Installation of Truck Water Mains in 9th Avenue
(W.51st Street to W.59th Street)
Project ID: MED609
Community Board 4 Public Meeting
________, 2017 6:00PM
Project Data
Project ID: MED609
Registered Date: December 9, 2015
Notice To Proceed: March 1, 2017
Contractor: Waterworks JV
Contract Value: $ 28,000,000.00
Contract Duration: 1460 Days
Federal / State Fund: No
Holiday Embargo: Thanksgiving – New Year Holiday
Field Office: 333 W.52nd Street – Room 406
Brief Description of Project
• Installation of new 36” Trunk water main. • Installation of valves, regulators and chambers. • Replacement of 20” and 12” distribution water mains. • Replacement of 12” sewer pipe with new 15” sewer pipe. • Private utility upgrades (gas, electric and communication). • Reconstruction of curbs and sidewalk in certain locations. • Pedestrian ramps at corners (based on field conditions). • Installation of new traffic signals and street lighting poles.
Community Board MEETING Manhattan CB4
330 West 42nd St 26th Floor
New York, New York 10036
Construction Schedule Overview
PRELIMARY SCHEDULE: WORK HOURS / SPECIAL NOTES:
City DOT Allowable Work Hours
• 7AM – 4PM: Monday – Friday
• 8AM – 4PM: Saturday & Sunday
• Typical weekday work hours are 7AM to 3:30PM, Monday – Friday
• Night Time Hours may be requested for work involving water main
shut downs or when special conditions apply.
COMMUNITY IMPACTS • Pedestrian access will be maintained at all times
• Temporary Street closures and / or limited access may be necessary
• Uniformed NYPD traffic agents assigned for traffic control & Uniformed Flaggers for
Pedestrian movement
• R.E. will monitor operations and work within DEP Noise Code regulations
• Sidewalk and/or loading dock access from the curb may be temporarily restricted while
work is conducted (coordination will be arranged on a case by case basis)
• Parking may be temporarily restricted during construction
• Bus Stops may be temporarily relocated
• Garbage/Trash pick up may be affected
COMMUNITY IMPACTS CONT’D
Water Service Interruptions:
• 72-Hour Advance Advisory will be provided, followed by 24 hour
confirmation/cancellation notice.
• Specific instruction will be provided prior to water shutoff
• If your water service is not restored within 3 hours of the indicated time on the Shutoff
Notice, please contact the Community Construction Liaison (CCL) or 311 if after hours.
• Water Shut-downs are typically scheduled at night.
Special Needs:
Individuals with special needs should contact the CCL
DDC field staff will work specially with those individuals to minimize certain
inconveniences
KEEPING YOU INFORMED • Wayan Brown will be the Community Construction Liaison (CCL). He will be responsible
for keeping the community informed by:
– Being the first point of contact between the project and the community
– Identifying, addressing and/or resolving field inquiries & issues as well as any coordination between the project and needs of the affected stakeholders
– Providing regular updates/advisories for the community to better plan around construction activities
• CCL contact information: Name: Wayan Brown Email: [email protected] Field Office: 333 W.52nd Street, Suite 406 Telephone : (646) 738-4894
• DDC Website: www.nyc.gov/ddc • DDC Video: www.nyc.gov/webuild • During Non-Working hours, please call 311 and give the Project ID: MED609