16
DNV-BEW T&D Department James MacPherson, Power Systems Engineer November 8, 2011 Integrating High PV Penetrations Into the U.S. Distribution System, Experiences with SynerGEE Electric

Integrating High PV Penetrations Into the U.S. Distribution System … · 2019-12-26 · DNV-BEW T&D Department James MacPherson, Power Systems Engineer November 8, 2011 Integrating

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Integrating High PV Penetrations Into the U.S. Distribution System … · 2019-12-26 · DNV-BEW T&D Department James MacPherson, Power Systems Engineer November 8, 2011 Integrating

DNV-BEW T&D Department James MacPherson, Power Systems Engineer

November 8, 2011

Integrating High PV Penetrations Into the U.S. Distribution System,

Experiences with SynerGEE Electric

Page 2: Integrating High PV Penetrations Into the U.S. Distribution System … · 2019-12-26 · DNV-BEW T&D Department James MacPherson, Power Systems Engineer November 8, 2011 Integrating

© Det Norske Veritas AS. All rights reserved.

Update on High PV Penetration on Transmission and Distribution Grids

Overview Background on High PhotoVoltaic (PV) Penetration Studies

- Hawaiian Electric Company (HECO) - Sacramento Municipal Utility District (SMUD), CPUC CSI RD&D project - Objective: Enable capability to reliably plan and operate with high

penetration of variable renewable resources on the grid - Using SynerGEE to study steady-state limitations of renewable resources

Model Development - Model creation & maintenance - Adding 1000’s of existing & potential PV units to model - PV penetration sweep (load-flow and fault analysis) - Conversion to balanced 3-phase model

Example Results

2

Page 3: Integrating High PV Penetrations Into the U.S. Distribution System … · 2019-12-26 · DNV-BEW T&D Department James MacPherson, Power Systems Engineer November 8, 2011 Integrating

© Det Norske Veritas AS. All rights reserved.

Update on High PV Penetration on Transmission and Distribution Grids

Distribution Modeling Analytical Tools

• SynerGEE Electric – GL Noble Denton – Steady State Analysis – Voltage Analysis – Balanced and unbalanced load flow – Fault current studies

• Equivalent inverter modeling for steady state and fault analysis

– Harmonics – Time sequential analysis (hourly) – Switching routines – Tap changer impacts – Capacitor control and regulation impacts

• PSS/Sincal – Siemens PTI – Steady State and Dynamic Capability – Same as SynerGEE for steady state

analysis, but also includes – Detailed inverter modeling for fault current

studies – Dynamic/Transient Modeling of

Generators – Sub hourly irradiance data input

3

Page 4: Integrating High PV Penetrations Into the U.S. Distribution System … · 2019-12-26 · DNV-BEW T&D Department James MacPherson, Power Systems Engineer November 8, 2011 Integrating

© Det Norske Veritas AS. All rights reserved.

Update on High PV Penetration on Transmission and Distribution Grids

PV Penetration Limits at Different System Levels

4

46kV:12kV

Load Pocket

15 kW Distributed Residential PV

Large Customer PV

NO

3.6 MVAr

W1

W4

W3

W2

46kV:12kV

Area 1

Area 3

Feeder Transformer

Substation

Page 5: Integrating High PV Penetrations Into the U.S. Distribution System … · 2019-12-26 · DNV-BEW T&D Department James MacPherson, Power Systems Engineer November 8, 2011 Integrating

© Det Norske Veritas AS. All rights reserved.

Update on High PV Penetration on Transmission and Distribution Grids

Model Creation & Maintenance

5

• GIS database continually updated by utility

• Convert GIS database to SynerGEE format

• Run in SynerGEE and identify errors (BEW)

• Identify corrections and where to correct (BEW/utility)

• Propose updates to GIS database

Page 6: Integrating High PV Penetrations Into the U.S. Distribution System … · 2019-12-26 · DNV-BEW T&D Department James MacPherson, Power Systems Engineer November 8, 2011 Integrating

© Det Norske Veritas AS. All rights reserved.

Update on High PV Penetration on Transmission and Distribution Grids

Model Development: Adding Existing PV to Model

Done in Excel & Access

Input from utility - Address - Rated kW Capacity - Feeder - Phasing at point of interconnection

For each existing PV unit - Convert address to geographical coordinates

(X,Y) - Match to nearest node with same feeder &

phasing

Aggregate existing PV units as necessary

6 Source: HECO 6

Page 7: Integrating High PV Penetrations Into the U.S. Distribution System … · 2019-12-26 · DNV-BEW T&D Department James MacPherson, Power Systems Engineer November 8, 2011 Integrating

© Det Norske Veritas AS. All rights reserved.

Update on High PV Penetration on Transmission and Distribution Grids

Model Development: Allocating Potential PV

Page 8: Integrating High PV Penetrations Into the U.S. Distribution System … · 2019-12-26 · DNV-BEW T&D Department James MacPherson, Power Systems Engineer November 8, 2011 Integrating

© Det Norske Veritas AS. All rights reserved.

Update on High PV Penetration on Transmission and Distribution Grids

Model Development: Sweeping Potential PV Capacity with Recipe Objective: Create a Recipe to run multiple analyses, changing PV output, and

saving results to CSV files

• Identify potential PV units • Set Generator Output to “Specify Output %”

• Initialize potential PV % outputs (e.g. 0%)

• Run Analyses (e.g. Load-Flow, Fault, etc.)

• Export Results to Excel (.csv)

• Increment PV % outputs (e.g. +1%, +5%)

Loop Until 100%

Page 9: Integrating High PV Penetrations Into the U.S. Distribution System … · 2019-12-26 · DNV-BEW T&D Department James MacPherson, Power Systems Engineer November 8, 2011 Integrating

© Det Norske Veritas AS. All rights reserved.

Update on High PV Penetration on Transmission and Distribution Grids

Example Results: Hi Potential PV Sweep

Effect of PV Penetration on - Min/Max Voltage, Max Loading, Tap

Position

9

Backfeeding at - Feeders, Transformers, and Substation - Minimum Daytime Load

0

2

4

6

8

10

12

0.0

20.0

40.0

60.0

80.0

100.0

120.0

140.0

128

180

232

280

337

386

442

491

546

594

643

905

1166

1423

1681

1939

2203

2462

2719

2981

3237

Tap

Posi

tion

Max

Loa

ding

(%),

Volt

age

(120

V b

ase)

Total PV Generation (kW)

"Feeder A" Potential PV Sweep ResultsMinimum Voltage Maximum Voltage Maximum Loading Depot Rd TSF TP

0 1000 2000 3000 4000 5000 6000 7000 8000 9000 10000

Feeder 4

Feeder 3

TSF 2

Feeder 2

Feeder 1

TSF 1

Substation

Total kW of PV When Backfeeding Occurs

Total kW of PV When Backfeeding Occurs for Feeders, Transformers, and Substation

≈ Sum of TSF 1 & 2

≈ Sum of Feeders 1 & 2

≈ Sum of Feeders 3 & 4

Page 10: Integrating High PV Penetrations Into the U.S. Distribution System … · 2019-12-26 · DNV-BEW T&D Department James MacPherson, Power Systems Engineer November 8, 2011 Integrating

© Det Norske Veritas AS. All rights reserved.

Update on High PV Penetration on Transmission and Distribution Grids

Model Development: Fault Analysis with Distributed PV Inverters not yet

modeled in SynerGEE Electric

Need another means of modeling a current source for fault analysis

Current method time-consuming and difficult to automate in PV sweep

PSLF, Sincal - Dynamics &Transient

stability - Inverter dynamic models

from IEEE and WECC guidelines

Equivalent Inverter Model

Low Voltage Network

Representation

Generator

Transformer

3 PH Fault Current on Distribution

Line

Equivalent Fault Contribution from

Inverter

Switch

Page 11: Integrating High PV Penetrations Into the U.S. Distribution System … · 2019-12-26 · DNV-BEW T&D Department James MacPherson, Power Systems Engineer November 8, 2011 Integrating

© Det Norske Veritas AS. All rights reserved.

Update on High PV Penetration on Transmission and Distribution Grids

Example Results: 3-Phase Fault Current Analysis

0% 1% 2% 3% 4% 5% 6% 7% 8% 9%

10% 11% 12% 13% 14%

0 1000 2000 3000 4000 5000 6000 7000

% C

hang

e in

Fau

lt C

urre

nt fr

om N

o PV

Cas

e

PV Generation on Feeder (kW)

Feeder Max. 3P Fault Current vs. PV Generation

Distributed Potential PV Potential PV at Start of Feeder Potential PV at END of Feeder

5% FC Increase

10% FC Increase

15% PV penetration FC

Page 12: Integrating High PV Penetrations Into the U.S. Distribution System … · 2019-12-26 · DNV-BEW T&D Department James MacPherson, Power Systems Engineer November 8, 2011 Integrating

© Det Norske Veritas AS. All rights reserved.

Update on High PV Penetration on Transmission and Distribution Grids

Results: Time of Day with PV Irradiance Profiles

Separate solar irradiance profile applied to each feeder

Recipe used to loop through 24 hours

-16

-12

-8

-4

0

4

8

12

16

0

200

400

600

800

1000

1 2 3 4 5 6 7 8 9 101112131415161718192021222324

Tap

Posi

tion

PV G

ener

atio

n (k

W)

Hour

Time of Day PV Generation ProfilesFeeder 1 Feeder 2 TSF Tap Position

Page 13: Integrating High PV Penetrations Into the U.S. Distribution System … · 2019-12-26 · DNV-BEW T&D Department James MacPherson, Power Systems Engineer November 8, 2011 Integrating

© Det Norske Veritas AS. All rights reserved.

Update on High PV Penetration on Transmission and Distribution Grids

Model Development: Converting SynerGEE Unbalanced 1-P Model to 3-P Balanced Model

Purpose - Need to study dynamic/transient impacts of

distributed PV

Problem - No automatic conversion between SynerGEE and

other load flow software

Solution - Manually convert models into CIM format

Steps for Conversion - Perform single and two phase “roll up” to three

phase in SynerGEE - Export to Excel database - Manual manipulation of SynerGEE data into CIM

format - Import to other load flow software

Investigating the automation of this conversion process

13

Comparison of voltages at specified distances along the feeder

Page 14: Integrating High PV Penetrations Into the U.S. Distribution System … · 2019-12-26 · DNV-BEW T&D Department James MacPherson, Power Systems Engineer November 8, 2011 Integrating

© Det Norske Veritas AS. All rights reserved.

Update on High PV Penetration on Transmission and Distribution Grids

Summary

Working with SynerGEE to accomplish steady-state load-flow, fault current, harmonics studies

Key needs from SynerGEE: - Inverter PQ model for fault current

analysis - Transient analysis capability - Sub-hourly irradiance inputs

14

Page 15: Integrating High PV Penetrations Into the U.S. Distribution System … · 2019-12-26 · DNV-BEW T&D Department James MacPherson, Power Systems Engineer November 8, 2011 Integrating

© Det Norske Veritas AS. All rights reserved.

Update on High PV Penetration on Transmission and Distribution Grids

Contact James MacPherson Engineer, Power Systems BEW Engineering, Inc. 2303 Camino Ramon, Suite 220 San Ramon, CA 94583 Email: [email protected] Main: 1-925-867-3330 Phone: 1-925-327-3030

15

Page 16: Integrating High PV Penetrations Into the U.S. Distribution System … · 2019-12-26 · DNV-BEW T&D Department James MacPherson, Power Systems Engineer November 8, 2011 Integrating

© Det Norske Veritas AS. All rights reserved.

Update on High PV Penetration on Transmission and Distribution Grids

16

Safeguarding life, property and the environment

www.dnv.com