noted as the primary contributors to the noise build-up. Occasional vehicle movements within the site were also audible as was distant plant noise from the Intel site and wind noise on nearby foliage. Noise levels were in the range 50 to 54dB LAeq and 38 to 42dB LA90. During the night-time survey periods, audible noise sources included distant traffic on surrounding roads and distant plant noise from the Intel site. Noise levels were in the range 37 to 40dB LAeq and of the order of 31dB LA90. During all measurement periods local road traffic movements along Kellystown Lane were paused out as far as possible in order to prevent this source from dominating the measured noise levels.
2.6.2 Location NM02
Table 2 below presents the noise level measurements at Location NM02.
Time (hrs)
Measured Noise Level, dB re 210-5
Pa
LAeq LAmax LAmin LA10 LA90
09:59 – 10:14 48 61 30 53 35
11:26 – 11:41 46 64 30 50 33
12:45 – 13:00 47 69 31 51 35
23:21 – 23:36 37 53 27 39 30
00:40 – 01:55 34 55 28 34 29
01:58 – 02:13 37 50 31 39 33
Table 2 Noise Level Measurements at Location NM02
During the daytime survey periods, distant road traffic movements were noted as the primary contributors to the noise build-up. Birdsong and wind noise on nearby foliage were also noted. Plant noise from the Intel site was inaudible during daytime periods at this location. Noise levels were in the range 46 to 48dB LAeq and 33 to 35dB LA90.
JM/10/5043NR01 AWN Consulting Limited
___________________________________________________________________________________________________
_____________________________________________________________________________________________________
Page 8
During the night-time survey periods, audible noise sources included distant traffic on surrounding roads and very distant plant noise from the Intel site. Noise levels were in the range 34 to 37dB LAeq and 29 to 33dB LA90. During all measurements local road traffic movements were paused out as far as possible in order to prevent this source from dominating the measured noise levels.
2.6.3 Location NM03
Table 3 below presents the noise level measurements at Location NM03.
Time (hrs)
Measured Noise Level, dB re 210-5
Pa
LAeq LAmax LAmin LA10 LA90
10:19 – 10:34 44 59 33 47 36
11:45 – 12:00 48 66 33 49 38
13:03 – 13:18 46 63 34 49 37
23:58 – 00:13 36 61 30 36 32
01:18 – 01:33 36 48 32 36 34
02:34 – 02:49 40 47 36 41 38
Table 3 Noise Level Measurements at Location NM03
During daytime periods at this location, steady plant noise from the Intel site along with birdsong and distant traffic were the dominant noise sources. Noise levels were in the range 44 to 48dB LAeq and 36 to 38dB LA90. During night-time periods, steady plant noise was again the dominant source of noise. Occasional distant traffic movements were also audible. Noise levels were in the range 36 to 40dB LAeq and 32 to 38dB LA90.
2.6.4 Location NM04
Table 4 below presents the noise level measurements at Location NM04.
Time (hrs)
Measured Noise Level, dB re 210-5
Pa
LAeq LAmax LAmin LA10 LA90
10:45 – 11:00 45 64 31 48 35
12:04 – 12:19 48 66 31 53 36
13:23 – 13:38 46 63 32 50 36
23:39 – 23:54 38 56 29 40 31
00:58 – 01:13 35 61 27 38 28
02:16 – 02:31 39 73 33 38 35
Table 4 Noise Level Measurements at Location NM04
During the daytime survey periods, distant road traffic movements were noted as the primary contributor to the noise build-up. Plant noise from the Intel site was not audible at this location. Birdsong and wind noise on nearby foliage were also noted. Noise levels were in the range 45 to 48dB LAeq and 35 to 36dB LA90.
JM/10/5043NR01 AWN Consulting Limited
___________________________________________________________________________________________________
_____________________________________________________________________________________________________
Page 9
During night-time periods, occasional distant road traffic movements and plant noise from the Intel site were audible. Noise levels were in the range 35 to 39dB LAeq and 28 to 35dB LA90. During all measurements local road traffic movements were paused out as far as possible in order to prevent this source from dominating the measured noise levels.
2.6.5 Location NM05
Table 5 below presents the noise level measurements at Location NM05.
Time (hrs)
Measured Noise Level, dB re 210-5
Pa
LAeq LAmax LAmin LA10 LA90
14:22 – 14:37 42 65 34 44 36
15:28 – 15:43 46 66 32 47 36
16:35 – 16:50 43 66 35 45 38
22:43 – 23:58 39 61 35 41 37
23:52 – 00:07 41 63 36 41 37
00:57 – 01:12 38 62 35 39 36
Table 5 Noise Level Measurements at Location NM05
During the daytime survey periods, distant road traffic movements were noted as the primary contributor to the noise build-up. Plant noise from the Intel site was audible at low level. Birdsong, occasional distant train movements, aircraft movements and wind noise on nearby foliage were also noted. Noise levels were in the range 42 to 46dB LAeq and 36 to 38dB LA90. During the night-time survey periods, broadband plant noise was audible from the rear of the site. Other sources included occasional traffic on the R148 and distant traffic from the direction of the N4. Noise levels were in the range 38 to 41dB LAeq and 36 to 37dB LA90.
2.6.6 Location NM06
Table 6 below presents the noise level measurements at Location NM06.
Time (hrs)
Measured Noise Level, dB re 210-5
Pa
LAeq LAmax LAmin LA10 LA90
14:06 – 14:21 45 64 36 47 40
15:12 – 15:27 44 64 33 46 37
16:17 – 16:32 45 62 36 47 40
23:01 – 23:16 46 59 35 49 38
00:09 – 00:24 41 61 31 44 33
01:14 – 01:29 42 62 36 44 38
Table 6 Noise Level Measurements at Location NM06
During the daytime survey periods, road traffic movements on the R148 were noted as the primary contributor to the noise build-up. Birdsong, occasional train
JM/10/5043NR01 AWN Consulting Limited
___________________________________________________________________________________________________
_____________________________________________________________________________________________________
Page 10
movements, distant aircraft movements and wind noise on nearby foliage were also noted. Plant noise from the Intel site was barely audible at this location. Noise levels were in the range 44 to 45dB LAeq and 37 to 40dB LA90. During the night-time survey periods, occasional road traffic movements on the R148 and broadband plant noise from the rear of the site were noted as being the primary contributors to the noise build-up. An idling train was the dominant contributory noise source during the first night-time measurement period. Noise levels were in the range 41 to 46dB LAeq and 33 to 38dB LA90.
2.6.7 Location NM07
Table 7 below presents the noise level measurements at Location NM07.
Time (hrs)
Measured Noise Level, dB re 210-5
Pa
LAeq LAmax LAmin LA10 LA90
14:50 – 15:05 55 72 45 57 49
15:53 – 16:08 55 71 46 57 51
16:58 – 17:13 54 72 45 56 49
22:04 – 22:19 44 59 37 44 38
23:26 – 23:41 41 55 35 43 37
00:32 – 00:47 37 55 31 39 33
Table 7 Noise Level Measurements at Location NM07
During the daytime survey periods, birds nesting in nearby trees were the dominant source of noise. Other audible sources included traffic on surrounding roads and occasional train movements. A distant lawnmower was noted during the first measurement period. Plant noise from the Intel site was not audible during the daytime measurement periods. Noise levels were in the range 54 to 55dB LAeq and 49 to 51dB LA90. Distant traffic movements were noted to be the dominant noise source during the night-time periods. Plant noise from the Intel site was not audible during the night-time measurement periods. Noise levels were in the range 37 to 44dB LAeq and 33 to 38dB LA90.
2.6.8 Comment on Measured Noise Levels
The LAeq values are a type of average of the noise level during the measurement period. As it is a logarithmic average, it is especially sensitive to relatively loud noises of short duration. For example, a single passage of a vehicle can govern the LAeq value of a measurement over a period much longer than the time for which the vehicle was audible. Thus, where the noise emissions from the Intel site are steady, as plant items are in continuous operation, the LA90 value better reflects the magnitude of these emissions.
JM/10/5043NR01 AWN Consulting Limited
___________________________________________________________________________________________________
_____________________________________________________________________________________________________
Page 11
3.0 DISCUSSION The noise levels in terms of the LAeq level are presented in Table 8 below, and compared to the relevant IPPC Licence Criterion.
NSL
Daytime Night-time
LAeq (dB) Limit Value LAeq (dB)
Satisfies? LAeq (dB) Limit Value LAeq (dB)
Satisfies?
NM01 50 – 54
55
37 – 40
45
NM02 46 – 48 34 – 37
NM03 44 – 48 36 – 40
NM04 45 – 48 35 – 39 NM05 42 – 46 38 – 41
NM06 44 – 45 41 – 46*
NM07 54 – 55 37 – 44
Table 8 Measured LAeq levels for day and night-time periods compared to IPPC License criteria. * An idling train was the dominant contributory noise source during this night-time measurement period.
The measured LAeq levels are within the daytime limit value at all locations. However in many instances the LAeq values are governed by source not related to the site such as traffic on public roads, aircraft movements, train movements and birdsong. During the 2009 and 2010 IPPC surveys the measurements were paused as much as possible during local traffic movements and other individual events not associated with the Intel site. This explains the decrease in the reported levels at some locations when compared to surveys conducted in previous years. Due to the nature of the operations carried out at Intel, external noise sources run steadily over 24 hours. For this reason, it is more appropriate to compare the measured LA90 values against the limit values in the IPPC Licence. This is presented in the Table 9 below.
NSL
Daytime Night-time
LA90 (dB) Limit Value LAeq (dB)
Satisfies? LA90 (dB) Limit Value LAeq (dB)
Satisfies?
NM01 38 – 42
55
31
45
NM02 33 – 35 29 – 33
NM03 36 – 38 32 – 38
NM04 35 – 36 28 – 35
NM05 36 – 38 36 – 37
NM06 37 – 40 33 – 38
NM07 49 – 51 33 – 38
Table 9 Measured LA90 levels for day and night-time periods compared to IPPC License criteria It is therefore concluded that site noise emissions from Intel comply with the relevant limit values at all surveyed locations. It is also noted that measured plant noise levels are generally slightly lower than those monitored during the 2009 IPPC noise survey. It is feasible that the reduced noise levels are a result of the decommissioning of various plant items within the FAB 14 building.
JM/10/5043NR01 AWN Consulting Limited
___________________________________________________________________________________________________
_____________________________________________________________________________________________________
Page 12
An additional review of one-third octave band Leq noise levels has been conducted. One-third octave band measurement results are included in Appendix A. Review of this data has concluded that there is no tonal component to any of the noise levels measured during the 2010 survey.
JM/10/5043NR01 AWN Consulting Limited
___________________________________________________________________________________________________
_____________________________________________________________________________________________________
Page 13
4.0 CONCLUSIONS Noise levels have been measured at the locations stipulated in the relevant IPPC Licence. Audible noise sources include traffic on surrounding roads, the passage of trains, aircraft movements, birdsong, wind noise on nearby foliage and steady external plant noise from the Intel site. Due to the continuous nature of these external plant noise sources, it is appropriate to compare the measured LA90 which represents the steady background component of the environmental noise climate at each location. At all locations, the LA90 values are within the given limit values, for both day and night-time periods. In addition, review of one-third octave band data confirms that there is no tonal component to measured noise levels. It may therefore be concluded that this facility is in compliance with Condition 5 of the IPPC Licence in respect of noise.
Project
Intel 2010 IPPC Noise
Monitoring Reference
JM/10/5043NR01
Figure 1
Site Layout and Noise
Monitoring Locations
The Tecpro Building, Clonshaugh Business and Technology Park, Dublin 17
T: +353 1 847 4220 F: +353 1 847 4257
NM01
NM02
NM03
NM04
NM05
NM06
NM07
_____________________________________________________________________________________________________
Page 15
APPENDIX A
NOISE MEASUREMENT RESULTS 1/3 OCTAVE BAND
_____________________________________________________________________________________________________
Page 16