INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

Embed Size (px)

Citation preview

  • 7/25/2019 INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

    1/25

    Table of Contents

    Index of Figures ..................................................................................................................................... 26

    1. Objective of Project ......................................................................................................................... 3

    2. Spectrum of Work Parts .................................................................................................................. 3

    2.1. Item I - stepped shaft .............................................................................................................. 3

    2.2. Item IIcasing .......................................................................................................................... 4

    2.3. Item IIIsleeve 1 ..................................................................................................................... 5

    2.4. Item IVsleeve 2 .................................................................................................................... 6

    2.5. Item Vplate 1 ....................................................................................................................... 7

    2.6. Item VIsleeve3 ..................................................................................................................... 8

    2.7. Item VIIlever....................................................................................................................... 9

    3. Resources ...................................................................................................................................... 10

    3.1. Available machines ................................................................................................................ 10

    3.2. Human resources................................................................................................................... 14

    4. Flow Modelling .............................................................................................................................. 15

    4.1. Flow process chart ................................................................................................................. 15

    4.2. Aggregated material flow by machines ................................................................................. 15

    5. Spatial Structure. ....................................................................................................................... 16

    6. Method of Scheduling ................................................................................................................... 17

    7. Production Schedule ..................................................................................................................... 17

    8. Resource Utilization ...................................................................................................................... 19

    9. Reports .......................................................................................................................................... 22

    10. Conclusions ................................................................................................................................ 23

    10.1. Critical path ....................................................................................................................... 24

    10.2. Bottlenecks ........................................................................................................................ 25

    11. Bibliography ............................................................................................................................... 26

  • 7/25/2019 INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

    2/25

    INTEGREATED SYSTEM OF METALWORK PRODUCTION PAGE3

    1. Objective of Project

    The objective of this project is planning of production of various items usingmachines available in an

    assumed production hall. The first part of the project includes the choice of items to be made,

    assigning necessary types and times of tooling for each part, choosing machines and ways oftransport, and planning of locating them in the production hall. Next step is using computer aided

    machining software. It will allow us to optimize the production process itself, but it will also improve

    the use of machines and reduce time of work and demurrage, which makes the production

    adjustable to dynamically changing market needs

    2. Spectrum of Work Parts

    Selected objects are made of semi-finished steel products and they require fallowing machining

    processes: turning, milling, drilling, grinding, tempering. Each item in the final stage is checked for

    preserving the required dimensions and tolerances on shape and position-coordinate measuring

    machine. The following items were presented with the scheduling of machining sequence.

    2.1. Item I - stepped shaft

    Figure 1 Stepped shaft

    Semi-finished product

    shaft 45x300, with prepared Centring holes and face surfaces

    Machining planning

    No. Operation of technological process Machine Identification

    1.Profile turning-threading M30, groove

    machiningTurning Centre TC

    2. Milling key way and slot Milling Centre MC

    3. Finish grinding Grinder G

    4. Quality assurance(control of shapes anddimensions)

    Coordinate Measuring Machine CMM

  • 7/25/2019 INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

    3/25

    INTEGREATED SYSTEM OF METALWORK PRODUCTION PAGE4

    2.2. Item II casing

    Figure 2 Casing

    Semi-finished product

    Steel cuboid 200x150x90

    Base: central hole 46,25H6

    Machining planning

    No. Operation of technological process Machine Identification

    1. Processingdatumhole 46,25H6 Milling Centre MC

    2. Milling surfaces Milling Centre MC

    3. Machining 14, 6 and threading M14, M6 Milling Centre MC

    4. Quality assuranceCoordinate Measuring

    MachineCMM

  • 7/25/2019 INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

    4/25

    INTEGREATED SYSTEM OF METALWORK PRODUCTION PAGE5

    2.3. Item III sleeve 1

    Figure 3 Sleeve I

    Semi-finished product

    Rolled rod 120

    Base: rolledsurface 120

    Machining planning

    No. Operation of technological process Machine Identification

    1. Turning cylindrical surfaces 63j6, 55 Turning Centre TC

    2. Turning phases Turning Centre TC

    3.Performance of hole 35H6 and stepped

    holes 13, 24Milling Centre MC

    4. Performance of side hole 15 Milling Centre MC

    5. Grinding surface 63j6 Grinder G

    6. Grinding hole Grinder G

    7. Quality assuranceCoordinate Measuring

    Machine

    CMM

  • 7/25/2019 INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

    5/25

    INTEGREATED SYSTEM OF METALWORK PRODUCTION PAGE6

    2.4. Item IV sleeve 2

    Figure 4 Sleeve II

    Semi-finished product

    Rolled rod 66

    Base: rolled surface 46

    Machining planning

    No. Operation of technological process Machine Identification

    1. Face milling Turning Centre TC

    2. Rough turning Turning Centre TC

    3. Profile turning Turning Centre TC

    4. Finish turning Turning Centre TC

    5. Key way Milling Milling Centre MC

    6. Drilling Milling Centre MC

    7. Finishgrinding Grinder G

    8. Hardening Induction Hardening Machine IH

    9. Quality assuranceCoordinate Measuring

    MachineCMM

  • 7/25/2019 INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

    6/25

    INTEGREATED SYSTEM OF METALWORK PRODUCTION PAGE7

    2.5. Item V plate 1

    Figure 5 Plate

    Semi finished product

    Rolled rod 212

    Base: rolled surface 212

    Machining planning

    No. Operation of technological process Machine Identification

    1. Turning the cylindrical surface 140 Turning Centre TC

    2. Turning phases and rounding Turning Centre TC

    3.Performance of holes 145, 131, 120,

    95H8, 85, 73, 8, 6, 3Milling Centre MC

    4. Tapping of holes 8 Milling Centre MC

    5. Quality assuranceCoordinate Measuring

    MachineCMM

  • 7/25/2019 INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

    7/25

    INTEGREATED SYSTEM OF METALWORK PRODUCTION PAGE8

    2.6. Item VI sleeve3

    Figure 6 Sleeve with flange

    Semi finished product

    Rolled rod 120

    Base: rolled surface 120

    Machining planning

    No. Operation of technological process Machine Identification

    1. Turning cylindrical surfaces 60j6 Turning Centre TC

    2. Turning phases Turning Centre TC

    3. Performance of hole 35H6 and holes 13 Milling Centre MC

    5. Grinding surface 60j6 Grinder G

    6. Grinding hole 35H6 Grinder G

    7. Tapping M36 thread Grinder G

    8. Quality assuranceCoordinate Measuring

    MachineCMM

  • 7/25/2019 INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

    8/25

    INTEGREATED SYSTEM OF METALWORK PRODUCTION PAGE9

    2.7. Item VII lever

    Figure 7 Lever

    Semi-finished product

    Forging

    Base: hole 20H7

    Machining planning

    No. Operation of technological process Machine Identification

    1.Preparation of the baseperformance of

    20H7 holesMilling Centre MC

    2. Face milling Milling Centre MC

    4. Quality assuranceCoordinate Measuring

    MachineCMM

  • 7/25/2019 INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

    9/25

    INTEGREATED SYSTEM OF METALWORK PRODUCTION PAGE10

    3. Resources

    3.1. Available machines

    a) Turning Centre

    Figure 8 Turning Centre

    Horizontal turning centre

    For turning of shafts: using tusk, the turned item is fixed in the spindle grip

    Provided with a tools warehouse

    Presence of a worker responsible for tooling and changing of items is required

  • 7/25/2019 INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

    10/25

    INTEGREATED SYSTEM OF METALWORK PRODUCTION PAGE11

    b) Milling Centre

    Figure 9 Milling centre

    Vertical milling centre

    Milling the external surfaces and holes

    Drilling and threading the holes

    Provided with a tools warehouse

    Presence of a worker responsible for tooling and changing of items is required

  • 7/25/2019 INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

    11/25

    INTEGREATED SYSTEM OF METALWORK PRODUCTION PAGE12

    c) CNC grinder

    Figure 10 CNC Grinder

    For grinding the external surfaces and holes

    For grinding small and medium elements for unit and series production

    d) Coordinate Measuring Machine

    Figure 11 Coordinate Measuring Machine

    High quality measuring

    Measurement of complicated items

    Multisensor machine for different measuring jobs

  • 7/25/2019 INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

    12/25

    INTEGREATED SYSTEM OF METALWORK PRODUCTION PAGE13

    e) Induction Hardening Machine

    Figure 12 Induction Hardening Machine

    Heat treatment; induction hardening

    For induction hardening the surfaces of shafts, bolts, sleeves, flat surfaces, sleeve fronts, gear

    wheels

    High efficiency, series treatment

    f) Forklift

    Figure 13 Forklift

    Manual forklift with a scale

    Capacity of 2500kg

  • 7/25/2019 INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

    13/25

    INTEGREATED SYSTEM OF METALWORK PRODUCTION PAGE14

    3.2. Human resources

    According to Figure 16 "Diagram of a 2-cellular production hall", there will be two cells equipped with

    machines. In first - two milling and turning centres. In second - induction hardening machine, grinder

    and coordinate measuring machine. All of machines have to be operated on some level.

    a) Cell one

    Two milling and turning centres will be operated by 4 persons from. There is need to manual

    change of objects.

    b) Cell two

    Grinder will be operated by one qualificated employee

    CMM will be operated by one qualificated employee

    c) Both cells

    There is need of two persons that would transport semi-finished products between

    machines.

  • 7/25/2019 INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

    14/25

    INTEGREATED SYSTEM OF METALWORK PRODUCTION PAGE15

    4. Flow Modelling

    4.1. Flow process chart

    Routes present planned machining sequence of products.

    Figure 14 Flow process chart. P1-P7 products; TC turning center; MCmilling center; G grinder; IH induction

    hardening machine; CMMcoordinate measuring machine; S1,S2 storages.

    4.2. Aggregated material flow by machines

    Routes present material flow that helps to find disproportion in use of machines.

    Figure 15 Network of material connections

  • 7/25/2019 INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

    15/25

    INTEGREATED SYSTEM OF METALWORK PRODUCTION PAGE16

    Both figures help to findpossible bottle-necks. It is easy tonotice that MC and CMM have to work on

    more parts then other machines.

    5. Spatial Structure.

    Main aim of setting spatial structure is to shorter ways of semi-finished products, this leads to short

    times of transport and work that is put into it. Less work = less money spent.

    At first step machines were supposed to be set by criterion of product specialization as it is shown in

    table 1.

    Cell Machine P1 P3 P4 P6 P2 P5 P7

    1

    IH 4

    G 3 3 3 3

    TC 1 1 1 1 1

    2MC 2 2 2 2 1 2 1

    CMM 4 4 5 4 2 3 2

    Table 1 Spatial structure set by criterion of product specialization

    But after analyzing this structure in front of flow process it was noticed that products would flow

    back to previous cell which is waste of time. Observation was cause of working out better solution

    and after taking into account this fact final structure was set by criterion of organisational

    concentration [Table 2].

    Cell Machine P1 P2 P3 P4 P5 P6 P7

    1TC 1 1 1 1 1

    MC 2 1 2 2 2 2 1

    2

    G 3 3 3 3

    IH 4

    CMM 4 2 4 5 3 4 2

    Table 2Spatial structure set by criterion of organisational concentration

    Figure 15 visualizes final spatial structure.

  • 7/25/2019 INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

    16/25

    INTEGREATED SYSTEM OF METALWORK PRODUCTION PAGE17

    Figure 16 Diagram of a 2-cellular production hall

    6. Method of Scheduling

    In the educational version of Preactor 9.3 there are three methods of scheduling: forward

    scheduling, backward scheduling and APS (Advanced Planning System). Present project uses forward

    scheduling, providing a solution characterized by the earliest date of completion of production. In

    addition operations were set in compliance with FIFO (First In First Out)strategy. The earliest ordersare executed first and the latest are at the end of the list.

    7. Production Schedule

    Gant chart below presents the scheduling of process.

  • 7/25/2019 INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

    17/25

    INTEGREATED SYSTEM OF METALWORK PRODUCTION PAGE18

    Figure 17 Gantt chart

  • 7/25/2019 INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

    18/25

    INTEGREATED SYSTEM OF METALWORK PRODUCTION PAGE19

    8. Resource Utilization

    Figure 18 Resource utilization chart. Red line indicates average machine utilization(15,39%)

    Charts below present theindividual use of machinesin %.

    10,56%

    1,67%

    87,77%

    Turning centre TC1

    Util ization time Set-up time No work time

    8,75%

    1,25%

    90,00%

    Turning centre TC2

    Utilization time Set-up time No work time

  • 7/25/2019 INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

    19/25

    INTEGREATED SYSTEM OF METALWORK PRODUCTION PAGE20

    16,11% 2,64%

    81,25%

    Milling centre MC1

    Util ization time Set-up time No work time

    15,90% 2,22%

    81,88%

    Milling centre MC2

    Utilization time Set-up time No work time

    10,67%1,94%

    87,39%

    CNC grinder - G

    Utilization time Set-up time No work time

    30,35%

    4,17%

    65,48%

    Coordinate Measuring

    Machine CMM

    Utilization time Set-up time No work time

    2,08% 0%

    97,92%

    Forklift 1

    Utilization time Set-up time No work time

    8,33%0%

    91,67%

    Forklift 2

    Utilization time Set-up time No work time

  • 7/25/2019 INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

    20/25

    INTEGREATED SYSTEM OF METALWORK PRODUCTION PAGE21

    In analysis of the chart presented above, one concludes that uniform loadings are not possible. The

    forklifts are the least used machines in this chart, because they carry entire series of products, not

    individual parts.

    The most used machine is Coordinate Measuring Machine. Every part must be checked, so the

    company can provide high quality of products. This problem could be resolved by reducing steps of

    quality assurance to most important parts or not checking all objects but only a part of them. In

    order to provide high quality of products, the system has to assume a high chance of dimensional

    incapability, therefore a big part of the production must be checked, so the usage of CMM remains

    very big. Automation of quality assurance could also solve the problem.

    4,17% 0%

    95,83%

    Induction Hardening Machine

    IH

    Utilization time Set-up time No work time

  • 7/25/2019 INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

    21/25

    INTEGREATED SYSTEM OF METALWORK PRODUCTION PAGE22

    9. Reports

    Table 3 Schedule performance metrics

    Table 4Summary of orders

  • 7/25/2019 INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

    22/25

    INTEGREATED SYSTEM OF METALWORK PRODUCTION PAGE23

    10.Conclusions

    Job Completion Data

    Total Minimum Average Maximum

    Lead time 2d 4h 20min 3h 39min 7h 29min 11h 23min

    Added Value Percentage 23,43 49,03 87,36

    Resource Data

    Minimum Average Maximum

    Working Percentage 4,3 24,51 62,61

    Setup Percentage 0 3,18 8,6

    Schedule Duration 11h 38 min

    Table 5 Shorten schedule performance metrics

    Conclusions are based on reports collected from Preactor APS program, presented in the previous

    section.

    Our criterion was integration of production system. Optimal solution has been found using Preactor.

    Characteristic parameters of the system are presented below.

    Length of the ProductionCycle(LPC)

    In the present system, the production of the FIFO scheduling forward - by benchmarks - the

    length of the production cycle is 11 hours 38 minutes.

    This is the time it takes to complete a set of tasks, so this value should decrease to the

    minimum, which proves most effective use of work time for each machines. The lower the

    LPC time, the faster the company can accept new orders and generate more profits.

    Degree of Utilization of Resources (DUR)

    Resources are machines and forklifts. Value DUR should strive for the maximum, however

    forklifts significantly decrease the average utilization of resources. At the same time at this

    point it is worth mentioning that loadings should be similar if we want to avoid bottle necks.

    If one machine is overloaded other machines have to wait until previous steps are executed.

    Order Flow Time (OFT)

    The value of the order flow time strive for minimum because it presents the time, an object

    stays in the system. In this project the total execution time is 2d 4h 20min which is collective

    timeforall orders. This is not atimeof technological processes, because in addition tothe time

  • 7/25/2019 INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

    23/25

    INTEGREATED SYSTEM OF METALWORK PRODUCTION PAGE24

    requiredto performeach operation,downtimeis also taken into account. The pointis to

    obtainthe smoothest possibleflow.

    The percentage ofadded value

    The percentage of added value is also a measure of the effectiveness of the system. The

    highest values are recommended, because it grows during an ongoing machining of the work

    piece. This is the equivalentto sayingthat during downtime, that is, when the object is waiting

    for its turn, the added valuedoes not change. In the present case it is much about 49.03%.

    10.1. Critical path

    Longest sequence ofactivities in aproject plan which must becompleted on time for theproject to

    complete ondue date.An activity on the critical path cannot be started until its predecessor activity

    is complete; if it is delayed for aday,the entire project will be delayed for a day unless the activity

    following the delayed activity is completed a day earlier. Figure 19 shows critical path on Gant chart.

    Figure 19 Critical path

    As could be seen critical path is mainly processing of item P1. Whole time is 11h and 38min if any

    operation of critical path will be longer, final time will get longer too.

    http://www.businessdictionary.com/definition/activity.htmlhttp://www.businessdictionary.com/definition/project-planning.htmlhttp://www.businessdictionary.com/definition/completed.htmlhttp://www.businessdictionary.com/definition/project.htmlhttp://www.businessdictionary.com/definition/due-date.htmlhttp://www.businessdictionary.com/definition/day.htmlhttp://www.businessdictionary.com/definition/day.htmlhttp://www.businessdictionary.com/definition/due-date.htmlhttp://www.businessdictionary.com/definition/project.htmlhttp://www.businessdictionary.com/definition/completed.htmlhttp://www.businessdictionary.com/definition/project-planning.htmlhttp://www.businessdictionary.com/definition/activity.html
  • 7/25/2019 INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

    24/25

    INTEGREATED SYSTEM OF METALWORK PRODUCTION PAGE25

    10.2. Bottlenecks and possible improvements

    Bottlenecks are caused by overlapping of orders at the same time - conflict situations arise, e.g.

    Different types of treatment areperformed at the same machines. This leads to delays and waiting

    for the next objects to bemachined. This is undesirable, however, with a limited number of

    resources, and a more complex structure of the socket it is hard to avoid this phenomena. One

    solution could be to equip a production hall with an additional machine, but only if such a step would

    be profitable for the company.

    Figure 20 Bottlenecks on Gantt chart

    On the figure above we can see bottlenecks of order P6/CARGOTECH/02. We can easily notice that

    the largest exist before CMM and as it was said in chapter "Resource utilization" times of operations

    should be shortened or new machine should be bought. There is also need of intermediate store

    because CMM is a bottleneck for almost every part.

    Another way to increase the efficiency of the production process is to include an industrial robot to

    automate the material handling. This solution requires scheduling of the robot, and makes the

    planning of process more complex, but it would increase the productivity significantly.

    10.3. Summary

    The integration of the production system manifests itself in sockets cooperation, as well as in the

    stream intert wining activities around basic operations, such as transport and storage activities or

    setup. The integration therefore allows a flexible response to market needs, changes and

    modernization ofproduction processes. One should therefore seek to obtain it, which will increase

    the productivity and efficiency of the entire system.

  • 7/25/2019 INTEGREATED SYSTEM OF METALWORK PRODUCTION.pdf

    25/25

    Index of Figures

    Figure 1 Stepped shaft............................................................................................................................. 3

    Figure 2 Casing ........................................................................................................................................ 4

    Figure 3 Sleeve I ....................................................................................................................................... 5

    Figure 4 Sleeve II ...................................................................................................................................... 6

    Figure 5 Plate ........................................................................................................................................... 7

    Figure 6 Sleeve with flange ..................................................................................................................... 8

    Figure 7 Lever .......................................................................................................................................... 9

    Figure 8 Turning Centre ......................................................................................................................... 10

    Figure 9 Milling centre ........................................................................................................................... 11

    Figure 10 CNC Grinder ........................................................................................................................... 12

    Figure 11 Coordinate Measuring Machine ............................................................................................ 12

    Figure 12 Induction Hardening Machine ............................................................................................... 13

    Figure 13 Forklift ................................................................................................................................... 13

    Figure 14 Flow process chart .....................................................................Error! Bookmark not defined.

    Figure 15 Network of material connections .......................................................................................... 15

    Figure 16 Diagram of a 2-cellular production hall ................................................................................. 17

    Figure 17 Gantt chart ............................................................................................................................ 18

    Figure 18 Resource utilization chart ...................................................................................................... 19

    Figure 19 Critical path ........................................................................................................................... 24

    Figure 20 Bottlenecks on Gantt chart ................................................................................................... 25

    11.Bibliography

    [1] M. Siemitkowski, INTEGRTED SYSTEMS OF PRODUCTION - lectures, Gdask: GUT, 2014.

    [2] Preactor International Ltd., Preactor - Podrcznik uytkownika, Warszawa: Prtczyski, 2004.