INTEGRATED CAISSON TEAM (ICT)
OPERATING MODEL
INTRODUCTION: Due to platform life extension,
Caissons have often been in place longer
than planned, and deterioration and failure of
Caissons is a growing trend in the North Sea
and worldwide. This deterioration and failure
may present a dropped object risk to subsea
structural and piping systems.
The Integrated Caisson Team (ICT) is a Global
Energy Group Production IRM initiative that
provides a cost efficient and value added
turnkey Caisson solution and “one-stop” shop service consisting of the following
capabilities:
Initial Integrity Inspection
Survey
Caisson Design
Caisson Fabrication
Caisson Destruct
Caisson Installation
Caisson Repairs
Caisson Maintenance
The philosophy behind the ICT model is the provision of a “one-stop” Caisson
remediation and replacement offering that identifies best value solutions by
combining the services of selected ICT Partners throughout the project lifecycle.
Key to the ICT philosophy is the decision by GEG PIRM not to add mark-ups to other
ICT Member services and end deliverables
Of significant value is the ability of the ICT to offer options to a variety of solutions from
within the structure of the ICT, without the requirement to bring in additional external
resources.
Examples include:
Options for either welded or weldless connections of Caisson sections
Use of conventional rigging equipment or specialist Caisson lifting tools during
destruct and construct
Options to coat Caissons with Client specified coating systems or utilisation of
1 coat systems complete with coating warranties during the fabrication
process
Option to install Marine Growth Prevention Systems at time of Caisson
installations, or as retrofit solutions to existing Caissons (this option is available
to Risers, Conductors, and structural tubulars)
Options for nitrox diving capability to 50mtr or Cofferdam support in the splash
zone
Alternative access solutions including rope access, WEB Deck and tension
netting systems, all installed by multi-disciplined access and trade technicians
Options for platform, vessel or daughter craft based diving operations
INTEGRATED CAISSON TEAM – RANGE OF SERVICES
PROJECT MANAGEMENT
SPECIALIST ACCESS
Subsea and topside special access systems, including:
Vessel or platform based diving systems using nitrox to increase dive time and
reduce decompression burdens
Custom built Daughter craft that offers diving, ROV and UAV launch
capabilities
Rope access, engineered decking, tension netting, catenary anchor systems
and aerial drones
INSPECTION
Subsea and topsides inspection
REPAIRS
Welded
Composites
Liners
DESTRUCT/DECOMMISSIONING
Multi-skilled access and trade specialists
Internal and external caisson lifting tools
FLUID MANAGEMENT
SURVEY
Full survey capabilities, including mark-up of work points for new Caisson
clamp and guide installation
DESIGN
FABRICATION
UK Fabrication facilities
European Fabrication facility
COATINGS
Including anti-fouling product
SPECIAL TOOLING
Weld-less connectors
Caisson lifting tools, including the capability to secure damaged caissons
during destruct scopes
COFFERDAMS
INSTALLATION
Subsea and topside construction & rigging teams
Special access services
Clamp and guide work point assurance (laser survey)
Weld-less connections removing requirement for hot work, habitats and
associated NDT
Full fabrication and welding capability where hot work is available
Habitats
Specialised Caisson Lifting Tools
Marine Growth prevention devices (including retrofit option for existing
structures)
MAINTENANCE
Impressed Current CP Systems
Marine Growth Prevention Tools
INTEGRATED CAISSON TEAM – MODEL FLOW DIAGRAM
INTEGRATED CAISSON TEAM – CAPABILITY AND DELIVERABLES
GEG STATS GMC Acotec CETCO Cathelco
Project Management
Access: Topside and Subsea
Inspection
Survey
Destruct
Design
FAB – UK
FAB – EUR
Coatings - UK
Coatings - EUR
Special Tooling Marine Growth Prevention Systems
Cofferdams
Installation
Fluid Management
Cathodic Protection
PREPARING FOR NEW CAISSON INSTALLATION
Transferring Control Panel to
Work Location
Transferring the Make-Up Tool
to Work Location
Lifting and Handling Tool
Installed to caisson
Sections
Removing Lifting and Hang-Off Rigging in Preparation for Lowering Caisson
Lowering caisson in Preparation for Making Up of Next Joint
Final Dead Weight Support Preparations and Caisson Successfully Installed to
Location
Dead Weight Support Installed
Integrated Caisson Team (ICT)
CONTACTS:
Global Energy (Group) Limited
Andy Graham
Tel: +44(0) 1224 794 869
Email: [email protected]
STATS (UK) LIMITED
Brett Laurenson
Tel: +44(0) 1224 772 461
Email: [email protected]
GMC LIMITED
Phil Jones
Tel: +44(0) 1189 657 512
Email: [email protected]
ACOTEC NV
Philip Starr
Tel: +44 74 320 487
Email: [email protected]
CETCO
Kris Frampton
Tel: +44(0) 1224 787 340
Email: [email protected]
Cathelco
Marc McKinlay
Tel: +44(0) 1467 632 136
Email: [email protected]