Liste des Contrles dInstallation Installation Check List
ICL ICQ 0200
DESIGNATION DE MONTAGE :
Assembly designation
AIR INTAKE FILTER Mechanical part
MODULE(S) : /
Modulus
NOM DE L'AFFAIRE : DEIR AMMAR
Project name
TYPE DE MACHINE : TG-9E Machine type
MARQUAGE : 9048058/01 ; 9048064/01 &
9048065/01
Identification
N CLIENT : 104/498997, 104/498998 & 104/498999- E1315 Customer Nr
REFERENCE : 48058meca REV/Issue : A PAGE :1/3
Ce document, proprit exclusive de GE Energy Products France SNC, est
strictement confidentiel. Il ne peut tre communiqu, copi, ou reproduit sans
notre autorisation crite.
This document, exclusive property of GE Energy Products France SNC, is strictly
confidential. It must not be communicated, copied or reproduced without our
written consent.
RESPONSABLE(S) QUALITE DE L'ENTREPRISE(S) DE MONTAGE
Assembly manufacturer's quality representative
Entreprise : Nom : Date/Signature :
S
Q
S
Date : Nom : Signature :
DT-7C
GE Of
ficial
Liste des Contrles
dInstallation Installation Check List
ICL REFERENCE : 48058meca
REV/Issue : A Page : 2/3
LIGNE
Line
NATURE DES CONTROLES
Type of checks
EXIGENCES Requirements
SPECIFICATIONS
REV
Issue
N RAPPORT / REPORT Nr
Signature & date
N PV NC
NCR Nr
Subcontractor
or Partner
GE Customer
V = Vrification / Verify W = Convocation + vrification / witness point
R = Document rapport / Document Report H = Point d'arrt + vrification/Hold point + verify Plan Qualite Site.DOT
01 Site inspection delivery and storage: R Packing list . Visual . Quantity
02 Inspection of supporting structure R . Levels, alignement; . Bolts, tightening, evenness; . Visual and measurement
03
04
Erection of the flexible below . Check need shims for horizontal position . Check all eye lifting bolts . Control position with gas turbine axis . Control bolt securing on structure
Erection of transition piece:
V Erection procedure - Mechanical part Tightening torque refer to appendix of erection book
. Check need shims for horizontal position V Erection procedure - Mechanical part
. Check all eye lifting bolts Tightening torque refer to appendix . Control position with gas turbine axis of erection book . Control bolt securing on structure
05
Erection of inlet module.
. Check all eye lifting bolts V Tightening torque refer to appendix . Control tightness and securing with transition piece of erection book . Control position with gas turbine axis Air seal between the modules refer to . Control bolt securing on structure appendix of erection book
Liste des Contrles
dInstallation Installation Check List
ICL REFERENCE : 48058meca
REV/Issue : A Page : 3/3
LIGNE
Line
NATURE DES CONTROLES
Type of checks
EXIGENCES Requirements
SPECIFICATIONS
REV
Issue
N RAPPORT / REPORT Nr
Signature & date
N PV NC
NCR Nr
Subcontractor
or Partner
GE Customer
V = Vrification / Verify W = Convocation + vrification / witness point
R = Document rapport / Document Report H = Point d'arrt + vrification/Hold point + verify Plan Qualite Site.DOT
06 Erection of Downstream module. V Erection procedure - Mechanical part . Check all eye lifting bolts Tightening torque refer to appendix . Control tightness and securing with transition piece of erection book . Control position with gas turbine axis Air seal between the modules refer to . Control bolt securing on structure appendix of erection book
07 Erection of coalescers cells: V check open cells are installed vertically
check the securing of latches Erection procedure - Mechanical part
of erection book 08 Erection of prefilters cells : V
check open cells are installed vertically Erection procedure - Mechanical part
09 Erection of HF filter cells : V Erection procedure - Mechanical part check open cells are installed vertically
check the securing of latches
10 Final inspection of all installed equipment V Erection procedure - Mechanical part Internal cleaning and dedusting of the housing and
filter frames visual control
Refer to the commissioning book
NomDoc=48058MECA|NomFic=PQS_48058_mec_A_en.pdf