22
The Full Kit Project Link Engineering Dante Cicchelli, Andrew Choraszewski, Shannon Manalel, Nathan Taschler OM 300 Section 001, Team #5

Integrated Report OM300 Team 5

Embed Size (px)

Citation preview

Page 1: Integrated Report OM300 Team 5

The Full Kit ProjectLink Engineering

Dante Cicchelli, Andrew Choraszewski, Shannon Manalel,

Nathan Taschler

OM 300 Section 001, Team #5

Page 2: Integrated Report OM300 Team 5

Agenda

Company (description)Interviewees Project Overview and DriversProject Steps

Show and Tell

Project Challenges & SolutionsProject BenefitsFuture OpportunitiesLeader Career Lessons

Page 3: Integrated Report OM300 Team 5

Business Description

• Privately Held• Multinational • Headquartered in Plymouth, Michigan

(Interview)• In business for over 75 years• Employs 400 worldwide, 175 at the World HQ• $80 million in revenues• Since implementing Lean production increase

of 30%

Page 4: Integrated Report OM300 Team 5

• Manufactures Dynoameters (Dyno’s) for Automotive, Train, and Aerospace

• Dyno’s test parts under all weather conditions and stress tests

• Can conduct in-house testing and refurbishing at customers choice

• Plymouth location builds the model 3900 and 3000 Dyno

• Ships worldwide

Business Description (Continued)

Page 5: Integrated Report OM300 Team 5

Dynoameter 3000

Page 6: Integrated Report OM300 Team 5

Dynoameter 3900

Page 7: Integrated Report OM300 Team 5

Interview Info

Jerry Verkerke•Vice President of Test Operations and Director of Operations

•Oversees day to day operations at Plymouth shop Headquarters

•At Link for 5 years

•Spent 25 years working for Ford Motor Company

•Brought in to make a change

•Student of Lean

Page 8: Integrated Report OM300 Team 5

Project Overview• Project Started January 2013• Completed end of the year, December 2013• Link Engineering Implementation of Lean

Manufacturing• Verkerke was brought in to make a change • Project Team consisted of 12 people• Needed cooperation and commitment from all

employees• Project Team looked for employee input• Consistent shipping intervals

Page 9: Integrated Report OM300 Team 5

Before the Project

• Unorganized plant shop

• Waste• Unwanted materials and machines

• D-O-W-N-T-I-M-E

Page 10: Integrated Report OM300 Team 5

Link Shop Layout: (Original)

Page 11: Integrated Report OM300 Team 5

Project Description

Eliminate waste (Sell/Scrap) Launch 5S system that welcomed input (Company

Wide)Re-organize floor planThe Crib (Inventory)KittingDividing the plant into assembly baysProduct begins simultaneously in different areas

Page 12: Integrated Report OM300 Team 5

Project Description

Meet in the middle at the scheduled bayMeet in the middle at the scheduled bayImprove motion (Wheeled Mobility)Improve motion (Wheeled Mobility)Standard paintStandard paintPaint when readyPaint when ready

Page 13: Integrated Report OM300 Team 5

The “Kit” of the Kitting Project

Page 14: Integrated Report OM300 Team 5

Link Shop Layout: (Post Project)

Page 15: Integrated Report OM300 Team 5

How and Why Full Kit?

“It just works”Lead time was too highEfficient use of spaceFull Kit eliminated D-O-W-N-T-I-M-EBetter communication between

departments

Page 16: Integrated Report OM300 Team 5

Project Challenges & Solutions

Barriers to the plan

Employee Resistance

Rewards for “speaking up”

Mobilization (waste in time/resources)

Page 17: Integrated Report OM300 Team 5

Project Benefits: Quantitative

• Importance of improvement

• Customer satisfaction and attraction

• 30% increase in production and revenue• Significant decrease in inventory

• Getting rid of “wasteful misfortunes”• Decrease in excess machinery and equipment

• Consistent shipping intervals

Page 18: Integrated Report OM300 Team 5

Project Benefits: Qualitative

• Improvement in:• quality of products • in Link Engineering’s production rates • in customer satisfaction

• Reorganizing

• Employee morale

• Attracted more business

Page 19: Integrated Report OM300 Team 5

Future Opportunities

• Applies Kaizen• Brainstorms new ideas

• Advancement in shop’s floor – 19 bays• Expanding World Headquarters in Plymouth, MI• Optimize/Improve logical flow• Reduce costs by using space • Relocating offices – desk jobs above the floor• Employees’ input

Page 20: Integrated Report OM300 Team 5

Leader Career Lessons

• Be persistent

• ALWAYS room for improvement

• Do what YOU want

• Mentors, mentors, mentors!• Exchange ideas• Professional networking

Page 21: Integrated Report OM300 Team 5

Leader Career Lessons

Page 22: Integrated Report OM300 Team 5

Thanks for your time

• Questions